CGC019795, BN5805, SREF & GSM Veteran Owned Small Business (Construction Consulting Services) 102 W. Targa Ct. Tampa, FL 33606 305-797-8676 Off / Cell [email protected] / [email protected] Website: www.bwspragueconsulting.com February 2021 Report Thornton Construction Company, Inc. continues to make good progress on the construction of the Upper Keys Center. Since the last report, the following tasks have been completed: The placement of hollow-core concrete plank sections for the 2 nd floor Beams for support of roof slab planks have been formed and poured The placement of hollow-core concrete plank sections for the roof has begun Placement of grout onto hollow-core plank sections of 2 nd Floor Electrical contractor has begun rough-in of conduit for 1 st floor Interior concrete block walls completed on 2nd Floor CMU tie beams and overhead beams have been poured Testing of Grout for CMU Walls and Concrete Beams / each 50 yds Crane inspected by Thornton Construction Safety Officer Poured interior beams at entry of 2 nd Floor Thornton Construction collecting needed documents from sub-contractors required for EDA approval Thornton Construction posted Submittals and RFIs on Procore Placed Cameras 1, 2 & 3 Onsite K2M Design Review and Approval of Submittals and RFI’s

Transcript of February 2021 Report

Page 1: February 2021 Report

CGC019795, BN5805, SREF & GSM

Veteran Owned Small Business (Construction Consulting Services) 102 W. Targa Ct. Tampa, FL 33606

305-797-8676 Off / Cell [email protected] / [email protected]

Website: www.bwspragueconsulting.com

February 2021 Report

Thornton Construction Company, Inc. continues to make good progress on the construction of the Upper Keys Center. Since the last report, the following tasks have been completed:

• The placement of hollow-core concrete plank sections for the 2nd floor

• Beams for support of roof slab planks have been formed and poured

• The placement of hollow-core concrete plank sections for the roof has begun • Placement of grout onto hollow-core plank sections of 2nd Floor • Electrical contractor has begun rough-in of conduit for 1st floor

• Interior concrete block walls completed on 2nd Floor

• CMU tie beams and overhead beams have been poured

• Testing of Grout for CMU Walls and Concrete Beams / each 50 yds

• Crane inspected by Thornton Construction Safety Officer

• Poured interior beams at entry of 2nd Floor

• Thornton Construction collecting needed documents from sub-contractors required for EDA

approval

• Thornton Construction posted Submittals and RFIs on Procore

• Placed Cameras 1, 2 & 3 Onsite

• K2M Design Review and Approval of Submittals and RFI’s

Page 2: February 2021 Report

• K2M Design Weekly Calls, Weekly Construction Reports, and Onsite Team Meetings

• Wall layout and slab preparation on the first floor completed

• SREF inspections, threshold inspections, and testing are ongoing

Page 3: February 2021 Report

The College of the Florida Keys

February 2021

________________________________

_ NEW UPPER KEYS CENTER Owners Progress Report

February 2021

Page 4: February 2021 Report

EXECUTIVE SUMMARY

In the month of January 2021, the project hit a major milestone. With the foundation and the Slab-on-Grade poured, the Tilt Wall Panels erected, the team focused on preparation to receive the hollow-core planks. The second floor planks were flown, set in place and secured followed later by the roof planks. Interior space layout and planning activities have begun with overhead ceiling MEP coordination and placement.

As the building begins to go up, the shape, and size of the structure becomes apparent and a welcome sight to the town of Key Largo.

Thornton is currently performing the following activities:

Hollow-core plank placement Electrical ceiling layout and hangar rod installation Mechanical ceiling layout and hangar rod installation Plumbing ceiling layout and hangar rod installation Tilt Wall Panels (Bracing & Rubbing) Exterior Electrical service pole removal Exterior Electrical transformer and underground pipe layout CMU Wall 2st Floor CMU wall wet beam form and pour Welding Panel and plank connections Drainage installation

Hollow-core plank subcontractor Structural work.

Project submittals and RFI’s are being processed and forwarded to the Architect for approvals.

Thornton is working closely with the College (Bill Sprague & Lucia Cuculino) on the Direct Owner Purchase Program to ensure appropriate materials, are being purchased to execute the work and meet our project goals & project target completion dates.

As of the end of January 2021 the project is approximately 28% completed.