Figuring out where you are and does your contractor agree?
-
Upload
public-technology-institute -
Category
Technology
-
view
508 -
download
0
description
Transcript of Figuring out where you are and does your contractor agree?
![Page 1: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/1.jpg)
Roger D. H. Warburton, PhD, PMP
Associate Professor,Metropolitan College, Boston University
Figuring Out:Where Are You?
&
Does your Contractor Agree?
![Page 2: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/2.jpg)
The “How ya doin?”
Problem
Contractor: We’re a little behind, but it’s not a problem. We’ll make it up.
What do you say?
![Page 3: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/3.jpg)
Route 93 Re-Paving Problem
![Page 4: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/4.jpg)
We Have a Plan
From 128/I93 to I90-I93 is 7.7 miles.
Plan: 0.77 miles each monthSchedule:10 months. Cost: $1,470,000.
![Page 5: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/5.jpg)
What Actually Happened?
Month 1:
Contractor: We’re a little behind, but it’s not a problem. We’ll make it up.
![Page 6: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/6.jpg)
What Actually Happened?
Month 2:
Contractor: We’re a little behind, but it’s not a problem. We’ll make it up.
![Page 7: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/7.jpg)
What Actually Happened?
Month 3: We’re a little behind, but it’s not a problem. We’ll make it up.
Enough Already!
![Page 8: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/8.jpg)
Here’s the bill!
Actual$1,869,000
Budget$1,470,000
Month 11
There is a better way!
![Page 9: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/9.jpg)
How Do We Measure“Progress?”
Actual 0.66 miles
Planned 0.77 miles
You can always measure something!
Against the plan …..
![Page 10: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/10.jpg)
What Was Accomplished? Miles of Roadway Lines of code designed, written,
tested Drawings completed Reports delivered Units delivered Square Meters of Paint Feet of Steel Erected Cubic Yards of Tunnel Dug Out
WBS:Deliverable
Oriented Hierarchy
![Page 11: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/11.jpg)
You Already Have The Data
Monthly Reports:What was planned?What was accomplished?What did it cost?
You are the PM. The Mayor wants to know the status of the project.
![Page 12: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/12.jpg)
End of Month 2
Planned 1.54 miles
2) Report Costs:
1) Measure Progress:
Actual 1.49 miles
Planned $294,000
Actual $329,000
![Page 13: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/13.jpg)
The “Value” of a Mile
Planned Cost / Mile = $190,909
Plan: 7.7 milesCost: $1,470,000
Complete ½ mile:“Value” = $190,909 ÷ 2
= $95,455
![Page 14: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/14.jpg)
The “Value” of a Mile
Planned Cost / Mile = $190,909
Plan: 7.7 milesCost: $1,470,000
Complete ½ mile:“Value” = $190,909 / 2
= $95,455EarnedValue
![Page 15: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/15.jpg)
Glossary Planned Value, PV
The sum of the value of the work planned
Earned Value, EV The sum of the value of work performed
Actual Cost, AC The sum of the costs incurred
![Page 16: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/16.jpg)
Budget At Completion,BAC Estimated At Completion, EAC Estimate To Complete, ETC
$
Time Now
Actual CostsTo Date
Budget, BAC EstimateTo Complete
ETC
EAC
Glossary
![Page 17: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/17.jpg)
Glossary Cost Performance Index, CPI
Schedule Performance Index, SPI
![Page 18: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/18.jpg)
CPI: Cost Efficiency Cost Performance Index
Cost Efficiency
𝑪𝑷𝑰=1.43𝑥 $190,909$342,000
=0.80
Planned 1.54 miles
Actual 1.43 milesCost / Mile = $190,909
![Page 19: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/19.jpg)
SPI: Schedule Efficiency
Schedule Performance Index, SPI
𝑺𝑷𝑰=1.43 𝑥 $190,9091.54 𝑥 $190,909
=0.93
Planned 1.54 miles
Actual 1.43 miles
You are behind schedule
![Page 20: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/20.jpg)
How Much Behind? Schedule Variance, SV
𝑺𝑽 (𝒕 )=$𝟐𝟕𝟑 ,𝟎𝟎𝟎−$𝟐𝟗𝟒 ,𝟎𝟎𝟎
Planned 1.54 miles
Actual 1.43 miles
You are $21,000 behind schedule!
𝑺𝑽=𝑬𝑽 (𝒕 )−𝑷𝑽 (𝒕)
𝑺𝑽 (𝒕 )=−$𝟐𝟏 ,𝟎𝟎𝟎
![Page 21: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/21.jpg)
Route 93 Status: Month 4
(Miles Completed) Cost
Month Planned Completed Planned Actual
1 0.77 0.77 $147,000 $181,000
2 0.77 0.66 $147,000 $161,000
3 0.77 0.62 $147,000 $187,000
4 0.77 0.58 $147,000 $177,000
You are the PM. The Mayor wants to know the status of the project.
Plot Everything!
![Page 22: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/22.jpg)
What actually happened?
Months
![Page 23: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/23.jpg)
Add the Cost
Months
![Page 24: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/24.jpg)
Cumulative Costs
Months
![Page 25: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/25.jpg)
Efficiency
Months
![Page 26: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/26.jpg)
Graphs vs. Tables
Months
CPI =
Month CPI1 0.81 2 0.80 3 0.74 4 0.71
![Page 27: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/27.jpg)
Typical CPI & SPI
CPI falls & Levels off SPI falls & rises → 1.0
![Page 28: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/28.jpg)
How Much Will It Cost?
BAC = $1,470,000
𝑬𝑨𝑪=𝑩𝑨𝑪
¿𝑪𝑷𝑰 >¿ ¿
CPI = 0.8 → EAC = $1,838,000
Estimate at Completion
![Page 29: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/29.jpg)
Estimate at Completion #2
𝑬𝑨𝑪=𝑨𝑪 (𝒕 )+ 𝑩𝑨𝑪−𝑬𝑽 (𝒕 )𝑪𝑷𝑰 (𝒕 )
𝑬𝑨𝑪=𝑨𝑪 (𝒕 )+ 𝑹𝒆𝒎𝒂𝒊𝒏𝒈𝑾𝒐𝒓𝒌𝑬𝒇𝒇𝒊𝒄𝒊𝒆𝒏𝒄𝒚
𝑬𝑨𝑪=$𝟔𝟖𝟏 ,𝟎𝟎𝟎+$𝟏 ,𝟒𝟕𝟎 ,𝟎𝟎𝟎−$𝟓𝟒𝟔 ,𝟎𝟎𝟎
𝟎 .𝟖𝟎
𝑬𝑨𝑪=$𝟏 ,𝟖𝟑𝟔 ,𝟎𝟎𝟎#1: EAC = $1,838,000
![Page 30: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/30.jpg)
Plot EAC (t)
𝑬𝑨𝑪=𝑨𝑪 (𝒕 )+ 𝑩𝑨𝑪−𝑬𝑽 (𝒕)𝑪𝑷𝑰 (𝒕)
𝑩𝑨𝑪
𝑨𝒄𝒕𝒖𝒂𝒍
![Page 31: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/31.jpg)
Earned Value Management (EVM)
Christensen & Heise, 1992 DOD experience >400 programs since 1977 Without exception:
The cumulative CPI does not significantly improve during the period of 15% through 85% of the contract
Provides early warning of trouble EAC reliable ~ 20% into a project
In fact it tends to decline!
![Page 32: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/32.jpg)
“I did not use EVM because …”
“Not needed on small projects” “Hard to apply” (Kim, 2000)
“The implementation requirements, terminology, and the countless rules and interpretations, are perceived as overly restrictive” (Fleming & Koppelman, 2005)
It is difficult to find a balance between the utility of the EV technique . . . versus the effort it takes to implement (Quentin & Koppelman, 2005)
ContractorExcuses
![Page 33: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/33.jpg)
From Earned Value
toTCPI
![Page 34: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/34.jpg)
The to-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC.
PMBOK 4th Edition
![Page 35: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/35.jpg)
A simple formula to change the world!
“Once our customers start calculating TCPI, we will no
longer be able to fudge project cost!”
TCPI
![Page 36: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/36.jpg)
What is TCPI?
![Page 37: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/37.jpg)
TCPI: Month 4 Work Remaining:
BAC – EV(t) = $1,470,000 – $546,000 Funds Remaining:
BAC – AC(t) = $1,470,000 – $681,000
= 1.17
![Page 38: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/38.jpg)
You:You need a 17% improvement.
Contractor:No problem!
Trust me, we’ll make it up.
Everything will be OK.
![Page 39: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/39.jpg)
Really?!
Your current efficiency is 80%
Your TCPI is 117%
You need a 37% improvement!
![Page 40: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/40.jpg)
It’s Getting Worse!
You need a 37% improvement!
37%
![Page 41: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/41.jpg)
You Can’t Win!
TCPI → ∞!
You need to be here!
You are here!
![Page 42: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/42.jpg)
Admit it,
You’re here
![Page 43: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/43.jpg)
The “Modus” Project
![Page 44: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/44.jpg)
Cumulative Doesn’t Help
![Page 45: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/45.jpg)
Modus: CPI & SPI
![Page 46: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/46.jpg)
We Know the Cost
![Page 47: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/47.jpg)
Guidance EVM Works
2 Simple Formulae:
You already have the data! TCPI is a powerful addition to EVM
CPI is about the past TCPI is about the future
Graphs are powerful Weekly data is the key
SPI doesn’t really work
![Page 48: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/48.jpg)
Conclusion
Earned Value is the Public Sector Manager’s
Friend
![Page 50: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/50.jpg)
If it becomes obvious that the BAC is no longer viable, the EAC supersedes the BAC
PMBOK to the Rescue!
![Page 51: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/51.jpg)
TCPI with EAC
Required efficiency is just the CPI!
![Page 52: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/52.jpg)
Admit it,
You’re here
![Page 53: Figuring out where you are and does your contractor agree?](https://reader034.fdocuments.us/reader034/viewer/2022042813/54642bceaf795967228b6ef1/html5/thumbnails/53.jpg)
Schedule Prediction
𝑻 𝒂=𝑻 𝒑
√𝑺𝑷𝑰