Fiesta Pa Sow v1.5 Final
Transcript of Fiesta Pa Sow v1.5 Final
-
8/3/2019 Fiesta Pa Sow v1.5 Final
1/25
IMS FIESTA PA Project
STATEMENT OF WORK (SOW)
Prepared By: Charlotte L. GreggDate: 05/11/2004
FINAL: Version 1.5
-
8/3/2019 Fiesta Pa Sow v1.5 Final
2/25
Statement of Work for IMS FIESTA PA
REVISION HISTORY
Date Description Version
05/11/2004 Created (draft version) by Charlotte Gregg. 1.0
05/20/2004Incorporated Kimbers changes. Inserted picture of new baselined project plan. Newending date for entire project is 09/13/04. Assigned document version number 1.1. Sentout to Kimber, Sesh, and Robert for their review.
1.1
06/08/2004
Incorporated Sesh Paladugus changes. Changed three sentences in theBACKGROUND section:1. Data entry of site inventory, related party, permit type, and phase of application is
performed at Department headquarters and/or District offices was changed to readData entry of site inventory, related party, permit type, and status of application is
performed at Department headquarters and/or District offices.2. the intent is to encourage them to be eager to bring their particular program area date
into the core when it is time changed to read the intent is to encourage them to beeager to bring their particular program area data into the core (at the appropriatetime).
3. The project is completed prior to any current PA business processes requiring
modifications due the IMS project was changed to read The IMS FIESTA PAproject is completed before any other IMS projects require that any current PAbusiness processes be modified.
1.2
06/08/2004
Incorporated Robert Rouses comments into the document. Changed the followinginformation in the BACKGROUND, History section:1. The primary function of the schema is to track permits from the application received
through application issued/denied phases for all permitted DEP sites changed to readThe primary function of the schema is to store data about environmental permitsrequired by DEP. This includes the point from application reception, through theapplication review process, and up to final agency determination.
2. Removed the following out-of-date and incorrect sentences: The application is usedboth within and outside the agency for determining permit trends. The trends areused to track enforcement of permitted requirements within the Florida.
1.3
06/08/2004
Charlotte inserted Project Risk Assessment Matrix (PRAM) into appropriate section.
Added Ron Wright to the Project Roles and Responsibilities table as Oracle Forms SMEand added the following new responsibility Provide assistance to lead programmer withthe analysis, design, and development of the new form(s). Inserted a new Project Plan
picture with actual hours entered through 06/03/04.
1.4
06/09/2004
Modifications suggested during review of SOW in 06/09/04 Project Kickoff Meeting.1. Changed the PROJECT SCOPE: Out of Scope section to eliminate the following
item: Modifications to the existing PA ERD or Server Model. It has beendetermined that two new PA tables are needed; therefore changes to the ERD andSMD will be made.
2. The Project Organization Chart was modified to include Ron Wright and to addKimber Allen as Project Sponsor.
3. The Project Roles and Responsibilities table was modified to add Ron Wright underthe following existing roles: Data Architect, Programmer, and Testing Lead.
4. The Project Roles and Responsibilities Table was modified to add a Tester Role.
5. Modified the Probability from H to M for the Project Manager Availability row in thePRAM.
1.5
81271623.doc > 1/13/2012
-
8/3/2019 Fiesta Pa Sow v1.5 Final
3/25
Statement of Work for IMS FIESTA PA
DEFINITIONS
Abbreviation Meaning
BCRP BIS Control and Reporting Process
BIS Bureau of Information SystemsDBA Database Administrator
DEP Department of Environmental Protection
FIESTA Florida Integrated Environmental System TodAy
GUI Graphical User Interface
IMS Integrated Management System
ISDM Information System Development Methodology
MS Microsoft
PA Permitting ApplicationPMO DEP Project Management Office
PRAM Project Risk Assessment Matrix
SOW Statement of Work
81271623.doc > 1/13/2012
-
8/3/2019 Fiesta Pa Sow v1.5 Final
4/25
Statement of Work for IMS FIESTA PA
TABLE OF CONTENTS
REVISION HISTORY ................................................................................... 2
DEFINITIONS ............................................................................................. 3
TABLE OF CONTENTS .................................................................................. 4
I.REQUEST .................................................................................................. 6
BACKGROUND ............................................................................................ 6
History of the Project .................................................................... 6
Business or IT Objectives of the Project ....................................... 6
Critical Success Factors of the Project .......................................... 6
PROJECT SCOPE ......................................................................................... 7
In-Scope ....................................................................................... 7
Out of Scope ................................................................................. 8
MANAGEMENT APPROACH .......................................................................... 8
Plan Management ......................................................................... 8
Communications Management ...................................................... 8Team communications ............. .............. .............. ............... .............. .............. .............. ............. ..... .8Customer communications ............. .............. .............. .............. .............. ............... .............. .......... ..8Project Notebook .............. .............. .............. .............. ............... .............. .............. .............. ........... ..8
Issues Management ...................................................................... 8
QUALITY ASSURANCE ................................................................................. 9
TECHNICAL ENVIRONMENT ........................................................................ 9
Oracle Development Environment ................................................. 9
GIS Development Environment ................................................... 10
Middle-Tier Environment ............................................................. 10
Access & Security ........................................................................ 11
WORK APPROACH AND DELIVERABLES .................................................... 11
Work Approach ........................................................................... 11
Deliverables (& Milestones) ........................................................ 12Strategy Phase .............. ............... .............. .............. .............. .............. ............... ............ ..... ...... .....12
(#1)MS Project Plan ............................................................................................................... .12(#2)Statement of Work (SOW) ...............................................................................................12Milestone - Project Kickoff Meeting ......................................................................................13Milestone - Project Notebook Setup .......................................................................................13
Needs Assessment Phase ............. .............. .............. .............. ............... .............. .............. ......... .....13(#3)Candidate Needs ...............................................................................................................13(#4)Candidate Requirements ...................................................................................................13(#5)Impact Assessment Summary (IAS) .................................................................................14
System Design Phase ............. .............. .............. ............... .............. .............. .............. ............. ..... ..14Alpha Development Phase .............. .............. ............... .............. .............. .............. .............. ..........14
Milestone - Database and all Database Objects (ALPH) .......................................................14(#6)Forms / Screens / Menus .................................................................................................. .14(#7)Beta Test Plan ...................................................................................................................15
81271623.doc > 1/13/2012
-
8/3/2019 Fiesta Pa Sow v1.5 Final
5/25
Statement of Work for IMS FIESTA PA
(#8)DBA Migration Package (from ALPH to BETA) ............................................................15Milestone - Supplement to the PA Users Manual (DRAFT) ..................................................15
Beta Testing Phase .............. .............. .............. ............... .............. .............. .............. ........... ...... .....15Milestone - BETA Environment Setup ...................................................................................15(#9)User BETA Testing ..........................................................................................................16Milestone - Supplement to the PA Users Manual (FINAL) ...................................................16Milestone - Training Plan ........................................................................................................16(#10)Training Plan Checklist ..................................................................................................16(#11)Implementation Plan ................................................................................................. ......17(#12)DBA Migration Package (from BETA to PROD) .........................................................17
Implementation Phase ............. .............. .............. .............. .............. ............... .............. ...... ...... .....17
(#13)Production Move and Verification .................................................................................17
ROLES & RESPONSIBILITIES ................................................................... 18
Project Organization Chart .......................................................... 18
Project Roles and Responsibilities Table ..................................... 18Executive Project Sponsor ............. ............... .............. .............. .............. .............. ......... ...... ...... ...19Project Role .............. .............. ............... .............. .............. .............. .............. .............. ..... ..... ..... ....20Project Customer .............. .............. ............... .............. .............. .............. .............. .......... ..... ..... ....20Project Manager .............. .............. .............. .............. ............... .............. .............. ....... ..... ..... ..... ...20
Business Analyst ............... .............. .............. .............. .............. .............. ............... ............. ..... ..... ..20Data Architect .............. ............... .............. .............. .............. .............. .............. .......... ..... ..... ...... ...20Programmer ............. .............. .............. .............. .............. ............... .............. ............. ..... ..... ...... ....20Testing Lead ............. .............. .............. .............. .............. ............... .............. ............. ..... ..... ...... ....20Testers .............. .............. .............. .............. ............... .............. .............. .............. .......... ..... ..... ..... ...20Project Role .............. .............. ............... .............. .............. .............. .............. .............. ..... ..... ..... ....21Project Officer ............ ............... .............. .............. .............. .............. ............... .............. ............ ....21SME-Permitting Application .............. ............... .............. .............. .............. .............. ........... ..... ...21SME-Applications .............. ............... .............. .............. .............. .............. ............... ......... ..... ..... ...21SME-Oracle Forms .............. .............. .............. .............. ............... .............. .............. .............. ...... .21BIS Management Group ............. .............. .............. .............. .............. ............... .......... ..... ..... ..... ..21SME-Database Administration ............... .............. .............. .............. .............. ........ ...... ...... ...... ...21SME-Network & Systems .............. .............. .............. .............. .............. .............. ............... ...........21SME-Middle Tier .............. .............. .............. .............. ............... .............. .............. .............. ...... ....21
Permitting Application (PA) Data Entry Team .............. .............. ............... ......... ..... ..... ...... .....21
PROJECT PLAN ......................................................................................... 22
RISK MANAGEMENT .................................................................................. 22
Project Risks ............................................................................... 23
CHANGE MANAGEMENT ............................................................................ 24
Change Procedure ....................................................................... 24
Change Criteria ........................................................................... 24
ACCEPTANCE MANAGEMENT .................................................................... 24
Acceptance Procedure ................................................................. 24Final Acceptance ......................................................................... 25
APPROVED BY: ......................................................................................... 2525
81271623.doc > 1/13/2012
-
8/3/2019 Fiesta Pa Sow v1.5 Final
6/25
I. REQUEST
In late March 2004, Charlotte Gregg was assigned as Project Manager of the IMS FIESTA PAsub-project. (IMS stands for Integrated Management System. FIESTA is the acronym for
Florida Integrated Environmental System TodAy and PA is the Permitting Application shortname.) Linda Lakes was the original PM; she created the initial project plan. After a meetingwith select team members (Robert Rouse, Linda Lakes, Charlotte Gregg and Kimber Allen), itwas decided that this project would change significantly in nature. This project will no longerwait on the other IMS integrations (WAFR and CHAZ), but will immediately create a singlemethod for permit data entry purposes, with the IMS FIESTA look and feel. Thedevelopment of the new FIESTA PA form(s) will comply with current existing businessconstraints; when the business rules in the various program areas are changed based on new rulesimposed by the IMS, at that time, modifications to FIESTA PA (and the unchanged PA) will beaddressed at that time. The form(s) created/modified for this project will still use the existingapplication area data stores. Changes to the existing database(s) will be minimal; therefore,several deliverables are not required for this project, including the ERD and Server Model.
BACKGROUND
History of the ProjectThe following information is taken from the IMS master SOW, in the IMS Sub-Projects PhaseI section for this project:
FIESTA Permitting Application: A common, high-level IMS interface for creating new Managed Entitiesthat result from the processing of Permit Applications. Staff would interact with a common interface that
prompts for CORE information. Until designated applications are integrated, the appropriate "specialized"
PA interface (Generic PA, ARMS PA, etc.) would be invoked as necessary.
The Permitting Application (PA) contains information relating to permitted sites within Florida.The primary function of the schema is to store data about environmental permits required byDEP. This includes the point from application reception, through the application reviewprocess, and up to final agency determination.
Data entry of site inventory, related party, permit type, and status of application is performed atDepartment headquarters and/or District offices. Many DEP divisions use the PermittingApplication. There are currently over 800 users of PA.
Business or IT Objectives of the ProjectThe primary IT objective for this project is to provide a single method for permit data entrypurposes with the look and feel of the other IMS FIESTA Oracle forms. Another objective ofthis project is to encourage the PA users to come on board the IMS bandwagon. By providingthese users the slick, modern FIESTA PA form, the intent is to encourage them to be eager tobring their particular program area data into the core (at the appropriate time).
Critical Success Factors of the ProjectThe Critical Success Factors constitute the Project Sponsors answer to the question: How willyou define the success of the project? These factors are prioritized and serve as a guideline
-
8/3/2019 Fiesta Pa Sow v1.5 Final
7/25
used by the Project Manager to do trade-off analysis. Whenever these factors come into conflictthroughout the project, the Project Manager will use this list as a guide for decision-making.The Critical Success Factors for this project are the following:
1. The IMS FIESTA PA form(s) provide a single method for permit data entry.2. The IMS FIESTA PA form(s) mirror the look and feel of the other IMS FIESTA
Oracle forms.3. The IMS FIESTA PA project is completed before any other IMS projects require that
any current PA business processes be modified.4. The project is implemented according to the project plan and SOW.
PROJECT SCOPE
In-ScopeThis project involves the development of new Oracle form(s) to allow for the following highest-level functions:
1. Input of DEP permit data;2. A new method (entry point) for data entry PA users to access ARMS PA, WAFR PA and
Generic PA; and3. A format within the new form(s) that mimics the look and feel of other IMS FIESTA
Oracle forms.
The project is divided into the following phases:
ISDM Phase Purpose
Strategy Phase:The purpose of this phase is to initiate the project. Developed in thisphase, the detailed, agreed upon, approved project plan and Statement ofWork should comprise the road map that is used to navigate the project.
Needs AssessmentPhase:
The purpose of this phase is to determine the user needs and applicationspecifications.
System DesignPhase:
The purpose of this phase is to convert all logical requirements (gatheredin the previous phase) into physical/technical specifications to be used fordeveloping a working system.
AlphaDevelopmentPhase:
The purpose of this phase is to create the first working system1 based onthe physical/technical specifications.
Beta TestingPhase: The purpose of this phase is to review the system to ensure it achieves thegoals specified during the System Design Phase.
ImplementationPhase:
The purpose of this phase is to install the system on the appropriateproduction platform, grant access to users and provide training.
The work in detail will be outlined in the WORK APPROACH AND DELIVERABLES section.
1 The definition of System encompasses the database and the application. Database is defined as a sharedcollection of logically related data. Application is a finite set of job functions, which have been automated, andact on data residing in a database.
-
8/3/2019 Fiesta Pa Sow v1.5 Final
8/25
Out of ScopeThe following items are out of scope for this project:
1. Modifications to existing business rules and/or procedures currently followed in theprogram areas using PA;
2. Changes to the existing PA system to comply with IMS constraints (whether related to
the core database or any Clearinghouse issues);3. Creation of FIESTA PA reports;4. Changes/enhancements to existing PA reports; and5. Clean up of any PA data.
MANAGEMENT APPROACH
Plan ManagementBIS will develop a detailed project plan at the beginning of this project using MS Project 2000.The plan will be baselined at the beginning of the project. The baseline will only be adjusted
when the customer approves a change request that affects the schedule.The Project Manager will update the project plan weekly with data supplied by all teammembers in the progress reporting process. The Project Manager will control potential changesto the baseline project schedule and/or estimates through the use of the change procedure asdescribed in this SOW.
Communications ManagementCommunications Management will focus on providing regular updates on the contributions,commitments and challenges for the project effort to all project participants as defined in theproject roles and responsibilities and/or project organizational chart. Communications consist ofthe following processes:
Team communicationsEach project participant will submit to the Project Manager a weekly Individual ProjectStatus Report (IPSR) that identifies completed tasks, tasks expected to be completed in thenext reporting period, lost time, issues, and time reporting by task (including actual effort,effort estimates-to-complete, estimated completion date). The weekly individual reports areconsolidated into a summarized weekly project report. The project team will meet weekly toshare overall project status, to discuss issues, and to provide assignments and goals.
Customer communicationsThe Project Manager will meet weekly with the customer to review overall project status, toreview deliverables and discuss issues. A weeklyProject Status Report (PSR) will bedistributed to the customer and all project participants.
Project NotebookA project notebook is kept as a single repository for all documentation of projectmanagement, project reporting and control materials. It is accessible to the project team as areference document throughout the project.
Issues ManagementAn issue is defined as any item adversely affecting execution of the project plan. Issues mayadversely impact the cost, time frame and/or quality of the deliverables of the project. Resolvingissues is an on-going process throughout the life of any project. The keys to effective issueresolution are early identification, communication and management. Our process is as follows:
http://opt/scribd/conversion/tmp/scratch6190/IPSR%20template.xlshttp://opt/scribd/conversion/tmp/scratch6190/IPSR%20template.xlshttp://opt/scribd/conversion/tmp/scratch6190/ProjectStatusReportTemplate.dochttp://opt/scribd/conversion/tmp/scratch6190/ProjectStatusReportTemplate.dochttp://opt/scribd/conversion/tmp/scratch6190/IPSR%20template.xlshttp://opt/scribd/conversion/tmp/scratch6190/IPSR%20template.xlshttp://opt/scribd/conversion/tmp/scratch6190/ProjectStatusReportTemplate.doc -
8/3/2019 Fiesta Pa Sow v1.5 Final
9/25
Issues are recorded into a Project Issue Log. Every record in the Issue Log contains a descriptionof the issue, actual or potential impact if not resolved, who raised the issue, when the issue wasraised, updates, and final resolution. Every issue has a target date for resolution after which theproject is impacted. Every issue has an owner responsible for driving resolution and keeping theProject Manager up to date on progress.
Issues are listed (or the Issues Log is attached) in the weekly Project Status Report (PSR). Issuesare reviewed weekly in team status and customer status meetings. Issues are closed only whenthe initiator is comfortable that the resolution addresses their problem.
Note: Critical issues will be reported to the Project Manager as they are identified,without consideration to the standard status reporting procedures.
Escalation: There may be instances where an issue needs to be escalated. Escalationinvolves bringing the issue to the attention of the Project Sponsor for resolution.
QUALITY ASSURANCE
This project will use the standard BIS Control and Reporting Process (BCRP) to monitor projectquality. BCRP deals with project management expectations within BIS and sets rigorous, butminimum standards for quality in project management. Projects within BIS are randomlyselected for review at Project Initiation, Quarterly, and at Project Closure.
The quality processes that will be used on this project are: quality audits from the BIS ProjectManagement Office (PMO), Peer/Quality Assurance Reviews of project deliverables, and thestandard quality processes built into the BIS Information System Development Methodology(ISDM).
TECHNICAL ENVIRONMENT
Oracle Development EnvironmentThe Oracle forms development work will conform to the standards described below: User Workstation requirements - Any user must have the following software on their PC:
Internet Explorer and the current version of JInitiator. A user must have a valid Oracleaccount on the appropriate database (on ORABETA for beta testing; on ORAPROD forproduction). Also, a user must have been granted access, in the Web Access ControlApplication (WACA), to the appropriate application(s).
Development environment - Forms will be created on the development middle tier server,EPIC227 (ALPH). The database that will be used for development and testing is ORADEV.
The developers will use the Development URL for testing: http://depdev.dep.state.fl.us:8888.
Testing environment -The application will be moved to the Beta region of EPIC227 by oneof the BIS developers. The users in this region should test the application by using the betaURL: http://depbeta.dep.state.fl.us: 7777. The database that will be used for applicationtesting is ORABETA.
Production environment - Once approved by BETA testers the application forms can bemoved to production. The items will be moved from EPIC227 (BETA) to the productionserver, by one of BIS Database Administrators (DBA), at the request of the BIS project
http://opt/scribd/conversion/tmp/scratch6190/Issues%20Log%20Template.dochttp://opt/scribd/conversion/tmp/scratch6190/Issues%20Log%20Template.doc -
8/3/2019 Fiesta Pa Sow v1.5 Final
10/25
lead. The new system will then be available from this URL: http://depapps.dep.state.fl.us:7777/. The production database is ORAPROD.
GIS Development EnvironmentGIS products, services and data will conform to the standards below:
User Workstation Requirements - ArcIMS users must have MS Internet Explorer 5.5 orbetter. Desktop GIS users must have ArcGIS 8.1.2 or better and a workstation that conformsto the ESRI hardware recommendations for the current release of ArcGIS.
Development Environment - ArcIMS applications and web services will be developed inArcIMS 4.0.1 on either the developer's workstation or on GISAIMSDEV1. ArcIMSapplications and web services must conform to the published BIS/GIS Web Mapping System(WMS) technical standards (which can be viewed at http://depnet/gis/services/arcims.htm).ArcIMS applications must use data provided by ArcSDE rather than local copies of data.Data products will be developed on GISTEST in ArcSDE 8.3 and Oracle 9.2.0.2.
Testing Environment - ArcIMS applications and web services will be tested onGISAIMSBETA1 running ArcIMS 4.0.1 and configured in accordance with the publishedWMS standards referenced above. All data products will be tested on GISTEST,
configuration noted above. Staging Environment - ArcIMS applications and web services will be ported to
GISWEBSTG4, GISMAPSTG4, and GISMAPSTG5 and tested prior to porting to theproduction environment. GISWEBSTG4, GISMAPSTG4, and GISMAPSTG5 run ArcIMS4.0.1 and are configured in accordance with the published WMS standards referenced above.
Production Environment - ArcIMS applications and web services will be ported toGISWEB4, GISMAP4, and GISMAP5 running ArcIMS 4.0.1 and configured in accordancewith the published WMS standards referenced above. All data products will be copied orimported to EPIC31 running ArcSDE 8.3 and Oracle 9.2.0.2.
Middle-Tier Environment
Oracle development tools and application server have been upgraded to the latest version (9i) inorder to remove any bugs that may have been fixed from earlier versions and also to provide themost robust development environment available from Oracle Corporation. This upgradeprovides J2EE 1.3 capabilities needed now for integration of GIS and Oracle Formsfunctionality. It is expected that within the next year DEP will upgrade to the next version (10g)when that software is mature for the previous reasons and to provide J2EE 1.4 capabilities.Oracle upgrades are always planned and carefully managed and they occur with explicitapproval of the CIO.
http://depnet/gis/services/arcims.htmhttp://depnet/gis/services/arcims.htm -
8/3/2019 Fiesta Pa Sow v1.5 Final
11/25
Access & SecurityAccess to DEP systems is done through the use of the Web Access Control Application(WACA). The system is designed to give the authorized end-users control over the access totheir Information Systems. As part of the development process, the user community workswith application development staff to specify and set up the security levels and roles for theapplication. The application is then developed to use this information to limit access in theapplication based upon the role (security level) assigned. Individual access is granted to theseroles through the use of the WACA system.
WORK APPROACH AND DELIVERABLES
Work ApproachThe following methodologies and standards will be taken into account during development foreach phase of this project:
1. DEPs Information Systems Development Methodology (ISDM)2. BIS Productivity Management Standards3. BIS Oracle Designer Naming Standards
-
8/3/2019 Fiesta Pa Sow v1.5 Final
12/25
The work approach for the project will be deliverable-based. A collection of pre-determineddeliverables will be completed, as the project proceeds through the seven phases of the DEPInformation Systems Development Methodology (ISDM). Those ISDM phases are Proposal,Strategy, Needs Assessment, System Design, Alpha Development, Beta Testing, andImplementation. The project deliverables and milestones are outlined in the next section, underthe appropriate ISDM phase.
Deliverables (& Milestones)The project deliverables, which will require approval and acceptance from the customer, will beassigned a deliverable number. This number will be used in the project plan, in projectreporting, and in the next section to uniquely identify the particular project deliverable. Adeliverable will have defined acceptance criteria; these criteria will be the basis for approvalwhen the deliverable has been completed. A milestone is a thing of significance to the project.Milestones are different from deliverables in that they do not require approval and they will nothave an assigned number. However, the project milestones will be documented in the followingsection, along with the deliverables, and will be included in project reporting. Milestones willhave Completion Criteria and will often require a reviewer, but a Milestone will not require an
approver.
Strategy PhaseThe purpose of this phase is to produce a project plan and Statement of Work to define and direct theremainder of the project. The following are the deliverables and/or milestones to be produced during theStrategy Phase for this project:
(#1) MS Project Plan
Description:The project plan details all (known) project tasks, work estimates, resource assignments, percentof the project that is complete, proposed task begin and end dates, and proposed start and enddates for the project.
Produced by: Charlotte Gregg
AcceptanceCriteria:
The delivery of the Project Plan and Statement of Work (SOW) will be determined
ACCEPTABLE when the following criteria are met: The team has developed a fair estimate of the time, costs, and schedules; and The team has correctly identified the deliverables for the project; The Project Sponsor/Project Customer agrees the direction of the project accurately aligns
with the needs of the organization; and The Project Plan accurately reflects the schedule, deliverables, and tasks as defined in the
SOW.
Reviewer(s): Terri Rein, Fred Blanton, Robert Rouse, Sesh Paladugu
Approver(s): Kimber Allen
(#2) Statement of Work (SOW)
Description:This document details the agreements between BIS and the customer as to how, when, whereand in what way the project will be carried out.
Produced by: Charlotte Gregg
AcceptanceCriteria:
The delivery of the Statement of Work (SOW) will be determined ACCEPTABLE when thefollowing criteria are met: The project manager and project team understand the problem, opportunity, or need; The Project Sponsor agrees the direction of the project accurately aligns with the needs of
the organization; The Statement of Work accurately reflects the work to be done; and The Project Plan accurately reflects the schedule, estimates and resources as defined in the
SOW.
Reviewer(s): Robert Rouse, Sesh PaladuguApprover(s): Kimber Allen, Terri Rein, Charlotte Gregg, Management Steering Committee (MSC)
-
8/3/2019 Fiesta Pa Sow v1.5 Final
13/25
Milestone - Project Kickoff Meeting
Description:The initial meeting of the project participants. The meeting, led by the Project Manager (PM), isthe time during which the customer is first led through the Project Plan and Statement of Work
by the PM.
Produced by: Charlotte Gregg
CompletionCriteria:
The Project Kickoff Meeting will be determined COMPLETE when the following criteria aremet: The PM and project team members meet and review the Project Plan and The PM and project team members meet and review the DRAFT of the Statement of Work
(SOW).
Reviewer(s): N/A
Milestone - Project Notebook Setup
Description: Creation of the physical project notebook and the electronic project directory.
Produced by: Charlotte Gregg
CompletionCriteria:
The setup of the Project Notebook will be determined COMPLETE when the following criteriaare met: The Project Notebook has been created with its particular Project Notebook cover and spine
and
The Electronic Project Directory has been created on a network drive.Reviewer(s): N/A
Needs Assessment PhaseThe customer requirements, functions, and business rules are determined and documented during the NeedsAssessment phase. The information needed to complete the different project deliverables may be obtainedthrough various techniques, including customer interviews, Joint Application Development (JAD) workshops,
prototyping, etc. It is also during this phase that the impacts of the proposed system to the current agencyinfrastructure are discovered and documented. The following are the deliverables and/or milestones to be
produced during the Needs Assessment Phase for this project:
(#3) Candidate Needs
Description:
Document containing needs statements. A statement of need identifies the business/user needs,
independent of how the need will be met. The document should contain clear statements ofeither a particular problem the business/user needs solved or an ability (or capability) that isneeded. A needs statement is "solution neutral".
Produced by: Robert Rouse, Sesh Paladugu
AcceptanceCriteria:
The delivery of the Candidate Needs document will be determined ACCEPTABLE when thefollowing criterion is met: The project sponsor agrees that the document reflects the candidate needs.
Reviewer(s): Charlotte Gregg
Approver(s): Kimber Allen
(#4) Candidate Requirements
Description:
Document containing requirement statements. A requirement statement is a statement of whata system would have to do in order to meet the business needs. Requirements specify whatwill
be done to satisfy one or more business needs. Contrast with business (or user) need statements
that reflect what the business needs to have solved, independent of the how.Produced by: Robert Rouse, Sesh Paladugu
AcceptanceCriteria:
The delivery of the Candidate Requirements document will be determined ACCEPTABLEwhen the following criteria are met: There is at least one requirement mapping back to every statement of need in the
Candidate Needs document and The Candidate Requirements are detailed to the point that the new form(s) can be created.
Reviewer(s): Charlotte Gregg
Approver(s):Kimber Allen, Management Steering Committee(MSC needs Candidate Requirements document plus an Executive Summary, which details thesolution summary, including impact to the User Community.)
-
8/3/2019 Fiesta Pa Sow v1.5 Final
14/25
(#5) Impact Assessment Summary (IAS)
Description:A document that details the impacts (if any) in the following areas: databases, middle tierservers, systems and network servers, help desk and GIS.
Produced by: Sesh Paladugu, Robert Rouse
AcceptanceCriteria:
The delivery of the Impact Assessment Summary (IAS) will be determined ACCEPTABLE
when the following criteria are met: The document explains/considers all potential impacts to the following BIS sections:
Application Development, Database Administration, Geographic Information System, HelpDesk, Middle Tier, and Networking; and
The document details any exceptions to normal operating procedures that this system ormodule will require.
Reviewer(s): Charlotte Gregg
Approver(s): Kimber Allen, Jon Canter, Linc Clay, Barbara Kennedy, Kevin Kerchkoff, Spencer Lepley
System Design PhaseThe deliverable of greatest importance created during the System Design Phase is the Detailed RequirementsSpecification (DRS) document. It is with this document that the programmer is given the details or thespecifics for coding the system. Another product of this phase is the Server Model or physical schema. Thereare no deliverables or milestones to be produced during the System Design Phase for this project. There will
be no changes to the database. Also, it has been elected that the programmer will create the new FIESTA PAform from the Candidate Requirements document, not from a DRS document.
Alpha Development PhaseThe actual system begins to take shape in this phase. Forms or screens and reports or other output are usuallythe two key deliverables. In addition, at the end of this phase, a Beta Test Plan, that will direct the BetaTesting effort during the next phase, is created. The following are the deliverables and/or milestones to be
produced during the Alpha Development Phase for this project:
Milestone - Database and all Database Objects (ALPH)
Description:The creation and/or modification of all development database objects, including tables, views,indexes, triggers, procedures, and roles.
Produced by: Sesh Paladugu
CompletionCriteria:
The delivery of the Database and all Database Objects will be determined COMPLETE whenthe following criteria are met: All database objects needed for development of alpha deliverables (i.e., forms and/or
reports) have been created (and populated, as needed); All appropriate SQL and PL/SQL scripts have been run correctly on the development
database; and All applicable database objects have been compiled without errors on the development
database.
Reviewer(s): Charlotte Gregg, Robert Rouse
(#6) Forms / Screens / Menus
Description:The forms, screens, and menus are what the users see when using the application. The screenscan be of various types, including data entry and query screens.
Produced by: Sesh Paladugu
AcceptanceCriteria:
The delivery of the Forms, Screens, or Menus will be determined ACCEPTABLE when thefollowing criteria are met: Each form or screen is developed according to specifications derived from the Candidate
Requirements document and Each form or screen is developed according to current BIS Oracle Forms Standards.
Reviewer(s): Charlotte Gregg, Donna Gorton, Robert Rouse
Approver(s): Kimber Allen
-
8/3/2019 Fiesta Pa Sow v1.5 Final
15/25
(#7) Beta Test Plan
Description:A plan that defines who will participate in testing (during the next phase), how the testing should
be carried out, where and when beta training will occur, how test results will be recorded andtransmitted back to the developers, and the estimated length of test period.
Produced by: Robert Rouse, Sesh Paladugu
AcceptanceCriteria:
The delivery of the Beta Test Plan will be determined ACCEPTABLE when the followingcriteria are met: The Beta Test Plan identifies and documents the tests to be run; The Beta Test Plan documents how the tests will be counted as successes or failures; The Beta Test Plan maps each test script (with associated test cases) back to a Requirement
ID; The Beta Test Plan identifies details of how testing will be carried out; The Beta Test Plan identifies the procedure for recording and transmitting test results; and The Beta Test Plan identifies test participants (with potential backups) and a confirmation of
their availability to test and their willingness to test in accordance with the prepared testplan and documented procedures.
Reviewer(s): Charlotte Gregg
Approver(s): Kimber Allen
(#8) DBA Migration Package (from ALPH to BETA)
Description: Data migrations plan for transferring data from existing applications to the new system. Thisplan identifies specific data to migrate and migration methods.
Produced by: Sesh Paladugu
AcceptanceCriteria:
The delivery of the DBA Migration Package will be determined ACCEPTABLE when thefollowing criteria are met: The number of beta users, with their locations, is detailed; The number and size of tables and the expected growth of the database is described; The package includes a list of the scripts that must be run to create and populate the Beta
database; and The package addresses the Beta environment as well as the DOPPLER (data warehouse)
environment, where necessary.
Reviewer(s): Charlotte Gregg, Robert Rouse
Approver(s): Spencer Lepley, Kimber Allen
Milestone - Supplement to the PA Users Manual (DRAFT)
Description:DRAFT of the supplement to the current PA Users Manual that describes how to use the newFIESTA PA form.
Produced by: Robert Rouse
CompletionCriteria:
The delivery of the DRAFT Supplement to the PA Users Manual will be determinedCOMPLETE when the following criteria are met: The supplemental information contains screen print(s) of the new form(s); The supplemental information describes any new functionality that has been added to the
PA system with the creation of the FIESTA PA form; and The supplemental information describes the difference between choosing the PA or the
FIESTA PA system from the Oracle main menu.
Reviewer(s): Charlotte Gregg
Beta Testing PhaseFollowing the setup of the BETA environment, User BETA Testing in accordance with the BETA Test Planwill be the major accomplishment/deliverable during this phase. Also, several documents that deal with theimplementation and training for the production system may be produced, such as the Training Plan, theImplementation Plan, and the DBA Migration Package (from BETA to PROD). The following are thedeliverables and/or milestones to be produced during the Beta Testing Phase for this project:
Milestone - BETA Environment Setup
Description: The Setup of the BETA Environment in preparation for User BETA Testing. This may includethe following: e-mail to the UNIX and Middle Tier groups to setup a path for Oracle forms onEPIC227 (BETA), the creation of a web on tlhora5, and the tasks required for the application
-
8/3/2019 Fiesta Pa Sow v1.5 Final
16/25
Milestone - BETA Environment Setup
security in WACA.
Produced by: Sesh Paladugu
Completion
Criteria:
The BETA Environment Setup will be determined COMPLETE when the following criteria aremet:
The correct path has been created on EPIC227 (BETA) for Oracle forms; The appropriate web has been created on tlhora5; and The WACA setup for BETA Testing has been completed.
Reviewer(s): Charlotte Gregg, Robert Rouse
(#9) User BETA Testing
Description:This deliverable represents the time and associated tasks for the user community to BETA testthe new system following the BETA test plan. The BETA Test is carried out in accordance withthe BETA Test Plan.
Produced by: Robert Rouse, Sesh Paladugu
AcceptanceCriteria:
The User BETA Testing will be determined ACCEPTABLE and COMPLETEwhen thefollowing criteria are met: The new FIESTA PA form is working as expected in the BETA environment; The data in the BETA environment database is accurate and formatted correctly; and All appropriate users were able to test the system and have the correct access and authority
to function as required in the BETA FIESTA PA form.
Reviewer(s): Charlotte Gregg, PA Data Entry team
Approver(s): Kimber Allen
Milestone - Supplement to the PA Users Manual (FINAL)
Description:FINAL supplement to the current PA Users Manual that describes how to use the new FIESTAPA forms.
Produced by: Robert Rouse
Completion
Criteria:
The delivery of the FINAL Supplement to the PA Users Manual will be determinedCOMPLETE when the following criteria are met: The supplemental information contains screen print(s) of the new form(s); The supplemental information describes any new functionality that has been added to the
PA system with the creation of the FIESTA PA form; and The supplemental information describes the difference between choosing the PA or the
FIESTA PA system from the Oracle main menu.Reviewer(s): Charlotte Gregg
Milestone - Training Plan
Description:This plan describes how user training will be conducted when the application is moved into
production.
Produced by: Robert Rouse
CompletionCriteria:
The delivery of the Training Plan will be determined COMPLETE when the following criteriaare met: The plan sufficiently details what if any training will be needed for users to use the new
FIESTA PA form and
The plan outlines how and when needed training will occur.Reviewer(s): Charlotte Gregg
(#10) Training Plan Checklist
Description: The Training Plan checklist should address all of the details necessary for training users.
Produced by: Sesh Paladugu
AcceptanceCriteria:
The delivery of the Training Plan Checklist will be determined ACCEPTABLE when thefollowing criterion is met: The training plan checklist is completed and all items pertaining to training have been
identified and planned for in the Training Plan.
Reviewer(s): Charlotte Gregg, Robert Rouse
-
8/3/2019 Fiesta Pa Sow v1.5 Final
17/25
(#10) Training Plan Checklist
Approver(s): Kimber Allen
(#11) Implementation Plan
Description:The Implementation Plan should include the details necessary for production migration; forexample, dates, file names, and locations of programs which must be run. Coordination with
Database Administration staff and the user community is imperative.Produced by: Sesh Paladugu
AcceptanceCriteria:
The delivery of the Implementation Plan will be determined ACCEPTABLE when the followingcriteria are met: The implementation plan identifies the steps that must be taken before the new system is
implemented in the production environment (excluding those details that will be in the DBAMigration Package) and
The implementation plan identifies all parties that should be notified of the new system tobe implemented.
Reviewer(s): Charlotte Gregg, Robert RouseApprover(s): Kimber Allen
(#12) DBA Migration Package (from BETA to PROD)
Description:
Data migrations plan for transferring data from existing applications to the new system. This
plan identifies specific data to migrate and migration methods.
Produced by: Sesh Paladugu
AcceptanceCriteria:
The delivery of the DBA Migration Package will be determined ACCEPTABLE when thefollowing criteria are met: The number of production users, with their locations, is detailed; The number and size of production tables and the expected growth of the database is
described; The package includes a list of the scripts that must be run to create and populate the
production database; The package addresses the production environment as well as the DOPPLER (data
warehouse) environment, where necessary; and The package lists the forms that must be moved from the beta to the production server(s).
Reviewer(s): Charlotte Gregg, Robert Rouse
Approver(s): Spencer Lepley, Kimber Allen
Implementation PhaseVerification of the successful production implementation is the key deliverable for this phase. In addition, a
project milestone for this phase can be updates to existing system documentation and/or additional training.The following is the deliverable to be produced during the Implementation Phase for this project:
(#13) Production Move and Verification
Description:
This deliverable involves physically installing the system on the appropriate production platformin accordance to the Implementation Plan. It also includes migrating data and granting access tothe appropriate users. At this point the application belongs to the program area and developersno longer have update access.
Produced by: Sesh Paladugu
AcceptanceCriteria:
The Production Move will be determined ACCEPTABLE when the following criteria are met:
All forms are working as expected in the production system;
All reports are working as expected in the production system;
The data in the production database is correct and formatted correctly; and
All start up users for the system have the correct access and authority to function as requiredin the FIESTA PA system.
Reviewer(s): Charlotte Gregg, Robert Rouse
Approver(s): Kimber Allen
-
8/3/2019 Fiesta Pa Sow v1.5 Final
18/25
ROLES & RESPONSIBILITIES
Project Organization ChartSee the picture below for the project organization chart. The assigned project role follows the individualor committee name. In most cases, these role names do not correspond to the individuals job titles;
however, they do indicate the position of responsibility to be played within this project.
F I E S T A P A S u b - P r o j e c t O r g a n i z a
K A l l e n , A pS M E - A p p
J C a n t e r , I
L C l a y , GS M E - G
B K e n n e d y ,
S M E - M i d
K K e r c h k o f S M E - N e t
S L e p l e y ,S M E - D B A
S P a l a d u g u /P A S M E , B
D a t a A r c h i t
P e r m i t t i( P A ) D aO r a c l e F
R R o u s e ,B u s i n e s s A n
D G o r t o n , SS M E - O r a
C G r e g gF I E S T A P A
K A l l e nP r o j e c t S
F B l a n t oS M E - P r
T T i z z a r dS M E - P r
T R e i nP r o j e c t M a
M a n a gE x e c u t i v e P r o j e c
Project Roles and Responsibilities TableThe following outlines the roles and responsibilities needed for the successful execution of thisproject:
Project Role Name Project Responsibilities
Note: This chart represents an organization structure only as it pertains to this project.
echnicalgmt. Group
Core SME Group
PM Group
-
8/3/2019 Fiesta Pa Sow v1.5 Final
19/25
ExecutiveProjectSponsor
ManagementSteeringCommittee
Approve Statement of Work (SOW) Approve changes in project scope or budget (change
requests) Final project approval
-
8/3/2019 Fiesta Pa Sow v1.5 Final
20/25
Project Role Name Project Responsibilities
ProjectCustomer KimberAllen
Approve Project Plan and Statement of Work (SOW) Approve changes in project scope or budget (change
requests) Resolution of escalated issues
Approve Deliverables Monitor project progress monthly Break ties for escalated issues that cannot be resolved by
the project team Project recommendations and guidance Final project approval
ProjectManager
CharlotteGregg
Develop Statement of Work (SOW) Validate critical success factors Develop and manage project to baseline project plan Oversee project status and communications Implement and track Quality Assurance (QA) on project Manage and facilitate resolution of issues Manage and facilitate change requests Manage and facilitate deliverable acceptance Manage risks identified in the SOW Develop and maintain a Project Notebook Archive Project documents when complete Deliver project results on time, within budget, without
surprises
BusinessAnalyst
RobertRouse, SeshPaladugu
Document business processes/rules for the CandidateNeeds
Document business processes/rules for the CandidateRequirements
Create the Impact Assessment Summary (IAS) Create Implementation Plan
Data Architect
SeshPaladugu,Ron Wright
Create/modify all needed database objects, includingtables, views, indexes, triggers, procedures, and/or roles.
ProgrammerSeshPaladugu,Ron Wright
Create forms/screens for data input Meet with users concerning form/screen needs and
preferred layout and style
Testing Lead
RobertRouse, SeshPaladugu
Create and document project BETA Test Plan Define project testers and user testers Lead testing effort
Testers Bob Shaw,CharlotteGregg
Perform tests of the new FIESTA PA form following theBETA Test plan
-
8/3/2019 Fiesta Pa Sow v1.5 Final
21/25
Project Role Name Project Responsibilities
Project OfficerTerryTizzard
Perform Project Reviews Assist Project Manager with implementation of BIS
Project Management Standards
SME-
PermittingApplication
Robert
Rouse, SeshPaladugu
Review Project Plan and Statement of Work (SOW)
SME-
Applications
KimberAllen
Review SOW Review Project Plan Review Candidate Needs and Candidate Requirements Review Impact Assessment Summary prior to distribution
to other BIS managers Review the forms Review the Beta Test Plan Provide subject matter expertise on application interfaces Provide testing assistance
SME-OracleForms
Ron Wright,DonnaGorton
Provide assistance to lead programmer with the analysis,design, and development of the new form(s).
Review Oracle forms Provide subject matter expertise on application interfaces
BISManagement
Group
KimberAllen, JonCanter, LincClay,BarbaraKennedy,KevinKerckhoff,
SpencerLepley
Review and approve the Impact Assessment Summary(IAS)
SME-DatabaseAdministratio
n
SpencerLepley
Approve DBA Migration Packages Review impact to database administration Provide subject matter expertise on database
administration issues Testing assistance
SME-Network& Systems
KevinKerckhoff
Provide subject matter expertise on network and systemissues
Testing assistance
SME-Middle
Tier
Barbara
Kennedy
Provide subject matter expertise on middle tier issues
Testing assistancePermittingApplication(PA) DataEntry Team
To bedetermined
Review Statement of Work Review Project Plan Provide subject matter expertise in the appropriate area Assist in the definition of data elements Review the ERD
-
8/3/2019 Fiesta Pa Sow v1.5 Final
22/25
PROJECT PLAN
A summarized project plan is presented here showing planned tasks and activities; planned startand finish dates and work estimates. This project was estimated using experienced basedestimating.
RISK MANAGEMENT
Risks exist on every project; however, proactive management can reduce risk occurrence andrisk impact to the project. A structured process serves to monitor, assess, and deal with knownrisks and to uncover new risks as they arise. Risks are communicated to the project team and tothe customer to encourage shared management of the potential risks. Risks are reviewed with the
-
8/3/2019 Fiesta Pa Sow v1.5 Final
23/25
customer to create awareness of what we are doing to address risk and also to make the customeraware we may seek their involvement in mitigation.
Risks are formally reviewed during creation of the SOW and each month thereafter. Theprevious risk assessment serves as input to the next risk assessment. However, new risks may beidentified and priorities can/do change. The Project Risk Assessment (PRAM) will be reviewed
and updated on a more frequent basis if warranted.
Project RisksThe following risks have been identified that may have an adverse impact on completion of theproject objectives. Risks are an attempt to predict potential issues that may come up in the lifecycle of the project. For probability (PROB) and consequence (CONSQ), H = High, M =Medium, and L = Low.
RiskID
RiskVariables
PRO
B
CONS
Q
Positive ImpactExpectation orEstimating
Assumption
Negative ImpactMitigation Steps(include mitigation
tasks in project plan)
1ProjectManagerAvailability
M MManagers are availableand complete tasks ontime.
The Project Manager willbe available to manageand complete all assignedtasks.
The Project Manager isimpeded by other
project tasks andassigned tasks aredelayed.
If necessary, shift tasks toother managers so thatthey are completed ontime.
2Vulnerabilityto Change
M M
Additionalneeds/requirements areidentified that clarifyinformation needed tocomplete the project.
The identified needs andrequirements will not beexpanded. It isanticipated that allcurrent business rules willremain unchanged for theFIESTA PA forms.
Additionalneeds/requirements areidentified that requireadditional modificationsto the detailedspecifications.
Request review of needsand requirements byappropriate staff; requestreview of detailedspecifications byappropriate staff; developa prototype and present itto appropriate staff.
3StaffAvailability
L M
The deliverables, dataentry interfaces, andreports will bethoroughly reviewed ortested and delivered ontime.
BIS staff will be availablefor deliverable reviewand testing.
The deliverables anddata entry interfaces arenot thoroughlyreviewed or tested.Forms may containcoding errors thatrequire correction.
Project status reports willidentify any resourceimpacts and requestreassignment of other BISstaff to replace anystaffing deficiencies andmitigate project impact.
4
CustomerParticipationin BetaTesting
M M
Select PA data entryusers are available to
beta test the newform(s); the new form(s)is (are) thoroughlytested.
A sufficient number ofPA data entry users will
be available to beta testthe new form(s).
Insufficient numbers ofPA data entry users areavailable for betatesting; the applicationis not thoroughly tested
prior to production
implementation.
Identify select PA dataentry users and schedule
beta testing sessions earlyin the project. Identifyalternate beta testers.
5 Timeframe M M
The application iscomplete andimplemented/available in
production before theend of September 2004.
The application iscomplete andimplemented/available in
production by the end ofSeptember 2004.
The form(s) logic ismore complex than theestimates provided inthe project plan.
Add an additionalresource, an Oracle Formexpert, to assist the lead
programmer with theanalysis, design anddevelopment of the newform(s).
http://opt/scribd/conversion/tmp/scratch6190/PRAM%20Template.xlshttp://opt/scribd/conversion/tmp/scratch6190/PRAM%20Template.xls -
8/3/2019 Fiesta Pa Sow v1.5 Final
24/25
CHANGE MANAGEMENT
Change ProcedureThe change procedure will be used in any situation where a change occurs to the project asdefined in this Statement of Work. As the project proceeds, there can be occasions when changes
are desired to the scope, approach, processes and procedures that were originally agreed to. Thechange process will also be used when these processes and procedures are violated or when thereis a failure to perform some aspect of the Statement of Work. The Project Manager estimates theimpact of change requests as to the need or benefit, the impact to cost and schedule and thensecures appropriate management approval before adjusting. Note that some changes do notimpact cost or schedule but alters expectations. These are called Informational Change Requestsand will be handled the same as non-informational change requests.
1. Anyone on the project team may request a change. This request is given to the ProjectManager. The Project Manager analyzes the change request and completes the ChangeRequest Form and presents the request to the Project Sponsor and/or Project Customer forreview, discussion, and disposition.
2. The change request must be disposed (approved or rejected) within 3 business days aftersubmittal. This approval/rejection must be in writing. The project will not be adjusted untilthe change request is approved. If no reply is received within the timeframe, the change istreated as an issue.
Change CriteriaThe change procedure will be used for any changes to the accepted Statement of Work,approved deliverables or approved change requests. A change request can adjust somethingprevious agreed to or define something that did not happen as planned. Examples include systemnot being available (lost time), people not performing their duties per the agreed roles andresponsibilities, changes to deliverables or project scope.
ACCEPTANCE MANAGEMENT
Acceptance ProcedureDeliverables are defined throughout the life of the project. These provide the building blocksthat move the project towards final completion. Acceptance of a deliverable means the customerhas given a go to use this deliverable as input to related future deliverables. Acceptance ofdeliverables on a timely basis is critical in order to avoid delays to the project. In order to ensuresmooth delivery and acceptance of all deliverables, the following process will be employed:
1. The Project Manager provides the deliverable to the appropriate and authorized signor for
review, accompanied by an Acceptance Form. The Acceptance Form includes a descriptionof the deliverable and the pre-approved acceptance criteria defined in the Statement of Workfor that deliverable.
2. Acceptance must be in writing (no verbal approvals). E-mail approvals are acceptable if theyare explicit (that is, clear which deliverable is approved). A walkthrough of the deliverablewith the customer is the preferred means of securing approval.
3. Acceptance must occur on a timely basis to avoid delays to the project. For this project,deliverables must be approved within 3 business days after receipt, unless an alternative time
http://opt/scribd/conversion/tmp/scratch6190/Change%20Request%20Form.dochttp://opt/scribd/conversion/tmp/scratch6190/Change%20Request%20Form.dochttp://opt/scribd/conversion/tmp/scratch6190/Deliverable%20Acceptance%20Form.dochttp://opt/scribd/conversion/tmp/scratch6190/Change%20Request%20Form.dochttp://opt/scribd/conversion/tmp/scratch6190/Change%20Request%20Form.dochttp://opt/scribd/conversion/tmp/scratch6190/Deliverable%20Acceptance%20Form.doc -
8/3/2019 Fiesta Pa Sow v1.5 Final
25/25
frame is mutually agreed upon. The Acceptance Form lists the specific due date to eliminateany confusion about when approval is needed to stay on schedule. If approval is not receivedon a timely basis, its lateness is treated as an issue. We never assume default acceptance orrejection. Rejections must specify what is unacceptable.
Final AcceptanceAt the conclusion of the project, after all project deliverables are approved, a Final ProjectAcceptance form will be submitted to acknowledge completion of all work and fulfillment of allobligations under this Statement of Work (and as amended through approved change requests).
APPROVED BY:
Kimber Allen, Project Customer& DEP Applications Section Manager
DATE
Charlotte Gregg, Project Manager DATE
Executive Project Sponsor or Bureau Chief DATE