Office of Energy Projects 1 FERC Update Robert J. Cupina Deputy Director Office of Energy Projects Federal Energy Regulatory Commission Wyoming Infrastructure Authority Board Of Directors January 31, 2006

description

FERC Update. Wyoming Infrastructure Authority Board Of Directors January 31, 2006. Robert J. Cupina Deputy Director Office of Energy Projects Federal Energy Regulatory Commission. Adequate Infrastructure OEP. Effective Market Rules OEMR. Market Oversight OMOI. - PowerPoint PPT Presentation

Transcript of FERC Update

Page 1: FERC Update

Office of Energy Projects

1

FERC Update

Robert J. CupinaDeputy Director

Office of Energy Projects Federal Energy Regulatory Commission

Wyoming Infrastructure Authority Board Of DirectorsJanuary 31, 2006

Page 2: FERC Update

2

FERC

Office of Energy Projects

FERCHelping Markets Work

AdequateInfrastructure

OEP

MarketOversight

OMOI

CompetitiveMarketFERC

EffectiveMarket Rules

OEMR

Page 3: FERC Update

3

FERC

Office of Energy Projects

FERC’sHydropower Projects

Transmission Line Capacity0 - 59 kV60 - 229 kV≥ 230kV

Page 4: FERC Update

4

FERC

Office of Energy Projects

FERC’s HydroTransmission Lines

Transmission Line Capacity

Number of Transmission

Lines≥ 230 kV 82

60 – 229 kV 300

< 60 kV 1216

5,800 miles of primary transmission line

Page 5: FERC Update

5

FERC

Office of Energy Projects

Source: Based on Platts PowerMap

FERC certificatesU.S. interstate natural gas

pipelines

Page 6: FERC Update

6

FERC

Office of Energy Projects

Existing LNGImport Terminals

LAKE CHARLESLAKE CHARLES

ENERGY BRIDGEENERGY BRIDGE

ELBA ISLANDELBA ISLAND

COVE POINTCOVE POINT

EVERETTEVERETT

Page 7: FERC Update

7

FERC

Office of Energy Projects

Existing Gas StorageFacilities

Source: Based on Platts PowerMap, October 2005.

Page 8: FERC Update

8

FERC

Office of Energy Projects

Siting Infrastructure:Lessons Learned

• Early staff involvement• Proactively identity issues and

alternative siting• Develop advocates not adversaries• Expertise to provide a sound record • Recommendations based on

technical analysis

Page 9: FERC Update

9

FERC

Office of Energy Projects

Energy Policy Actof 2005

• EPAct 2005 provides for federal siting of interstate electric transmission facilities (§1221) by amending the FPA (§216)- Designation of National Interest Electric

Transmission Corridors (§216(a))- Construction Permit (§216(b))- Coordination of Federal Authorizations

for Transmission Facilities (§216(h))

Page 10: FERC Update

10

FERC

Office of Energy Projects

EPAct 2005Electric Transmission Corridors

• Conduct study within one year of electric transmission congestion

– Every three years thereafter

• Issue report based on study– Designate any geographic area that

experiences congestion as a “National Interest Electric Transmission Corridor”

Page 11: FERC Update

11

FERC

Office of Energy Projects

EPAct 2005Construction Permit

• FERC can authorize construction of transmission facilities in a corridor if:

– A state has no authority to either site facilities or consider interstate benefits, or

– A state, with authority to site, either does not act within one year or conditions approval such that there is either no reduction in congestion or is not economically feasible

Page 12: FERC Update

12

FERC

Office of Energy Projects

EPAct 2005Construction Permit

• Application to be filed with FERC– Filing requirements to be issued

• Comments will be received• Rights-of-way

– Right of eminent domain– Acquired right-of-way used exclusively

for electric transmission facilities

• Compensation

Page 13: FERC Update

13

FERC

Office of Energy Projects

EPAct 2005Coordination of Federal Authorizations

• Lead agency for permit coordination and environmental review

– Must issue regulations within 18 months– Must enter into an MOU with other

agencies within one year– Provide a pre-filing mechanism

• All permit decisions and environmental reviews shall be completed within one year

– Failure to act within deadlines may be appealed to the President

• DOE delegation to FERC likely

Page 14: FERC Update

Major Pipeline Projects Certificated (MMcf/d)

2000 to Present

42.2 BCF/D Total8,474 Miles

Transco (204,236,323)

Southern (336,330)

Kern River

(135,886)

6

NorthBaja(500)

Tuscarora(96)

Northwest(162,113)

Kern River (282)

TETCO(250)

Northwest(224)

NFS/DTI (150)

GeorgiaStraits (96)

SCG Pipeline (190)

1

23

4

Northwest(191)

East Tennessee (510)

Tennessee (320)

TETCO (197)

Greenbrier (584)

El Paso (230,320,620)

WBI(80)

ANR(194,750,210,220,

107,143,168)

17

TETCO(223)

Cove Point(445)

Ocean Express(842)

14

CheyennePlains (560,170)

16

13. CIG (282,92)14. CIG (85,133,118,105)15. TransColorado (125,300)16. WIC (120,116,675,350)17. El Paso (140) 18. Rendezvous (300) 19. Entrega (1,500)

8

Calypso (832)

Discovery (150)

Transwestern (150,375)

5

Trunkline(1,500)

Cheniere Sabine (2,600)

Trunkline (200)

Questar

(272,102) 6

Petal (700,600)

Horizon(380)

GTN(207)

Otay Mesa (110)

Florida Gas (239,270)

East Tennessee (170)

7

1. Algonquin (285) 2. Islander East (285) 3. Iroquois (230,85) 4. Columbia (135,270) 5. Algonquin (140) 6. Transcontinental (105) 7. Transcontinental (130) 8. Tennessee (200) 9. Maritimes (80,360)10. Algonquin (301)11. Tennessee (500)12. Mill River (800)

8

Millenium (700)9

10

Northern Border

(544,130)

Independence (916)

TransUnion (430)

Southern Trails (120)

Gulfstream(1,130)

11

Guardian(750)

Trailblazer(324)

1315

El Paso (502)

Center Point (113)

Vista del Sol (1,100)

Golden Pass (2,000)

12

1819

San Patricio (1,000)

Dominion South (200)

Columbia (172)

East Tennessee (86)

Tennessee(400,200)

Cheniere Corpus Christi (2,600)

14

FERC

Office of Energy Projects

Page 15: FERC Update

15

FERC

Office of Energy Projects

Sources: NERC Summer and Winter Assessments, WECC Existing Generation and Significant Additions and Changes to System Facilities Reports and FERC’s Transmission Database

Major ElectricTransmission Lines

2000 to Present

345 kV

230 kV

Transmission Projects

DC

CaldwellCaldwellOntarioOntario

ClarksvilleClarksville Chamber Springs RoadChamber Springs Road

Mt. EnterpriseMt. EnterpriseTenaskaTenaska

LamarLamar HolcombHolcomb

BrownleeBrownleeOxbowOxbow

SpurlockSpurlock

Tap of Stuart/ W H Zimmer Tap of Stuart/ W H Zimmer ShorehamShoreham

New Haven HarborNew Haven Harbor

345 kV

230 kV

Transmission Projects

328 miles

Page 16: FERC Update

16

FERC

Office of Energy Projects

Related Proceedings

• Transmission Investment Pricing Reform– RM06-04– NOPR Issued November 18, 2005– Comments due January 11, 2006

• 109 comments filed

– Final rule due in one year (August 2006)• DOE’s National Interest Electric

Transmission Corridor Study– NOI expected soon

Page 17: FERC Update

17

FERC

Office of Energy Projects

Issues forElectric Transmission

• Clear Regulatory Path• Contract Commitment• Pricing Incentives• Market Response - Timing

Page 18: FERC Update

18

FERC

Office of Energy Projects

What Will MakeThis Work

• FERC staff involvement as early as possible

• Develop a pre-filing process• Start with two points and work the

route• Voluntary agency enlistment• Rational Siting Process

– One federal lead agency, one record for decisions, one avenue of appeal