New reinjection technologies in hydrocarbon fields Ravenna, 28 March 2008.
FGD retrofit a techno economic case study -...
Transcript of FGD retrofit a techno economic case study -...
FGD retrofit - a techno economic case study
Prof. Dr. W.A. BeneschDirector Energy Technologies
STEAG Energy Services Germany
Overview
• The power station
• The flue gas treatment system
• Used FGD technology
• Wet stack• Wet stack
• Technical data and features
• Material recommendations
• Costs
• Major messages
30.1.2017
Voerde power plantHistory of a site
1970/71 Commissioning of units 1 and 2 of the power plant West, 350 MW each
1975 Forming of the special purpose company “Kraftwerk Voerde STEAG-
RWE oHG”;RWE Power AG 25 %, Steag 75 %
1982 Commissioning of unit A of the Voerde power plant (710 MW) with flue
gas desulfurization system
1985 Commissioning of unit B of the Voerde power plant (710 MW) with flue
gas desulfurization system
1987 Retrofitting of the power plant West with a flue gas desulfurization
systemsystem
1989 Retrofitting of both power plants with nitrogen oxide reduction
systems
2005 Partial modernization of flue gas desulfurization system,
with capacity increase (2 x 50 MW)
2006 Retrofitting of the power plant West with capacity increase (2 x 6 MW)
2017 The entire plant will be shut down in April due to the “Energy
Turnaround “
At Voerde site, STEAG operates the power plants West and Voerde.
2 pulverized-coal fired Benson slag tap boilers ( 980 t/h each),
2 pulverized-coal fired Benson boilers – dry ash removal (2,160 t/h each),
4 turbine-generator sets (2 x 350 MW, 2 x 761 MW in total 2222MW)
30.1.2017
General layout of the site
1. Coal conveyor belt
2. Boiler
3. Turbine hall
4. SCR
5. Ammonia storage5. Ammonia storage
6. ESP
7. FGD
8. ID-Fans
9. Stack
10. Cooling tower
11. Coal storage
Background
The units Voerde A/B had been equipped stepwise with flue-
gas treatment installations.
• Originally 30% of the flue gas had been cleaned of SO2.
• Later on, this had been extended to 100% of the flue-gas
stream.
• 1989 also the SCR technology had been implemented for
30.1.2017
• 1989 also the SCR technology had been implemented for
NOx reduction after
• exhaustion of all primary NOx measures before.
Over the years, especially the complicated FGD installation
caused high maintenance costs and OPEX which led to the
wish of a related cost reduction.
A study on a simple improvement of the FGD system did not
show the desired reduction of maintenance costs.
FGD-plant units Voerde A/BDesign data
Full load operating hours / year 2,000 to 7,000
Start up time (cold) 180 min
Ramp rate 7% / min
Primary Fuel: hard coal
LHV 25.5 to 30 MJ/kg
sulphur content 0.3 to 1.3 %
Flue gas data (110% load)
Volume 2,677,180 m³/h (st. wet)
SO2 content 640 to 2,635 mg/m³
HCL max 230 mg/m³
Dust max 100 mg/m³
Inlet temperature 130 to 180°C
Temperature in case of failure 220°C (max. 15 min)30.1.2017
FGD-plant for the units A/BPerformance dataEmissions (referring to dry flue gas, standard conditions, 6% O2 )
SOX as SO2 < 150 mg/m³
85 % sulphur reduction at the lowest
SO2 concentration in raw gas of 640 mg/m³ < 96 mg/m³
SO2 distribution in the flue gas downstream of the scrubber:
admissible deviations of the SO2 clean gas value
over the measuring section based on100 mg/m³ ± 30 % over the measuring section based on100 mg/m³ ± 30 %
Change of emission and performance values at
a concentration range in the flue gas of 10 % / min
HCl < 10 mg/m³
Content of dust < 10 mg/m³
Content of droplets in the flue gas downstream
of the mist eliminator < 20 mg/m³
30.1.2017
FGD-plant for the units A/BSpecial performance characteristics:
Gypsum dewatering
Residual moisture max. 10 %
Max. gypsum mass flow per filter 32.6 t/h
Absorbent consumption
per absorber (100% load) 10.48 t/hper absorber (100% load) 10.48 t/h
Energy consumption
per absorber (100% load) 2,935 kWh/h
Auxiliary plants 630 kWh/h
Admissible content of chlorine in absorber slurry
due to process and material technology 60,000 ppm
30.1.2017
FGD-plant for the units A/BAbsorber ain data and corrosion protection
Total height 35.8 m
Diameter 17 m
Bottom height 9.5 m
Bottom volume 2,383 m³
Absorber space velocity 3.8 m/sec
Number of nozzle levels 4
Suspension pumps 4 x 8,800 m³/h
Number of nozzles per level 189
Level distance 1.8 m
30.1.2017
4 single-stage centrifugal pump (mineral cast)
1 pump variable speed
capacity 8.800 m³/h
delivery height max. 21 m
power consumption 900 kW
Circulation pumps FGD VoerdeDetails
iron volute casing (with mineral-cast)
closed impeller (mineral-cast)
axial suction flange
tangential discharge flange
suction-side wear plate (mineral-cast)
single acting mechanical seal
pressure side diffusor / compensator-combination
Reasons for the FGD replacement (2005)
Improvement of the environmental situation
● SO2: from 400 to 200 mg/Nm³
● Dust: from 50 to 20 mg/Nm³
Capacity increase (710 MW ���� 760 MW, 2 x 50 MW) (710 MW ���� 760 MW, 2 x 50 MW)
Reduction of maintenance costs due to deletion of components
● Gas-gas heaters
● Flue gas dampers
● FGD booster fans
30.1.2017
No flue gas reheating• Reduction of the investment
• Reduction of the pressure loss, operating costs
• Reduction of the maintenance costs
Advantages and technical opportunities in case of no lower limit for the exhaust gas temperature
T > 72°C
Opportunities in that case:
Wet Flue gas discharge over
wet Stack
cooling tower
T 50-52°C
T 50-52°C
Decision for a wet stack
Total height 230 m
Diameter Ø 8 m
Reinforced concrete shaft with 2 flues
out of GRP (glass reinforced plastics)
Flue gas velocity < 18 m/s at 110% load
Condensate catching groove at flue gas inlet and exit of the stack
Condensate return in closed vertical channel
Avoidance of any obstacles in the flue gas stream
30.1.2017
• Flow velocity < 18 m/s
• Avoidance of guide vanes
• Avoidance of condensate accumulation
• Optimum hydraulic design for the flue gas duct entry
• Avoidance of vortex flows
Design criteria for „Wet Stacks“in general
• No reinjection of already condensed water into the flue gas stream
• Expansion joints with condensate extraction
• Complete acid resistant stack head
• No flange connection of flue gas ducts
• Condensate catching groove at flue gas inlet and exit of the stack
• FGD with three stage demister
• Acid resistant design of the flue gas duct and of flue gas guide vanes
30.1.2017
• Boiler: utilization of existing reserve capacity
• Turbine: utilization of existing reserve capacity
• ESP: static reinforcement
• Raw gas ducts static reinforcement or new
Units Voerde A/BOverall retrofit measures and costs
• ID – fans: retrofit
• Absorbers: new
• Clean gas ducts: new
• Stack: new wet stack
Investment: 80 Mio €
30.1.2017
The key for the successful, economic solution was the combination of different improvement measures for the entire power plant in one project. So
• the existing boiler margin had been used,
• slight improvements of the turbine had been done,
• the efficiency of the entire plant had been increased,
Major messages
30.1.2017
• the efficiency of the entire plant had been increased,
• the I&C-System had been retrofitted and
• the opportunities of a new regulatory frame work allowing a wet stack without reheating of the flue gases had been used.
• Finally, a simplified FGD system using the latest know-how of FGD technology, meeting also the in the meantime more stringent emission limits could make a successful project out of it, while
• the overall plant capacity had been increased by 2 x 50 MWel .
• At least the maintenance cost had been reduced significantly.