FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical...

28
FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013

Transcript of FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical...

Page 1: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

FCP-Modify – High level Process & Illustrative Examples Gary WilliamsonOpenreach LLU Technical Development ManagerVersion 1 – 15th April 2013

Page 2: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Introduction

FCP-Modify is about getting more from existing LLU infrastructure through rejuvenation and in-life upgrade: May be considered for any existing ‘pre-FCP’ PoP type. Firm order acceptance is always subject to survey. For some PoPs,

physical expansion may not be possible due to the presence of surrounding equipment belonging to other customers or BT. Openreach will offer what is possible for customer consideration.

Can help improve service continuity through greater power resilience. Offers more for the customer – eg ‘Customer Use Cabinet’ (CuC). Lowers DC energy costs due to >95% power efficiency (cf 89%-92%) Can help customers to prepare for consolidation of their LLU estates.

Page 3: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Key Points

1. It is important that:

1. Prior to APO placement there is a customer / Openreach dialogue to agree and document the customer requirements to be met.

2. Following receipt of an APO in which multiple similar PoPs are to be upgraded, the work is undertaken as a programme. This will help to ensure consistency of delivery for the customer.

3. Customers have a person who is the primary point of contact for FCP-Modify orders over the end-to-end delivery process.

2. A ‘rack face’ map will be created for added cabinets and added rack spaces. This will help the required positions of ethernet fibre and equipment to be thought through and defined by the customer.

3. In some cases the APO survey will find that there is insufficient suitable space and/or ac mains power capacity to satisfy the customer’s requirement. Openreach will seek to offer an alternative based on what appears feasible.

Page 4: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Definitions – Categorisation for APO

FCP-New Build is the provision of a new PoP in response to a customer order.

FCP-Modify is the means to upgrade an existing ‘pre-FCP’ LLU PoP such that is subsequently treated as an FCP installation for billing and future upgrade path purposes. Will always include provision of at least one new FCP DC Power System. Will always replace any existing Openreach maintained DC system(s). Is not offered in ‘AC Only’ form. May include additional rack space units (RSUs), Customer Use Cabinets and HDF racks. Is always subject to survey for space and ac power supply capacity reasons. Is always the subject of customer requirements document produced by the Openreach LLU Technical

Development Team for customer approval and having an solution code.

FCP-Refresh applies to an existing FCP installation for the incremental increase or decrease of power capacity and/or the provision of additional features within the original physical footprint / expected future maximum power envelope (eg Add an HDF / HDF sub-racks, supply and install a Customer Use Cabinet). Does not entail re-engineering of the PoP.

FCP-Augment will entail re-engineering of an in-life FCP PoP to increase its spatial and/or maximum power capacity envelope beyond the original expected future maximum.

LLU-Regrade applies to any Non-FCP LLU PoP and encompasses changes of a minor engineering nature within the existing design limits of the relevant product type.

Page 5: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Customer Requirements Definition

Microsoft Word Document

The embedded document is the blank template to be completed for each new customer requirement that arises. One document may apply to many or few LLU PoPs of a given type.

Dialogue with the customer may entail a degree of iteration as actual requirements are confirmed and the associated indicative pricing is understood.

Once agreed, a PDF version of the Customer Requirements Definition paper will be stored and made available for use by the Openreach Plan & Build and EIPB teams. Each approved requirement will result in a “Solution Code”.

The customer will then be able to place APOs quoting the solution code on one or many occasions.

Page 6: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

FCP-Modify Pre-build process

Customer & Openreach SRM / LLU tech team discuss and agree the

customer’s requirements.

Bill applicable charges & Finish

Customer places APO quoting the relevant

Solution Code

LLU Technical Development Team produces LTDP document (PDF) defining the customer

requirement and indicative pricing.Document is given an solution code and published internally once agreed with the

customer, EIPB and the APO Team.

APO survey work is undertaken and the

results with floorplans are returned to the

Openreach P&B team.

Openreach / EIPB APO survey(s) scheduled.

Openreach P&B team prepares an ‘Art of the

possible’ survey response for technical sign-off. An Openreach

response is then returned to the customer

for consideration

Solution recorded and

published internally.

Yes Customer confirms

firm order?

No

Proceed to order delivery planning.

Dimensioning detail provided for LLUMS ‘wizard’

Solution Code at ‘Agreed for APO’ status is notified

to customer to enable APO placement

Use relevant solutiondocument

Equipment layout issued

Page 7: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

FCP-Modify – Delivery Planning

Order is complete.

Finish.

New equipment installation date(s)

confirmed

On-site installation work is undertaken up to the point of changeover from old to

new.

MUA RFI date(s) confirmed

Delivery Manager liaises with customer to agree

installation and changeover date(s).

Confirms work activities involved and roles.

Changeover activity is undertaken to

transfer customer power loads onto the

new FCP power system(s). Customer confirms service is

OK

Recovery of redundant

equipment is undertaken in

accordance with agreed scope of

works.

Job completion QA and handover

documentation into Openreach P&B. PIRM updated.

Billing activity undertaken inventory

and verified

Handover Pack issued to customer. Customer Handover – virtual or attended.

Start Delivery planning

for firm build order(s)

On-site delivery – a virtual single visit engineering undertaking

Page 8: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Annex 1 provides examples of possible FCP-Modify

requirements – this is not exhaustive

Page 9: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Versatility – FCP-Modify Parameters

FCP-Modify may be used to achieve the following - subject to survey

1.Power capacity up to 10kW (single Power Base cabinet).

2.Power capacity 10.1kW to 20kW (two Power Base cabinets)

3.Dual power system working for resilience – two Power Base up to 10kW.

4.Dual power system working for resilience – four Power Base 10.1kW to 20kW

5.Additional rack space units – up to ten additional RSUs

6.Choice of added RSU sizes – choose from 600x600, 600x800 or 800x800mm.

7.Customer Use Cabinets (CuCs) on unused existing RSUs or new RSUs.

8.Additional HDF capacity to augment existing B-Buss HDF capacity.

9.Expanded Battery Capacity Cabinet (EBC-C option) where Non-ESS mains supply due to insufficient standby generator capacity – or where greater battery reserve is required.

10.Range of bespoke services covering changeover of customer equipment power connections from old to new power system, recovery and disposal of replaced, customer owned, power systems to free up space within customer cabinets / RSUs.

11.Retrofit upgrade of PoP lighting to FCP LED system (if required).

Page 10: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 1 - B-Buss7: “I want 11kW total power now, up to 15kW in the future, three more 600x600 RSUs, one with a CuC, another HDF rack and sub-racks for up to 54 more tie cables”

Rear

Front

RSU1600x600

RSU2600x600

Rear

Front

RSU3600x600

RSU4600x600

RSU5600x600

RSU7600x600

RSU6600x600

FCP-Modify – Indicative Solution Design

HDF1 HDF2

Rear

Front

RSU1600x600

RSU2600x600

Rear

Front

RSU3600x600

RSU4600x600

RSU5600x600

RSU7600x600

RSU6600x600

The existing B-Buss7 PoP (8kW DC)

DC MIDI600x600

HDF1 HDF2

RSU8600x600

RSU10600x600

RSU9600x600

Rear

Front

HDF3Power Base 2 of 2

Power Base 1 of 2

Rear

Front

CuC 1 of 1

The APO survey is undertaken and results in an FCP-Modify solution design as below

Old MIDI removed following

changeover

Rear

Front

Front

Page 11: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 2 - B-Buss7: “I want to fit 800mm deep cabinets in my B-Buss7 footprint. I don’t currently need more power capacity overall but do need versatility in terms of being able to house ethernet, routers and possibly more tie cables.

Rear

Front

RSU1600x600

RSU2600x600

Rear

Front

RSU3600x600

RSU4600x600

RSU5600x600

RSU7600x600

RSU6600x600

The existing B-Buss7 PoP (8kW DC)

DC MIDI600x600

HDF1HDF2 space

The APO survey is undertaken and results in an FCP-Modify solution design as below

800mm

Rear

Front

RSU1600x800

RSU2600x800

RSU3600x800

HDF1 RSU4600x800

RSU5600x800

Power Base 1 of 1

(800 x 800)

CuC1 of 1

(800 x 800)

Page 12: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 3 B-Buss3: “I have an AC only B-Buss3 and want 3.6kW DC now, up to 6kW in the future”.

FCP-Modify – Indicative Solution Design

FCP Power Base Cabinet 1 of 1 is installed and commissioned.

Transfer of live existing dc wiring from the customer’s old DC system will be a service option (price for out of hours cut-over option to be advised.

Recovery and disposal of the old DC system will be a service option (price tba)

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

HDF1

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

The existing B-Buss3 PoP ((AC only). All customer RSUs have customer cabinets in place.

One houses the customer’s old DC system.

HDF1

Power Base 1 of 1

Rear

Front

The APO survey is undertaken and results in an FCP-Modify solution design as below

Shows RSU1 cleared – old DC cabinet removed

Page 13: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 4 B-Buss3: “I want to grow my B-Buss3 to have two more RSUs and a dual power system with 6kW capacity now and up to 10kW in the future”.

FCP Power Base Cabinets 1 & 2 replace the existing DC midi system.

FCP Power Base Cabinet 2 of 2 provides redundant mirrored capacity needed for resilience.

Where possible, pre-provision of new Power Base cabinets will be made to simplify changeover from the old MIDI.

The existing B-Buss3 PoP (4kW )

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

DC MIDI600x600

HDF1

The APO survey is undertaken and results in an FCP-Modify solution design as below

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

FCP-Modify – Indicative Solution Design

HDF1RSU4

600x600RSU5

600x600

Power Base 1 of 2

Rear

Front

Power Base 2 of 2

New RSUs

Old MIDI removed following

changeover

Page 14: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 5 B-Buss3: “I want to grow my B-Buss3 to have two more RSUs (600Wx800D) with 6kW capacity now and up to 10.1kW in the future. I’ll need more HDF capacity for up to 20 tie cables”.

The APO survey is undertaken and results in an FCP-Modify solution design as below

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600HDF1

Power Base 1 of 2

(800 x 800)

Power Base 2 of 2

(600 x 800)Rear

New RSU

Front

Front

Rear

RSU4600x800

RSU5600x600

New RSU

Other equipment

Other equipment

Page 15: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 6 B-Buss3: “My Non-ESS fed B-Buss3 has become critical in my network. It needs another RSU and a dual power system with 7kW capacity and the EBC option for maximised battery autonomy”.

FCP Power Base Cabinet 1 of 2 + EBC-C 1 of 2 replaces the existing DC midi system.

FCP Power Base Cabinet 2 of 2 + EBC-C 2 of 2 provides the mirrored capacity needed for resilience.

Note that Power Base 1 could be commissioned before removal of the old MIDI. EBC-C1 could be added post-removal of the MIDI for ease of changeover.

The EBC cabinets each provide ~24VU 19” space for customer use.

The existing B-Buss3 PoP (4kW )

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

DC MIDI600x600

HDF1

The APO survey is undertaken and results in an FCP-Modify solution design as below

Rear

Front

RSU1600x600

RSU2600x600

RSU3600x600

RSU4600x600

FCP-Modify – Indicative Solution Design

HDF1

Rear

Front

Power Base 2 of 2

New RSU

EBC-C1 of 2

EBC-C 2 of 2

Power Base 1 of 2

Page 16: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 7 – Migrate an MCU2 into FCP“I want 4kW power capacity now, up to 6kW in the future and another RSU with a CuC of 600mm width x 800mm depth. I also need HDF for 21 more LLUT tie cables”.

Rear

Front

RSU1600x600

RSU2600x600

Existing MCU2 PoP

The APO survey is undertaken and results in an FCP-Modify solution design as below

Rear

Front

RSU1600x600

RSU2600x600

As FCP-Modify

900mm x

600mm

CuC1 of 1

600x800

Front

Rear

Power Base 1 of 1

800x800

RSU3FCP Power Base Cabinet 1 of 1 replaces the existing APS3 DC system.

FCP Power Base Cabinet is 800x800mm to house the added HDF capacity needed.

There will be an out of hours service option for changeover of live DC wiring from the old APS3 system and its removal.

Page 17: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 8 – MCU2 to ‘MCU2-Max Aux’“I want something like the ‘MCU2-Max-Aux’ upgrade with a 3rd RSU, 3.9kW of power now and up to 6kW in the future. I want an 800mm wide Power Base”.

Rear

Front

RSU1600x600

RSU2600x600

Power Base1 of 1

800x600

RSU3600x600

The existing MCU2

Space availability drives a cross-suite FCP-Modify

solution

Other existing equipment

Other existing equipment

Other existing

equipment

Page 18: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 9 – MCU2 to FCP“I have a land-locked MCU2 and now need 4.1kW of power to make full use of it”.

Rear

Front

RSU1600x600

RSU2600x600

The existing MCU2

Other existing equipment

Other existing equipment

Other existing

equipment

Other existing equipment

FCPTransplant

‘Open Heart Surgery’ Power System Transplant using FCP Power Core – undertaken as out of hours changeout*

Page 19: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 10 (1 of 2) – MCU2-Max Aux“I’ve outgrown my MCU2-Max-Aux and now need to add one RSU of 600x800mm and I need 8kW power capacity”.

Rear

Front

RSU1600x600

RSU2600x600

MCU-Max Aux

RSU3600x600

The original MCU2 from 2006

The MCU-Aux -Max upgrade from 2009

Ceased LLU PoP still in-situ

Other existing equipment

Other existing

equipment

Page 20: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 10 (2 of 2) – MCU2-Max Aux

Note: The power is now all supplied from the new FCP Power Base. The redundant Eaton RM6 DC system is recovered from the Aux cabinet, the space freed within being used by the customer.

Rear

Front

RSU1600x600

RSU2600x600

MCU-Max Aux

RSU3600x600

The original MCU2 from 2006

The MCU-Aux-Max upgrade from 2009

Other existing equipment

Other existing

equipment

Front

Rear

Power Base 1 of 1RSU4

The FCP-Modify upgrade in 2013/14

Space vacated by recovery of ceased LLU PoP

MCU HDF

Page 21: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 11 – LCU (also for BSR & CSR)“I’ve outgrown my LCU and now need to double my equipment mounting capacity and add 7 tie cables but can’t afford to set up and kit out a new PoP. I need 2kW now and I want DC and the inverter option”.

LCU

Other existing equipmentOther

existing equipment

Power Base 1 of 1

800 x 600 c/w 3 HDF sub-racks

Note: The power is now all supplied from the new FCP Power Base. The redundant AC / DC system is recovered from the LCU. If ties re-provided, the old LCU enclosure may be removed to enable the

customer to expand their existing RSU upwards on the LCU space.

Front

Rear

Other existing equipment

Page 22: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

RSU1600x600

RSU2600x600

Power Base1 of 1

800x600

The existing ASS600-C3

Example 12 – ASS600-C3“I just want the FCP Power Base with 3kW so I can rejuvenate and maximise usage of this PoP”. I need more HDF too.

Below: After the upgrade.

Other existing equipment

Other existing

equipment

RSU3600x600HDF

AC board

RSU1600x600

RSU2600x600

Other existing equipment

Other existing

equipment

RSU3600x600HDF

The PoP following upgrade via FCP-Modify

All power now via Power Base. Old ac removed.

Capacity for up to 30 additional ties in PowerBase.

Customer is able to clear and re-use RSU3 due to recovery of their old DC system.

Page 23: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 13 Bespoke Co-location Rooms

Start point would be a review of room usage and electrical supply design check.FCP-Modify would provide Power-Base hardware and, as required, RSU / HDF and CuC facilities. Note – different commercial terms apply for bespoke rooms.

BT AC mains supply to room.Typically via ESS.

Originally designed for customer specified max power load.FCP-Modify design would review ac capacity to room to ensure correctly rated supply.May need to include some ventilation / cooling based on heat density.

Customer LLU equipment – incl DC power and UPS

Page 24: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Example 14 Hostel Bays (Type A and B)“I want to exploit my Hostel Bay and add capacity. I need 8kW now and up to 10kW in the future. I want two more 600W x 800D RSUs each with a CuC to hold my new equipment. I also need an HDF for up to 54 new ties”.

CP ‘Z’ – no change

As a result, the Openreach survey and design offers a solution that looks like this.

Bay 1 Type A 8kW / 3.6metres

Bay 2 Type B 4kW / 1.8 metres

CP ‘X’ – FCP-Modify upgrade

AC Supply to Hostel room continues to be used

FCP HDF

Page 25: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

Annex 2

‘FCP-Refresh’ high level APO process ‘FCP-Augment’‘LLU Regrade’

Further work is to be undertaken on these.

Page 26: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

FCP-Refresh – Power capacity increaseStart

FCP PoP

Customer pro-actively requests increase in ac power supply capacity from initial maximum

power to a higher value not exceeding the

‘expected future maximum power’ stated at original

build order.

Finish

Customer places APO quoting LLUC(s) and the

required new ‘usable maximum power’ value

required (xx.xkW).

Where FCP DC system is present alarm settings are changed to reflect

the applicable new maximum load current

(from dimensioning tool).

EIPB / FE D/L assumed until PIMMS remote

config eliminates need for site visit.

Openreach / EIPB APO Power capacity survey(s)

undertaken

LLUMS & Billing System

Yes

Enough ac power capacity

for an increase? No

Inventory records updated & billing

triggered.

Customer is advised of order completion via an itemised statement of

new charges arising from the APO.

Customer informed of power capacity situation and indicative timescale before an increase may

become possible.

Page 27: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

FCP-Augment (applies to in-life FCP PoP that originated as a new build or via FCP-Modify).

• Process would be similar to FCP-Modify and begin with a customer requirements definition exercise to ensure that the need / indicative pricing is documented and agreed.

• APO placed as the customer’s authority to proceed.

• APO survey would be undertaken for each PoP in scope.

• Response to customer based on ‘art of the possible’.

• Customer firm order decision.

• Delivery planning, date setting, installation, QA.

• Handover to customer.

• Billing & inventory.

Page 28: FCP-Modify – High level Process & Illustrative Examples Gary Williamson Openreach LLU Technical Development Manager Version 1 – 15 th April 2013.

LLU-Regrades (‘Minor-works’)

In scope:-MCU-Max & Aux: 4.95kW to 6.6kW (rectifier infill)-B-Buss3: 4.4kW to 6.6kW (rectifier / battery infill)-Additional DC sub-distribution connected to existing DC system-Additional AC sub-distribution connected into existing AC system.-MCU1 to MCU2 (+1 rectifier & +5 HDF sub-racks + RSU#2 if space).-B-Buss7 Supplementary HDF rack-B-Buss7 to B-Buss3 downgrade-Inverter tower -Non-ESS to ESS transfer-Retrofit sub-meter.-HDF sub-rack provision into available space in or adjacent to the PoP.

Note: The above is not and exhaustive listing – further low-capex re-grade solutions of a minor engineering nature may be added.