Feed-in Tariff factsheet - E.On

22
Feed-in Tariff factsheet

Transcript of Feed-in Tariff factsheet - E.On

Feed-in Tariff factsheet

2

The Feed-in Tariff (FIT) scheme is

a government initiative that pays

householders and businesses to generate

their own energy from renewable sources.

The FIT scheme makes it more financially

viable for householders and businesses

to buy and install a renewable energy

generator, such as solar photovoltaic

(PV) panels or a wind turbine.

Qualifying generators will be eligible to receive a

set payment rate for every unit (kWh) of electricity

produced, even if this electricity is used on site.

Additional export payments may also apply.

Payment rates for both generated and exported

electricity are fixed (and Retail Price Index adjusted

each year), and for solar PV, generation rates apply

for up to 20 years. This gives anyone participating in

the scheme the security of a long-term market for

the electricity they produce.

Introducing Feed-in Tariffs

Electricity generated

On-site generation unit

Electricity used

Electricity flows

Total generation meter

Import meter

Export meter

Network

3

The benefits of Feed-in Tariffs

As well as receiving FIT payments, there are other

important reasons why you should consider installing

a renewable energy generator.

• Research has shown that property buyers are willing

to pay more for a property that has been fitted with

a renewable energy generator.*

• DECC have designed the tariffs so that it is possible to

recoup the entire cost of buying and installing eligible

generators and potentially make a profit.

• You could make a valuable contribution to reducing

carbon emissions, helping to protect our environment.

• Your electricity bills should be reduced because

you’re likely to need to buy less electricity from

your energy supplier.

* Source: Energy Saving Trust Market Research, September 2009

Which renewable energy generators will qualify?

The following generators may be eligible

for FIT payments:

• Solar PV

• Wind

• Hydro

• Anaerobic digestion

• Domestic micro CHP

(with an installed capacity of 2kW or less).

4

Feed-in Tariff elements

Generation paymentYou’ll receive a generation payment for every kWh

of electricity you generate, whether you use it

yourself or export it to the Electricity Network.

The rate per kWh varies depending on factors, such

as the generator type and size. To provide investor

certainty, Generation Tariff rates are largely fixed

throughout the duration of your FIT agreement; but

will move in line with the Retail Prices Index (RPI) to

ensure inflation is taken into account.

See the table to the right for an overview of the

current rates and tariff lifetimes. These rates

should apply until 31 March 2014 when the next RPI

changes come into effect, however the government

may revise prices before then.

Export paymentFor all eligible generators connected to the

Electricity Network, an export payment,

currently fixed at 4.5p per kWh will be available.

Although this rate is fixed (and RPI adjusted) again

the Government has reserved the right to change

the export rate should they consider it

appropriate to do so. Export payments are

made in addition to the generation payment.

NB: If your generator is ‘off-grid’, you won’t

be able to export electricity and so will not

be eligible to receive export payments.

Generation payment rates (p/kWh)

Installations registered in FITs Year 4 (01 April 2013 -

31 March 2014)

Generator Scale Tariff received until 31 March 2014

Tariff lifetime (years)

* This tariff is only available for 30,000 micro CHP installations. A review will take place when 12,000 units have been installed.

** Assumes EPC level D and no Multi Installation Tariff reduction.

Source: Department of Energy & Climate Change.

*** Actual rate dependant on EU approval.

Anaerobic <250kW 15.16 20

250kW-500kW 14.02 20

500kW+ 9.24 20

CHP <2kW 12.89 10

Hydro <15kW 21.65 20

15kW-100kW 20.21 20

100kW-500kW 15.98 20

500kW-2mW 12.48 20

2mW+ 3.23 20

Solar <4kW 15.44 20

4kW-10kW 13.99 20

10kW-50kW 13.03 20

50kW-100kW 11.50 20

100kW-150kW 11.50 20

150kW-250kW 11.00 20

250kW+ 7.10 20

Standalone 7.1 20

Wind <1.5kW 21.65 20

1.5kW-15kW 21.65 20

15kW-100kW 21.65 20

100kW-500kW 18.04 20

500kW-1.5mW 9.79 20

1.5mW+ 4.15 20

ROO Migrated Installations

<50kW 10.21 20

5

How much could you be paid?Take a look at the diagram below to see how

much a typical household could receive in FIT

payments. This is an illustrative example only,

and is based upon solar PV panels with an

installed capacity of 4kW or less, fitted to an older

property (ie not installed as part of a new build).

Meters, meter readings and paymentsTo qualify for the FIT scheme, you must have an

approved generation meter fitted to measure how

much electricity you’re generating.

If you’re exporting electricity to the Electricity Network,

you may also need an approved export meter fitted.

• If your generator has an installed capacity greater

than 30kW, it is mandatory that you have an export

meter fitted to measure the amount of electricity

being exported to the Electricity Network. If you do

not already have an export meter, we can arrange

for one to be fitted.*

• If your generator has an installed capacity of 30kW

or below, you do not need an export meter as we’ll

deem (or estimate) your export amount based upon

50% of your total generation (75% for hydro).

You’ll need to supply us with quarterly readings

from your relevant meters so that we can calculate

your FIT payments. We’ll then pay these into your

nominated bank account when due.

We can supply and install both generation and

export meters*, so please contact us for details.

* There is a charge for this service.

Elements Without solar panels With solar panels

Import costs 3,300 x 16pkWh = £528/Annum 2,300 x 16p/kWh = £368/annum

Generation costs 0 3,400 x 15.4p/kWh = £525/annum

Export tariff 0 1,700 x 4.6p/kWh = £78/annum

Total -£528/annum +£235/annum

Example

Generation

Total generation 2,500kWhDiffers by technology and scale

Imported

Electricity usage4,500kWh

Export tariff

Total export 1,250kWhFixed at 4.5p/kWh

Solar panel

This customer has generated

3,400kWh of their own electricity,

avoiding costs for 1,700kWh from

their supplier.

6

Eligibility for FIT payments

If your renewable energy generator was installed

after 1 April 2010, the key rules for qualification are

that your generator must:

• have an installed electrical capacity of 5MW or less

(2kW or less for domestic scale micro CHP units)

• be one of five approved types:

• Anaerobic digestion

• Solar PV

• Wind

• Hydro

• Domestic scale micro CHP units

(with a capacity of 2kW or less).

• have appropriate accreditation in place

• Generators with an electrical capacity of

50kW or less (other than anaerobic digestion)

must be appropriately accredited under the

Microgeneration Certification Scheme (MCS).

If you’re unsure if your device is MCS accredited,

please check with your installer.

• Generators with an electrical capacity above

50kW up to and including 5MW (and anaerobic

digestion) must be accredited under the

Renewables Obligation Order (ROO) FIT process.

If your generator is not currently accredited,

please contact Ofgem for further advice.

• have an approved generation meter. If you don’t

already have one, we can arrange for one to be

fitted as part of your application*.

• be connected to the Electricity Network to claim

FIT export payments. If your installed electrical

capacity is above 30kW in size, you must also

have an appropriate export meter to measure

the amount of electricity being exported.

• not be registered to receive FIT generation

payments from more than one energy supplier.

• not be registered to claim ROCs at the same time

as any FIT payments.

• comply with eligibility requirements where grants

have been issued.

• from 1 April 2012 obtain an EPC level D certificate to

ensure higher generation rate are paid for PV

installations below 250kWh.

If your renewable energy generator was installed

prior to 1 April 2010, please contact us to find out

if you’re eligible.

And finally when you complete your application

please ensure the following are included:

• Proof of ID

• Proof of ownership

• valid Start Reading

• evidence of rights to generate (if relevant)

• generator accreditation if 50kW and below

• EPC certificate

• appropriate solar PV declaration

Failure to do this will result in your application being

invalid.

* There is a charge for this service.

Further reading

You can read more about Feed-in Tariffs and

their background at the following websites:

www.decc.gov.uk

www.energysavingtrust.org.uk

www.FITariffs.co.uk

www.lowcarboneconomy.com

www.ofgem.gov.uk

7

Glossary of terms

Carbon Dioxide (CO2)

A greenhouse gas.

Kilowatt (kW)

One thousand watts.

Megawatt (MW)

One thousand kilowatts.

Micro Combined Heat and Power unit (mCHP)

It heats the building in the same way as a gas boiler

and also generates electricity, most of which is used

in the building.

Microgen

A device that produces electricity from a low carbon

source with an installed capacity of 50kW or below.

Microgeneration

The production of heat and/or electricity on

a small scale from a low carbon source.

Microgeneration Certification Scheme (MCS)

A process of accreditation to be undertaken

for generating units with an installed capacity

of 50kW or less.

Off Grid

A generation unit which is connected to a private

wire network and not the Electricity Network.

Renewables Obligation Certificate (ROC)

An existing government scheme to reward generators

with an installed capacity above 50kW.

Solar Photovoltaic (PV)

Converts sunlight into electricity.

How to apply for the FIT scheme

Before you apply, please check to make sure that your

generator qualifies. If you need more information,

read our FAQs or call us on 0845 301 4884 for advice,

or to request an application form. Our opening hours

are 9am to 6pm Monday to Friday, 8am to 4pm Saturday.

You can also download the form from our website:

eonenergy.com/feedintariffs

Useful contact details

E.ON FIT helpline: 0845 301 4884

MCS helpdesk: 0207 090 1082

Ofgem: ofgem.gov.uk

Ofgem Renewables and CHP Register:

0207 901 7310

8

Frequently asked questions

What are FIT payments based on? The Government

sets minimum FIT rates which are priced to offer around

a 5-8% return on your investment, based on average

calculations for an appropriately located generator.

As an illustrative example only, if you’ve spent £10,000

on FIT-eligible solar photovoltaic (PV) panels, you can

typically expect to receive between £500 and £800 a

year in FIT-related ‘benefit’ (this benefit includes typical

expected savings as a result of reduced electricity bills

due to generating and consuming electricity on site).

How do I define the date of commission of my technology? This is assumed to be the date on which

your generator was installed and confirmed to be

working (generating).

Can I claim Renewable Obligations Certificates (ROCs) at the same time as FIT payments? No. If you have a choice

between the two schemes, you must choose one only.

Note: Microgenerators (generation with an installed

electrical capacity of 50kW or less) from 1 April 2010, can

only register for the FIT scheme (not ROCs). Small-scale

generators with an installed electrical capacity above

50kW and not greater than 5MW who had applied under

the Renewables Obligation (RO) for ROCs, before 15 July

2009, will remain in the RO and will not be eligible to

transfer to the FIT scheme.

Can E.ON accredit my installation? No. With the exception

of anaerobic digestion, eligible microgeneration (with

an installed electrical capacity of 50kW and below) and

installed after 1 April 2010 must be accredited under

the Microgeneration Certification Scheme (MCS).

Generators with an installed capacity of more than

50kW and anaerobic digestion must be accredited

under the Renewables Obligation Order (ROO-FIT

accreditation) as administered by Ofgem. Please

see back page for contact details.

What happens if I have more than one eligible generator on a single site? If each different type of

eligible generator has an installed electrical capacity

not exceeding 5MW (2kW or less for domestic scale

micro CHP), you’ll be able to receive FIT payments

for each of your eligible generators.

Will my electricity Direct Debit payment go down? The amount won’t change just because you’ve signed

up to the FIT scheme. But if you start buying less

electricity, your Direct Debits should be adjusted

when your payment amount is periodically reviewed.

Do I need to be on a green energy tariff to qualify for the FIT scheme? No, you can be on any type

of energy tariff.

As I’m getting paid for exporting electricity, is it in my interests to export everything I generate? Typically, no. The FIT scheme is designed to encourage

efficient use of the electricity you generate on site.

This should reduce the amount of electricity you need

to buy from your energy supplier, resulting in lower bills.

Improving energy efficiency should enable you to export

more ‘surplus’ electricity to the Electricity Network. Fixed

FIT export payments will attract a payment of 3p/kWh.

Will I be taxed on the generation and export payments I receive? Householders will not be taxed on the payments

they receive. Businesses and corporations should check

their tax liability with HM Revenue & Customs (HMRC).

Are generation and export payments inflation-linked? Yes. Payment levels will be adjusted every year in line

with the Retail Price Index (RPI).

Will you read my meters? You’ll need to read your

generation and export meters quarterly and submit

the readings to us. However, we’ll periodically read

these meters for audit purposes. Your import meter

will continue to be read as normal.

What happens if I move house or business premises? You can agree change of ownership of your generator

as part of your property sale.

Can landlords claim FIT payments for generators at tenants’ properties? Yes. If you’re a landlord installing

FIT-eligible generation at your property(s) you can claim

FIT payments. You’ll need to agree provision of these

meter reads with your tenants.

Can builders receive FIT payments if they install renewable energy generators at new properties? Under the Code for Sustainable Homes, builders can

claim FIT payments on new builds. The Government

sees this as a good way of helping builders meet the

costs of achieving Zero Carbon Buildings.

A more detailed list of FAQ’s is available on our FIT

website:

eonenergy.com

Anaerobic <250kW 1 Apr 10 - 31 Mar 11Anaerobic digestion with total installed capacity of 250kW or less

13.1

250kW-500kW 1 Apr 10 - 31 Mar 11Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW

13.1

500kW and over 1 Apr 10 - 31 Mar 11Anaerobic digestion with total installed capacity greater than 500kW

10.2

CHP <2kW 1 Apr 10 - 31 Mar 11Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units)

11.3

Hydro <15kW 1 Apr 10 - 31 Mar 11Hydro generating station with total installed capacity of 15kW or less

22.6

15kW-100kW 1 Apr 10 - 31 Mar 11Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW

21.7

100kW-500kW 1 Apr 10 - 31 Mar 11Hydro generating station with total installed capacity greater than 100kW but not exceeding 500kW

12.5

500kW-2mW 1 Apr 10 - 31 Mar 11Hydro generating station with total installed capacity greater than 500kW but not exceeding 2MW

12.5

2mW+ 1 Apr 10 - 31 Mar 11Hydro generating station with total installed capacity greater than 2MW

5.1

Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1)

9

Feed-in tariff payment rate tables for eligible installations

Depending on the year when eligibility commenced please refer to

appropriate appendix for latest prices.

Appendix 1 1 April 2010 - 31 March 2011 (FIT Year 1)

Appendix 2 1 April 2011 - 31 March 2012 (FIT Year 2)

Appendix 3 1 April 2012 - 31 March 2013 (FIT Year 3)

Appendix 4 1 April 2013 - 31 March 2014 (FIT Year 4)

All FIT payment rates are pence per kilowatt hour (p/kWh) at 2013/14 values.

Appendix 1 1 April 2010 - 31 Mar 2011 (FIT Year 1)

Appendix

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description p/kWh

ROO Migrated Installations

<50kW 1 Apr 10 - 31 Mar 11

Eligible Installations with a declared net capacity of 50kW or less commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010

10.2

Solar <4kW 1 Apr 10 - 31 Mar 11Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

46.8

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

40.8

4kW-10kW 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

40.8

10kW-50kW 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW

35.6

50kW-100kW 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

35.6

100kW-150kW 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

33.2

150kW-250kW 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

33.2

250kW+ 1 Apr 10 - 31 Mar 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW

33.2

n/a 1 Apr 10 - 31 Mar 11Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building)

33.2

Wind <1.5kW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity of 1.5kW or less 39.1

1.5kW-15kW 1 Apr 10 - 31 Mar 11Wind with total installed capacity greater than 1.5kW but not exceeding 15kW

30.2

15kW-100kW 1 Apr 10 - 31 Mar 11Wind with total installed capacity greater than 15kW but not exceeding 100kW

27.3

100kW-500kW 1 Apr 10 - 31 Mar 11Wind with total installed capacity greater than 100kW but not exceeding 500kW

21.2

500kW-1.5mW 1 Apr 10 - 31 Mar 11Wind with total installed capacity greater than 500kW but not exceeding 1.5MW

10.7

1.5mW+ 1 Apr 10 - 31 Mar 11Wind with total installed capacity greater than 1.5MW

5.1

Export n/a 1 Apr 10 - 31 Mar 11 All FIT Export Tariff Rate 3.3

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description p/kWh

Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1)

10

Anaerobic <250kW 1 Apr 11 - 29 Sept 11Anaerobic digestion with total installed capacity of 250kW or less

13.1

30 Sept 11 - 31 Mar 12Anaerobic digestion with total installed capacity of 250kW or less

15.2

250kW-500kW 1 Apr 11 - 29 Sept 11Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW

13.1

30 Sept 11 - 31 Mar 12Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW

14.0

500kW and over 1 Apr 11 - 31 Mar 12Anaerobic digestion with total installed capacity greater than 500kW

10.2

CHP <2kW 1 Apr 11 - 31 Mar 12Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units)

11.3

Hydro <15kW 1 Apr 11 - 31 Mar 12Hydro generating station with total installed capacity of 15kW or less

21.9

15kW-100kW 1 Apr 11 - 31 Mar 12Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW

19.6

100kW-500kW 1 Apr 11 - 31 Mar 12Hydro generating station with total installed capacity greater than 100kW but not exceeding 500kW

12.1

500kW-2mW 1 Apr 11 - 31 Mar 12Hydro generating station with total installed capacity greater than 500kW but not exceeding 2MW

12.1

2mW+ 1 Apr 11 - 31 Mar 12Hydro generating station with total installed capacity greater than 2MW

4.9

ROO Migrated Installations

<50kW 1st Apr 11 - 31 Mar 12

Eligible Installations with a declared net capacity of 50kW or less commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010

10.2

Solar <4kW 1 Apr 11 - 2 Mar 12Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

46.8

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

40.8

11

Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1)

Appendix 2 1 April 2011 - 31 March 2012 (FIT Year 2)

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description p/kWh

Solar (cont.d)

3 Mar 12 - 31 Mar 12Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

21.7

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

21.7

4kW-10kW 1 Apr 11 - 2 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

40.8

3 Mar 12 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

17.3

10kW-50kW 1 Apr 11 - 2 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW

35.6

3 Mar 12 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW

15.7

50kW-100kW 1 Apr 11 - 31 July 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

35.6

1 Aug 11 - 2 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

20.5

3 Mar 12 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

13.3

100kW-150kW 1 Apr 11 - 31 July 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

33.2

1 Aug 11 - 2 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

20.5

3 Mar 12 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

13.3

150kW-250kW 1 Apr 11 - 31 July 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

33.2

1 Aug 11 - 2 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

16.2

12

Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description p/kWh

Solar (cont.d)

3 Mar 12 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

13.3

250kW+ 1 Apr 11 - 31 July 11Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW

33.2

1 Aug 11 - 31 Mar 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW

9.2

n/a 1 Apr 11 - 31 July 11Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building)

33.2

1 Aug 11 - 31 Mar 12Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building)

9.2

Wind <1.5kW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity of 1.5kW or less 39.1

1.5kW-15kW 1st Apr 11 - 31 Mar 12Wind with total installed capacity greater than 1.5kW but not exceeding 15 kW

30.2

15kW-100kW 1st Apr 11 - 31 Mar 12Wind with total installed capacity greater than 15kW but not exceeding 100kW

27.3

100kW-500kW 1st Apr 11 - 31 Mar 12Wind with total installed capacity greater than 100kW but not exceeding 500kW

21.2

500kW-1.5mW 1st Apr 11 - 31 Mar 12Wind with total installed capacity greater than 500kW but not exceeding 1.5MW

10.7

1.5mW+ 1st Apr 11 - 31 Mar 12Wind with total installed capacity greater than 1.5MW

5.1

Export n/a 1st Apr 11 - 31 Mar 12 All FIT Export Tariff Rate 3.3

Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description p/kWh

13

Anaerobic <250kW1 Apr 12 - 31 Mar 13

Anaerobic digestion with total installed capacity of 250kW or less

15.2

250kW-500kW1 Apr 12 - 31 Mar 13

Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW

14.0

500kW and over1 Apr 12 - 31 Mar 13 Anaerobic digestion with total

installed capacity greater than 500kW

10.2

1 Dec 12 - 31 Mar 13

9.2

CHP <2kWBefore the conditional date*

Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units)

11.3

After the conditional date*

12.9

Hydro <15kW1 Apr 12 - 30 Nov 12

Hydro generating station with total installed capacity of 15kW or less

22.6

1 Dec 12 - 31 Mar 13

21.7

15kW-100kW1 Apr 12 - 31 Mar 13

Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW

20.2

100kW-500kWBefore the conditional date* Hydro generating station with

total installed capacity greater than 100kW but not exceeding 2MW

12.5

After the conditional date*

16.0

500kW-2mW1 Apr 12 - 31 Mar 13

Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW

12.5

2mW+1 Apr 12 - 30 Nov 12

Hydro generating station with total installed capacity greater than 2MW

5.1

1 Dec 12 - 31 Mar 13

4.6

Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1)

Appendix 3 1 April 2012 - 31 March 2013 (FIT Year 3)

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

Solar <4kW 1 Apr 12 - 31 Jul 12

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

21.7 17.3 9.3

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

21.7 17.3 9.3

1 Aug 12 - 31 Oct 12

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

16.5 14.9 7.3

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

16.5 14.9 7.3

1 Nov 12 - 31 Mar 13

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

15.4 13.9 7.1

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

15.4 13.9 7.1

4kW-10kW 1 Apr 12 - 31 Jul 12

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

17.3 13.8 9.3

1 Aug 12 - 31 Oct 12

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

15.0 13.5 7.3

1 Nov 12 - 31 Mar 13

14.0 12.6 7.1

10kW-50kW 1 Apr 12 - 31 Jul 12

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW

15.7 12.6 9.3

1 Aug 12 - 31 Oct 12

13.9 12.5 7.3

1 Nov 12 - 31 Mar 13

13.0 11.7 7.1

Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

Solar (cont.d)

50kW-100kW 1 Apr 12 - 31 Jul 12

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

13.3 10.6 9.3

1 Aug 12 - 31 Oct 12

11.9 10.7 7.3

1 Nov 12 - 31 Mar 13

11.5 10.4 7.1

100kW-150kW 1 Apr 12 - 31 Jul 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

13.3 10.6 9.3

1 Aug 12 - 31 Oct 12

11.9 10.7 7.3

1 Nov 12 - 31 Mar 13

11.5 10.4 7.1

150kW-250kW 1 Apr 12 - 31 Jul 12Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

13.3 10.6 9.3

1 Aug 12 - 31 Oct 12

11.3 10.2 7.3

1 Nov 12 - 31 Mar 13

11.0 9.9 7.1

250kW+ 1 Apr 12 - 31 Jul 12

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW

9.2

1 Aug 12 - 31 Oct 12

7.3

1 Nov 12 - 31 Mar 13

7.1

Standalone 1 Apr 12 - 31 Jul 12Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building)

9.3

1 Aug 12 - 31 Oct 12

7.3

1 Nov 12 - 31 Mar 13

7.1

Wind <1.5kW1 Apr 12 - 30 Nov 12

Wind with total installed capacity of 1.5kW or less

36.9

1 Dec 12 - 31 Mar 13

21.7

Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

Wind (cont.d) 1.5kW-15kW1 Apr 12 - 30 Nov 12 Wind with total installed

capacity greater than 1.5kW but not exceeding 15 kW

28.9

1 Dec 12 - 31 Mar 13

21.7

15kW-100kW1 Apr 12 - 30 Nov 12 Wind with total installed

capacity greater than 15kW but not exceeding 100kW

26.2

1 Dec 12 - 31 Mar 13

21.7

100kW-500kW1 Apr 12 - 30 Nov 12 Wind with total installed

capacity greater than 100kW but not exceeding 500kW

21.2

1 Dec 12 - 31 Mar 13

18.0

500kW-1.5mW1 Apr 12 - 30 Nov 12 Wind with total installed

capacity greater than 500kW but not exceeding 1.5MW

10.7

1 Dec 12 - 31 Mar 13

9.8

1.5mW+1 Apr 12 - 30 Nov 12

Wind with total installed capacity greater than 1.5MW

5.1

1 Dec 12 - 31 Mar 13

4.6

ROO Migrated Installations

<50kW1 Apr 12 - 31 Mar 13

Eligible Installations with a declared net capacity of 50kW or less Commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010

10.2

Export n/a 1 Apr 12 - 31 Jul 12

Solar Export Tariff Rate

3.3

1 Aug 12 - 31 Mar 13

4.6

1 Apr 12 - 30 Nov 12

Non Solar Export Tariff Rate

4.6

1 Dec 12 - 31 Mar 13

4.6

Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

* The Conditional Date referred to in the entries for certain descriptions of installations applies only where the European Commission gives state aid approval on or before 31 March 2013 for the higher rate specified in the entry and in such case the conditional date is the later of (a) 1 December 2012, or (b) the date on which the approval is given. If state aid approval is not given on or before 31 March 2013, the lower rate specified in the entry applies throughout FIT Year 3.

Anaerobic <250kW1 Apr 13 - 31 Mar 14

Anaerobic digestion with total installed capacity of 250kW or less

15.2

250kW-500kW1 Apr 13 - 31 Mar 14

Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW

14.0

500kW and over1 Apr 13 - 31 Mar 14

Anaerobic digestion with total installed capacity greater than 500kW

9.2

CHP <2kWAfter the conditional date*

Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units)

12.9

Hydro <15kW1 Apr 13 - 31 Mar 14

Hydro generating station with total installed capacity of 15kW or less

21.7

15kW-100kW1 Apr 13 - 31 Mar 14

Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW

20.2

100kW-500kW1 Apr 13 - 31 Mar 14

Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW

16.0

500kW-2mW1 Apr 13 - 31 Mar 14

Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW

12.5

2mW+1 Apr 13 - 31 Mar 14

Hydro generating station with total installed capacity greater than 2MW

3.2

Solar <4kW1 Apr 13 - 31 Mar 14

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied

15.4 13.9 7.1

Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation

15.4 13.9 7.1

Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4)

Appendix 4 1 April 2013 - 31 March 2014 (FIT Year 4)

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

Solar (cont.d)

4kW-10kW1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW

14.0 12.6 7.1

10kW-50kW1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW

13.0 11.7 7.1

50kW-100kW1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW

11.5 10.4 7.1

100kW-150kW1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW

11.5 10.4 7.1

150kW-250kW1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW

11.0 9.9 7.1

250kW+1 Apr 13 - 31 Mar 14

Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW

7.1

Standalone1 Apr 13 - 31 Mar 14

Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building)

7.1

Wind <1.5kW1 Apr 13 - 31 Mar 14

Wind with total installed capacity of 1.5kW or less

21.7

1.5kW-15kW1 Apr 13 - 31 Mar 14

Wind with total installed capacity greater than 1.5kW but not exceeding 15 kW

21.7

15kW-100kW1 Apr 13 - 31 Mar 14

Wind with total installed capacity greater than 15kW but not exceeding 100kW

21.7

100kW-500kW1 Apr 13 - 31 Mar 14

Wind with total installed capacity greater than 100kW but not exceeding 500kW

18.0

Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4)

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

Wind (cont.d) 500kW-1.5mW1 Apr 13 - 31 Mar 14

Wind with total installed capacity greater than 500kW but not exceeding 1.5MW

9.8

1.5mW+1 Apr 13 - 31 Mar 14

Wind with total installed capacity greater than 1.5MW

4.2

ROO Migrated Installations

<50kW1 Apr 13 - 31 Mar 14

Eligible Installations with a declared net capacity of 50kW or less Commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010

10.2

Export n/a1 Apr 13 - 31 Mar 14

Non Solar Export Tariff Rate 4.6

Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4)

Technology type

Generation levelPeriod in Year Eligibility Started

Technology Description EPC Level Requirement

n/aHigher rate

Middle rate

Lower rate

E.ON UK plc Westwood Way Westwood Business Park Coventry CV4 8LG

Registered in England and Wales No 2366970

eonenergy.com/business 0172

/07/

12