Filed Sub-Bid Coordination and Communication

Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications [email protected]

Page 2: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

We have work to do

5,000,000 people move to citiesevery monthTriumph of the City - Ed Glaeser

Page 3: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

We have to get it right during design

Page 4: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

Even sustainability is a point of view

Page 5: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

DCAMM Standard Specifications Update

MGL Chapter 149 filed sub-bidsMGL Chapter 149A trade bidsDivision 1 issued with CM RFQFiled sub-bids and trade bids$ 25,000 trade bid thresholdPrequalify trade bidders

Page 6: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

DCAMM Standard Specifications

Overview of 2018 Update

DBB / CMR Versions DifferentDCAMM E-bid RoomCAMIS Equipment TemplatesCommissioningProduct/Standards UpdatesLEED V4MEP/FP Specs by Engineers

Page 7: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

DCAMM Standard Spec – Sub Sub-Bids

Section 210001 - Fire ProtectionNone

Section 220001 - PlumbingPlumbing Insulation

Section 230001 - HVACHVAC InsulationHVAC Ducts and CasingsStartup, Testing and BalancingTemperature Control System

Section 260001 - Electrical WorkFacility Lightning ProtectionCommunications SystemsAudiovisual SystemsSecurity Systems

Page 8: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

Filed Sub-Bids – Spec Hot Topics

RFIs / Bid ProtestsPrior to Receipt of BidsAfter Bids ReceivedProprietary Specs

Scope of Filed Sub-BidsExterior Glazing not in FSBDiv 27/28 part of Div 26

Construction Management IssuesTrade CrossoversSupplemental Scope Req’ts

Page 9: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move

© 2009 Autodesk

Programming

Conceptual Design

Detailed Design Analysis

Documentation

Fabrication

Construction4D/5D

ConstructionLogistics

Operation and Maintenance

Demolition

Renovation

BuildingInformationModeling

Page 10: Filed Sub-Bid Coordination and Communication · Mark Kalin FAIA FCSI LEED - Kalin Associates Specifications mkalin@kalinassociates.com. We have work to do. 5,000,000 people . move