FCC ENVIRONMENTAL ASSESSMENT
AT&T Site Blackwater MD1785
Prepared for:
&
Prepared by:
AARCHER, Inc. 910 Commerce Road
Annapolis, Maryland 21401 (410) 897-9100 aarcherinc.com
Submitted:
June 21, 2010
The Environmental Navigators ®
![Page 2: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/2.jpg)
June 21, 2010
Katy Kilmon
Bechtel Communications, Inc
AT&T Mobility - Baltimore-Washington
9200 Berger Road
Columbia, MD 21046
RE: FCC Environmental Assessment, Blackwater MD1785, 3445 Golden Hill Road,
Church Creek, Dorchester County, Maryland, 21622
Ms. Kilmon:
AARCHER Inc., (AARCHER) is pleased to provide the following Federal Communications Commission
(FCC) Environmental Assessment (EA) report for the proposed AT&T telecommunications facility to be
located at 3445 Golden Hill Road, Church Creek, Dorchester County, Maryland, 21622.
Should you have any questions, please do not hesitate to contact me at (410)-897-9100 ext. 106 or
Sincerely,
AARCHER INC.
Renee de Sibour
Environmental Scientist
The Environmental Navigators ®
![Page 3: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/3.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
TABLE OF CONTENTS
1.0 EXECUTIVE SUMMARY ..................................................................................................1
2.0 ENVIRONMENTAL INFORMATION .................................................................................1
2.1 Proposed Action and Need ...........................................................................................1
2.2 Site Location and Description........................................................................................2
2.3 Site Zoning Classification ..............................................................................................2
2.4 Community Response...................................................................................................2
2.5 Potential Adverse Environmental Effects ......................................................................2
2.6 Action Alternatives.........................................................................................................3
2.7 Local Land Use Approval ..............................................................................................3
3.0 NEPA CRITERIA...............................................................................................................3
3.1 Officially Designated Wilderness Area ..........................................................................3
3.2 Officially Designated Wildlife Preserve..........................................................................4
3.3 Threatened or Endangered Species or Designated Critical Habitats............................4
3.4 Resources Listed, or Eligible for Listing, in the National Register of Historic Places ....4
3.5 Indian Religious Sites....................................................................................................5
3.6 Floodplain......................................................................................................................5
3.7 Surface Features...........................................................................................................6
3.8 High Intensity White Lights............................................................................................6
3.9 Radiofrequency Radiation .............................................................................................7
4.0 CONCLUSIONS................................................................................................................7
5.0 FINDINGS, ISSUES, AND RECOMMENDATIONS..........................................................7
5.1 Findings.........................................................................................................................7
5.2 Issues............................................................................................................................8
5.3 Recommendation ..........................................................................................................8
EXHIBITS
Exhibit 1: Site Photographs Exhibit 2: Topographic Map Exhibit 3: Construction Drawings & FAA 1-A Survey Certification Exhibit 4: Building Permit & Electrical Permit Exhibit 5: State Historic Preservation Office Correspondence & Public Notice Exhibit 6: Tribal Consultation Exhibit 7: National Wilderness Preservation System (NWPS) Map National Wildlife Refuge System (NWRS) Map USFWS Blackwater Refuge Map Federal Agency Consultation Exhibit 8: Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map (FIRM) Exhibit 9: United States Geological Survey (USGS) National Wetland Inventory (NWI) Map Maryland Department of Natural Resources Wetlands Map Maryland Department of the Environment Letter of Authorization Exhibit 10: FCC Environmental Assessment Checklist
![Page 4: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/4.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 1
1.0 EXECUTIVE SUMMARY
AARCHER Inc., (AARCHER) prepared the following Federal Communications Commission (FCC)
Environmental Assessment (EA) (per 47 CFR 1.311 and 47 CFR 1.1307(a) 6) on behalf of AT&T
Mobility (AT&T). AT&T is the potential lessee of a 35-foot by 50-foot proposed tower compound
leasehold, which is defined for this report as the Subject Property. The Subject Property includes existing
buildings and other fixtures/improvements located on the Subject Property. The proposed tower
compound will be located at 3445 Golden Hill Road, Church Creek, Dorchester County, Maryland 21622.
AT&T proposes to construct a 195-foot guyed tower and install nine antennas at a centerline height of
193 feet. The total height of the proposed guyed tower, including lightning rod, will be 199 feet above
ground level (AGL). Four equipment cabinets will be installed on a 16-foot by 16-foot raised steel
platform within the proposed 35-foot by 50-foot fenced facility compound.
During AARCHER’s preliminary site screening of the project site, it was determined that the proposed
tower will significantly change surface features and is located within the boundaries of the Federal
Emergency Management Agency (FEMA) Flood Insurance Rate Map (FIRM) 100-year floodplain (Zone
A4). In accordance with 47 CFR 1.1307(a)6, an EA must be prepared to assess the impacts of the
proposed tower construction on existing environmental conditions.
AT&T obtained a construction permit from Maryland Department of the Environment (MDE) for the
clearing of vegetation, filling, grading, and construction of a communications tower within emergent
nontidal wetlands at the Subject Property. AT&T has met all mitigation requirements by investing into
the Maple Dam Conservation, LLC wetland mitigation bank. Based on the issuance of the permit and the
completion of mitigation bank investment, AARCHER concludes that the proposed Federal undertaking
will not have any substantial impact to the emergent wetland located at the site. AARCHER recommends
that a finding of no significant impact (FONSI) be issued by the FCC for this proposed Federal
undertaking.
The proposed construction drawings, provided in Exhibit 3 of this report, indicate that the proposed
equipment shelter and all associated mechanical and electrical equipment will be elevated approximately
7.375 inches above the base flood elevation (BFE) of 6 feet. AARCHER concludes that the proposed
Federal undertaking will not have any substantial impact to the flood storage capacity of the local
floodplain. AARCHER recommends that a finding of no significant impact (FONSI) be issued by the
FCC for this proposed Federal undertaking.
2.0 ENVIRONMENTAL INFORMATION
2.1 Proposed Action and Need
AT&T proposes to construct a 195-foot guyed tower and install nine antennas at a centerline height of
193 feet. The total height of the proposed guyed tower, including lightning rod, will be 199 feet AGL.
Equipment cabinets will be installed on a proposed 16-foot by 16-foot elevated steel platform within the
proposed 35-foot by 50-foot fenced equipment compound. Construction drawings are provided in Exhibit
3 of this report.
The proposed tower compound will serve the AT&T’s customers by providing continuous cellular
coverage in the service area.
![Page 5: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/5.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 2
2.2 Site Location and Description
The Subject Property is located at 3445 Golden Hill Road, Church Creek, Dorchester County, Maryland
21622. The Subject Property is located approximately 750 northeast of the intersection of Golden Hill
Road and Hoopers Island Road. The Subject Property is bordered on the north by grass/marshland,
beyond which is the site of a construction business. An unpaved access road to the larger property is
located to the south of the Subject Property, beyond which are marsh grasses and wooded marshland.
Cleared land comprising marsh grasses is located west of the Subject Property, and further west is Golden
Hill Road. Cleared land comprising marsh grasses is located east of the Subject Property. Site
photographs are provided in Exhibit 1 of this report.
The geographic coordinates of the Subject Property are latitude N 38º 23’ 33.806”, longitude
W 76º 11’ 34.642.” According to the FAA 1-A survey certification, the Subject Property is located
approximately 1.08 feet above mean sea level (AMSL). A copy of the USGS 7.5-minute topographic
quadrangle (Golden Hill, MD) depicting the location of the Subject Property is provided in Exhibit 2 of
this report.
2.3 Site Zoning Classification
According to the approved building permit documents issued by Dorchester County, Maryland, on
April 25, 2006 and extended to February 4, 2010, the Subject Property is located on a lot zoned as
“I-2 Heavy Industrial.” The building permit and electrical permit are provided in Exhibit 4 of this report.
2.4 Community Response
The Applicant and its zoning representatives reported no public controversy regarding the proposed tower
or compound during the permitting review process. The Applicant has no knowledge of public
controversy or other community response regarding the project.
As part of the State Historic Preservation Office (SHPO) review process conducted in 2006, two measures
were undertaken to obtain public comment. A sign was posted at the proposed site location describing the
project and the method to submit comments in writing. The project was also submitted through the local
zoning process. No public comments have been received to date.
2.5 Potential Adverse Environmental Effects
The Subject Property is not located within the USFWS National Wetlands Inventory (NWI) online
mapped wetland areas; however, the proposed tower site is within estuarine wetland areas mapped by the
Maryland Department of Natural Resources. AARCHER observed some conditions of wetland areas
during its initial site visit, such as saturated soil. A wetland delineation was completed on
November 17, 2009. The delineation determined that the entire Subject Property, with exception of the
existing gravel access road for the larger property, meets the criteria of a wetland as defined in the Corps
of Engineers Wetlands Delineation Manual. The proposed construction requires clearing of vegetation,
filling, grading, and construction of a communications tower, access road, and equipment compound.
Construction plans state that land disturbance will be limited to a fenced compound leasehold area having
approximate dimensions of 35 feet by 50 feet and an approximate 12-foot by 130-foot gravel based access
road. According to construction plans, the total area of disturbance will be 4,541 square feet.
Construction activities are anticipated to have a significant effect on emergent wetlands located at the site.
AT&T obtained a permit from MDE (Authorization Number: 09-NT-2052/200960936) dated
![Page 6: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/6.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 3
May 17, 2010. The permit authorizes the clearing of vegetation, filling, grading, and construction of a
communications tower that will permanently affect approximately 4,541 square feet. AT&T purchased
wetland bank credits from Maple Dam Conservation, LLC mitigation bank as mitigation for the proposed
undertaking.
In addition, the Subject Property is located within the 100-year floodplain (FIRM Zone A4, Dorchester
County, Maryland, Community-Panel Number 240026 0325 A, dated October 15, 1981). According to
the FAA 1-A survey certification, the ground elevation of the Subject Property is approximately 1.08 feet
AMSL. Construction plans indicate that the equipment shelter will be elevated approximately 6.675 feet
above ground level on concrete piers and, therefore, will be located approximately 7.375 inches above the
base flood elevation. Construction activities are not anticipated to have a significant effect on flood zone
drainage pathways, thus limiting potential adverse environmental effects to the floodplain.
2.6 Action Alternatives
This FCC EA considered several alternatives to the proposed Federal undertaking, including “No Action”
and “Alternate Location.”
Under the Alternate Location alternative, neither rooftop collocation nor collocation on an existing tower
were practicable alternatives. No rooftops exist in the vicinity of the proposed location that would offer
continued cellular coverage for the area. A guyed radio tower was previously located at the Subject
Property address. AT&T investigated collocating on the existing tower; however, the tower was not
designed to support the antenna installation proposed by AT&T. Since initial investigation into the site,
the existing radio tower has been removed. There are no additional telecommunication towers available in
the area for collocation. In addition, due to the size of the wetlands and floodplain in the vicinity of the
project area, impacts could not be avoided. Moving the location of the proposed compound leasehold
outside of the emergent wetlands and 100-year floodplain to an alternate location would result in
inconsistent coverage and dropped calls within the service area.
Under the No Action alternative, the applicant’s customers will continue to lack coverage within the
service area, resulting in dropped calls and an inability to originate or receive calls within the service area.
2.7 Local Land Use Approval
A building permit and electrical permit are provided in Exhibit 4 of this report which provides
documentation of approval by Dorchester County Planning and Zoning of the construction plans and site
location.
3.0 NEPA CRITERIA
The following sections provide information regarding compliance of the proposed project with the
required NEPA elements.
3.1 Officially Designated Wilderness Area
In addressing whether the facility is located in an officially designated wilderness area, AARCHER
reviewed information from the National Wilderness Preservation System (NWPS). The NWPS is
comprised of lands designated as wilderness area by the U.S. Forest Service, Bureau of Land
Management, U. S. Fish and Wildlife Service (USFWS), and the National Park Service. A copy of the
NWPS search is included in Exhibit B. The site is not located within a designated wilderness area.
![Page 7: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/7.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 4
3.2 Officially Designated Wildlife Preserve
In addressing whether the facility is located in an officially designated wildlife preserve, AARCHER
reviewed information from the USFWS National Wildlife Refuge System (http://refuges.fws.gov/). Based
on information provided by the National Wildlife Refuge System, there are five wildlife refuges in the
State of Maryland. Blackwater National Wildlife Refuge is identified in the vicinity of the Subject
Property. AARCHER reviewed a map of the Blackwater National Wildlife Refuge boundary provided by
the USFWS. A map of the wildlife refuges in Maryland and the USFWS Blackwater National Wildlife
Refuge is provided in Exhibit B. The site is not located within a designated wildlife preserve.
3.3 Threatened or Endangered Species or Designated Critical Habitats
AARCHER submitted the proposed project for review by the USFWS Chesapeake Bay Field Office and
the Maryland Department of Natural Resources (DNR) on October 13, 2008. In a letter dated
December 22, 2008, the USFWS determined that the proposed project will is located within the
immediate vicinity of the Delmarva fox squirrel habitat; however, because no forests will be cleared
because of the construction, the proposed project is not likely to adversely affect Delmarva fox squirrels.
In addition, in a letter dated December 15, 2008, the Maryland DNR determined that there are no State of
Federal records for rare, threatened, or endangered species within the boundaries of the project site.
Therefore, they had no specific requirements pertaining to protection measures at the site.
Agency correspondence is provided in Exhibit 7.
3.4 Resources Listed, or Eligible for Listing, in the National Register of Historic Places
AARCHER submitted the proposed collocation for review under the National Historic Preservation Act
(NHPA) Section 106 on March 27, 2006. In email correspondence with Jonathan Sager, Preservation
Officer with the Maryland Historical Trust (MHT), on March 16, 2006, Mr. Sager stated that if MHT
does not provide comment within 30 to 45 days of project submission, AT&T should proceed without
written notice from SHPO.
Section VII. B. p 586 of the Nationwide Programmatic Agreement for Review Under the National
Historic Preservation Act provides the following guidance for proceeding under NHPA without
individual review from SHPO:
If the SHPO does not provide written notice to the Applicant that it agrees or disagrees
with the Applicant’s determination of no Historic Properties affected within 30 days
following receipt of a complete Submission Packet, it is deemed that no Historic
Properties exist within the APE or the Undertaking will have no effect on Historic
Properties. The Section 106 process is then complete and the Applicant may proceed with
the project, unless further processing for reasons other than Section 106 is required. (A
copy of this section of the PA is provided as an attachment).
More than 30 days have passed since the completed Submission Packet (FCC Form 620) was submitted
to MHT for review, and no written notice was provided by the SHPO indicating agreement or
disagreement with AARCHER’s determination that the construction would have no effect to historic
properties. Therefore, AT&T met its NHPA compliance obligations set by the PA, and may continue with
the proposed project without effect to historic properties.
![Page 8: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/8.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 5
AARCHER contacted the Maryland Historical Trust (MHT) on June 9, 2010. Ms. Elizabeth Cole,
Administrator for Review and Compliance, stated that unless the designed of the proposed project has
changed or new historic properties have been identified, then MHT does not wish to review the project
again and the existing determination is still valid.
On June 10, 2010, AARCHER conducted inventory research at the MHT Library. No new historic
properties were identified within the area of potential effects for the Subject Property; therefore, the
SHPO agrees with the AARCHER’s determination that the construction will have no effect to historic
properties.
3.5 Indian Religious Sites
AT&T submitted the proposed project through the FCC’s Tower Construction Notification System
(TCNS) on December 12, 2005. Of the tribes contacted, two tribes responded:
On May 30, 2006, the Delaware Tribe of Indians responded to the original that they have no
objection to the proposed construction.
On June 14, 2006, The Shawnee Tribe responded that they have no objection to the proposed
construction.
TCNS notification and tribal consultation are included in Exhibit 6.
AT&T submitted the proposed project through the TCNS again on November 21, 2008. Of the tribes
contacted, two responded to the second submittal:
On November 21, 2008, the Tuscarora Nation responded to the original submission stating that if
the applicant does not receive a response from the Tuscarora Nation within 30 days, then they
have no interest in the proposed project and the applicant may proceed. To date, no response has
been received.
On December 4, 2008, The Shawnee Tribe sent an automated repose for the TCNS requesting
additional information. On June 21, 2010, AARCHER contacted Ms. Kim Jumper, Assistant
Tribal Historic Preservation Officer with the Shawnee Tribe to determine if the response from
July 21, 2006 is still valid. Ms. Jumper stated that unless the designed of the proposed project has
changed, then the Shawnee Tribe does not wish to review the project again and the existing
determination is still valid.
3.6 Floodplain
During AARCHER’s preliminary site screening of the Subject Property, it was determined that the
proposed tower and compound leasehold are located within the boundaries of the Federal Emergency
Management Agency (FEMA) Flood Insurance Rate Map (FIRM) 100-year floodplain (Zone A4). FCC
regulations require that an EA be prepared to assess the impacts of the tower on existing environmental
conditions.
AARCHER reviewed the FEMA FIRM depicting the location of the Subject Property (Dorchester
County, Maryland, Community-Panel Number 240026-0325A, dated October 15, 1981). The FIRM
indicates flood boundaries of specific areas within Dorchester County. According to the FIRM, the area in
which the Subject Property is located has a BFE of 6 feet. Given the variance in the BFE as stated in the
![Page 9: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/9.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 6
FEMA FIRM for Dorchester County, AARCHER determined that a BFE of 6.0 feet would be appropriate
for the purposes of this EA. A copy of the portion of the FEMA FIRM that includes the Subject Property
is provided in Exhibit 8 of this report.
The building permit and associated documents provided by Dorchester County Planning and Zoning does
not specifically require the applicant to compensate for the flood level or make amendments to the site
construction plans.
The Subject Property was granted an appropriate building permit, which included a review of the
proposed construction by Dorchester County. According to the FAA 1-A survey certification provided by
Bechtel Communications, the ground elevation at the base of the proposed guyed tower is approximately
1.08 feet AMSL. Construction drawings provided by Bechtel Communications depict the base of the
tower be constructed at ground level and the based of the equipment platform be constructed at a height of
approximately 6 feet 7.375 inches AMSL, approximately 7.375 inches above the BFE. Based on the size
of the flood zone, the footprint of the proposed project, and that the equipment platform will be
constructed above the base flood elevation, the Subject Property is not anticipated to have a significant
effect on flood zone drainage pathways. A copy of the building permit and electrical permit are provided
in Exhibit 4 of this report; a copy of FAA 1-A survey certification and construction drawings are provided
in Exhibit 3 of this report; and a copy of the FEMA FIRM is provided in Exhibit 8.
3.7 Surface Features
Per AT&T policy, AARCHER reviewed the USFWS National Wetlands Inventory (NWI) online and
conducted a site visit to determine whether significant change in surface features would occur as a result
of the proposed undertaking. The proposed tower site is shown outside of NWI mapped wetland areas;
however, the proposed tower site is within estuarine wetland areas mapped by the Maryland DNR.
At the request of Bechtel and MDE, AARCHER completed a wetland delineation for the Subject Property
on November 17, 2009. The delineation determined that the entire Subject Property and 50 feet in all
directions, with exception of the existing gravel access road for the larger property on which the Subject
Property is located, meets the criteria of a wetland as defined in the Corps of Engineers Wetlands
Delineation Manual. The proposed construction requires clearing of vegetation, filling, grading, and
construction of a communications tower, access road, and equipment compound. Construction plans state
that land disturbance will be limited to a leasehold area having approximate dimensions of 35 feet by 50
feet, an approximate 12-foot by 130-foot gravel based access road, and guy anchors. According to
construction plans, the total area of disturbance will be 4,541 square feet.
AT&T obtained a permit from MDE (Authorization Number: 09-NT-2052/200960936) dated May 17,
2010. The permit authorizes the clearing of vegetation, filling, grading, and construction of a
communications tower that will permanently affect approximately 4,541 square feet. As mitigation for the
proposed undertaking, AT&T purchased wetland bank credits from Maple Dam Conservation, LLC
mitigation bank. Based on the issuance of the permit and that the investment in Maple Dam Conservation
as mitigation has been approved by MDE, the Subject Property is not anticipated to have a significant
effect on wetlands. A copy of the building permit and electrical permit are provided in Exhibit 4 of this
report.
3.8 High Intensity White Lights
According to the site plan information provided by Bechtel, proposed site development does not include
installation of high intensity white lights. A copy of the construction drawings are provided in Exhibit 3
of this report which verifies that the tower will not include high intensity white lights.
![Page 10: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/10.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 7
3.9 Radiofrequency Radiation
The FCC requires that human exposure to radiofrequency radiation (RF) must be below the limits set in
47 CFR 1.1310 and 2.1093. AT&T is responsible for ensuring the proposed undertaking will not exceed
appropriate limits.
4.0 CONCLUSIONS
AARCHER has prepared this FCC EA under contract to Bechtel Communications on behalf of AT&T.
AT&T proposes to construct a 195-foot guyed tower and install antennas at a centerline height of 193
feet. The total height of the proposed guyed tower, including lightning rod, will be 199 feet above ground
level (AGL). Four equipment cabinets will be installed on a 16-foot by 16-foot raised steel platform
within the proposed 35-foot by 50-foot fenced facility compound. The Subject Property is the subject of
this report and is located at 3445 Golden Hill Road, Church Creek, Dorchester County, Maryland. This
EA was prepared using readily available published information, online resources, Federal Agency
correspondence, and information provided by AT&T and the previous tower owner.
AT&T understands their responsibilities under NEPA, as an FCC licensee, and fully recognizes that
assessment of environmental impacts is to be completed prior to site development. Because the Subject
Property will result in significant changes to surface features (e.g., wetland fill) and is located within a
100-year floodplain, FCC regulations require an EA to assess the environmental effects of the
undertaking.
AT&T obtained a permit from MDE (Authorization Number: 09-NT-2052/200960936) dated
May 17, 2010. The permit authorizes the clearing of vegetation, filling, grading, and construction of a
communications tower that will permanently affect approximately 4,541 square feet. As mitigation for the
proposed undertaking, AT&T purchased wetland bank credits from Maple Dam Conservation, LLC
mitigation bank. Based on the issuance of the permit and that the investment in Maple Dam Conservation
as mitigation has been approved by MDE, the Subject Property is not anticipated to have a significant
effect on wetlands.
The Subject Property was granted an appropriate building permit, which included a review of the
proposed construction by Dorchester County. According to the FAA 1-A survey certification provided by
Bechtel Communications, the ground elevation at the base of the proposed guyed tower is approximately
1.08 feet AMSL. Construction drawings provided by Bechtel Communications depict the base of the
tower be constructed at ground level and the based of the equipment platform be constructed at a height of
approximately 6 feet 7.375 inches aboveground level, approximately 7.375 inches above the BFE. Based
on the size of the flood zone, the footprint of the proposed project, and that the equipment platform will
be constructed above the base flood elevation, the Subject Property is not anticipated to have a significant
effect on flood zone drainage pathways.
5.0 FINDINGS, ISSUES, AND RECOMMENDATIONS
5.1 Findings
AARCHER determined that the Subject Property is located in the boundaries of the Federal Emergency
Management Agency (FEMA) Flood Insurance Rate Map (FIRM) 100-year floodplain (Zone A4) and
will result in a significant chance in surface features (e.g. wetland fill).
![Page 11: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/11.jpg)
FCC ENVIRONMENTAL ASSESSMENT Blackwater MD1785
FCC ENVIRONMENTAL ASSESSMENT REPORT - PRIVILEGED DOCUMENT
Page 8
5.2 Issues
FCC regulations require an EA be prepared to assess the impacts of the proposed tower construction on
existing environmental conditions.
5.3 Recommendation
AARCHER concludes that the proposed federal undertaking will not have any substantial impacts.
Therefore, AARCHER recommends that a FONSI be issued by the FCC for this proposed Federal
undertaking.
![Page 12: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/12.jpg)
The Environmental Navigators®
Exhibit 1
Site Photographs
![Page 13: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/13.jpg)
1. View facing south of the Subject Property and surrounding area.
2. View facing south from the Subject Property.
![Page 14: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/14.jpg)
3. View facing north from the Subject Property.
4. View facing east from the Subject Property.
![Page 15: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/15.jpg)
5. View facing west from the Subject Property.
![Page 16: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/16.jpg)
The Environmental Navigators®
Exhibit 2
Topographic Map
![Page 17: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/17.jpg)
![Page 18: FCC ENVIRONMENTAL ASSESSMENT](https://reader031.fdocuments.us/reader031/viewer/2022020621/61ea488aee183c084d7243b8/html5/thumbnails/18.jpg)
The Environmental Navigators®
Exhibit 3
Construction Drawings
FAA 1-A Survey Certification