Feasibility Study FOREST GLEN PASSAGEWAY April 10, 2012 1 Isiah Leggett Montgomery County Executive Arthur Holmes, Jr. Director Department of Transportation Division of Transportation Engineering 100 Edison Park Drive 4th Floor Gaithersburg, MD 20878 Phone: 240-777-7223 Fax: 240-777-7277 Bruce Johnston, P.E. Division Chief Holger Serrano, P.E. Engineering Services Specialist Sogand Seirafi, P.E. Planning & Design Chief Tom Reise Property Acquisition Chief «« PUBLIC MEETING »» N Tuesday, April 10, 2012 7:00PM – 9:00PM Sligo Middle School 1401 Dennis Avenue Silver Spring, MD 20902 Dennis Ave Dennis Ave PROJECT SITE G e o r g i a Av e G e o r gi a Av e Capital Capital Beltway Beltway Forest Forest Glen Glen Rd Rd Sligo Middle School M metro

Transcript of Feasibility Study FOREST GLEN PASSAGEWAY April 10, 2012 1 Isiah Leggett Montgomery County Executive...

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

1

Isiah LeggettMontgomery County Executive

Arthur Holmes, Jr. Director

Department of Transportation

Division ofTransportation Engineering

100 Edison Park Drive4th Floor

Gaithersburg, MD 20878Phone: 240-777-7223

Fax: 240-777-7277 

Bruce Johnston, P.E.Division Chief

Holger Serrano, P.E.Engineering Services

Specialist

Sogand Seirafi, P.E.Planning & Design Chief

Tom Reise Property Acquisition Chief

Girum Awoke, Ph.D., P.E.Construction Chief

«« PUBLIC MEETING »»

N

Tuesday, April 10, 2012

7:00PM – 9:00PM

Sligo Middle School1401 Dennis Avenue

Silver Spring, MD 20902

Dennis AveDennis Ave

PROJECT SITE

Georg

ia A

ve

Georg

ia A

ve

CapitalCapital BeltwayBeltway

ForestForest GlenGlen RdRd

SligoMiddle School

Mmetro

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

2

«« PURPOSE OF PUBLIC MEETING »»

• Introduce project team

• Outline project purpose and need

• Share background data

• Present alternatives and draft concepts

• Explain project procedure and schedule

• Listen to community’s concerns and gather feedback

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

«« PURPOSE OF PROJECT »»

• To provide a grade separated pedestrian passageway across Georgia Avenue at Forest Glen Road for improved safety

• To provide direct access to Forest Glen Metro Station and improved ADA accessibility to the mezzanine of the Metro Station

3

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

4

«« NEED FOR PROJECT »»

• There is a need for improved pedestrian safety at the intersection and improved access to the Metro Station Highly congested intersection Frequent conflicts between pedestrians and

vehicles 90% of pedestrians crossing Georgia Ave are

to/from the Metro Station No existing direct ADA access to the mezzanine

of the Metro Station

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

5

«« EXISTING SITE CONDITIONS »»

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

6

«« EXISTING VEHICULAR TRAFFIC CONDITION »»

xxx (xxx) = AM (PM) Peak Hour Volume

• Highly congested intersection 80,000 vehicles/day

• Long signal cycle – 150 seconds

• Potential pedestrian delay ≈ 140 seconds

• Long delay encourages jaywalking

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

7

«« EXISTING PEDESTRIAN OPERATIONS »»

• Counts performed Tuesday, April 26, 2011

• Significant crossings of all 4 legs of the intersection

• > 800 crossings of Georgia Avenue

• 90% of pedestrian activity is to/from Metro

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

«« ALIGNMENT OPTIONS »»

8

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

9

• 90% of pedestrian traffic is related to Metro

• Preferred Alternatives should provide direct access to Metro

«« PRELIMINARY EVALUATION »»

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

10

«« TUNNEL ALTERNATIVE 1 »»SOUTHEAST QUADRANT TO METRO STATION

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

11

«« TUNNEL ALTERNATIVES »»

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

12

«« TUNNEL ALTERNATIVE 2 »»NORTHEAST QUADRANT TO METRO STATION

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

13

«« BRIDGE ALTERNATIVE 1 »»SOUTHEAST QUADRANT TO METRO STATION

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

14

«« BRIDGE ALTERNATIVE 1 »»SOUTHEAST QUADRANT TO METRO STATION

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

15

Recommendation: (Note: A recommendation for a preferred alternative will be made after consultation with the project team, solicitation of public comment, and review by county officials.)

«« ALTERNATIVE COMPARISON »»

Tunnel Alternative 1(SE Quadrant to Metro)

Tunnel Alternative 2(NE Quadrant to Metro)

Bridge Alternative 1(SE Quadrant to Metro)

Length (Ft) 303 324 270

Width (Ft) 23 (18 Ft Clear) 23 (18 Ft Clear) 12 (10 Ft Clear)Estimated Pedestrian Usage (Crossing MD 97/ Day)

759 461 683

Average Travel Time Savings (Sec/Pedestrian)

119 103 57

Construction Duration 39 months 39 months 15 months

Maintenance of Traffic

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (3 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave.

Single overnight complete closure of Georgia Ave

Properties Impacted 1 Property, 2200 Square Feet 1 Property, 4100 Square Feet 1 Property, 1500 Square Feet

Utility Impacts High - Underground, overhead,

and traffic signal High - Underground, overhead,

and traffic signal Moderate - Overhead and traffic

signalConstruction Cost $11.5M $12.1M $5.8M

Tunnel Alternative 1(SE Quadrant to Metro)

Tunnel Alternative 2(NE Quadrant to Metro)

Bridge Alternative 1(SE Quadrant to Metro)

Length (Ft) 303 324 270

Width (Ft) 23 (18 Ft Clear) 23 (18 Ft Clear) 12 (10 Ft Clear)Estimated Pedestrian Usage (Crossing MD 97/ Day)

759 461 683

Average Travel Time Savings (Sec/Pedestrian)

119 103 57

Construction Duration 39 months 39 months 15 months

Maintenance of Traffic

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (3 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave.

Single overnight complete closure of Georgia Ave

Properties Impacted 1 Property, 2200 Square Feet 1 Property, 4100 Square Feet 1 Property, 1500 Square Feet

Utility Impacts High - Underground, overhead,

and traffic signal High - Underground, overhead,

and traffic signal Moderate - Overhead and traffic

signalConstruction Cost $11.5M $12.1M $5.8M

Tunnel Alternative 1(SE Quadrant to Metro)

Tunnel Alternative 2(NE Quadrant to Metro)

Bridge Alternative 1(SE Quadrant to Metro)

Length (Ft) 303 324 270

Width (Ft) 23 (18 Ft Clear) 23 (18 Ft Clear) 12 (10 Ft Clear)Estimated Pedestrian Usage (Crossing MD 97/ Day)

759 461 683

Average Travel Time Savings (Sec/Pedestrian)

119 103 57

Construction Duration 39 months 39 months 15 months

Maintenance of Traffic

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (3 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave.

Single overnight complete closure of Georgia Ave

Properties Impacted 1 Property, 2200 Square Feet 1 Property, 4100 Square Feet 1 Property, 1500 Square Feet

Utility Impacts High - Underground, overhead,

and traffic signal High - Underground, overhead,

and traffic signal Moderate - Overhead and traffic

signalConstruction Cost $11.5M $12.1M $5.8M

Tunnel Alternative 1(SE Quadrant to Metro)

Tunnel Alternative 2(NE Quadrant to Metro)

Bridge Alternative 1(SE Quadrant to Metro)

Length (Ft) 303 324 270

Width (Ft) 23 (18 Ft Clear) 23 (18 Ft Clear) 12 (10 Ft Clear)Estimated Pedestrian Usage (Crossing MD 97/ Day)

759 461 683

Average Travel Time Savings (Sec/Pedestrian)

119 103 57

Construction Duration 39 months 39 months 15 months

Maintenance of Traffic

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (3 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave.

Single overnight complete closure of Georgia Ave

Properties Impacted 1 Property, 2200 Square Feet 1 Property, 4100 Square Feet 1 Property, 1500 Square Feet

Utility Impacts High - Underground, overhead,

and traffic signal High - Underground, overhead,

and traffic signal Moderate - Overhead and traffic

signalConstruction Cost $11.5M $12.1M $5.8M

Tunnel Alternative 1(SE Quadrant to Metro)

Tunnel Alternative 2(NE Quadrant to Metro)

Bridge Alternative 1(SE Quadrant to Metro)

Length (Ft) 303 324 270

Width (Ft) 23 (18 Ft Clear) 23 (18 Ft Clear) 12 (10 Ft Clear)Estimated Pedestrian Usage (Crossing MD 97/ Day)

759 461 683

Average Travel Time Savings (Sec/Pedestrian)

119 103 57

Construction Duration 39 months 39 months 15 months

Maintenance of Traffic

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (18 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave and Forest Glen Rd

Partial Night Time Work (3 months)

Overnight Lane Closures to 2-3 Lanes on Georgia Ave.

Single overnight complete closure of Georgia Ave

Properties Impacted 1 Property, 2200 Square Feet 1 Property, 4100 Square Feet 1 Property, 1500 Square Feet

Utility Impacts High - Underground, overhead,

and traffic signal High - Underground, overhead,

and traffic signal Moderate - Overhead and traffic

signalConstruction Cost $11.5M $12.1M $5.8M

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

• Collect data; develop alternatives and draft concepts; and evaluate impacts and constructability

• Obtain public input

• Select recommended Preferred Alternative and refine concept.

• Obtain approval from the Director of DOT & County elected officials on Preferred Alternative and concept

I. FEASIBILITY STUDY(Funded)

Complete in Summer 2012

16

«« PROJECT PROCEDURE & SCHEDULE »»

Obtain Federal Funds

1 ½ Years

II. FINAL DESIGN(Funded)

3 ¼ Years (Tunnel)1 ¼ Years (Bridge)

III. CONSTRUCTION(Not Funded)

WE ARE HERE

Feasibility StudyFOREST GLEN PASSAGEWAY

April 10, 2012

17

«« OBtain Public INPUT »»

Project Manager: Greg Hwang

Mailing Address: Department of Transportation

Division of Transportation Engineering

100 Edison Park Drive, 4th Floor

Gaithersburg, Maryland 20878

E-mail: [email protected]

Phone: 240-777-7279 Fax: 240-777-7277

Division of Transportation Engineering Home Page:http://www2.montgomerycountymd.gov/DOT-DTE/Common/home.aspx

• Public Meeting on April 10, 2012

• Comment Period thru April 24, 2012 By postage paid comment card By mail or e-mail to Project Manager