FEDERAL AID PLAN DEVELOPMENT
Federal Aid Group
MN/DOT METRO DISTRICT STATE AID STAFF
Colleen VanWagner Project Manager 651-234-7779
Jim Deeny Construction Specialist
651-234-7762 [email protected]
Scott Eue Project Manager 651-234-7764
Dmitry Tomasevich Project Manager 651-234-7778
Michelle Moser Project Manager 651-234-7775
Dan Erickson Federal Aid Engineer
651-234-7763 [email protected]
Federal Aid and State Aid Construction
FEDERAL AID
PROCESS OVERVIEW(steps to complete a Federal Aid project)
State Transportation Improvement Program (STIP)
Project Kick Off Meeting Project Development Report Construction Plan Review and Approval Authorization of Federal Funds Letting, Contract Award, & Approval Contract Administration
State Transportation Improvement Program (STIP)
Projects are awarded federal funding Regional Solicitation, High Priority, Safe Routes
to School, Non-Motorized All federal funded projects must be listed
in or amended into the current approved STIP.
Projects added when new STIP is created Formal STIP Amendment
2-3 month approval process
Project Kick Off Meeting
Federal Aid Project Manager meets with Local Agency
Items for discussion include: Project Schedule/Sunset Date Project proposed vs. project application Type of Project Development Report needed Project Issues
R/W 4(f) Historic Railroad
Funding; total dollars/local match Regulatory Agencies (CRU, Environmental Serv., DNR)
Project Development ReportInitial Review Submit 4 signed, unbound copies to Federal Aid Project
Manager Document will be reviewed and comments forwarded to
SALT LPA will receive Metro and SALT comments LPA makes correctionsFinal Review LPA submits 5 copies signed, unbound copies to
Federal Aid Project Manager Federal Aid Project Manager submits to SALT for
approval.
Construction Plan SubmittalInitial Review Unbound Copies of the plan
(please keep the originals) 1 copy for Project Manager review 1 additional copy if Storm Sewer is proposed 1 additional copy if project includes a RR crossing 1 additional copy if bridge is proposed 15 additional copies if project contains a Trunk
Highway endpoint or x-ing
Construction Plan SubmittalInitial Review (continued) DCP Form 01 Plan Review Checklists (State Aid and Federal Aid)
See Samples Engineers Estimate Laboratory Testing Services Form Parking Resolutions Drainage Area Maps & Computations R Value/ESAL documentation (pavement design calcs) SJRs and/or Warrant Analysis
Construction Plan SubmittalFinal Review and Approval (DCP 02 Form) Signed original plan and 3 copies Revised Engineer’s Estimate R/W Certificate #1 and checklist or #1A Utility Relocation Certificate Permits Special Provisions Resolution for City Approval (County projects)
Required if City signature is not on plan
Plan Review and Approval Log plan into data base
Route to TH functional areas if applicable Route to State Aid Hydraulics, RR or other agencies if
applicable
Compare plan to Project Development Report Project Termini Construction Elements/Scope Typical Section
Project Cost Significant increases in cost may require a formal STIP
Amendment
Plan Review and Approval Review Preliminary Plan
Format and Plan Content Conformance to State Aid Rules/Standards
Hierarchy: State Aid Rules, Road Design Manual, AASHTO
Federal Eligibility (see handouts) Check for required Permits/Documentation Forward R/W Certificate for Review and Approval Prepare Review Letter and/or Red Line Prints and
Send to Designer or Local Agency for plan revisions
Plan Review and Approval Review Final Plan
Verify all Comments have been addressed Request DBE Goal Check for Required Documentation
Revised Eng. Estimate, R/W Certificate, etc.
Obtain State Aid Engineer Signature for Approval Request Federal Authorization
Plan FormatTitle Sheet (see sample) Minnesota Department of Transportation Construction Plan For
Work description (pay item level of detail) Located on ___________ from _______ to _________ SP # lower right corner Minn. Proj. No. in upper right corner Length Blocks for each roadway
Length must agree with stationing on index map Bar Scales Sheet numbers in lower right corner
Numerical sequencing
Plan FormatTitle Sheet (continued) Index Map
Label major roadways Begin and end SP and stationing Proposed Signals and Bridges
Unless a general layout is included in the project
Governing Specifications Note Utility Quality Level (see handout) Index of Sheets
List A & B sheets separately Include “This plan contains XX Sheets” below index
Plan FormatTitle Sheet (continued) Design Designation Block (roadway)
Must match Approved Proj. Development Report Present (year to be let) and 20 year projected ADT Design Speed and exceptions (must be in approved PDR) Structural Design Strength Soil Factor and HCADT or R Value and ESAL (must
match supporting documentation) Number of Traffic Lanes (thru lanes only) Number of Parking lanes or shoulder width
Plan FormatTitle Sheet (continued) Design Designation Block (bikeway)
Must match approved Proj. Development Report Design Speed Height of Eye/Height of Object Design Exceptions (must be in approved PDR)
Plan Preparation Certification Required on all sheets except x-sections Required on Standard Plan sheets that have been
modified
Plan FormatTitle Sheet (continued) Signature Block (see handout)
County Signature – County Funds City Signature – City Funds Agency receiving funds if not City or County Mn/DOT Signatures if Trunk Highway Funded Signature or permit required if project impacts
another agencies R/W State Aid Signatures
Plan FormatStatement of Estimated Quantities TRNS*PORT list
Match item numbers and units; descriptions vary Trunk Highway funded; match TRNS*PORT exactly
Funding Columns All federal participating items in one column Separate column for Storm Sewer Separate column for federal non-participating (but CSAH
or MSA eligible) Separate column for Local Funds (not state aid or federal
aid eligible.
Plan FormatStatement of Estimated Quantities Include Traffic Control Item Basis for Estimated Quantities
Bituminous mix, tack coat, fertilizer, seed mix
Construction Notes Define compaction, tapers through the base
material, topsoil stripping and stockpiling
Plan FormatTabulations Consider for fence, trees, removal, storm sewer, and
earthwork Quantities on charts must match the EQ Chart
Standard Plates These standard plates as approved by the FHWA shall
apply. Use current letter designation for each plate number Provide additional construction details for items that
do not have a Mn/DOT standard plate (ie: benches, signs, etc.)
Plan FormatTypical Sections Must match the proposed roadway section in the
Proj. Dev. Report Individual lanes widths labeled
Thru Lanes, turn lanes, shoulders, parking lanes Location of the Profile Grade labeled Pavement Cross Slope, Inslope and Backslope Ratio Specification and Depth of Roadway so GE can be
verified R/W Width Recovery Area/Clear Zone Topsoil Depth and Seed and Sod Requirements
Plan FormatConstruction Plan and Profile Horizontal Curve Data Vertical Curve Data Construction Limits Existing and Proposed Right of Way Begin and End Station with SP Numbers Bar scales and North Arrow Superelevation (if applicable) Station Equations (if applicable) Label Removal and Construction Items
Plan FormatCross Sections Cross Sections cover the entire project limits Spacing adequate to compute earthwork quantities. Right of Way and Temporary Easement Lines required Include Centerline and Entrance Culverts Station to Station Limits in lower right corner
Ad for Bid/Letting Date Local Agency Sets Letting Date
Schedules Letting Date in Consultation with State Aid
State Aid provides Local Agency with required Ad Language Local agency prepares ad
Local Agency Submits Ad to State Aid for Review and Approval Upon approval, Local Agency submits ad to Constr. Bulletin
and local paper
DO NOT PLACE AD UNTIL NOTIFIED BY STATE AID
DCP Packet/Proposal Fed. Aid Project Manager prepares DCP Packet
Contains Required Federal Components Do Not add any Special Programs that Contain a
Goal or Conflict with any of the Mn/DOT Language Local Agency submits Proposal for Review
Federal Aid Project Manager reviews Document for Required Federal Language/Documents
Final Proposal Copies Submitted to State Aid 3 Copies for our File and Distribution
Project Award Local Agency notifies State Aid of low
bidder/amount Local Agency notifies low bidder to submit Request
for DBE Certification to Civil Rights (DCP 03) Local Agency sends Pre-Award Information to Civil
Rights (DCP 04) Civil Rights certifies DBE Participation and notifies
LPA
DO NOT AWARD UNTIL NOTIFIED BY CIVIL RIGHTS OFFICE.
Bikeways State Aid Rules
8’ minimum width (10’ desired) 2’ shoulder/clear zone 20 mph design speed (30 mph for >4% and 500’) 10’ vertical clearance
Bikeways Mn/DOT Bikeway Facility Design Manual
Separation between path and roadway (Fig. 5-4) Typically 4’ urban; depends on roadway posted speed Separation/clear zone different material than trail or
striping
Safety Railing on steep slopes if separation is less than 5 ft (Figure 5-16) 3:1 or greater and drop off is 6’ or more 2:1 or greater and drop off is 4’ or more 1:1 or greater and drop off is 2’ or more
Bikeways Mn/DOT Bikeway Facility Design Manual
On Road Facilities (Chapter 4) Table 4-1 and 4-2 for bikeway design
ADT and motor vehicle speed determine design selection
Dedicated Bicycle lanes Shoulders (at least 4’ in width) Wide Outside Lanes Shared Lanes
See Chapter 4 for detailed description and guidance on the selection of on-road facilities.
Signal Justification Reports SJR is required for:
New signal installation Complete reconstruction of existing signal Major geometric change at intersection
SJL (justification letter) can be used for: Revision to existing signal Addition of EVP
ICE (intersection control evaluation) is required if any leg is a Trunk Highway.
Signal Justification Reports SJR Contents
Title/Signature Page Index Map Intersection Layout (existing and proposed) Project Description Warrant Analysis and Summary Justification Statement Appendix with counts, studies, etc.
SJL Contents Letter of description and justification with signature blocks at the end Warrant Analysis
Helpful Resources State Aid Websites
www.dot.state.mn.us/metro/stateaid/home.html
www.dot.state.mn.us/stateaid State Aid Manual – Chapter 5.4 Plans & Proposals
State Aid Rules DCP Checklist Minnesota Bikeway Guidelines