FGD retrofit a techno economic case study -...

22
FGD retrofit - a techno economic case study Prof. Dr. W.A. Benesch Director Energy Technologies STEAG Energy Services Germany

Transcript of FGD retrofit a techno economic case study -...

FGD retrofit - a techno economic case study

Prof. Dr. W.A. BeneschDirector Energy Technologies

STEAG Energy Services Germany

Overview

• The power station

• The flue gas treatment system

• Used FGD technology

• Wet stack• Wet stack

• Technical data and features

• Material recommendations

• Costs

• Major messages

30.1.2017

Voerde power plantHistory of a site

1970/71 Commissioning of units 1 and 2 of the power plant West, 350 MW each

1975 Forming of the special purpose company “Kraftwerk Voerde STEAG-

RWE oHG”;RWE Power AG 25 %, Steag 75 %

1982 Commissioning of unit A of the Voerde power plant (710 MW) with flue

gas desulfurization system

1985 Commissioning of unit B of the Voerde power plant (710 MW) with flue

gas desulfurization system

1987 Retrofitting of the power plant West with a flue gas desulfurization

systemsystem

1989 Retrofitting of both power plants with nitrogen oxide reduction

systems

2005 Partial modernization of flue gas desulfurization system,

with capacity increase (2 x 50 MW)

2006 Retrofitting of the power plant West with capacity increase (2 x 6 MW)

2017 The entire plant will be shut down in April due to the “Energy

Turnaround “

At Voerde site, STEAG operates the power plants West and Voerde.

2 pulverized-coal fired Benson slag tap boilers ( 980 t/h each),

2 pulverized-coal fired Benson boilers – dry ash removal (2,160 t/h each),

4 turbine-generator sets (2 x 350 MW, 2 x 761 MW in total 2222MW)

30.1.2017

General layout of the site

1. Coal conveyor belt

2. Boiler

3. Turbine hall

4. SCR

5. Ammonia storage5. Ammonia storage

6. ESP

7. FGD

8. ID-Fans

9. Stack

10. Cooling tower

11. Coal storage

Power Station Voerde Unit A/B

Boiler and turbine generator set

30.1.2017

Background

The units Voerde A/B had been equipped stepwise with flue-

gas treatment installations.

• Originally 30% of the flue gas had been cleaned of SO2.

• Later on, this had been extended to 100% of the flue-gas

stream.

• 1989 also the SCR technology had been implemented for

30.1.2017

• 1989 also the SCR technology had been implemented for

NOx reduction after

• exhaustion of all primary NOx measures before.

Over the years, especially the complicated FGD installation

caused high maintenance costs and OPEX which led to the

wish of a related cost reduction.

A study on a simple improvement of the FGD system did not

show the desired reduction of maintenance costs.

Units Voerde A/B, FGD – retrofit

Before retrofit

30.1.2017

Units Voerde A/B, FGD – retrofit

Retrofit without Bypass

30.1.2017

FGD-plant units Voerde A/BDesign data

Full load operating hours / year 2,000 to 7,000

Start up time (cold) 180 min

Ramp rate 7% / min

Primary Fuel: hard coal

LHV 25.5 to 30 MJ/kg

sulphur content 0.3 to 1.3 %

Flue gas data (110% load)

Volume 2,677,180 m³/h (st. wet)

SO2 content 640 to 2,635 mg/m³

HCL max 230 mg/m³

Dust max 100 mg/m³

Inlet temperature 130 to 180°C

Temperature in case of failure 220°C (max. 15 min)30.1.2017

FGD-plant for the units A/BPerformance dataEmissions (referring to dry flue gas, standard conditions, 6% O2 )

SOX as SO2 < 150 mg/m³

85 % sulphur reduction at the lowest

SO2 concentration in raw gas of 640 mg/m³ < 96 mg/m³

SO2 distribution in the flue gas downstream of the scrubber:

admissible deviations of the SO2 clean gas value

over the measuring section based on100 mg/m³ ± 30 % over the measuring section based on100 mg/m³ ± 30 %

Change of emission and performance values at

a concentration range in the flue gas of 10 % / min

HCl < 10 mg/m³

Content of dust < 10 mg/m³

Content of droplets in the flue gas downstream

of the mist eliminator < 20 mg/m³

30.1.2017

FGD-plant for the units A/BSpecial performance characteristics:

Gypsum dewatering

Residual moisture max. 10 %

Max. gypsum mass flow per filter 32.6 t/h

Absorbent consumption

per absorber (100% load) 10.48 t/hper absorber (100% load) 10.48 t/h

Energy consumption

per absorber (100% load) 2,935 kWh/h

Auxiliary plants 630 kWh/h

Admissible content of chlorine in absorber slurry

due to process and material technology 60,000 ppm

30.1.2017

FGD-plant for the units A/BAbsorber ain data and corrosion protection

Total height 35.8 m

Diameter 17 m

Bottom height 9.5 m

Bottom volume 2,383 m³

Absorber space velocity 3.8 m/sec

Number of nozzle levels 4

Suspension pumps 4 x 8,800 m³/h

Number of nozzles per level 189

Level distance 1.8 m

30.1.2017

Nozzle Level / Raw Gas Inlet

PP-Nozzle

Level

Brombutyl-

caoutchouc

Raw Gas

Inlet

Alloy

30.1.2017

4 single-stage centrifugal pump (mineral cast)

1 pump variable speed

capacity 8.800 m³/h

delivery height max. 21 m

power consumption 900 kW

Circulation pumps FGD VoerdeDetails

iron volute casing (with mineral-cast)

closed impeller (mineral-cast)

axial suction flange

tangential discharge flange

suction-side wear plate (mineral-cast)

single acting mechanical seal

pressure side diffusor / compensator-combination

Units Voerde A/BFGD – retrofit

Reasons for the FGD replacement (2005)

Improvement of the environmental situation

● SO2: from 400 to 200 mg/Nm³

● Dust: from 50 to 20 mg/Nm³

Capacity increase (710 MW ���� 760 MW, 2 x 50 MW) (710 MW ���� 760 MW, 2 x 50 MW)

Reduction of maintenance costs due to deletion of components

● Gas-gas heaters

● Flue gas dampers

● FGD booster fans

30.1.2017

No flue gas reheating• Reduction of the investment

• Reduction of the pressure loss, operating costs

• Reduction of the maintenance costs

Advantages and technical opportunities in case of no lower limit for the exhaust gas temperature

T > 72°C

Opportunities in that case:

Wet Flue gas discharge over

wet Stack

cooling tower

T 50-52°C

T 50-52°C

Decision for a wet stack

Total height 230 m

Diameter Ø 8 m

Reinforced concrete shaft with 2 flues

out of GRP (glass reinforced plastics)

Flue gas velocity < 18 m/s at 110% load

Condensate catching groove at flue gas inlet and exit of the stack

Condensate return in closed vertical channel

Avoidance of any obstacles in the flue gas stream

30.1.2017

• Flow velocity < 18 m/s

• Avoidance of guide vanes

• Avoidance of condensate accumulation

• Optimum hydraulic design for the flue gas duct entry

• Avoidance of vortex flows

Design criteria for „Wet Stacks“in general

• No reinjection of already condensed water into the flue gas stream

• Expansion joints with condensate extraction

• Complete acid resistant stack head

• No flange connection of flue gas ducts

• Condensate catching groove at flue gas inlet and exit of the stack

• FGD with three stage demister

• Acid resistant design of the flue gas duct and of flue gas guide vanes

30.1.2017

• Boiler: utilization of existing reserve capacity

• Turbine: utilization of existing reserve capacity

• ESP: static reinforcement

• Raw gas ducts static reinforcement or new

Units Voerde A/BOverall retrofit measures and costs

• ID – fans: retrofit

• Absorbers: new

• Clean gas ducts: new

• Stack: new wet stack

Investment: 80 Mio €

30.1.2017

The key for the successful, economic solution was the combination of different improvement measures for the entire power plant in one project. So

• the existing boiler margin had been used,

• slight improvements of the turbine had been done,

• the efficiency of the entire plant had been increased,

Major messages

30.1.2017

• the efficiency of the entire plant had been increased,

• the I&C-System had been retrofitted and

• the opportunities of a new regulatory frame work allowing a wet stack without reheating of the flue gases had been used.

• Finally, a simplified FGD system using the latest know-how of FGD technology, meeting also the in the meantime more stringent emission limits could make a successful project out of it, while

• the overall plant capacity had been increased by 2 x 50 MWel .

• At least the maintenance cost had been reduced significantly.