Federal AviationAdministrationData Comm 1

Federal AviationAdministrationKey Site Timelines

Hal Ludwig &

Pete Muraca

Page 2: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 2

Accomplishments Since Last DCIT

• SLC IOC Declared 8/7/2015• IAH and HOU upgraded to TDLS V.12 SW• HOU TDLS-ERAM Direct Connect Interface is operational• International Flights

– Hyphen issue for non-US Flag carriers will be fixed in release on 9/10– International flights for all carriers only CAF initially (revision by voice

only)– Resolved prior to waterfall.

• Coordinated with first set of waterfall sites –– ZHU ZID ZNY – held first two coord mtgs –

• On track for IOC at MSY, SDF, and EWR.

• Aug. 25 kickoff with second set of waterfall sites (ZLA, ZME, ZBW, ZDV)

Page 3: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 3

SLC Test Status-IOC Declared• Operators Supported Testing leading up to IOC at Salt Lake City

7 FedEx Express (MD11)

7 UPS (B767 & MD11)

7 United Airlines (B737-900)

7 Southwest Airlines (B737-800)

7 Harris Corporation (Falcon 9)

7 US Air Force (KC-135)

Page 4: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 4

Path to ISD2015

10/22

JUL AUG SEPT OCT NOV DEC

ZLC/SLC IOC

8/7

ZHUIAHIOC

9/10

ZHUHOUIOC

9/30

ZLCZTL

Complete

11/30

IOAComplete

12/09

ISD

Phase 3

EAD40

Phase 5

Mil

es

ton

es

V12.0.411/6

EADXX = ERAM

= TDLS

= TIMS

V12.XX

V12.XX

ZLC

SLC

ZTL

Draft v5.1

9/3

Field Activities

ZLC/ZTL Nat’l Site Failover

CPDLC - SLC

ZLC/SLCDFV Dry run& Conduct

Phase 4

8/19

9/10 9/30

ZHU/IAH/HOU DFV Dry Run &

Conduct

IAH/HOU Enhanced CHI

ZHU EAD30 Install

TDLS

9/18

V12.0.512/18

ZLC EAD30 Install

8/7

ARTCC EAD40 Install

8/27

Test onlyT

IMS

You are here

P1 P1

ZHUERAMuplevelto DC

7/6 - 7/9

P0

IAHTEDC

HOUTEDC

7/1

8/13

V12.0.3.xxx9/10

SLCBOI

V12.0.2

V12.0.2Int’l Flights

IAHHOU

7/21

ZL

C/S

LC

TO

& F

M T

estin

g

7/9-11

7/22

SLCBOI

IAH

HOU

7/23-25

9/10

P3

7/29 – 8/5

8/3-4 8/6-8/12

EAD30

7/30 - 8/1

ZL

C/Z

HU

Par

ent/N

at’l

Inte

grat

ion

P4

8/13-17

SLCBOIIAHHOU

SLCBOIIAHHOU

V12.0.27/15

SLCBOI

7/16-18

V12.0.2

TIM

S

V12.0.38/14

SLCBOI

IAHHOU

8/15-17

11/21

Thanksgiving

11/30 12/19

Christmas

1/4

8/18-20

ZTL EAD30 Install

8/17ZTL

Network Connectivity Testing &SSM-220

8/31 9/4

8/5

8/5

Page 5: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 5

KIAH – Carrier DFV Participation Lead-Up Timeline

8/22 - 8/27

Testing w/ Carrier

8/19 - 8/27

May-15 Sep-15

Jun-15 Jul-15 Aug-15 Sep-15

Sep-15Aug-15

8/19 - 8/27

8 /11Final Test Scripts

Provided to Participants

5/18IAH Coordination Meeting

Coordinate Detailed KIAH DFV Schedule

with Participants

8/28 - 9/38/19 - 8/27Dry Run w/ Tech Center Avionics and Carrier

8/19 - 8/21Testing w/ WJHTC

8/28 - 9/3 9/3KIAH IOC

KIAH DFV Dry Run

8/28 - 9/3DFV - File and Fly Flights

KIAH DFV Conduct

9/3

KIAH IOC

Page 6: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 6

KIAH DateTesting Window Tentative

ERAMDispatch

(FPL Filing)

Local Flight Deck

Remote Flight Deck

AOC System

Testing w/ WJHTC

08/19 – 08/21W, Th, F

Mid-ShiftActive and Back-Up

mode

Testing w/ Carrier

08/22 – 08/23Sa, Su

Mid-ShiftActive and Back-Up

mode

Testing w/ Carrier

08/24 – 08/27M, Tu, W, Th

Mid-Shift orDay & Swing

Shift (as Aircraft

avail.)

Active and Back-Up

mode

CarrierFile and Fly

08/28 – 09/03F, Sa, Su, M, Tu, W, Th

Normal OpsActive and Back-up

mode

IOC 9/3

Note: Mid-Shift is 2200-0300 or 0500 (Local)

Page 7: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 7

IAH Test Status• Conduct DFV field testing @ IAH with the following major carriers

and test facilities:– UPS – UAL– FDX – FAA Technical Center Bench Avionics (B757 / 767, B737)

Page 8: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 8

KHOU – Carrier DFV Participation Lead-Up Timeline

8/27 - 9/2

Testing w/ Carrier

8/24 - 9/2

May-15 Oct-15

Jun-15 Jul-15 Aug-15 Sep-15 Oct-15

9/3 - 9/10

9/10KHOU IOC

Sep-15Aug-15

8/24 - 9/2

7/9Final Test Scripts

Provided to Participants

5/12KHOU Coordination Meeting

Coordinate Detailed KHOU DFV Schedule

with Participants

8/24 - 9/2Dry Run w/ Tech Center Avionics and Carrier

9/3 - 9/10

KHOU DFV Conduct

9/3 - 9/10

DFV - File and Fly Flights

8/24 - 8/26Testing w/ WJHTC

9/10KHOU IOC

KHOU DFV Dry -Run KHOU DFV Conduct

Page 9: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 9

KHOU DateTesting Window

TentativeERAM

Dispatch (FPL

Filing)

Local Flight Deck

Remote Flight Deck

AOC System

Testing w/ WJHTC

08/24 – 08/26M, Tu, W

Mid-ShiftActive and Back-Up

mode

Testing w/ Carrier

08/27 – 08/28Th, F

Mid-ShiftActive and Back-Up

mode

Testing w/ Carrier

08/29 – 09/02Sa, Su, M, Tu, W

Mid-Shift or Day & Swing

Shift (as Aircraft

avail.)

Active and Back-Up

mode

CarrierFile and Fly

009/03 – 09/10Th, F, Sa, Su, M, Tu, W, Th

Normal OpsActive and Back-up

mode

IOC 9/10

Note: Mid-Shift is 2200-0300 or 0500 (Local)

Page 10: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 10

HOU Test Status• Conduct DFV field testing @ HOU with the following major

carriers:– UPS – SWA – UAL– FDX – FAA Technical Center Bench Avionics (B757 / 767, B737)

Page 11: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 11

AOC Interface Scorecard

• Completed testing with UPS, FDX, and UAL• Working with USAF TACC to test Interface• SWA working based on SLC testing.

Page 12: Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.

Federal AviationAdministrationData Comm 12

Discussion Items

• TDLS Updated IRD Review– IRD Rev A has NAS CCB approval

• Interface is available for test (WJHTC and IFCET)– IRD Rev B NAS CCB approval

• SDB Inputs– Web interface activation delayed for additional testing.