February 3, 2011TAC
ERCOT Planning Go-Live Update
Jay TeixeiraManager, Model Administration
2 TACFebruary 3, 2011
For ERCOT, Planning Go-Live means using the output from NMMS Topology Processor case as the “seed” into the NMMS Model on Demand (MOD) system to build Annual Planning Cases to comply with Protocol 3.10.2. This system will be designated “TP-MOD”.
For TSPs, Planning Go-Live means using an existing SSWG case as the “seed” into MOD to build SSWG Planning cases and resolving or documenting the differences between the SSWG-MOD case and the Topology Processor processed case. This system is designated “SSWG-MOD”.
For both systems, some parts of SCR760 are desirable.
What does Go-Live mean?
3
Protocol Required Annual Planning Model vs SSWG Cases
TACFebruary 3, 2011
•Created by SSWG and ERCOT
•Approved by SSWG
•TSPs allowed to model facilities
as they please
•78% Consistent with TP output
Annual Planning Models
5 Summer Peak Cases
SSWG Cases
Data Set A1 Summer Peak Case
7 Others
Data Set B5 Summer Peak Cases
1 Other
•Created and Approved by ERCOT
•TAC Approved Rules of Consistency
Apply
•100% Consistent with TP output
•No topology changes allowed from TP
output case without corresponding
NOMCR submittal
4
5 SSWG Cases were going to be Annual Planning Models (Option 1)
TACFebruary 3, 2011
Annual Planning Models
5 Summer Peak Cases
SSWG Cases
Data Set A1 Summer Peak Case
7 Others
Data Set B5 Summer Peak Cases
1 Other
•ERCOT and SSWG were going to build the current set of SSWG cases and use
the 5 Summer Peak Cases as the 5 Annual Planning Model cases except:
•Rules of Consistency Apply
•Had to start with TP output
•Changes not allowed that altered the branch consistency between models
•All SSWG cases were to be built using TP-MOD
5
ERCOT will take lead in building Annual Planning Models as specified in Protocol 3.10.2
TACFebruary 3, 2011
TP-MOD Environment
•Identified as Option 1 in ROS
January 13th meeting
•ERCOT will build parallel to
SSWG process with assistance
from TSPs as required by Op
Guide 5.5
•ERCOT will assume responsibility
to meet timelines
Annual Planning Models
5 Summer Peak CasesStarting with next year summer peak case to be completed by
Oct 15th per Protocol 3.10.2
•Created and Approved by ERCOT
•TAC Approved Rules of Consistency
Apply
•100% Consistent with TP output
•No topology changes allowed from TP
output case without corresponding
NOMCR submittal
6
ERCOT will add second MOD environment so that SSWG can build their cases
TACFebruary 3, 2011
SSWG Cases
Data Set A1 Summer Peak Case
7 Others
Data Set B5 Summer Peak Cases
1 Other
SSWG-MOD Environment
•Identified as Option 2 in ROS
January 13th meeting
•SSWG will build cases in
accordance with SSWG
procedures with assistance from
ERCOT
•SSWG will assume more direct
responsibility to meet timelines
and build cases
•ERCOT will supply dispatch
•Created by SSWG and ERCOT
•Approved by SSWG
•TSPs allowed to model facilities as
they please
•Move towards increasing consistency
with Option 2 comparison with TP as
mandated by ROS
7
Block Diagram of ERCOT Proposal
TACFebruary 3, 2011
SSWG-MOD
MOD
Smaller Set of
StandardPMCRs
Topology Processor
Case
MOD
TSP Profiles
TSP FuturePMCRs
Existing SSWG Case
TP-MOD
Case Completion
Case Completion
Includes comparison to
TP
TSP ContingenciesNERC B,C,D
Credible Single
ContingencyAnalysis
ContingencyAnalysis
ERCOT TranslateW TSP Help
ERCOT TranslateW TSP Help
Common Elements
Contingency Analysis Comparison
Cases Complete
Cases Complete
Annual Planning Case creation (TP-MOD process) would only be done with the one summer peak
case from Data Set A and all 5 summer peak cases from Data Set B
ERCOT Profiles
SSWG-MOD process completed for all Data Set A and Data Set B cases
8
SSWG Presented with Proposal
TACFebruary 3, 2011
At the regularly scheduled SSWG Conference Call on Jan 26, 2011 – ERCOT presented the dual MOD environment to SSWG for the first time. SSWG raised some concerns and requested more time to review.
Among the concerns raised:
•Having 2 sets of planning cases could open ERCOT and TSPs to demonstrate NERC compliance with both sets of cases.
• There are no NERC requirements for the Planning Authority and Transmission Planner to use the same cases to demonstrate compliance.
• Whichever cases the Transmission Planner uses to plan its system, those are the cases they will use for NERC.
•Wanted clarification on ERCOT and TSP responsibilities for both systems.•Some TSPs still want to eventually go to the TP-MOD system and have only one set of planning cases.•Other TSPs needed more time to look at the proposal.
9
ERCOT Responsibilities
TACFebruary 3, 2011
•Maintain two MOD environments – TP-MOD and SSWG-MOD•Load base cases into both environments•Submit ERCOT Generation dispatch to both environments•Copy TSP submitted Load and Device Control profiles from SSWG-MOD environment into TP-MOD environment and translate as necessary
•Copy TSP submitted Planning Model Change Requests (PMCRs) from SSWG-MOD environment into TP-MOD environment and translate as necessary
•Use SSWG Pass 0 comparison introduced at ROS Jan 13, 2011 meeting to translate profiles, PMCRs, and contingencies if necessary from TSP submission to SSWG-MOD environment to TP-MOD
•Maintain timeline for case completion in TP-MOD•Compare SSWG-MOD and TP-MOD contingency results and resolve
10
TSP Responsibilities
TACFebruary 3, 2011
•Submit Load and Device Control profiles into SSWG-MOD environment
•Submit future Planning Model Change Requests into SSWG-MOD environment
•Complete Pass 0 comparison with Topology Processor case as introduced at ROS Jan 13, 2011 meeting
•Maintain timeline for TSP data submission and case completion in SSWG-MOD
•Submit contingency list for SSWG-MOD environment•Compare SSWG-MOD and TP-MOD contingency results and resolve
Questions
February 3, 2011 TAC