FCE546 Transp Eng IIIB - March 2012 v0

131
FCE 546 - TRANSPORTATION ENGINEERING IIIB (45 HRS) PAVEMENT DESIGN

Transcript of FCE546 Transp Eng IIIB - March 2012 v0

Page 1: FCE546 Transp Eng IIIB - March 2012 v0

FCE 546 - TRANSPORTATION ENGINEERING IIIB (45 HRS)

PAVEMENT DESIGN

Page 2: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

1-1

REPORT TITLE

CONTENTS

Chapter Description Page

1 COURSE SYLLABUS AND REFERENCES 1

1.1 The Syllabus 1

1.2 Recommended References 1

2 TYPES OF PAVEMENTS 2

2.1 Functions and Desirable Characteristics of Pavement 2

2.2 Pavement Courses 2

2.3 Pavement Types 3

2.4 Comparison of Rigid and Flexible pavements 4

2.4.1 Design precision 4

2.4.2 Life 5

2.4.3 Maintenance 5

2.4.4 Initial cost 5

2.4.5 Stage construction 5

2.4.6 Availability of materials 5

2.4.7 Surface characteristics 5

2.4.8 Penetration of water 6

2.4.9 Utility location 6

2.4.10 Labour vs Capital intensive technology 6

2.4.11 Traffic dislocation during construction 6

2.4.12 Overall economy 6

3 PAVEMENT DESIGN 22

3.1 Objectives of pavement design 22

3.2 Solutions to pavement design problems 22

3.2.1 The design process 22

3.2.2 The pavement structure 22

3.2.3 Design of paved roads 23

3.3 Functions of pavement layers 23

3.3.1 The flexible pavement structure 23

3.3.2 The Rigid pavement structure 24

3.4 Factors Affecting Pavement Design 24

3.4.1 Wheel Load 25

(a) Magnitude of wheel load and tyre pressure 25

(b) Equivalent standard axle 25

(c) Design traffic loading 27

(d) Design life 27

3.4.2 Climatic Factors 28

(a) Surface Drainage 28

(b) Temperature 28

Page 3: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

1-2

3.5 Flexible Pavement Design 28

3.5.1 Methods of Flexible Pavement Design 28

3.5.2 Theoretical Methods 29

(a) Boussinesq's Theory: Stresses in a homogeneous mass 29

(b) Burmister's theory: Stresses in layered systems 30

(c) Other models 31

(d) Three-layered analysis 31

(e) Multi-layer system of analysis 32

3.5.3 Empirical and semi-empirical pavement design methods 33

(a) Group Index method 33

(b) CBR design method 35

(c) Road Note 29 design method* 36

(d) Road Note 31 design method* 37

(e) The Kenya Pavement Design Method 42

(f) CEBTP pavement design method for tropical countries 45

(g) AASHTO design guide 45

(h) Other methods 46

3.6 Design of concrete pavements 47

3.7 Design of unpaved roads 48

3.7.1 Design of gravel roads 48

3.7.2 Design of earth roads 49

3.8 Examples of pavement design Error! Bookmark not defined.

4 SOIL STABILISATION 50

4.1 Definition 50

4.2 Purpose of Soil Stabilization 50

4.3 Types of Stabilisation Techniques 50

4.4 Mechanical Stabilisation 50

4.4.1 Principles 50

4.4.2 Applications 51

4.4.3 Soil-aggregate mixtures 51

4.4.4 Sand-clay roads 52

4.4.5 Sand-gravel mixtures 52

4.4.6 Stabilisation of soil with soft aggregates 53

5 ROAD MAINTENANCE 82

5.1 Pavement Evaluation 82

5.1.1 Introduction 82

5.1.2 Methods of Pavement Evaluation 82

5.1.3 Visual Rating 82

5.1.4 Pavement Serviceability Index (PSI) 83

5.1.5 Roughness Measurements 83

5.1.6 Benkelman Beam Deflection 84

5.1.7 Falling Weight Deflectometer 86

5.1.8 Skid Resistance Surveys 86

5.1.9 Pavement Deterioration Research 87

5.2 Road Inventorying 88

5.2.1 Need for Road Inventorying 88

5.2.2 Road Features Covered by Inventorying 88

5.2.3 Periodicity of Inventorying 89

5.2.4 Manual Methods of Inventorying 89

Page 4: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

1-3

5.2.5 Instrument-Aided Inventorying 89

5.2.6 Computer-Aided Road Data Bank System 89

5.2.7 QUESTION 90

5.3 Highway Maintenance 91

5.3.1 Need for Maintenance 91

(a) Traffic Factors 91

(b) Environmental Factors 91

5.3.2 Assessing Maintenance Needs 91

5.3.3 Maintenance of Earth Roads 92

(a) Grading 92

(b) Dragging 93

(c) Rolling 93

(d) Filling of rain-cuts 93

5.3.4 Maintenance of Gravel Roads 93

(a) Filling local depressions 93

(b) Grading 93

(c) Dragging 93

(d) Regravelling 93

5.3.5 Maintenance of Water-bound Macadam Roads 94

5.3.6 Maintenance of Bituminous Surfaces 95

(a) Defects, symptoms, causes and remedies 95

(b) Pot-hole repair (patch repair) 98

5.3.7 Maintenance of Cement Concrete Surface 98

(a) Cracks 99

(b) Joints 99

(c) Patching of slabs 99

(d) Mud-pumping and blowing 99

5.3.8 Maintenance of Shoulders 99

5.3.9 Maintenance of Slopes of Embankments 99

5.3.10 Maintenance of Bridges and Culverts 100

(a) Bridge and culvert register 100

(b) Periodic Inspection 100

(c) Painting of steel bridges 100

(d) Maintenance of masonry 100

(e) Scour 101

(f) Bearings 101

(g) Expansion joints 101

(h) Weak and narrow structures 101

5.3.11 Special Problems of Hill Road Maintenance 101

(a) Snow clearance 101

(b) Slips and landslides 101

(c) Drainage maintenance 101

5.3.12 Maintenance Practice in Kenya 101

(a) 27121. Organisation 101

(b) Types of maintenance operations 102

5.3.13 Maintenance Management System (MMS) 102

5.3.14 QUESTIONS 102

5.4 Overlay Design and Construction 102

5.4.1 Need for Overlays 102

5.4.2 Overlay Design for Flexible Pavements 103

(a) Principles of design 103

5.4.3 Overlay Design Methods for Flexible Pavements 103

(a) Measurement of pavement strength 103

(b) TRRL procedure 103

(c) Asphalt Institute method 103

(d) Analytical methods 104

5.4.4 Overlay Design Methods for Rigid Pavement 104

(a) Types of rigid overlays 104

Page 5: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

1-4

(b) Design of rigid overlays 105

(c) Flexible overlays over rigid slabs 105

5.5 Skid Resistance 105

5.5.1 Importance of Skid-Resistant Surfaces 105

5.5.2 Factors Governing Skid Resistance 106

5.5.3 Measurement of Skid Resistance 106

5.5.4 Standards for Skid Resistance 107

5.5.5 Construction of Skid Resistant Surfaces 108

5.5.6 Maintenance of Skid Resistance of Surfaces 109

5.5.7 QUESTIONS 109

5.6 Pavement Roughness 109

5.6.1 Importance of Smooth Riding Surface 109

5.6.2 Need for Roughness Measurements 109

5.6.3 What Constitutes Road Roughness 110

5.6.4 Measurement of Road Roughness 110

6 TENDERS, CONTRACTS AND SPECIFICATIONS 111

6.1 Methods of Execution 111

7 ROAD CONSTRUCTION PROGRAMMING AND MANAGEMENT 113

7.1 401. Need for Construction Programming 113

8 QUALITY CONTROL IN HIGHWAY ENGINEERING 117

8.1 41.1 Importance of Quality Control 117

Page 6: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

1

1 COURSE SYLLABUS AND REFERENCES

1.1 The Syllabus

FCE 546 - Transportation Engineering IIIB

a) Types of road pavements. Functions of various pavement layers. b) Pavement loading characteristics: Behaviour of layered pavement systems under

traffic loading, Stress distribution in flexible pavements. c) Bearing capacity considerations, evaluation of sub-grade and pavement materials. d) Flexible road pavements: analysis and design. e) Road maintenance: methods of evaluation and strengthening of existing road

pavements. f) Pavement materials: stabilization for road construction materials, bituminous mixes -

their ingredients and design. g) Road construction Techniques and quality control. Laboratory Work

• H1 - CBR Test • H2 - Soil Stabilization • H3 - Marshall Test

1.2 Recommended References

Reference books recommended for the course are as follows: 1. Principals of Pavement Design - Yoder, T and Witzack 2. Essentials of Highway Engineering - Gichaga, F and Parker 3. Highways: Location, Design, Construction & Maintenance - O’Flaherty 4. Highway Engineering – Martin Rogers 5. Traffic and Highway Engineering – NJ Garber & LA Hoel 6. Highway Engineering – L R Kadiyali

Page 7: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

2

2 TYPES OF PAVEMENTS

2.1 Functions and Desirable Characteristics of Pavement

A highway pavement is designed to support the wheel loads imposed on it from traffic moving over it. Additional stresses are also imposed by changes in the environment. It should be strong enough to resists the stresses imposed on it and it should be thick enough to distribute the external loads on the earthen subgrade, so that the subgrade itself can safely bear it. For satisfactorily performing the above functions, the pavement should have many desirable characteristics. These are:

1. It should be structurally sound enough to withstand the stresses imposed on it. 2. It should be sufficiently thick to distribute the loads and stresses to a safe value on the

subgrade soil. 3. It should provide a reasonably hard wearing surface, so that the abrasion action of

wheels (pneumatic and iron-tired) does not damage the surface. 4. it should be dust-proof so that traffic safety is not impaired. 5. Its riding quality should be good. It should be smooth enough to provide comfort to the

road users at the high speeds at which modern vehicles are driven. 6. The surface of the pavement should develop as low a friction with the tyres as possible.

This will enable the energy consumption of the vehicles to be low. 7. The surface of the pavement should have a texture and adequate roughness to prevent

skidding of vehicles. 8. The surface should not produce excessive levels of sound when travelling. 9. The surface should be impervious so that water does not get into the lower layers of the

pavement and the subgrade and cause deterioration. 10. The pavement should have long life and the cost of maintaining it annually should be

low. Some of the requirements enumerated above are conflicting. A good pavement should be a compromise among such conflicting needs

2.2 Pavement Courses

A pavement consists of one or more layers. The topmost layer is the surfacing the purpose of which is to provide a smooth, abrasion resistant, dust-proof and strong layer. The base, which comes immediately next below, is the medium through which the stresses imposed are distributed evenly. Additional help in distributing the loads is provided by the sub-base layer. The subgrade is the compacted natural earth immediately below the pavement layers. The top of the sub-grade is also known as the formation level. In a concrete road, the concrete slab itself acts as the wearing surface and distributes the load. The slab may be directly placed on the subgrade, or, in case of weak soils, a base and sub sub-base may be interposed between the slab and the subgrade.

Page 8: FCE546 Transp Eng IIIB - March 2012 v0

a) Kenyan practice

b) American practice

c) British practice Fig. 14.1. Pavement layers. In American practice, the top course in a flexible pcourse and a binder course beneath it. In U.K. practice, the surfacing is similarly composed of the wearing course at top and a base course beneath it. The sopractice corresponds to the roadbase in British practice. The functions of the sub-base layer are:

(i) To provide additional help to the base and surface courses in distributing the loads.(ii) To prevent intrusion of fine(iii) To minimise the damagin(iv) To facilitate drainage of free water that might get accu

The functions of the base course are:

(i) To act as the structural portion of the pavement and thus distribute the loads.(ii) If constructed directly o

the pavement. The functions of the surface course are:

(i) To perform as a structural portion of the pavement, (ii) To resist the abrasive forces of traffic.(iii) To reduce the amount of surface water pen(iv) To provide a skid(v) To provide a smooth and uniform riding surface.

2.3 Pavement Types

From the point of view of structural performance, pavements can be classified as: (i) Flexible (ii) Rigid

3

1. Pavement layers.

In American practice, the top course in a flexible pavement is itself composed of the surface course and a binder course beneath it. In U.K. practice, the surfacing is similarly composed of the wearing course at top and a base course beneath it. The so-called base course in Kenyan

e roadbase in British practice.

base layer are:

To provide additional help to the base and surface courses in distributing the loads.To prevent intrusion of fine-grained road-bed soils into base courses.To minimise the damaging effects of frost action. To facilitate drainage of free water that might get accumulated below the pavement.

The functions of the base course are: To act as the structural portion of the pavement and thus distribute the loads.If constructed directly over the sub-grade„ to prevent intrusion of sub

The functions of the surface course are: To perform as a structural portion of the pavement, To resist the abrasive forces of traffic. To reduce the amount of surface water penetrating the pavement. To provide a skid-resistant surface. To provide a smooth and uniform riding surface.

From the point of view of structural performance, pavements can be classified as:

avement is itself composed of the surface course and a binder course beneath it. In U.K. practice, the surfacing is similarly composed of the

called base course in Kenyan

To provide additional help to the base and surface courses in distributing the loads. bed soils into base courses.

mulated below the pavement.

To act as the structural portion of the pavement and thus distribute the loads. grade„ to prevent intrusion of sub-base soils into

From the point of view of structural performance, pavements can be classified as:

Page 9: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

4

(iii) Semi-rigid (iv) Composite. A flexible pavement is one which has low flexural strength. Thus, the external load is largely transmitted to the subgrade by the lateral distribution with increasing depth. Because of the low flexural strength, the pavement deflects if the subgrade deflects. The pavament thickness is so designed that the stresses on the subgrade soil are kept within its bearing power and the subgrade is prevented from excessive deformations. This implies that in a flexible pavement, the subgrade plays an important role as it carries the vehicle loads transmitted to it through the pavement. The strength and smoothness of the pavement depends to a great extent on the deformation suffered by the subgrade and its resistance to such As a contrast, a rigid pavement derives its capacity to withstand loads from the flexural strength or beam strength (modulus of elasticity), permitting the slab to bridge over minor irregularities in the subgrade, sub-base or base upon which it rests. This implies that the inherent strength of the slab itself is called upon to play a major role in resisting the wheel load. Minor imperfections or localised weak spots in the material below the slab can be taken care of by the slab itself. This is not to under-rate the role of the sub-grade soil. In fact, a good, stable and uniform support is necessary for a rigid pavement as well. But as long as a certain minimum requirement is met with in this regard, the performance of the rigid pavement is more governed by the strength of the slab itself than by the subgrade support. A semi-rigid pavements represents an intermediate stage between the flexible and the rigid pavement. It has much lower flexural strength compared to concrete slabs, but it also derives support by the lateral distribution of loads through the pavement depth as in a flexible pavement. Typical examples of a semi-rigid pavement are the lean-concrete base, soil-cement and lime-pozzolana concrete construction. A composite pavement is one which comprises of multiple, structurally significant layer of different - sometimes heterogeneous - composition. A typical example is the brick-sandwiched concrete pavement, which has been tried in India. It consists of top and bottom layers of cement concrete which sandwich a brick layer in the neutral axis zone. The design of composite pavements lies outside the well-established fields of flexible or rigid pavement design and is still in infancy. A very frequent term in highway engineering practice in developing countries is "low-cost pavements". These pavements represent specifications involving the use of locally available materials, often with stabilization techniques. Another distinction in pavement description is between "paved" and "unpaved" and "surfaced" and "unsurfaced". The exact definition of these terms is lacking. One often uses the terms "paved" roads to mean a road which has at least a stone-aggregate course laid over the subgrade. The stone-aggregate course may be left bare without any bituminous surfacing in which case the road, though paved, is "unsurfaced". An "unpaved" road is one which has only gravel or earthen surface. In Kenya, a "surfaced" road is one which has a bituminous or concrete surface. In contrast, "unsurfaced" roads are those which have no bituminous or concrete surfaces.

2.4 Comparison of Rigid and Flexible pavements

2.4.1 Design precision

A cement concrete pavement is amenable to a much more precise structural analysis than a flexible pavement. This is because of the fact that the flexural strength of concrete, which is used as the main basis for design, is well understood. On the other hand, flexible pavement designs are mainly empirical. It may be because of the design precision associated with a concrete pavement and the accuracy in predicting the performance of a rigid pavement. Latest research in understanding the performance of bituminous materials has furthered the knowledge on their behaviour. Computer aided analysis of layered systems is making the flexible pavement design more exact than hitherto.

Page 10: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

5

2.4.2 Life

A well-designed concrete slab has a life of about 40 years. The life of a flexible pavement varies from 10 to 20 years. Even this shorter life can be achieved only with extra maintenance input as discussed separately.

2.4.3 Maintenance A well-designed cement concrete pavement needs practically very little maintenance. The only maintenance needed is in respect of joints. Continuously Reinforced Concrete Pavement (CRCP) have reduced the number of joints to be attended to. The hard surface can withstand the abrasion caused by iron-tyred vehicles, (bullock carts) in Kenya and studded tyres in the West used under snowy conditions. The surface is unaffected by spillage of oil and lubricants. Bituminous surfaces, on the other hand, need great inputs in maintenance. Sealing cracks, making good potholes, resurfacing and resealing are done very frequently. The surface is affected by spillage of oil and lubricants. The surface is affected by natural weathering agents like air, water and temperature changes.

2.4.4 Initial cost The argument so far used against a cement concrete slab is that it is much more costly than a flexible pavement. However, while cost of cement has increased very much in recent years, so has the cost of bitumen, and this has comparison has required a re-think in recent years as

2.4.5 Stage construction Due to extreme scarcity of resources in the country, road construction is generally done adopting a policy of stage construction. A new road, for example, is constructed with the barest minimum specifications, which may involve just a thin bituminous surfacing over a partially designed thickness. As traffic grows, additional layers, in the form of water-bound macadam, bitumen-bound bases and superior surfacings are added on. Initial outlay is minimum and additional outlays are in keeping with traffic growth. Thus, at no stage is the investment made in advance of the actual requirement. This is a great advantage when dealing with new roads in an atmosphere of austerity. Cement concrete slabs do not fit into such a scheme of stage construction.

2.4.6 Availability of materials Cement, bitumen, stone aggregates and sand are the major materials involved in pavement construction. Cement has been in serious short supply in the country for the past many decades. The situation is likely to ease considerably since many new cement plants have been licensed. If cement becomes freely available, it is certain that the Kenyan highway engineers will start constructing roads again after a lapse of nearly forty years. Bitumen is also not locally available in Kenya. There is also the danger of the entire oil reserves in the world shrinking up soon in the next two or three decades. Bitumen is thus also a scarce commodity worldwide Moreover, import of bitumen involves foreign exchange, whereas cement is indigenously manufactured. In locations where stone aggregates are scarce, cement concrete may have an advantage, since the total construction thickness may be less than a flexible pavement. In locations where water is scarce, bitumen-bound layers are the only alternative. An example of this is in desert regions.

2.4.7 Surface characteristics A good cement concrete surface is smooth and free from rutting, potholes and corrugations. Thus the riding quality of a cement concrete surface is always assured. In a bituminous surface, it is only the asphaltic concrete surface that can give comparable rideability. Thin surfaces such as premix open-textured carpets and surface dressing are very rough. A well-constructed cement surface can have a permanent non-skid surface. On the other hand, if the design is faulty a cement concrete surface may become very smooth in course of time. If it does, it is extremely

Page 11: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

6

costly to restore the non-skid characteristics. Grooving and etching will have to be adopted. Grooved slabs cause noise. A bituminous surface can also be designed to have a good skid-resistant surface. If it fattens up, a rough seal cost with a brushing of coarse aggregates can easily restore the lost property.

2.4.8 Penetration of water A cement concrete slab is practically impervious, except at joints. If joints are sealed and well-maintained water will not penetrate and soften the subgrade. If joints are faulty, water easily finds it way in and serious defects such as "mud-pumping" can follow. A bituminous surface is not impervious. Water can find its way into the lower layers through cracks and pores. Such water can impair the stability of the pavement.

2.4.9 Utility location In cement concrete slabs, proper thought has to be given to locate utilities, such as water pipes, telephone lines and electric cables. It is difficult to rip open the slab and restore it to the original condition if any changes in the utility lines are to be made. For this purpose, gaps are left in the pavement which are constructed with bituminous materials. Thus, the digging up of pavements at random, a common feature in city streets in Kenya, is avoided. The disadvantage is thus converted to an advantage.

2.4.10 Labour vs Capital intensive technology Cement concrete pavements can be laid by paving machines, as is the practice in the West. Such a technology is highly capital intensive. On the other hand, cement concrete pavement construction, as practised in some developing countries, is a labour-intensive technology, employing only small machines like concrete mixers and screed vibrators. As against this, a superior bituminous construction such as an asphaltic concrete or bituminous macadam involves the use of costly equipment such as hot-mix plants and paver finishers. For a labour-surplus economy like ours, this is an undesirable thing. Concrete pavements have a grey colour which can cause glare under sunlight. Coloured cement can reduce the glare. Black bituminous pavements are free from this defect. On the other hand, bituminous roads need more street lighting.

2.4.11 Traffic dislocation during construction A cement concrete pavement requires 28 days before it can be thrown open to traffic. On the other hand, a bituminous surface can be open to traffic after it is rolled. Further traffic will facilitate its compaction. Thus concrete pavements cause dislocation of traffic, in case the work is done on an existing road.

2.4.12 Overall economy A good road is costly to construct, but once constructed, such a road requires little maintenance and results in savings in vehicle operating costs. Overall economic considerations, a rigid pavement is far more economical than the flexible one.

Page 12: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

7

3 EVALUATION OF SUBGRADE AND PAVEMENT MATERIALS

3.1 The Natural Environment

3.1.1 Climate

Climate has a considerable influence on road performance and should therefore be taken into account by the design engineer.

• Kenya has a very wide variety of climates, comprising: • Afro-alpine climate • Equatorial climate • Wet-tropical climate • Semi-arid climate • Arid climate • Very arid climate

Moreover, the pattern of the climatic zones is rather complex, since the Kenyan climates are largely governed by altitude. The design of drainage and anti-erosion systems largely depends on the expected climatic conditions. The choice of roadmaking materials will also be influenced by climate. In this respect, the following principles should be followed by the design engineer: (i) In wet areas (mean annual rainfall greater than 500mm), the use of plastic pavement materials should be as limited as economically feasible. Bituminous surfacings should be as impervious as possible. Shoulders should be impermeable or properly sealed. Great attention should always be paid to both internal and external drainage. (ii) In dry areas (mean annual rainfall less than 500 mm), higher plasticities can be accepted for pavement materials and open-textured base materials can be used. Difficulties may occur with cement-treated materials, because of the rapid evaporation of water hindering the hydration of cement and the tendency of the treated material to crack extensively as a result of shrinkage and volumetric changes caused by the daily temperature variations. Drainage and protection against erosion should not be neglected as short but heavy storms are likely to occur even in the driest areas.

3.1.2 Natural Materials and Soils In order to minimize construction costs, natural materials should be used as much as possible. Every endeavour should be made to use the cheap local materials before considering the importation of material from some distance. It is therefore of prime importance to make a complete inventory of all available roadmaking materials, such as stone, gravel, sand and clayey sand at the investigation stage. Kenya has abundant resources of hard stone. Detailed information regarding the various types of stone available and their roadmaking characteristics can be found in Materials Branch Report No. 336. Many different sorts of gravels exist in Kenya: lateritic gravels, quartzitic gravels, calcareous gravels, some forms of weathered rock, soft stone, coral rag, etc. Various types of sand and silty or clayey sands are also found. Detailed information concerning these materials and their engineering properties can be found in Materials Branch Reports No. 343 and 344. It will be useful for the design engineer to consult all relevant documents, such as materials reports, geological and pedological maps and reports.

Page 13: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

8

3.2 Subgrade

3.2.1 Classification of Kenyan Soils

For a rational approach to pavement design/ the most important characteristic of the subgrade is its elastic modulus. However, the measurement of this modulus requires fairly complicated and time-consuming tests. However, it has been proved that there is good correlation between the California Bearing Ratio and the elastic modulus of Kenyan soils. Since the CBR test is a fairly easy and widely used test, it has been decided to retain it as the quantitative means of evaluating the subgrade bearing strength.

(a) Classes of Subgrade Bearing Strength A survey of Kenyan subgrade soils, described in Materials Branch Report No. 345, has shown that they can be grouped into the following 6 bearing strength classes TABLE 6.1.1 : SUBGRADE BEARING STRENGTH CLASSES Soil Class CBR Range Median

SI 2-5 3.5 S2 5-10 7.5 S3 7-13 10 S4 10 - 18 14 S5 15 - 30 22.5 S6 30 The above CBR ranges correspond to the results actually obtained on materials of the same type along sections of road considered homogeneous. They reflect both the variations of the characteristics of the soil which inevitably occur, even at small intervals, and the normal scatter of test results. The following points should be noted: (i) No allowance for CBR's below 2 has been made, because it is, technically and economically, out of the question to lay a pavement on soils of such poor bearing capacity. Such weak soils are saturated expansive clays, saturated fine silts or compressible (swampy) soils, e.g. mud, soft clay, etc. They should be dealt with as described in Section 4.2.2. Moreover, the measurement of the bearing strength of such soft soils is most uncertain and CBR's below 2 are of little significance. (ii) The use of Class SI soils (CBR 2-5) as direct support for the pavement should be avoided as much as possible. Wherever practicable, such poor quality soils should be excavated and replaced, or covered with an improved subgrade• (iii) The CBR range of Class S5 is fairly wide. This is because Class S5 is either gravelly material or unsoaked soil, the CBR's of which always show considerable scatter. Furthermore, the difference in the pavement thickness required is comparatively small when the subgrade bearing strength varies from the lower to the upper limit of this class. (iv) Class S6 covers all subgrade materials having a CBR over 30 and which comply with the plasticity requirements for natural materials for subbase (See Chart SB1). In such cases, no subbase is required. No class of higher bearing capacity has been considered as such subgrade materials are extremely rare and as a roadbase is always necessary to provide a homogeneous and uniform layer. (v) It will be noted that the subgrade categories overlap. For any one section of a road the average (CBR should be higher or equal to the mean of the subgrade class selected for design, and no individual result shall be below the lowest value of the range for that subgrade class. Where the subgrade CBR values are very variable the designer should balance the cost of

Page 14: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

9

having very short sections of different subgrade categories against a conservative design taking account of the worst conditions encountered over longer sections.

(b) Classification of the Most Common Kenyan Subgrade Materials The following materials cover almost all the subgrade materials encountered in Kenya, and they may be classified on the basis of bearing strength, as shown in Table 6.1.2 overleaf. TABLE 6.1.2 : CLASSIFICATION OF KENYA SUBGRADE MATERIALS

Type of material Bearing Strength Class

After 4 days soak At O.M.C. (Standard)

Black cotton soils SI S5 Micaceous silts (decomp.rock) SI S3 Other eluvial silts (decomp.rock) S2 S4 Red friable clays S3 S5 Sandy clays on volcanics S3 or S4 S5 Ash and pumice soils S3 or S4 S5 Silty loams on gneiss and granite S4 S5 Calcareous sandy soils S4 S5 Sandy clays on basement S4 S5 Clayey sands on basement S4 or S5 S5 or S6 Dune sands S4 S4 or S5 Coastal sands S4 S5 Weathered lava S4 or S5 S5 or S6 Quartzitic gravels S4 - S6 S5 or S6 Soft (weathered) tuffs S4 - S6 S5 or S6 Calcareous gravels S4 - S6 S5 or S6 Lateritic gravels S5 or S6 S6 Coral gravels S5 or S6 S6 * Some of the ash and pumice soils have a very low maximum dry density and a lower

Young's Modulus than might be expected from the-measured CBR values. Such soils (Standard Compaction MDD less than 1.4 Mg/m^) cannot be classified for pavement design purposes on the basis of CBR only

3.2.2 Determining the Subgrade Strength

(a) Recommended Subgrade CBR Test Procedure

The actual strength of the subgrade and, in particular, its actual CBR, depend on the type of material, its density and its moisture content. For each type of material, it is therefore necessary to determine the relative compaction that should be obtained in-situ and the maximum moisture content likely to occur in the subgrade. In order to obtain a complete knowledge of the relationship between density, moisture content and CBR, a "6 point" CBR test should be carried out on a representative sample of each type of subgrade material encountered. The tests are conducted in the following way:

The material shall be compacted at 3 different levels of compaction. The samples shall be moulded at the moisture content which is expected at the time of in-situ compaction (in general, at the Optimum Moisture Content). At each level of compaction, one CBR shall be measured immediately on one soaked specimen. The time of soaking will depend on the anticipated subgrade conditions. The amount of water absorbed during soaking and the eventual swell shall also be measured.

The above method enables an estimate to be made of the subgrade CBR at different densities and thus helps in deciding the relative coupaction required. It also indicates the loss of strength which soaking may cause. A full particle size analysis should also be done on each representative sample.

Page 15: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

10

(b) Subgrade Compaction The compaction requirements are generally as follows:

The upper 300 mm of the subgrade shall be compacted to a dry density of at least 100% MDD (Standard Compaction) in cuttings where there is no improved subgrade and on all fills. In cuttings where an improved subgrade is to be placed, the upper 150 mm of the subgrade, prior to placing the improved subgrade layer(s), shall be compacted to at least 100% MDD (Standard Compaction) and the lower 150 mm to at least 95% MDD (Standard Compaction). All improved subgrade shall be compacted to a dry density of at least 100% MDD (Standard Compaction). The maximum compacted thickness which shall be paid, processed and compacted at one time is generally 300 mm. The moisture content shall be adjusted in order that the required relative compaction is obtained, but the moisture content at the time of compaction shall not exceed 105% of the Optimum Moisture Content (Standard Compaction). If it proves feasible, dry compaction may be accepted, especially in dry areas.

In some cases, it is advantageous to obtain relative compactions higher than the above figures, since compaction not only improves the subgrade bearing strength, but also reduces permeability. This applies, in particular, to clayey sands, silty sands and granular materials, the coarse particles of which are hard enough not to crumble under heavy compaction.

(c) Estimating the Subgrade Moisture Content The actual moisture content of the subgrade soil under the road pavement will depend on many factors, principally:

• local climate • depth of the water table • type of soil • topography and the drainage • permeability of the pavement materials • permeability of the shoulders

The study of Kenyan subgrade moisture conditions, as described in Materials Branch Report No. 345, has revealed the general relationships between mean annual rainfall, soil type, drainage conditions and subgrade moisture content. TABLE 6.2.1 : SUBGRADE MOISTURE CONTENTS Mean Annual Rainfall (mm) Water Table Soil Type Drainage Subgrade Moisture

Content

Non-existent or deep

Predominantly clays or silts

Impermeable pavement, reasonable surface drainage

Average slightly less than OMC Maximum 3% units above OMC

> 500 Permeable pavement, poor surface drainage

Average, often exceeds OMC. Maximum equivalent to saturation.

< 500 Non-existent or deep

Sands to sandy-clays Average well below OMC.

Maximum equal to OMC. Notes 1. OHC is measured with Standard Compactive Effort.

Page 16: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

11

2. Permeable pavements include pavements constructed with open-textured materials and, mostly, deteriorated pavements exhibiting surfacing and/or base cracks.

(d) Determining the Subgrade Design Strength Unless a more accurate estimation of the ultimate subgrade moisture content can be made and backed by factual data, the subgrade strength shall be determined as follows: (i) In areas where the mean annual rainfall exceeds 500 mm, the determination of the subgrade strength shall be based on CBR* s measured after 4 days soak. (ii) In dry areas, where the mean annual rainfall is less than 500 mm, the subgrade strength may be evaluated in terms of CBR's measured at Optimum Moisture Content (Standard Compaction). However, a design based on such unsoaked CBR's will be permitted only where it has been established that no prolonged soaking may occur. For this purpose, consideration shall be given to factors such as permeability of the natural ground and topography (in other words, to the ability of water to drain rapidly under all circumstances).

3.3 Subgrade Requirements for Pavement Design

3.3.1 Materials Suitable for Pavement Support

Materials forming the direct support of the pavement shall normally comply with the following requirements:

• CBR at 100% MDD (Standard Compaction) and 4 days soak : more than 5 • Swell at 100% MDD (Standard Compaction) and 4 days soak : less than 2% • Organic matter (percentage by weight) : less than 3%

This means that no pavement should be placed directly on Class SI soil and that an improved subgrade is required on such soil.

3.3.2 Improved Subgrade Placing an improved subgrade not only increases the bearing strength of the direct support of the pavement, but also

• protects the upper layers of earthworks against adverse weather conditions (protection against soaking and shrinkage),

• facilitates the movement of construction traffic, • permits proper compaction of the paveme-t layers, • reduces the variation in the subgrade bearing strength, and • prevents pollution of open-textured subbases by plastic fines from the natural subgrade.

It may prove technically and economically advantageous to lay an improved subgrade not only on SI, but also on S2 and S3 Class soils. The decision will generally depend on the respective costs of subbase and improved subgrade materials. An improved subgrade would generally not be economically justified on Class S4 soils. An improved subgrade placed on soils of any particular class must obviously be made of a material of a higher class (up to Class S5, since Class S6 is subbase quality).

3.3.3 Influence of Improved Subgrade or. Subgrade Bearing Strength Where a sufficient thickness of improved subgrade is placed, the overall subgrade bearing strength is increased to that of a higher class and the subbase thickness may be reduced accordingly.

Page 17: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

12

Table 6.3.1 shows the minimum thickness of each class of improved subgrade required on each class of natural soil to obtain a higher class of subgrade bearing strength. These minimum thicknesses have been calculated taking into account the respective elastic moduli of each class of soil. TABLE 6.3.1 ; MINIMUM THICKNESS OF IMPROVED SUBGRADE REQUIRED Strength Class of native subgrade soils

Improved subgrade New Class of subgrade bearing strength

Material Strength Class

Minimum thickness required (mm)

S1*

S2 400 S2

S3 350 S2 425 S3

S4 275 S2 325 S3 450 S4

S2 S3 300 S3

S4 200 S3 350 S4

S3 S4 300 S4

S5 150 S4 350 S5

• Many Class S1 soils will be expansive clays. There may also be problems in achieving high degrees of compaction in Class S4 or S5 material overlying a Class S1 soil.

3.3.4 Lime Treated Subgrade

Treatment of the subgrade soils with lime may be considered in the following cases: (i) Where the natural soils are excessively clayey and no better material is economically available, their treatment with hydrated lime may be the cheapest solution. (ii) Where the natural soils are excessively wet and cannot be dried out because of adverse weather conditions, their treatment with quicklime may allow construction to proceed and provide a markedly stronger subgrade. The treated soils will be classified in accordance with their CBR range and the final bearing strength class of the pavement support will be determined as indicated above.

3.4 Materials Sampling and Testing Programme

3.4.1 General

(a) Introduction

Road design may be divided into three stages, namely feasibility study, preliminary design and final design. This Chapter describes the materials sampling and testing programmes applicable to each stage of the design.

(b) Mass of Samples Required The total mass of sample required depends on the tests to be carried out, the grading of the material (its maximum particle size, in particular) and its susceptibility to crushing during compaction. For general guidance, Table 14.1.1 below shows the minimum mass of sample required for various sequences of tests and typical materials, namely:

• Fine grained soil (Maximum size: 2mm)

Page 18: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

13

• Coarse grained gravel (Maximum size: 40 mm), not susceptible to crushing during compaction.

• Coarse grained gravel (Maximum size: 40 mm), susceptible to crushing during compaction.

• Solid stone. The masses indicated in Table 14.1.1 include some allowance for drying, wastage and rejection of coarse fragments where necessary. TABLE 14.2.1: MINIMUM MASS OF SAMPLE REQUIRED SOILS AND GRAVELS SOILS AND GRAVELS

Tests Required Fine grained soil (max size 2mm)

Coarse grained gravel (max. size 40mm) not susceptible to crushing

Coarse grained gravel (max. size 40 mm) susceptible to crushing

Grading * * * * * * * * * * * * Atterberg Limits * * * * * * * * * * * * Compaction * * * * * * * * * CBR (1 point) * * *

CBR (3 points) * * * * * *

Treatment Tests * * * Minimum Sample Mass(kg) 5 20 35 80 20 40 60 150 20 60 80 180

SOLID STONE Tests Required Solid Stone I.A.A. * * A.C.V. * * S • S • o • * * S.G. * * Bitumen Affinity * * Crushing * Grading * F.I. * S.B. * Compaction * Minimum Sample Mass (kg) 50 . 200

3.5 Materials Testing at Preliminary Design

3.5.1 Alignment Soils

(a) Sampling

At least one sample shall be taken per kilometre of anticipated alignment, with more frequent samples where there are major changes in soil type. To this end, pits shall be dug mostly in anticipated out areas, if possible down to at least 0.5 m below the expected formation level. Further, in the case of a new alignment, the depth of any pit shall in no case be less than 1.5m, unless rock or other material impossible to excavate by hand is encountered. The position of each trial pit shall be accurately determined and recorded. In every trial pit, all layers, including top soil, shall be accurately described and their thicknesses measured. All layers of more than 300 mm (except top soil) shall be sampled. The sample shall be taken over the full depth of the layer by taking a vertical slice of material.

Page 19: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

14

The log of each trial pit shall be accurately drawn and included in the Materials Report.

(b) Testing of soils on new alignments The size of each sample shall be sufficient for the following tests to be carried out.

• Grading to 0.075 mm sieve • Atterberg Limits • Compaction test (Standard Compaction: 2.5 kg rammer) • CBR and swell on samples moulded at 100% MDD (Standard Compaction) and OMC

(Standard Compaction) • Mineralogical analysis of main soil types

Note: CBR's'shall normally be measured after 4 days soak, except in arid areas (annual rainfall

less than 500 mm), where they maj be measured at OMC or after a reduced soaking period, depending on the equibrium moisture contents predicted under the pavement in the area (see Chapter 6, Section 6.2.4). The moisture contents after soaking shall be measured, both on the whole CBR specimen (by weighing it after soaking) and on a sample taken from beneath the plunger, after testing.

(c) Testing of subgrade on alignments of existing gravel roads

This applies to sections of existing gravel roads which are to be upgraded, the geometric standards of which are good enough to maintain the existing alignment. If deep cuttings are proposed through materials indicated to be variable by trial pits and a study of the geological maps: consideration is to be given to drilling the cuttings at the final design stage when the potential hard stone sources are being investigated.. Where more than 100 mm of existing gravel wearing course is in place on the road and where the shape is adequate, samples of subgrade are to be submitted to tests. In addition, the Field Moisture Content and Field Dry Density of each sample shall be measured; this is to decide whether to leave the subgrade undisturbed or to recompact it. If the degree of field compaction is found to be consistently satisfactory, the CBR's shall be measured at Field Dry Density. If not, the subgrade will need recompaction and the CBR's shall then be measured at 100% M.D.D. (Standard Compaction).

3.5.2 Existing Gravel Wearing Course Where a gravel road is to be upgraded on the same alignment, the existing gravel wearing course may provide extra material either for subbase, or for improved subgrade. Measurements of thickness and width of gravel wearing course shall then be recorded every 100m. One sampIe per kilometre of existing gravel wearing course shall be taken, where the gravel layer is at least 150 mm thick. .

3.5.3 Soil and Gravel Borrow Pits

(a) General Where feasible, borrow pits should be spaced so as to obtain the most economic use or materials. The minimum thickness of deposit normally considered workable is of the order of one metre. However, there may be instances when thinner horizons have to be exploited, as no suitable alternative exists. The absolute minimum depends on the area of the deposit and the thickness of overburden. (If there is no overburden as may be the case in arid areas, horizons as thin as 300 mm may be workable).

Page 20: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

15

(b) Field investigations and sampling procedure

Trial pits shall be dug on a 60 m grid, through the full depth of the layer(s) proposed for use. A minimum of 5 trial pits is required for each proposed borrow pit. The location of each proposed borrow pit shall be indicated on a key plan. A site plan of each proposed borrow pit shall be prepared, showing the position of each trial pit, the characteristic features of the site and the means of access and location. In every trial pit, all layers, including top soil and overburden, shall be accurately described and their thicknesses measured. All layers proposed for use shall be sampled. The sample shall be taken over the full depth of the layer proposed, by taking a vertical slice of material. The log of each trial pit shall be accurately drawn and included in the Materials Report.

(c) Frequency of sampling and testing A sufficient number of samples, each of sufficient quantity, are to be taken to carry out tests to determine the main materials, processes and additives to be used, the approximate borrow pit location and hauls and the approximate pavement thicknesses and percentages of additives required. Samples for identification tests Sampling shall be carried out so as to obtain at least one sample per 4,000 m3 of material proposed for use. At least one sample shall be taken from each positive trial pit, even if the volume represented is small. Each sample shall be submitted to the following tests:-

(a) Grading to 0.075 mm sieve (b) Atterberg Limits

Large samples for Compaction and CBR tests Large samples for Compaction and CBR tests shall be obtained by either of the following methods: 1. Mix Method: Large samples shall be obtained by mixing "small" identification samples. A

mix must be representative of a workable area. All the "small" samples to be incorporated in a mix must be of the same type of material and must have fairly consistent identification characteristics (Grading and Atterberg Limits). Within each borrow pit, the mixes shall be chosen so as to adequately cover the range of materials proposed for use.

2. Re-Sampling Method: In consideration of the above identification results, large samples shall be obtained by re-sampling from typical existing trial pits which are representative of the various categories of material found within the potential borrow pit area.

At least one large sample, whether mixed or re-sampled, is required per 15,000 m3 of material proposed for use. Each large sample shall be submitted to the following tests:

• Grading to 0.075 mm sieve • Atterberg Limits • Compaction test (Heavy Compaction: 4.5 kg rammer) • CBR and swell at 4 days soak, on specimens moulded at OMC (Heavy Compaction) at 3

levels of compaction, normally around 90, 95 and 100% MDD (Heavy Compaction). The moisture contents after soaking shall be measured. Note: For the types of gravel susceptible to crushing during compaction, the grading of the

specimen compacted closest to 95% MDD shall be determined after compaction and

Page 21: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

16

CBR testing and compared witn the grading before compaction of the specimen prepared for CBR.

Treatment tests (when appropriate) If the above Compaction and CBR tests show that the available natural materials do not meet the quantity or quality requirements, treatment tests shall be carried out on the relevant large samples (as defined above). Each sample shall be mixed with cement or lime, whichever is expected to give the best results. Three amounts of additive shall be chosen so as to give a representative picture of the treated material's characteristics. The following tests shall be carried out:

• Compaction test (Heavy Compaction) on the large sample mixed with the amount of additive expected to be appropriate (usually the intermediate value of the three)

• CBR and/or UCS at 7 days cure plus 7 days soak on specimens moulded at OMC and 95% MDD (as determined by test (e) above, with each of the 3 amounts of additive.

• Atterberg Limits on one set of 3 specimens (3 amounts of additive). At least one large sample per 15,000 m3 of material proposed for treatment shall be submitted to.

3.5.4 Stone Quarries

(a) General Potential sources of stone should be identified. Those visually considered suitable, in terms of stone quality and quantity, should then be further investigated. Practical considerations concerning the exploitation of the potential quarries, such as access, ease of working, overburden, etc. should be noted. The location of each potential source of stone shall be indicated on a key plan. A site plan of each potential quarry shall be prepared, showing the characteristic features of the site (including outcrops) and the means of access and location.

(b) Sampling Hand sampling from existing faces or outcrops shall be carried out. At least 3 samples shall be taken from each potential source. The position of each sampling point or group of sub-sampling points shall be accurately determined and reported on the site plan. Each sample shall be accurately described, from a geological and mineralogical viewpoint. Great care shall be taken to ensure that the samples are obtained from sound rock and not from a superficial horizon of weathered rock.

(c) Testing Each sample shall contain sufficient material to carry out the following tests.

• Los Angeles Abrasion • Aggregate Crushing Value • Sodium Sulphate Soundness (or magnesium sulphate soundness) • Plasticity Index on L.A.A. fines • Mineralogical analysis

3.5.5 Materials Testing at Final Design

3.5.6 E arthworks and Subgrade

(a) Sampling

Page 22: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

17

At least one sample shall be taken per 500 metres along the length of the proposed alignment, with more frequent samples where necessary to record changes of soil type or to provide an adequate assessment of the subgrade strength. A good knowledge of the materials to be cut is also essential. For these purposes, holes shall be excavated mostly in proposed cut areas, down to at least 0.5 m below the anticipated formation level, unless rock is encountered. The position of each test hole shall be accurately determined and reported. In hilly or mountainous terrain, deep holes will be required to accurately determine the materials to be cut. It is sometimes impossible to dig trial pits to the depth of the anticipated formation level. It is then recommended to use a hand or power auger to drill holes to the depth required. In every hole, all layers, including top soil, shall be accurately described and their thicknesses measured and recorded. All layers of more than 300 mm (except top soil) shall be sampled. In every hole in cuts, one sample shall be taken at the approximate level of the formation. The other samples shall be representative either of the anticipated fill materials or of the anticipated subgrade in fills. The sample shall be taken over the full depth of the layer by taking a vertical slice of material. The log of each test hole shall be accurately drawn and included in the Materials Report. To assess the quantities of the various earthwork categories (i.e. rock, rippable or normal material), it will in some cases be necessary to drill boreholes. This type of investigation may advantageously be supplemented by a seismic survey or a resistivity survey.

(b) Testing of soils on new alignments Basic testing Sufficient material shall be obtained of each sample to carry out the following tests:

• Grading to 0.0 75 mm sieve • Atterberg Limits • Compaction test (Standard Compaction: 2.5 kg rammer) • CBR and swell on samples moulded at 100% M.D.D. (Standard Compaction) and OMC

(Standard Compaction). Note: CBR's shall normally be measured after 4 days soak, except in arid areas (annual rainfall

less than 500 mm) where they may be measured at OMC or after a reduced soaking period, depending on the equilibrium moisture content predicted under the pavement in the area. The moisture contents after soaking shall be measured.

Classification of the subgrade soils and testing of samples representative of each soil category The results from the above basic testing, combined with the relevant field observations, will enable a classification of the subgrade soils to be made. A category of soil should include the soils of the same type having fairly consistent geotechnical characteristics (Grading, Atterberg Limits, Compaction and CBR). Usually, the number of soil categories will not exceed 4 or 5 for a given road project. For each soil category, one representative large sample shall then be taken. Each large sample shall be submitted to the following tests:

• Full particle size distribution analysis • Atterberg Limits • Compaction test (Heavy Compaction: 4.5 kg rammer) • "6 points" CBR test as summarized below: • Mineralogical composition determination

For a "6 points" CBR test the material shall be compacted at 3 levels of compaction, normally around 95, 100 and 105% MDD (Standard Compaction). The specimens shall be moulded at the

Page 23: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

18

moisture content expected at the time of in-situ compaction (in general at OMC). At each level of compaction, one CBR shall be measured immediately on one unsoaked specimen and one CBR shall be measured on one soaked specimen. The time of soaking will depend on the anticipated subgrade conditions. The amount of water absorbed during soaking and the eventual swell shall be measured. This method enables an estimate to be made of the subgrade CBR at different densities and thus assists in determining the relative compaction to be specified. It also indicates the loss of strength which soaking may cause Treatment tests (when appropriate) If treatment of some of the alignment materials is contemplated, for use either as improved subgrade or as subbase, the treatment tests shall be carried out, as indicated in Section 14.3.3, on the above large samples typical of each relevant soil category. (iii) Testing of subgrade on existing gravel road alignments

3.5.7 Existing Gravel Wearing Course (where appropriate) No further sampling or testing is required at this stage. Indeed, existing gravel wearing courses are subject to cnanges both in quantity and quality, under the action of traffic and weather. They should be considered as possible extra sources of material, to be re-evaluated at the construction stage.

3.5.8 Soil and Gravel Borrow Pits

(a) General Information obtained at the Preliminary Design stage will enable a selection of the most suitable borrow areas to be made. Consideration shall be given to the following factors:

• quality of the materials • location of the proposed borrow areas, so as to minimize haul and obtain the most

economic use of materials • ease of working (land acquisition, clearance of the site, access, overburden, thickness of

exploitable horizon, etc.).

(b) Field investigations and sampling procedures Pits shall be dug at every point on a 30 m grid, through the full depth of the layer(s) proposed for use. The position of each proposed borrow pit shall be indicated on a key plan. A site plan of each proposed borrow pit shall be prepared, showing the position of each trial pit, the characteristic features of the site and the means of access and location. In every trial pit, all layers, including top soil and overburden, shall be accurately described and their thicknesses measured and recorded. All layers proposed for use shall be sampled. The sample shall be taken over the full depth of the layer proposed for use by taking a vertical slice of material. The log of each trial pit shall be accurately drawn and included in the Materials Report.

(c) Frequency of sampling and testing Samples for identification tests

Page 24: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

19

Sampling shall be carried out so as to obtain at least one sample per 1,000 m3 of material proposed for use. At least one sample shall be taken from each positive trial pit, even if the volume represented is small. Each sample shall be submitted to the following tests:

1. Grading to 0.075 mm sieve 2. Atterberg Limits

Large samples for Compaction and CBR tests Large samples for compaction and CBR tests shall be obtained either by the Mix-method or by the Re-sampling method. At least one large sample, whether mixed or re-sampled, is required per 5,000 m3 of material proposed for use. Each large sample shall be submitted to the following tests:

1. Grading to 0.075 mm sieve 2. Atterberg Limits 3. Compaction test (Heavy Compaction: 4.5 kg rammer) 4. CBR and swell at 4 days soak, on specimens moulded at O.M.C. (Heavy

Compaction) at 3 levels of compaction, normally around 90, 95 and 100% MDD (Heavy Compaction). The moisture contents after soaking shall be measured.

Note: For the types of gravel susceptible to crushing during compaction, the grading of the

specimen compacted closest to 95% MDD (Heavy Compaction) shall be determined after compaction and CBR testing and compared with the grading before compaction of the specimen prepared for CBR.

In addition to the foregoing tests, the Los Angeles Abrasion and the Aggregate Crushing Value of the coarse particles shall be determined for at least one typical sample from each site of gravelly material. Treatment tests (when appropriate) Information obtained at the Preliminary Design stage combined with the results of the above tests, will enable the design engineer to decide which borrow pit materials require treatment and the nature of that treatment (i.e. type of additive and approximate percentage needed, method of mixing, etc.). Treatment tests shall then be carried out on the relevant large samples (as defined above). First, if it is suspected that the chemical composition of the material may give rise to detrimental reactions, the following chemical tests shall be carried out:

1. Organic matter content 2. pH value 3. Sulphate content

Then, if the material appears to lend itself to treatment, the representative large sample shall be mixed with the additive chosen. 3 amounts of additive shall be selected so as to give a representative picture of the treated material's characteristics. The following tests shall be carried out:

1. Compaction test (Heavy Compaction) on the large sample mixed with the amount of additive expected to be appropriate (in general, the intermediate value of the three).

2. CBR and/or UCS at 7 days cure plus 7 days soak on specimens moulded at OMC and 95% MDD (as determined by test (h) above) with 3 amounts of additive. CBR tests apply to improved materials, whereas UCS apply to stabilised ones (The results of the Preliminary Design stage should enable the distinction between "Improvement" and "Stabilisation" to be made).

Page 25: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

20

3. Atterberg Limits on one set of 3 specimens (3 amounts of additive) from (1) above.

At least one large sample per 5,000 m3 of material proposed for treatment shall be submitted to tests.

3.5.9 Stone Quarries

(a) General Information obtained at the Preliminary Design stage will enable a selection of the most suitable quarry sites to be made, on the basis of stone quality, location, access and ease of working.

(b) Investigations, drilling and sampling Each selected potential quarry site shall be investigated as follows:

• Trial holes shall be dug or drilled on a 30 m grid to prove overburden. • Boreholes shall be drilled to prove quantity and quality of stone. It is

recommended that, normally, the cores diameter be 76 mm (Coring bits required: HWG, formerly HX). In any case, the minimum coring diameter shall be 55 mm (NWG, formerly NX), so as to recover stone in sufficient quantity for testing. The log of each borehole shall be accurately recorded, drawn and included in the Materials Report.

• Consideration should be given to the use of a bulldozer or other mechanical excavator to prove the availability of solid rock. Such an excavation may also be shown to tenderers during a conducted site visit.

• Samples of fresh rock shall be obtained by hand, or pneumatic drilling from existing faces and outcrops. Great care shall be taken to avoid sampling from a superficial horizon of weathered rock and to ensure the samples are representative of the stone to be used.

• In addition, whenever possible, deeper samples shall be obtained by blasting. Depending on the consistency of the stone and whether it is an existing or a new quarry, 5 to 10 samples are required per quarry. A site plan of each potential quarry shall be prepared, showing the characteristic features of the site (outcrops, existing faces, etc.) and the means of access and location. The position and level of each borehole and each sampling point shall be accurately determined and recorded on the site plan, after the quarries have been drilled.

(c) Testing Each sample shall contain sufficient material to carry out the following tests:

• Los Angeles Abrasion • Aggregate Crushing Value • Sodium Sulphate Soundness • Plasticity Index on L.A.A. fines & Plasticity Index on Material passiny the 425 micron

sieve • Specific Gravity (oven-dry method) • Bitumen Affinity (for stone proposed for use with bitumen).

Moreover, one large sample shall be obtained from each quarry, so as to be representative of the stone to be used. This large sample shall be crushed with a small crusher (and not broken by hand), to a maximum size depending on the proposed use of the stone (usually ranging from 20 to 40 mm). The crushed stone shall be submitted to the above tests and, in addition, to the following tests:

• Grading to 0.075 mm sieve • Flakiness Index • Sand Equivalent • Compaction test (Vibrating Hammer method), wnen appropriate.

Page 26: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

21

Page 27: FCE546 Transp Eng IIIB - March 2012 v0

4 PAVEMENT DESIGN

4.1 Objectives of pavement design

Pavement design is aimed at achieving a pavement structure which is economical comfortable to the motorist; and which minimises development of pavement distress features such as rutting, cracking, potlife of the pavement. The design should take account of eof staged construction. It must also aim at a desirable balance between construction, roadand maintenance costs. For completeness, the design should specify the level of maintenance necessary to keep the pavement at the design serviceability level. The designer should preferably specify the required regularity of monitoring certain pavement characteristics which would indicate the likelihood of certain distress features occur

4.2 Solutions to pavement desig

4.2.1 The design process Pavement design involves the study of the properties of soils along the selected road alignment, the identification and selection of construction materials for the various layers, and the determination of the thicknesses conditions expected to prevail during the design life of the pavement. Design should aim at providing adequate cover to the subgrade so that stresses at the subgrade level are low enough to prevematerials which are strong enough to resist the stresses and strains imposed by wheel loads. The complete design should also ensure that the pavement structure is adequately drained.

4.2.2 The pavement structure A road pavement consists of a number of layers, with subgrade at the bottom, and, in the case of a flexible pavement, includes sub

Example of Section through A concrete or rigid pavement will normally consist of a concrete slab laid on a subwhich rests on subgrade.

22

Objectives of pavement design

Pavement design is aimed at achieving a pavement structure which is economical comfortable to the motorist; and which minimises development of pavement distress features such as rutting, cracking, pot-holes, ravelling, fretting, crazing, distortions, etc, during the design life of the pavement. The design should take account of environmental factors and the possibility of staged construction. It must also aim at a desirable balance between construction, road

For completeness, the design should specify the level of maintenance necessary to keep the ment at the design serviceability level. The designer should preferably specify the required

regularity of monitoring certain pavement characteristics which would indicate the likelihood of certain distress features occurring.

Solutions to pavement design problems

Pavement design involves the study of the properties of soils along the selected road alignment, the identification and selection of construction materials for the various layers, and the determination of the thicknesses of various layers for the traffic loading and environmental conditions expected to prevail during the design life of the pavement.

Design should aim at providing adequate cover to the subgrade so that stresses at the subgrade level are low enough to prevent excessive deformation, in addition to providing pavement materials which are strong enough to resist the stresses and strains imposed by wheel loads. The complete design should also ensure that the pavement structure is adequately drained.

A road pavement consists of a number of layers, with subgrade at the bottom, and, in the case of a flexible pavement, includes sub-base, base and surfacing on top.

hrough a Flexible Pavement Structure

rigid pavement will normally consist of a concrete slab laid on a sub

Pavement design is aimed at achieving a pavement structure which is economical and comfortable to the motorist; and which minimises development of pavement distress features

holes, ravelling, fretting, crazing, distortions, etc, during the design nvironmental factors and the possibility

of staged construction. It must also aim at a desirable balance between construction, road-user

For completeness, the design should specify the level of maintenance necessary to keep the ment at the design serviceability level. The designer should preferably specify the required

regularity of monitoring certain pavement characteristics which would indicate the likelihood of

Pavement design involves the study of the properties of soils along the selected road alignment, the identification and selection of construction materials for the various layers, and the

loading and environmental

Design should aim at providing adequate cover to the subgrade so that stresses at the subgrade nt excessive deformation, in addition to providing pavement

materials which are strong enough to resist the stresses and strains imposed by wheel loads. The complete design should also ensure that the pavement structure is adequately drained.

A road pavement consists of a number of layers, with subgrade at the bottom, and, in the case of

rigid pavement will normally consist of a concrete slab laid on a sub-base or base

Page 28: FCE546 Transp Eng IIIB - March 2012 v0

Example of Section through Pavement design aims at providing a pavement structure that will serve traffic safely, conveniently and economically during the design life of that pavement.

4.2.3 Design of paved roads Many design methods have been developed to suit different climatic and trafficconditions. For historical reasons most of the design methods used in theadapted from those developed for the European temperate climate. Flexible pavement design methods can be divided broadly into empirical and analytical methods. With the development and greater availability of computers, analyticalpopularity. However, because of the amount of accumulated experience in the use of empirical and semi-empirical methods, these methods are likely to continue to be used for the foreseeable future. This section looks at design methodapplicable in his country. Concrete pavements have yet to prove to be economically attractive in the African continent. This is an area where studies are necessary to establish whether those countries whiccement and import bitumen could find concrete pavements attractive. Concrete pavements have longer design lives but they also have complicated maintenance and rehabilitation problems when defects such as cracks occur.

4.3 Functions of pavement la

When distress features appear on the road surface they lead to discomfort as well as higher vehicle operating costs. Thus, the objective of the pavement designer should be to reduce the possibility of these distress features appearing. The designer the functions of the various layers of the road pavements so that his completed design will minimise the likelihood of this happening.

4.3.1 The flexible pavement structure The strength of a flexible pavement is derived from the pavement. These layers are thus arranged in such a way that layer strength increases from the subgrade upwards, with the strongest material being placed on the surface. a) Surfacing layer

• It provides a running surface capable of carrying wheel loads without undmotorists.

• Protects the underlying layers from adverse environmental effects• Provides the necessary skid resistance for ensuring road safety characteristics w

braking becomes necessary. b) Road Base

23

hrough a Concrete (Rigid) Pavement

Pavement design aims at providing a pavement structure that will serve traffic safely, onveniently and economically during the design life of that pavement.

Many design methods have been developed to suit different climatic and trafficconditions. For historical reasons most of the design methods used in the tropical countries were adapted from those developed for the European temperate climate.

Flexible pavement design methods can be divided broadly into empirical and analytical methods. With the development and greater availability of computers, analytical methods are gaining in popularity. However, because of the amount of accumulated experience in the use of empirical

empirical methods, these methods are likely to continue to be used for the foreseeable future. This section looks at design methods which the reader may wish to compare with those

Concrete pavements have yet to prove to be economically attractive in the African continent. This is an area where studies are necessary to establish whether those countries whiccement and import bitumen could find concrete pavements attractive. Concrete pavements have longer design lives but they also have complicated maintenance and rehabilitation problems when defects such as cracks occur.

Functions of pavement layers

When distress features appear on the road surface they lead to discomfort as well as higher vehicle operating costs. Thus, the objective of the pavement designer should be to reduce the possibility of these distress features appearing. The designer will therefore need to understand the functions of the various layers of the road pavements so that his completed design will minimise the likelihood of this happening.

The flexible pavement structure

The strength of a flexible pavement is derived from the composite effect of the various layers of the pavement. These layers are thus arranged in such a way that layer strength increases from the subgrade upwards, with the strongest material being placed on the surface.

ing surface capable of carrying wheel loads without und

rotects the underlying layers from adverse environmental effects, and the necessary skid resistance for ensuring road safety characteristics w

necessary.

Pavement design aims at providing a pavement structure that will serve traffic safely,

Many design methods have been developed to suit different climatic and traffic loading tropical countries were

Flexible pavement design methods can be divided broadly into empirical and analytical methods. methods are gaining in

popularity. However, because of the amount of accumulated experience in the use of empirical empirical methods, these methods are likely to continue to be used for the foreseeable

s which the reader may wish to compare with those

Concrete pavements have yet to prove to be economically attractive in the African continent. This is an area where studies are necessary to establish whether those countries which produce cement and import bitumen could find concrete pavements attractive. Concrete pavements have longer design lives but they also have complicated maintenance and rehabilitation problems

When distress features appear on the road surface they lead to discomfort as well as higher vehicle operating costs. Thus, the objective of the pavement designer should be to reduce the

will therefore need to understand the functions of the various layers of the road pavements so that his completed design will

the composite effect of the various layers of the pavement. These layers are thus arranged in such a way that layer strength increases from

ing surface capable of carrying wheel loads without undue discomfort to

and the necessary skid resistance for ensuring road safety characteristics when

Page 29: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

24

• It is the main load-carrying structural component in a flexible pavement. • It resists and distributes stresses induced by vehicles to the underlying layers.

c) Subbase

The inclusion of the sub-base in a pavement structure normally depends on the bearing strength of the subgrade. • It helps in distributing induced stresses onto the subgrade • Also protects the base layer from adverse soil conditions that may prevail in the

subgrade. d) Subgrade

• It represents the natural or improved ground on which the pavement structure is constructed.

• Pavement design should minimise the possibility of excessive deformation in the sub-grade.

4.3.2 The Rigid pavement structure In the case of concrete roads the concrete slab is the main load-carrying element, acting as a beam. Because concrete slabs have a relatively high modulus of elasticity, small depressions in the subgrade are easily bridged over but when these depressions are large the concrete slab may crack.

4.4 Factors Affecting Pavement Design

Various environmental factors must be considered in pavement design. The loading due to traffic is considered in terms of the magnitude and repetitions of traffic loads. Thus, a pavement with an apparently good surface when the road was first opened to traffic could deteriorate under ' repeated traffic loadings if the design neglected such repeated wheel loads or if maintenance has not been properly carried out. Some of the factors governing pavement design are discussed below:

A. Traffic Factors 1. Wheel load Pavement wheel load causes stresses and strains in pavement

layers and subgrade. The tyre pressure determines the area of application

2. Impact Imperfections in surface and at joints cause additional leads due to impact.

3. Repetition of wheel: loads

Apart from single wheel load design-criterion; the repetition of loads causes plastic and elastic deformation.

4. Position of wheel load across pave-ment

The concentration of wheel load at a localised width of the pavement can cause eextra distress

B. Climatic Factors 1. Rainfall Rainfall affects pavement drainage and can thus be a significant

factor. 2.Frost Frost heave can disrupt pavement structured 3. Temperature Variation of temperature can cause stresses in the pavement. D. Road Geometry 1. Curvature Pavements on curves are subjected to extra stresses due to

cornering. Pavements at junctions are typical examples. 2. Vertical profile Pavements on grades are subjected to extra forces due to

acceleration, deceleration and braking. D. Soil and drainage

Page 30: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

25

1. Soil strength Soil type, grain-size distribution and density determine pavement design.

2. Drainage The drainage of pavement, sub-surface and from adjoining land affects soil strength and hence the pavement design.

A good design must embody all the above factors.

4.4.1 Wheel Load

(a) Magnitude of wheel load and tyre pressure The load from the wheel is transmitted to the pavement through The wheel load from a rubber tyre is distributed on a large area, depending upon the tyre pressure. The tyre pressures on commercial vehicles vary from 0.5 to 0.7 MN/m2 (70 - 100 psi). A value of 0.5 MN/m2 is typical. Tyre pressures are much more important in the design of airfield pavements. A much higher tyre pressure, in the range between 1.0 and 1.5 MN/m2 (150 - 200 psi) is used in airfield design. The spacing of axles also affects the stresses induced. Tandem axles are common on modern road transport vehicles. The AASHO Road test has shown that an 18,000 lb single axle load is equivalent in its damaging effect to a 32,000 lb tandem axle load. Similarly, a single load of 22,400 lbs had about the same damaging effect as a 40,000 lb tandem axle load. Repetition of wheel loads is very important in causing pavement distress. It is, therefore, necessary to select the design and assess the total number of repetitions of axle loads during the pavement life.

(b) Equivalent standard axle A difficulty arises in assessing the number or repetitions of loads since the traffic consists of a mixture of axle loads of varying magnitudes. Some vehicles are heavy while some are not. Some have a large number of axles. The standard procedure to deal with this problem is to express the traffic in terms of an equivalent number of standard axles. To allow for comparison of the relative damaging effect of various axle loads, a standard axle of 8.2t (18,000 lbs) was adopted following the AASHO Road Test conducted between 1959 and 1960 in the USA. Other axle loads can be converted to equivalent standard axles using the following approximate equation:

��� = � ���.�

� = � 8.2�

Where

Feq = Equivalent standard axle factor DL = measure of damage caused by an axle load L

D8.2 = measure of damage caused by an axle load 8.2t n = a factor which depends on the thickness of the pavement For the factor n, the fourth power rule applies in causing structural damage (but n = 4.5 is used in Kenya). The rule can be stated thus: The structural damage caused by an axle load varies as the fourth power-of its ratio to the standard axle load. Thus, the equivalence of a 120 kN axle is

06.580

1204

=

=F

Example 1

Page 31: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

26

The results of a one-day axle load survey of trucks on a road are tabulated in Table Eg1. Determine the number of repetitions of a standard 80 kN axle in a year. Solution. The working is facilitated in a tabular form as in Table Eg1 Table Eg1

Weight in tonnes

Mid-point in tonnes

Mid-point in kN

Number of axles (N)

(L/80)4 (L/80)

4 x N

1 - 2 1.5 15 14 0.0012 0.02 2 - 3 2.5 25 76 0.0095 0.72 3 - 4 3.5 35 77 0.0366 2.82 4 - 5 4.5 45 70 0.1001 7.01 5 - 6 5.5 55 28 0.2234 6.26 6 - 7 6.5 65 18 0.4358 7.84 7 - 8 7.5 75 10 0.7725 7.72 8 - 9 8.5 85 11 1.2744 14.02 9 - 10 9.5 95 11 1.9885 21.87 10 - 11 10.5 105 11 2.9675 32.64 11 - 12 11.5 115 12 4.2700 51.24 12 - 13 12.5 125 15 5.9605 89.41 13 - 14 13.5 135 7 8.1021 56.76 14 - 15 14.5 145 3 10.7922 32.38 15 - 16 15.5 155 1 14.0918 14.09 Total 364 344.8

Therefore, number of 80kN axles per year = 344.8 x 365 = 125,852. The numerical problem solved above demonstrates that the axle loads which are small in magnitude, say up to 3 tonnes do not have any significant effect on the structural design. Thus passenger cars and light vans do not contribute to the failure of pavements. On the contrary, extremely heavy axle loads, even though few in number, contribute to the failure. Apart from the fourth power rule, standard tables are available, which have been deduced from the AASHO Road Test as illustrated in Table 15.2 below. Table 15.2 Equivalence factors and damaging power of different axle loads

Axle Load (kg) lbs Equivalence factor

910 2000 0.0002 1810 4000 0.0025 2720 6000 0.01 3630 8000 0.03 45*0 10000 0.09 5440 12000 0.19 6350 14000 0.35 7260 16000 0.61 8160 18000 1.0 9070 20000 1.5 9980 22000 2.3 10890 24000 3.2 11790 26000 4.4 12700 28000 5.8 13610 30000 7.6 14520 32000 9.7 15420 34000 12.1 16320 36000 15.0 1723Ô 38000 18.6 18140 40000 22.8

Page 32: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

27

(c) Design traffic loading

The lateral placement of wheel loads affects design significantly. If the tendency of the traffic is to follow a certain fixed position across the pavement, the strip under the wheel loads gets severely loaded whereas the remaining portion of the pavement gets less loads. Theoretically, therefore, pavements can be made of varying thickness depending upon the lateral placement of vehicles. In actual practice, however, this is not done and a uniform pavement thickness is provided. In airport run-ways, the central one-third of paved width is principally used, and edges can be made with lesser thickness. The current Kenyan practice on the distribution of commercial traffic is as under: (i) Single carriageway roads of width less than 7m. Since traffic tends to be more channelised it is assumed that the central section of the road is used by 70 to 80% of the commercial vehicles. The sum of standard axles in both directions is used to allow for the overlap. (ii) Two-lane single carriageway roads of width greater than 7m The design should be based on the sum of standard axles in the most heavily trafficked direction (iii) Dual carriageway roads. The slow-traffic lanes will carry 80 – 90% of the commercial vehicles as long as the flow in the direction considered does not exceed 2000 commercial vehicles per day. In this case the design should be based on 80% of the sum of standard axle loads in the most heavily trafficked direction. The distribution factor may be reduced by 20 per cent for each additional lane.

(d) Design life In order to calculate the number of repetitions of the wheel loads, information is also needed on the design life and traffic growth rate. In the Kenyan practice, the design philosophy is generally guided by "stage-construction" for low volume roads and in cases where resources constraints prevail. As per this practice, the road is built in stages and its specifications made to match at each period of its life with the traffic. Arterial/primary roads are now designed for a 20 year period. Other roads may be designed for a shorter period of say 10 to 15 years, with strengthening or upgrading scheduled at the end of the design period of when traffic demand reaches a prescribed level. The rate of growth of traffic is determined from past trends or on the basis of growth of other sectors of the economy (e.g. growth of GNP, agricultural output, motor vehicles, diesel consumption etc.). The rate in Kenya on National Highways varies from 8 to 15 per cent per annum. In the absence of any detailed studies, a rate of 7'5 per cent per annum is commonly adopted. The equation used for calculating the cumulative number of standard axles is as under

�� = 365 ∗ � ∗ [�1 + r�� − 1� ]

where Ns = Cumulative number of standard axles to be catered for in the design. A = Initial traffic (commercial vpd) duly modified to account for lane distribution. r=Annual growth rate of commercial traffic. n=Design life in years. VDF=Vehicle damage factor.

Example: A two-lane two-way road is at present carrying-a traffic of 1000 commercial vehicles per day. It ia to be strengthened for the growing traffic needs. The vehicle damage factor has been found to be 3'Q The rate of growth of traffic is 10 per cent per annum. The period of

Page 33: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

28

construction is 5 years. The pavement is to be designed for 16 years after completion. Calculate the cumulative standard axles to be used ifr design. Solution. Present traffic = 1000 cv/day Traffic after completion ofstxengthening = 1000(H-0-l)£r = 1611 cv/day. Number of commercial vehicles per day in design lane? = 1611X0*75 Cumulative standard axles l^' ?65xl6UxQ-75;X3[(l+0-1)15-:l] = 01 365x 1611 x0-75x 3x 3-177 ~ 0'lxl0a

= 42'03 million standard axles (msa).

4.4.2 Climatic Factors

(a) Surface Drainage Surface drainage is another important environmental feature which the designer must incorporate in the design. Many road pavements are known to have deteriorated because of flooding which normally results from inadequate drainage. Subsurface drainage also forms part of design and normally requires that the sub-base layer of the pavement is free-draining to take into account, for example, the rise in level of the water table. Pavements suffer damage due to frost heave and loss of sub-grade support during the thawing period. When the water which is tapped in soil pores freezes under low temperature conditions, suction force builds up, causing migration of water into the freezing zone. Ice lenses grow, and they displace the pavement surface causing frost heave. When frost melts during thawing water causes the subgrade materials to become soft and lose their bearing power. Precipitation in the form of rainfalls also causes softening of sub-grade. Adequate drainage of soil and pavement layers is thus very important for pavement performance. If the design is to take account of drainage, it is necessary for the designer to understand the rainfall pattern and the catchment area involved. These aspects are considered adequately under Drainage Design.

(b) Temperature Temperature is another environmental factor important in design, especially for road materials whose strength is affected significantly by changes in temperature. In the case of flexible pavements, the performance of the bituminous layers will be a function of the pavement temperature, as strength properties such as stiffness will decrease with increase in temperature. In the case of concrete pavements, a decrease in temperature can lead to tensile stresses developing in the concrete slab. Differential stresses can also develop as a result of temperature gradients.

4.5 Flexible Pavement Design

4.5.1 Methods of Flexible Pavement Design

Methods available for the design of flexible pavements can be grouped as under: 1. Theoretical methods 2. Empirical methods using no soil strength tests 3. Empirical methods using soil strength tests.

Page 34: FCE546 Transp Eng IIIB - March 2012 v0

4.5.2 Theoretical Methods The behaviour of pavements subject to wheel load applications has been studied using fullexperiments as well as theoretically. The main advantage of theoretical analysis is the flexibility and convenience of being able to vary different parameters without having to carry out expensive full-scale experiments. However, fullmodels are applicable to the problem being considered. It is important that the models selected are tested to ensure that they are relevant and are capable of predicting the behaviour of the pavement structure under the repetitive loading which simulates the traffic loading. There have been difficulties in developing models that can accurately predict pavement behaviour under different loading and environmental conditions, and until viscoare fully developed to a level theories will remain the best alternative theoretical basis for analysing flexible pavements. A number of models based on elastic theories have been used to definflexible pavements. The theoretical approach is also known as the "analytical""structural design" approach.

(a) Boussinesq's Theory: Stresses in For a uniformly-distributed circular load on a hotheory defines the stress at given depth as follows:

The Boussinesq theory assumes that pavement material is isotropic and semielastic properties are identical in every direction thr The Poisson's ratio, µ is the ratio of the strain normal to the applied stress to the strain parallel to the applied stress. For soils it is generally around 0 5. The Modulus of Elasticity E, elastic behaviour. The vertical displacement at the surface (z=0) under the centre of the applied load is given by:

This equation is applicable for a flexible plate. For a rigid plate,

29

The behaviour of pavements subject to wheel load applications has been studied using fullexperiments as well as theoretically. The main advantage of theoretical analysis is the flexibility and convenience of being able to vary different parameters without having to carry out expensive

scale experiments. However, full-scale experiments are necessary to ensure that the selected models are applicable to the problem being considered. It is important that the models selected are tested to ensure that they are relevant and are capable of predicting the behaviour of the

under the repetitive loading which simulates the traffic loading.

There have been difficulties in developing models that can accurately predict pavement behaviour under different loading and environmental conditions, and until visco

ully developed to a level where they can be adopted by highway engineers, theories will remain the best alternative theoretical basis for analysing flexible pavements.

A number of models based on elastic theories have been used to define stresses and strains in The theoretical approach is also known as the "analytical"

"structural design" approach.

Stresses in a homogeneous mass

distributed circular load on a homogeneous layer of infinite depth, the Boussinesq theory defines the stress at given depth as follows:

The Boussinesq theory assumes that pavement material is isotropic and semielastic properties are identical in every direction throughout the material.

is the ratio of the strain normal to the applied stress to the strain parallel to the applied stress. For soils it is generally around 0 5.

E, of soil is the ratio of unit stress to the unit strain in the region of

The vertical displacement at the surface (z=0) under the centre of the applied load is given by:

This equation is applicable for a flexible plate. For a rigid plate,

The behaviour of pavements subject to wheel load applications has been studied using full-scale experiments as well as theoretically. The main advantage of theoretical analysis is the flexibility and convenience of being able to vary different parameters without having to carry out expensive

nts are necessary to ensure that the selected models are applicable to the problem being considered. It is important that the models selected are tested to ensure that they are relevant and are capable of predicting the behaviour of the

under the repetitive loading which simulates the traffic loading.

There have been difficulties in developing models that can accurately predict pavement behaviour under different loading and environmental conditions, and until visco-elastic theories

, the use of elastic theories will remain the best alternative theoretical basis for analysing flexible pavements.

e stresses and strains in The theoretical approach is also known as the "analytical" or "rational" or

mogeneous layer of infinite depth, the Boussinesq

The Boussinesq theory assumes that pavement material is isotropic and semi-infinite, and that

is the ratio of the strain normal to the applied stress to the strain parallel to

the unit strain in the region of

The vertical displacement at the surface (z=0) under the centre of the applied load is given by:

Page 35: FCE546 Transp Eng IIIB - March 2012 v0

This equation can be used forthe pavement, to a desired value. Example. Calculate the deflection at the surface of a pavement due to a wheel load of 40 kN and a tyre pressure of 0'5 MN/m2. The value of E of the pavbe uniformly equal to 20 MN/m2. Solution. Radius of contact area

Full-scale experiments have shown that the actual stresses below a sand/ asphalt base are similar to or slightly greater than thosstresses below a soil/cement base are lower than those predicted using the Boussinesq theory.The drawbacks in the simple Boussinesq's approach (i) The assumption that soil is perfeconly upto a certain limit. (ii) The pavement consists of number of layers, each with its own modulus of elasticity. Hence the assumption of one constant property for the entire mass is not justif(iii) The assumption that the load is uniformly distributed may not be correct. In spite of the drawbacks, application Boussinesq's theory was the first attempt in analytical solution to pavement design.

(b) Burmister's theory: Stresses in layered syst For this theory, it is assumed that the top layer (consisting of the pavement structure) is an infinite elastic horizontal slab overlying a semiinterface assumed to be either perfectly rough or perassumed to be uniformly-distributed over a circular area. In simplified form Burmister's twosystem can be used to compute the elastic deflection at the pavement surface using the following expression:

30

quation can be used for design of a pavement by limiting the value of ∆, the deformation of the pavement, to a desired value.

Calculate the deflection at the surface of a pavement due to a wheel load of 40 kN and a tyre pressure of 0'5 MN/m2. The value of E of the pavement and subgrade may be assumed to be uniformly equal to 20 MN/m2.

Solution. Radius of contact area a, is given by :

scale experiments have shown that the actual stresses below a sand/ asphalt base are similar to or slightly greater than those computed using the Boussinesq theory, while the actual stresses below a soil/cement base are lower than those predicted using the Boussinesq theory.The drawbacks in the simple Boussinesq's approach therefore are:

(i) The assumption that soil is perfectly elastic and homogeneous is not true. Soil may be elastic

(ii) The pavement consists of number of layers, each with its own modulus of elasticity. Hence the assumption of one constant property for the entire mass is not justified. (iii) The assumption that the load is uniformly distributed may not be correct.

In spite of the drawbacks, application Boussinesq's theory was the first attempt in analytical solution to pavement design.

: Stresses in layered systems

For this theory, it is assumed that the top layer (consisting of the pavement structure) is an infinite elastic horizontal slab overlying a semi-infinite solid of lower elastic modulus, with the interface assumed to be either perfectly rough or perfectly smooth. The surface loading is

distributed over a circular area. In simplified form Burmister's twosystem can be used to compute the elastic deflection at the pavement surface using the following

, the deformation of

Calculate the deflection at the surface of a pavement due to a wheel load of 40 kN and ement and subgrade may be assumed to

scale experiments have shown that the actual stresses below a sand/ asphalt base are e computed using the Boussinesq theory, while the actual

stresses below a soil/cement base are lower than those predicted using the Boussinesq theory.

tly elastic and homogeneous is not true. Soil may be elastic

(ii) The pavement consists of number of layers, each with its own modulus of elasticity. Hence

In spite of the drawbacks, application Boussinesq's theory was the first attempt in analytical

For this theory, it is assumed that the top layer (consisting of the pavement structure) is an in-infinite solid of lower elastic modulus, with the

fectly smooth. The surface loading is distributed over a circular area. In simplified form Burmister's two-layer

system can be used to compute the elastic deflection at the pavement surface using the following

Page 36: FCE546 Transp Eng IIIB - March 2012 v0

Burmister suggested that the displacement under the wheel load can be limited to 5flexible pavements.

(c) Other models There are a number of other models which have been used to analyse pavement structures for stresses or displacements. Some are very apthat stresses are distributed downwards from the loaded surface in a 45° cone. Meyerhoff s method of analysis is based on the Burmister's twoexpression gives the transient def

(d) Three-layered analysis With quick computational facilities now available, the analysis of three or more layers is no more a difficult task. The three-layer system can be conceived as follows : 1. Top layer, representing all the bituminous layers taken together.2. Second layer, representing the unbound road3. Third layer, representing the sub The system is shown belowpresented in the form of Tables. Table 16T will facilitate design for some values which are commonly met with.

31

ster suggested that the displacement under the wheel load can be limited to 5

There are a number of other models which have been used to analyse pavement structures for stresses or displacements. Some are very approximate, such as those based on the assumption that stresses are distributed downwards from the loaded surface in a 45° cone.

Meyerhoff s method of analysis is based on the Burmister's two-layer system and the guiding expression gives the transient deflection, as shown in the following equation:

With quick computational facilities now available, the analysis of three or more layers is no more layer system can be conceived as follows :

r, representing all the bituminous layers taken together. 2. Second layer, representing the unbound road-base and sub-base. 3. Third layer, representing the sub-grade.

below. The stresses and strains in the system were analysed and sented in the form of Tables. Table 16T will facilitate design for some values which are

ster suggested that the displacement under the wheel load can be limited to 5.0 mm for

There are a number of other models which have been used to analyse pavement structures for proximate, such as those based on the assumption

that stresses are distributed downwards from the loaded surface in a 45° cone.

layer system and the guiding

With quick computational facilities now available, the analysis of three or more layers is no more

were analysed and sented in the form of Tables. Table 16T will facilitate design for some values which are

Page 37: FCE546 Transp Eng IIIB - March 2012 v0

Fig. Three layered system. The materials in the three layers are assumed to be elastic and their mechanical property is characterized by the Modulus of Elasticity, E.be uniformly distributed over a circular contact area. The more commonly evaluated quantities are: (i) The vertical compressive strains and stresses reaching the top of the layers subgrade and unbound layers.(ii) The horizontal and vertical stresses at the bottom of the unbound granular layer.(iii) The horizontal tensile strain at the bottom of the bitu(iv) Surface deflection. The following non-dimensional parameters are used in the analysis of the system:

For design of pavements, values of E are needed. They can be determined from laboratory tests. A rough formula used for determining E is: E= 10 CBR (MN/m2) The pavement analysis proced1. Determine the wheel load and contact pressure.2. Select a pavement with a top bituminous layer of thickness base of thickness h2 3. Evaluate the Modulus of Elasticity of all the th4. Calculate the vertical and horizontal stresses and strains at the two interfaces from standard tables. 5. Compare the stress and strains with allowable values for the materials selected.6. Make adjustments if necessary.

(e) Multi-layer system of analysis With the development in computer techniques it has become possible to carry out analyses of fairly complicated mathematical models. This development has made it possible for the pavement structure to be represented as a multiproperties (the elastic or stiffness modulus and Poisson's ratio) for each layer are known.

32

The materials in the three layers are assumed to be elastic and their mechanical property is dulus of Elasticity, E. In simpler treatments, the loading is assumed to

be uniformly distributed over a circular contact area. The more commonly evaluated quantities

(i) The vertical compressive strains and stresses reaching the top of the layers subgrade and unbound layers. (ii) The horizontal and vertical stresses at the bottom of the unbound granular layer.(iii) The horizontal tensile strain at the bottom of the bituminous bound layer.

dimensional parameters are used in the analysis of the system:

For design of pavements, values of E are needed. They can be determined from laboratory tests. A rough formula used for determining E is:

The pavement analysis procedure consists of the following steps: 1. Determine the wheel load and contact pressure. 2. Select a pavement with a top bituminous layer of thickness h1 and a bottom layer of granular

3. Evaluate the Modulus of Elasticity of all the three layers. 4. Calculate the vertical and horizontal stresses and strains at the two interfaces from standard

5. Compare the stress and strains with allowable values for the materials selected.. Make adjustments if necessary.

of analysis

With the development in computer techniques it has become possible to carry out analyses of fairly complicated mathematical models. This development has made it possible for the pavement structure to be represented as a multi-layered system, but it does require that strength properties (the elastic or stiffness modulus and Poisson's ratio) for each layer are known.

The materials in the three layers are assumed to be elastic and their mechanical property is In simpler treatments, the loading is assumed to

be uniformly distributed over a circular contact area. The more commonly evaluated quantities

(i) The vertical compressive strains and stresses reaching the top of the layers representing the

(ii) The horizontal and vertical stresses at the bottom of the unbound granular layer.

dimensional parameters are used in the analysis of the system:

For design of pavements, values of E are needed. They can be determined from laboratory

and a bottom layer of granular

4. Calculate the vertical and horizontal stresses and strains at the two interfaces from standard

5. Compare the stress and strains with allowable values for the materials selected.

With the development in computer techniques it has become possible to carry out analyses of fairly complicated mathematical models. This development has made it possible for the

but it does require that strength properties (the elastic or stiffness modulus and Poisson's ratio) for each layer are known.

Page 38: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

33

Pavement loading is then introduced and analysis carried out to determine the stresses and strains at critical points in the structure. The stresses and strains obtained are compared with allowable values for the various materials used in the pavement structure. If the calculated stresses or strains are greater than these allowable values, the design is repeated using thicker layers or alternative materials. The finite-element technique, for example, can be used to carry out the structural analysis of a multi-layer system. The technique involves dividing a structure into finite elements, each of which is a simple unit whose structural behaviour can be readily analysed. The solution to the complete system is obtained by assembling the elements. While mathematical models are desirable in the design of pavement structures, there have been serious limitations in using such models, mainly for the following reasons:

• Mathematical models will have been developed on the basis of assumptions that may not apply to the problem being considered. For example, stress/strain relationships for road pavement materials are generally non-linear and are dependent on loading time as well as on temperature,

• It is also difficult to model the fatigue characteristics of road pavement materials. For example, with increased repetitions of wheel loads the permissible levels of strains and stresses decrease.

Such relationships may not have been established for the materials of the various layers. Nonetheless, experimental results have supported the use of elastic theories in pavement design and they have been found useful, especially in carrying out comparative analysis. With greater availability of powerful computers it has become more accepted practice to carry out theoretical structural analysis of flexible pavements as a design exercise, the important input data being the engineering properties for the material under various loading and environmental conditions. This underlines the need for detailed studies of the behaviour of materials commonly used for road construction under various environmental conditions, so that the necessary input data for such theoretical analyses can be adequately documented.

4.5.3 Empirical and semi-empirical pavement design methods Empirical and semi-empirical design methods have been developed on the basis of long-term pavement performance for specific traffic loading and environmental conditions. This therefore means that as long as conditions for which these methods were developed prevail, the performance of the pavement should be satisfactory. Some design methods developed for use in different countries are described here. Although some may no longer be in use, they are included due to their peculiar features which should be noted.

(a) Group Index method This empirical design method, developed in the USA, is based on the particle size distribution and plasticity of the subgrade materials. The following is the design formula:

Page 39: FCE546 Transp Eng IIIB - March 2012 v0

GI ranges between 0 and 20; GI = 0 implies very good material (high bearing capacity), and GI = 20 implies very poor material (low bearing capacity). The design chart shown in Fig. 6.25 provides the pavemencorresponding to different traffic

34

GI ranges between 0 and 20; GI = 0 implies very good material (high bearing capacity), and GI = 20 implies very poor material (low bearing capacity).

The design chart shown in Fig. 6.25 provides the pavement layer thickness for values of GI corresponding to different traffic-loading levels

GI ranges between 0 and 20; GI = 0 implies very good material (high bearing capacity), and GI =

t layer thickness for values of GI

Page 40: FCE546 Transp Eng IIIB - March 2012 v0

Curve A-thickness of selected material subCurve B-combined thickness of surface, base & selected material subCurve C-combined thickness of surface, base & selected material subCurve D-combined thickness of surface, base & selected material subCurve E - thickness of additional base which may be substituted for subCurve F — combined thickness of surface and base Curve G - combined thickness of surface and base (no subCurve H - combined thickness of surface and base (no sub

(b) CBR design method The CBR design method, as developed by the Calidetermination of the CBR value of the subgrade as well as that of the submaterials. Pavement layer thicknesses are then selected from the chart shown in basis of the relevant design wheel load.

Fig. Design curves for the CBR method.

35

thickness of selected material sub-base only combined thickness of surface, base & selected material sub-base (light traffic)

ness of surface, base & selected material sub-base (medium traffic) combined thickness of surface, base & selected material sub-base (heavy traffic) thickness of additional base which may be substituted for sub-base of curve A

combined thickness of surface and base (no sub-base, light traffic) combined thickness of surface and base (no sub-base, medium traffic) combined thickness of surface and base (no sub-base, heavy traffic)

BR design method, as developed by the California State Highway Departmentdetermination of the CBR value of the subgrade as well as that of the submaterials. Pavement layer thicknesses are then selected from the chart shown in basis of the relevant design wheel load

Fig. Design curves for the CBR method.

base (light traffic) base (medium traffic) base (heavy traffic)

base of curve A base, light traffic)

base, medium traffic) base, heavy traffic)

fornia State Highway Department, involves the determination of the CBR value of the subgrade as well as that of the sub-base and base materials. Pavement layer thicknesses are then selected from the chart shown in Fig. 6.26 on the

Page 41: FCE546 Transp Eng IIIB - March 2012 v0

This method has undergone considerable modification over the years to accommodate varying traffic-loading patterns, as well as different environmental co

(c) Road Note 29 design method* Road Note 29 (RN29) presents a guide to the structural design of pavements for new roads for UK conditions. RN29 has, however, been used in some tropical countries where traffic loading was beyond that covered by Ro Sub-base thickness is selected on the basis of subgrade CBR and the expected cumulative standard axles during the pavement design life. Base and surfacing thicknesses are determined from charts, on the basis of the type of construction materiaFigs. 6.28 and 6.29 overleaf show design charts for dense macadam, wetmacadam road-bases.

36

This method has undergone considerable modification over the years to accommodate varying loading patterns, as well as different environmental conditions.

Road Note 29 design method*

Road Note 29 (RN29) presents a guide to the structural design of pavements for new roads for UK conditions. RN29 has, however, been used in some tropical countries where traffic loading was beyond that covered by Road Note 31.

base thickness is selected on the basis of subgrade CBR and the expected cumulative standard axles during the pavement design life. Base and surfacing thicknesses are determined from charts, on the basis of the type of construction material and the design life of the pavement. Figs. 6.28 and 6.29 overleaf show design charts for dense macadam, wet-mix and dry

This method has undergone considerable modification over the years to accommodate varying

Road Note 29 (RN29) presents a guide to the structural design of pavements for new roads for UK conditions. RN29 has, however, been used in some tropical countries where traffic loading

base thickness is selected on the basis of subgrade CBR and the expected cumulative standard axles during the pavement design life. Base and surfacing thicknesses are determined

l and the design life of the pavement. mix and dry-bound

Page 42: FCE546 Transp Eng IIIB - March 2012 v0

* RN29 has been superseded by TRRL report No. LR1132 which is a probabilistic design method based on empirical results, extended to provide for higher axle loads using mechanistic methods.

(d) Road Note 31 design method* Road Note 31 (RN31), developed by TRRL for developing countries, presents a guide to the structural design of bitumenedition of RN31 considers the traffic loading in terms of the cumulative number of standard axles

37

* RN29 has been superseded by TRRL report No. LR1132 which is a probabilistic design method mpirical results, extended to provide for higher axle loads using mechanistic methods.

Road Note 31 design method*

Road Note 31 (RN31), developed by TRRL for developing countries, presents a guide to the structural design of bitumen-surfaced roads in tropical and sub-tropical countries (13). The third edition of RN31 considers the traffic loading in terms of the cumulative number of standard axles

* RN29 has been superseded by TRRL report No. LR1132 which is a probabilistic design method

mpirical results, extended to provide for higher axle loads using mechanistic methods.

Road Note 31 (RN31), developed by TRRL for developing countries, presents a guide to the tropical countries (13). The third

edition of RN31 considers the traffic loading in terms of the cumulative number of standard axles

Page 43: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

38

on the basis of which the type of surfacing, and thicknesses of the base and sub-base, are selected. Selection of the sub-base thickness is also based on the bearing strength of the subgrade, as is shown below. RN31 KEY TO STRUCTURAL CATALOGUE

Page 44: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

39

Page 45: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

40

RN31 TABLE 10.1 Summary of material requirements for the design charts CHART NO

SURFACING ROADBASE REFER TO CHAPTERS

1 Double surface dressing T1-T4 use GB1.GB2 or GB3 T5 use GB1 ,A or GB1 ,B T6 must be GB1.A

6 and 9

2 Double surface dressing T1-T4useGB1, GB2 or GB3 T5 use GB1 T6,T7,T8 use GB1.A

6. 7 and 8

3 'Flexible' asphalt T1-T4 use GB1 or GB2 T5 use GB1 T6 use GB1.A

6 and 8

4 'Flexible' asphalt T1-T4 use GB1 or GB2 T5 use GB1 T6-T8 use GB1.A

6, 7 and 8

5 Wearing course and basecourse GB1.A 6 and 8 6 Wearing course and basecourse GB1 or GB2 6, 7 and 8 7 High quality single seal or double

seal for T4. 'Flexible' asphalt for T5-T8

RB1, RB2 or RB3 8 and 9

8 Double surface dressing CB1, CB2 7 and 9

Page 46: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

41

RN31 CHART 1

Page 47: FCE546 Transp Eng IIIB - March 2012 v0

(e) The Kenya Pavement Design

Pavement design in Kenya has undergone considerable development since ruledesign in the 1940s and 1950s. During the 1960s most major roads were designed on the basis of the earlier editions for RN31 and RN29. Then, a road design manual adopted in 1970 required the designer to determine traffic loading on the basis of the number of heavexpected per 24-hour day five years after the road was opened to traffic. The latest design procedure, adopted in 1981, requires the designer to determine the subgrade quality, in terms of the CBR and traffic loading, during the design life of pavement, in terms of cumulative standard axles as determined by RN29. The pavement structure is then selected from a catalogue of structures for construction. It will be noted that the Kenyan design procedure adoptof using a catalogue of pavement structures unlike RN29, which uses charts. The reader may wish to note that the differences between using the catalogues and using the charts would be insignificant for given values of traffic loading,materials. The following four basic steps are involved.

42

esign Method

Pavement design in Kenya has undergone considerable development since rulein the 1940s and 1950s. During the 1960s most major roads were designed on the

basis of the earlier editions for RN31 and RN29. Then, a road design manual adopted in 1970 required the designer to determine traffic loading on the basis of the number of heav

hour day five years after the road was opened to traffic.

The latest design procedure, adopted in 1981, requires the designer to determine the quality, in terms of the CBR and traffic loading, during the design life of

pavement, in terms of cumulative standard axles as determined by RN29. The pavement from a catalogue of structures depending on the materials available

for construction. It will be noted that the Kenyan design procedure adopts the . French method of using a catalogue of pavement structures unlike RN29, which uses charts. The reader may wish to note that the differences between using the catalogues and using the charts would be insignificant for given values of traffic loading, subgrade strength and pavement construction materials. The following four basic steps are involved.

Pavement design in Kenya has undergone considerable development since rule-of-thumb in the 1940s and 1950s. During the 1960s most major roads were designed on the

basis of the earlier editions for RN31 and RN29. Then, a road design manual adopted in 1970 required the designer to determine traffic loading on the basis of the number of heavy vehicles

The latest design procedure, adopted in 1981, requires the designer to determine the quality, in terms of the CBR and traffic loading, during the design life of the

pavement, in terms of cumulative standard axles as determined by RN29. The pavement depending on the materials available

s the . French method of using a catalogue of pavement structures unlike RN29, which uses charts. The reader may wish to note that the differences between using the catalogues and using the charts would be

subgrade strength and pavement construction

Page 48: FCE546 Transp Eng IIIB - March 2012 v0

43

Page 49: FCE546 Transp Eng IIIB - March 2012 v0

Analysis and classification of traffic loading. The classification of traffic loading is as follows:Evaluation of alignment soils and classififollows: [TcJUk- Ô^As-^-i-JSelection of construction materials which meet the specifications shown in Tables 5.1 to 5.3. Traffic loading Equivalent standard axles

44

Analysis and classification of traffic loading. The classification of traffic loading is as follows:Evaluation of alignment soils and classification of the subgrade, on the basis of the CBR as

J Selection of construction materials which meet the specifications shown in Tables 5.1 to 5.3.

Equivalent standard axles

Analysis and classification of traffic loading. The classification of traffic loading is as follows: cation of the subgrade, on the basis of the CBR as

Selection of construction materials which meet the specifications shown in Tables 5.1 to 5.3.

Page 50: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

45

class x 106 Tl 25-60 T2 10 - 25 T3 3-10 T4 1 - 3 T5 0.25 - 1 Subgrade class CBR

(per cent) SI 2-5 S2 5-10 S3 7-13 S4 10 - 18 S5 15 - 30 S6 > 30 • Selection of the pavement structure from a catalogue of structures. (-eg • fn\ t 6 f»C'*v Interpretation, of solutions It is important for the designer to understand the implications of his choice of design method. If the design method is empirical he must guard against extrapolation by the introduction of loading and environmental conditions which did not prevail during the development of the method. The designer must also have an appreciation of the accuracy involved and its implications in terms of construction costs and maintenance costs.

(f) CEBTP pavement design method for tropical countries (Centre Experimental de Recherches et d'Etudes du Bâtiment et des Travaux Publics, Manuel de dimensionnement de chaussées pour les pays tropicaux Secretariat d'Etat aux Affaires Etrangères). This is a common design method in French-speaking tropical countries (14). The subgrade strength is assessed on the basis of the CBR, and traffic is categorised into four classes. It is essentially a modification of the original CBR design method. Design involves selection of a pavement structure from a list of four basic pavements.

(g) AASHTO design guide This guide was developed from the results of the AASHTO Road Test and is suitable for use in the USA. However, it has been widely used in tropical countries. Subgrade strength is defined in terms of the soil support value, while pavement thickness is expressed in terms of the structural number (SN) ranging from 1.0 to 6.0. Traffic loading is expressed in terms of cumulative standard axles during the design life of the pavement, or in terms of daily axle applications, as shown in Fig. 6.31 (15).

Page 51: FCE546 Transp Eng IIIB - March 2012 v0

Thus, given the soil support value (which could be defined in terms of the^G©R_or the group index of the alignment soil) and the trafficaxles), one obtains a structural number, SN, as shown in Fig. 6.31. By apfactor a new weighted structural number, SN' is obtained. This new structural number is used in the design equation shown in Fig. 6.31. The coefficients of one location to another. The designer is required toand sub-base which satisfy the design equation, as well as the econconstraints. For example, for weighted structural number SN = 2.7, the folpossible solution, (i) If the pavemen

(h) Other methods There are other methods which can be included in this category of empirical and semiempirical design procedures and it is not intended to cover them exhaustively here. However, mention should be made of: the shell pavement design method which has been developed over the years to incorporate the effect of temperature on bituminous materials; and the

46

iven the soil support value (which could be defined in terms of the^G©R_or the group index of the alignment soil) and the traffic-loading value (in terms of equivalent daily standard axles), one obtains a structural number, SN, as shown in Fig. 6.31. By applying a regional factor a new weighted structural number, SN' is obtained. This new structural number is used in the design equation shown in Fig. 6.31. The coefficients of Di, D2 and D3 could vary from one location to another. The designer is required to select the thicknesses of surfacing, base

base which satisfy the design equation, as well as the economic and other constraints. For example, for weighted structural number SN = 2.7, the following could be a possible solution, (i) If the pavement were to be made up of one layer (cheap pavement), then:

There are other methods which can be included in this category of empirical and semiempirical design procedures and it is not intended to cover them exhaustively here. However,

ention should be made of: the shell pavement design method which has been developed over the years to incorporate the effect of temperature on bituminous materials; and the

iven the soil support value (which could be defined in terms of the^G©R_or the group loading value (in terms of equivalent daily standard

plying a regional factor a new weighted structural number, SN' is obtained. This new structural number is used

and D3 could vary from select the thicknesses of surfacing, base

omic and other lowing could be a

t were to be made up of one layer (cheap pavement), then:

There are other methods which can be included in this category of empirical and semi-empirical design procedures and it is not intended to cover them exhaustively here. However,

ention should be made of: the shell pavement design method which has been developed over the years to incorporate the effect of temperature on bituminous materials; and the

Page 52: FCE546 Transp Eng IIIB - March 2012 v0

Hveem stabilometer design method in which primary soil strength is deterHveem stabilometer (a closed tridetermined on the basis of a cohesiotraffic index.

4.6 Design of concrete pavements

The concrete pavement slab functions as a beam on an elastic subgrade so that the deflection of the pavement slab due to applied wheel loads is accompanied by an equal deformation of the subgrade. Temperature changes cause concrete slabs to expand and contract, as stresses are set up (when this contraction or expansion is prevented). Movement of the slab could be entirely or partially prevented by friction between the slab and the subgrade, thereby leading to tensile stresses developing in the slabproviding a concrete section that is capable of resisting the stresses developed; if necessary reinforcement may be provided. Joints are provided in concrete pavements for a variety of reasons (17). The cont(see the example shown in Fig. 6.37) for example, are provided to relieve tensile stresses resulting from contraction and warping of the concrete slab. Dowel bars are used for load transfer across the joints.

Expansion joints (see the exbreaks in the concrete slab, to allow for expansion. Again, dowel bars are used for load transfer across the joints. Construction joints (see the example shown in Fig. 6.37) mark the end of a dwork and are normally of the butt type with dowel bars provided for load transfer. Hinge and warping joints (see the example shown in Fig. 6.37) are used to control cracking along the centreline of the concrete pavement slab. Pumping and blowing are major problems associated with concrete pavements. Pumping is the ejection of water and subgrade soil through joints, cracks and along the edges of pavements, as a result of downward slab movement caused by the passage of heavy axle loads over the pavement slab. Extensive deformation of the contransverse cracking by cantilever action. Blowing is a form of pumping, associated with the

47

Hveem stabilometer design method in which primary soil strength is deter- Hveem stabilometer (a closed tri-axial cell), the flexural strength of the paving materials is determined on the basis of a cohesio-meter test, and traffic loading is expressed in terms of a

Design of concrete pavements

te pavement slab functions as a beam on an elastic subgrade so that the deflection of the pavement slab due to applied wheel loads is accompanied by an equal deformation of

Temperature changes cause concrete slabs to expand and contract, as a result of which stresses are set up (when this contraction or expansion is prevented). Movement of the slab could be entirely or partially prevented by friction between the slab and the subgrade, thereby leading to tensile stresses developing in the slab with a fall in temperature. The design aims at providing a concrete section that is capable of resisting the stresses developed; if necessary reinforcement may be provided.

Joints are provided in concrete pavements for a variety of reasons (17). The cont(see the example shown in Fig. 6.37) for example, are provided to relieve tensile stresses resulting from contraction and warping of the concrete slab. Dowel bars are used for load

Expansion joints (see the example shown in Fig. 6.37.) are provided, in the form of clear breaks in the concrete slab, to allow for expansion. Again, dowel bars are used for load

Construction joints (see the example shown in Fig. 6.37) mark the end of a day's construction work and are normally of the butt type with dowel bars provided for load transfer.

Hinge and warping joints (see the example shown in Fig. 6.37) are used to control cracking along the centreline of the concrete pavement slab.

d blowing are major problems associated with concrete pavements. Pumping is the ejection of water and subgrade soil through joints, cracks and along the edges of pavements, as a result of downward slab movement caused by the passage of heavy axle

ment slab. Extensive deformation of the concrete slab leads to transverse cracking by cantilever action. Blowing is a form of pumping, associated with the

mined using a axial cell), the flexural strength of the paving materials is

meter test, and traffic loading is expressed in terms of a

te pavement slab functions as a beam on an elastic subgrade so that the deflection of the pavement slab due to applied wheel loads is accompanied by an equal deformation of

a result of which stresses are set up (when this contraction or expansion is prevented). Movement of the slab could be entirely or partially prevented by friction between the slab and the subgrade, thereby

with a fall in temperature. The design aims at providing a concrete section that is capable of resisting the stresses developed; if necessary

Joints are provided in concrete pavements for a variety of reasons (17). The contraction joints (see the example shown in Fig. 6.37) for example, are provided to relieve tensile stresses resulting from contraction and warping of the concrete slab. Dowel bars are used for load

ample shown in Fig. 6.37.) are provided, in the form of clear breaks in the concrete slab, to allow for expansion. Again, dowel bars are used for load

ay's construction work and are normally of the butt type with dowel bars provided for load transfer.

Hinge and warping joints (see the example shown in Fig. 6.37) are used to control cracking

d blowing are major problems associated with concrete pavements. Pumping is the ejection of water and subgrade soil through joints, cracks and along the edges of pavements, as a result of downward slab movement caused by the passage of heavy axle

crete slab leads to transverse cracking by cantilever action. Blowing is a form of pumping, associated with the

Page 53: FCE546 Transp Eng IIIB - March 2012 v0

base or sub-base under the concrete slab, which leads to longitudinal cracking. Mudand joint sealing are used to correct these defects.

4.7 Design of unpaved roads

The development of rural areas in many developing countries will continue to depend on road transportation for the foreseeable future. sometimes earth) standard due to

4.7.1 Design of gravel roads The design of a gravel wearing course is generally based on the bearing capacity of the subgrade and the expected traffic volume. The the total thickness of the wearing course for new gravel roads in Kenva (16):

Table 6.21 Minimum gravel wearing course thickness Dx (mm)

Subgrade strength CBR (%)

Initial daily commercial vehicles (

< 15

2- 5 350 5-10 225 7-13 175 10-18 150 15-30 125 > 30 -

Source: Road Design Manual, Kenya, reference (16). In general, shoulders should pwearing course and a cross fall of 4 per cent should normally be provided.

48

base under the concrete slab, which leads to longitudinal cracking. Mudand joint sealing are used to correct these defects.

Design of unpaved roads

The development of rural areas in many developing countries will continue to depend on road transportation for the foreseeable future. Rural roads are generally constructed to gravel (and

due to limited funds and low traffic volumes,.

The design of a gravel wearing course is generally based on the bearing capacity of the subgrade and the expected traffic volume. The following equation has been used to determine the total thickness of the wearing course for new gravel roads in Kenva (16):

Table 6.21 Minimum gravel wearing course thickness Dx (mm)

Initial daily commercial vehicles (both directions)

15-50 50-150 150- 500

425 500 575 275 325 375 225 250 275 175 200 225 150 175 200 - -

Road Design Manual, Kenya, reference (16).

In general, shoulders should preferably be made up of the same material as the gravel wearing course and a cross fall of 4 per cent should normally be provided.

base under the concrete slab, which leads to longitudinal cracking. Mud-jacking

The development of rural areas in many developing countries will continue to depend on road tructed to gravel (and

The design of a gravel wearing course is generally based on the bearing capacity of the following equation has been used to determine

referably be made up of the same material as the gravel

Page 54: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

49

The design should consider the possibility of upgrading the gravel road to a paved road; for this the alignment costs should be carefully weighed against the possibility of incurring further costs in re-alignment during upgrading.

4.7.2 Design of earth roads Earth roads are generally formed of natural materials found along the road alignment or adjacent to the road line. Earth roads have become very important in rural areas as they help to improve the way of life for the farming communities, by providing access to markets, schools, health centres, water supply and administrative centres. In many cases, they are constructed by the communities themselves and the results, as might be expected, are poor. They are supposed to link up with existing classified gravel or bitumen roads. The design of an earth road should aim at providing all-weather access as far as is practical, at the lowest cost possible. Labour-intensive construction techniques are generally used. The road alignment should avoid areas requiring major drainage structures and the cross-section should ensure rapid discharge of surface run-off.

Page 55: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

50

5 SOIL STABILISATION

5.1 Definition

Soil stabilization is a process of treating a soil in such a manner as to maintain, alter or improve the performance of the soil as a construction material. The changes in the soil properties are brought about either by the incorporation of additives or by mechanical blending of soil types.

5.2 Purpose of Soil Stabilization

Soil-stabilization is practised in road construction with one or more of the following objectives:

i. To improve the strength of sub-bases, bases and, in the case of low-cost roads, surface courses.

ii. To bring about economy in the cost of a road. iii. To make use of locally available soils and other materials which are otherwise inferior. iv. To eliminate or improve certain undesirable properties of soils, such as excessive

swelling or shrinkage, high plasticity, difficulty in compacting etc. v. To control dust. vi. To stabilise the moisture in the soil, so as to facilitate compaction and increase load-

bearing property. vii. To reduce frost susceptibility. viii. To reduce compressibility and thereby settlements. ix. To alter permeability characteristics.

5.3 Types of Stabilisation Techniques

Broadly, soil-stabilization takes the following forms: (i) Mechanical stabilization, where by the stability of the soil is increased by blending the available soil with imported soil or aggregate so as to obtain a desired particle-size distribution, and by compacting the mixture to a desired density. Compacting a soil at an appropriate moisture content is itself a form of mechanical stabilisation. (ii) Stabilisation by additives such as lime, cement, sodium silicate, calcium chloride, bituminous materials and resinous materials. Chemical stabilisation is the general term implying the use of chemicals for bringing about stabilisation.

5.4 Mechanical Stabilisation

5.4.1 Principles

Mechanical stabilisation is achieved by intelligently blending locally occurring materials so as to obtain a desired grading. (Compaction of soil is also a form of mechanical stabilisation.) It is well-known that a dense, well-graded mass offers the maximum resistance to lateral displacement under a load. If the well-graded material is compacted, densification of the mass takes place. The mechanical strength of the mass is due to the internal friction and the cohesion.

Page 56: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

51

Internal friction is supplied by the coarser particles (gravels, sands and silts) whereas cohesion is due to the clay fraction.

5.4.2 Applications The application of the principle of mechanical stabilisation is evident in the following specifications: (i) Soil-aggregate mixtures (ii) Sand-clay roads (iii) Sand-gravel mixtures (iv) Stabilisation of soil with soft aggregates.

5.4.3 Soil-aggregate mixtures As the name itself implies, a soil-aggregate mixture is a material in which soil and aggregate particles are mixed in suitable proportions such that the resulting mixture conforms to a dense and stable mix when properly compacted. This technique is used for the construction of base courses, and in the case of low-traffic roads for the surface course as well. The particle-size distribution of the mixture is a major factor determining the stability. The aggregates should be so graded that a grain-to-grain contact exists, producing internal friction. For a high value of density to result, the grain-size distribution should follow the Fuller's curve given by the equation:

! = 100 #$�%

where p = percentage passing any sieve

d = aperture of the sieve in question D = the maximum size of the aggregate n = exponential, whose value can be taken as 0.5.

Typical specifications for sub-base/base courses are given in the table below Table 17.1 Specifications for soil-aggregate sub-base courses

Sieve Designation Per cent by weight passing the sieve for a nominal maximum size of: 80 mm 40 mm 20 mm

80 mm 100 - - 40 mm 80-100 100 - 20 mm 60-80 80-100 100 10 mm 45-65 55-80 80-100 4.75 mm 30-50 40-60 50-75 2.36 mm - 30-50 35-60 600 micron 10-30 15-30 15-35 75 micron 0-10 0-10 0-10 Notes :

1. Not less than 10 per cent should be retained between each pair of successive sieves specified for use excepting the largest pair.

2. The material passing 425 micron sieve shall have liquid limit and plasticity index of not more than 25 per cent and 6 per cent respectively.

3. Some authorities specify that the percentage passing 75 micron sieve should be 5-15, so as to supply cohesion

It may be noted from the above Table that the plasticity of the binder is also an important factor contributing to the satisfactory performance of the specification. A maximum value of 25 for L.L. and 6 for P.I. is usually specified for sub-base mixtures. For surfacing mixtures, a slight relaxation

Page 57: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

52

is allowed so as to provide greater cohesion and help offset the moisture lost by evaporation. This L.L. should not exceed 35. The construction is accomplished in lift thickness of 100-200 mm and compaction to 100 per cent of the laboratory maximum density is sought after. The moisture at the time of compaction generally is 1 per cent above to 1 per cent below the OMC. When used as a surfacing course, which is to be maintained for some time without bituminous surface treatment, it is necessary to specify that a minimum of 8 per cent pass the 75 micron sieve.

5.4.4 Sand-clay roads A sand-clay road is composed of a favourable mixture of clay, silt and sand. If some coarser materials such as gravel are also present, the mixture will perform still better. In order to get over the undesirable characteristics of clay, the blending of clay with a proportion of sand can alter the properties significantly. If sand is available at economical leads, the specification can be very cheap. Sand-clay mixtures are constructed to a thickness of about 200 mm and used as a surfacing course for low-traffic roads. The mixture can also serve as a good sub-base and base. When used as a subbase, the mix should have a minimum soaked CBR of 20, whereas when used as a base for heavily trafficked roads, the minimum soaked CBR should be normally 80. A somewhat smaller value is permissible for low-traffic roads. The gradings given in Table below are recommended. Table 172 Specifications for sand-clay mixtures

Sieve Designation

AASHO Indian Road Congress (IRC)

25 mm 100 - - 10 mm - 100 - 4'75 mm 70-100 80-100 100 2'36 mm - 50-80 80-100 200 mm 55- 100 - - 1-18 mm - 40-65 50-80 600 micron - - 30-60 425 micron 30- 70 - - 300 micron - 20-40 20-45 75 micron 8-25 10-25 10-25

The requirements of liquid limit and plasticity index given under soil-aggregate mixtures apply to sand-clay roads also. The mixture is compacted to 100 per cent of the miximum dry density at a moisture content of 1 per cent above to 2 per cent below the O.M.C.

5.4.5 Sand-gravel mixtures Gravel is a general term which denotes a meterial having predominantly coarse particles 2.0-60 mm dia, and resulting from disintegration of rock. Gravel occurs as a natural deposit in a river bed if the disintegrated rock particles are transported by river. In this case, the particles are often rounded. The material also occurs in pits, when it is found mixed with soil and sand. In tropical countries, the material obtained from the disintegration of laterite is extensively found in a natural admixture or clay and coarse fractions and is known as lateritic gravel (or murram). Often, the natural murram contains too much of plastic material which lowers its value as a road pavement material. A suitable admixture of moorum with sand will not only result in a better gradation and increased strength, but also reduce the plasticity.

Page 58: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

53

5.4.6 Stabilisation of soil with soft aggregates There are many areas with an abundant supply of natural soft aggregates, including gravel, murram and kankar (an impure form of limestone mixed with clay and earth). A method of stabilisation of soil using these soft aggregates was introduced successfully in India and is known as Mehra's method. The principle behind this method is to embed in a soil motar coarse aggregates roughly one-third of the total volume. The aggregates are normally often aggregates such as over-burnt brick ballast, kankar, moorum or laterite. Because of the larger proportion of the soil mortar, the resulting material has no grain-to-grain contact in the coarse aggregates, which merely float in the soil. Each aggregate is thus enveloped all round in the compacted soil and is thus protected from the crushing effect of traffic. This enables the Hsation. soft aggregate to retain its strength and angular character for an indefinite period (Ref. 9). About 10 percent of the coarse aggregates which are collected are not mixed with the soil, but are saved and spread on the layer of the soil-aggregate mixture before rolling.

5.5 The soil is required to have a P.I. value 8—11 and a minimum sand content of 33 per cent (Ref 10). The soft aggregates should have a maximum Wet Aggregate Impact value of 50 per cent when used as a sub-base, 40 per cent when used as a base-course with bituminous surfacing and 30 per cent when used as a surfacing course (Ref. 8).

The stabilised layer is suitable as a surfacing course without any bituminous treatment for very light traffic (about 50 tonnes per day). For light traffic (about 20u tonnes per day), a light bituminous surfacing is needed. For medium traffic (about 500 tonnes per day), a thin stone grafting (about 25 mm thick) is given on the soil-soft aggregate mixture while compacting, and a thin bituminous surfacing provided. For areas with a high rainfall, it is necessary to provide two coats of surface dressing. The soil aggregate mixture is compacted at optimum moisture content.

5.5.1 17'4'7. Combining materials to obtain required gradation In dealing with mechanical stabilisation it is often found necessary to combine different materials to obtain the finally desired gradation. Rothfuch's graphical method is a reasonably quick, accurate and simple method, and is used for design of cement concrete mixes, bituminous mixes and granular mixes. The method consists of the following stages :

Fig. 17*3. Rothfuch's graphical method of combining aggregates.

Page 59: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

54

(i) Using the desired aggregate gradation, a distribution curve is plotted with the percentage

passing as linear ordinates and the sieve sizes on the horizontal scale. In order to mark the sieve sizes on the horizontal scale, an inclined line (OA in Fig. 173) is first of all drawn. By marking the known percentages passing each size sieve on this line and dropping vertically the intersection point to the horizontal axis, the location of the sieve size on the horizontal axis is determined.

(ii) The particle size distribution of the given materials to be blended are plotted on this scale. The distribution curves will not generally be straight lines (Lines OB, ODE and OF OA in Fig. 17*3).

(iii) With the aid of a transparent straight edge, straight lines are drawn representing the particle size distribution in the best possible manner (Lines HJ and KA). This means that the areas enclosed between the distribution curve and the straight line should be minimum and are balanced about the line.

(iv) The opposite ends of these lines are joined together tLineS BR and JK). (v) The proportions for blending can be read off from the points where the joining lines cross

the straight line representing the mixture. These points are L and M. The method is illustrated by the following example. Cols. 1 and 2 in the Table 17'3 give the gradation limits for various sieve sizes of a stabilised mixture. Three materials are available, whose gradations are given in Cols. 4, 5 and 6. Work out the blending proportion. Solution. Col. 3 in Table 173 gives the average percentage passing. Table |7 3 Blending of materials Percentage passing

Sieve Design - ation U)

Required Grada-tion limits (2)

Materials available

47%A 49%B 4%G (7)

Si a c B 9 *q (3)

Coarse Aggre-gates (A) (4)

Sand (By (5)

Local Soil (G) (6)

40 mm 100 100 100 100 20 mm 80—100 90 75 . 88 10 mm 55—80 67-5 20 62 4*75 mm 40—60 50 8 100 53 2"36 mm 30—50 40 6 80 42 600 mm 15—30 22'2 2 40 21 75 micron 0—10 5 Nil 2 100 5 A reference to Fig. 17'3 will illustrate the stages involved In the graphical method. The percentages of various materials as scaled out are : Material (A) : 49% Material (B): 49% Material (C): 4%. The gradation of the final mixture on the basis of the above blending is indicated in Col. 7 of the Table. Another graphical method in which 3 materials can be blended is by means of a triangular chart. The use of this method is illustrated by an example in which three materials. A, B and 0 are to be blended to obtain a gradation shown in Cols. 2 and 3 of Table 174. Cols. 4, 5 and 6 give the gradation of the three individual materials.

Page 60: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

55

Table 17 4 Blending of Materials Sieve Design-ation

Percentage passing Gradation Limits Average Material A

Material (B) Material 0

1 2 3 4 5 6 20 mm 100 100 100 - 10 mm 80—100 90 80 - 4"75 mm 50—75 63 25 100 - 2'36 mm 35—60 48 10 80 - 600 mm 15—35 25 5 40 - 75 micron 0—10 5 Nil Nil 100 From the Table 17*4, the gravel, sand and silt-clay fractions of the three materials are as below.

Material Percentage of Qravel Sand Silt-clay

A 90 10 0 B 20 80 0 C 0 0 100 In the triangular chart, Fig. 17"4, each side of the equilateral triangle represents percentages (0—100) of the three materials, viz., gravel, sand and silt-clay.

Fig. 17*4. Triangular blending chart. The gradation limits of the desired mix is composed of the three fractions as follows: Gravel 40 - 65 Sand 35 - 50 Silt-clay 0 - 10 Plotting these on the triangular chart, one obtains a hatched parallelogram which will contain all combinations of the three materials which will fulfil the gradation requirements. A point "D" is selected inside this parallelogram about its centre.

Page 61: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

56

Point "A" represents the material "A", point "B" represents material "B" and point "G" represents material "O". The triangle ABG represents all possible combinations of the three materials. Join O to D and produce CD to meet AB at E. The following ratio of lengths is then determined by scaling off: AE 7B =0-5 EB AB =05

Page 62: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

57

Table 17'5 Blending of Materials Sieve designation

Gradation limits

Percentage passing

Total Colt. 4+6+8

(1)

(2)

(9)

20 mm

100

100

10 mm

80—100

91

4'75 mm

50—75

65

2*36 mm

35—60

49

600 mm

15—35

28

7 6

Page 63: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

58

5 mic ron

It is seen that the final grading as given in Col. 9, satisfies the limits given in Col. 2 r 174 7'3. In some cases, it is possible to arrive at the blending proportion by simple calculations. As an example, consider the gradation desired in Table 176. Col. 2 gives the desired gradation limits and Col. 3 the mean. The gradation of Materials A, B and G are given in Cols, 4, 5 and 6. By examination it Is seen that material retained on 4 75 mm size sieve is to be fully supplied by Material A. The quantity of such material in Material A is 100—23=77 per cent, whereas the desired quantitiy in the final mix is 50 per cent. Table 176 Sieve desig-nation

Percentage passing

Gradation limits

Mean

Material U)

Material (B)

Material

0) (2) (3)

(4) (5) (6)

40 mm

100

100

100

20 mm

80-100

90

82

10 mm

55—80

68

48

475 mm

40-60

50

23 100

2"36 mm

30—50

40

11 91

1-18 mm

- - 6 34 100

425 micron

15-30

23

3 10 84

150 micron

- - 1 3 59

75 micron

5—15

10

0 2 36

Therefore, the required proportion of Materia! A in the final The combined proportion of B and 0 will be It is seen that as regards material passing 425 micron sieve, Material A forming 65 per cent of the total mix, can supply only : But the requirement being 23 percent, 21 per cent will have to be supplied by Materials B and O. The combined proportion -of Materials B and 0 in the final mixture being 35 per cent, it is

Page 64: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

59

obvious that these two materials must be blendeded suitably. Let b and c denote the percentage of Material B and C respectively. 6+e=35 10 , 84 100+ex Too 0-106+0"84c=21 But 6+e=35 Solving the simultaneous equations, 6=11 e=24 With the above blending proportion, Jhe resulting gradation is tabulated below Table 17'7. Table 177 /Steve designation

Grada-tion limits

Total cols. 4 + 6+8

(D

(2)

(9)

40 mm

100

100

20 mm

80—100

88

10 mm

55—80

66

4'75 mm

40—60

50

2'36 mm

30—50

41

1*18 mm

— 32

425

15—

23

Page 65: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

60

mic

30

ron

150 mic-

- 15

ron

75 mic-

5-15

9

ron

It is seen that the gradation in Col. 9 satisfies the requirements in Col. 2.

Page 66: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

61

17 4'7*4. When only 2 materials are to be combined, a simple graphical method described below can be followed : It is required to blend sand (A) and silt-clay 1(B) to obtain the following gradation : Sieve designation

Percentage passing

Material (A)

Material (B)

4'75 mm 100 100 2'36 mm 80—

100 91

1*18 mm 50—80

34 100

425 micron 30-60 10 84 300 micron 20-45 3 59 75 microh 10—

25 2 36

Steps : (i) On a convenient size of rectangular graph, scale off top linearly from 100 to 0 as percentage of A in mix. Scale off the base correspondingly from 0 to 100 as percentage of B in mix. Scale off the vertical ordinate from 100 at top to 0 at bottom on the left and 0 at top to 100 at bottom on the right, representing the percentages passing sieve (Fig. 17'5). Fig. 17-5. Graphical method of combining two aggregates. (it) On the left ordinate mark off percentage passing the given sieves for material A. On the right ordinate mark off percentages passing the given sieves for material B. (iii) For each sieve size, connect by a straight line the points, representing the respective percentages passing each material. The intersection of each sieve line by any vertical line will define the combined grading of the two materials mixed in the proportions shown in the top and bottom horizontal scales. (»») On each sieve line, the specified percentage passing limits are marked by small circles. The intercept lying between the crosses represents for any particular sieve line the range of proportion that will comply the specification. (t>) If mixtures within the specification limits are possible, vertical lines can be erected such that their intersection points with all sieve lines lie on the acceptable intercepts. The hightest and the lowest percentages of either material at which this can be done represent the limiting mixtures which conform to the specifications. The mid-point between the limiting mixtures will usually provide the best mixture. (vi) In Fig. 17 5, the limits indicated are (i) 68 per cent A, 32 per cent B and (it) 26 per cent A, 74 per cent B. In practice, the acceptable properties would lie in the range of A : B=2 : 1 to A : B=l : 3. Probably a ratio of A : B= 1 : 1 would be the best. 17'4'8. Combining for plasticity The specifications for mixtures usually give an upper limit for the L.L. and P.1 values. While the individual materials may have unacceptable L.L. and P.l. values, the correct blend of materials can be arrived at to result in acceptable L.L. and P.I. values. For this purpose, some formulae will be useful. Consider materials ^ and B being combined to form a mixture O.

Page 67: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

62

Altenatively, if the L.L. and P.I. of the constituent materials are known, and the percentage of material A in the mixture has been selected previously to meet the particle size distribution criteria, the values of L, and I, can be determined from the following formulae :

The following examples illustrate the use of these formulae : Problem 17*1. It is proposed to construct a sand clay road conforming to the following gradation specifications : Table 17 8 Sieve designation (I)

Percentage Gradation Limits (2)

Passing Mean (3)

Sand Material M (A) (4)

Silt-clay aterial (B) (5)

4'75 mm 100 100 100

2-36 mm 80—10

90 91

1-18 mm 50—?0

65 34 100

425 micron

30—60

45 10 84

300 micron

20—45

33 3 59

75 micron 10—25

18 2 36

Sand (4) and silty clay (B) are available, whose gradation is indicated in Cols. 4 and 5 respectively in Table 17 8. Gradation requirements indicate that a 1 ; 1 ratio Oi the two materials would be adequate. L.L. and P.I. of Materials A and B are as under : A B L.L. 25 38 P.I. 2 10 What will be the L L. and P.I. of the mixture ? If the maximum L.L. and P.I. are to be respectively 35 and 9, what should be the proportion of A and B in the mi* ? La=25 h —2 F,= 10 84 * .= 50

Page 68: FCE546 Transp Eng IIIB - March 2012 v0
Page 69: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

64

" 154 = 55%. Obviously, the values worked out by the earlier formula, i.e.. 66% of A would be suitable for the P.I., criterion also. Hence a practical mix of A : B=2 : 1 would be suitable. This mix, it may be noted from para 17 4 7, also satisfies the gradation requirements. 175. Soil-Lime Stabilisation 175T. During the last twenty-five years, the use of soil-lime stabilisation has gained in popularity in the U.S.A., Africa, Australia and India (Ref. 11, 12). Soil-lime mixtures are used as sub- base or base courses. Because of the favourable climatic conditions in India and the occurrence of clayey soils in large areas, this technique offers considerable scope. 17 7'2. Mechanism of lime-soil interaction When lime (CaO) is added to a fine-grained soil, a number of reactions take place. Some of them occur immediately while others are slow to occur. One of the early reactions is base-exchange (ion- exchange). Clay particles are usually negatively charged, with exchangeable ions of sodium, magnesium, potassium or hydrogen adsorbed on the surface. The strong positively charged ions of calcium present in lime replace the weaker ions of sodium, magnesium, potassium or hydrogen, resulting in a preponderance of positively charged calcium ions on the surface of the clay particles. This in turns reduces the plasticity of the soil. The clay particles tend to agglomerate into large sized particles (flocculation), imparting friability to the mixture. After the above first stage reactions are complete, any additional quantity of lime will react chemically with the clay minerals. The aluminous and siliceous materials in the clayey soil will react with lime in the presence of water to form cementitious gels, which increase the strength and durability of the mixture. These pozzolanic reactions are slow and extend over a long period of time, sevsral years in some instances (Ref. 13). Another possible source of strength is the formation of calcium carbonate due to the absorption of carbon dioxide from air. 17'5'3. Soils amenable to treatment Clayey soils are most amenable to lime treatment. The fraction passing 425 p should be at least 15 and the clay content should be at least 10. The P.I. of the soil should be at least 10. These conditions are satisfied by many soils in India. The aluvial silty soils of the northern plains, the clayey soils of the deltas, the black-cotton soils and the moorum found in many parts are eminently suitable for soil-lime stabilisation. 17'5'4. Quantity of lime The strength of a soil lime mixture is greatly influenced by the lime content. A concentration of lime less than 2 per cent is not generally amenable to proper mixing and is not recommended for use (Ref. 14). A quantity of 3 to 10 per cent by weight of dry soil is normally required to stabilise most soils. Ca(OH,) (i.e. hydrated lime) in a powder form is preferred to CaO (quick lime) because of the danger from burns that can be caused to unprotected workmen when handling quicklime. 17'5'5. Properties of soil-lime Due to the aggregation of smaller particles into bigger ones, one of the early effects of adding lime is to make the grains coarser. Lime brings about a substantial reduction in plasticity. The liquid limit generally decreases and the plastic limit increases, thus causing a reduction in the Plasticity Index of the soil, vide Fig. 17-6.

Page 70: FCE546 Transp Eng IIIB - March 2012 v0

Fig. 17-6. Effect of lime on plasticity index.The soil swell and shrinkage potential is significantly reduced by the adition of lime. This is highly important in dealing with expansive soils, which swell in volume when water is added and shrink in volume when then moisture content is reduced.The strength of soil increases substantially whan treated with lime. The unconfined compressive strength of typical fine-grainedsoils range from 0" 18 to 0 may be of the order of 0 7 toThe benefits of addition of lime depend to a large extent on factors such as purity of lime, the fineness of lime, the degree of pulverization of the soil, the compaction imparted, the time between final mixing and compaction and the curing conditions. For puspecified that at least 80 per cent should pass through 475 mm sieve and all tpass through 25 mm sieve. Provided the soil-lime mixtures are designed pioperly, the durare not in doubt. Although some reduction in strength due to cyclic freezemoisture effects is possible, the residual strength itself is sufficient to meet the design requirements adequately. 17'5'6, Design of pavement layersThe CBR method of design is often used to detemine the thickflexible system. For use asdesired. For use in base couses, CBR of 8uncertainties in mixing in the field, current Indian pracof the laboratory CBR value as the CBR under field conditions.17*5'7. The main advantage of soilin this country. The manufacture of lime and the soil lime stabilisation techniques are amenable to labour-intensive technology and are ideally suited to our country. However, the experience in lime-soil work has not been so far very successful. This is mainly because lime of a high degree of purity is needed and a great deal of control over quality i17'5'8. Lime-cement-soil stabilisationBoth lime and cement produce cementitious products in the presence of clay minerals and water. A mixture of lime and cement is sometimes used for stabilisation. The combined lime and cement content can normally be around 1I : 3 and 3 : 2 depending upon the soil type and strength desired. Working with highly expansive clays, lime is added initially upto about 3 per cent to render thequantity of lime and cement are added subsequently.17 5 9. Lime-pozzolana stabilisationPozzolana is a siliceous material, which, while in itself possesin a finely divided form and in tcemen- titious compounds. Pozzolana can be a naturally occurring volcawaste such as fly

me on plasticity index.

The soil swell and shrinkage potential is significantly reduced by the adition of lime. This is highly in dealing with expansive soils, which swell in volume when water is added and shrink

in volume when then moisture content is reduced. The strength of soil increases substantially whan treated with lime. The unconfined compressive

grained 7 MN/m2. Increases in strength of 28 days cured lime

may be of the order of 0 7 to 1'7 MN/m2. The benefits of addition of lime depend to a large extent on factors such as purity of lime, the

me, the degree of pulverization of the soil, the compaction imparted, the time between final mixing and compaction and the curing conditions. For pulverisation, it is generally specified that at least 80 per cent should pass through 475 mm sieve and all the particles should

lime mixtures are designed pioperly, the durability characteristics of the mixture

are not in doubt. Although some reduction in strength due to cyclic freeze-thaw or prolonged s is possible, the residual strength itself is sufficient to meet the design

17'5'6, Design of pavement layers The CBR method of design is often used to detemine the thickness of the various layers in a flexible system. For use as a sub-base layer, a minimum CBR value of 20desired. For use in base couses, CBR of 80—100 is normally stipulated. To accouncertainties in mixing in the field, current Indian practice (Ref. 14) is to assume 4

he laboratory CBR value as the CBR under field conditions. The main advantage of soil-lime is that lime is a cheap material which is locally available

in this country. The manufacture of lime and the soil lime stabilisation techniques are amenable intensive technology and are ideally suited to our country. However, the experience in

soil work has not been so far very successful. This is mainly because lime of a high degree of purity is needed and a great deal of control over quality is necessary in execution.

soil stabilisation Both lime and cement produce cementitious products in the presence of clay minerals and water. A mixture of lime and cement is sometimes used for stabilisation. The combined lime and cement ontent can normally be around 10—15 per cent, and the ratio of lime to cement can be between

I : 3 and 3 : 2 depending upon the soil type and strength desired. Working with highly expansive clays, lime is added initially upto about 3 per cent to render the soil more friable. Additional quantity of lime and cement are added subsequently.

pozzolana stabilisation Pozzolana is a siliceous material, which, while in itself possessing no cementitious properties, will in a finely divided form and in the presence of water, react with calcium hydroxide and form

titious compounds. Pozzolana can be a naturally occurring volcanic ash or industrial waste such as fly-ash, or can be produced by

The soil swell and shrinkage potential is significantly reduced by the adition of lime. This is highly in dealing with expansive soils, which swell in volume when water is added and shrink

The strength of soil increases substantially whan treated with lime. The unconfined compressive

Increases in strength of 28 days cured lime-soil specimens

The benefits of addition of lime depend to a large extent on factors such as purity of lime, the me, the degree of pulverization of the soil, the compaction imparted, the time

risation, it is generally he particles should

ability characteristics of the mixture thaw or prolonged

s is possible, the residual strength itself is sufficient to meet the design

ness of the various layers in a 0—30 is normally

00 is normally stipulated. To account for the tice (Ref. 14) is to assume 45—60 per cent

lime is that lime is a cheap material which is locally available in this country. The manufacture of lime and the soil lime stabilisation techniques are amenable

intensive technology and are ideally suited to our country. However, the experience in soil work has not been so far very successful. This is mainly because lime of a high degree

s necessary in execution.

Both lime and cement produce cementitious products in the presence of clay minerals and water. A mixture of lime and cement is sometimes used for stabilisation. The combined lime and cement

5 per cent, and the ratio of lime to cement can be between I : 3 and 3 : 2 depending upon the soil type and strength desired. Working with highly expansive

soil more friable. Additional

sing no cementitious properties, will he presence of water, react with calcium hydroxide and form

nic ash or industrial ash, or can be produced by

Page 71: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

66

calcining clay. When fly ash is used, the mixture is known as lime- flyash stabilised mixture, or in an abreviated form LFA stabilised mixture. Not all soils possess enough quantity of clay minerals with which lime can react to form cementitious products. If, therefore, a pozzolanic material is added to such soils, the stabilisation can easily take place. Silts, sandy soils, gravels, crushed stone and slags are some of the material types where lime-pozzolana stabilisation can be successful. The aluvial silts of northern India fall into this category of soils which can be stabilised with lime-pozzolana. The ratio of lime to pozzolana depends upon a number of factors and can vary so widely as from 1 : 1 to 1 : 9. The combined quantity of lime pozzolana in a mixture can vary from 10 to 25 per cent. Lime-pozzolana-aggregate mixtures can be used for the superior strength road bases. A layer of this material has great structural strength and behaves more like a semi-rigid pavement. The use of lime-pozzolana in our country is still in an early stage, but in view of the problem of disposal of huge quantity of fly-ash from thermal plants, the future may see more and more use of this material. 17 6. Soil-cement stabilisation 17'6'7. The addition of cement to soil to improve its strength is now in vogue for the past forty years or so. The material is very popular in the U S.A., U.K. and in African countries (Ref. 15, 16, 17), but its use in India has not caught on mainly due to the shortage of cement. Excellent summaries of India practice have been published by the Concrete Association of India (Ref. 18) and by Antia (Ref. 22). The principal advantages with soil-cement are that almost all soils are amenable to this technique. It is a scientifically designed engineering material and cement itself is a standard material whose quality is tested and assured. Because of its very high flexu- ral strength, it has a very high load spreading property. Thus soil cement is able to spread the load over a wider area and bridge over locally weak spots of the underlying sub-grade or sub-base. In view of its high flexural rigidity, it is often classed as a semi-rigid pavement, something which is intermediate between a flexible pavement and a rigid pavement. The durability of soil cement is of a high order and its strength is known to increase with age. The main disadvantages are the higher cost than lime-soil and the need for a high degree of quality control. Because of volumetric changes that take place when cement hydrates, early shrinkage cracks are formed in soil-cement layers, affecting their overall performance. 17 62. Action involved in cement-soil stabilisation When water is added to cement, major cementitious products like calcium silicate hydrates and calcium aluminium hydrates are produced. In stabilisation of granular materials with cement, these cementitious materials provide the bond between the mineral parti - cles. In the case of fine-grained soils, the cementitious bond provided by the calcium silicate hydrates and the calcium aluminate hydrates is further helped by the secondary hydrous calium silicates and aluminates formed by the reaction of free lime to the cement paste and the clay mineral particles. The reaction phenomenon between the fr.e lime and the clay mineral particles is just the same as in the case of lime-soil stabilisation. Base-exchange and flocculation also take place, rendering the soil more friable and reducing the plasticity. 17*6*3. Factors affecting strength of soil-cement mixes (i) Cement Content : The cement content necessary for effective stabilisation varies with the soil type. The strength of a soil-cement mix for a particular soil type varies with the cement content. As a rough guide, the cement content, expressed as a percentage by weight of the dry soil, varies between 4 and 14. For preliminary estimation purposes, a value of 10 per cent seems reasonable. The cement content is generally selected to obtain the desired compressive strength. The criterion most commonly followed (Ref. 18) is a 7 day unconfined compressive strength of 1'7 MN/m" with moist-cured cylindrical specimens having a height to diameter ratio of 2*1. Table 17*9 gives the range of cement requirements as per American practice (Ref. 19). Table 179 Cement requirements for various soil types Soil Type (PR A classification)

Usual range in cement requirement by weight (per cent)

A—I—a 3—5

A—l—b 5—8 A-2 5-9 A-3 7—11 A—4 7—12 A—5 8—13

Page 72: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

67

A—6 9-15 A—l 10—16

From the above Table, it is seen that the quantity of cement needed to stabilise gravelly soil is much less than that required to stabilise silty and clayey soils. It is observed that for the range of cement contents normally employed in stabilisation work, the strength of the mixture increases with increase in cement content.

Page 73: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

68

Ordinary Portland Cement is used for the majority of soil- stabilisation work. A rapid-hardening cement can be used if high strengths are desired initially. (it) Moisture Content Since hydration of cement takes place only in the presence of water, the importance of water is obvious. Water also improves the workability of the soil and facilitates compaction. The exact amount of water to be added is governed by many considerations. One important factor is that the soil-cement mixtures exhibit the same type of moisture-density relationship as an ordinary soil. Thus, for a given compactive effort, there is an "optimum moisture content" at which the maximum density is obtained. The best moisture content for maximum density may not necessarily be the optimum moisture content for maximum strength. It is generally seen that highest compressive strength can be obtained with specimens compacted slightly below the optimum for maximum density (Ref. 2). Some of the water is taken up by the cement for hydration. The moisture necessary for maximum compaction is sufficient to provide for this. (»»») Soil Soil type has a profound influence on the success of stabilisation with cement. It is often claimed that almost any type of soil can be stabilised with cement. Though this is true in a large measure, certain soil types cannot be stabilised with cement at economical costs. Soil with a low organic matter are generally preferred. A safe- upper limit is 2 per cent, though soils with 3 to 4 per cent organic matter have also been successfully stabilised with cement (Ref. 2). It is well-known that the presence of sulshates has a harmful effect on the life of cement concrete. For the same reasons, the presence of sulphates in the soil has to be viewed with suspiciton. For cohesive soils, a maximum sulphate content of 0"25 per cent is usually specified, though for non-cohesive materials an upper limit of of 10 per cent may be all right (Ref. 20). The presence of a small amount of clay in the soil is beneficial to cement stabilisation, but large clay content brings in problems of mixing and pulverising. It is desirable if the clay content is restricted to 5 per cent (Ref. 16). A thumb rule often employed (Ref. 17) is that the practical upper limit for stabilisation with machinery is when the P.t. multiplied by the percentage finer than 425 is greater than 3500. As the plasticity of the soil, increases, the amount of cement needed to effectively react increases. Highly plastic soils cannot, therefore, be economically stabilised with cement. An upper limit of 45 for L.L. (Liquid Limit) and 20 for P.I. (Plasticity Index) is generally observed (Ref. 20). More plastic soils can be treated with cement after being pre-treated with lime. As regards the grading of the soils, it is recognised that a well-graded mixture requires less of cement and is preferred. British practice (Ref. 20) indicates the following grading as suitable, Table 1710. Table 17T0 Grading of materials for soil-cement Sieve size (nearest) equivalent IS sieve

Percentage by weight passing

50 mm 100 40 mm 95 20 mm 45 10 mm 35 4'75 mm 25 600 micron 8 300 micron 5 75 micron 0

It is also specified that the uniformity coefficient (i.e. ratio of the particle size for which 60 per cent is finer to the particle size for which 10 per cent is finer) should not be less than 5. Though British practice limits soil-cement work to well-graded materials below 50 mm size, experience elsewhere has shown that sandy and gravelly soils containing 10—35 per cent combined silt and clay, sandy soils deficient in fines, silty soils and clayey soils can also be effectively stabilised. Single sized sands with a low uniformly coefficient (less than about 3) present problems for cement stabilisation. (iv) Degree of pulverisation in mixing The presence of lumps of soil inhibits effective stabilisation. Pulverization of soils, especially clays, must be carried out before mixing The following requirements are often laid down„ Table 17'H. Table 17'11 Requirements for pulverisation for stabilisation with cement

Page 74: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

69

Sieve designation Percentage by weight of soil passing the sieve after pulverisation

25 mm 100

4'74 mm 80

Page 75: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

70

Mixing For best results, cement should be uniformly distributed and mixed throughout the material. The addition of water helps the cement to adhere to the particles of the soil and prevents segraga- tion. Compacting The hydration of cement starts ai soon as water is added, and it therefore is desirable to compact the material as soon as mixing is completed. Any delay is likely to result in the loss of the cementing action of the additive and in the need for extra com- pactive effort to break down the cement bonds that have already formed. A serious loss in strength can follow. For this purpose, it is often stipulated that compaction should be completed within two hours of mixing (Ref. 3). (»»»*) Caring As in the case of cement concrete, soil cement requires the presence of sufficient moisture to meet the needs of chemical reactions. A seven days' moist curing is necessary. 17*6*4. Design criteria The most popular design criterion for soil-cement is in terms of the unconfined compressive strength after 7 days' moist curing. A value of 1*7 MN/ma with cylindrical specimens (ratio of height to diameter of 2 : 1) is specified for Indian conditions (Ref. 18). Practice abroad requires higher strengths. For example, in U.K. a minimum strength of 2*76 MN/m* is specified (Ref. 20) for cylindrical specimens. But it should be noted that in U.K. soil- cement mixtures are with well-graded granular materials 50 mm and below in size. A minimum strength of 2"76 MN/m2 is generally desirable for heavily trafficked roads and for higher layers of the pavement structure (i.e. base course), whereas for lightly trafficked roads and for bottom layers of the pavement structure (i.e. sub- base course) a minimum strength of 1 iMN/m' is probably adequate. The CBR method of design is also applied to soil-cement layers. For this purpose, the specimens are initially cured for 7 days and soaked in water for 4 days prior to testing. For use as sub-bases, a CBR value of 20—30 is desirable, whereas a value of 80—100 is desirable for use as a base course. Since imperfections in mixing in the field can yield to lower strength values, it is desirable to design the laboratory mix to yield a higher CBR value. Normally, it can be assumed that the field mix can yield a strength which is 60 per cent of the laboratory strength (Ref. 21). When determining the thickness of the layer, an equivalency factor of 1*5 can be assumed -vis-a-vis unbound granular layers (Ref. 32).

Page 76: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

71

If a small quantity of cement, say in the range of 2—3 per cent, is added to a soil, the soil properties can be improved appreciably, though not to the same extent as a soil-cement mixture. Such a mixture can be used as a sub-base, and is known by the name of cement-modified soil (Ref. 21). The soil should possess characteristics similar to those required for soil-cement. The design is generally based on CBR method. A CBR value to 20—30 in the field is generally suitable for sub-base. 177. Chloride Stabilisation T7'7'l. Granular soils lack stability when they are too dry. If their moisture content can be stabilised by the addition of some chemicals, then these soils can be used successfully. Chlorides of calcium and sodium are two of the most popular salts used for this purpose. 17 72. Calcium Chloride Calcium chloride has been used extensively for as a dust- palliative and moisture stabiliser for more than half a century. Its wide use is reported in the US. A. and Canada. The material has also been used as a dust palliative in India, and on an experimental basis in the body of the subgrade and sub-bases (Ref. 23). Calcium chloride has deliquesent and hygroscopic properties. By the former is meant the ability of a material to absorb moisture from the air and thus to dissolve and become liquid. By the latter is meant the ability of a material to absorb and retain moisture without necessarily becoming liquid. These properties render the material ideally suitable as a dust-palliative on untreated low cost roads. In dry climate regions, the moisture evaporates from the road during the day, but if calcium chloride is present the moisture can be regained in the night. Another property of calcium chloride is that it lowers the vapour pressure of water in which it is dissolved. This reduces the rate of evaporation. An increase in the surface tension of water is noticed when calcium chloride is present in a soil-water mixture, As the surface tension of the pore water rises, the rate of evaporation falls. When some evaportion takes place, the pore water content is itself reduced, and this in turn causes surface tension to rise further. The water films then close on the soil particles and grip them together. If calcium chloride is added to a soil, it is observed that its unit weight increases for a given compactive effort. In other words, to obtain a desired density, less compactive effort is needed. This is mainly because of the lubricating effect of the chemical. It is well known that chlorides dissolved in water lo ver the freezing temperature of water. This property makes the chemical extremely useful in frost- susceptible locations. Calcium chloride is obtained as a waste product in the manufacture of ammonia, ammonium carbonate, potassium chlorate and sodium carbonate. Its disposal was considered a problem, and its use as a soil stabiliser in such situations is to be welcomed. The rate of application of the material as a dust palliative for untreated roads is about 4"8—1*5 kg/sq. m. per year. The material is applied in a dry form and the road surface is bladed. As an admixture to the soil to obtain greater density and strength, it is used at a small rate of about 05 per cent by dry weight of soil. Work carried out in India has shown (Ref. 9) that calcium chloride can retain the moisture in the surface only when the relative humidity of the atmospheie is above 31 per cent. This precludes its use in extremely dry areas. 17-7-3. Sodium chloride Sodium chloride, common salt, is available in a natural state as rock salt and sea water. Its use as a stabiliser derives from the many properties listed under Calcium Chloride. It is, however, less hygroscopic and inferior to Calcium Chloride as a lubricant for aiding compaction. An important beneficial effect is the crystallisation of the salt forming a compact and hard surface which improves the stability of the layer and prevents evaporation. The quantity of sodium chloride is roughly the same as calcium chloride, viz., about 0'5 per cent by weight. 17'8. Other Chemicals/Materials A number of other chemicals/materials have been used for chemical stabilisation of soils. Some of them are : Sodium silicate Lignin Resins Molasses. Sodium silicate reacts in acqueous solutions with soluble- calcium salts, forming insoluble and gelatinous calcium silicates. Calcium needed for the reaction can either be present in the soil itself (as in lime-stone aggregates or chalky soils) or be added in acqueous solutions. The amount of chemical needed may vary from one to ten per cent. Experimental work carried out in India (Ref. 24) on stabilisation of sand with sodium silicate has yielded satisfactory results. The natural binding material that holds together the fibres in wood is lignin. The material is a major byeproduct in paper manufacturing industry. Liguin is available from the paper

Page 77: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

72

manufacturing process in a water solution known as calcium lignosulphonic acid. Calcium lignosulphate (or lignin sulphate or

Page 78: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

73

simply ligtrin) is the constituent which is used as a road binder. About 0"5 to 1 per cent by weight of dry soil is used for stabilisation. Stabilisation is by the cementing bond that develops between the soil particles due to the presence of the binder. The material also closes the voids and thus reduces penetration of water through the layer. It retards the rate of evaporation of water and arrests loss of moisture. Natural or processed resins can also be used for soil stabilisation. Vinsol resin and resin or derivatives of resin are commonly used. Resins are wood products. Resin-treated soils reduce water absorption, facilitate compaction and increase the stability of the treated mixtures. Their drawback is their susceptibility for micro-biological attack by bacteria and fungi, but this handicap can be identified and surmounted. A quantity of 1 to 3 per cent by weight of soils is normally sufficient. Molasses is a waste-product from the process of manufacturing sugar from sugarcane. A thick syrupy liquid, it is hygroscopic and can be used as a dust-palliative and as a binder for incorpora-tion during compaction. It is easily leached out by rain water. But some additives have been tried to make it insoluble. If water is prevented from entering the mixture, as by means of an impermeable bituminous surfacing, it can be excepted to last long. 17 9. Soil Bitumen Stabilisation 17"9T. Basic principles The addition of a bituminous binder to a soil improves its properties considerably. Firstly, if the soil lacks cohesion, the bitumen coats the soil particles, binds them together and supplies cohesion. Example of such a stabilisation is a sand bitumen in which sand and bitumen are mixed and laid. Secondly, bitumen being a waterproofing material, ihe mixture becomes less prone to the adverse effects caused by ingress of water. Soil-aggregate mixtures or cohesive soils can be made to benefit from this action. A third procedure is to spray a bituminous binder on a dry surface of a low-cost road (earth/gravel), with a view to prevent dust and to stop the entry of moisture into the road. The success of the above principles really lies in selecting the right quantity and type of the binder. An excess of the binder will result in too thick a binder film around the soil particles and destroy part of ihe internal friction. When aiming at waterproofing it is seldom necessary to fill up the entire void space. The gradation of the soil particles also has an important bearing on the satisfactory performance of the stabilisation technique. These factors will be discussed in detail under the different types of soil-bitumen stabilisation processes. 17*9*2. Types of soil-bitumen stabilisation processes The following are the variations in the bituminous stabilisation* techniques : (») Sand-bitumen (*») Soil-bitumen (Hi) Soil-aggregate-bitumen (iv) Spraying bitumen on earth/gravel roads foiling) 17 9 3. Sand-bitumen 17*9"3T. There are regions where sand is the only predominant road building material available within economical leads and stone aggregate or gravel has to be conveyed over a long distance. There are also areas where there is acute scarcity of water, and specifications such as water-bound macadam or compacted gravel will have to be discarded. Under such conditions, a successful specification is sand-bitumen. This has been tried in the Middle East, Africa, U.S.S.R. and India. The arid desert region of Rajas- than where dune sand is met with and the coastal plains of the South where beach sand is available, are examples of such areas (Ref. 25, 26, 27) where the technique has been tried successfully. Based on the limited experience in the country, the Indian Roads Congress have come out with specifications for use of sand-bitumen as a base- course (Ref. 28). 17 9 3*2. Gradation of sand Typical gradation of Rajastban sand for sand-bitumen stabilisation A wide range of sands can be successfully stabilised with bitumen. Though a well-graded sand-bitumen mixture will have a higher stability, poorly graded sands and single size sands have been satisfactorily stabilised with bitumen. The latter include the windblown dune-sands. Indian practice limits the use of this specification to sands having less than 10 per cent of material passing 75 microns sieve (Ref. 28). A typical gradation of the Rajasthan desert sand is given in Table 17T2. Table 17 12 Sieve Designation Percentage Passing

600 microns 100

300 microns 98-100

Page 79: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

74

150 microns 60—65 75 microns 4—5

Page 80: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

75

In the U.S.A., sands with not more than 25 per cent passing 75 microns sieve are permitted for stabilisation, but with certain other added precautions. 1793 3- Type of binder The types of binder used for sand-bitumen work are : (t) Penetration Grade Bitumen (it) Road Tar (tit) Cold Application Cut-back (iv) Hot application Cut-back (v) Emulsions Penetration Grade bitumen 30/40 or 80/100 can be used pro* vided the sand is pre-heated and dried to a suitable temperature (135—165° C). A small quantity of flux such as kerosene can be beneficitl to make the bitumen workable. Road Tar of grade RT-3 has also been used. The use of cold-application cut-backs has been very popular for sand-bitumen stabilisation. A medium-curing cut-back such as MC-1 and MC-2 are most common, though both rapid-curing and slow-curing (RC-1, RC-2 and SC-1 and SC-2) have also been freuqently used (Ref. 2). In India, RC-3 has been tried successfully (Ref. 25. 27, 29). A hot-application cut-back such as Shelspra BS available in India is also suitable. Emulsions are ideal for dry conditions in desert regions in the tropics, since they provide the optimum fluids content for compaction. The use of emulsions for sand-bitumen under wet conditions is however, difficult. 17-93 4. Quantity of binder For sand-bitumen stabilisation, the quantity I of binder ift selected after carrying out stability tests with various binder contents. The optimum binder content at which the stability is maximum is determined. The range of binder contents found to be satisfactory is 4—10 per cent by weight of total mix. 17 9 3'5. Incorporation of hard aggregates Blending of sand with some quantity of hard crushed aggregate will improve the stability of sand-bitumen mixtures, especially if the sand is single-size. The proportion of coarse aggregates can be abjut 30 per cent by weight. 17 9 3 6. Design criteria For satisfactory peformance as a base course, the Hubbard- Field stability values should be as below :

Page 81: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

76

Table 17 13 Minimum values of Hubbard-Field stability of sand-bitumen for base course (Ref. 25, 28)

Type of mix Specimen*

Teat Method

Stability (kg)

Sand-bitumen with penetration grade bitumen

5 cm dia x2'5 cm height

Testing at 60°C

360

Sand-bitumen with cut-back bitumen

5 cm dia x 5 cm height

Testing at 25°C

540

Sand-bitumen with incorporation of coarse aggregates

15 cm dia x7 cm height

Testing at 60°C

900

Sand-bitumen with incorporation of coarse aggregate

15 cm dia X7 cm height

Testing at 25°C

1100

17 9 3 7. Surfacing Sand-bitumen base courses are generally laid to a compacted thickness of 100 mm. They require a surfacing course to provide a good running surface and to protect the base from abrasive action of traffic. A 20 mm premix chipping carpet has been found to be suitable for this purpose in India (Ref. 25, 28). Such roads have been found to be satisfactory for light to medium traffic in India. 1794. Soil-bitumen 17'9'4*1. The term soil-bitumen is generally used for stabilising cohesive fine-grained soils. The incorportion of bitumen in a cohesive soil result in water-proofing the layer. Such soils have good bearing capacity at low moisture contents, but they tend to lose the bearing capacity when the moisture content increases. The bituminous binder en.-ures that the moisture content never reaches beyond the safe limit. Soil-bitumen layers are used as sub-bases and bases. 17 9'4'2. Type of soils suitable for stabilisation The following gradation limits are generally prescribed (Ref. 30); Sieve Designation Percentage

Passing 4'75 mm 50 425 micron 35—100 75 micron 10—50 The liquid limit should be less than 40 and the plasticity index should be less than 18. Highly plastic soils are hard to stabilise, because of the difficulty in dispersing the binder. 17'9'4'3. Typical amount of binder The binders which find ready application for soil-bitumen are the cut-backs, road tars and emulsions. A medium-curing cut-back is preferable, but slow-curing cut-backs can be used with relatively highly plastic soils. Rapid curing cut-backs can be used with sandy soils. Road Tars in the grades RT-3, RT-4, RT-5 and RT-6 can be used. Emulsions can be used with relatively less plastic soils and in dry climates, where the natural moisture content of the soils is not high. Slow-curing emulsions are appropriate. The amount of binder depends upon the moisture content of the soil, the type of soil and type of binder used. The combined volume of bitumen and water must not exceed the pore space in the soil at the desired density. The normal range is 4 to 8 per cent by weight of dry mix It is usually found that if the clay mineral content is high, a greater quantity of binder is needed. On the other hand, if the iron and aluminium content is high, a smaller quantity of binder is needed. The binder content is selected after carrying out tests such as density-fluids content, strength, water absorption and swelling. 17'9'4'4. Design criteria

Page 82: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

77

Soil-bitumen stabilisation is yet in a developmental stage and further research is needed to understand the behaviour. Design criteria can thus be very tentative. A common requirement is that the Hubbard-Field Stability Value on 5 cm diax5 cm height specimens should not be less, than 180 kgs after standing the specimens in water for 7 days. The stability value of the specimen before saturation should be 453 kgs. A further requirement is that the swelling should not exceed 5 per cent and water absorption should exceed 7 per cent (Ref. 31). ITi'A'S. Useage Soil-bitumen is generally used as a sub-base. The thickness provided varies from 100 mm to 200 mm. 17'9'5. Soil-aggregate bitumen stabilisation 179-51. Principles Soil-aggregate-bitumen mixture implies the addition of a suitable quantity of bituminous binder to a granular mixture which is fairly well graded and has good internal friction but lacks cohesion. The binder not only supplies cohesion, but also waterpoofs the layer. The addition of binder prevents softening and loss of strength in a mixture containing fines. 17-9-52. Gradation The gradation of the granular materials should be generally similar to those indicated under mechanical stabilisation (Table 171). The miximum P.I. values can, however be in the range of 10 to 15.

Page 83: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

78

17953. Binder A rapid curing cut-back (RC-1, RC-2 or RC-3) or a slow- curing emulsion or Road Tar (RT-4, RT-5 or RT-6) is generally suitable. The quantity to be used will generally be in the range of 2—6 percent by weight of dry materials. The binder should be able to coat adequately the individual particles of the fines fraction. 179-5-4. Design criteria For soil-aggregate-bituminous mixtures, the CBR tests can be conveniently used for design. The CBR values of the untreated and treated mixtures can both be determined and compared before selecting the final design. 17 96. Spraying bitumen on eartb/gravel roads (oiling) 17-961. Principles Earth/gravel surfaces are dusty in the dry season when the moisture which binds the soil particles is absent. In the wet season, water easily enters the surface and softens the same. The conditions can be improved by spraying a binder which will coat the dusty particles and hold them together, at the same time providing a reasonably water-proof surface. The binder is of a law viscosity so that it is able to penetrate the compacted surface by gravity. The process is rather cheap and economical and is suitable for low- volume low-cost roads. 17-96-2. Binder The binder is usually a medium curing or a slow-curing cut-back. MC-0, MC-1, SC-0 or SC-1 cut-backs are generally suitable. Slow-curing cut-backs have the advantage that the vola- tiles do not evaporate too rapidly, thus giving more time for the binder to seep into the soil. A rate of application of about 5 litres per sq.m. in two" or three applications will usually result in a penetration of about 15 mm to 25 mm into th? soil and be found to be satisfactory. A light dressing of sand will render the surface non-slippery in* wet weather. 171'. Constructional practice in soil-stabilised roads 17101. General The constructional practice in soil-stabilisation varies with the type of stabilisation, but there are certain steps and procedures which are common. It is, therefore, convenient to deal with the construction practice for all types of stabilisation together. The minor variations needed for each type of stabilisation will be indicated at the appropriate place. The construction technique to be adopted for a given situation depends upon a number of factors, viz. : (<) Type of stabilisation (»*) Type to binder, if any, to be added (Hi) Type of soils (iv) Leads involved for the materials (v) Magnitude of the project (vi) Availability of equipment (CM) Availability of labour. Broadly, the following three construction techniques can be identified : (») Labour intensive methods (ii) Machinery intensive methods Labour intensive techniques are indicated forlthe following conditions : Availability of cheap labour, as in developing countries, making it more economical to use labour-intensive techniques than equipment intensive techniques. Small magnitude of the work, which is also scattered. This condition is prevalent in developing countries where the construction of link roads to villages is given emphasis. (tit) Equipment is not manufactured indigenously, and the level of skill needed for operation and maintenance of imported equipment has not been developed. Equipment intensive techniques are indicated for the following conditions : (») The equipment is produced indigenously. (ii) Labour is scarce, and it becomes more economical to use equipments. (tit) The work is of a large magnitude, fairly concentrated, and the time schedule for compaction is tight. Intermediate or appropriate technology is an intellegent blend of labour and machinery. Under this, it is recognised that small implements and tools and simple mechanical equipment can raise the productivity of labour and aid in obtaining good quality of work. India is a country which has already a good industrial base for manufacturing and servicing simple tools and equipment, and at the same time has surplus labour. Intermediate technology can be applied with good benefit in India under the prevailing conditions. 17 10 2. Labour intensive methods The various operations involved can be discussed under the- following heads :

Page 84: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

79

(») Collection of materials (ii) Preparation of the subgrade (Hi) Pulverisation, where necessary (»*«) Mixing (v) Spreading (vi) Compaction. The materials (soil, sand, gravel etc.) are collected on the sides of the sub-grade in requisite proportions and stacked in the form of windrows. The sub-grade is well-compacted to the required density and true to grades and the desired cross-profile. If clay is one of the soil materials to be used, it is necessary to pulverise it. The clods are broken with the help of pick-axes or rammers. Application of a country plough driven by a bullock can also be tried. If a power roller is available, the same can be passed over the layer of clods a number of times, with frequent raking of the crushed material. If the materials to be mixed are soil, sand and gravel, they are mixed by dry labour using spades or shovels. The required quantity of water is added and the materials are wet mixed by manual labour. If an additive such as lime or cement is to be added, the soil is first spread to a uniform thickness and the bags of lime or cement are spotted at the desired spacings. The bags are then opened and the contents spread by manual means to cover the calculated area, which should be marked by strings. Water to the required quantity is added in stages and the soil and lime are mixed till the mixture has a uniform colour and the desired moisture content. If a bituminous binder is to be added, the mixing should preferably be done in a paddle type mixer, for a period of about 1 to 2 minutes. Bitumen stabilised mixtures are spread to a uniform thickness in loose layers not exceeding 15 cm. Mechanically stabilised mixes, soil-lime nmes and soil-cement mixes are spread to a thickness which will give a compacted thickness of not more than 150 mm. The thickness of any stabilised laver should not be less than 100 mm. The cement soil mix should be compacted within 2 hours of the mixing (Ref. 3). When cut-back bitumen is used as a binder, rolling should start only after the mix has cured. The curing time depends upon the type of cut-back used and varies from 1 to 7 days. With penetration grade mixes, rolling can start as soon as the mix is laid and spread. When emulsions are used, the rolling can start after £ hour. Rolling of stabilised mixtures should be by 8— 10 tonne power rollers. When sand-bitumen and soil bitumen stabilisation is used, it is preferable to carry out initial rolling by means of a light pneumatic tyred roller. Rolling is carried out till 100 per cent laboratory density is achieved. Traffic is allowed on bitumen and sand-bitumen layers only after 24 hours Only light pneumatic vehicles are allowed initially. Normal traffic is allowed only after a month. Soil-lime and soil- cement layers are moist cured for a period of 7 days. Curing is achieved by providing or covering the surface with damp sand, straw or hessian. 17 IG'3. Machinery intensive methods 17'10 31. Three basic construction methods are available when machinery is employed, viz., (») Mix-in-place (ii) Travelling plant (Hi) Stationary plant. 17 10 3 2. Mix-in-place method In this method, a train of machines is run over the soil to ber processed. For breaking and pulverising the soil, rippers, cultivators, rotary tillers, ploughs, scarifiers or disc harrows are used. Water is then added to the loose soil from a water tanker. If the stabiliser is liquid, it is distributed by a spraying tanker. Dry powder is "either spread manually or from bulk spreaders. Mixing is carried out by means of disc harrows or pulvi-mixers. Dry mixing is initially done in two to three passes of the machines and is followed by wet mixing with the addition of water. A single- pass stabiliser is also used, and it performs the various operations such as cutting the soil, pulverising and mixing in one operation itself. Compacting is done by rollers which follow the machines for laying the mix. niO'SS. Travelling plant method This method involves the use of a travelling plant which travels along the job site, picking up the soil and stabiliser, mixing it in a mixer, discharging the mix on the ground. Compacting is done separately by rollers which follow the travelling plant. 17 10 3 4. Stationary plant method This method is based on the process of mixing the ingredients in a centrally located plant, conveying the mix to the site, laying and compacting the same. The central mixing plant can be of the batch type or continuous type. 17'10"3'4. The advantages and disadvantages of the three types are summarised below.

Page 85: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

80

Advantages and Disadvantages of Types of Stabilisation Techniques using Equipment Table 17 14 Type Advantages Disadvantages

1. Mix-in place?

(i) Plant is simple, cheap .. and easily transported.

(i) It is difficult to obtain a uniform thickness of lift, because of the difficulty of setting the machines to a given depth.

(ii) The number of machi-nes can be adjusted to suit the quantum of work. Flexibility is available.

(ii) The mixing is not uniform as with travelling plant or stationary plant.

(Hi) The whole processed section is ready for compaction at the same time.

(in) Heavy rain is likely to spoil the whole section.

(iv) A large out-put may be maintained.

(iv) In a dry climate, water lost by evaporation is difficult to replace.

(v) If excess moisture is to be got rid of as, for example, in a wet area, this is the only suitable method.

Travel ling plant

- (») Accurate propoition- ing of added water possible.

(i) The cost of plant initially is high.

(ii) Uniform mixing obtained.

(ii) Is suitable for concentrated and large/ quantum of work.

(Hi) Short mixing time is involved.

(Hi) Minor breakdowns can cause considerable dislocation.

(iv) Uniform surface can be obtained.

(v) Depth of lift can be accurately controlled.

(vi) It has the highest out-put for given expenditure of plant and labour.

Type Advantages Disadvantages

3. Stationar Plant

y (i) Accurate proportioning of mixture and water is possible.

(») Expensive if in-situ soil is to be processed.

(ii) The depth can be easily and accurately controlled.

(m) Material must be compacted as delivered and not as a complete section.

(Hi) Concrete mixers can be used.

(iv) Losses of moisture during mixing and transporting are small.

(v) Suitable for location where form work is needed, as in the case of sandy layers where vibrators are needed.

(vi) No additional haulage in soil has to be taken from a borrow pit.

17*10*4. Intermediate or appropriate technology for soil stabilisation The use of simple tools, implements and equipment can be beneficial in soil-stabilisation work in many ways. Firstly, it can lend itself to a reasonable control over the quality of the work, which is so essential for the success of the specification. Secondly, it can be suitable for a large quantum

Page 86: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

81

of work which is to be completed in a tight schedule. Thirdly, it does not do away with labour totally, and hence is not inappropriate to labour-surplus economies. The implements that are frequently used are the agricultural attachments such as disc harrows, disc ploughs, grader blades, rotillors etc. which can be conveniently towed by a small agricultural tractor or even by animal power. Water tankers for adding water can be pneumatic-wheeled and pulled by bullocks. The Central Road Research Institute has developed a simple equipment known as the Rotillor which is a versatile multi-purpose machine suitable for agriculture as well as for road making. For road making, the machine scarifies the top soil upto the required depth, pulverises the soil and mixes the soil and stabiliser. The equipment is towed by an agricultural tractor. QUESTIONS 1. (a) Define the term soil stabilisation. (6) What is the purpose of soil stabilisation?

Page 87: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

82

6 ROAD MAINTENANCE

6.1 Pavement Evaluation

6.1.1 Introduction

Pavement evalution is a techinque of assessing the condition of a pavement, both structurally and from the point of view of surface characteristics. It is also known as pavement condition survey and rating of pavement. Pavement evaluation is a handy tool in the hands of a highway engineer and serves a variety of purposes, such as : 1. To research on the performance of pavements of different specifications over a period of time. 2. To assess maintenance needs such as patch repairs, renewals and reseating. 3. To assess the need for structural overlays on distressed pavements.

6.1.2 Methods of Pavement Evaluation The methods available for pavement evaluation are : Visual rating Pavement Serviceability Index Concept Roughness Measurements Benkelman Beam Deflection Method. the Falling Weight Deflectomenter

6.1.3 Visual Rating Visual rating is a simple method of inspecting the pavement surface for detecting and assessing the amount and severity of various Sypes of damage. The usual manifestation of distress or damage occurs in the form of : 1. rutting 2. corrugations 3. ravelling 4. flushing 5. alligator cracking 6. extent of repairs 7. longitudinal cracking 8. transverse cracking. There are various methods of visual rating in use by different organisations the world over. One of the most widespread methods was initially developed at the Texas A and M University (Ref. 1) and is commonly known as the Deduct Value or Deduct Point method. In this method, certain deduct points are associated with specific values of various distress factors. The deduct points indicate the relative importance of the distress type. These deduct points are then subtracted from an established "perfect" score (usually 100) to arrive at the overall rating score of the pavement. Table 25'1 gives the deduct points for various levels of distress. There is as yet no rating system developed for Indian conditions though there is a great need of developing one. Table 25.1 Deduct values for flexible pavement

Types of Distress Degrees of Distress Extent or Amount of Distress

( 1 ) (2) (3)

Rutting Slight 0 2 5 Moderate 5 7 10 Severe 10 12 15 Ravelling Slight 5 8 10

Page 88: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

83

Moderate 10 12 15 Severe 15 18 20 Flushing Slight 5 8 10 Moderate 10 12 15 Severe 15 18 20

Corrugations Slight 5 8 10 Moderate 10 12 15 Severe 15 18 20 Alligator cracking Slight 5 10 15 Moderate 10 15 20 Severe 15 20 25 Patching Good 0 2 5 Fair 5 7 10 Poor 7 15 20 Failures - 20 30 40 Deduct Points for Cracking

Sealed Partially Sealed Not Sealed 1) (2) (3) ( 1 ) (2) (3) ( 1 ) (2) (3)

Longitudinal Cracking Slight 2 5 8 3 7 12 5 10 15 Moderate 5 8 10 7 12 15 10 15 20 Severe 8 10 15 12 15 20 15 20 25 Transverse cracking Slight 2 5 8 3 7 10 3 7 12 Moderate 5 8 10 7 10 15 7 12 15 Severe 8 10 15 10 15 20 12 15 20

6.1.4 Pavement Serviceability Index (PSI) One of the major contributions of the AASHO Road Test was the development of a rating system involving the measurement of permanent deformation, riding quality and the extent of cracking and patching (Ref. 2, 3). The rating is well-known by the term Present Serviceability Index (PSI) and is probably the most widely used pavement rating measure in existence today. The following equations give the value of PSI for flexible and rigid pavements :

In the above equations: PSI = Present Serviceability Index SV = Slope variance over a 22.5 cm length, giving an index of the longitudinal profile RD = Rut depth under al'2m straight edge C=Per cent of total area showing distress in terms of cracked area P=Per cent of total area showing distress in terms of patched area. In the AASHO Test, the longitudinal profile was monitored by the CHOLE Profilometer.

6.1.5 Roughness Measurements The riding quality of a pavement is determined to a large extent by its structural adequacy, the traffic load repetitions it has been subjected to the specifications adopted for the surfacing initially

Page 89: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

84

and the maintenance inputs. Hence a measure of the pavement performance can be obtained by monitoring its roughness. In view of the importance of the subject, a detailed account of roughness measurement is given later.

6.1.6 Benkelman Beam Deflection An evaluation of the structural performance of flexible pavements can be obtained by the Benkelman Beam Deflection method. The Lacroix deflectograph serves the same purpose. Pavement sections, which have been subjected to traffic deform elastically under a load. The elastic deflection depends upon various factors, such as : 1. Subgrade soil type. 2. Moisture content and compaction of subgrade soil. 3. Pavement thickness, composition, quality and condition. 4. Drainage conditions. 5. Pavement surface temperature. 6. Wheel load. The Benkelman beam and the Lacroix Deflectograph measure the deflections under standard wheel load conditions. Two kinds of deflection measurements are possible: 1. Rebound deflection, which is the recoverable deflection or the elastic deflection. In a well-designed road, the deflection is entirely elastic and recoverable. 2. Residual deflection, which is the non-recoverable deflection. As a pavement ages, it loses a portion of its elastic properties and a permanent deflection takes place. The Benkelman beam is a handy instrument which is most widely used for measuring deflection of pavements. The instrument is illustrated in Fig. 25.1.

It consists of a lever 3.66m long pivoted 2.44 m form the end carrying the contact point which rests on the surface of the pavement. The deflection of the pavement surface produced by the test load is transmitted to the other end of the beam where it is measured by a dial gauge or recorder. The movement at the dial gauge end of the beam is one-half of that at the contact point end. The load on the dual wheel can be in the range 2.7 to 4.1 Tonnes. The CGRA procedure of measuring the rebound deflection is. as follows: 1. Select 10 points along the outer wheel path (i.e. 60 cm from the pavement edge) for each lane. 2. Bring the rear dual wheel assembly of the truck near the marked point and insert the probe of the beam between the dual wheels so that the top rests on the road where the deflection is to be measured. The dual wheels are centred over the marked point. 3. A standard wheel load of 4085 kg is used for the test, the tyre pressure being 1560 KN/M2. 4. The dial gauge reading is noted initially in the position described under 2 above. 5. The truck is driven forward at a slow speed and dial gauge readings are taken when the truck stops at 2.7 m and 9 m from the measuring point, and when the rate of recovery is equal to 0"025 mm per minute or less.

Page 90: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

85

6. Pavement temperature is recorded. 7. The final and intermediate dial readings are subtracted from the initial reading. If the differential readings obtained compare within 0.025 mm, the actual pavement deflection is twice the final differential reading. If the differential readings do not compare to 0'025 mm, twice the final differential reading represents the apparent pavement deflection. The true deflection is obtained by the formula:

where XT=True pavement deflection XA=Apparent pavement deflection Y=Vertical movement of the front legs, i.e., twice the difference between the final and intermediate dial readings. The WASHO procedure, known as creep load method, is similar to the above, except that the truck rear is initially located 1.2 m behind the selected point. The probe arm is located 1.2 m In front of the wheel. The initial reading is noted and the truck is moved forward at a creeping speed of 2 km/hr to at least 3 m past the tip of the beam. The maximum dial reading will occur when the wheels are in the line with the probe arm. This value is noted. After a reasonable length of time or when the dial needle has come to rest, the final reading is recorded. The maximum deflection is twice the difference between the initial and the maximum readings. The rebound deflection is twice the difference between the maximum reading and the final reading. The residual deflection is twice the difference between the final reading and the initial reading. Problem. A Benkelman mean was used to measure the deflection. The readings obtained on the dial gauge at positions of wheel indicated below are: Wheel positions Dial Beading 1. 2.

1 . 2 m behind selected point At selected point

0'06 mm 0'46 mm

3. 3 m in front of selected point 0'08 mm

Calculate the (1) maximum deflection (2) rebound deflection (3) residual deflection.

A Lacroix Deflectograph consists of a truck with a rear-wheel assembly, an arrangement for carrying the deflection measuring beam on the truck itself and an arrangement for advancing it intermittingly (Ref. 7). The truck advances at a constant speed (3 km/hour) while the measuring system consisting of a reference beam and sensor rods advances intermittingly. Each measuring cycle consists of the following sequence:

Page 91: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

86

The reference beam is placed in front of the rear axle of the vehicle in such a manner that the sensor roads are situated in the path of a twin rear wheel, outside the zone subjected to the deflection. The twin wheels advance to vards the sensor rods, entering into the deformed zone of the road. The deflection is recorded when the rear axle has passed the extremity of the sensor rod. The deflection recorded is maximum in this position. The reference beam is now pulled forward (4 to 6 metres) in front of the rear wheels to its initial position. The process is again repeated. The system is capable of giving an output of 15-20 km/day (600 measurements per km). The results can be recorded on tapes and analysed on a computer. The Dynaflect is another truck-mounted device for quick measurement of dynamic deflections. The Dynaflect carries contra-rotating masses in a small trailer and applies a maximum dynamic force of 2270 N at a fixed frequency of 8 Hz superimposed on a static load of 125 kg., and the same is transmitted to the road surface through two small rigid, wheels 05 m apart. The maximum deflection midway between the wheels and four other points along the centre line between the vehicle is recorded by velocity sensitive transducers. The equipment can be trailer mounted or carried on the front of a light vehicle. About 300 measurerrents at a single frequency are possible in a working day. The Dynaflect measures the shape of the deflected pavement near the point of maximum deflection. This shape is sensitive to changes in upper pavement layers and is relatively unaffected by the subgrade. 1 bus, the profile of the deflected shape provides sufficient information to charaterise the stiffness of the pavement.

6.1.7 Falling Weight Deflectometer Another simple instrument to measure the dynamic deflection is the Falling Weight Deflectomenter (FWD), which drops a weight of 150 kg from a variable height on to a spring system. This in turn transmits a load pulse of 28 ms duration to the road surface through a circular plate. A maximum peak load of 60 Kn develops a deflected dish that can be recorded by upto five velocity-sensitive transducers, arrayed radially from the loaded area. The equipment is carried on a single axle trailer. About 200 measurements can be taken daily. Fig. 25.2 gives the diagrammatic arrangement of the device.

Fig. 25-2. Diagrammatic arrangement of Falling Weight Defiectometer. The Benkelman mean and Deflectograph are used for designing the thickness of overlays of pavements.

6.1.8 Skid Resistance Surveys A smooth surface is dangerous to traffic, especially when the surface is wet and the vehicles move fast. While care is normally taken to construct reasonable skid-resistant surfaces, the passage of vehicles polish the aggregates. Excess bitumen tends to fatten the surface and render it slippery. An'evaluation of the skid-resistance of the surface at periodic intervals is needed to ensure that the roughness level has not fallen to dangerously low levels. This is accomplished by measurement of skid-resistance periodically.

Page 92: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

87

6.1.9 Pavement Deterioration Research

Pavements deteriorate due to traffic and environmental factors. The extent of deterioration is also a function of the initial pavement thickness and composition. The exact way in which a pavement deteriorates is of great importance to a maintenance engineer to work out the maintenance strategy and to a highway planner to work out the economic evaluation of schemes. Interest in this field is, therefore, increasing the world over. The Kenya stndy8 and the Brazilian study9 have determined the pavement deterioration models. It is also proposed to take up a similar study in India. A recent development in the field of pavement research and evaluation is the Heavy Vehicle Simulators (HSV). This machine is capable of applying wheel loads of upto 100KN through a dual or single wheel assembly on a pavement, and can apply upto 1400 repetitions of load per hour. Thus, upto half a million repetitions of load can be applied to a pavement in 20 to 30 days. This equipment can, therefore, save considerable time in testing a pavement under actual traffic. QUESTION 1. What are the methods of pavement evaluation? 2. Describe the Benkelman Beam and its use.

Page 93: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

88

6.2 Road Inventorying

6.2.1 Need for Road Inventorying

Road inventorying is a systematic procedure of collecting details of existing roads. It serves a variety of purposes, such as: Assessment of deficiencies in the existing system in regard to land width, cross-sectional elements, geometries, surface type, riding quality, cross-drainage structures, traffic signs, pavement markings. Such an assessment will facilitate planning of improvements, fixation of priorities and allocation of resources. Assessment of maintenance needs with a knowledge of accurate road length, pavement width and specifications, terrain, rainfall intensity etc. Assessment of the hydraulic and structural adequacy and carriageway width of cross-drainage structures, with view to plan for their improvements.

6.2.2 Road Features Covered by Inventorying A comprehensive system of road inventorying should covers many features of the road as possible. A list of such features given in Table 26'1. Table 26 1 Road features to be covered by inventorying

A Highway Classification

1. Name of highway

2. Classification

3.Number Total Length B Right of Way From Km To Km Width (m) C Urban/Rural Roads

From Km To Km

Urban Sections

Rural Sections

D Terrain From Km To Km Plain Rolling Hilly E Pavement Width

From Km To Km Pavement width Single width/ Intermediate/ Double lane/ Four lane

F Pavement surface type

From Km To Km Surface type Earth/WBM/ Gravel/ ST/AC/CC

G Pavement ride quality

Km Roughness (IRI)

Page 94: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

89

H Shoulder type From Km To Km Shoulder Type

Earth/Gravel/ST J Horizontal curvature

Location Radius

K Vertical Profile From Km To Km Gradient (+/-) L Junctions Location Type M Culverts/Bridges

Location Type Width

Structural Rating

Hydraulic Adequacy

6.2.3 Periodicity of Inventorying A road inventory which is out-of-date is not of much use. It therefore has to be updated at periodic intervals. An interval of 5 years is considered satisfactory.

6.2.4 Manual Methods of Inventorying Manual methods of inventorying involve engineering surveys of alignment, vertical profile, and other physical measurements. They are tedious and time-consuming and represent large manpower requirements. In view of the difficulties involved, they cannot be routinely carried out and require special effort.

6.2.5 Instrument-Aided Inventorying Since manual method of road inventorying is tedious, instrument aided methods are now being followed. This is normally accomplished by an instrumented car containing the following: An accurate distance measuring device, actuated from the speedo-cable of the car, having an accuracy of 20 m. A gyroscope for measuring horizontal curvature, which takes the direction readings at the beginning and the end of each horizontal curve, along with the corresponding distance readings. The deflection angle and radius can thus be computed from these readings. A gradometer, for indicating the per cent upward or downward gradient as the car moves along. A car-mounted bump-integrator which gives the roughness reading for each kilometre. In addition to the above readings, the observer in the car can also record the terrain, pavement surface type, urban or rural sections, shoulder type and location of junctions and their type. The above data can be supplemented by manual data collection on details of cross-drainage works.

6.2.6 Computer-Aided Road Data Bank System The storage and retrieval of data is rendered easy if computer-aided Management Information System is adopted. Apart from storing the road inventory data, the data bank can also include traffic census data, particulars of maintenance inputs (renewals, resurfacing etc.), soil particulars, drainage aspects etc.

Page 95: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

90

6.2.7 QUESTION 1. (a) What is Highway Inventorying? (b) How is Highway Inventorying accomplished?

Page 96: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

91

6.3 Highway Maintenance

6.3.1 Need for Maintenance

A highway facility deteriorates in its characteristics due to various causes. These are : Traffic Factors Environmental Factors

(a) Traffic Factors The traffic operating on the facility causes ravelling, rutting, corrugations, cracking, loss of material, loss of skid-resistance and structural deformation. The extent of deterioration depends upon the intensity of traffic, especially the wheel load and its repetitions. Iron-wheeled traffic can be significance in the case of water-bound macadam roads and earthen roads.

(b) Environmental Factors The external influence of environmental factors such as rainfall, snowfall, temperature variation and atmospheric conditions can cause deterioration of the pavement. Rainfall causes erosion of shoulders and slopes and ingress of water into the pavement structure and subgrade and affects the performance of drainage structures. Snowfall can cause ingress of moisture into the pavement structure and subgrade and result in frost action. It can also disrupt traffic. Temperature variations can soften the binder and affect the performance of bituminous surfaces and cement concrete pavements Atmospheric action can oxidise the binder and cause deterioration. In addition to the above, the extent of deterioration and its rate are governed by the standards to which a facility was designed initially If a facility is designed to higher standards initially, its maintenance needs will be lower than if it is designed to lower standards initially. The economic benefits of a well-planned maintenance policy are : Reduction in road user costs, such as vehicle operating costs, travel time savings and accident costs. Reduction in the level of future maintenance and rehabilitation costs (remember : a stitch in time saves nine), Reduction or prevention of the economic loss due to road closures. From the above, it is clear that a good policy of highway maintenance should be one of the aims of any highway department.

6.3.2 Assessing Maintenance Needs Till recently, the assessment of maintenance needs was done by intuition and past experience of the highway engineer. He used to travel on his roads, visually Inspecting the condition of the surface and its extent of deterioration. The travel in inspection vehicles used to enable him to judge the riding quality, his accumulated experience used to guide him in determining the periodicity and specifications for resurfacing and resealing. While in India the above system is still in vogue, in the advanced countries great strides have been recently made in assessing maintenance needs on a more scientific and exact basis. The steps Involved in such a system are: 1. Evaluation of the pavement characteristics by various methods. 2. Development of minimum standards for road characteristics like roughness and skid resistance. 3. Provision of the needed maintenance inputs based on (1) and (2) above at appropriate periodicity.

Page 97: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

92

The selection of minimum standards for maintenance can be scientifically done if research is conducted on the deterioration of road characteristics over a period of time under traffic and the road user costs under different levels of road characteristics. The most common road characteristic used for this purpose is roughness. It is generally observed that a road deteriorates in its roughness over time under traffic, due to cracking, ravelling, rutting, deformation etc. When the deterioration reaches such a level that the rioad user costs mount up, it is advisable to resurface the road and restore it to its original condition. This principle is illustrated in Fig. 27 1. The curves pertaining to road deterioration as a function of age (or equivalent standard axles) can be constructed after careful research.

Fig. 27-1. Typical road deterioration-vs-age curve Some organisations have fixed standards for road characterises for purposes of a good maintenance management policy. E.g. Standards for skid-resistance recommended in the Marshall Committee (U.K.) Table 27-1 Recommended Roughness Values for Roads in India (mm/km measured on towed fifth wheel bump integrator) Surface Type Road Condition Good Average Poor Very Poor 1. Asphaltic concrete 2000 - 2500 2500 - 3500 3500 - 4000 Over 4000 2. Premix bituminous carpet 2500 - 4500 4500 - 5500 5500 - 6500 Over 6500 3. Surface dressing 4000 - 5000 5000 - 6000 6500 - 7500 Over 7500 4. Water-bound macadam or gravel

8000 - 9000 9000 - 10000 10000 - 12000 Over 12000

Resurfacing can be done when the roughness values reach the lower values under the column "poor" in the above Table.

6.3.3 Maintenance of Earth Roads Earth roads form a major percentage of rural roads in India and hence their efficient maintenance is of great importance. Because of the low specifications (inadequate embankment height, small roadway width and low cost drainage arrangements), good maintenance can preserve the assets and prolong their life. The principal maintenance operation consists of maintaining the cross-section by grading and dragging.

(a) Grading The shaping and sectioning of an earth road «s best done by blading with a grader or motor grader. A grader of about 110 HP is suitable for the purpose. In India, it is most unlikely that mechanical graders are available for routine maintenance operations. Manual methods should include making up ruts and deformations by additional soil from borrow pits and restoring the

Page 98: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

93

camber. If iron-tyred traffic is heavy and ruts are formed, the ruts can be rilled by quarry rubbish, gravel or other inferior local materials.

(b) Dragging Dragging stops the formation of corrugations. A typical drag, which can be towed by animal power, by men or by motor grader, is illustrated in Fig. 27*2 (Ref. 2). Dragging does not restore the cross-section of the road.

Fig. 27-2. Drag.

(c) Rolling If a power roller is available, the earth surface should be rolled and compacted after grading and dragging. A light sprinkling of water can be done if rolling is done in dry season.

(d) Filling of rain-cuts Rain-cuts in the embankment slopes should be filled up after the rainy season. Turfing prevents rain erosion.

6.3.4 Maintenance of Gravel Roads Gravel roads (also known as murram roads) are very common in Kenya. The maintenance operations involved are filling local depressions, grading, dragging, rolling and re-gravelling.

(a) Filling local depressions Local depressions and longitudinal ruts should be filled up by adding fresh materials of the same specifications as the original material. Light sprinkling and tamping with hand rammers will help in compacting the material.

(b) Grading Grading is an operation intended to restore the camber and shape of the gravel surface. A motor grader is ideal for this purpose. For gravel roads, heavy grading is inadvisable without the provision of additional surfacing material if the remaining thickness of gravel is less than 75 mm.

(c) Dragging One of the common defects that develops in a gravel road is corrugations. Dragging can stop the formation of corrugations.

(d) Regravelling Re-gravelling is necessary to make up the loss in material caused by the combined action of traffic, rain and wind. The loss per year is about 25 mm thickness. Regravelling is done once in

Page 99: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

94

2-5 years. Additional gravel, 25-75 mm loose thickness is spread after scarifying the old surface. Wafer is sprinkled to facilitate compaction which is done preferably at optimum moisture content. The layer is rolled by a power roller.

6.3.5 Maintenance of Water-bound Macadam Roads Untreated water-bound macadam is a common specification. Water-bound macadam surface deteriorates in the following typical ways : 1. Formation of ruts 2. Formation of potholes 3. Formation of corrugation 4. Ravelling 5. Damaged edges. Formation of ruts is caused by excessive camber and preponderance of iron-tyred traffic. Ruts are made good by rut-renewal, which consists of (i) cleaning and watering the rut, (ii) scarifying and removing the stones to an approximately rectangular section with fiat bottom and vertical sides, (iii) filling the section with salvaged metal and fresh metal, (iv) rolling with the addition of screenings, gravel and watering, (v) finally spreading 6 mm sand layer. Pot-holes are formed due to lack of binding properties in the binder material, poor quality of stones, local sub-grade failure or defects in consolidation. Pot-holes are remedied by patch repairs, The area to be patched is cut to a rectangular or square shape with vertical sides. The sequence of operations for laying patch material is the same as in rut renewal. Hand rammers can be used for patch repairs instead of power rollers. Corrugations result in a wavy surface, causing discomfort to travel. Corrugations are caused by a variety of factors such as: 1. Defective rolling Lack of control in rolling can result in corrugations.

Especially jerks and non-uniform rolling speed can cause corrugations.

2. Vibrations set up by pneumatic tyres

Pneumatic tyred vehicles running at speed cause vibrations to be set up in the spring loaded axles. These vibrations are harmonic in nature and cause waves.

3. Vibrations set up due to braking

At locations where constant braking of vehicles is involved, such as a bus stop, vibrations are set up in the vehicle. These eventually cause corrugations.

4. Use of excessive quantity of blinding material

Excessive blinding material at the surface tend to get deposited in regular waves, depending upon the spring action in the wheels.

5. Transverse picking of WBM surface

If during laying a thin renewal coat of WBM, transverse picking has been done, corrugations are bound to result. Picking should therefore be randomised or longitudinal.

When corrugations have been formed, the excess blinding material that has got deposited in ripples should be immediately removed by dragging or brooming. If corrugations have developed in the WBM course itself, a renewal layer is needed. This should be laid after careful scarifying of the corrugated surface. 27'5'6. Ravelling is the phenomenon under which stones get loosened and are freely scattered on the surface. Ravelling is due to (i) lack of binding properties in the binding material (ii) inadequate consolidation (iii) use of too plastic a binder (iv) excess quantity of binder and (v) evaporation of moisture in the hot weather. Ravelling can be detected early by the presence of

Page 100: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

95

tiny hairline cracks. The tendency can be remedied by blinding with a good binder and watering the surface. Damaged edges, are caused by lack of shoulder support. Unless prompt action is taken, the damage can progressively travel to the inner portions of the carriageway. The damaged portion is removed and renewed with fresh material.* Rolling the edge and the shoulder should be done simultaneously. Reverse camber in the shoulders should be remedied by grading. Water bound macadam surface gets worn due to traffic and needs periodic renewal. The periodicity of renewal varies from 2-6 years, depending upon traffic, quality of aggregates etc. Renewal is done in layers of 50 to 75 mm loose. Renewal consists of the following sequence of operations: 1. Cleaning the surface of all dust and caked mud by wire brushes and brooms. 2. Picking up and scarifying the surface after moistening the surface 3. Screening the salvaged materials. 4. Forming stable shoulders by additional earthwork. 5. Spreading the salvaged materials and additional material. 6. Dry rolling with a power roller. 7. Wet rolling. 8. Application of screenings. 9. Spreading binding material and rolling. 10. Spreading a 6 mm layer of coarse sand. 11. Curing by light sprinkling of water for 15 days. Traffic can be allowed after 2-3 days.

6.3.6 Maintenance of Bituminous Surfaces

(a) Defects, symptoms, causes and remedies A bituminous surface wears out due to (») traffic (it) weather, such as ingress of water, loss of volatiles in the binder and oxidation of binder (Hi) inadequacies in the initial specifications and construction standards. Table 27*2 lists out the type of distress, symptoms, probable causes and possible types of treatments (Ref. 5).

Page 101: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

96

Table 27 2 Symptoms, causes, and treatment of defects in bituminous suafacings

Types of distress Symptoms 1

2

Probable causes 3

Possible types of treatment 4

A. Surface defect

1. Fatty surface

Collection of binder on the surface

Excessive binder in premix, spray or tack coat; loss of covet aggregates, excessively heavy axle load.

Sand-blinding; open-graded pre-mix; liquid seal coat ; burning of excess binder ; removal of affected area.

2. Smooth surface Slippery Polishing of aggregates under traffic, or excessive binder.

Resurfacing with surface dressing or premix carpet.

3. Streaking

Presence of alternate lean and heavy lines of bitumen

Non-uniform application of bitumen, or at a low temperature Application of a new surface.

4. Hungry surface

Loss of aggregates or presence of fine cracks

Use of less bitumen or absorptive aggregates Slurry seal or fog seal.

B. Cracks

1. Hair-line crack Short and fine cracks at close intervals on the surface

Insufficient bitumen, excessive filler or improper compaction

The treatment will depend on whether pavement is structurally sound or unsound. Where the pavement is structurally sound, the cracks should be filled with a low viscosity binder or a slurry seal or fog seal depending on the width of cracks. Unsound cracked pavements will need strength-ening or rehabilitation treatment.

2. Alligator crack Inter-connected cracks forming series of small blocks

Weak pavement, unstable conditions of subgrade or lower layers, excessive overloads or brittleness of binder

3. Longitudinal crack Cracks on a straight line along the road

Poor drainage, shoulder settlement, weak joint between adjoining spreads of pavement layers or differential frost heave

4. Edge crack Crack near and parallel to pavement edge

Lack of support from shoulder, poor drainage, frost heave, or inadequate pavement width

5. Shrinkage crack

Cracks in transverse direction or inter-connected cracks forming a series of large blocks

Shrinkage of bituminous layer with age

6. Reflection crack Sympathetic cracks over joints and cracks in the pavement underneath

Due to joints and cracks in the pavement layer underneath

C. Deformation

1. Slippage

Formation of crescent shaped cracks pointing in the direction of the thrust of wheels

Unusual thrust of wheels in a direction, lack or failure of bond between surface and lower pavement courses

Removal of the surface layer in the affected area and replacement with fresh material.

Page 102: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

97

Types of distress Symptoms 1

2

Probable causes 3

Possible types of treatment 4

2. Rutting Longitudinal depression in the wheel tracks

Heavy channelised traffic, inadequate compaction of pavement layers, poor stability of pavement material or heavy bullock cart traffic

Filling the depressions with premix material.

3. Corrugations Formation of regular undula-tions

Lack of stability in the mix, oscillations set up by vehicle springs, or faulty laying of surface course

Scarification and relaying of surfacing, or cutting of high spots and filling of low spots.

4 Shoving Localised bulging of pavement surface along with crescent-shaped cracks

Unstable mix, lack of bond between layers, or heavy start-stop type movements and those involving- negotiations of curves and gradients

Removing the material to firm base and relaying a stable mix.

5. Shallow depression Localised shallow depressions Presence of inadequately compacted pockets Filling with premix materials.

6. Settlement and upheaval Large deformation of pavement

Poor compaction of fills, poor drainage, inadequate pavement or frost heave

Where fill is weak the defective fill should be excavated and redone. Where inadequate pavement is the cause, the pavement should be strengthened.

D. Disintegration

1. Stripping Separation of bitumen from aggregates in the presence 61 moisture

Use of hydrophilic aggregate, inadequate mix composition, continuous contact with water, poor bond between aggregate and bitumen at the time of construction, etc.

Spreading and compacting heated sand over the affected area in the case of surface dressing; replacement with fresh bituminous mix with added anti-stripping agent in other cases.

2. Loss of aggregate Rough surface with loss of aggregate in some portions

Ageing and hardening of binder, stripping, poor bond between binder and aggregate, poor compaction etc.

Application of liquid seal, fog seal or slurry seal depending on the extent of damage.

3. Ravelling

Failure of binder to hold the aggregates shown up by pock marks of eroded areas on the surface.

Poor compaction, poor bond between binder and aggregate, insufficient binder, brittleness of binder etc.

Application of cutback covered with coarse sand, or slurry seal, or a premix renewal coat.

4. Pot-hole Appearance of bowl shaped holes, usually after rain

Ingress of water into the pavement, lack of bond between the surfacing and WBM base, insufficient bitumen content etc.

Filling pot-holes with premix material, or penetration patching.

5. Edge-breaking Irregular breakage of pave-ment edges.

Water infiltration, poor lateral support from shoulders, inadequate strength of pavement edges, etc.

Cutting the affected area to regular sections and rebuilding with simultaneous attention paid to the proper construction of shoulders.

Page 103: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

98

(b) Pot-hole repair (patch repair) The amount of patching needed to make up pot-holes and localised failures may vary from 0 to 25 per cent of the surface area annually. Patching prolongs the surface life until a time will come when it will be more economical and desirable to renew the surface entirely. Patching can be done by (i) sand premix, (ii) open-graded premix (iii) dense-graded premix (iv) penetration patching or (v) surface dressing Dense-graded premix patch is rarely used and only where the existing surface itself is dense-graded asphaltic concrete. Surface dressing (one or two coats) can be done for existing surfaces with a similar specifications and where the traffic is not too heavy. Patching consists of the following sequence of operations: 1. Cleaning the area by brooming 2. Trimming the sides vertically and the shape to a rectangle or square and levelling the bottom. 3. Painting the sides and bottom of the hole with a tack coal if a premixed material is used. 4. Following the regular specifications of the treatment. 5. Rolling or hand tamping and checking the profile with straight edge. Sealing the surface is resorted to rectify hungry surface, repair cracks, and arrest loss of aggregates. Sealing can take the form of the following treatements : 1. Liquid seal 2. Fog seal 3. Slurry seal. Liquid seal is an application of a binder (penetration grade or emulsion) at 9.8 kg/10 sq m followed up with a spread of cover aggregates, 6.3 mm nominal size, at a rate of 0.09 cu m/10 sq m and rolling in position. Fog seal is a spray of slow-setting emulsion diluted with equal amount of water at a rate of 0.5-1 litre sq m. Traffic is allowed after the seal sets in. It is provided over a hungry surface, a cracked surface, a surface where there is loss of aggregates and over a surface exhibiting ravelling. A slurry seal is the application of a slurry composed of slow-setting emulsion, water and aggregates to a thickness of 5-10 mm. The emulsion and water are 18-20 per cent and 10-12 per cent respectively of the weight of aggregates. The slurry is spread at the rate of 200 sq m per tonne. No rolling is needed. Slurry seal is provided over a hungry surface, cracked surface, a surface where there is loss of aggregates and over a surface exhibiting ravelling. Because of low viscosity of the binder, the specification results in sealing voids and cracks. When patching becomes too high, it is more economical to renew the surfaces with a single cost surface dressing (SD), a 20 mm premix chipping carpet (PC) or a mix-seal (MS). Such renewals are part of preventive maintenance and prolong the life of a pavement. They result in a better riding quality when the surface has deteriorated. The periodicity of renewals and their type are given in Table 27-3.

6.3.7 Maintenance of Cement Concrete Surface A well designed and properly constructed cement concrete pavement needs hardly any maintenance. In fact, this is one of the strong points of this specification. However, defects do appear due to the following reasons:

Page 104: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

99

1. Ingress of water to the subgrade causing uneven settlement especially through joints. 2. Inadequate design and faulty workmanship.

(a) Cracks The common defect noticed in a cement concrete slab is the appearance of cracks. Cracks can be shrinkage cracks, structural cracks, contraction cracks, corner cracks and warping cracks. They can be of varying width. Usually hair cracks are not dangerous since they do not admit water to the subgrade. Medium and wide cracks are harmful since they can cause progressive destruction of the subgrade support by allowing water to percolate. Cracks are filled up by liquid substances such as bituminous emulsions, cutback bituminous or joint sealing compounds, whose basic ingredient is bitumen. Before the cracks are sealed, they are cleaned of dust and foreign matter. Compressed air jets and nozzles are useful to achieve this. The dry joints are then filled with appropriate bituminous binder poured by cans. The poured material is topped up with sand or fine chips to prevent the removal of binder under traffic.

(b) Joints The maintenance of joints consists in examining whether the joints are properly sealed and, if not, to immediately seal them. If the preformed joint filler has rotted and deteriorated, it should be removed and substituted by a fresh compressible filling material. The sealing material is then poured.

(c) Patching of slabs A variety of defects, such as scaling, spalling, depressions, irregularities and failures, can occur locally in a slab. In such cases, it is necessary to patch up the defective portions immediately to arrest further deterioration. Bituminous premix materials are very widely used for this purpose. When the distress is more pronounced, concrete patch-work is resorted to. Such patches are of regular geometrical shapes, without acute-angled corners. The sides are first trimmed and made vertical and fresh concrete is laid and tamped.

(d) Mud-pumping and blowing When the subgrade becomes moist with free accumulation of water, heavy axle loads passing over the slab will eject water and mud through the joints, cracks and pavement edges. This phenomena is known as mud-pumping and blowing. When a pavement exhibits this phenomenon, the joints and cracks should be inspected and defective ones refilled and sealed. A bituminous under-seal can be pumped underneath the slab to prevent recurrence of the defect. This is accomplished through drilled holes in the slab. A viscous binder is preferred. This fills voids in between the slab and the subgrade.

6.3.8 Maintenance of Shoulders Shoulders give lateral support to the pavement and provide room for wheels when crossing and overtaking on narrow pavements. They are also used by vehicles for parking. Shoulders constructed of gravel, WBM or bituminous specifications are maintained in the same manner as the pavement of such specifications. Shoulders of earth or gravel need periodic attention. Proper maintenance of cross-section and camber are the key to successful pavement performance. Shoulders should never be allowed to be depressed below the pavement level. Reverse camber causes a ditch at the junction of the pavement and the shoulder, where water accumulates. This should be avoided by proper blading Rain cuts should be made up by fresh earthwork.

6.3.9 Maintenance of Slopes of Embankments

Page 105: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

100

Embankment slopes get easily damaged due to rains. Rain cuts, unless properly attended to in time, erode the slopes right up to the pavement edges and damage the pavement ultimately. Turfing is one of the easiest and most effective ways of maintaining the slopes. Turfing checks erosion and improves the aesthetics of the road vastly. Turf should be mowed periodically, preferably before the monsoons. The slopes of embankments subjected to inundation and flooding are protected often with boulder pitching. They tend to get dislodged due to slips and settlements. The damaged stones should be removed, the slopes made up and pitching redone with adequate granular bedding.

6.3.10 Maintenance of Bridges and Culverts

(a) Bridge and culvert register The maintenance of bridges and culverts is greatly facilitated if a register containing the salient features of structures is maintained. The structures should be numbered as per standard practice. Thus, a number 343/3 would indicate that the structure is the third in the 343rd mile on kilometre. The number should be painted prominently in the parapet of the structure. The register should give bring particulars such as : 1. Number of structure 2. Date of construction 3. Type of structure 4. Waterway (number and length of spans) 5. Foundation particulars 6. Behaviour of structure during floods (HFL to be indicated). 7. History of periodic maintenance (painting, pointing of masonry, re-girdering etc.).

(b) Periodic Inspection The structures should be periodically inspected at least once in a year by (1) Junior Engineers in case of culverts of waterway up to 6 m (2), Assistant Engineers in case of minor bridges (length 6-30 m), Executive Engineers in case of medium bridges length 30-150m) and Superintending Engineers in case of major bridges (length greater than 150 m). The following points should be noted during inspection: 1. Condition of foundations, and any signs of scour 2. Condition of substructure and any signs of damage 3. Condition of floor protection works, and signs of scour and dislodgement 4. Bearings: greasing, tilts, signs of corrosion 5. Superstructure: signs of cracks, corrosion 6. Condition of painting of steel girders 7. Signs of settlement 8. Condition of wing walls 9. Condition of guide bunds 30. Condition of approaches 11. Condition of wearing coat, hand rails, approach slab curbs, drainage spouts and guard stones. 12. H.F.L. reached 13. Condition of river channel and its banks 14. Adequacy of the opening 15. Condition of pipes in a pipe culvert and minimum cushion.

(c) Painting of steel bridges Steel members get corroded unless protected by painting. Painting should be done once in 6 to 12 years, depending on location and nearness to sea.

(d) Maintenance of masonry Repainting of joints of brick and stone masonry should be done if deterioration is noticed. All vegetable growth should be cleared. Roots of trees which are likely to cause disruption of the

Page 106: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

101

masonry of abutments and wing walls should be cleared. Weepholes of abutments and wing walls should not be allowed to clog.

(e) Scour Control of scour of foundation can be obtained by dumping boulders, construction of spurs and dumping a garland of concrete blocks or stone sausages around piers. Scour meters provide good information on the extent of scour.

(f) Bearings Metallic bearings deserve special attention. They should be cleaned un greased with a natural graphite grease.

(g) Expansion joints Expansion joints get dislodged and loosened frequently. They should be immediately restored.

(h) Weak and narrow structures Rating of bridges and culverts should be done periodically and the safe load displayed prominently on the structures.

6.3.11 Special Problems of Hill Road Maintenance Some of the special problems of hill road maintenance are: 1. Snow clearance 2. Slips and landslides 3. Drainage.

(a) Snow clearance Roads cold sub-tropical and polar regions get covered with snow. Snow clearance can be done manually or by special equipment (dozers, snow masters and snow blasts).

(b) Slips and landslides Slips and landslides are a common feature of hill roads. The causes for these and remedial measures to prevent them are discussed elsewhere. Read maintenance in areas subjected to slips and landslides poses severe problems. The greatest of them is quick removal of debris and restoration of traffic. Mechanical equipment like dozers are necessary.

(c) Drainage maintenance Maintenance of drainage structures is an important task in hill road maintenance. The quick and efficient removal of water prevents slips and landslides and road deterioration. Drainage arrangement such as catchwater drains, cross-drainage structures, side drains and burried drains should be inspected before the rainy season and cleared of all obstructions.

6.3.12 Maintenance Practice in Kenya

(a) 27121. Organisation The Kenya Ministry of Roads plays an oversight role on roads development and maintenance through four main agencies as follows:

Agency Abbreviation Responsibility Kenya National Highways Authority

KeNHA Primary Roads: i.e. class A, B and C

Page 107: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

102

Kenya Rural Roads Authority

KERRA Minor roads: class D, E and Special Purpose roads

Kenya Urban Roads Authority

KURA Roads in Urban Areas (excluding classified roads)

Kenya Roads Board

KRB Management of the Road Fund

(b) Types of maintenance operations Maintenance operations n Kenya fall under the following groups: 1. Routine Maintenance, including patching, earthwork, shoulders, drainage, road furniture, road signs, arboriculture. 2. Periodical Maintenance, including resealing (renewal of surface at specified intervals) and re-carpeting and/or strengthening 3. Special Maintenance, such as flood damage restoration, major, painting of steel girders, etc.

6.3.13 Maintenance Management System (MMS) A Maintenance Management System (MMS), also known as Pavement Management System (PMS), is a computer package which facilitates maintenance planning and optimal allocation of resources. Its main elements are: (i) a basic road data bank (ii) a pavement performance model (iii) selection of intervention levels and (iv) listing out priorities for maintenance (renewal and overlay) for a given budget. Many countries have developed and implemented their own MMS. Kenya is also in the process of developing one.

6.3.14 QUESTIONS 1. Describe why highway maintenance is needed. 2. How are maintenance needs assessed? 3. Describe how an earth road is maintained. 4. Describe how a gravel road is maintained. 5. Write short notes on corrugations in pavements 6. Describe how a water-bound-macadam road is maintained. 7. What are the common defects, symptoms, causes and remedies for bituminous surfaces? 8. Describe the operations of sealing of bituminous surfaces. 9. What is the current practice for periodic renewal of surfaces of National Highways? 10. Describe the maintenance of cement concrete roads.

6.4 Overlay Design and Construction

6.4.1 Need for Overlays

Pavements which have been in service deteriorate due to a variety of factors. A part of such deterioration can be made good by patching and periodic renewals. When the extent of deterioration is beyond such simple maintenance solutions, the pavement needs an additional overlay. Strengthening with such an overlay will overcome the structural inadequacy caused by traffic that has used the pavement so far and will enable the strengthened pavement to withstand the expected traffic in the design period.

Page 108: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

103

6.4.2 Overlay Design for Flexible Pavements

(a) Principles of design An overlay design differs from design of new pavement in that in the former the strength of the existing pavement is to be evaluated, whereas in the later the strength of the subgrade on which the new pavement has to be constructed is evaluated. Thus, overlay designs involve the following steps: 1. Estimation of the traffic to be carried by the overlaid pavement 2. Measurement and estimation of the strength of the existing pavement 3. Determination of the thickness and type of the overlay. The exact design of overlays by analytical methods is rather difficult. Most of the design methods are empirical.

6.4.3 Overlay Design Methods for Flexible Pavements

(a) Measurement of pavement strength After estimation of the future traffic, the next information needed for design is the strength of the existing pavement. Measurement of deflection of a flexible pavement is one of the indirect methods for assessing its strength. Most of the methods currently in use by various organisations round the world use deflection criterion as the basis of design. The appeal of this method is the ease and speed with which deflections can be measured, without disturbance of the pavement structure. The method is based on the assumption that there is a strong correlation between deflection and the stresses and strains developed in the subgrade. This assumption is not always correct and surface deflection is not uniquely related to pavement strength.

(b) TRRL procedure A detailed procedure for overlay design has been developed by TRRL. The method is based on extensive measurements of surface deflection and their relationship with performance obtained by TRRL during many years' work on road experiments. The basic types of design charts are given: Relationship between the existing deflection and the amount of traffic carried since construction, enabling an assessment of the time when it may require structural strengthening. Chart showing the thickness of rolled asphalt overlay to reduce the present deflection to a value consistent with the satisfactory performance under traffic which is forecast for the future. With these charts, it is possible to conclude whether any given section of pavement needs an overlay now or later, and if so, what is the thickness of the overlay.

(c) Asphalt Institute method In the U.S.A., the design procedure for asphalt overlays published by the Asphalt Institute is followed. The existing pavement is evaluated by measuring the surface deflection by the Benkelman beam. The thickness of the overlay is determined from the deflection and an estimate of the traffic to determined from the deflection and an estimate of the traffic to be carried. Traffic is expressed in terms of a Design Traffic Number (DTN) which is the average daily number of 8.2 Tonne single axle loads over the design period. A typical chart is given in Fig. 28.2.

Page 109: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

104

Fig. 28-2. Aspbalt Institute overlay design chart.

(d) Analytical methods Just as a flexible pavement can be designed both by empirical methods and analytical methods, so also it is possible to;: design overlay thickness by analytical methods in addition to the empirical methods described so far. The methods are based on sound theoretical formulation of pavement response using multilayer elastic systems. These have the advantage that they are much less dependent on local conditions and can be applied universally. They, however, suffer from the disadvantage that they are very complex, involving often computer analysis, and are thus beyond the reach of the average highway engineer.

6.4.4 Overlay Design Methods for Rigid Pavement Concrete pavements develop structural cracks if they are under-designed or if they have been subjected to heavy traffic. These slabs can be rehabilitated with a rigid or a flexible overlay, and thus given them a further lease of useful life.

(a) Types of rigid overlays Rigid overlays are those constructed with a cement concrete slab. There are three types of rigid overlays, viz. Bonded, or monolithic overlays, in which the thin overlay slab is bonded on to the existing slab after specially preparing the existing surface through acid-etching or scarifying using cold milling machines equipped with silicon carbide teeth and mortar coating. Such overlays act monolithically with the original slab and hence need the minimum thickness. Partially bonded overlay, in which the overlay slab is placed directly over the existing slab after cleaning the surface. Unbonded overlay (also called over-slabbing) consisting of a thick slab laid over a separation course. The separation course is laid over the existing slab. The overlay slabs acts independently of the underlying concrete slab. Fig. 28 3 gives the three types. Thin bonded overlays (minimum thickness 25 mm) are not recommended where the existing slab has severely failed. Partially bonded overlays (minimum thickness 120 mm) are also not recommended if the existing slab has severely failed. Unbonded overlays of a minimum thickness of 150 mm can be provided over badly failed slabs too.

Page 110: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

105

Fig. 28-3. Types of rigid overlays. Reflection cracks can be expected in thin bonded overlays. They are also usually expected in partially bonded overlays, but are not normally expected in unbonded overlays. Steel reinforcement is not normally used in thin bonded overlays. In partially bonded overlays, steel requirement is independent of the steel in the existing pavement. In unbonded overlays, steel requirement is entirely independent of steel in the existing pavement.

(b) Design of rigid overlays Various organisations have evolved empirical formulae for design of rigid overlays. The formulae of the Corps of Engineers and the Federal Aviation Agency are popular. These are given .below :

In the above formulae, h0 = overlay thickness required (inches) hm = thickness of monolithic slab required (inches) he = thickness of existing pavement slab (inches) C = Pavement condition factor = 1.00 when the existing pavement is in good condition

=0.75 when the existing pavement shows initial cracking. =0.35 when the existing pavement is badly cracked.

(c) Flexible overlays over rigid slabs

Flexible overlays can also be provided over inadequate concrete slabs. The disadvantage of this specification is that reflection cracks appear on the bituminous overlay. Such cracks can be eliminated only if the thickness of the overlay is substantial, say over 125 mm. Many empirical formulae and design procedures are available for determining flexible overlay thickness.

6.5 Skid Resistance

6.5.1 Importance of Skid-Resistant Surfaces One of the common causes of road accidents is skidding of fast-moving vehicles. The problem has been getting aggravated as the vehicle speeds have been increasing over the year (due

Page 111: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

106

to better vehicle design) and as the pavements are designed to provide a smooth riding surface. If a vehicle skids, the driver loses control of the vehicle and the resulting accident is normally of a serious nature.

6.5.2 Factors Governing Skid Resistance The factors governing skidding of vehicles can be grouped under the following four major heads: 1. Roadway factors 2. Vehicle factors 3. Traffic factors 4. Environmental factors

6.5.3 Measurement of Skid Resistance A common measure of skid resistance is the coefficient of friction between the tyre and road interface. Thus, if a vehicle travelling at a speed of v m/sec is suddenly braked such that the wheels are locked (prevented from rotating), the vehicle decelerates with a certain rate α m/sec2, and comes to a stop in a distance of d metres. If f is the coefficient of friction developed and m is the mass of the vehicle in kg, then equating the change in kinetic energy to the work done, the following equation results

Fig. 29.2. Braking car method of determining skid resistance.

Based on the above principles, a number of methods have been standardised for the measurement of skid resistance. The important ones among them are: 1. Stopping of test vehicles 2. Braking of trailers towed by vehicles 3. Braking of vehicles with a test wheel 4. Measuring [sideway force that develops when a wheel placed at an inclination side-slips ' 5. Portable Laboratory Instrument. In the stopping car method, a vehicle driving at a certain known speed is braked and the distance it takes to bring it to a stop is measured. Then Equation 29.2 gives the friction developed. In this method, arrangement for wetting the road surface can be made by sprinkling water. If a decelerometer is mounted on the vehicle, the deceleration can be directly recorded. Equation 29.3 then gives the friction factor developed. Instead of bringing the vehicle to a stop,

Page 112: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

107

the car wheels can be locked for a small duration, say one second, when the vehicle is travelling at a certain speed (say 50 KMPH) and the deceleration recorded. In the trailer wheel method the trailer wheel is locked and the force developed at the tyre-pavement interface is recorded by a suitable device. The ASTM measures the skid resistance in terms of a Skid Number (SN), which is obtained by multiplying the ratio of frictional force to normal load by 100. Thus :

In some methods, for example the Swedish Test vehicle method, a fifth wheel is mounted in the vehicle itself and is made to slip at various values. Slipping is achieved when a freely rotating wheel is braked so that its speed is reduced. The method in use in U.K. is to measure the sideway force coefficient (SFC). In the standard testing equipment, commonly known as the SCRIM (sideway force coefficient routine investigation machine), consists of a standard four-wheeled vehicle carrying a fifth wheel set at an angle of 20 degrees to the direction of travel. A smooth tyre (3 x 20 inch) is fitted to the fifth wheel which has a dead weight load of 200 kg. A water tank of 2750 litres capacity is carried by the chassis. Speeds in the range of 15-100 KMPH can be adopted. A common speed of measurement is 50 KMPH. About 50 km-70 km of road section can be tested in a day. The method most readily available to a highway engineer is the British Portable Tester

6.5.4 Standards for Skid Resistance In order to maintain the road surfaces in a reasonable rough condition, various authorities recommend minimum values of skid resistances depending upon the site conditions. The Marshall Committee Report on maintenance recommends certain values of skid resistance to be aimed at. These values are classified according to the site conditions. Table 29.1 Target values of skidding resistance proposed by the Marshall Committee in 1970

Page 113: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

108

The standards recommended for the USA in a publication by the Highway Research Board are reproduced here. Table 29.2 Interim Skid Resistance Requirements for Main Highways

Traffic Speed KMPH

Recommended Values of SN

Measured at Traffic Speed

Measured at 65 KMPH

50 36 31 65 33 33 80 32 37 100 31 41 120 31 46

6.5.5 Construction of Skid Resistant Surfaces

In order to achieve a good skid-resistant surface, care should be taken in the design and construction of surfaces. In particular* the following points deserve notice: 1. The aggregates should be selected carefully, with due consideration to their texture,

polishing characteristics, shape and gradation. 2. In bituminous surfaces, the skid-resistance is generally governed by the larger aggregates

which are coarser than 2.36 mm. In cement concrete surfaces, fine aggregates' control skid-resistance.

Page 114: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

109

3. Excess of bituminous binder should be avoided. 4. In cement concrete mixes, water cement ratio should be strictly controlled. 5. In cement concrete surfaces, the surface finishing operations (brooming, brushing,

dragging with burlap, belting etc.) determine the final texture of the surface and should be carried out with extreme care.

6. Special surfaces involving either naturally occurring hard polish-resistant aggregates or artificially prepared aggregates (like calcined bauxite) and a high adhesive epoxy resin are being used at difficult sites, where a high skid resistance is needed.

6.5.6 Maintenance of Skid Resistance of Surfaces

When the skid resistance of a surface falls below the desired minimum value, special treatments are provided to restore the skid resistance. Some of the proven expedients are: 1. If bituminous surfaces become fattened, due to excess of binder in the mix, sand or a

gritty material is sprinkled and rolled. 2. Pre-coated chipping carpets can be rolled into fat bituminous surfaces. 3. Bituminous surfaces having polished aggregates can be made rough by surface dressing. 4. Cement concrete surfaces which have become smooth can be roughened by acid etching,

grooving and bonding additional layers. Roughening the surface by subjecting the pavement to steel ball shots at high pressure has also been tried effectively.

6.5.7 QUESTIONS

1. What are the factors governing skid resistance of pavements? 2. How is skid resistance measured? 3. What are the practices for improving the skid resistance of surfaces ?

6.6 Pavement Roughness

6.6.1 Importance of Smooth Riding Surface

For the fast motor traffic, one of the desirable characteristics is a reasonably smooth riding quality. A smooth surface brings about many advantages. Some of them are : 1. Higher speeds: The smoother the road surface, the higher is the speed at which vehicles

can drive. 2. Less fuel consumption: The fuel consumed in a vehicle is proportional to the work required

to be done to overcome various resistances (air resistance, frictional resistance and grade resistance). The frictional resistance is a function of the coefficient of friction at type-road interface. Smoother surfaces thus bring about considerable fuel economy.

3. Less wear and tear of tyres: The life of a tyre depends to a large extent on the smoothness of the road surfaces. Rough roads shorten tyre life.

4. Less consumption of spare parts: Important spare parts of a vehicle such as the suspension system, springs, shock absorbers, body and chassis get punished more on rough roads than on smooth roads.

5. Riding comfort: Smooth roads result in high riding comfort. On the other hand, rough roads result in jerky motion and poor riding comfort.

6. Safety: Roads which are full of potholes, ruts and corrugations endanger the safety of travel since the possibility of sudden failure of vital parts increases on bad roads. However, extremely smooth roads are dangerous since they increase the chances of skidding Thus, the smoothness to be aimed at has to be a compromise between the conflicting needs of anti-skid properties and economic arid comfortable travel.

6.6.2 Need for Roughness Measurements

Page 115: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

110

Since roughness of a road is a major determinant of the safety, cost, comfort and speed of travel, its accurate measurement is of vital importance to a highway engineer. The important uses of roughness measurements are: 1. To assess maintenance needs 2. To assess quality of construction 3. For research purposes

6.6.3 What Constitutes Road Roughness Road roughness can be defined as "deviations of a travelled surface from a true planar surface with characteristic dimensions that affect ride quality, vehicle dynamics, dynamic pavement loads and pavement damage". The deviations from the true planar surface could be due to the surface texture, care in finishing operations, tolerances specified during construction, potholes, cracks, corrugations, rutting and pavement deformations.

6.6.4 Measurement of Road Roughness The methods of measuring roughness can be broadly grouped under two categories: 1. Direct measurement of the longitudinal profile. 2. Response-type instrument methods. The direct measurement of the longitudinal profile is an ideal and accurate method since it theoretically gives scaled reproductions of the pavement profile along a straight line. In practice, however, the range and resolution of the profiling devices are limited, but within these limits, the measurements may be called absolute. The well-known response-type of instruments are : 1. Bureau of Public Roads (BPR) Roughometer, developed as early as 1925 It is a single-wheel trailer which measures the uni-directional vertical movements of the damped, leaf sprung wheel by a mechanical integrator unit. The results are recorded in inches psr mile. The standard speed of measurement is 32 KMPH. 2. The British Towed Fifth Wheel Bump Integrator, which is basically a BPR Roughometer type instrument that has undergone considerable development at the TRRL (U.K.). 3. APL trailer, developed by the French Bridge and Pavement Laboratory (LCPC). 4. Mays Meter, which is car-mounted device, giving a paper plot, whose length at the end of a test is the raw roughness numeric for that test. The instrument can be operated a various speeds. 5. Car-mounted integrator unit of the TRRL Towed Fifth Wheel. The common disadvantages of all response-type roughness measurement systems are: 1. Absence of an internationally accepted conversion method to relate readings from different instruments. 2. Variability of readings depending upon speed of measurement. 3. Need for calibrating the instruments at periodic intervals. QUESTIONS 1. What is the importance of pavement roughness? 2. How is pavement roughness measured?

Page 116: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

111

7 TENDERS, CONTRACTS AND SPECIFICATIONS

7.1 Methods of Execution

Generally two methods are adopted for execution of roadworks in the country, viz. (t) departmental execution and (i») execution through contracts. Departmental execution is generally resorted to for small works such as maintenance and repair. It is also resorted to when sufficient response is not forth-coming from contractors. Generally, execution through contracts results in cheaper costs. Hence, the choice of method of execution should generally be in favour of contracts, unless there are special reasons for not doing so. 392. Types of Tender There are three following types of tender being practised in India : Item rate Percentage rate Lump-sum. Item rate tender requires the identification of all items of work, their description and their estimated quantities. The contractor is required to quote his rate for each item of work. The tender is finally evaluated on the basis of the cost of the full work at the rates quoted by the tenders for different items. This method is suittd for road works and small bridge works. Percentage rate tender asks the tenderer to quote a plus or minus percentage with reference to the departmental rates. This method is suited for roadworks and small bridge works. Lump-sum tender, generally adopted for large bridges in India, requires the tenderer to quote a single lump-sum for all the works included in the bid. In some cases, the tenderer is free to evolve his alternative design for the bridge and quote his lumpsum quotation on the basis of his own design. Though the method is simple to operate, the evaluation of the tenders on an equitable basis becomes difficult, especially if to the bids are accompanied by special conditions (Ref. 1). 39 3. Pre-qualification of Contractors Pre-qualification of contractors is a procedure intended to ensure that only such contractors who have the requisite experience, resources and capability to execute the intended work are given the invitation to tender. In this process it eliminates incapable and inexperienced contractors from tendering, quoting unrealistic rates, securing the work and finally abandoning the work in an incomplete condition. Prequalification short-lists the contractors and thus avoids unnecessary work involved in evaluating a large number of tenders. Prequalification is done by issuing an invitation to prequaiify, which can be published in the Press. On response by the firms, prequalification documents are issued to them. They should indicate the scope of the work, its cost and time frame. The information sought from the contractors should be in the form of standard questionnaires, eliciting information on the (i) structure and organisation of the firm, (ii) financial statement of works executed by the firm, including the names of the bankers, (Hi) resources (personnel, equipment etc.), and (iv) past experience (Ref. 2). On the basis of the information receivej, the pre-qualification is done and the list of selected tenderers is notified. In the PWDs in India, there is a system of registration of contractors and categorisation, depending upon their capacity. But the system of prequalification is not existing. It needs to be introduced, at least for large works. 39'4. Tender Documents 39'41. The tender document consist of the following : Notice Inviting Tenders (NIT) Instructions to Tenderers Conditions of contract Form of Tender Specifications Bill of Quantities Drawings. 39 4 2. The NIT is a brief press advertisement giving particulars of the work—title, location, approximate cost etc., the particulars of the availability of the tender documents, last date of receipt of application for tender documents and the last date for submission of tender documents.

Page 117: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

112

39'4'3, The instructions to fenders give additional information on the date, time and place of submission of tenders, number of copies required and other information necessary lor proper filling of the Tender Form tnd quotations. If alternative designs are allowed, then the same should be specified. The amount of earnest money deposit, performance bond, validity of the tender etc. are other items indicated in the instructions. 39'4"4. The conditions of contract are normally standardised by each highway agency. There is no common set of conditions of contract applicable to highway works in India. They coverall legal requirements of the contract. 39'4'5. The form of tender is the proposal or offer by the tenderer to carry out the works in accordance with the stipulations laid down. 39'4"6. The specifications contain detailed description of various items of work, the manner in which they are to be executed, the quantity to be achieved and the basis of payment. In India, the specifications for highway and bridge works have been standardised by the Ministry of Shipping and Transport (Roads Wing) and these are applicable to National Highway Works (Ref 3). For State works, the State have their own specifications. In addition, the standard specifications and codes of practices by bodies such as the Indian Roads Congress and the Indian Standards Institution are referred to in the Tender. 39-4-7 gjn cf quantities contain the various items of work and their quantities. Against each item the tenderer is expected to enter his quoted rate and work out the cost ot the item. The cost of each item is similarly entered and totalled in the end. 39'4'8. Drawings should provide the tenderer with sufficient detail to enable him to make an accurate assessment of the work and to bid accordingly. The drawings become part of the contract documents, to be supplemented subsequently during the execution of works. 49'5. Agreement When a tenderer has been selected for the execution of works, he enters into a formal Agreement with the Department. The Agreement is the most fundamental of the contract documents. Therefore, it should contain reference to each of the contract documents such as the conditions of contract, Form of Tender, Specifications, Bill of Quantities and Drawings.

Page 118: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

113

8 ROAD CONSTRUCTION PROGRAMMING AND MANAGEMENT

8.1 401. Need for Construction Programming

40'11. Highway projects involve lumpy investments of public funds. Where resources are scarce, these funds have competing demands. Their channelisation into the roads sector is at the cost of other sectors of the econ.my. This underlines the need to utilise the allotted funds in the shortest time possible so that long gestation periods are avoided. Delays in construction involve locking up of scarce resources and inconveniencing the public. Delays in construction lead to cost escalation and claims by the contractor. Such delays should be avoided at all coits. This can be achieved by careful programming and monitoring of the works. 40T2. Highway construction today is a complex process, involving a variety of sub jobs and specialisation. A number of suppliers and contractors may have to be working on different sub-components of the main work. There is a need to effectively coordinate the activities such that no bottlenecks arise. 40T3. The timely availability of labour, materials and equipment is crucial to the successful implementation of a project. Labour availabilitj in India is seasonal since the rural labour is gainfully employed in agricultural operations in the appropriate seasons. Materials like cement, bitumen aod steel are scarce commodities in a developing country and a good deal of advance planning and procurement is needed. Equipment is equally scarce. Though indigenous capacity exists in the country to manufacture the road-making equipment, it is necessary to order them in advance and plan their utilisation. A good construction programmees can take care of the constraints. 40 1'4. Due to seasonal characteristics, certain specifications and items of work cannot be carried on throughout the year. For example, bituminous specifications have to be suspended in the rainy season. On the other hand, water-bound-macadam can be ideally undertaken during rainy season. Well-sinking and foundation works in mid-stream have to be suspended and the rainy season. These seasonal constraints have to be identified and taken care of in a construction programme. 40T5. Many of the activities in a project are interdependent. For example, land acquisition is a pre-requisite for road construction. Many of the activities need to be synchronised. For example, the contruction of bridge and its approaches should be completed at the same time. One without the other cannot be used. 40'2. Requirements of a Programme A good construction programme should : Identify all elements of activities Estimate the time taken for each activity accurately Recognise the sequence of operations and mutual interdependence of critical activities Recognise seasonal and other constraints Be flexible and have capabilities for updation Be easy of achievement and not too tight nor too lax. 403. Bar Chart A bar dart is the most simple and satisfactory form of percen- tation of a piogramme. It is also known as a Gantt chart, after Gantt who evolved it and popularised it. It is highly amenable to programming and monitoring of road works. The bar-chart, a sample of which is given in Fig. 40*1, is prepared on the following lines : The work is broken up into major activities. These activities are listed one below the other, roughly in the sequence of operation in which they are found necessary In the chart, these activities are entered on the left side. The quantities of works are also listed preferable. Time frame is indicated on the horizontal axis. Most convenient unit of time is a mouth, though a week or a quarter can also be used. The beginning of each activity is selected depending upon the resources availability, seasonal constraints and financial limitations. This is marked against each activity. The length of the bar is decided based on the manpower, equipment and financial resources and the possible rate of progress. The percentages of each activity are scaled off and marked on the bar. The financial progress is indicated at the bottom.

Page 119: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

114

As the activity progresses, it is covered by hatching the blank space within the bar. If a work is completed, the hatched area is covered by a full patch or a crosshatch.

Page 120: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

115

Page 121: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

116

404. GPM Some of the best known methods of modern project monitoring are the PERT (Programme Evaluation and Review Technique) and the CPM (Critical Path Method). The latter is particularly, suited to monitor highway c ad bridge projects. The CPM is a diagrammatic representation of a project by means of a network. The network is constructed of various activities and depicts the sequence and interplay of these activities. The path in the network which is critical to the Projects is determined and is known as the Critical Path. The project is broken up into smaller activities and the duration of each of these is determined. The earliest finishing time (EFT) and latest finish time (LFT) of each event are then determined. The lines connecting the events where the EFT and LFT are the same from, the CPM. The advantages of the CPM to a highway project are : It enables the planner to chalk out a logical programme with inter-dependence of the various activities and the restraints. A thorough and detailed examination of the project is, compulsorily done. The resources can be scheduled to the best advantage. The activities which are likely to cause delays and bottlenecks are identified in the beginning itself and the engineer can keep a vigil over them. The CPM can bring about considerable savings in cost and time. The CPM can be used for planning, design, construction and maintenance, which are the normal activities conducted by a Highway Department. 405 Construction Management Whether the road-work is executed departmentally or through contracts, the management of the construction is an important responsibility. The management of the work starts much before the actual commencement of the work. It includes activities such as invitation of tenders, selection of contractors, mobilisation and. actual execution. The following aspects deserve careful considera-r tions in construction management : Management of materials Management of labour Management of equipment Financial management Materials required for road and bridge works cover a wide variety. More important among them are cement, steel, bitumen, stone aggregates, sand and gravel. Efficient management of the materials includes activities such as assessment of requirement, location of source of supply, purchase, transport, storage and issue on works. The procurement should be so phased that works do not suffer at any stage due to lack of materials and at the same time the stock of materials is not unnecessarily high. Labour available for large scale road construction is seasonal in some parts of India, depending upon the agriculture activities. Hence careful thought should be given to ensure an adequate supply of labour. Amenities to labour such as temporary housing, medical facilities and creches for childern are provided by the contractor as part of the conditions o f contract. Their wages are governed by the Minimum Wages Act. Road construction equipment is costly to purchase and operate. Its efficient management is thus of prime importance. Important points to be kept in view are : Selection of proper size, number and specifications of equipment to do the work in hand. Preparation of an utilisation programme. Care in operation, by experienced operators. Adequate maintenance, which needs a back-up of spare parts and skilled mechanics. Financial management covers budgeting, keeping, proper accounts, ensuring adequates flow of funds and keeping watch over the financial progress.

Page 122: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

117

9 QUALITY CONTROL IN HIGHWAY ENGINEERING

9.1 41.1 Importance of Quality Control

Highway construction involves the use of a variety of materials and deals with a range of properties of the materials and the finished product. By their very nature, the materials and the finished product, exhibit variability in their properties as measured from time to time. The highway engineer is thus called upon to decide whether the materials and the finished product are of acceptable standlrds. For doing so, he conducts a number of tests and evaluates the test results against certain well-established test criteria evolved after considerable research and observation of past behaviour. The field of his work is called Quality Control. Since statistical principles are generally followed in quality control, the field is well known as Statistical Quality Control (SQC). Quality Control of works is exercised for the following reasons : As a routine measure to ensure that the materials and finished product have desired properties. As a method of accepting or rejecting contractor's work. As an aid to help in designing mixes in the laboratory having properties which bear relation to the properties which can be realistically achieved in actual construction. It is generally observed that quality control pays for itself. For example, whereas the cost of quality control (manpower, materials, and equipment) is about 1J to 2 per cent of the cost of the work, the direct and indirect economic returns from quality control could be of the order of 5—10 per cent of the cost of construction or more. Quality control detects faults in manufacturing process at an undertaken in time. 41*2. Process Control or End Product Control In manufacturing cement concrete, for example, control can be exercised in the process itself, including the selection of the ingredient (cement, aggregates and water), their gradation and proportioning, mixing, laying and curing of concrete. This is known as process control. As an alternative, the finished concrete can be tested for its cube srength or flexural strength and the test result evaluated against minimum criteria previously selected. This is known as the end product control. In actual practice, both forms of quality control individually or a combination of the two are adopted in India (Ref. 1). Some of the highway departments in the United States now adopt a contract clause under which if the end product falls below a specified standard, it is accepted at reduced rat^s. The "pay factors", which are percentages of the accepted full rates, are devised in such a way that as the quality of the end product falls progressively below the set standard the pay factors also are lower. 41*3. Statistical Method in Quality Control 41*3*1. Normal distribution

A typical shape of this function is given Fig. 41 1.

Fig. 41 1. Normal disttibution curve. It is generally found that the properties of highway materials- and end products, when tested a number of times obtaining samples from the same lot or the same work, follow a "normal

Page 123: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

118

distribution". The normal density function, also called the Gaussian function, is given by the following equation : it is seen that the curve is bell shaped and is symmetrical with respect to the population mean. A useful transformation of this equation is obtained when and o— 1. The variable z, known as the standard normal variable, is defined as :

The above relationship is given in Fig. 41*2, which is known as Che standard normal density curve.

Fif. 41-2. Standard normal density curve. The area below this curve is unity. Standard tables are available giving the value of the area under any part of the normal curve for different values of z. In these tables, the cumulative unit normal distribution, or F(z), also denoted as <!>(*), is plotted for various values of z above 0. By symmetry, for values less than 0, ^(-z)=l-<D(z). 413 2. Mean, standard deviation and coefficient of deviation The most common measure of central tendency of values is the arithmetic mean, or simply the "mean". Suppose there are • observations of a variable x (i.e. sample size =n), and these are Equation (41*1) then becomes

denoted by <rlt x„ x% xn, then the mean x Is given by the formula :

When the observations are grouped into different classes, a simplified procedure enables a quick determination of the mean {Ref. 2). A measure of the dispersion of the data is the standard deviation, which is obtained from ;

From the normal distribution table the values of the standard normal variable z«. associated with various confidence levels y are summarised in Table 41'1. It may be noted that

Table 411 where s=standard deviation a<=each individual observation x=mean, as found from Eqn. (41'4) n=number of observations. It may be noted that x and a obtained from above are estimates of the true mean, (x and the true standard deviation, a of the population The coefficient of variation is defined as the ratio between the standard deviation and the mean. Coefficient of variation=-j- (for the sample) .. (41'6) u = — (for the population) ..(41-7)

Page 124: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

119

<T 41'3'3. Distribution of sample mean When the sample mean, * is determined repeatedly with n observations, it will be found that x also takes a normal distribution with mean n and standard deviation The latter is known by the term standard error of the mean, If the value of a is not known, a can be taken equal to s, the standard deviation of the sample. Problem 41 1. The thicknees of an asphaltic concrete layer is designed and constructed to be 80 mm. The standard deviation is 15 mm. What is the probability that if a sample of 100 readings of the thickness is tested that the mean observed thickness exceeds 76 mm ?

41*3'4. Point estimate and interval estimate The sample mean x is a point estimate of the population mean n. It is more usual to estimate a parameter within an interval. Thus, if tx and t2 are two values of a random variable t and it is desired to estimate the parameter Q, then

Pr denotes the probability indicated in [ ] and Y=sPec>fied probability. The set of values between tx and (inclusive) is called the confidence interval. The values and ts are called the confidence limits. The probability measure y is called the confidence level. The confidence level is the proportion of the samples for which the interval includes the true value. Standard normal variable associated with various confidence levels

Confidence Level 2

Tolerance Level (proportion of test results that fall below the minimum

za

0 80 0 90 1 in 10 1282 090 095 1 in 20 1645 095 0*975 1 in 40 I960 0*98 099 1 in 100 2-326 0'99 0995 I in 200 2-576 0-998 0999 1 in 1000 309 0999 09995 1 in 2000 3*291 The probability that the observed mean thickness of 100 readings exceeds 75 mm is 9996 per cent.

Page 125: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

120

Fig. 41-3 Problem 412. A series of 303 observations of the cube

strength of concrete gives a mean of 39'7 MN/m* and a standard deviation of 6 8 MN/m%. Qive a 05 per cent confidence interval for ihe population mean. Problem 41*3. In connection with a quality control testing of concrete cubes, it is desired to obtain the mean 28 day crushing strength within an accuracy of 2 MN/m', with a probability of 0 95. Previous tests have indicated that the standard deviation is 8 MN/m*. What should be the sample size for testing ?

Page 126: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

121

Problem 41*4. The 28-day crushing strength of concrete cubes gave a mean value of 34 0 MS jm? and a standard deviation of 40 MN/m', the number of samples tested being 57. The minimum specified strength is 28 MN/m'. The tolerance level, which is the proportion of samples that can fall below the stipulated strength, is 1 in 10. Are the specifications being met ? Solution. 7 = 340 • = 40 n=57 #ro<n=28'0 o=0"90, since 90 per cent of the test results should fall above the stipulated minimum z.=(from Table 4 11) = 1 '282 3W.=34*0-1 282X4 0 =28 9 MN/m* which is greater than 28 0 MN/m1 Hence the specifications are being met. 41"3'5. Control chart In industrial processes, control charts have been used on a large scale to monitor the quality of work and detect when the process goes out of control. These charts can be used for quality control of highway works also. Control charts are constructed around the target mean value of the property being tested. Depending upon the known variability of the value (its standard deviation), upper and lower limits are fixed. Thus when the mean of the samples tested on any occasion is found out, it is possible find out whether the sample means is within the range specified or outside it. If outside, the process is out of control. The exact fixation of the upper and lower limits depend upon the tolerance level that is specified. Normally two limits are specified : Warning limits Action limits. The warning limits are fixed such that percent of the samples will be bejond each warning limit (so that 95 per cent of the sample means should within the limits) The warning limits give indication that something is wrong with the process. The action limits are generally set such that 01 per cent of the samples mean values lie outside each limit. If the sample mean falls outside the action limits, the process should be stoppeu and action taken to locate the cause of the trouble and to rectify the same. From Table 41*1, the warning limit of 2i per cent samples lying beyond is reached with ^±196 (SE) where /i=mean of population S.E.=standard error of the mean a • V n *I n a=standard deviation of the population «=same standard deviation «=number of samples tested. Similary, from Table 41*1 the action limit of 01 percent of sample means lying outside the limits is reached with m±3'09 (S.E.).

Page 127: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

122

Problem 415. The O.B.R. values of sub-base material are tested every day. Four samples are taken each day and tested. The target CBR value is 15 and the standard deviation is 3. Find the teaming limit such that not more than 2J per cent of the samples lie below the warning limit and the action Umit such that not more than 0 1 per cent of the sample means lie below the action limit. Solution. Lower Warning limit -*»-]'96 S.E. = 15-0-1*96 -4j- V4 = 150- 1'96 X 1*50 = 12 06, say 12. Lower action limit=n—3*09 SE -H—3*09x1-50 = 10*36 Control charts can also be constructed by finding out the moving average of the five tests. 414. Frequency of Tests The limits are illustrated in Fig. 41*4.

Fig. 41-4. Control chart. A major decision that needs to be made in any quality control process is regarding the frequency of tests. The frequency varies from work to work. The frequency laid down by IRC (Ref 1) is given in Table 41*3. Table 41*2 Frequency of tests for quality control 8. No. Item of work Frequency 1. Earthwork (») Soil particle size, Atterberg Limits 1—2 tests per 8000 m' (ii) C.B.R. on a set of 3 specimens One test per 3000 m« (iii) Natural moisture content One test per 250 m8

(iv) Moisture content before compaction 2—3 tests per 250 m'

(v) Dry density of compacted area

One test \ er 1000 m" for embankments to be increased to one test per 500—1000 m" for subgrade layers.

2. Gravel sub-base (i) Gradation, plasticity One test per 200 m" (ii) Moisture content One test per 250 ra1 (iii) Density One test per 500 m" 3. Lime-soil (») Purity of lime One test per 5 T (ii) Lime content, moisture content One test per 250 m1 (iii) Density One test per 500 m1 4. Water-bound macadam

(0 Los Angeles Abrasion or Aggregate Impact Value, Flakiness Index

One test per 200 m»

(it) grading of materials One test per 100 m' (Hi) Plasticity of binder One test per 25 m8 5. Bituminous Macadam

(i) Los Angeles Abrasion Value or Aggregates Impact Value, Flakiness Index, Stripping Value

One test per 50—100 m»

Page 128: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

123

(ii) Mix grading, binder content. aeerecate gradation Two tests per day

8. No Item of work Frequency 6. Surface dressing and premix carpet

(i) Los Angeles Abrasion Value or Aggregate Impact Value, Stripping Value, Flakiness Index Water absorption

One test per 50 ma

(ii) Grading of aggregate One test per 25 m3

(Hi) Rate of spread of binder and aggregate for surface dressing One test per 500 m«

(»©) Binder content for premix carpet Two tests per day

7. Asphaltic concrete

(0 Los Angeles Abrasion Value or Aggregate Impact Value, Stripping Value, Water absorption, Flakiness Index

One test per 50—100 m*

(ii) Sieve analysis for filler One test per 5 ms

(in) Mixing grading, binder content One test per 100 T of mix, minimum 2 tests per day

(iv) Stability 3 Marshall specimens per 100 T of mix.

(v) Thickness and density One test per 500 m8. 8. Cement concrete pavement (i) Gradation of aggregates One test for 15 m8

(ii) Los Angeles Abrasion Value or Aggregate Impact Value, Soundness Once for each source

(tit) Cerr;enf, physical and chemical Once for each source (iv) Workability One test per 10 m8

(t>) Concrete strength

3 cube/beam samples for each 7 days and 28 days for' every 30 m* of concrete

(vi) Core strength on hardened concrete.

2 corcs for every 30 m3 of concrete

Page 129: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

124

41*5. Acceptance Sampling Inspectioni for accepting a material or product enable another method of statistical quality control. The method involves testing a few samples, determining the mean and standard deviation and making a decision whether it is of acceptable quality or not. The method presupposes a knowledge of the population mean and its standard deviation and it also requires a stipulation of the proportion of values that may fall above (or below) the axeptable value.

Fig. 41-5 In Fig. 41*5. the normal curve for the population is given io dotted line, the mean being n and the standard deviation a. The specifications require that the minimum test value should be y such that, say p per cent of the values can be below y. The corresponding standard normal variable is za The curve in full line denotes the normal curve of the sample mean, the sample size being n. The standard error of the mean is

/ Solution. In this example, using Eqn. (4110), xlmin) for ncoeptance

The value z,' is 10 selected that it signifies the risk of rejecting an acceptable material. Thus, the minimum value of * should then be (Ref. 3) :

Page 130: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

125

The following example illustrates the concept.

Problem 41"6. The specified Marshall stability value of an asphaltic concrete mix is 500 lb, the standard deviation being 30 lb. It is required that not more than 10 per cent of the tests should fall below the specified value. 4 samples are taken from a lot and the mean value of stability is found to be 510 lb Can the lot be accepted if the risk of rejecting an acceptable material is to be 2\ per cent ?

Page 131: FCE546 Transp Eng IIIB - March 2012 v0

FCE546 Transp Eng IIIB - March 2012 v0 Issue 1.0 / Insert the report issue date here

126