Fieldbus Design and Project Executionfor FPSO Projects
Murali Krishnan Tand
aus u es pan eEmerson Process Management, Asia Pacific
1
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 2/24
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 3/24
Agenda
• Typical project organization•
Implementation Process• Modular concept• S stem hardware desi n deliver and installation
flexibility•
Software standards for FPSO automation• f hn l i
3Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 4/24
Proven project execution model
Project Manager
Involving specialist in• Operational experience• Power and Automation Systems
Project Execution Model• Stages with definedobjectives
How do ou do it?SpecialistsHSE
• Milestones
Asset
Conce tual System and Power Safety and Automation Installation su ort & O erational
ro ec supporOptimisation
engineering detail engineering Systems System Commissioning Support
Experienced personnel in• Project Management• Application knowledge
• Global Support• Engineering
•• Safety and Automation System• Instrumentation / Valves• Power Systems• Fieldbus Technology
• Installation supervision• Commissioning• Service• Fieldbus Workshops
4Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 5/24
Project Execution
FEED Phase
Integrated Engineering Team during FEED, follow-up
• ( Customer / Contractor / Suppliers / End-user )• Customer/End-User/Contractor experts availability• -
• Prepare and train customer organization and yard-teams for
utilization of new designs/techniques and maximize the yield• Prepare and distribute project design specifications and
perform FEED• Empowered participation in the preparation of tender
documents and package procurement to enforce standardsand improve data from package units
5Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 6/24
Project Execution
• Design phase• Implementation phase•
FAT – Metering Skid• FAT – Top Sides
• Site work on Offshore location
FDS helpsensureagreement
6Singapore FPSO Seminar - 21 August 2009
consistency
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 7/24
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 8/24
FEED Phase
FieldbusDeployment
FEED PhaseExample of Physical Design: HazardousArea•Easier live maintenance:-Exi- ExnL
•What device and component hazardousarea certification is required?-FISCO devices for FNICO-Entity Exi devices for Entity ExnL
8Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 9/24
Engineering Phases
FieldbusDeployment
FEED Phase
FieldbusTechnical
Fieldbus
Engineering Phase
ApplicationWorkshop Design /
Segmentation
SimulationTest
9Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 10/24
Training for Success
• Training is a critical success factor for any projects• For most projects the customer, EPC, and sub-contractors have not
undergone extensive Foundation fieldbus training• Standard training must be customized to the unique design and
requirements of each project
ay
1) Foundation Fieldbus Technical Overview2) Project Fieldbus Component3) Segment Design4) Fieldbus Installation5) Field-Check and Troubleshooting
6) Transmitter - Fieldbus functionality7) Valve Positioner - Fieldbus functionality8) Fieldbus Systems Setup (Hands-on)
10Singapore FPSO Seminar - 21 August 2009
9) Roundup : Questions and Answers
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 11/24
Fieldbus Application Workshop
EPC defines philosophy (rules) by which
Workshop topics for discussion:
achieve desired control availability
Consists of:- Definition of control loop criticality level
• Application Scope of Foundation Fieldbus
• Cable Selection
- Restrictions for allocation for controlcriticality level- Analysis and ranking of control
loops/valves
• rrangemen o , roun ng
• Redundant Philosophy
• Macro-cycle philosophy
Impacts:- Number of devices per bus- Number of loops per bus
• Function Block Requirement• Controller Location (CIC/CIF)
• Zone Application
11Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 12/24
Functional Design Specification (FDS)
• Generated by the ProjectTeam
•
Common design philosophydocument for all parties
– Hazardous area concept
– Components – r ng – Design considerations – Control strategy
– Etc.
12Singapore FPSO Seminar - 21 August 2009 12
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 13/24
Fieldbus Implementation Methodology
EPC
• EPC will load the segment based on process plot plan and results from
Se ment Desi n Tool risk assessment rocess criticalit and e ui ment
unit.Segment Allocation = assigning devices to busSegment Loading = block and communication timing
13Singapore FPSO Seminar - 21 August 2009
egmen es gn = ca cu a e curren an vo age
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 14/24
Fieldbus Segment Design Tool
14Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 15/24
Fieldbus Implementation Methodology
• EPC will load the segment based on process plot plan and results from, , .
• MIV will then validate for any software constraint and provide FieldbusSegment Software Analysis to EPC.
15Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 16/24
Fieldbus Software Validation
• Report
– Macrocycle – VCRs and other resources
16Singapore FPSO Seminar - 21 August 2009 16
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 17/24
Site Commissioning Phase
FieldbusDeployment
FEED Phase Site Commissioning Phase
CommissioningWorksho
FieldbusTechnical
Fieldbus
Engineering Phase Final Review
Loop Check &Commissioning
ApplicationWorkshop Design /
Segmentation
SimulationTest
17Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 18/24
Installation & Pre-commissioning
Test E ui ment• Establish procedure and checklist• Hands-on training• Installation test tools are made available in required
quantity so as to not delay project – – Fieldbus tester
– Oscilloscope – • Pre-commissioning test tools are made available
– Fieldbus tester
– Handheld field communicator
18Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 19/24
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 20/24
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 21/24
Technical solution for FPSO
Cabinets with ‘late IO bindin ’
21Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 22/24
Software Configuration Flexibility
AI module PID module Pump module
Database-Area: M10 - Separation
Modules in DCS Engineering Database
M10 – Se aration skid M41 - MCC
AI PIDPump
22Singapore FPSO Seminar - 21 August 2009
Classic & HART I/O Fieldbus I/O
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 23/24
Use of Bus Technology for FPSO
Safety Control & ElectricalDataMonitoringAcquisition
23
Digital system architecture that uses the power of field intelligence to
23Singapore FPSO Seminar - 21 August 2009
8/2/2019 Ff Design and Project Execution
http://slidepdf.com/reader/full/ff-design-and-project-execution 24/24
Summary
Key success factors:
– oun a on e us a rea y use n severa
projects
– construction approach of FPSOs
– FDS discussion hel s to o timize desi n and savecost
– Tools and Documentation by Vendor
24 – Training at all stages is vital for success
24Singapore FPSO Seminar - 21 August 2009