FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality...

108
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION 00 01 05 (00005) Certifications Page 00 01 10 (00010) Table of Contents PROCUREMENT AND CONTRACTING REQUIREMENTS Invitation to Bid Form of Proposal AIA Contract Forms STANDARD FORM OF AGREEMENT BETWEEN OWNER & CONTRACTOR (AIA DOCUMENT A101 – 1997) GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION (AIA DOCUMENT A201 – 1997) PERFORMANCE BOND AND PAYMENT BOND (AIA DOCUMENT A312 – 1984) CHANGE ORDER (AIA DOCUMENT G701 - 1987) APPLICATION AND CERTIFICATE FOR PAYMENT (AIA DOCUMENT G702 - 1992) CONTINUATION SHEET (AIA DOCUMENT G703 - 1992) CERTIFICATE OF SUBSTANTIAL COMPLETION (AIA DOCUMENT G704 - 1992) CONTRACTOR’S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS (AIA DOCUMENT G706 – 1994) CONTRACTOR’S AFFIDAVIT OF RELEASE OF LIENS (AIA DOCUMENT G706A - 1994) CONSENT OF SURETY COMPANY TO FINAL PAYMENT (AIA DOCUMENT G707 – 1994) CHANGE ORDER PROPOSAL REQUEST (AIA DOCUMENT G709 – 1993) CONSTRUCTION CHANGE DIRECTIVE (AIA DOCUMENT G714 - 1987) AVAILABLE PROJECT INFORMATION 00 31 13.43 (00370) Interior Finish Index 00 31 13.45 (00380) Exterior Finish Index 00 31 32 (00320) Geotechnical Data Note: the following AIA Documents have not been included in the project manual, but are in effect on this project. They are available upon request. FAIRFIELD INN & SUITES at The Highlands Town Center PROJECT MANUAL TABLE OF CONTENTS Fairfield Inn and Suites by Marriott at the Highlands Town Center ▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪ ▪ PAGE 1 ▪ November 7, 2014

Transcript of FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality...

Page 1: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

00 01 05 (00005) Certifications Page

00 01 10 (00010) Table of Contents

PROCUREMENT AND CONTRACTING REQUIREMENTS

Invitation to Bid

Form of Proposal

AIA Contract Forms

STANDARD FORM OF AGREEMENT BETWEEN OWNER & CONTRACTOR (AIA DOCUMENT A101 – 1997)

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION (AIA DOCUMENT A201 – 1997)

PERFORMANCE BOND AND PAYMENT BOND (AIA DOCUMENT A312 – 1984)

CHANGE ORDER (AIA DOCUMENT G701 - 1987)

APPLICATION AND CERTIFICATE FOR PAYMENT (AIA DOCUMENT G702 - 1992)

CONTINUATION SHEET (AIA DOCUMENT G703 - 1992)

CERTIFICATE OF SUBSTANTIAL COMPLETION (AIA DOCUMENT G704 - 1992)

CONTRACTOR’S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS (AIA DOCUMENT G706 – 1994)

CONTRACTOR’S AFFIDAVIT OF RELEASE OF LIENS (AIA DOCUMENT G706A - 1994)

CONSENT OF SURETY COMPANY TO FINAL PAYMENT (AIA DOCUMENT G707 – 1994)

CHANGE ORDER PROPOSAL REQUEST (AIA DOCUMENT G709 – 1993)

CONSTRUCTION CHANGE DIRECTIVE (AIA DOCUMENT G714 - 1987)

AVAILABLE PROJECT INFORMATION

00 31 13.43 (00370) Interior Finish Index

00 31 13.45 (00380) Exterior Finish Index

00 31 32 (00320) Geotechnical Data

Note: the following AIA Documents have not been included in the project manual, but are in effect on this

project. They are available upon request.

FAIRFIELD INN & SUITES at The Highlands Town CenterPROJECT MANUAL

TABLE OF CONTENTS

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 1 ▪

November 7, 2014

Page 2: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

CONSTRUCTION PRODUCTS AND ACTIVITIES

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 (01110) Summary of Work

01 23 00 Alternates

01 26 00 (01250) Contract Modification Procedures

01 31 00 (01310) Project Management and Coordination

01 33 00 (01330)

01 35 13.21 (01000) Special Procedures for Hospitality Projects

01 42 19 (01420) Reference Standards

01 45 00 (01450) Quality Control

01 50 00 (01500) Temporary Facilities and Controls

01 58 00 (01580) Project Identification

01 60 00 (01600) Product Requirements

01 71 23 (01720) Field Engineering

01 73 29 (01730) Cutting and Patching

01 74 00 (01740) Cleaning & Waste Management

01 77 00 (01770) Closeout Procedures

01 78 13 (01780) Bonds & Warranties

01 78 23 (01830) Operating and Maintenance Data

01 78 39 (01785) Project Record Documents

01 78 43 (01790) Spare Parts

01 79 00 (01820) Demonstration and Training

DIVISION 02 – EXISTING CONDITIONS

Not Used

DIVISION 03 - CONCRETE

03 30 00 (03300) Cast-In-Place Concrete

03 54 13 (03500) Gypsum Cement Underlayment

DIVISION 04 - MASONRY

04 20 00 (04200) Unit Masonry

04 72 00 Cast Stone Masonry

DIVISION 05 - METALS

05 12 00 (05120) Structural Steel Framing

05 31 00 (05300) Steel Decking

05 40 00 (05400) Cold-Formed Metal Framing

05 50 00 (05500) Metal Fabrications

05 52 00 (05520) Metal Railings

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 (06100) Rough Carpentry

06 17 53 (06175) Shop-Fabricated Wood Trusses

06 20 00 (06200) Finish Carpentry

06 25 00 Prefinished Paneling

06 61 13 (06610) Cultured Marble Fabrications

Submittal and Substitution Procedures

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 2 ▪

November 7, 2014

Page 3: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 10 00 (07100) Damproofing and Waterproofing

07 19 00 (07190) Water Repellents

07 20 00 (07200) Thermal Protection

07 24 19 (07241)

07 27 00 (07270) Air Barriers

07 54 23 (07543) Thermoplastic Polyolefin (TPO) Roofing

07 61 00 (07610) Sheet Metal Roofing

07 62 00 (07620) Sheet Metal Flashing & Trim

07 72 33 (07724) Roof Hatches

07 81 00 (07810) Applied Fireproofing

07 84 00 (07840) Firestopping

07 92 00 (07920) Joint Sealants

DIVISION 08 - OPENINGS

08 11 13 (08110) Hollow Metal Doors and Frames

08 14 00 (08210) Wood Doors

08 31 00 (08310) Access Doors and Panels

08 41 13 (08412) Aluminum Framed Entrances and Storefronts

08 42 29 (08460) Automatic Entrances

08 51 13 (08520) Aluminum Windows

08 71 00 (08710) Door Hardware

08 80 00 (08800) Glazing

DIVISION 09 - FINISHES

09 21 16 (09255) Gypsum Board Assemblies

09 21 16.23 (09265) Gypsum Board Shaft-Wall Assemblies

09 30 00 (09310) Tiling

09 51 23 (09512) Acoustical Tile Ceilings

09 54 23 (00945) Linear Metal Ceilings

09 65 00 (09650) Resilient Flooring

09 65 66 (09620) Resilient Athletic Flooring

09 68 00 (09680) Carpeting

09 72 00 (09720) Wall Coverings

09 90 00 (09900) Painting

09 96 00 (09960) High Performance Coatings

DIVISION 10 - SPECIALTIES

10 11 00 (10110) Visual Display Surfaces

10 14 00 (10400) Signage

10 26 00 (10260) Wall and Door Protection

10 28 00 (10800) Toilet, Bath and Laundry Accessories (10 28 00a)

10 31 00 (10305) Manufactured Fireplaces

10 44 00 (10520) Fire Protection Specialties

10 51 13 (10500) Metal Lockers

10 56 13 (10670) Metal Storage Shelving

10 75 00 (10350) Flagpoles

Water Drainage Exterior Insulation and Finish Systems (EIFS)

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 3 ▪

November 7, 2014

Page 4: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

DIVISION 11 - EQUIPMENT

11 23 00 (11110) Commercial Laundry and Dry Cleaning Equipment

11 25 13 (11080) Registration Equipment

11 31 00 (11450) Residential Appliances

11 40 00 (11400) Food Service Equipment

DIVISION 12 - FURNISHINGS

12 32 13 (06400) Manufactured Wood-Veneer-Faced Casework

12 32 16 (06400) Manufactured Plastic Laminate Clad Casework

12 36 23 (06415) Plastic Countertops

12 36 61 (09385) Simulated Stone Countertops

12 36 61.13 (06610) Cultured Marble Countertops

12 36 61.16 (06620) Solid Surfacing Countertops

12 48 13 (12480) Entrance Floor Mats and Frames

12 54 13.13 (12505) Hospitality Furniture Installation

DIVISION 13 - SPECIAL CONSTRUCTION

13 11 00.02 (13152) Swimming Pools - Indoor

DIVISION 14 - CONVEYING EQUIPMENT

14 21 23 (14210) Electric Traction Passenger Elevator System

14 91 33 (14560) Laundry and Linen Chutes

DIVISIONS 15 – 20

Not Used

DIVISION 21 – FIRE SUPPRESSION

21 05 00 (15050) Common Work Results for Fire Suppression21 10 00 (13900) Fire Suppression Systems

DIVISION 22 – PLUMBING

22 05 00 (15050) Common Work Results for Plumbing

22 05 13 (15055)

22 05 19 (15122) Meters and Gages for Plumbing Piping

22 05 23 (15110) General Duty Valves for Plumbing Piping

22 05 29 (15060)

22 05 48 (15070)

22 05 53 (15075) Identification for Plumbing Piping and Equipment

22 07 00 (15083) Plumbing Insulation

22 08 00_01 Plumbing Testing Requirements

22 08 00_02 Plumbing Prefunctional Checklists

22 08 00_03 Plumbing Sample Functional Test Procedures

22 11 16 (15140) Domestic Water Piping

22 11 23 (15440) Domestic Water Pumps

22 13 16 (15150) Sanitary Waste and Vent Piping

22 30 00 (15430) Plumbing Equipment

22 34 00 (15486) Fuel-Fired, Domestic Water Heaters

22 40 00 (15410) Plumbing Fixtures (22 40 00-1)

22 45 00 Swimming Pools

Common Motor Requirements for Plumbing Equipment

Hangers and Supports for Plumbing Piping and Equipment

Vibration and Seismic Control for Plumbing Piping and Equipment

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 4 ▪

November 7, 2014

Page 5: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

DIVISION 23 – HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 00 (15050) Common Work Results for HVAC

23 05 13 (15090)

23 05 29 (15060)

23 05 48 (15070)

23 05 53 (15075) Identification for HVAC Piping and Equipment

23 05 93 (15950) Testing, Adjusting, and Balancing for HVAC

23 07 00 (15081) HVAC Insulation

23 11 23 (15194) Facility Natural-Gas Piping

23 23 00 (15530) Refrigerant Piping

23 31 13 (15815) Metal Ducts

23 33 00 (15820) Air Duct Accessories

23 34 23 (15833) HVAC Power Ventilators

23 37 00 (15850) Air Outlets and Inlets

23 41 00 (15861) Particulate Air Filtration

23 74 33 (15733) Dedicated Outdoor Air Units

23 81 13.13 (15735) Packaged Terminal Air-Conditioning Units

23 82 39 (15767) Unit Heaters

DIVISIONS 24 - 25

Not Used

DIVISION 26 – ELECTRICAL

26 05 00 (16050) Common Work Results for Electrical

26 05 19 (16120)

26 05 26 (16060) Grounding and Bonding for Electrical Systems

26 05 33 (16130) Raceways and Boxes for Electrical Systems

26 05 36 (16139) Cable Trays for Electrical Systems

26 05 53 (16075) Identification for Electrical Systems

26 05 72 Overcurrent Protective Device Short-Circuit Study

26 05 74 Overcurrent Protective Device Arc-Flash Study

26 22 00 (16460) Low-Voltage Transformers

26 24 00 (16440) Switchboards and Panelboards

26 27 26 (16140) Wiring Devices

26 28 16 (16410) Enclosed Switches and Circuit Breakers

26 29 13 (16420) Enclosed Controllers

26 41 13 (13100) Lightning Protection for Structures

26 43 13 (16289)

26 51 00 (16510) Interior Lighting (26 51 00-01)

26 56 00 (16520) Exterior Lighting

26 60 00 (16580) Lighting Accessories

DIVISION 27 – COMMUNICATIONS

27 05 00 Common Work Results for Communications

27 10 00 (16710) Structured Cabling

27 20 00 (16740) Communication and Data-Processing Equipment

27 41 16 (16850) New Building Television Equipment

27 51 00 (16810) Distributed Audio-Video Communications System

Common Motors Requirements for HVAC Equipment

Surge Protection for Low Voltage Electrical Power Circuits

Low-Voltage Electrical Power Conductors and Cables

Vibration and Seismic Control for HVAC Piping and Equipment

Hangers and Supports for HVAC Piping and Equipment

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 5 ▪

November 7, 2014

Page 6: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 16 00 (13730) Intrusion Detection

28 23 00 (13740) Video Surveillance

28 31 00 (13850) Fire Alarm and Detection Systems

DIVISIONS 29 – 49

Not Used

END OF SECTION

Fairfield Inn and Suites by Marriott at the Highlands Town Center

▪ SECTION 01 01 10 (00010) - TABLE OF CONTENTS ▪

▪ PAGE 6 ▪

November 7, 2014

Page 7: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 01 23 00 - ALTERNATES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements governing Alternates.

1.3 DEFINITIONS

A. Definition: An alternate is an amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if the Owner decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. 1. The cost or credit for each alternate is the addition to or deduction from the Contract Sum

to incorporate the Alternate into the Work. No other adjustments are made to the Contract Sum.

1.4 PROCEDURES

A. Coordination: Modify or adjust affected adjacent Work as necessary to completely and fully integrate that Work into the Project. 1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar

items incidental to or required for a complete installation whether or not mentioned as part of the Alternate.

B. Notification: Immediately following the award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate whether alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to alternates.

C. Execute accepted alternates under the same conditions as other Work of this Contract.

D. Schedule: A "Schedule of Alternates" is included at the end of this Section. Specification Sections referenced in the Schedule contain requirements for materials necessary to achieve the Work described under each alternate.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Add Alternate No. 1: Add the cost to provide a labor, material and performance bond to the cost of the contract.

END OF SECTION

Page 8: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. HVAC Pipe and Pipe Fittings

2. Joining Materials

3. HVAC Sleeves

4. HVAC Sleeve Seals

5. HVAC Specialties

6. HVAC Piping System Installation

7. HVAC Equipment Installation

8. Concrete Bases.

9. Erection of Metal Supports

10. Erection of Wood Supports

11. Cutting and Patching

B. Related Sections:

1. Section 01 31 00 - Project Management and Coordination

2. Section 01 73 29 - Cutting and Patching

3. Section 01 78 43 - Spare Parts and Materials

4. Section 01 79 00 - Training

5. Section 01 78 23 - Operating and Maintenance Data

6. Section 03 30 00 - Cast-in-Place Concrete

7. Section 06 10 01 - Rough Carpentry

8. Section 07 62 00 - Sheet Metal Flashing and Trim

9. Section 07 84 00 - Firestopping

10. Section 08 31 00 - Access Doors

11. Section 09 90 00 - Painting

12. Section 23 05 53 – Identification for HVAC Piping and Equipment: Labeling and identifying HVAC systems and equipment.

1.02 REFERENCES

A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless"

2. B32 "Standard Specification for Solder Metal"

3. C1107 "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)"

B. American Welding Society (AWS) Publications:

Page 9: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. BRH "Brazing Handbook"

2. A5.8 "Specification for Filler Metals For Brazing And Braze Welding"

3. D1.1 "Structural Welding Code - Steel"

4. D10.12 "Guide for Welding Mild Steel Pipe"

C. Copper Development Association (CDA) Publications:

1. "Copper Tube Handbook"

1.03 DEFINITIONS

A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawl spaces, and tunnels.

B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

C. Exposed, Exterior Installations: Exposed to view outdoors, or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in duct shafts.

E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants, but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.

F. The following are industry abbreviations for plastic materials:

1. ABS: Acrylonitrile-butadiene-styrene plastic.

2. CPVC: Chlorinated polyvinyl chloride plastic.

3. PVC: Polyvinyl chloride plastic.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: For dielectric fittings, flexible connectors, plumbing sleeve seals, and identification materials and devices.

2. Coordination Drawings: Detail major elements, components, and systems of plumbing equipment and materials in relationship with other systems, installations, and building components. Show space requirements for installation and access. Indicate if sequence and coordination of installations are important to efficient flow of the Work. Include the following:

a. Planned piping layout, including valve and specialty locations and valve-stem movement.

b. Clearances for installing and maintaining insulation.

c. Clearances for servicing and maintaining equipment, accessories, and specialties, including space for disassembly required for periodic maintenance.

d. Equipment and accessory service connections and support details.

Page 10: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

e. Exterior wall and foundation penetrations.

f. Fire-rated wall and floor penetrations.

g. Sizes and location of required concrete pads and bases.

h. Scheduling, sequencing, movement, and positioning of large equipment into building during construction.

i. Floor plans, elevations, and details to indicate penetrations in floors, walls, and ceilings and their relationship to other penetrations and installations.

1.05 QUALITY ASSURANCE

A. Equipment Selection: Equipment of higher electrical characteristics, physical dimensions, capacities, and ratings may be furnished provided such proposed equipment is approved in writing and connecting plumbing and electrical services, circuit breakers, conduit, motors, bases, and equipment spaces are increased. Additional costs shall be approved in advance by appropriate Contract Modification for these increases.

1. If minimum energy ratings or efficiencies of equipment are specified, equipment must meet design requirements. See drawings for equipment schedules and requirements.

1.06 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and prevent entrance of dirt, debris, and moisture.

B. Protect stored pipes and tubes from moisture and dirt. Elevate above grade. Do not exceed structural capacity of floor, if stored inside.

C. Protect flanges, fittings, and piping specialties from moisture and dirt.

D. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.

1.07 SEQUENCING AND SCHEDULING

A. Coordinate HVAC equipment installation with other building components.

B. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction to allow for mechanical installations.

C. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components, as they are constructed.

D. Sequence, coordinate, and integrate installations of mechanical materials and equipment for efficient flow of the Work. Coordinate installation of large equipment requiring positioning before closing in building.

E. Coordinate connection of HVAC systems with exterior underground and overhead utilities and services. Comply with requirements of governing regulations, franchised service companies, and controlling agencies.

F. Coordinate requirements for access panels and doors if mechanical items requiring access are concealed behind finished surfaces. Access panels and doors are specified in Section 08 31 00 - "Access Doors and Panels."

G. Coordinate installation of identifying devices after completing covering and painting, if devices are applied to surfaces. Install identifying devices before installing acoustical ceilings and similar concealment.

1.08 Posted Operating Instructions

A. Provide and post operating instructions for all HVAC systems.

Page 11: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. HVAC Sleeve Seals:

a. Metraflex Inc. (800-621-4347)

b. PSI-Thunderline/Link-Seal (800-423-2410)

2.02 JOINING MATERIALS

A. Solder Filler Metals: ASTM B32.

1. Alloy Sn95 or Alloy Sn94: Approximately 95 percent tin and 5 percent silver, with 0.10 percent lead content.

2. Alloy E: Approximately 95 percent tin and 5 percent copper, with 0.10 percent maximum lead content.

3. Alloy HA: Tin-antimony-silver-copper zinc, with 0.10 percent maximum lead content.

4. Alloy HB: Tin-antimony-silver-copper nickel, with 0.10 percent maximum lead content.

5. Alloy Sb5: 95 percent tin and 5 percent antimony, with 0.20 percent maximum lead content.

B. Brazing Filler Metals: AWS A5.8.

1. BCuP Series: Copper-phosphorus alloys.

2. BAg1: Silver alloy.

3. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

2.03 HVAC SLEEVES

A. Sleeves: The following materials are for wall, floor, slab, and roof penetrations:

1. Steel Sheet Metal: 0.0239-inch minimum thickness, galvanized, round tube closed with welded longitudinal joint.

2. Steel Pipe: ASTM A53, Type E, Grade A, Schedule 40, galvanized, plain ends.

3. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain ends and integral water stop, unless otherwise indicated.

4. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange. Include clamping ring and bolts and nuts for membrane flashing.

a. Underdeck Clamp: Clamping ring with set screws.

2.04 HVAC SLEEVE SEALS

A. Description: Modular design, with interlocking rubber links shaped to continuously fill annular space between pipe and sleeve. Include connecting bolts and pressure plates.

2.05 HVAC SPECIALTIES

A. Grout:

1. Non-shrink, Nonmetallic Grout: ASTM C1107, Grade B.

Page 12: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

a. Characteristics: Post-hardening, volume-adjusting, dry, hydraulic-cement grout, non-staining, non-corrosive, nongaseous, and recommended for interior and exterior applications.

b. Design Mix: 5000-psig, 28-day compressive strength.

c. Packaging: Premixed and factory packaged.

PART 3 EXECUTION 3.01 HVAC PIPING SYSTEMS - COMMON REQUIREMENTS

A. General: Install HVAC piping as described below, unless piping Sections specifies otherwise. Individual Division 23 Piping Sections specifies unique piping installation requirements.

B. General Locations and Arrangements: Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Install piping as indicated, unless deviations to layout are approved on Coordination Drawings as required by Division 01 Sections and as outlined in Part 1 of this section.

C. Install components with pressure rating equal to or greater than system operating pressure.

D. Install piping in concealed interior and exterior locations, except in equipment rooms and service areas.

E. Install piping free of sags and bends.

F. Install exposed interior and exterior piping at right angles or parallel to building walls. Diagonal runs are prohibited, unless otherwise indicated.

G. Install piping tight to slabs, beams, joists, columns, walls, and other building elements. Allow sufficient space above removable ceiling panels to allow for ceiling panel removal.

H. Install piping to allow application of insulation plus 1-inch clearance around insulation.

I. Install sleeves for pipes passing through concrete and masonry walls, and concrete floor and roof slabs.

1. Cut sleeves to length for mounting flush with both surfaces.

a. Exception: Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches above finished floor level. Extend cast-iron sleeve fittings below floor slab as required to secure clamping rings where required.

2. Build sleeves into walls and slabs as work progresses.

3. Install sleeves large enough to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation.

4. Use Type S, Grade NS, Class 25, Use O, neutral-curing silicone sealant.

J. Aboveground, Exterior-Wall, Pipe Penetrations: Seal penetrations using sleeves and mechanical sleeve seals. Size sleeve for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

1. Install steel pipe for sleeves smaller than 6 inches in diameter.

2. Install cast-iron "wall pipes" for sleeves 6 inches in diameter and larger.

3. Assemble and install mechanical sleeve seals according to manufacturer's written instructions. Tighten bolts that cause rubber sealing elements to expand and make watertight seal.

Page 13: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

K. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with fire stopping materials. Refer to Section 07 84 00 - "Firestopping" for materials.

L. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements.

M. Piping Joint Construction: Join pipe and fittings as follows and as specifically required in individual piping specification Sections:

1. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

2. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

3. Soldered Joints: Construct joints according to CDA’s "Copper Tube Handbook."

4. Brazed Joints: Construct joints according to AWS’s "Brazing Handbook," Chapter "Pipe and Tube."

3.02 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment to provide maximum possible headroom, if mounting heights is not indicated.

B. Install equipment according to approved submittal data. Portions of the Work are shown only in diagrammatic form. Refer conflicts to Owner’s Representative.

C. Install equipment level and plumb, parallel and perpendicular to other building systems and components in exposed interior spaces, unless otherwise indicated.

D. Install mechanical equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations.

E. Clearance from Electrical Equipment: Piping and ductwork are prohibited in electric rooms and closets, elevator machine rooms and installation over transformers, switchboards and motor control centers.

3.03 ERECTION OF METAL SUPPORTS AND ANCHORAGE

A. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor mechanical materials and equipment.

B. Field Welding: Comply with AWS D1.1, "Structural Welding Code--Steel."

C. Prime and paint all metal supports per Section 09 90 00 requirements similar to “Pipes and Mechanical Equipment”.

3.04 ERECTION OF WOOD SUPPORTS AND ANCHORAGE

A. Cut, fit, and place wood grounds, nailers, blocking, and anchorage to support and anchor HVAC materials and equipment.

B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten connections between members. Install fasteners without splitting wood members.

C. Attach to substrates as required to support applied loads.

3.05 CUTTING AND PATCHING

A. Cut, channel, chase, and drill floors, walls, partitions, ceilings, and other surfaces necessary for mechanical installations. Perform cutting by skilled mechanics of trades involved.

B. Repair cut surfaces to match adjacent surfaces.

Page 14: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 00 (15050) - COMMON WORK RESULTS FOR HVAC ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

C. Refer to Division 01 Sections for additional requirements.

3.06 GROUTING

A. Install nonmetallic, non-shrink, grout for mechanical equipment base bearing surfaces, pump and other equipment base plates, and anchors. Mix grout according to manufacturer's written instructions.

B. Clean surfaces that will come into contact with grout.

C. Provide forms as required for placement of grout.

D. Avoid air entrapment during placing of grout.

E. Place grout, completely filling equipment bases.

F. Place grout on concrete bases to provide smooth bearing surface for equipment.

G. Place grout around anchors.

H. Cure placed grout according to manufacturer's written instructions.

END OF SECTION

Page 15: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 13 (15090) - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 13 (15090) - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Basic Motor Requirements

2. Polyphase Motors

3. Single Phase Motors

B. Related Sections:

1. Division 23 Sections for application of motors and reference to specific motor requirements for motor-driven equipment.

1.02 REFERENCES

A. Institute of Electrical and Electronics Engineers (IEEE) Publications:

1. 112 “Standard Test Procedure for Polyphase Induction Motors and Generators”

B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:

1. MG 1 “Motors and Generators”

C. National Fire Protection Association (NFPA) Publications:

1. 70 "National Electric Code"

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: Show nameplate data and ratings; characteristics; mounting arrangements; size and location of winding termination lugs, conduit entry, and grounding lug; and coatings.

1.04 QUALITY ASSURANCE

A. Comply with NFPA 70.

B. Listing and Labeling: Provide motors specified in this Section that are listed and labeled.

1. Terms "Listed and Labeled": As defined in the National Electrical Code, Article 100.

PART 2 PRODUCTS 2.01 BASIC MOTOR REQUIREMENTS

A. Basic requirements apply to mechanical equipment motors, unless otherwise indicated.

B. Motors 1/2 HP and Larger: Polyphase.

C. Motors Smaller than 1/2 HP: Single phase.

D. Frequency Rating: 60 Hz.

E. Voltage Rating: Determined by voltage of circuit to which motor is connected.

Page 16: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 13 (15090) - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

F. Service Factor: According to NEMA MG 1, general purpose continuous duty, design type “B.”

G. Capacity and Torque Characteristics: Rated for continuous duty and sufficient to start, accelerate, and operate connected loads at designated speeds, in indicated environment, with indicated operating sequence, and without exceeding nameplate ratings or considering service factor.

H. Enclosure: Open drip-proof, unless otherwise indicated.

I. Efficiency: Motors shall have a higher efficiency rating than industry standard average motor as delineated in IEEE Standard 112, Test Method 13.

2.02 POLYPHASE MOTORS

A. Description: NEMA MG 1, medium induction motor.

1. Design Characteristics: NEMA MG 1, Design B, unless otherwise indicated.

2. Energy-Efficient Design: Where indicated.

3. Stator: Copper windings, unless otherwise indicated. Multi-speed motors have separate winding for each speed.

4. Rotor: Squirrel cage, unless otherwise indicated.

5. Bearings: Double-shielded, pre-lubricated ball bearings suitable for radial and thrust loading.

6. Temperature Rise: Match insulation rating, unless otherwise indicated.

7. Insulation: Class F, unless otherwise indicated.

B. Motors Used with Reduced-Inrush Controllers: Match wiring connection requirements for indicated controller, with required motor leads brought to motor terminal box to suit control method.

C. Motors Used with Variable-Frequency Controllers: Ratings, characteristics, and features coordinated with and approved by controller manufacturer.

1. Critical vibration frequencies are not within operating range of controller output.

2. Temperature Rise: Match rating for Class B insulation.

3. Insulation: Class H

4. Thermal Protection: Where indicated, conform to NEMA MG 1 requirements for thermally protected motors.

D. Source Quality Control: Perform the following routine tests according to NEMA MG 1:

1. Measurement of winding resistance.

2. No-load readings of current and speed at rated voltage and frequency.

3. Locked rotor current at rated frequency.

4. High-potential test.

5. Alignment

2.03 SINGLE-PHASE MOTORS

A. Type: As indicated or selected by manufacturer from one of the following, to suit starting torque and other requirements of specific motor application.

1. Permanent-split capacitor.

Page 17: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 13 (15090) - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2. Split-phase start, capacitor run.

3. Capacitor start, capacitor run.

B. Shaded-Pole Motors: Do not use, unless motors are smaller than 1/20 hp.

C. Thermal Protection: Where indicated or required, internal protection automatically opens power supply circuit to motor when winding temperature exceeds a safe value calibrated to temperature rating of motor insulation. Thermal protection device automatically resets when motor temperature returns to normal range, unless otherwise indicated.

D. Bearings: Ball-bearing type for belt-connected motors and other motors with high radial forces on motor shaft. Sealed, pre-lubricated sleeve bearings for other single-phase motors.

PART 3 EXECUTION 3.01 ADJUSTING

A. Use adjustable motor mounting bases for belt-driven motors.

B. Align pulleys and install belts.

C. Tension according to manufacturer's written instructions.

END OF SECTION

Page 18: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Hangers And Supports For HVAC System Piping And Equipment.

B. Related Sections:

1. Section 05 50 00 (05500) - Metal Fabrications

2. Section 09 90 00 (09900) - Painting

3. Section 23 05 48 (15070) – Vibration and Seismic Control for HVAC Piping and Equipment

1.02 REFERENCES

A. The American Society of Mechanical Engineers (ASME) Publications:

1. B31.9 “Building Services Piping”

B. American Welding Society (AWS) Publications:

1. D1.1 "Structural Welding Code - Steel"

C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A36 “Standard Specification for Carbon Structural Steel”

2. A780 "Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings"

3. C552 “Standard Specification for Cellular Glass Thermal Insulation”

4. C1107 "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)"

D. Metal Framing Manufacturers Association (MFMA)

E. Manufacturers Standardization Society of the Valve and Fittings Industry. (MSS) Publications:

1. SP-6 “Standard Finishes for Contact Faces of Pipe Flanges and Connecting-End Flanges of Valves and Fittings”

2. SP-58 “Pipe Hangers and Supports - Materials, Design, and Manufacture”

3. SP-69 “ANSI/MSS Edition Pipe Hangers and Supports - Selection and Application”

4. SP-89 “Pipe Hangers and Supports -Fabrication and Installation Practices”

1.03 DEFINITIONS

A. MSS: Manufacturers Standardization Society for the Valve and Fittings Industry.

B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and Supports.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

Page 19: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data:

a. For each type of pipe hanger, channel support system component, and thermal-hanger shield insert indicated.

1.05 QUALITY ASSURANCE

A. Engineering Responsibility: Where required by the local authority having jurisdiction design and preparation of Shop Drawings and calculations for each multiple pipe support, trapeze, and seismic restraint by a qualified professional engineer.

1. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of hangers and supports that are similar to those indicated for this Project in material, design, and extent.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Pipe Hangers, Supports, and Components:

a. Cooper B-Line, Inc. (618-654-2184)

b. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)

c. National Pipe Hanger Corporation (609-261-5353)

2. Channel Support Systems:

a. Cooper B-Line, Inc. (618-654-2184)

b. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)

c. National Pipe Hanger Corporation (609-261-5353)

3. Thermal-Hanger Shield Inserts:

a. Carpenter & Patterson, Inc. (301.333.4631)

b. Erico (Michigan Hanger) (440-248-0100)

c. PHS Industries, Inc. (800-626-2336)

4. Powder-Actuated and Mechanical Anchor Fastener Systems:

a. Gunnebo Fastening Corp. (800-336-1640)

b. Hilti, Inc.(800-879-8000)

c. ITW Ramset/Red Head (800-899-7890)

2.02 HANGERS AND SUPPORTS

A. Pipe Hangers, Supports, and Components:

1. MSS SP-58, factory-fabricated components. Refer to "Hanger and Support Applications" Article in Part 3 for where to use specific hanger and support types.

a. Galvanized, Metallic Coatings: For piping and equipment that will not have field-applied finish.

Page 20: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

b. Nonmetallic Coatings: On attachments for electrolytic protection where attachments are in direct contact with copper tubing.

B. Channel Support Systems:

1. MFMA-2, Factory-fabricated components for field assembly.

2. Coatings: Manufacturer's standard finish.

3. Nonmetallic Coatings: On attachments for electrolytic protection where attachments are in direct contact with copper tubing.

C. Thermal-Hanger Shield Inserts:

1. 100-psi minimum compressive-strength insulation, encased in sheet metal shield.

2. Material for Cold Piping: ASTM C552, Type I cellular glass.

3. Material for Hot Piping: ASTM C552, Type I cellular glass.

4. For Trapeze or Clamped System: Insert and shield cover entire circumference of pipe.

5. For Clevis or Band Hanger: Insert and shield cover lower 180 degrees of pipe.

6. Insert Length: Extend 2 inches beyond sheet metal shield for piping operating below ambient air temperature.

2.03 MISCELLANEOUS MATERIALS

A. Powder-Actuated Drive-Pin Fasteners: Powder-actuated-type, drive-pin attachments with pull-out and shear capacities appropriate for supported loads and building materials where used.

B. Mechanical-Anchor Fasteners: Insert-type attachments with pull-out and shear capacities appropriate for supported loads and building materials where used.

C. Structural Steel: ASTM A36, steel plates, shapes, and bars, black and galvanized.

D. Grout: ASTM C1107, Grade B, factory-mixed and -packaged, non-shrink and nonmetallic, dry, hydraulic-cement grout.

1. Characteristics: Post hardening and volume adjusting; recommended for both interior and exterior applications.

2. Properties: Nonstaining, noncorrosive, and nongaseous.

3. Design Mix: 5000-psi, 28-day compressive strength.

PART 3 EXECUTION 3.01 HANGER AND SUPPORT APPLICATIONS

A. General:

1. Specific hanger requirements are specified in Sections specifying equipment and systems.

2. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in piping system Specification Sections.

B. Horizontal-Piping Hangers and Supports: Unless otherwise indicated and except as specified in piping system Specification Sections, install the following types:

1. Adjustable Steel Clevis Hangers (MSS Type 1): For suspension of noninsulated or insulated stationary pipes, NPS 1/2 to NPS 30.

2. Steel Pipe Clamps (MSS Type 4): For suspension of cold and hot pipes, NPS 1/2 to NPS 24 if little or no insulation is required.

Page 21: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3. Pipe Hangers (MSS Type 5): For suspension of pipes, NPS 1/2 to NPS 4 to allow off-center closure for hanger installation before pipe erection.

4. Adjustable Steel Band Hangers (MSS Type 7): For suspension of noninsulated stationary pipes, NPS 1/2 to NPS 8.

5. Adjustable Band Hangers (MSS Type 9): For suspension of noninsulated stationary pipes, NPS 1/2 to NPS 8.

6. Adjustable Swivel-Ring Band Hangers (MSS Type 10): For suspension of noninsulated stationary pipes, NPS 1/2 to NPS 2.

7. Split Pipe-Ring with or without Turnbuckle-Adjustment Hangers (MSS ype 11): For suspension of noninsulated stationary pipes, NPS 3/8 to NPS 8.

8. Adjustable Pipe Saddle Supports (MSS Type 38): For stanchion-type support for pipes, NPS 2-1/2 to NPS 36 if vertical adjustment is required, with steel pipe base stanchion support and cast-iron floor flange.

C. Vertical-Piping Clamps: Unless otherwise indicated and except as specified in piping system Specification Sections, install the following types:

1. Extension Pipe or Riser Clamps (MSS Type 8): For support of pipe risers, NPS 3/4 to NPS 20 (DN20 to DN500).

D. Hanger-Rod Attachments: Unless otherwise indicated and except as specified in piping system Specification Sections, install the following types:

1. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches for heavy loads.

E. Building Attachments: Unless otherwise indicated and except as specified in piping system Specification Sections, install the following types:

1. Top-Beam C-Clamps (MSS Type 19): For use under roof installations with bar-joist construction to attach to top flange of structural shape.

2. Side-Beam or Channel Clamps (MSS Type 20): For attaching to bottom flange of beams, channels, or angles.

3. Welded Beam Attachments (MSS Type 22): For attaching to bottom of beams if loads are considerable and rod sizes are large.

4. C-Clamps (MSS Type 23): For structural shapes.

5. Welded-Steel Brackets: For support of pipes from below or for suspending from above by using clip and rod. Use one of the following for indicated loads:

a. Light (MSS Type 31): 750 lb.

b. Medium (MSS Type 32): 1500 lb.

F. Saddles and Shields: Unless otherwise indicated and except as specified in piping system Specification Sections, install the following types:

1. Steel Pipe-Covering Protection Saddles (MSS Type 39): To fill interior voids with insulation that matches adjoining insulation.

2. Protection Shields (MSS Type 40): Of length recommended by manufacturer to prevent crushing insulation.

Page 22: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.02 HANGER AND SUPPORT INSTALLATION

A. Pipe Hanger and Support Installation: Comply with MSS SP-69 and MSS SP-89. Install hangers, supports, clamps, and attachments as required to properly support piping from building structure.

B. Channel Support System Installation: Arrange for grouping of parallel runs of piping and support together on field-assembled channel systems.

1. Field assemble and install according to manufacturer's written instructions.

C. Install building attachments to structural steel. Space attachments within maximum piping span length indicated in MSS SP-69. Install additional attachments at concentrated loads, including valves, flanges, guides, strainers, and expansion joints, and at changes in direction of piping.

D. Install powder-actuated drive-pin fasteners in concrete after concrete is placed and completely cured. Use operators that are licensed by powder-actuated tool manufacturer. Install fasteners according to powder-actuated tool manufacturer's operating manual.

E. Install mechanical-anchor fasteners in concrete after concrete is placed and completely cured. Install fasteners according to manufacturer's written instructions.

F. Install hangers and supports complete with necessary inserts, bolts, rods, nuts, washers, and other accessories.

G. Install hangers and supports to allow controlled thermal and seismic movement of piping systems, to permit freedom of movement between pipe anchors, and to facilitate action of expansion joints, expansion loops, expansion bends, and similar units.

H. Load Distribution: Install hangers and supports so that piping live and dead loads and stresses from movement will not be transmitted to connected equipment.

I. Pipe Slopes: Install hangers and supports to provide indicated pipe slopes and so maximum pipe deflections allowed by ASME B31.9, "Building Services Piping," is not exceeded.

J. Insulated Piping: Comply with the following:

1. Attach clamps and spacers to piping.

a. Piping Operating above Ambient Air Temperature: Clamp may project through insulation.

b. Piping Operating below Ambient Air Temperature: Use thermal-hanger shield insert with clamp sized to match OD of insert.

c. Do not exceed pipe stress limits according to ASME B31.9.

2. Install MSS SP-58, Type 39 protection saddles, if insulation without vapor barrier is indicated. Fill interior voids with insulation that matches adjoining insulation.

3. Install MSS SP-58, Type 40 protective shields on cold piping with vapor barrier. Shields shall span arc of 180 degrees.

4. Shield Dimensions for Pipe: Not less than the following:

a. NPS 1/4 to NPS 3-1/2 (DN8 to DN90): 12 inches long and 0.048 inch thick.

b. NPS 4 (DN100): 12 inches long and 0.06 inch thick.

5. Insert Material: Length at least as long as protective shield.

Page 23: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 29 (15060) - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.03 EQUIPMENT SUPPORTS

A. Fabricate structural-steel stands to suspend equipment from structure above or to support equipment above floor.

B. Grouting: Place grout under supports for equipment and make smooth bearing surface.

C. Prime and Paint Equipment Supports as specified in Section 09 90 00 “Painting”.

3.04 METAL FABRICATION

A. Cut, drill, and fit miscellaneous metal fabrications for heavy-duty steel trapezes and equipment supports.

B. Fit exposed connections together to form hairline joints. Field-weld connections that cannot be shop-welded because of shipping size limitations.

C. Field Welding: Comply with AWS D1.1 procedures for shielded metal arc welding, appearance and quality of welds, and methods used in correcting welding work, and with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. Finish welds at exposed connections so no roughness shows after finishing and contours of welded surfaces match adjacent contours.

3.05 ADJUSTING

A. Hanger Adjustment: Adjust hangers to distribute loads equally on attachments to level equipment and to achieve indicated slope of pipe.

3.06 PAINTING

A. Touching Up: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal are specified in Section 09 90 00 “Painting”.

B. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A780.

END OF SECTION

Page 24: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 48 (15070) – VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 48 (15070) - VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Vibration Isolators.

2. Roof Curb Mounted Vibration Isolation Bases.

B. Related Sections:

1. Section 03 30 00 (03300) - Cast-In-Place Concrete

2. Section 04 20 00 (04200) - Unit Masonry

3. Section 05 12 00 (05120) - Structural Steel

4. Section 06 10 01 (06100) - Rough Carpentry

5. Section 09 90 00 (09900) - Painting

6. Section 23 05 00 (15050) – Common Work Results for HVAC

7. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: for pipe hanger restraints.

8. Section 23 31 13 (15815) - Metal Ducts: for flexible duct connectors.

1.02 REFERENCES

A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A36 “Standard Specification for Carbon Structural Steel”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: Indicate types, styles, materials, and finishes for each type of isolator specified. Include load deflection curves.

2. Shop Drawings: Show designs and calculations, certified by a professional engineer, as required by the local authority, for the following:

a. Design Calculations: Calculations for selection of vibration isolators and design of vibration isolation bases.

1.04 COORDINATION

A. Coordinate layout and installation of vibration isolation devices with other construction that penetrates ceilings or is supported by them, including light fixtures, HVAC equipment, fire-suppression-system components, and partition assemblies.

B. Coordinate size and location of concrete housekeeping and vibration isolation bases. Cast anchor-bolt inserts into base. Concrete, reinforcement, and formwork requirements are specified in Division 03 Sections.

Page 25: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 48 – VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

C. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items are specified in Division 07 Sections.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Cooper B-Line Systems, Inc. (800-851-7415)

2. Kinetics Noise Control, Inc. (877-457-2695)

3. Mason Industries, Inc. (631-348-0282)

2.02 VIBRATION ISOLATORS

A. Isolator Pads: Oil and water resistant and factory cut to sizes that match requirements of the equipment supported.

1. Rubber Isolator Pads: Elastomer (neoprene or silicone) arranged in single or multiple layers and molded with a nonslip pattern and steel baseplates of sufficient stiffness to provide uniform loading over the pad area.

2. Load Range: From 10 to 50 psig and a deflection not less than 0.08 inch per 1 inch of thickness. Do not exceed a loading of 50 psig.

B. Rubber Isolator Mounts: Double-deflection type, with molded, oil-resistant rubber or neoprene isolator elements, with encapsulated top- and baseplates. Factory-drilled and tapped top plate for bolted equipment mounting. Factory-drilled baseplate for bolted connection to structure. Color-code to indicate capacity range.

C. Spring Isolators: Freestanding, laterally stable, open-spring-type isolators.

1. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

2. Minimum Additional Travel: 50 percent of the required deflection at rated load.

3. Lateral Stiffness: More than 1.2 times the rated vertical stiffness.

4. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure.

5. Baseplates: Factory drilled for bolting to structure and bonded to a 1/4-inch- thick, rubber isolator pad attached to the baseplate underside. Size baseplates to limit floor loading to 100 psig.

6. Top Plates: Provide threaded studs for fastening and leveling equipment.

7. Finishes: Manufacturer's standard corrosive-resistant finish.

D. Restrained Spring Isolators: Vertically restrained, freestanding, laterally stable, steel open-spring-type isolators.

1. Housing: Welded steel with resilient vertical limit stops to prevent spring extension due to wind loads or when weight is removed. Factory-drilled baseplate for bolting to structure and bonded to a 1/4-inch thick, rubber isolator pad attached to the baseplate underside. Provide adjustable equipment mounting and leveling bolt.

2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

3. Minimum Additional Travel: 50 percent of the required deflection at rated load.

Page 26: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 48 (15070) – VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

4. Lateral Stiffness: More than 0.8 times the rated vertical stiffness.

5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure.

6. Finishes: Baked enamel for metal components on isolators for interior use. Hot-dip galvanized for metal components on isolators for exterior use.

E. Rubber Hangers: Double-deflection type, with molded, oil-resistant rubber or neoprene isolator elements bonded to formed-steel housings with threaded connections for hanger rods. Color-code to indicate capacity range.

F. Spring Hangers: Combination spring and elastomeric hanger with coil spring and elastomeric insert in compression.

1. Frame: Formed steel, fabricated for connection to threaded rods and to allow for 30 degrees of angular hanger rod misalignment without binding or reducing isolation efficiency.

2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

3. Minimum Additional Travel: 50 percent of the required deflection at rated load.

4. Elastomeric Element: Molded, oil-resistant rubber or neoprene.

5. Finishes: Baked enamel for metal components. Color-code to indicate capacity range.

2.03 ROOF CURB MOUNTED VIBRATION ISOLATION BASES

A. Extended aluminum bases designed and fabricated by the isolation equipment manufacturer. Mason Industries Model CMAB or equivalent.

1. Curb mounted rooftop equipment shall be mounted on isolation bases that fit over the roof curb and under the isolated equipment.

2. The extruded aluminum top member shall overlap the bottom member to provide water run-off should the seal fail.

3. The aluminum members shall house springs. Spring diameters shall be no less than 0.8 of the spring height at rated load.

4. Wind resistance shall be provided by means of resilient snubbers in the corners with a minimum clearance of 0.25” so as not to interfere with the spring action except in high winds.

5. The weather seal shall consist of continuous closed cell sponge materials both above and below the base and a waterproof flexible ductlike EPDM connection joining the outside perimeter of the overlapping aluminum members.

PART 3 EXECUTION 3.01 INSTALLATION

A. Install and anchor vibration- and sound-control products according to manufacturer's written instructions and authorities having jurisdiction.

B. Anchor interior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt isolator baseplates to structural floors as required by authorities having jurisdiction.

C. Anchor exterior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt isolator baseplates to structural supports as required by authorities having jurisdiction.

D. Install pipe connectors at connections for equipment supported on vibration isolators.

Page 27: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 48 – VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.02 ADJUSTING AND CLEANING

A. Adjust limit stops on restrained spring isolators to mount equipment at normal operating height. After equipment installation is complete, adjust limit stops so they are out of contact during normal operations.

B. Adjust thrust restraints for a maximum of 1/4 inch of movement at start and stop

END OF SECTION

Page 28: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 53 (15075) - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 53 (15075) - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Identifying Devices and Labels

B. Related Sections:

1. Section 23 05 00 (15050) – Common Work Results for HVAC

1.02 REFERENCES

A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. C1036 “Standard Specification for Flat Glass”

B. The American Society of Mechanical Engineers (ASME) Publications:

1. A13.1 “Scheme for the Identification of Piping Systems”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: For identification materials and devices.

2. Samples: Of color, lettering style, and graphic representation required for each identification material and device.

1.04 QUALITY ASSURANCE

A. Comply with ASME A13.1, "Scheme for the Identification of Piping Systems" for lettering size, length of color field, colors, and viewing angles of identification devices.

1.05 SEQUENCING AND SCHEDULING

A. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied.

B. Install identifying devices before installing acoustical ceilings and similar concealment.

PART 2 PRODUCTS 2.01 GENERAL

A. General: Products specified are for applications referenced in other Division 23 Sections. If more than single type is specified for listed applications, selection is Installer's option.

B. Pipes Including Insulation: Full-band pipe markers, extending 360 degrees around pipe at each location.

2.02 IDENTIFYING DEVICES AND LABELS

A. Lettering: Manufacturer's standard preprinted captions as selected by Owner's Representative.

B. Lettering: Use piping system terms indicated and abbreviate only as necessary for each application length.

Page 29: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 53 (15075) - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Arrows: Either integrally with piping system service lettering, to accommodate both directions, or as separate unit, on each pipe marker to indicate direction of flow.

C. Plastic Duct Markers: Manufacturer's standard laminated plastic, in the following color codes:

1. Green: Cold-air supply.

2. Yellow: Hot-air supply.

3. Blue: Exhaust, outside, return, and mixed air.

4. Terminology: Include direction of airflow; duct service such as supply, return, and exhaust; duct origin, duct destination, and design flow.

D. Plastic Tape: Manufacturer's standard color-coded, pressure-sensitive, self-adhesive, vinyl tape, at least 3 mils thick.

1. Width: 1-1/2 inches on pipes with OD, including insulation, less than 6 inches; 2-1/2 inches for larger pipes.

2. Color: Comply with ASME A13.1, unless otherwise indicated.

E. Valve Tags: Stamped or engraved with 1/4-inch letters for piping system abbreviation and 1/2-inch sequenced numbers. Include 5/32-inch hole for fastener.

1. Material: 0.032-inch thick, polished brass.

2. Size: 1-1/2-inches diameter, unless otherwise indicated.

F. Valve Tag Fasteners: Brass, wire-link chain and S-hooks.

G. Access Panel Markers: 1/16-inch thick, engraved plastic-laminate markers, with abbreviated terms and numbers corresponding to concealed valve. Provide 1/8-inch center hole for attachment.

H. Valve Schedule Frames: Glazed display frame for removable mounting on masonry walls for each page of valve schedule. Include screws.

1. Frame: Extruded aluminum.

2. Glazing: ASTM C1036, Type I, Class 1, Glazing quality B, 2.5-mm, single-thickness glass.

I. Lettering and Graphics: Coordinate names, abbreviations, and other designations used in mechanical identification with corresponding designations indicated. Use numbers, letters, and terms indicated for proper identification, operation, and maintenance of mechanical systems and equipment.

1. Multiple Systems: Identify individual system number and service if multiple systems of same name are indicated.

PART 3 EXECUTION 3.01 LABELING AND IDENTIFYING PIPING SYSTEMS

A. Install pipe markers on each system as indicated below. Include arrows showing normal direction of flow.

1. Gas.

2. Condensate.

3. Vent.

4. Pool water.

Page 30: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 53 (15075) - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Marker Type: Plastic markers, with application systems. Install on pipe insulation segment where required for hot, noninsulated pipes.

C. Fasten markers on pipes and insulated pipes by one of following methods:

1. Snap-on application of pretensioned, semirigid plastic pipe marker.

D. Locate pipe markers where piping is exposed in machine rooms; accessible maintenance spaces such as shafts, tunnels, and plenums; and exterior nonconcealed locations according to the following:

1. Near each valve and control device.

2. Near each branch connection, excluding short takeoffs for fixtures and terminal units. Mark each pipe at branch, where flow pattern is not obvious.

3. Near penetrations through walls, floors, ceilings, or nonaccessible enclosures.

4. At access doors, manholes, and similar access points that permit view of concealed piping.

5. Near major equipment items and other points of origination and termination.

6. Spaced at a maximum of 50-foot intervals along each run. Reduce intervals to 25 feet in areas of congested piping and equipment.

7. On piping above removable acoustical ceilings, except omit intermediately spaced markers.

3.02 VALVE TAGS

A. Install on valves and control devices in piping systems, except check valves, valves within factory-fabricated equipment units, plumbing fixture supply stops, shutoff valves, faucets, convenience and lawn-watering hose connections, and HVAC terminal devices and similar roughing-in connections of end-use fixtures and units. List tagged valves in valve schedule.

B. Valve Tag Application Schedule: Tag valves according to size, shape, color scheme, and with captions similar to those indicated in the following:

1. Pool Water

C. Tag Material: Brass.

D. Tag Size and Shape: According to the following:

1. Pool Water: 1-1/2 inches round.

2. Gas: 1-1/2 inches round.

E. Install framed valve schedule in each major mechanical equipment room.

F. Valve schedule and tag locations shall be shown on record drawings.

3.03 LABELING AND IDENTIFYING DUCT SYSTEMS.

A. Duct Systems: Identify air supply, return, exhaust, intake, and relief ducts with duct markers; or provide stenciled signs and arrows showing service and direction of flow.

1. Location: Locate signs near points where ducts enter into concealed spaces and at maximum intervals of 50 feet in each space where ducts are exposed or concealed by removable ceiling system.

3.04 ADJUSTING AND CLEANING

A. Relocate HVAC identification materials and devices that have become visually blocked by work of this or other Divisions.

Page 31: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 53 (15075) - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Clean faces of identification devices and glass frames of valve charts

END OF SECTION

Page 32: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Balancing airflow within distribution systems, including sub-mains, branches, and terminals, to indicated quantities according to specified tolerances.

2. Adjusting total HVAC systems to provide indicated quantities.

3. Measuring electrical performance of HVAC and plumbing equipment.

4. Setting quantitative performance of HVAC and plumbing equipment.

5. Verifying that automatic control devices are functioning properly.

6. Reporting results of the activities and procedures specified in this Section.

7. Adjustment of recirculating domestic hot water return system.

8. Verify performance of package terminal air conditioning units.

B. Related Sections:

1. Testing and adjusting requirements unique to particular systems and equipment are included in the Sections that specify those systems and equipment.

2. Field quality-control testing to verify that workmanship quality for system and equipment installation is specified in system and equipment Sections.

1.02 REFERENCES

A. Associated Air Balance Council (AABC): "National Standards for Testing, Adjusting and Balancing"

B. Air Movement & Control Association International, Inc. (AMCA): 201, "Fans and Systems

C. National Environmental Balancing Bureau (NEBB): “Procedural Standards for Testing, Adjusting and Balancing of Environmental Systems”

D. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): "HVAC Systems--Duct Design"

1.03 DEFINITIONS

A. Adjust: To regulate fluid flow rate and air patterns at the terminal equipment, such as to reduce fan speed or adjust a damper.

B. Balance: To proportion flows within the distribution system, including sub-mains, branches, and terminals, according to design quantities.

C. Draft: A current of air, when referring to localized effect caused by one or more factors of high air velocity, low ambient temperature, or direction of airflow, whereby more heat is withdrawn from a person's skin than is normally dissipated.

D. Procedure: An approach to and execution of a sequence of work operations to yield repeatable results.

E. Report Forms: Test data sheets for recording test data in logical order.

F. Static Head: The pressure due to the weight of the fluid above the point of measurement. In a closed system, static head is equal on both sides of the pump.

Page 33: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

G. Suction Head: The height of fluid surface above the centerline of the pump on the suction side.

H. System Effect: A phenomenon that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system.

I. System Effect Factors: Allowances used to calculate a reduction of the performance ratings of a fan when installed under conditions different from those presented when the fan was performance tested.

J. Terminal: A point where the controlled medium, such as fluid or energy, enters or leaves the distribution system.

K. Test: A procedure to determine quantitative performance of a system or equipment.

L. Testing, Adjusting, and Balancing Agent: The entity responsible for performing and reporting the testing, adjusting, and balancing procedures.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Quality-Assurance Submittals: Within 30 days from the Contractor's Notice to Proceed, submit 2 copies of evidence that the testing, adjusting, and balancing Agent and this Project's testing, adjusting, and balancing team members meet the qualifications specified in the "Quality Assurance" Article below.

C. Contract Documents Examination Report: Within 45 days from the Contractor’s Notice to Proceed, submit 2 copies of the Contract Documents Review Report as specified in Part 3 of this Section.

D. Submittals Examination Report: Prior to the start of duct or piping fabrication, submit 2 copies of the Submitted Examination Report as specified in Part 3 of this Section.

E. Certified Testing, Adjusting, and Balancing Reports: Submit 2 copies of reports prepared, as specified in this Section, on approved forms certified by the testing, adjusting, and balancing Agent.

1.05 QUALITY ASSURANCE

A. Agent Qualifications: Engage a testing, adjusting, and balancing agent certified by either AABC or NEBB.

B. Certification of Testing, Adjusting, and Balancing Reports: Certify the testing, adjusting, and balancing field data reports. This certification includes the following:

1. Review field data reports to validate accuracy of data and to prepare certified testing, adjusting, and balancing reports.

2. Certify that the testing, adjusting, and balancing team complied with the approved testing, adjusting, and balancing plan and the procedures specified and referenced in this Specification.

C. Testing, Adjusting, and Balancing Reports: Use testing, adjusting, and balancing standard forms from AABC’s “National Standards for Testing, Adjusting and Balancing” or NEBB's “Procedural Standards for Testing, Adjusting and Balancing of Environmental Systems”.

D. Instrumentation Calibration: Calibrate instruments at least every 6 months or more frequently if required by the instrument manufacturer.

Page 34: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

E. Testing, Adjusting, and Balancing Conference: Meet with the Owner’s representatives on approval of the testing, adjusting, and balancing strategies and procedures plan to develop a mutual understanding of the details. Ensure the participation of testing, adjusting, and balancing team members, equipment manufacturers’ authorized service representatives, HVAC controls Installer, and other support personnel. Provide 7 days advance notice of scheduled meeting time and location. As a minimum include the following agenda items:

1. Submittal distribution requirements.

2. Contract Documents examination report.

3. Testing, adjusting, and balancing plan.

4. Work schedule and Project site access requirements.

5. Coordination and cooperation of trades and subcontractors.

1.06 COORDINATION

A. Coordinate the efforts of factory-authorized service representatives for systems and equipment, HVAC controls installers, and other mechanics to operate HVAC systems and equipment to support and assist testing, adjusting, and balancing activities.

B. Notice: Provide 7 days' advance notice for each test. Include scheduled test dates and times.

C. Perform testing, adjusting, and balancing after leakage and pressure tests on air and water distribution systems have been satisfactorily completed.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine Contract Documents to discover conditions in systems' designs that may preclude proper testing, adjusting, and balancing of systems and equipment and submit “Contract Documents Examination Report”.

1. Contract Documents are defined in the General and Supplementary Conditions of the Contract.

2. Verify that balancing devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers, are required by the Contract Documents. Verify that quantities and locations of these balancing devices are accessible and appropriate for effective balancing and for efficient system and equipment operation.

3. Examine Engineer’s design data, including HVAC and Plumbing system descriptions, statements of design assumptions for environmental conditions and systems’ output, and statements of philosophies and assumptions about HVAC and Plumbing systems and equipment controls.

B. Examine approved submittal data of HVAC and Plumbing systems and equipment including sheet metal duct fabrication and plumbing piping shop drawings to ensure that the distribution system is reasonably complete and sufficiently designed to accurately balance the complete building. Submit “Submitting Examination Report”.

1. Examine equipment performance data, including fan and pump curves. Relate performance data to project conditions and requirements, including system effects that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system. Calculate system effect factors to reduce the performance ratings of HVAC equipment when installed under conditions different from those presented when

Page 35: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

the equipment was performance tested at the factory. To calculate system effects for air systems, use tables and charts found in AMCA 201, "Fans and Systems," Sections 07 through 10; or in SMACNA's "HVAC Systems--Duct Design," Sections 05 and 06. Compare this data with the design data and installed conditions.

C. Examine system and equipment installations to verify that they are complete and that testing, cleaning, adjusting, and commissioning specified in individual Specification Sections have been performed.

1. Examine HVAC and Plumbing systems and equipment installations to verify that indicated balancing devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers, are properly installed, and their locations are accessible and appropriate for effective balancing and for efficient system and equipment operation.

2. Examine systems for functional deficiencies that cannot be corrected by adjusting and balancing.

3. Examine air-handling equipment to ensure clean filters have been installed, bearings are greased, belts are aligned and tight, and equipment with functioning controls is ready for operation.

4. Examine terminal units to verify that they are accessible and their controls are connected and functioning.

5. Examine plenum ceilings, utilized for return air, to verify that they are airtight. Verify that pipe penetrations and other holes are sealed.

6. Examine heat-transfer coils for clean and straight fins.

7. Examine equipment for installation and for properly operating safety interlocks and controls.

8. Examine automatic temperature system components to verify the following:

a. Dampers, and other controlled devices operate by the intended controller.

b. Dampers are in the position indicated by the controller.

c. Integrity dampers for free and full operation and for tightness of fully closed and fully open positions. This includes dampers in variable-air-volume terminals.

d. Thermostats are located to avoid adverse effects of sunlight, drafts, and cold walls.

e. Sensors are located to sense only the intended conditions.

f. Sequence of operation for control modes is according to the Contract Documents.

g. Controller set points are set at design values. Observe and record system reactions to changes in conditions. Record default set points if different from design values.

h. Interlocked systems are operating.

i. Changeover from heating to cooling mode occurs according to design values.

D. Examine project record documents described in Section 01 78 39 (01785) - “Project Record Documents”.

E. Report deficiencies discovered before and during performance of testing, adjusting, and balancing procedures.

Page 36: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.02 PREPARATION

A. Prepare a testing, adjusting, and balancing plan that includes strategies and step-by-step procedures.

B. Complete system readiness checks and prepare system readiness reports. Verify the following:

1. Permanent electrical power wiring is complete.

2. Automatic temperature-control systems are operational.

3. Equipment and duct access doors are properly located, sized, and securely closed.

4. Verify that fire dampers are open.

5. Isolating and balancing valves are open and control valves are operational.

6. Access to balancing devices is provided.

7. Windows and doors can be closed so design conditions for system operations can be met.

3.03 GENERAL TESTING AND BALANCING PROCEDURES

A. Perform testing and balancing procedures on each system according to the procedures contained in AABC national standards and this Section; or in NEBB's "Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems" and this Section.

B. Mark equipment settings with paint or other suitable, permanent identification material, including damper-control positions, balancing, valve indicators, fan-speed-control levers, and similar controls and devices, to show final settings.

C. Cut insulation, ducts, pipes, and equipment cabinets for installation of test probes to the minimum extent necessary to allow adequate performance of procedures. After testing and balancing, close probe holes and patch insulation with new materials identical to those removed. Restore vapor barrier and finish according to the insulation Specifications for this Project. Plastic plugs with retainers may be used to patch drilled holes in ductwork and housings.

3.04 FUNDAMENTAL AIR SYSTEMS' BALANCING PROCEDURES

A. Prepare test reports for both fans and outlets. Obtain manufacturer's outlet factors and recommended testing procedures. Crosscheck the summation of required outlet volumes with required fan volumes.

B. Prepare schematic single line diagrams of systems' "as-built" duct layouts and domestic hot water distribution.

C. Determine the best locations in main and branch ducts for accurate duct airflow measurements.

D. Check the airflow patterns from the outside-air louvers and dampers and the return- and exhaust-air dampers, through the supply-fan discharge and mixing dampers.

E. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.

F. Verify that motor starters are equipped with properly sized thermal protection.

G. Check dampers for proper position to achieve desired airflow path.

H. Check for airflow blockages.

I. Check condensate drains for proper connections and functioning.

J. Check for proper sealing of air-handling unit components.

Page 37: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.05 CONSTANT-VOLUME AIR SYSTEMS' BALANCING PROCEDURES

A. The procedures in this Article apply to constant-volume supply-, return-, and exhaust-air systems.

B. Adjust fans to deliver total design airflows within the maximum allowable rpm listed by the fan manufacturer.

1. Measure fan static pressures to determine actual static pressure as follows:

a. Measure outlet static pressure as far downstream from the fan as practicable and upstream from restrictions in ducts such as elbows and transitions.

b. Measure static pressure directly at the fan outlet or through the flexible connection.

c. Measure inlet static pressure of single-inlet fans in the inlet duct as near the fan as possible, upstream from flexible connection and downstream from duct restrictions.

d. Measure inlet static pressure of double-inlet fans through the wall of the plenum that houses the fan.

2. Measure static pressure across each air-handling unit component.

a. Simulate dirty filter operation and record the point at which maintenance personnel must change filters.

3. Measure static pressures entering and leaving other devices such as sound traps, heat recovery equipment, and air washers under final balanced conditions.

4. Compare design data with installed conditions to determine variations in design static pressures versus actual static pressures. Compare actual system effect factors with calculated system effect factors to identify where variations occur. Recommend corrective action to align design and actual conditions.

5. Adjust fan speed higher or lower than design with the approval of the Owner’s Representative. Make required adjustments to pulley sizes, motor sizes, and electrical connections to accommodate fan-speed changes.

6. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure no overload will occur. Measure amperage in full cooling, full heating, and economizer modes to determine the maximum required brake horsepower.

C. Adjust volume dampers for main duct, sub-main ducts, and major branch ducts to design airflows within specified tolerances.

1. Measure static pressure at a point downstream from the balancing damper and adjust volume dampers until the proper static pressure is achieved.

a. Where sufficient space in sub-mains and branch ducts is unavailable for Pilot-tube traverse measurements, measure airflow at terminal outlets and inlets and calculate the total airflow for that zone.

2. Re-measure each sub-main and branch duct after all have been adjusted. Continue to adjust sub-mains and branch ducts to design airflows within specified tolerances.

D. Measure terminal outlets and inlets without making adjustments.

1. Measure terminal outlets using a direct-reading hood or the outlet manufacturer's written instructions and calculating factors.

Page 38: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

E. Adjust terminal outlets and inlets for each space to design airflows within specified tolerances of design values. Make adjustments using volume dampers rather than extractors and the dampers at the air terminals.

1. Adjust each outlet in the same room or space to within specified tolerances of design quantities without generating noise levels above the limitations prescribed by the Contract Documents.

2. Adjust patterns of adjustable outlets for proper distribution without drafts.

3.06 MOTORS

A. Motors: Test at final balanced conditions and record the following data:

1. Manufacturer, model, and serial numbers.

2. Motor horsepower rating.

3. Motor RPM.

4. Efficiency rating if high-efficiency motor.

5. Nameplate and measured voltage, each phase.

6. Nameplate and measured amperage, each phase.

7. Starter thermal-protection-element rating.

3.07 CONDENSING UNITS

A. Verify proper rotation of fans and measure entering- and leaving-air temperatures. Record compressor data.

3.08 HEAT-TRANSFER COILS

A. Electric-Heating Coils: Measure the following data for each coil:

1. Nameplate data.

2. Airflow.

3. Entering- and leaving-air temperatures at full load.

4. Voltage and amperage input of each phase at full load and at each incremental stage.

5. Calculated kW at full load.

6. Fuse or circuit-breaker rating for overload protection.

3.09 TEMPERATURE TESTING

A. During testing, adjusting, and balancing, report need for adjustment in temperature regulation within the automatic temperature-control system.

B. Measure indoor and outdoor wet- and dry-bulb temperatures every other hour for a period of 2 successive 8-hour days, in each separately controlled zone, to prove correctness of final temperature settings. Measure when the building or zone is occupied.

3.10 TEMPERATURE-CONTROL VERIFICATION

A. Verify that controllers are calibrated and commissioned.

B. Check transmitter and controller locations and note conditions that would adversely affect control functions.

C. Record controller settings and note variances between set points and actual measurements.

D. Verify operation of limiting controllers (i.e., high- and low-temperature controllers).

Page 39: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 8 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

E. Verify free travel and proper operation of control devices such as damper and valve operators.

F. Confirm interaction of electrically operated switch transducers.

G. Confirm interaction of interlock and lockout systems.

H. Verify main control supply-air pressure and observe compressor and dryer operations.

I. Record voltages of power supply and controller output. Determine if the system operates on a grounded or non-grounded power supply.

J. Note operation of electric actuators using spring return for proper fail-safe operations.

3.11 TOLERANCES

A. Set HVAC system airflow rates within the following tolerances:

1. Supply, Return, and Exhaust Fans: Plus 5 to plus 10 percent.

2. Air Outlets and Inlets: 0 to minus 10 percent.

B. Set plumbing and pool system water flow rates within the following tolerances:

1. Domestic Hot Water Recirculation Flow Rate: 0 to minus 10 percent.

2. Pool Water Pumps Flow Rate: Plus 10 to minus 10 percent.

3.12 FINAL REPORT

A. General: Typewritten, or computer printout in letter-quality font, on standard bond paper, in 3-ring binder, tabulated and divided into sections by tested and balanced systems.

B. Include a certification sheet in front of binder signed and sealed by the certified testing and balancing engineer.

1. Include a list of the instruments used for procedures, along with proof of calibration.

C. Final Report Contents: In addition to the certified field report data, include the following:

1. Pump curves.

2. Fan curves.

3. Manufacturers' test data.

4. Field test reports prepared by system and equipment installers.

5. Other information relative to equipment performance, but do not include approved Shop Drawings and Product Data.

D. General Report Data: In addition to the form titles and entries, include the following data in the final report, as applicable:

1. Title page.

2. Name and address of testing, adjusting, and balancing Agent.

3. Project name.

4. Project location.

5. Owner’s name and address.

6. Engineer's name and address.

7. Contractor's name and address.

8. Report date.

Page 40: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 9 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

9. Signature of testing, adjusting, and balancing Agent who certifies the report.

10. Summary of contents, including the following:

a. Design versus final performance.

b. Notable characteristics of systems.

c. Description of system operation sequence if it varies from the Contract Documents.

11. Nomenclature sheets for each item of equipment.

12. Data for terminal units, including manufacturer, type size, and fittings.

13. Notes to explain why certain final data in the body of reports vary from design values.

14. Test conditions for fans and pump performance forms, including the following:

a. Settings for outside-, return-, and exhaust-air dampers.

b. Conditions of filters.

c. Cooling coil, wet- and dry-bulb conditions.

d. Other system operating conditions that affect performance.

E. System Diagrams: Include schematic layouts of air distribution systems and domestic hot water distribution systems. Present with single-line diagrams and include the following:

1. Quantities of outside, supply, return, and exhaust airflows.

2. Duct, outlet, and inlet sizes.

3. Location of manual volume control dampers.

4. Water flow meter.

5. Balancing valve sizes/locations.

F. Fan Test Reports: For supply, return, and exhaust fans, include the following:

1. Fan Data: Include the following:

a. System identification.

b. Location.

c. Make and type.

d. Model number and size.

e. Manufacturer's serial number.

f. Arrangement and class.

g. Sheave make, size in inches and bore.

h. Sheave dimensions, center-to-center and amount of adjustments in inches.

2. Motor Data: Include the following:

a. Make and frame type and size.

b. Horsepower and rpm.

c. Volts, phase, and hertz.

d. Full-load amperage and service factor.

e. Sheave make, size in inches and bore.

Page 41: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 05 93 (15950) - TESTING, ADJUSTING, AND BALANCING FOR HVAC ▪ ▪ PAGE 10 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

f. Sheave dimensions, center-to-center and amount of adjustments in inches (mm).

g. Number of belts, make, and size.

3. Test Data: Include design and actual values for the following:

a. Total airflow rate in cfm.

b. Total system static pressure in inches wg.

c. Fan rpm.

d. Discharge static pressure in inches wg.

e. Suction static pressure in inches wg

G. Air Handling Test Reports.

H. Gas-Fired Heat Apparatus Test Reports; i.e., unit heaters, duct furnaces, domestic water heaters.

I. Electric Coil Test Reports; i.e., electric baseboards, electric unit heaters, electric cabinet heaters.

J. Duct Traverse Reports.

K. Air Terminal Device Reports; i.e., diffusers/registers/grilles.

L. Pool Dehumidification Test Reports.

M. Package Terminal Air Conditioning Test Reports; including equipment leveling to ensure condensate is pitched to building exterior.

N. Plumbing Pump Test Reports including recirculating hot water, pool, and sump pumps.

O. Instrument Calibration Reports.

3.13 ADDITIONAL TESTS

A. Within 90 days of completing testing, adjusting, and balancing, perform additional testing and balancing to verify that balanced conditions are being maintained throughout and to correct unusual conditions.

B. Seasonal Periods: If initial testing, adjusting, and balancing procedures were not performed during near-peak summer and winter conditions, perform additional inspections, testing, and adjusting during near-peak summer and winter conditions.

END OF SECTION

Page 42: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 07 00 (15081) - HVAC INSULATION

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Insulation Materials

2. Jackets

3. Accessories and Attachments

4. Vapor Retarders

B. Related Sections:

1. Section 07 84 00 (07840) - Firestopping: Firestopping materials and requirements for penetrations through fire and smoke barriers.

2. Section 22 07 00 (15083) - Plumbing Insulation

3. Section 23 31 13 (15815) - Metal Ducts: For duct liner.

1.02 REFERENCES

A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A666 “Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar”

2. C533 “Standard Specification for Calcium Silicate Block and Pipe Thermal Insulation”

3. C534 “Standard Specification for Preformed Flexible Elastomeric Cellular Thermal Insulation in Sheet and Tubular Form”

4. C612 “Standard Specification for Mineral Fiber Block and Board Thermal Insulation”

5. C921 “Standard Practice for Determining the Properties of Jacketing Materials for Thermal Insulation”

6. C1126 “Standard Specification for Faced or Unfaced Rigid Cellular Phenolic Thermal Insulation”

7. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"

B. Military Specifications:

1. MIL-C-20079H “Cloth, Glass; Tape, Textile Glass and Thread, Glass and Wire-Reinforced Glass”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data:

a. Identify thermal conductivity, thickness, and jackets (both factory and field applied) for each type of product indicated.

2. Shop Drawings:

Page 43: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

a. Submit manufacturer’s data for each type of insulation used.

1.04 QUALITY ASSURANCE

A. Installer Qualifications: Skilled mechanics who have successfully completed an apprenticeship program or similar industry recognized craft training program.

B. Fire-Test-Response Characteristics: As determined by testing materials identical to those specified in this Section according to ASTM E84, by a testing and inspecting agency acceptable to authorities having jurisdiction. Factory label insulation and jacket materials and sealer and cement material containers with appropriate markings of applicable testing and inspecting agency.

1. Insulation Installed Indoors: Flame-spread rating of 25 or less, and smoke-developed rating of 50 or less.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Packaging: Ship insulation materials in containers marked by manufacturer with appropriate ASTM specification designation, type and grade, and maximum use temperature.

1.06 COORDINATION

A. Coordinate clearance requirements with duct Installer for insulation application.

1.07 SCHEDULING

A. Schedule insulation application after testing duct systems. Insulation application may begin on segments of ducts that have satisfactory test results.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Mineral-Fiber Insulation:

a. CertainTeed Corp. (610-647-3011)

b. Knauf Insulation. (800-825-4434)

c. Owens-Corning Fiberglas Corp. (800-447-3759)

2. Mineral-Fiber Blanket Thermal Insulation:

a. CertainTeed Corp. (610-647-3011)

b. Knauf Insulation. (800-825-4434)

c. Owens-Corning Fiberglas Corp. (800-447-3759)

3. Closed-Cell Phenolic-Foam Insulation:

a. "Kooltherm Pipe Insulation"; Kingspan Insulation Ltd. (904-486-0553).

4. Flexible Elastomeric Thermal Insulation:

a. Armstrong World Industries (800-448-1405)

b. Rubatex International LLC (800-782-2839)

2.02 INSULATION MATERIALS

A. Mineral-Fiber Board Thermal Insulation:

Page 44: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Glass fibers bonded with a thermosetting resin. Comply with ASTM C612, Type IB, without facing and with all-service jacket manufactured from kraft paper, reinforcing scrim, aluminum foil, and vinyl film.

B. Mineral-Fiber Blanket Thermal Insulation:

1. Glass fibers bonded with a thermosetting resin. Comply with ASTM C553, Type II, without facing and with all-service jacket manufactured from kraft paper, reinforcing scrim, aluminum foil, and vinyl film.

C. Closed-Cell Phenolic-Foam Insulation:

1. Block insulation of rigid, expanded, closed-cell structure. Comply with ASTM C1126, Type II, Grade 1.

D. Flexible Elastomeric Thermal Insulation:

1. Closed-cell, sponge or expanded-rubber materials.

2. Comply with ASTM C534, Type I for tubular materials and Type II for sheet materials

a. Adhesive: As recommended by insulation manufacturer.

b. Ultraviolet Protective Coating: As recommended by insulation manufacturer.

2.03 FIELD-APPLIED JACKETS

A. General: ASTM C921, Type 1, unless otherwise indicated.

B. Self-Adhesive Outdoor Jacket: 60-mil-thick, laminated vapor barrier and waterproofing membrane for installation over insulation located aboveground outdoors; consisting of a rubberized bituminous resin on a crosslaminated polyethylene film covered with stucco-embossed aluminum-foil facing.

1. Products: Subject to compliance with requirements, provide one of the following:

a. Polyguard Products, Inc.; Alumaguard 60.

b. MFM Building Products Corp.; Flex-Clad 400.

2.04 ACCESSORIES AND ATTACHMENTS

A. Glass Cloth and Tape: Comply with MIL-C-20079H, Type I for cloth and Type II for tape. Woven glass-fiber fabrics, plain weave, presized a minimum of 8 oz./sq. yd.

1. Tape Width: 4 inches.

B. Bands: 3/4 inch wide, in one of the following materials compatible with jacket:

1. Stainless Steel: ASTM A666, Type 304; 0.020 inch thick.

2. Galvanized Steel: 0.005 inch thick.

3. Aluminum: 0.007 inch thick.

4. Brass: 0.010 inch thick.

5. Nickel-Copper Alloy: 0.005 inch thick.

C. Wire: 0.080-inch, nickel-copper alloy; 0.062-inch, soft-annealed, stainless steel; or 0.062-inch, soft-annealed, galvanized steel.

D. Weld-Attached Anchor Pins and Washers: Copper-coated steel pin for capacitor-discharge welding and galvanized speed washer. Pin length sufficient for insulation thickness indicated.

1. Welded Pin Holding Capacity: 100 lb for direct pull perpendicular to the attached surface.

Page 45: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

E. Adhesive-Attached Anchor Pins and Speed Washers: Galvanized steel plate, pin, and washer manufactured for attachment to duct and plenum with adhesive. Pin length sufficient for insulation thickness indicated.

1. Adhesive: Recommended by the anchor pin manufacturer as appropriate for surface temperatures of ducts, plenums, and breechings; and to achieve a holding capacity of 100 lb for direct pull perpendicular to the adhered surface.

F. Self-Adhesive Anchor Pins and Speed Washers: Galvanized steel plate, pin, and washer manufactured for attachment to duct and plenum with adhesive. Pin length sufficient for insulation thickness indicated.

2.05 VAPOR RETARDERS

A. Mastics: Materials recommended by insulation material manufacturer that are compatible with insulation materials, jackets, and substrates.

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine substrates and conditions for compliance with requirements for installation and other conditions affecting performance of insulation application.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION

A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.

3.03 GENERAL APPLICATION REQUIREMENTS

A. Apply insulation materials, accessories, and finishes according to the manufacturer's written instructions; with smooth, straight, and even surfaces; and free of voids throughout the length of ducts and fittings.

B. Refer to schedules at the end of this Section for materials, forms, jackets, and thicknesses required for each duct system.

C. Use accessories compatible with insulation materials and suitable for the service. Use accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or dry state.

D. Apply multiple layers of insulation with longitudinal and end seams staggered.

E. Seal joints and seams with vapor-retarder mastic on insulation indicated to receive a vapor retarder.

F. Keep insulation materials dry during application and finishing.

G. Apply insulation with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by the insulation material manufacturer.

H. Apply insulation with the least number of joints practical.

I. Apply insulation over fittings and specialties, with continuous thermal and vapor-retarder integrity, unless otherwise indicated.

J. Hangers and Anchors: Where vapor retarder is indicated, seal penetrations in insulation at hangers, supports, anchors, and other projections with vapor-retarder mastic. Apply insulation continuously through hangers and around anchor attachments.

Page 46: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

K. Insulation Terminations: For insulation application where vapor retarders are indicated, seal ends with a compound recommended by the insulation material manufacturer to maintain vapor retarder.

L. Apply insulation with integral jackets as follows:

1. Pull jacket tight and smooth.

2. Joints and Seams: Cover with tape and vapor retarder as recommended by insulation material manufacturer to maintain vapor seal.

3. Vapor-Retarder Mastics: Where vapor retarders are indicated, apply mastic on seams and joints and at ends adjacent to duct flanges and fittings.

M. Cut insulation according to manufacturer's written instructions to prevent compressing insulation to less than 75 percent of its nominal thickness.

N. Install vapor-retarder mastic on ducts and plenums scheduled to receive vapor retarders.

1. Ducts with Vapor Retarders: Overlap insulation facing at seams and seal with vapor-retarder mastic and pressure-sensitive tape having same facing as insulation. Repair punctures, tears, and penetrations with tape or mastic to maintain vapor-retarder seal.

2. Ducts without Vapor Retarders: Overlap insulation facing at seams and secure with outward clinching staples and pressure-sensitive tape having same facing as insulation.

O. Roof Penetrations: Apply insulation for interior applications to a point even with top of roof flashing.

1. Seal penetrations with vapor-retarder mastic.

2. Apply insulation for exterior applications tightly joined to interior insulation ends.

3. Seal insulation to roof flashing with vapor-retarder mastic.

P. Interior Wall and Partition Penetrations: Apply insulation continuously through walls and partitions, except fire-rated walls and partitions.

Q. Fire-Rated Wall and Partition Penetrations: Terminate insulation at fire/smoke damper sleeves for fire-rated wall and partition penetrations.

R. Floor Penetrations: Terminate insulation at underside of floor assembly and at floor support at top of floor.

1. For insulation indicated to have vapor retarders, taper termination and seal insulation ends with vapor-retarder mastic.

3.04 MINERAL-FIBER INSULATION APPLICATION

A. Blanket Applications for Ducts and Plenums: Secure blanket insulation with adhesive and anchor pins and speed washers.

1. Apply adhesives according to manufacturer's recommended coverage rates per square foot, for 100 percent coverage of duct and plenum surfaces.

2. Apply adhesive to entire circumference of ducts and to all surfaces of fittings and transitions.

3. Install anchor pins and speed washers on sides and bottom of horizontal ducts and sides of vertical ducts as follows:

a. On duct sides with dimensions 18 inches and smaller, along longitudinal centerline of duct. Space 3 inches maximum from insulation end joints, and 16 inches o.c.

Page 47: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

b. On duct sides with dimensions larger than 18 inches. Space 16 inches o.c. each way, and 3 inches maximum from insulation joints. Apply additional pins and clips to hold insulation tightly against surface at cross bracing.

c. Anchor pins may be omitted from top surface of horizontal, rectangular ducts and plenums.

d. Do not overcompress insulation during installation.

4. Impale insulation over anchors and attach speed washers.

5. Cut excess portion of pins extending beyond speed washers or bend parallel with insulation surface. Cover exposed pins and washers with tape matching insulation facing.

6. Create a facing lap for longitudinal seams and end joints with insulation by removing 2 inches from one edge and one end of insulation segment. Secure laps to adjacent insulation segment with 1/2-inch staples, 1 inch o.c., and cover with pressure-sensitive tape having same facing as insulation.

7. Overlap unfaced blankets a minimum of 2 inches on longitudinal seams and end joints. Secure with steel band at end joints and spaced a maximum of 18 inches o.c.

8. Apply insulation on rectangular duct elbows and transitions with a full insulation segment for each surface. Apply insulation on round and flat-oval duct elbows with individually mitered gores cut to fit the elbow.

9. Insulate duct stiffeners, hangers, and flanges that protrude beyond the insulation surface with 6-inch wide strips of the same material used to insulate duct. Secure on alternating sides of stiffener, hanger, and flange with anchor pins spaced 6 inches o.c.

10. Apply vapor-retarder mastic to open joints, breaks, and punctures for insulation indicated to receive vapor retarder.

B. Board Applications for Ducts and Plenums: Secure board insulation with adhesive and anchor pins and speed washers.

1. Apply adhesives according to manufacturer's recommended coverage rates per square foot, for 100 percent coverage of duct and plenum surfaces.

2. Apply adhesive to entire circumference of ducts and to all surfaces of fittings and transitions.

3. Space anchor pins as follows:

a. On duct sides with dimensions 18 inches and smaller, along longitudinal centerline of duct. Space 3 inches maximum from insulation end joints, and 16 inches o.c.

b. On duct sides with dimensions larger than 18 inches. Space 16 inches o.c. each way, and 3 inches maximum from insulation joints. Apply additional pins and clips to hold insulation tightly against surface at cross bracing.

c. Anchor pins may be omitted from top surface of horizontal, rectangular ducts and plenums.

d. Do not overcompress insulation during installation.

4. Cut excess portion of pins extending beyond speed washers or bend parallel with insulation surface. Cover exposed pins and washers with tape matching insulation facing.

5. Create a facing lap for longitudinal seams and end joints with insulation by removing 2 inches from one edge and one end of insulation segment. Secure laps to adjacent

Page 48: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

insulation segment with 1/2-inch staples, 1 inch o.c., and cover with pressure-sensitive tape having same facing as insulation.

6. Apply insulation on rectangular duct elbows and transitions with a full insulation segment for each surface. Groove and score insulation to fit as closely as possible to outside and inside radius of elbows. Apply insulation on round and flat-oval duct elbows with individually mitered gores cut to fit the elbow.

7. Insulate duct stiffeners, hangers, and flanges that protrude beyond the insulation surface with 6-inch wide strips of the same material used to insulate duct. Secure on alternating sides of stiffener, hanger, and flange with anchor pins spaced 6 inches o.c.

8. Apply vapor-retarder mastic to open joints, breaks, and punctures for insulation indicated to receive vapor retarder.

3.05 CLOSED-CELL PHENOLIC-FOAM INSULATION APPLICATION

A. Apply insulation as follows:

1. Secure each layer of insulation to duct with stainless-steel bands at 12-inch intervals and tighten without deforming the insulation materials.

2. Apply two-layer insulation with joints tightly butted and staggered at least 3 inches. Secure inner layer with 0.062-inch, soft-annealed, stainless-steel wire spaced at 12-inch intervals. Secure outer layer with stainless-steel bands at 12-inch intervals.

3. On exposed applications, finish insulation with a skim coat of mineral-fiber, hydraulic-setting cement to surface of installed insulation. When dry, apply flood coat of lagging adhesive and press on one layer of glass cloth or tape. Overlap edges at least 1 inch. Apply finish coat of lagging adhesive over glass cloth or tape. Thin the finish coat to achieve smooth finish.

3.06 FLEXIBLE ELASTOMERIC THERMAL INSULATION APPLICATION

A. Apply insulation to straight pipes and tubes as follows:

1. Follow manufacturer’s written instructions for applying insulation.

2. Seal longitudinal seams and end joints with manufacturer’s recommended adhesive. Cement to avoid openings in insulation that will allow passage of air to the pipe surface.

B. Apply insulation to flanges as follows:

1. Apply pipe insulation to outer diameter of pipe flange.

2. Make width of insulation segment the same as overall width of the flange and bolts, plus twice the thickness of the pipe insulation.

3. Fill voids between inner circumference of flange insulation and outer circumference of adjacent straight pipe segments with cut sections of sheet insulation of the same thickness as pipe insulation.

4. Secure insulation to flanges and seal seams with manufacturer’s recommended adhesive. Cement to avoid openings in insulation that will allow passage of air to the pipe surface.

C. Apply insulation to fittings and elbows as follows:

1. Apply mitered sections of pipe insulation.

2. Secure insulation to flanges and seal seams with manufacturer’s recommended adhesive. Cement to avoid openings in insulation that will allow passage of air to the pipe surface.

Page 49: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 8 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

D. Apply insulation to valves and specialties as follows:

1. Apply preformed valve covers manufactured of the same material as pipe insulation and attached according to the manufacturer’s written instructions.

2. Apply cut segments of pipe and sheet insulation to valve body. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation. For check valves, fabricate removable sections of insulation arranged to allow access to strainer basket.

3. Apply insulation to flanges as specified for flange insulation application.

4. Secure insulation to valves and specialties and seal seams with manufacturer’s recommended adhesive. Cement to avoid openings in insulation that will allow passage of air to the pipe surface.

3.07 FIELD-APPLIED JACKET APPLICATION

A. Apply glass-cloth jacket, where indicated, directly over bare insulation or insulation with factory-applied jackets.

1. Apply jacket smooth and tight to surface with 2-inch overlap at seams and joints.

2. Embed glass cloth between two 0.062-inch thick coats of jacket manufacturer's recommended adhesive.

3. Completely encapsulate insulation with jacket, leaving no exposed raw insulation.

3.08 DUCT SYSTEM APPLICATIONS

A. Insulation materials and thicknesses are specified in schedules at the end of this Section.

B. Materials and thicknesses for systems listed below are specified in schedules at the end of this Section.

C. Insulate the following plenums and duct systems:

1. Indoor concealed supply-, return-, and outside-air ductwork.

D. Items Not Insulated: Unless otherwise indicated, do not apply insulation to the following systems, materials, and equipment:

1. Indoor exposed metal ducts, unless noted otherwise.

2. Metal ducts with duct liner, unless noted otherwise.

3. Factory-insulated flexible ducts.

4. Factory-insulated plenums, casings, terminal boxes, and filter boxes and sections, unless noted otherwise.

5. Flexible connectors.

6. Vibration-control devices.

7. Testing agency labels and stamps.

8. Nameplates and data plates.

9. Access panels and doors in air-distribution systems.

Page 50: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 9 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.09 INDOOR DUCT AND PLENUM APPLICATION SCHEDULE Service Material Thickness Number of

Layers R-Value

(Min. Installed)

Vapor Retarder Required

A. Round and rectangular, supply-air ducts, concealed

Mineral-fiber blanket

1-1/2” One 4.2 Yes

B. Round and rectangular, return-air ducts, concealed

Mineral-fiber blanket

1-1/2” One 4.2 Yes

C. Round and rectangular, outside-air ducts, concealed

Mineral-fiber blanket

2” One 4.2 Yes

D. Round and rectangular, supply-air ducts, exposed

None required, unless noted otherwise

E. Round and rectangular, return-air ducts, exposed

None required, unless noted otherwise

F. Round and rectangular, outside-air ducts, exposed

Mineral-fiber blanket

1-1/2” One 4.2 Yes

3.10 OUTDOOR DUCT AND PLENUM APPLICATION SCHEDULE Service Material Thickness Number of

Layers Field Applied

Jacket A. Round air ducts Closed-cell

phenolic foam

2” One Self-Adhesive Outdoor Jacket

B. Rectangular air ducts

Closed-cell phenolic foam

2” One Self-Adhesive Outdoor Jacket

3.11 PIPING SYSTEM APPLICATION SCHEDULE Service Material Thickness Field Applied

Jacket Finish

A. Refrigerant section, liquid and hot-gas piping (where required). Operating Temperature: 35 to 50 deg. F.

Flexible elastomeric

Copper Piping ALL

sizes: 1”

None None

Page 51: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 07 00 (15081) - HVAC INSULATION ▪ ▪ PAGE 10 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.12 EXTERIOR PIPE INSULATION APPLICATION SCHEDULE

A. This application schedule is for above ground insulation outside the building. Loose-fill insulation, for below ground piping, is specified in Division 33 piping distribution Sections.

Service Material Thickness Field Applied Jacket

Vapor Retarder Required

Finish

A. Above ground insulation outside the building Operating Temperature: 35 to 50 deg. F.

Flexible elastomeric

Copper Piping ALL

sizes: 1”

None Yes Two coats of manufacturer’s recommended

UV inhibitor

END OF SECTION

Page 52: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Pipe, Fittings and Joining Materials.

2. Protective Coating.

3. Piping Specialties.

4. Valves.

B. Related Sections:

1. Section 09 90 00 (09900) - Painting

2. Section 22 34 00 (15486) – Fuel-Fired, Domestic Water Heaters

3. Section 23 05 00 (15050) – Common Work Results for HVAC

4. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: For pipe hanger restraints.

5. Section 33 00 00 (02500) - Utility Services: For natural gas service piping, specialties, and accessories outside the building.

1.02 REFERENCES

A. American National Standards Institute (ANSI) Publications:

1. Z21.15/CGA 9.1 “Manually Operated Gas Valves for Appliances, Appliance Connector Valves and Hose End Valves”

2. Z21.21 “Automatic Valves for Gas Appliances (same as CSA 6.5)”

3. Z21.24/CGA 6.10 “Connectors for Gas Appliances”

4. Z21.41/CSA 6.9 “Quick Disconnect Devices for Use with Gas Fuel Appliances”

B. The American Society of Mechanical Engineers (ASME) Publications:

1. B1.20.1 "Pipe Threads, General Purpose, Inch"

2. B16.1 “Cast Iron Pipe Flanges and Flanged Fittings”

3. B16.3 “Malleable Iron Threaded Fittings”

4. B16.5 “Pipe Flanges and Flanged Fittings”

5. B16.9 “Factory-Made Wrought Buttwelding Fittings”

6. B16.11 “Forged Fittings, Socket-Welding and Threaded”

7. B16.24 “Cast Copper Alloy Pipe Flanges and Flanged Fittings: Classes 150, 300, 400, 600, 900, 1500 and 2500”

8. B16.33 “Manually Operated Metallic Gas Valves for Use in Gas Piping Systems up to 125 psi (Sizes NPS ½ through NPS 2)”

9. B16.38 “Large Metallic Valves For Gas Distribution (Manually Operated NPS-2 1/2 To 12,125 PSIG Max)”

10. B16.39 “Malleable Iron Threaded Pipe Unions”

Page 53: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless"

D. Manufacturers Standardization Society of the Valve and Fittings Industry. (MSS) Publications:

1. SP-70 “Gray Iron Gate Valves Flanged and Threaded Ends”

2. SP-78 “Socket Welding Reducer Inserts”

E. National Fire Protection Association (NFPA) Publications:

1. 54 “National Fuel Gas Code (ANSI Z223.1)”

F. The Society for Protective Coatings (SSPC) Publications:

1. Paint - Paint and Coating Standards and Specifications

1. Paint 16 “Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals”

G. Underwriter's Laboratories, Inc. (UL):

1. "Gas and Oil Equipment Directory"

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

1. Product Data for the following:

1. Corrugated, stainless-steel tubing systems. Include associated components.

2. Specialty valves. Include pressure rating, capacity, settings, and electrical connection data of selected models.

3. Pressure regulators. Include pressure rating, capacity, and settings of selected models.

1.04 QUALITY ASSURANCE

A. ANSI Standard: Comply with ANSI Z223.1, "National Fuel Gas Code."

B. IAS Standard: Provide components listed in IAS's "Directory of A. G. A. and C. G. A Certified Appliances and Accessories" if specified to be IAS listed.

C. UL Standard: Provide components listed in UL's "Gas and Oil Equipment Directory" if specified to be UL listed.

1.05 PROJECT CONDITIONS

A. Gas System Pressure: As indicated on Drawings

B. Design values of fuel gas supplied for these systems are as follows:

1. Nominal Heating Value: As indicated on Drawings.

2. Nominal Specific Gravity: As indicated on Drawings.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Corrugated, Stainless-Steel Tubing Systems:

Page 54: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Omega Flex, Inc. (800-355-1039)

2. Titeflex Corporation (800-765-2525)

3. Tru-Flex Metal Hose Corp. (800-255-6291)

4. B&K Industries, Inc. (800-782-2385)

5. Conbraco Industries, Inc.; Apollo Div. (704-841-6000)

2. Gas Valves, NPS 2 (DN 50) and Smaller:

1. Crane Valves (800-323-3679)

2. Milwaukee Valve Co., Inc. (262-432-2700)

3. Mueller Co.; Mueller Gas Products Div. (217-423-4471)

3. Plug Valves, NPS 2-1/2 (DN 65) and Larger:

1. Milliken Valve Co., Inc. (610-861-8803)

2. Mueller Co.; Mueller Gas Products Div. (217-423-4471)

4. Service Pressure Regulators:

1. American Meter Co. (215-830-1800)

2. Invensys Metering Systems (800-375-8875)

3. Fisher Controls, Division of Emerson. (800-558-5853)

2.02 PIPING MATERIALS

A. Refer to Part 3 "Piping Applications" Article for applications of pipe, tube, fitting, and joining materials.

2.03 PIPES, TUBES, FITTINGS, AND JOINING MATERIALS

A. Steel Pipe: ASTM A53; Type E or S; Grade B; Schedule 40; black.

1. Malleable-Iron Threaded Fittings: ASME B16.3, Class 150, standard pattern, with threaded ends according to ASME B1.20.1.

2. Unions: ASME B16.39, Class 150, malleable iron with brass-to-iron seat, ground joint, and threaded ends according to ASME B1.20.1.

3. Cast-Iron Flanges and Flanged Fittings: ASME B16.1, Class 125.

4. Steel Welding Fittings: ASME B16.9, wrought steel or ASME B16.11, forged steel.

5. Steel Threaded Fittings: ASME B16.11, forged steel with threaded ends according to ASME B1.20.1.

6. Joint Compound and Tape: Suitable for natural gas.

7. Steel Flanges and Flanged Fittings: ASME B16.5.

8. Gasket Material: Thickness, material, and type suitable for natural gas.

B. PE Pipe: ASTM D 2513, SDR 11.

1. PE Fittings: ASTM D 2683, socket-fusion type or ASTM D 3261, butt-fusion type with dimensions matching PE pipe.

2. PE Transition Fittings: Factory-fabricated fittings with PE pipe complying with ASTM D 2513, SDR 11; and steel pipe complying with ASTM A 53/A 53M, black steel, Schedule 40, Type E or S, Grade B.

Page 55: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3. Anodeless Service-Line Risers: Factory fabricated and leak tested.

a. Underground Portion: PE pipe complying with ASTM D 2513, SDR 11 inlet.

b. Casing: Steel pipe complying with ASTM A 53/A 53M, Schedule 40, black steel, Type E or S, Grade B with corrosion-protective coating covering.

c. Aboveground Portion: PE transition fitting.

d. Outlet shall be threaded or flanged or suitable for welded connection.

e. Tracer wire connection.

f. Ultraviolet shield.

g. Stake supports with factory finish to match steel pipe casing or carrier pipe.

4. Plastic Mechanical Couplings, NPS 1-1/2 and Smaller: Capable of joining PE pipe to PE pipe.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Lyall, R. W. & Company, Inc.

2) Mueller Co.; Gas Products Div.

3) Perfection Corporation; a subsidiary of American Meter Company.

b. PE body with molded-in, stainless-steel support ring.

c. Buna-nitrile seals.

d. Acetal collets.

e. Electro-zinc-plated steel stiffener.

5. Plastic Mechanical Couplings, NPS 2 and Larger: Capable of joining PE pipe to PE pipe, steel pipe to PE pipe, or steel pipe to steel pipe.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Lyall, R. W. & Company, Inc.

2) Mueller Co.; Gas Products Div.

3) Perfection Corporation; a subsidiary of American Meter Company.

b. Fiber-reinforced plastic body.

c. PE body tube.

d. Buna-nitrile seals.

e. Acetal collets.

f. Stainless-steel bolts, nuts, and washers.

6. Steel Mechanical Couplings: Capable of joining plain-end PE pipe to PE pipe, steel pipe to PE pipe, or steel pipe to steel pipe.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Dresser Piping Specialties; Division of Dresser, Inc.

2) Smith-Blair, Inc.

Page 56: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

b. Stainless-steel flanges and tube with epoxy finish.

c. Buna-nitrile seals.

d. Stainless-steel bolts, washers, and nuts.

e. Factory-installed anode for steel-body couplings installed underground.

C. Transition Fittings: Type, material, and end connections to match piping being joined.

D. Common Joining Materials: Refer to Section 23 05 00 - "Common Work Results for HVAC" for joining materials not in this Section.

2.04 PROTECTIVE COATING

A. Paint all exterior exposed gas piping with two coats of rust inhibitive paint.

2.05 PIPING SPECIALTIES

A. Flexible Connectors: ANSI Z21.24, copper alloy.

B. Quick-Disconnect Devices: ANSI Z21.41, convenience outlets and matching plug connector.

C. Valves, NPS 2 (DN 50) and Smaller: Threaded ends according to ASME B1.20.1 for pipe threads.

D. Valves, NPS 2-1/2 (DN 65) and Larger: Flanged ends according to ASME B16.5 for steel flanges and according to ASME B16.24 for copper and copper-alloy flanges.

E. Appliance Connector Valves: ANSI Z21.15 and IAS listed.

F. Gas Stops: Bronze body with AGA stamp, plug type with bronze plug and flat or square head, ball type with chrome-plated brass ball and lever handle, or butterfly valve with stainless-steel disc and fluorocarbon elastomer seal and lever handle; 2-psig (13.8-kPa) minimum pressure rating.

G. Gas Valves, NPS 2 (DN 50) and Smaller: ASME B16.33 and IAS-listed bronze body and 125-psig pressure rating.

H. Plug Valves, NPS 2-1/2 (DN 65) and Larger: ASME B16.38 and MSS SP-78 cast-iron, lubricated plug valves, with 125-psig pressure rating.

I. General-Duty Valves, NPS 2-1/2 (DN 65) and Larger: ASME B16.38, cast-iron body, suitable for fuel gas service, with "WOG" indicated on valve body, and 125-psig pressure rating.

1. Gate Valves: MSS SP-70, OS&Y type with solid wedge.

PART 3 EXECUTION 3.01 PREPARATION

A. Comply with NFPA 54 (ANSI Z223.1), "Prevention of Accidental Ignition" Paragraph.

3.02 SERVICE ENTRANCE PIPING

A. Extend fuel gas piping and connect to fuel gas distribution for service entrance to building.

1. Exterior fuel gas distribution system piping, service pressure regulator, and service meter will be provided by gas utility.

3.03 PIPING APPLICATIONS

A. Flanges, unions, transition, and special fittings with pressure ratings same as or higher than system pressure rating may be used in applications below, unless otherwise indicated.

B. Aboveground Natural Gas Piping (0.5 psig or less): Use the following:

Page 57: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

Note: Select one or more of the following to suit Project.

1. NPS 3/4 (DN 20) steel pipe, malleable-iron threaded fittings, and threaded joints.

2. NPS 3/4 and NPS 1 (DN 20 and DN 25): Steel pipe, malleable-iron threaded fittings, and threaded joints.

1. Option: Soft copper tube, copper fittings, and brazed joints may be used for runouts at individual appliances.

3. NPS 1-1/4 to NPS 2 (DN 32 to DN 50): Steel pipe, malleable-iron threaded fittings, and threaded joints.

4. NPS 2-1/2 to NPS 4 (DN 65 to DN 100): Steel pipe, steel welding fittings, and welded joints.

5. Larger Than NPS 4 (DN 100): Steel pipe, steel welding fittings, and welded joints.

C. Underground Natural Gas Piping (0.5 psig or less): Use the following:

1. Install underground, PE, natural-gas piping according to ASTM D 2774.

2. PE Piping Heat-Fusion Joints: Clean and dry joining surfaces by wiping with clean cloth or paper towels. Join according to ASTM D 2657.

a. Plain-End Pipe and Fittings: Use butt fusion.

b. Plain-End Pipe and Socket Fittings: Use socket fusion.

3. Underground natural-gas piping shall be one of the following:

a. PE pipe and fittings joined by heat fusion, or mechanical couplings; service-line risers with tracer wire terminated in an accessible location.

3.04 VALVE APPLICATIONS

A. Appliance Shutoff Valves for Pressure 0.5 to 2 psig: Gas stop or gas valve.

B. Piping Line Valves, NPS 2 (DN 50) and Smaller: Gas valve.

C. Piping Line Valves, NPS 2-1/2 (DN 65) and Larger: Plug valve or general-duty valve.

D. Valves at Service Meter, NPS 2 (DN 50) and Smaller: Gas valve.

E. Valves at Service Meter, NPS 2-1/2 (DN 65) and Larger: Plug valve.

3.05 PIPING INSTALLATION

A. Refer to Section 23 05 00 - "Common Work Results for HVAC" for basic piping installation requirements.

B. Concealed Locations: Except as specified below, install concealed gas piping in airtight conduit constructed of Schedule 40, seamless, black steel pipe with welded joints. Vent conduit to outside and terminate with screened vent cap.

1. Above-Ceiling Locations: Gas piping may be installed in accessible spaces, subject to approval of authorities having jurisdiction, whether or not such spaces are used as plenums. Do not locate valves above ceilings.

2. In Floors: Gas piping with welded joints and protective wrapping specified in "Protective Coating" Article in Part 2 may be installed in floors, subject to approval of authorities having jurisdiction. Surround piping cast in concrete slabs with minimum of 1-1/2 inches of concrete. Piping may not be in physical contact with other metallic structures such as reinforcing rods or electrically neutral conductors. Do not embed piping in concrete slabs containing quick-set additives or cinder aggregate.

Page 58: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3. In Floor Channels: Gas piping may be installed in floor channels, subject to approval of authorities having jurisdiction. Channels must have cover and be open to space above cover for ventilation.

4. In Partitions: Do not install concealed piping in solid partitions. Protect tubing from physical damage when installed inside partitions or hollow walls.

1. Exception: Tubing passing through partitions or walls.

5. In Walls: Gas piping with welded joints and protective wrapping specified in "Protective Coating" Article in Part 2 may be installed in masonry walls, subject to approval of authorities having jurisdiction.

6. Prohibited Locations: Do not install gas piping in or through circulating air ducts, clothes or trash chutes, chimneys or gas vents (flues), ventilating ducts, or dumbwaiter or elevator shafts.

1. Exception: Accessible above-ceiling space specified above.

C. Drips and Sediment Traps: Install drips at points where condensate may collect. Include outlets of service meters. Locate where readily accessible for cleaning and emptying. Do not install where condensate would be subject to freezing.

1. Construct drips and sediment traps using tee fitting with bottom outlet plugged or capped. Use minimum-length nipple of 3 pipe diameters, but not less than 3 inches (75 mm) long, and same size as connected pipe. Install with space between bottom of drip and floor for removal of plug or cap.

D. Conceal pipe installations in walls, pipe spaces, utility spaces, above ceilings, below grade or floors, and in floor channels, unless indicated to be exposed to view.

E. Install fuel gas piping at uniform grade of 0.1 percent slope upward toward risers.

F. Use eccentric reducer fittings to make reductions in pipe sizes. Install fittings with level side down.

G. Connect branch piping from top or side of horizontal piping.

H. Install unions in pipes NPS 2 (DN 50) and smaller, adjacent to each valve, at final connection to each piece of equipment, and elsewhere as indicated. Unions are not required on flanged devices.

I. Install corrugated, stainless-steel tubing system according to manufacturer's written instructions. Include striker plates to protect tubing from puncture where tubing is restrained and cannot move.

J. Install strainer on inlet of each line pressure regulator and automatic and electrically operated valve.

K. Install flanges on valves, specialties, and equipment having NPS 2-1/2 (DN 65) and larger connections.

L. Install vent piping for gas pressure regulators and gas trains, extend outside building, and vent to atmosphere. Terminate vents with turned-down, reducing-elbow fittings with corrosion-resistant insect screens in large end.

M. Install containment conduits for gas piping below slabs, within building, in gastight conduits extending minimum of 4 inches outside building, and vented to atmosphere. Terminate vents with turned-down, reducing-elbow fittings with corrosion-resistant insect screens in large end. Prepare and paint outside of conduits with coal-tar, epoxy-polyamide paint according to SSPC-Paint 16.

Page 59: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 8 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.06 JOINT CONSTRUCTION

A. Refer to Section 23 05 00 "Common Work Results for HVAC" for basic piping joint construction.

3.07 HANGER AND SUPPORT INSTALLATION

A. Refer to Section 23 05 29 - "Hangers and Supports for HVAC Piping and Equipment" for pipe hanger and support devices.

B. Install hangers for horizontal steel piping with the following maximum spacing and minimum rod sizes:

1. NPS 1 (DN 25) and Smaller: Maximum span, 96 inches; minimum rod size, 3/8 inch.

2. NPS 1-1/4 (DN 32): Maximum span, 108 inches; minimum rod size, 3/8 inch.

3. NPS 1-1/2 and NPS 2 (DN 40 and DN 50): Maximum span, 108 inches; minimum rod size, 3/8 inch.

4. NPS 2-1/2 to NPS 3-1/2 (DN 65 to DN 90): Maximum span, 10 feet; minimum rod size, 1/2 inch.

5. NPS 4 (DN 100) and Larger: Maximum span, 10 feet; minimum rod size, 5/8 inch.

3.08 CONNECTIONS

A. Drawings indicate general arrangement of fuel gas piping, fittings, and specialties.

B. Install piping adjacent to appliances to allow service and maintenance.

C. Connect piping to appliances using gas with shutoff valves and unions. Install valve upstream from and within 72 inches of each appliance. Install union downstream from valve.

D. Sediment Traps: Install tee fitting with capped nipple in bottom to form drip, as close as practical to inlet of each appliance using gas.

3.09 PAINTING

A. Use materials and procedures in Section 09 90 00 "Painting”

B. Paint exterior service meters, pressure regulators, specialty valves, and piping.

1. Color: Gray.

3.10 FIELD QUALITY CONTROL

A. Inspect, test, and purge piping according to NFPA 54 (ANSI Z223.1), Part 4 "Inspection, Testing, and Purging," and requirements of authorities having jurisdiction.

B. Repair leaks and defects with new materials and retest system until satisfactory results are obtained.

C. Report test results promptly and in writing to Owner’s Representative and authorities having jurisdiction.

D. Verify capacities and pressure ratings of service meters, pressure regulators, valves, and specialties.

E. Verify correct pressure settings for pressure regulators.

F. Verify that specified piping tests are complete.

Page 60: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 11 23 (15194) - FACILITY NATURAL-GAS PIPING ▪ ▪ PAGE 9 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.11 ADJUSTING

A. Adjust controls and safety devices. Replace damaged and malfunctioning controls and safety devices.

END OF SECTION

Page 61: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 23 00 (15530) - REFRIGERANT PIPING ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 23 00 (15530) - REFRIGERANT PIPING

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Tubes.

2. Fittings.

3. Joining Materials.

4. Specialties.

B. Related Sections:

1. Section 07 92 00 (07920) - Joint Sealants

2. Section 07 84 00 (07840) - Firestopping: Firestopping materials and requirements for penetrations through fire and smoke barriers.

3. Section 23 05 00 (15050) – Common Work Results for HVAC

4. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: for pipe hanger restraints.

5. Section 23 05 53 (15075) – Identification for HVAC Piping and Equipment

6. Section 23 07 00 (15083) – HVAC Insulation

1.02 REFERENCES

1. ASHRAE 15, "Safety Code for Mechanical Refrigeration."

B. The American Society of Mechanical Engineers (ASME) Publications:

1. “Boiler and Pressure Vessel Code”

2. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”

3. B31.5 “Refrigeration Piping and Heat Transfer Components”

C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. B88 “Standard Specification for Seamless Copper Water Tube”

2. B280 “Standard Specification for Seamless Copper Tube for Air Conditioning and Refrigeration Field Service”

D. American Welding Society (AWS) Publications:

1. A5.8 "Specification for Filler Metals For Brazing And Braze Welding"

E. Manufacturers Standardization Society of the Valve and Fittings Industry. (MSS) Publications:

1. SP-69 “ANSI/MSS Edition Pipe Hangers and Supports - Selection and Application”

F. Underwriter's Laboratories, Inc. (UL) Standards:

1. 207 “Standard for Refrigerant-Containing Components and Accessories, Nonelectrical”

2. 429 “Standard for Electrically Operated Valves”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

Page 62: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 23 00 (15530) - REFRIGERANT PIPING ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data for each valve type and refrigerant piping specialty specified.

2. Refrigerant piping indicated is schematic only. Contractor shall size and design the piping configuration and install the piping, including oil traps, double risers, specialties, and pipe and tube sizes, to ensure proper operation and conformance with warranties of connected equipment.

3. Qualification data for firms and persons specified in the "Quality Assurance" Article to demonstrate their capabilities and experience.

4. Maintenance data for refrigerant valves and piping specialties to include in the operation and maintenance manual specified in Division 01 Sections.

1.04 QUALITY ASSURANCE

A. ASME Compliance: Qualify brazing and welding processes and operators according to ASME Boiler and Pressure Vessel Code, Section IX, "Welding and Brazing Qualifications."

B. Regulatory Requirements: Comply with provisions of the following codes:

1. ASME B31.5, "Refrigeration Piping."

2. ASHRAE 15, "Safety Code for Mechanical Refrigeration."

C. UL Standard: Provide products complying with UL 207, "Refrigerant-Containing Components and Accessories, Non-electrical"; or UL 429, "Electrically Operated Valves."

D. Listing and Labeling: Provide products specified in this Section that are UL listed and labeled.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Refrigerant Valves and Specialties:

a. Henry Pratt Company, Subsidiary of Mueller Water Products, Inc. (877-436-7966)

b. Parker-Hannifin Corporation; Refrigeration & Air Conditioning Division (800-272-7537)

c. Sporlan Valve Company (314-647-2775)

2.02 TUBES

A. Use pre-charged tubing where possible.

B. Soft Copper Tube: ASTM B280, Type ACR, annealed temper.

2.03 TUBE FITTINGS

A. Copper Fittings: ASME B16.22, wrought-copper streamlined pattern.

2.04 JOINING MATERIALS

A. Brazing Filler Metals: AWS A5.8, Classification BAg-1 (Silver).

2.05 REFRIGERANT PIPING SPECIALTIES

A. Moisture/Liquid Indicators: 500-psig operating pressure, 200 deg F operating temperature; forged-brass body, with replaceable, polished, optical viewing window with color-coded moisture indicator, and solder-end connections.

Page 63: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 23 00 (15530) - REFRIGERANT PIPING ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Permanent Filter-Dryer: 350-psig maximum operating pressure, 225 deg F maximum operating temperature; steel shell, and wrought-copper fittings for solder-end connections; molded-felt core surrounded by desiccant.

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine roughing-in for compliance with requirements for installation tolerances and other conditions affecting performance of refrigerant piping. Do not proceed with installation until unsatisfactory conditions have been corrected.

3.02 APPLICATIONS

A. Above ground, within Building: Type ACR drawn-copper tubing.

B. Below ground for 2-Inch NPS (DN50) and Smaller: Type L (Type B) annealed-copper tubing installed in schedule 40 PVC sleeve.

3.03 INSTALLATION

A. Install refrigerant piping according to ASHRAE 15.

B. Basic piping installation requirements are specified in Section 23 05 00 (15050) - "Common Work Results For HVAC."

C. Install piping in short and direct arrangement, with minimum number of joints, elbows, and fittings.

D. Arrange piping to allow normal inspection and service of compressor and other equipment. Install valves and specialties in accessible locations to allow for service and inspection.

E. Install piping with adequate clearance between pipe and adjacent walls and hangers, or between pipes for insulation installation. Use sleeves through floors, walls, or ceilings, sized to permit installation of full-thickness insulation. Maximum fill: 40%

F. Below ground, install copper tubing in schedule 40 PVC conduit. Vent conduit outdoors.

G. Insulate suction lines.

1. Do not install insulation until system testing has been completed and all leaks have been eliminated.

H. Install branch lines to parallel compressors of equal length, and pipe identically and symmetrically.

I. Install copper tubing in rigid or flexible conduit in locations where copper tubing will be exposed to mechanical injury.

J. Slope refrigerant piping as follows:

1. Install horizontal suction lines with a uniform slope of 0.4 percent downward to compressor.

2. Install traps and double risers where indicated and where required to entrain oil in vertical runs.

3. Liquid lines may be installed level.

K. Use fittings for changes in direction and branch connections.

L. Install exposed piping at right angles or parallel to building walls. Diagonal runs are not permitted, unless expressly indicated.

M. Reduce pipe sizes using eccentric reducer fittings installed with level side down.

Page 64: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 23 00 (15530) - REFRIGERANT PIPING ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

N. Provide bypass around moisture-liquid indicators in lines larger than 2-inch NPS (DN50).

O. Install unions to allow removal of solenoid valves, pressure-regulating valves, expansion valves, and at connections to compressors and evaporators.

P. Install refrigerant valves according to manufacturer's written instructions.

Q. When brazing, remove solenoid-valve coils; remove sight glasses; and remove stems, seats, and packing of valves, and accessible internal parts of refrigerant specialties. Do not apply heat near bulb of expansion valve.

R. Electrical wiring for solenoid valves is specified in Division 16 Sections. Coordinate electrical requirements and connections.

S. Charge and purge systems, after testing, dispose of refrigerant following ASHRAE 15 procedures.

3.04 HANGERS AND SUPPORTS

A. General: Hangers, supports, and anchors are specified in Section 23 05 29 - "Hangers and Supports for HVAC Piping and Equipment." Provide according to ASME B31.5 and MSS SP-69.

B. Install hangers for copper tubing with the following maximum spacing and minimum rod sizes. Tube sizes are nominal or standard tube sizes as expressed in ASTM B88.

1. 1/2 Inch: Maximum span, 60 inches; minimum rod size, 1/4 inch.

2. 5/8 Inch: Maximum span, 60 inches; minimum rod size, 1/4 inch.

3. 1 Inch: Maximum span, 60 inches; minimum rod size, 1/4 inch.

4. 1-1/4 Inches: Maximum span, 72 inches; minimum rod size, 1/4 inch.

5. 1-1/2 Inches: Maximum span, 96 inches; minimum rod size, 3/8 inch.

3.05 PIPE INSULATION

A. Piping insulation is specified in Section 23 07 00 “HVAC Insulation”.

3.06 SPECIALTIES APPLICATION AND INSTALLATION

A. Install permanent filter dryers in low-temperature systems using hermetic compressors, and before each solenoid valve.

3.07 PIPE JOINT CONSTRUCTION

A. Basic pipe and tube joint construction is specified in Section 23 05 00 - "Common Work Results for HVAC."

B. Fill pipe and fittings with an inert gas (nitrogen or carbon dioxide) during brazing to prevent formation of scale.

3.08 VALVE INSTALLATIONS

A. Install refrigerant valves according to manufacturer's written instructions.

3.09 CONNECTIONS

A. Electrical: Conform to applicable requirements of Division 26 Sections for electrical connections.

3.10 FIELD QUALITY CONTROL

A. Inspect and test refrigerant piping according to ASME B31.5, Chapter VI.

Page 65: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 23 00 (15530) - REFRIGERANT PIPING ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Pressure test with nitrogen to 200 psig. Perform final tests at 27-psig vacuum and 200 psig using halide torch or electronic leak detector. Test to no leakage.

B. Test and adjust controls and safeties. Replace damaged or malfunctioning controls and equipment.

C. Repair leaks using new materials; retest.

3.11 ADJUSTING

A. Adjust thermostatic expansion valve to obtain proper evaporator superheat requirements.

3.12 CLEANING

A. Before installation of copper tubing other than Type ACR, clean tubing and fittings with trichloroethylene.

3.13 COMMISSIONING

A. Charge system using the following procedures:

1. Install core in filter dryer after leak test, but before evacuation.

2. Evacuate refrigerant system with vacuum pump until temperature of 35 deg is indicated on vacuum dehydration indicator.

3. During evacuation, apply heat to pockets, elbows, and low spots in piping.

4. Maintain vacuum on system for minimum of 5 hours after closing valve between vacuum pump and system.

5. Break vacuum with refrigerant gas, allowing pressure to build up to 2 psig.

6. Complete charging of system, using new filter-dryer core in charging line. Provide full-operating charge.

END OF SECTION

Page 66: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 31 13 (15815) - METAL DUCTS

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Sheet Metal Materials.

2. Duct Liner.

3. Sealant Materials.

4. Hangers and Supports.

5. Duct Fabrication.

B. Related Sections:

1. Section 07 84 00 (07840) - Firestopping: For fire-resistant sealants for use around duct penetrations and fire-damper installations in fire-rated floors, partitions, and walls.

2. Section 08 31 00 (08310) - Access Doors: For wall- and ceiling-mounted access doors for access to concealed ducts.

3. Section 23 05 93 (15950) - Testing, Adjusting, and Balancing: For air balancing and final adjusting of manual-volume dampers.

4. Section 23 07 00 (15081) – HVAC Insulation: For duct insulation.

5. Section 23 33 00 (15820) – Air Duct Accessories: For dampers, sound-control devices, duct-mounted access doors and panels, turning vanes, and flexible ducts.

6. Section 23 37 00 (15850) - Air Outlets and Inlets

1.02 REFERENCES

A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. A36 “Standard Specification for Carbon Structural Steel”

2. A336 “Standard Specification for Alloy Steel Forgings for Pressure and High-Temperature Parts”

3. A480 “Standard Specification for General Requirements for Flat-Rolled Stainless and Heat-Resisting Steel Plate, Sheet, and Strip”

4. A653 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process”

5. C168 “Standard Terminology Relating to Thermal Insulation”

6. C411 “Standard Test Method for Hot-Surface Performance of High-Temperature Thermal Insulation”

7. C916 “Standard Specification for Adhesives for Duct Thermal Insulation”

8. C920 “Standard Specification for Elastomeric Joint Sealants”

9. C1071 “Standard Specification for Fibrous Glass Duct Lining Insulation (Thermal and Sound Absorbing Material)”

B. American Welding Society (AWS) Publications:

1. D1.1 "Structural Welding Code - Steel"

Page 67: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2. D1.2 "Structural Welding Code--Aluminum"

3. D9.1 “Sheet Metal Welding Code“

C. National Fire Protection Association (NFPA) Publications:

1. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

2. 90B “Standard for the Installation of Warm Air Heating and Air-Conditioning Systems”

D. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) Publications:

1. “HVAC Air Duct Leakage Test Manual”

2. “HVAC Duct Construction Standards—Metal and Flexible”

1.03 DEFINITIONS

A. Thermal Conductivity and Apparent Thermal Conductivity (k-Value): As defined in ASTM C168.

1.04 SYSTEM DESCRIPTION

A. Duct system design, as indicated, has been used to select and size air-moving and -distribution equipment and other components of air system. Changes to layout or configuration of duct system must be specifically approved in writing by the Engineer of Record. Accompany requests for layout modifications with calculations showing that proposed layout will provide original design results without increasing system total pressure.

1.05 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data:

a. For duct liner and sealing materials.

2. Welding Certificates: Copies of certificates indicating welding procedures and personnel comply with requirements in "Quality Assurance" Article.

3. Field Test Reports: Indicate and interpret test results for compliance with performance requirements.

4. Record Drawings: Indicate actual routing, fitting details, reinforcement, support, and installed accessories and devices.

1.06 QUALITY ASSURANCE

A. Welding Standards: Qualify welding procedures and welding personnel to perform welding processes for this Project according to AWS D1.1, "Structural Welding Code--Steel" for hangers and supports; AWS D1.2, "Structural Welding Code--Aluminum," for aluminum supporting members; and AWS D9.1, "Sheet Metal Welding Code," for duct joint and seam welding.

B. Comply with NFPA 90A, "Installation of Air Conditioning and Ventilating Systems," unless otherwise indicated.

C. Comply with NFPA 90B, "Installation of Warm Air Heating and Air Conditioning Systems," unless otherwise indicated.

Page 68: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

PART 2 PRODUCTS 2.01 SHEET METAL MATERIALS

A. Galvanized, Sheet Steel: Lock-forming quality; ASTM A653, G90 coating designation; mill-phosphatized finish for surfaces of ducts exposed to view.

B. Aluminum Sheets: Comply with ASTM B 209 Alloy 3003, H14 temper; with mill finish for concealed ducts, and standard, one-side bright finish for duct surfaces exposed to view.

C. Reinforcement Shapes and Plates: Galvanized steel reinforcement where installed on galvanized, sheet metal ducts; compatible materials for aluminum and stainless-steel ducts.

D. Tie Rods: Galvanized steel, 1/4-inch minimum diameter for 36-inch length or less; 3/8-inch minimum diameter for lengths longer than 36 inches.

2.02 DUCT LINER

A. Flexible Elastomeric Duct Liner: Preformed, cellular, closed-cell, sheet materials complying with ASTM C 534, Type II, Grade 1; and with NFPA 90A or NFPA 90B.

1. Manufacturer: Armacell, AP Armaflex or approved equivalent.

2. Surface-Burning Characteristics: Maximum flame-spread index of 25 and maximum smoke-developed index of 50 when tested according to UL 723; certified by an NRTL.

3. Liner Adhesive: As recommended by insulation manufacturer and complying with NFPA 90A or NFPA 90B.

4. Thickness: 1 inch.

5. Thermal conductivity (k-value): 0.25 at 75 deg. F mean temperature.

2.03 SEALANT MATERIALS

A. Joint and Seam Sealants, General: The term "sealant" is not limited to materials of adhesive or mastic nature but includes tapes and combinations of open-weave fabric strips and mastics.

1. Joint and Seam Tape: 2 inches wide; glass-fiber fabric reinforced.

2. Joint and Seam Sealant: One-part, nonsag, solvent-release-curing, polymerized butyl sealant, formulated with a minimum of 75 percent solids.

3. Flanged Joint Mastics: One-part, acid-curing, silicone, elastomeric joint sealants, complying with ASTM C920, Type S, Grade NS, Class 25, Use O.

2.04 HANGERS AND SUPPORTS

A. Building Attachments: Concrete inserts, powder-actuated fasteners, or structural-steel fasteners appropriate for building materials.

1. Use powder-actuated concrete fasteners for standard-weight aggregate concretes or for slabs more than 4 inches thick.

2. Exception: Do not use powder-actuated concrete fasteners for lightweight-aggregate concretes or for slabs less than 4 inches thick.

B. Hanger Materials: Galvanized, sheet steel or round, threaded steel rod.

1. Hangers Installed in Corrosive Atmospheres: Electrogalvanized, all-thread rod or galvanized rods with threads painted after installation.

2. Straps and Rod Sizes: Comply with SMACNA's "HVAC Duct Construction Standards--Metal and Flexible" for sheet steel width and thickness and for steel rod diameters.

Page 69: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

C. Duct Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws; compatible with duct materials.

D. Trapeze and Riser Supports: Steel shapes complying with ASTM A36/A36M.

1. Supports for Galvanized-Steel Ducts: Galvanized steel shapes and plates.

2. Supports for Aluminum Ducts: Aluminum support materials.

2.05 FABRICATION - RECTANGULAR DUCT

A. General: Fabricate ducts, elbows, transitions, offsets, branch connections, and other construction with galvanized, sheet steel (or aluminum as indicated), according to SMACNA's "HVAC Duct Construction Standards--Metal and Flexible." Comply with requirements for metal thickness, reinforcing types and intervals, tie-rod applications, and joint types and intervals.

1. Lengths: Fabricate rectangular ducts in lengths appropriate to reinforcement and rigidity class required for pressure classification.

2. Materials: Free from visual imperfections such as pitting, seam marks, roller marks, stains, and discolorations.

2.06 SHOP APPLICATION OF LINER IN RECTANGULAR DUCTS

A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 7-11, "Flexible Duct Liner Installation."

1. Install in strict accordance with manufacturer's instructions.

2. Adhere a single layer of indicated thickness of duct liner with at least 90 percent adhesive coverage at liner contact surface area. Attaining indicated thickness with multiple layers of duct liner is prohibited.

3. Butt transverse joints without gaps, and coat joint with adhesive.

4. Fold and compress liner in corners of rectangular ducts or cut and fit to ensure butted-edge overlapping.

5. Do not apply liner in rectangular ducts with longitudinal joints, except at corners of ducts, unless duct size and dimensions of standard liner make longitudinal joints necessary.

B. Apply adhesive to liner facing in direction of airflow not receiving metal nosing.

C. Butt transverse joints without gaps and coat joint with adhesive.

D. Fold and compress liner in corners of rectangular ducts or cut and fit to ensure butted-edge overlapping.

E. Do not apply liners in rectangular ducts with longitudinal joints, except at corners of ducts, unless duct size and standard liner product dimensions make longitudinal joints necessary.

F. Secure liner with mechanical fasteners 4 inches from corners and at intervals not exceeding 12 inches transversely around perimeter; at 3 inches from transverse joints and at intervals not exceeding 18 inches longitudinally.

G. Secure transversely oriented liner edges facing the airstream with metal nosings that have either channel or "Z" profile or are integrally formed from duct wall. Fabricate edge facings at the following locations:

1. Fan discharge.

2. Intervals of lined duct preceding unlined duct.

Page 70: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

H. Terminate liner with duct buildouts installed in ducts to attach dampers, turning vane assemblies, and other devices. Fabricated buildouts (metal hat sections) or other buildout means are optional; when used, secure buildouts to duct wall with bolts, screws, rivets, or welds. Terminate liner at fire dampers at connection to fire-damper sleeve.

2.07 FABRICATION - ROUND DUCT

A. Round Ducts: Fabricate supply ducts of galvanized steel (or aluminum as indicated) according to SMACNA's "HVAC Duct Construction Standards--Metal and Flexible." All shall be spiral seam construction.

2.08 FABRICATION - ROUND SUPPLY AND EXHAUST FITTING

A. 90-Degree Tees and Laterals and Conical Tees: Fabricate to comply with SMACNA's "HVAC Duct Construction Standards--Metal and Flexible," with metal thicknesses specified for longitudinal seam straight duct.

B. Diverging-Flow Fittings: Fabricate with a reduced entrance to branch taps with no excess material projecting from body onto branch tap entrance.

C. Elbows: Fabricate in die-formed, gored, pleated, or mitered construction. Fabricate bend radius of die-formed, gored, and pleated elbows one and one-half times elbow diameter. Unless elbow construction type is indicated, fabricate elbows as follows:

1. Mitered-Elbow Radius and Number of Pieces: Welded construction complying with SMACNA's "HVAC Duct Construction Standards--Metal and Flexible," unless otherwise indicated.

2. 90-Degree, Two-Piece, Mitered Elbows: Use only for supply systems, or exhaust systems for material-handling classes A and B; and only where space restrictions do not permit using 1.5 bend radius elbows. Fabricate with single-thickness turning vanes.

3. Round Elbows, 8 Inches and Smaller: Fabricate die-formed elbows for 45- and 90-degree elbows and pleated elbows for 30, 45, 60, and 90 degrees only. Fabricate nonstandard bend-angle configuration or nonstandard diameter elbows with gored construction.

4. Round Elbows, 9 through 14 Inches: Fabricate gored or pleated elbows for 30, 45, 60, and 90 degrees, unless space restrictions require a mitered elbow. Fabricate nonstandard bend-angle configuration or nonstandard diameter elbows with gored construction.

5. Round Elbows, Larger Than 14 Inches: Fabricate gored elbows, unless space restrictions require a mitered elbow.

6. Die-Formed Elbows for Sizes through 8 Inches and All Pressures: 0.040 inch thick with two-piece welded construction.

PART 3 EXECUTION 3.01 DUCT INSTALLATION - GENERAL

A. Duct installation requirements are specified in other Division 23 Sections. Drawings indicate general arrangement of ducts, fittings, and accessories.

B. Construct and install each duct system for the specific duct pressure classification indicated.

C. Install round ducts in lengths not less than 12 feet, unless interrupted by fittings.

D. Install ducts with fewest possible joints.

E. Install fabricated fittings for changes in directions, changes in size and shape, and connections.

Page 71: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

F. Install couplings tight to duct wall surface with a minimum of projections into duct.

G. Install ducts, unless otherwise indicated, vertically and horizontally, parallel and perpendicular to building lines; avoid diagonal runs.

H. Install ducts close to walls, overhead construction, columns, and other structural and permanent enclosure elements of building.

I. Install ducts with a clearance of 1 inch, plus allowance for insulation thickness.

J. Conceal ducts from view in finished spaces. Do not encase horizontal runs in solid partitions, unless specifically indicated.

K. Coordinate layout with suspended ceiling, fire- and smoke-control dampers, lighting layouts, and similar finished work.

L. Electrical Equipment Spaces: Route ductwork to avoid passing through transformer vaults, electrical equipment spaces and enclosures, and through elevator equipment rooms.

M. Non-Fire-Rated Partition Penetrations: Where ducts pass through interior partitions and exterior walls, and are exposed to view, conceal space between construction opening and duct or duct insulation with sheet metal flanges of same metal thickness as duct. Overlap opening on four sides by at least 1-1/2 inches.

N. Fire-Rated Partition Penetrations: Where ducts pass through interior partitions and exterior walls, install appropriately rated fire damper, sleeve, and firestopping sealant. Fire and smoke dampers are specified in Section 23 33 00 "Air Duct Accessories." Firestopping materials and installation methods are specified in Section 07 84 00 "Firestopping."

3.02 SEAM AND JOINT SEALING

A. General: Seal duct seams, seal Class A as described in SMACNA's "HVAC Duct Construction Standards--Metal and Flexible."

B. Seal externally insulated ducts before insulation installation.

C. Materials: 3M Brand No. 800.

3.03 HANGING AND SUPPORTING

A. Install rigid round, rectangular, and flat-oval metal duct with support systems indicated in SMACNA's "HVAC Duct Construction Standards--Metal and Flexible."

B. Support horizontal ducts within 24 inches of each elbow and within 48 inches of each branch intersection.

C. Support vertical ducts at a maximum interval of 16 feet and at each floor.

D. Install upper attachments to structures with an allowable load not exceeding one-fourth of failure (proof-test) load.

E. Install concrete inserts before placing concrete.

3.04 CONNECTIONS

A. Connect equipment with flexible connectors according to Section 23 33 00 (15820) "Duct Accessories."

B. For branch, outlet and inlet, and terminal unit connections, comply with SMACNA's "HVAC Duct Construction Standards--Metal and Flexible."

3.05 ADJUSTING

A. Refer to Section 23 05 93 "Testing, Adjusting, and Balancing for HVAC" for detailed procedures.

Page 72: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 31 13 (15815) - METAL DUCTS ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.06 CLEANING

A. After completing system installation, including outlet fittings and devices, inspect the system. Vacuum interior as well as exterior of ducts before final acceptance to remove dust and debris.

END OF SECTION

Page 73: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES

PART 1 GENERAL 1.01 SUMMARY

A. Section includes:

1. Manual-Volume Dampers

2. Fire Dampers

3. Turning Vanes

4. Duct-Mounted Access Doors

5. Flexible Connectors

6. Flexible Ducts

7. Accessories

B. Related Sections:

1. Section 01 81 13 - Sustainable Design Requirements

2. Section 08 31 00 (08310) - Access Doors and Panels: For wall- and ceiling-mounted access doors and panels.

3. Section 23 05 53 - Identification for HVAC Piping and Equipment.

4. Section 23 05 93 - Testing, Adjusting, and Balancing for HVAC.

5. Section 23 37 00 (15850) - Air Outlets and Inlets.

6. Section 28 31 00 (13850) - Fire Alarm and Detection Systems: For duct-mounted fire and smoke detectors.

1.02 REFERENCES

A. National Fire Protection Association (NFPA) Publications:

1. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

2. 90B “Standard for the Installation of Warm Air Heating and Air-Conditioning Systems”

B. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) Publications:

1. “Fire Damper and Heat Stop Guide for Air Handling Systems”

2. “HVAC Duct Construction Standards—Metal and Flexible”

C. Underwriter's Laboratories, Inc. (UL) Standards:

1. 181 “Standard for Factory-Made Air Ducts and Air Connectors”

2. 181B “Closure Systems for Use With Flexible Air Ducts and Air Connectors”

3. 555 “Fire Dampers”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: For the following:

Page 74: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

a. Manual-volume dampers.

b. Fire dampers.

c. Duct-mounted access doors.

d. Flexible ducts.

2. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loadings, required clearances, method of field assembly, components, location, and size of each field connection. Detail the following:

a. Special fittings and manual- and automatic-volume-damper installations.

b. Fire damper installations, including sleeves and duct-mounted access doors and panels.

3. Product Certificates: Submit certified test data on dynamic insertion loss; self-noise power levels; and airflow performance data, static-pressure loss, dimensions, and weights.

1.04 QUALITY ASSURANCE

A. NFPA Compliance: Comply with the following NFPA standards:

1. NFPA 90A, "Installation of Air Conditioning and Ventilating Systems."

2. NFPA 90B, "Installation of Warm Air Heating and Air Conditioning Systems."

B. Sheet Metal and Air Conditioning Contractors National Association, Inc. manuals (SMACNA) except where details or notes on drawings indicate otherwise.

1. HVAC Duct Construction Standards—Metal and Flexible.

2. Fire Damper and Heat Stop Guide for Air Handling Systems.

C. Underwriters Laboratories (UL) Standard for Safety UL 181, UL 555.

1.05 EXTRA MATERIALS

A. Furnish extra materials described in Section 01 78 43 (01790) “Spare Parts and Materials” that match products installed, are packaged with protective covering for storage, and are identified with labels describing contents.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Manual Volume Dampers.

a. Ruskin Company (816-761-7476)

b. Air Balance, Division of Mestek (419-865-5000)

c. Prefco (Perfect Air Control, Inc.) (800-437-6653)

2. Fire Dampers.

a. Ruskin Company (816-761-7476)

b. Air Balance, Division of Mestek (419-865-5000)

c. Prefco (Perfect Air Control, Inc.) (800-437-6653)

3. Flexible Connectors.

Page 75: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

a. Ventfabrics, Inc. (800-621-1207)

b. Ward Industries, Inc. (630-595-7320)

c. Vent Products Co. (800-368-8368)

4. Flexible Ducts

a. Clevaflex. Ltd. (216-941-6505)

b. Approved Substitution

2.02 MANUAL-VOLUME DAMPERS

A. General: Factory fabricated with required hardware and accessories. Stiffen damper blades for stability. Include locking device to hold single-blade dampers in a fixed position without vibration. Close duct penetrations for damper components to seal duct consistent with pressure class.

B. Standard Volume Dampers: Multiple- or single-blade, parallel- or opposed-blade design as indicated, standard leakage rating, with linkage outside airstream, and suitable for horizontal or vertical applications.

1. Steel Frames: Hat-shaped, galvanized, sheet steel channels, minimum of 0.064 inch thick, with mitered and welded corners; frames with flanges where indicated for attaching to walls; and flangeless frames where indicated for installing in ducts.

2. Roll-Formed Steel Blades: 0.064-inch- thick, galvanized, sheet steel.

3. Blade Axles: Nonferrous.

4. Tie Bars and Brackets: Galvanized steel.

C. Damper Hardware: Zinc-plated, die-cast core with dial and handle made of 3/32-inch thick zinc-plated steel, and a 3/4-inch hexagon locking nut. Include center hole to suit damper operating-rod size. Include elevated platform for insulated duct mounting.

2.03 FIRE DAMPERS

A. General: Labeled to UL 555.

B. Fire Rating: One and one-half hour unless noted otherwise.

C. Frame: SMACNA Type B with blades out of airstream; fabricated with roll-formed, 0.034-inch- thick galvanized steel; with mitered and interlocking corners.

D. Mounting Sleeve: Factory- or field-installed galvanized, sheet steel.

1. Minimum Thickness: 0.052 inch or 0.138 inch thick and length to suit application.

2. Exceptions: Omit sleeve where damper frame width permits direct attachment of perimeter mounting angles on each side of wall or floor, and thickness of damper frame complies with sleeve requirements.

E. Mounting Orientation: Vertical or horizontal as indicated.

F. Blades: Roll-formed, interlocking, 0.034 inch thick, galvanized, sheet steel. In place of interlocking blades, use full-length, 0.034 inch thick, galvanized steel blade connectors.

G. Horizontal Dampers: Include a blade lock and stainless-steel negator closure spring.

H. Fusible Link: Replaceable, 165 F rated as indicated.

I. Provide access door in duct adjacent to each fire damper.

Page 76: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2.04 TURNING VANES

A. Fabricate to comply with SMACNA's "HVAC Duct Construction Standards—Metal and Flexible."

B. Manufactured Turning Vanes: Fabricate of 1-1/2 inch wide, curved blades set 3/4 inch o.c.; support with bars perpendicular to blades set 2 inches o.c.; and set into side strips suitable for mounting in ducts.

2.05 DUCT-MOUNTED ACCESS DOORS

A. General: Fabricate doors airtight and suitable for duct pressure class.

B. Frame: Galvanized, sheet steel, with bend-over tabs and foam gaskets.

C. Door: Double-wall, galvanized, sheet metal construction with insulation fill and thickness, and number of hinges and locks as indicated for duct pressure class. Include vision panel where indicated. Include 1-by-1-inch butt or piano hinge and cam latches.

D. Seal around frame attachment to duct and door to frame with neoprene or foam rubber.

E. Insulation: 1-inch thick, fibrous-glass.

2.06 FLEXIBLE CONNECTORS

A. General: Flame-retarded or noncombustible fabrics, coatings, and adhesives complying with UL 181, Class 1.

B. Standard Metal-Edged Connectors: Factory fabricated with a strip of fabric 3-1/2 inches wide attached to two strips of 2-3/4 inch wide, 0.028 inch thick, galvanized, sheet steel. Select metal compatible with connected ducts.

C. Transverse Metal-Edged Connectors: Factory fabricated with a strip of fabric 3-1/2 inches wide attached to two strips of 4-3/8 inch wide, 0.028 inch thick, galvanized, sheet steel Select metal compatible with connected ducts.

D. Conventional, Indoor System Flexible Connector Fabric: Glass fabric double coated with polychloroprene.

1. Minimum Weight: 26 oz./sq. yd.

2. Tensile Strength: 480 lbf/inch in the warp, and 360 lbf/inch in the filling.

3. Minimum Movement: 2 inches.

E. Conventional, Outdoor System Flexible Connector Fabric: Glass fabric double coated with a synthetic-rubber, weatherproof coating resistant to the sun's ultraviolet rays and ozone environment.

1. Minimum Weight: 26 oz./sq. yd.

2. Tensile Strength: 530 lbf/inch in the warp, and 440 lbf/inch in the filling.

3. Minimum Movement: 2 inches.

F. High-Corrosive-Environment System Flexible Connectors: Glass fabric coated with a chemical-resistant coating (For use in pool area equipment room).

1. Minimum Weight: 14 oz./sq. yd.

2. Tensile Strength: 450 lbf/inch in the warp, and 340 lbf/inch in the filling.

3. Minimum Movement: 2 inches.

Page 77: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2.07 FLEXIBLE DUCTS

A. General: Comply with UL 181, Class 1.

B. Flexible Ducts, Uninsulated: Corrugated aluminum. For use on dryer vents only.

C. Flexible Ducts, Insulated: Factory-fabricated, insulated, round duct, with an outer jacket enclosing 1-1/2-inch thick, glass-fiber insulation around a continuous inner liner.

1. Reinforcement: Steel-wire helix encapsulated in inner liner.

2. Outer Jacket: Glass-reinforced, silver Mylar with a continuous hanging tab, integral fibrous-glass tape, and nylon hanging cord.

3. Inner Liner: Polyethylene film.

D. Pressure Rating: 6-inch wg positive, 1/2-inch wg negative.

2.08 ACCESSORIES

A. Duct sleeves: Minimum 20 gauge USSG galvanized sheet steel unless otherwise indicated.

1. Clearances:

a. Non-insulated duct: 1 inch between duct and sleeve on all sides.

b. Insulated duct: 1 inch between insulation and sleeve on all sides.

c. Grilles, registers and diffusers: Zero clearance.

2. Provide closure collars for exposed ducts on each side of wall or floor opening. Collars shall be galvanized sheet metal, minimum 4 inch wide, and fit tight against surface and around duct or insulation. Install with nails 6 inch on center.

3. Framed openings: Provide clearances and closure collars the same as for duct sleeves.

4. Duct-mounted automatic control devices: Mount on mechanical equipment all devices related to automatic controls such as automatic dampers.

PART 3 EXECUTION 3.01 INSTALLATION

A. Install duct accessories according to applicable details shown in SMACNA's "HVAC Duct Construction Standards—Metal and Flexible" for metal ducts and NAIMA's "Fibrous Glass Duct Construction Standards" for fibrous-glass ducts.

B. Install volume dampers in lined duct; avoid damage to and erosion of duct liner.

C. Provide test holes at fan inlet and outlet and elsewhere as indicated.

D. Install fire dampers according to manufacturer's UL-approved written instructions.

1. Install fusible links in fire dampers.

E. Install duct access panels for access to both sides of duct coils. Install duct access panels downstream from volume dampers, fire dampers, turning vanes, automatic dampers, smoke detectors, outside and exhaust air plenums equipment, and other locations as indicated.

1. Install duct access panels to allow access to interior of ducts for cleaning, inspecting, adjusting, and maintaining accessories and terminal units.

2. Install access panels on side of duct where adequate clearance is available.

F. Label access doors according to Section 23 05 53 "Identification for HVAC Piping and Equipment."

Page 78: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 33 00 (15820) - AIR DUCT ACCESSORIES ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

G. Provide flexible connections at fan and building joints.

H. Install automatic dampers supplied by the automatic temperature control system manufacturer. Notch end of rod and label duct/casing to indicate open and closed blade position.

I. Provide volume dampers at following locations:

1. In all duct splits and branch connections of supply, return, and exhaust systems.

2. Ducts connecting to common plenums.

3. Ducts serving single outlet.

4. At open return duct in hung ceiling.

5. Other locations as indicated on drawings.

J. Provide access doors in following locations and as indicated on the Drawings.

1. Automatic dampers: linkage side.

2. Main balancing dampers.

3. Fire dampers.

4. Smoke detection heads.

5. On both sides of ducts where necessary to provide maintenance accessibility to equipment on the other side.

6. Outside air and exhaust air plenums.

K. Flexible Duct Installation:

1. Installation shall be in accordance with SMACNA and local building code standards.

2. Flexible duct runs shall be a maximum of 5 feet, straight lengths, no bends.

3. Connections to beaded sheet metal fittings shall be with 3 wraps of approved tape and stainless steel draw band for tight seal. Seal the outer jacket with 3 wraps of approved UL 181B tape.

4. A 1 ½” minimum strap shall be used to support the flexible duct at a distance not greater than 5’-0”. Maximum permissible sag is ½” per foot of duct length.

3.02 ADJUSTING

A. Adjust duct accessories for proper settings.

B. Adjust fire dampers for proper action.

C. Final positioning of manual-volume dampers is specified in Section 23 05 93 "Testing, Adjusting, and Balancing for HVAC”.

END OF SECTION

Page 79: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. In-Line Centrifugal Fans.

2. Motors

3. Factory Finishes

4. Quality Control

B. Related Sections:

1. Section 23 05 00 (15050) – Common Work Results for HVAC

2. Section 23 05 48 (15070) - Mechanical Sound, Vibration and Seismic Control.

3. Section 23 05 53 (15075) – Identification for HVAC Piping and Equipment

4. Section 23 05 13 (15090) – Common Motor Requirements for HVAC Equipment

5. Section 23 05 93 (15950) - Testing, Adjusting, and Balancing for HVAC

6. Section 23 09 00 (15900) – Instrumentation and Control for HVAC

7. Section 26 29 13 (16420) - Enclosed Controllers: For motor starters.

1.02 REFERENCES

A. Air Movement & Control Association International, Inc. (AMCA) Publications:

1. 99 "Standards Handbook" (Revised 2003)

2. 210 "Laboratory Methods of Testing Fans for Aerodynamic Performance Rating"

3. 300 "Reverberant Room Method for Sound Testing of Fans"

4. 301 "Methods for Calculating Fan Sound Ratings from Laboratory Test Data"

B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:

1. MG 1 “Motors and Generators”

C. National Fire Protection Association (NFPA) Publications:

1. 70 "National Electric Code"

D. Underwriter's Laboratories, Inc. (UL) Publications:

1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper Conductors”

2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”

3. 705 “Standard for Power Ventilators”

1.03 PERFORMANCE REQUIREMENTS

A. Project Altitude: Base air ratings on actual site elevations.

B. Operating Limits: Classify according to AMCA 99.

C. Fan Schedule: The following information is described in an equipment schedule on the Drawings.

Page 80: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Fan performance data including capacities, outlet velocities, static pressures, sound power characteristics, motor requirements, and electrical characteristics.

2. Fan arrangement including wheel configuration, inlet and discharge configurations, and required accessories.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data including rated capacities of each unit, weights (shipping, installed, and operating), furnished specialties, accessories, and the following:

a. Certified fan performance curves with system operating conditions indicated.

b. Certified fan sound power ratings.

c. Motor ratings and electrical characteristics plus motor and electrical accessories.

d. Material gages and finishes, including color charts.

e. Dampers, including housings, linkages, and operators.

2. Shop Drawings from manufacturer detailing equipment assemblies and indicating dimensions, weights, loadings, required clearances, method of field assembly, components, and location and size of each field connection.

3. Wiring diagrams detailing wiring for power and control systems and differentiating clearly between manufacturer-installed and field-installed wiring.

4. Maintenance data for power ventilators to include in the operation and maintenance manual specified in Division 01 and in Section 23 05 00 "Common Work Results for HVAC."

1.05 QUALITY ASSURANCE

A. Electrical Component Standard: Provide components that comply with NFPA 70 and that are listed and labeled by UL where available.

B. Listing and Labeling: Provide electrically operated fixtures specified in this Section that are listed and labeled.

1. The Terms "Listed" and "Labeled": As defined in the National Electrical Code, Article 100.

C. AMCA Compliance: Provide products that meet performance requirements and are licensed to use the AMCA Seal.

D. NEMA Compliance: Provide components required as part of fans that comply with applicable NEMA standards.

E. UL Standard: Provide power ventilators that comply with UL 705.

1.06 PROJECT CONDITIONS

A. Field Measurements: Verify dimensions by field measurements. Verify clearances.

B. Do not operate fans until ductwork is clean, filters are in place, bearings are lubricated, and fans have been commissioned.

Page 81: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1.07 COORDINATION AND SCHEDULING

A. Coordinate the size and location of structural steel support members.

B. Coordinate the installation of equipment supports.

1.08 EXTRA MATERIALS

A. Furnish extra materials described in Section 01 78 43 (01790) “Spare Parts and Materials” that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. In-Line Centrifugal Fans:

a. Loren Cook Company (417-869-6474)

b. Greenheck Fan Corporation(715-359-6171)

c. PennBarry (972-234-3202)

2.02 IN-LINE CENTRIFUGAL FANS

A. Description: In-line, direct-drive centrifugal fans consisting of housing, wheel, outlet guide vanes, fan shaft, bearings, drive assembly, motor and disconnect switch, mounting brackets, and accessories.

B. Housing: Split, aluminum housing, with aluminum straightening vanes; inlet and outlet flanges; and support bracket adaptable to floor, side wall, or ceiling mounting.

C. Direct-Drive Units: Motor encased in housing out of air stream, factory wired to disconnect and variable speed controller located on outside of fan housing.

D. Fan Wheels: Aluminum, airfoil blades welded to aluminum hub.

2.03 MOTORS

A. Refer to Section 23 05 13 - "Common Motor Requirements for HVAC Equipment" for general requirements for factory-installed motors.

B. Motor Construction: NEMA MG 1, general purpose, designed for variable speed drives.

C. Enclosure Type: The following features are required as indicated:

1. Open dripproof motors where satisfactorily housed or remotely located during operation.

2.04 FACTORY FINISHES

A. Sheet Metal Parts: Prime coat before final assembly.

B. Exterior Surfaces: Baked-enamel finish coat after assembly.

C. Aluminum Parts: No finish required.

2.05 SOURCE QUALITY CONTROL

A. Testing Requirements: The following factory tests are required as indicated:

1. Sound Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan Sound Ratings From Laboratory Test Data." Test fans according to AMCA 300, "Reverberant Room Method for Sound Testing of Fans." Label fans with the AMCA Seal.

Page 82: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2. Fan Performance Ratings: Establish flow rate, pressure, power, air density, speed of rotation, and efficiency by factory tests and ratings according to AMCA 210, "Laboratory Methods of Testing Fans for Rating."

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine areas and conditions for compliance with requirements of installation tolerances and other conditions affecting performance of the power ventilators. Do not proceed with installation until unsatisfactory conditions have been corrected.

3.02 INSTALLATION

A. Install power ventilators according to manufacturer's written instructions.

B. Support units using the vibration-control devices indicated. Vibration-control devices are specified in Section 23 05 48 - "Vibration, and Seismic Control for HVAC Piping and Equipment."

1. Suspend units from structural steel support frame using threaded steel rods and vibration isolation springs.

C. Install units with clearances for service and maintenance.

D. Label units according to requirements specified in Section 23 05 53 "Identification for HVAC Piping and Equipment."

3.03 CONNECTIONS

A. Duct installation and connection requirements are specified in other Division 15 Sections. Drawings indicate the general arrangement of ducts and duct accessories. Make final duct connections with flexible connectors.

B. Electrical: Conform to applicable requirements in Division 26 Sections.

C. Grounding: Ground equipment. Tighten electrical connectors and terminals, including grounding connections, according to manufacturer's published torque-tightening values. Where manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B.

3.04 FIELD QUALITY CONTROL

A. Manufacturer's Field Service: Provide services of a factory-authorized service representative to supervise the field assembly of components and installation of fans, including duct and electrical connections, and to report results in writing.

3.05 CLEANING

A. After completing installation, inspect exposed finish. Remove burrs, dirt, and construction debris, and repair damaged finishes including chips, scratches, and abrasions.

B. Clean fan interiors to remove foreign material and construction debris. Vacuum clean fan wheel and cabinet.

3.06 COMMISSIONING

A. Final Checks before Startup: Perform the following operations and checks before startup:

1. Verify that shipping, blocking, and bracing are removed.

2. Verify that unit is secure on mountings and supporting devices and that connections for piping, ducts, and electrical components are complete. Verify that proper thermal-overload protection is installed in motors, starters, and disconnects.

Page 83: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 34 23 (15833) - HVAC POWER VENTILATORS ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3. Perform cleaning and adjusting specified in this Section.

4. Verify that manual and automatic volume control and fire dampers in connected ductwork systems are in the fully open position.

5. Disable automatic temperature-control operators.

B. Starting procedures for fans are as follows:

1. Energize motor; verify proper operation of motor, drive system, and fan wheel. Adjust fan to indicated RPM.

2. Measure and record motor voltage and amperage.

C. Shut unit down and reconnect automatic temperature-control operators.

D. Refer to Section 23 05 93 "Testing, Adjusting, and Balancing for HVAC" for procedures for air-handling-system testing, adjusting, and balancing.

3.07 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain units.

1. Conduct training as specified in Section 01 79 00 (01820) "Training”.

2. Train Owner's maintenance personnel on procedures and schedules related to startup and shutdown, troubleshooting, servicing, and preventive.

END OF SECTION

Page 84: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 37 00 (15850) - AIR OUTLETS AND INLETS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 37 00 (15850) - AIR OUTLETS AND INLETS

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Diffusers

2. Registers

3. Grilles

4. Louvers

B. Related Sections:

1. Section 23 33 00 (15820) – Air Duct Accessories.

2. Section 23 05 93 (15950) - Testing, Adjusting, and Balancing for HVAC.

1.02 REFERENCES

A. Air Movement & Control Association International, Inc. (AMCA)

B. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Publications:

1. 70 "Method of Testing for Rating the Performance of Air Outlets and Inlets"

C. National Fire Protection Association (NFPA) Publications:

1. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

1.03 DEFINITIONS

A. Diffuser: Circular, square, or rectangular air distribution outlet, generally located in the ceiling and comprised of deflecting members discharging supply air in various directions and planes and arranged to promote mixing of primary air with secondary room air.

B. Grille: A louvered or perforated covering for an opening in an air passage, which can be located in a sidewall, ceiling, or floor.

C. Register: A combination grille and damper assembly over an air opening.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data: For each model indicated, include the following:

a. Data Sheet: For each type of air outlet and inlet, and accessory furnished; indicate construction, finish, and mounting details.

b. Performance Data: Include throw and drop, static-pressure drop, and noise ratings for each type of air outlet and inlet.

c. Schedule of diffusers, registers, and grilles indicating drawing designation, room location, quantity, model number, size, and accessories furnished.

d. Assembly Drawing: For each type of air outlet and inlet: indicate materials and methods of assembly of components.

Page 85: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 37 00 (15850) - AIR OUTLETS AND INLETS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

e. Provide Miami-Dade County Product Control Approval Notice of Acceptance.

1.05 QUALITY ASSURANCE

A. Product Options: Drawings and schedules indicate specific requirements of diffusers, registers, and grilles and are based on the specific requirements of the systems indicated.

B. NFPA Compliance: Install diffusers, registers, and grilles according to NFPA 90A, "Standard for the Installation of air-conditioning and Ventilating Systems."

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Diffusers, Registers, and Grilles:

a. Titus (972-699-1030)

b. Price (204-633-4808)

c. Krueger (972-680-9136)

2. Constant Airflow Registers:

a. American Aldes Ventilation Corp. (800-255-7749)

3. Exterior Louvers:

a. Ruskin Company (816-761-7476)

b. American Warming & Ventilating Co., A Division of Mestek, Inc. (419-865-5000)

c. Arrow United Industries, A Division of Mestek, Inc. (570-746-1888)

2.02 MANUFACTURED UNITS

A. Diffusers, Registers, and Grilles:

1. As scheduled on Drawings

B. Constant Airflow Registers:

1. As scheduled on drawings.

C. Exterior Louvers:

1. Provide exterior wall louvers; size as indicated on Drawings.

2. Louvers shall be AMCA certified for zero water penetration and maximum 1/8-inch pressure drop at a free area velocity of 900 fpm.

3. Louvers shall be stationary drainage blade type with a 4” deep constructed of 0.081” thick 6063-TS extruded aluminum complete with ½” aluminum screen in removable frame.

4. Frames shall be box type for masonry construction and flange type for frame construction.

5. Louver Finish shall have a factory baked enamel prime finish ready to accept full paint to match adjacent surfaces.

2.03 SOURCE QUALITY CONTROL

A. Testing: Test performance according to ASHRAE 70, "Method of Testing for Rating the Performance of Air Outlets and Inlets."

Page 86: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 37 00 (15850) - AIR OUTLETS AND INLETS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine areas where diffusers, registers, and grilles are to be installed for compliance with requirements for installation tolerances and other conditions affecting performance of equipment. Do not proceed with installation until unsatisfactory conditions have been corrected.

3.02 INSTALLATION

A. Install diffusers, registers, and grilles level and plumb, according to manufacturer's written instructions, Coordination Drawings, original design, and referenced standards.

B. Ceiling-Mounted Outlets and Inlets: Drawings indicate general arrangement of ducts, fittings, and accessories. Air outlet and inlet locations have been indicated to achieve design requirements for air volume, noise criteria, airflow pattern, throw, and pressure drop. Make final locations where indicated, as much as practicable. For units installed in lay-in ceiling panels, locate units in the center of the panel. Where architectural features or other item conflict with installation notify Owner’s Representative for a determination of final location.

C. Install diffusers, registers, and grilles with airtight connection to ducts and to allow service and maintenance of dampers, air extractors, and fire dampers.

3.03 ADJUSTING

A. After installation, adjust diffusers, registers, and grilles to air patterns indicated, or as directed, before starting air balancing.

3.04 CLEANING

A. After installation of diffusers, registers, and grilles, inspect exposed finish. Clean exposed surfaces to remove burrs, dirt, and smudges. Replace diffusers, registers, and grilles that have damaged finishes.

END OF SECTION

Page 87: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 41 00 (15861) - PARTICULATE AIR FILTRATION ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 41 00 (15861) - PARTICULATE AIR FILTRATION

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Disposable Panel Filters

2. Extended Surface Filters

B. Related Sections:

1. Section 23 81 13.13 (15735) - Packaged Terminal Air-Conditioning Units

2. Section 23 81 19 (15736) - Self-Contained Air-Conditioning Units

3. Section 23 37 00 (15850) - Air Outlets and Inlets

1.02 REFERENCES

A. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Publications:

1. 52.1 “Gravimetric and Dust-Spot Procedures for Testing Air-Cleaning Devices Used in General Ventilation for Removing Particulate Matter”

B. National Fire Protection Association (NFPA) Publications:

1. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

2. 90B “Standard for the Installation of Warm Air Heating and Air-Conditioning Systems”

C. Underwriter's Laboratories, Inc. (UL) Standards:

1. 900 “Test Performance of Air Filter Units”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data:

a. Include dimensions; shipping, installed, and operating weights; required clearances and access; rated flow capacity, including initial and final pressure drop at rated airflow; efficiency and test method; fire classification; furnished specialties; and accessories for each model indicated.

2. Maintenance Data: For each type of filter and rack to include in maintenance manuals specified in Division 01. Reference Section 01 78 23 (01830) “Operation and Maintenance Data” for additional requirements.

1.04 QUALITY ASSURANCE

A. Product Options: Drawings indicate size, profiles, and dimensional requirements of air filters and are based on the specific system indicated.

B. Comply with NFPA 90A and NFPA 90B.

C. ASHRAE Compliance: Comply with provisions of ASHRAE 52.1 for method of testing and rating efficiency, arrestance, and dust holding capacity.

Page 88: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 41 00 (15861) - PARTICULATE AIR FILTRATION ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

D. Underwriters Laboratories, Inc. (UL): Comply with UL Standards pertaining to safety and performance of air filter units including UL 900 “Test Performance of Air Filter Units.”

1.05 EXTRA MATERIALS

A. Furnish extra materials described in Section 01 78 43 (01790) “Spare Parts and Materials” that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Air Filters, Electrostatic Air Cleaners, and Filter-Holding Systems:

a. AAF International (800-477-1214)

b. Camfil Farr (973-616-7300)

c. International Air Filter, Inc. (800-797-1000)

2.02 DISPOSABLE PANEL FILTERS

A. Description: Factory-fabricated, viscous-coated, flat-panel type, disposable air filters with holding frames.

B. Media: Interlaced glass fibers sprayed with nonflammable adhesive.

C. Frame: Cardboard frame with perforated metal retainer.

D. Duct-Mounting Frames: Welded, galvanized steel with gaskets and fasteners and suitable for bolting together into built-up filter banks.

2.03 EXTENDED-SURFACE, DISPOSABLE PANEL FILTERS

A. Description: Factory-fabricated, dry, one 2-inch extended-surface filters with holding frames.

B. Media: Fibrous material formed into deep-V-shaped pleats and held by self-supporting wire grid.

C. Media and Media-Grid Frame: Nonflammable rigid drip board frame with expanded metal support cross braced on both sides of filter media.

D. Media and Media-Grid Frame: Galvanized steel.

E. Duct-Mounting Frames: Welded, galvanized steel with gaskets and fasteners, and suitable for bolting together into built-up filter banks.

PART 3 EXECUTION A. Install filter frames according to manufacturer's written instructions.

B. Position each filter unit with clearance for normal service and maintenance. Anchor filter holding frames to substrate.

C. Install filters in position to prevent passage of unfiltered air. Joints between filter frames and enclosing ductwork shall be gasketed and sealed against air leakages.

D. Coordinate filter installations with duct and air-handling unit installations.

3.02 CLEANING

A. After completing system installation and testing, adjusting, and balancing air-handling and air-distribution systems, clean filter housings and install new filter media.

Page 89: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 41 00 (15861) - PARTICULATE AIR FILTRATION ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

END OF SECTION

Page 90: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Dedicated Outdoor-Air Units with Energy Recovery

B. Related Sections:

1. Section 23 05 00 (15050) – Common Work Results for HVAC

2. Section 23 05 13 (15090) – Common Motor Requirements for HVAC Equipment

3. Section 23 05 48 (15070) – Vibration Control for HVAC Piping and Equipment

4. Section 23 05 53 (15075) – Identification for HVAC Piping and Equipment

5. Section 23 05 93 (15950) – Testing, Adjusting and Balancing for HVAC

6. Section 23 09 00 (15900) – Instrumentation and Control for HVAC

7. Section 23 09 93 (15940) – Sequence of Operation for HVAC Controls

8. Division 23 11 23 (15194) – Facility Natural-Gas Piping

9. Division 26 (16) Sections for electrical connections.

1.02 REFERENCES

A. Air-Conditioning, Heating and Refrigeration Institute (AHRI) Publications:

1. 410 "Forced Circulation Air-Cooling and Air-Heating Coils”

2. 1060 "Performance of Air-to-Air Heat Exchangers for Energy Recovery Ventilation Equipment”

B. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Publications:

1. 62.1 “Ventilation for Acceptable Indoor Air Quality (ANSI Approved)”

2. 90.1 “Energy Code for Commercial and High-Rise Residential Buildings”

C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)

1. B117 "Standard Practice for Operating Salt Spray (Fog) Apparatus"

D. National Fire Protection Association (NFPA) Publications:

1. 70 "National Electric Code"

2. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data including manufacturer's technical data, clearly indicated for each model, including: rated capacities, operating characteristics, dimensions, weights (shipping, installed, and operating), furnished specialties, accessories, and installation and startup instructions.

Page 91: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

2. Shop Drawings from manufacturer detailing equipment assemblies and indicate dimensions, weights, loadings, required clearances, method of field assembly, components, and location and size of each field connection. Detail mounting, securing, and flashing of roof curb to roof structure. Indicate coordinating requirements with roof membrane system.

3. Wiring Diagrams detailing wiring for power, signal, and control systems. Clearly differentiate between manufacturer-installed and field-installed wiring.

4. Commissioning report, including pre-functional testing checklists, indicating the results of unit startup, testing and commissioning requirements.

5. Maintenance data for energy recovery units to include in the operation and maintenance manual specified in Division 01 and in Section 23 05 00 "Common Work Results for HVAC."

1.04 QUALITY ASSURANCE

A. AHRI Certification: Units and their components shall be factory tested according to the applicable portions of AHRI 1060, "Performance of Air-to-Air Heat Exchangers for Energy Recovery Ventilation Equipment," and AHRI 410, "Forced Circulation Air-Cooling and Air-Heating Coils," and shall be listed and bear the label of the Air-Conditioning, Heating and Refrigeration Institute (AHRI ).

B. UL and NEMA Compliance: Provide motors required as part of air-handling units that are listed and labeled by UL and comply with applicable NEMA standards.

C. Comply with NFPA 70 for components and installation.

D. Listing and Labeling: Provide electrically operated components specified in this Section that are listed and labeled.

1. The Terms "Listed" and "Labeled": As defined in the NFPA National Electrical Code, Article 100.

E. Comply with ASHRAE/IESNA Standard 62.1-2004, Section 7 – "Construction and Startup."

1.05 DELIVERY, STORAGE, AND HANDLING

A. Deliver rooftop units as factory-assembled units with protective crating and covering.

B. Coordinate delivery of units in sufficient time to allow movement into building.

C. Handle rooftop units to comply with manufacturer's written rigging and installation instructions for unloading and moving to final location.

1.06 COORDINATION

A. Coordinate installation of roof curbs, equipment supports, and roof penetrations.

1.07 EXTRA MATERIALS

A. Furnish extra materials described in Section 01 78 43 (01790) “Spare Parts and Materials” that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1.08 WARRANTY

A. General Warranty: The manufacturer shall warrant all equipment for a period of one (1) year from date of substantial completion. Extended warranty specified in this Article shall not deprive Owner of other rights Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by Contractor under requirements of the Contract Documents.

Page 92: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

B. Extended Warranty: Manufacturer's standard form in which manufacturer agrees to replace components of rooftop air conditioners that fail in materials or workmanship within specified warranty period.

1. Extended Warranty Period for Compressors: Manufacturer's standard, but not less than five years from date of Substantial Completion.

2. Extended Warranty Period for Heat Exchangers: Manufacturer's standard, but not less than 10 years from date of Substantial Completion.

3. Extended Warranty Period for Energy Wheels: Manufacturer's standard, but not less than 5 years from date of Substantial Completion.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Dedicated Outdoor Air Unit

a. "Rebel"; Daikin (800-432-1342)

b. “SolutionAir”; JAFT Corp (888-871-2310 x-108)

c. “RN Series”; AAON, Inc. (905-631-9161)

d. "TotalAire (QS) Series"; Desert Aire (262-946-7400)

e. “Model ERCH”; Greenheck Fan Corporation (713-359-6171)

f. "Complevent"; Munters Corporation (800-843-5360)

g. "OAU"; Trane (608-787-4810)

h. Seresco (888-737-3726)

i. Advantix Systems (888-818-5171)

2.02 DEDICATED OUTDOOR-AIR UNITS WITH ENERGY RECOVERY

A. Description: Packaged self-contained, outdoor rooftop, DX/gas, 100% outside air, energy recovery unit of capacities and characteristics as scheduled on the drawings.

1. Each unit shall be completely factory assembled, piped, wired, tested and shipped in one piece.

2. Unit shall be capable of varying the amount of outside air delivered to the space based on occupancy, humidity, indoor air quality and differential pressure.

3. In the event that the space dry bulb temperature begins to deviate from set point, the DOAS shall be capable of varying the outside air supply air temperature to supplement the cooling or heating requirements of the space.

4. Unit shall be capable of varying the moisture content of outside air to the space based on space humidity. To maintain 59 grains of moisture per pound of dry air space conditions, the DOAS must be able deliver air down to 39°F dew point supply air at low air volume conditions.

5. Units shall be designed to cool or dehumidify with entering air temperatures of 45°-110°F and operate in heating mode down to -40°F. Units shall be capable of supplying air with a maximum of 59 grains of moisture per pound of dry air, or less if specified, at both the dry bulb / mean coincidental wet bulb and dew point / mean coincidental dry bulb temperatures at the 0.4% ASHRAE design conditions for the location of the installation.

Page 93: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

Units not capable of delivering 59 grains of moisture per pound of dry air, or less if specified, at both design conditions are unacceptable.

6. Units shall provide 100% outdoor air directly to the space, or delivered to the terminal unit(s) supply air duct. Mixed Air units are NOT acceptable.

B. Unit Cabinet:

1. Unit shall be specifically designed for outdoor rooftop application with a fully weatherproof cabinet. The unit roof shall be sloped or cross-broken to assure drainage. Unit base shall overhang the roof curb for water run-off. Rain break overhangs shall be provided above access doors.

2. Cabinet shall be of double wall, insulated design. The cabinet exterior shall be constructed of painted 20 gauge or heavier G90 galvanized steel, or unpainted Type 5052 marine grade aluminum using 12 gauge panels & 8 gauge structural members, or unpainted Type 304 stainless steel using 18 gauge panels & 14 gauge structuratl members. The interior shall be Type 5052 aluminum or Type 304 stainless of similar gauge to the cabinet exterior. The cabinet shall be weatherproof and suitable for outdoor construction and the entire floor shall be designed to operate as a drain pan so that in the event that rain would enter the cabinet, it will drain via the condensate drain connection. Insulation shall be in accordance with the requirements of ASHRAE Standard 90.1-2004, and shall be non-wicking and moisture resistant. The insulation must not be capable of supporting any biological growth of any kind. All insulation shall have a smoke and fire rating of 5-5 and shall be rated Class A. The insulation shall have a VOC content of zero (0).

3. Paint finish shall be capable of withstanding at least 2500 hours, with no visible corrosive effects, when tested in a salt spray and fog atmosphere in accordance with ASTM B117-95 test procedure.

4. Unit shall have insulated, hinged access doors with quarter turn handles and full perimeter gasketed seals. Door fastening screws are not acceptable.

5. Unit shall be factory pre-rigged for a 4-point crane lift.

6. All openings through the base pan of the unit shall have upturned flanges of at least 1/2” in height around the opening through the base pan.

7. Unit shall have a factory-installed cleanable, insulated, double-sloped condensate drain connection of aluminum or stainless steel.

8. Outdoor and exhaust air openings shall have a hood or louver with bird screen. Construction and color shall match cabinet.

9. Dampers:

a. Motor operated outside air damper assembly constructed of extruded aluminum, hollow core, airfoil blades with rubber edge seals and aluminum end seals. Damper blades shall be gear driven and designed to have no more than 15 CFM of leakage per sq. ft. of damper area when subjected to 2” w.g. air pressure differential across the damper.

b. Gravity type backdraft damper at the exhaust discharge.

10. All evaporator, condenser and water coils shall be cleanable. All coils shall be a maximum of 4 rows thick, 10 fins per inch and include a minimum of a 4 inch clean-out access between coils. The floor below the coil shall be suitable for drainage of the cleaning solution. All coils must be coated in order to reduce corrosion from contaminants from outside air and moisture and increase watershed capability. The

Page 94: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

coating shall be a thermal set acrylic having an ASTM B117 salt test rating that exceeds 1000 hours. Coatings shall be hydrophobic to aid in draining water from the coil. Interlaced coils shall NOT be acceptable. Units with coils that have more than 10 fins per inch or that have lanced fins are NOT acceptable.

11. Color coded wiring diagrams shall be laminated in plastic and permanently affixed inside the control compartment.

12. Unit shall have decals and tags to indicate unit lifting and rigging, service areas and caution areas.

13. Unit nameplates shall be fixed to the main control panel door.

C. Roof Curb: (DOAS-2)

1. Roof curb shall be constructed of similar metal as the cabinet construction. Curbs are to be factory welded construction providing full perimeter support, cross structure support and air seal for the unit. Curb shall be as described on the drawings.

D. Supply and Exhaust Fans:

1. Plenum supply fan shall be backward inclined, direct drive with factory installed variable frequency drive, non-overloading, and designed for high efficiency operation at higher static pressures with lower noise levels. Blowers shall be constructed of epoxy-coated steel for corrosion resistance.

2. Exhaust fan shall be backward inclined, direct drive type, non-overloading, and designed for high efficiency operation at higher static pressures with lower noise levels. Blowers shall be constructed of epoxy-coated steel for corrosion resistance.

3. Fans shall be statically and dynamically balanced.

4. The fan assembly shall be Blower and motor base is to be mounted on 4 spring and rubber isolators having minimum 3/4-inch deflection. Blower to be isolated from the cabinet with a flexible connector having a 25-50 fire rating.

5. Fan shaft bearings shall be heavy duty, permanently lubricated, self-aligning ball or roller pillow block type. Bearings shall have a minimum life (L-10) of 80,000 hours at maximum operating speed and horsepower for each construction level.

E. Air-Cooled Condenser:

1. The condensing section shall be equipped with vertical discharge, propeller type, direct drive fans with corrosion-resistant blades and supports. Direct drive fans shall be directly connected to and supported by the motor shaft. Fans shall be statically and dynamically balanced.

2. Condenser coils shall have enhanced surface aluminum plate fins mechanically bonded to the copper tubes with all joints brazed.

F. Refrigerant System:

1. Unit shall be factory charged with R-410A refrigerant.

2. Compressors:

a. Fully hermetic, scroll type compressors with crankcase heater, overload protection and short cycle protection with minimum on and off timers.

b. Compressors shall be mounted on the compressor manufacturer’s recommended rubber vibration isolators and shall be isolated from the base pan and supply air to avoid transmission of noise from the compressor into the building. Vibrasorb

Page 95: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 6 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

isolators shall be installed in both the suction and discharge tubing of each compressor.

c. Compressors shall be mounted in an isolated compartment to permit operation of the unit without affecting air flow when the door to the compartment is open.

d. Each compressor shall be individually staged for capacity control. Units exceeding 2,000 cfm shall have a minimum of 3 independent refrigeration circuits that have no shared components. Each circuit must be able to operate at any time without the assistance or aid of any component of the other circuits with the exception of the controls and blower. Any or all components of any single circuit must be constructed in such a way as to be removable without disturbing or disrupting or contaminating any of the other circuits. Each compressor shall be dedicated to an individual evaporator coil, TXV and condenser coil and operate independently. Tandem compressors shall NOT be acceptable. Minimum 2-stage capacity control on units over 10 tons and above.

3. Refrigerant System Specialties for each circuit:

a. Refrigerant dryer.

b. Adjustable thermostatic expansion valve.

c. High and low pressure switches.

d. Gage connection ports.

e. Liquid line sight glass.

f. Service/charging valves.

4. Reheat Coil: Hot gas reheat coil with 0-100% modulating hot gas reheat control valves piped to all reheat refrigerant circuits.

5. Capacity Control:

a. Multiple compressor design and Variable Speed Scroll compressor design shall provide 0-100% capacity control for continuous dehumidification upon demand. Energy wasting hot gas bypass refrigerant control shall NOT be acceptable.

b. Unit shall be equipped with variable speed low ambient head pressure control to allow operation down to 35 F.

6. Evaporator coil shall have minimum corrosion potential from dissimilar metals. Coil casing shall be either copper, aluminum, stainless steel. Galvanized steel coil casings shall NOT be acceptable

7. Evaporator coil shall be furnished with a double sloped drain pan fabricated of Type 5052 aluminum, or Type 304 stainless steel for the positive drainage of condensate.

G. Filter Section:

1. The outdoor air steams shall have 4” thick pleated, high efficiency filters with a minimum MERV-13 rating and the exhaust air steams shall have MERV-8 filters.

H. Filter Section:

1. Both outdoor and exhaust air steams shall have 2” thick fiberglass filters with a minimum MERV-7 rating.

I. Energy Recovery Wheel:

1. Wheel shall be of the enthalpy type for both sensible and latent recovery; moisture transfer shall occur entirely in the vapor phase. Wheel shall be constructed of alternate

Page 96: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 7 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

layers of corrugated and flat aluminum. Enthalpy wheels shall be permanently bonded with "Micro-Sieve" a desiccant adsorbent specifically developed for the selective transfer of moisture for equal transfer of sensible and latent energy. The air channels shall be formed smooth to ensure laminar airflow for low-pressure drops and allow free passage of particles up to 900 microns. Rotor structure shall be internally reinforced and mounted on pillow block type bearings. The rotor shall also be removable from the frame. Brush seals shall be provided around the periphery of the rotor and between the inlet and outlet air passages to effectively prevent air leakage and cross contamination between airflows. An adjustable purging sector shall be installed to prevent carryover of contaminated exhaust air into the supply air stream. Performance and cross contamination shall be documented through an independent laboratory conducted in accordance with ASHRAE 84-1991 and AHRI standards.

2. Factory provided integral DDC automatic temperature control that shall include remote temperature sensors mounted in each of the four airstreams to monitor exchanger performance. The control shall modulate rotor speed to prevent frost build-up. A rotor bypass section shall be incorporated into the cabinet design to bypass the rotor when conditions are beneficial for overall energy savings.

J. Winter Heating Mode

1. Indirect-Fired Gas Heating:

a. Gas heating shall be induced-draft combustion type with an energy saving direct spark ignition system and redundant main gas valves.

b. Heat exchanger shall be tubular section type, constructed of 20 gauge stainless steel.

c. Burners shall be modulating (10:1 turndown) in-shot type constructed of stainless steel and have sufficient staging as to provide the supply air temperature within 2 degrees (F) of the DOAS supply air setpoint, even at startup, regardless of the entering air temperature. As the supply air volume modulates to meet ventilation demands, the supply air temperature shall not rise above or below the set point temperature, +/- 2 degrees (F).

d. Gas shall enter the unit at a single location.

K. Controls:

1. Dedicated Outdoor-Air Unit Controller:

a. The unit shall include a factory installed microprocessor based unit controller which controls the operation of all unit functions including: dampers, supply and exhaust fans, energy recovery wheel, refrigerant system and gas heater.

b. Controller shall be capable of the monitoring the following functions, safeties and alarms.

1) Factory-installed dirty filter status for both supply and exhaust filter banks.

2) Factory-installed fan status switch for both supply and exhaust fans.

3) Energy wheel defrost control and air bypass.

c. Controller shall be BACNet, Modbus and LonWorks protocol compatible.

d. Shall include and alarm indicator and audible alarm signal.

2. Fan current transducer.

3. Supply air temperature sensor.

Page 97: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 8 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

4. Outside air temperature sensor.

5. Relative humidity sensor.

L. Fire Alarm System Interface:

1. Provide dry contact control interface to connect to fire alarm panel, so that unit shuts down in the event the fire alarm system goes into alarm.

M. Airflow Monitoring/Control & Building Pressure Control:

1. Provide building pressure differential sensor and controls to maintain building pressure at a user adjustable setting (initially set at 0.05” w.g.). The building pressure sensor is to be accurate to within 0.02” w.g. and is to be self-calibrating. Upon a rise in building pressure, the unit controls are to slow down the supply air fan (through the variable speed drive). The opposite is to happen on a drop in building pressure.

N. Electrical:

1. Unit shall be provided with a factory installed and wired main disconnect switch. Integral branch fusing shall be accomplished through the use of resettable circuit breakers. Replaceable fuses are NOT acceptable.

2. Unit shall be provided with phase and brown-out protection to shut down all motors in the unit if the phases are more than 10% out of balance on voltage, or the voltage is more than 10% under design voltage or on phase reversal. In the event that a poor power condition is detected, the power monitoring feature will instantaneously shut the unit down and isolate the microprocessor controller from the incoming power supply. The Power Monitor feature shall record and save a minimum of 10 fault conditions in the fault history log. The Power Monitor feature shall automatically restart the unit after power has returned within acceptable parameters for a preset period of time.

3. Unit shall be provided with a factory installed and wired 115 volt, 12 amp ground fault service receptacle powered by a 1.5 KVA transformer. The convenient outlet shall be fed by an independent power supply.

2.03 MOTORS

A. Refer to Division 23 Section "Common Motor Requirements for HVAC Equipment" for general requirements for factory-installed motors.

B. Motor Construction: NEMA MG 1, general purpose, continuous duty, Design B.

C. Enclosure Type: Open, dripproof.

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine roof for compliance with requirements for conditions affecting installation and performance of rooftop units. Do not proceed with installation until unsatisfactory conditions have been corrected.

3.02 INSTALLATION

A. Install units according to manufacturer's written instructions.

B. Install units level and plumb, maintaining manufacturer's recommended clearances.

3.03 CONNECTIONS

A. Piping installation requirements are specified in other Division 23 Sections. Drawings indicate the general arrangement of piping, fittings, and specialties. The following are specific connection requirements:

Page 98: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 9 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Install piping to allow service and maintenance.

2. Gas Piping: Comply with applicable requirements in Division 22 Section "Natural Gas Piping." Connect gas piping to burner, full size of gas train inlet, and connect with union and shutoff valve with sufficient clearance for burner removal and service.

B. Duct installation requirements are specified in other Division 23 Sections. Drawings indicate the general arrangement of ducts.

3.04 FIELD QUALITY CONTROL AND COMMISSIONING

A. Verify that installation is as indicated and specified.

B. Complete commissioning pre-functional testing and functional testing as part of the following.

C. Complete manufacturer's installation and startup checks and perform the following:

1. Level unit on curb or steel, and flash curbs to unit and to roof.

2. Inspect for visible damage to unit casing.

3. Verify that clearances have been provided for servicing.

4. Check that labels are clearly visible.

5. Verify that controls are connected and operable.

6. Remove shipping bolts, blocks, and tie-down straps.

7. Verify that filters are installed.

8. Clean furnace flue and inspect for construction debris.

9. Connect and purge gas line.

10. Adjust vibration isolators.

11. Inspect operation of barometric dampers.

12. Check operation of mixing dampers.

D. Lubricate bearings on fan.

E. Check fan-wheel rotation for correct direction without vibration and binding.

F. Adjust fan belts to proper alignment and tension.

G. Start unit according to manufacturer's written instructions.

H. Check and record performance of interlocks and protection devices; verify sequences.

I. Operate unit for an initial period as recommended or required by manufacturer.

J. Check internal isolators.

K. Check outside-air damper for proper stroke and interlock with return-air dampers.

L. Check controls for correct sequencing of heating, cooling, mixing dampers, and normal and emergency shutdown.

M. Perform the following operations for both minimum and maximum firing and adjust burner for peak efficiency. Adjust pilot to stable flame.

1. Measure gas pressure on manifold.

2. Measure combustion-air temperature at inlet to combustion chamber.

3. Measure flue-gas temperature at furnace discharge.

Page 99: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 74 33 (15733) - DEDICATED OUTDOOR AIR UNITS ▪ ▪ PAGE 10 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

4. Perform flue-gas analysis. Measure and record flue-gas carbon dioxide and oxygen concentration.

5. Measure supply-air temperature and volume when burner is at maximum firing rate and when burner is off. Calculate useful heat to supply air.

N. Start refrigeration system and measure and record the following:

1. Coil leaving-air, dry- and wet-bulb temperatures.

2. Coil entering-air, dry- and wet-bulb temperatures.

3. Outside-air, dry-bulb temperature.

4. Outside-air-coil, discharge-air, dry-bulb temperature.

O. Measure and record the following minimum and maximum airflows. Plot fan volumes on fan curve.

1. Supply-air volume.

2. Return-air volume.

3. Relief-air volume.

4. Outside-air intake volume.

P. After starting and performance testing, change filters, vacuum heat exchanger and coils, lubricate bearings, and adjust belt tension.

3.05 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel.

1. Conduct training as specified in Section 01 79 00 "Training”.

2. Train Owner's maintenance personnel on procedures and schedules related to startup and shutdown, troubleshooting, servicing, and preventive maintenance.

3. Review data in the maintenance manuals.

END OF SECTION

Page 100: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS

PART 1 GENERAL 1.01 SUMMARY

A. Section Includes:

1. Packaged Terminal Air Conditioning Units (PTAC) (Heat Pumps)

2. Controls

B. Related Sections:

1. Section 07 92 00 (07920) - Joint Sealants

2. Section 23 09 00 (15900) - HVAC Instrumentation and Controls

1.02 REFERENCES

A. American Architectural Manufacturers Association (AAMA) Publications:

1. 2604 “Voluntary Specification, Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusion and Panels”

B. Air-Conditioning, Heating and Refrigeration Institute (AHRI) Publications:

1. 270 “Sound Rating of Outdoor Unitary Equipment”

2. 310/380 "Packaged Terminal Air-Conditioners and Heat Pumps"

3. 390 “Performance Rating of Single Package Vertical Air-Conditioners and Heat Pumps”

C. American National Standards Institute (ANSI) Publications:

1. ANSI/NFPA 70, “National Electrical Code”

D. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Publications:

1. 15 “Safety Standard for Refrigeration Systems”

2. 90.1 “Energy Code for Commercial and High-Rise Residential Buildings”

E. Underwriter's Laboratories, Inc. (UL) Standards:

1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper Conductors”

2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product Data:

a. Include rated capacities, weights, furnished specialties, and accessories for each model indicated.

2. Shop Drawings: Detail layout and installation of wall penetrations.

a. Wiring Diagrams: Detail wiring for power, signal, and control systems and differentiate between manufacturer-installed and field-installed wiring.

Page 101: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3. Maintenance Data: For equipment to include in the maintenance manuals specified in Section 01 78 23 (01830), “Operation and Maintenance Data.”

4. Warranties: Special warranties specified in this Section.

1.04 QUALITY ASSURANCE

A. Fabricate and label refrigeration system to comply with ASHRAE 15, "Safety Code for Mechanical Refrigeration."

B. Energy Efficiency Ratio: Equal to or greater than prescribed by ASHRAE 90.1, "Energy Efficient Design of New Buildings except Low-Rise Residential Buildings."

C. Coefficient of Performance: Equal to or greater than prescribed by ASHRAE 90.1, "Energy Efficient Design of New Buildings except Low-Rise Residential Buildings."

D. Listing and Labeling: Provide electrically operated components specified in this Section that are listed and labeled by UL and cUL.

1. The Terms "Listed" and "Labeled": As defined in the ANSI/NFPA 70, “National Electrical Code, Article 100.

2. Unit shall be rated in accordance with AHRI Standard 390 and certified by UL or ETL.

1.05 COORDINATION

A. Coordinate layout and installation of units and wall construction where unit penetrates wall or is supported by it.

1.06 WARRANTY

A. General Warranty: The special warranty specified in this Article shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by the Contractor under requirements of the Contract Documents.

B. Special Warranty: A written warranty, executed by the manufacturer and signed by the Contractor, agreeing to replace components that fail in materials or workmanship within the specified warranty period, provided manufacturer's written instructions for installation, operation, and maintenance have been followed.

1. Full Warranty: After date of substantial completion and start-up, the manufacturer will repair or replace any parts which are defective in material or workmanship.

a. Warranty Period

1) Friedrich: Two years

2) LG: One year

3) GE: One year

4) Islandaire: One year 5) Amana: One year

2. Sealed Refrigeration System: Manufacturers standard extended warranty, but not less than four years after date of Substantial Completion.

a. Provide free of charge, on-site repair or replacement of the compressor, condenser, evaporator or connecting tubing if defective in material or workmanship. This shall include system refrigeration charge.

3. Non-Sealed Refrigeration System: Manufacturers standard extended warranty, but not less than five years after date of Substantial Completion.

Page 102: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

a. Provide free of charge, on-site repair or replacement of any non-sealed system part (motor, solenoid, thermistor, thermostat, relays, switch, capacitor, overload, drain valve, bulb heater, fan, stator) if defective in material or workmanship. The replacement part may be new or a remanufactured part. The limited warranty excludes labor including the cost of diagnostics, removal, and reinstallation necessary to accomplish the repair.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Avendra, LLC Preferred Manufacturers:

1. Friedrich Air Conditioning Co. (877-599-5665 x 508)

a. Contact: Bill Huber (210-546-0508)

B. Approved Manufacturers:

1. LG-PTAC a Division of Mainstreet Marketing Group, L.L.C.; (888-540-7822)

2. General Electric Company (800-770-4651)

3. Islandaire, Inc. (800-886-2759)

4. Amana (800-647-2982)

2.02 PACKAGED TERMINAL AIR CONDITIONING UNITS (PTAC)

A. Description: Packaged, self-contained, through-the-wall terminal units with room cabinet, electric refrigeration system, heating, and temperature controls; fully charged with refrigerant.

B. Cabinet: Provide removable front panel with concealed latches.

1. Mounting: Wall with wall sleeve.

2. Finish: Manufacturer’s standard color.

3. Control Knobs: If provided, shall be secured so that they can not be easily removed (anti-theft knobs).

4. Discharge Grille and Access Door: Provide discharge grille with hinged door in top of cabinet for easy access to controls. Hinged door not required if unit has unit or wall mounted digital controls.

5. Subbase: Enameled steel with adjustable leveling feet and adjustable end plates.

6. Wall Sleeves: Insulated, Galvanized steel.

7. Exterior Grille / Louvers: Extruded architectural aluminum or polymer construction. Only for units indicated.

a. Factory applied baked enamel finish.

b. Color: Refer to Exterior Finish Index.

C. Refrigeration System: Direct-expansion indoor coil with capillary restrictor, hermetically sealed compressor with internal spring isolation, external isolation, permanent-split-capacitor motor, and overload protection. Charge with R-410A. Include the following:

1. Outdoor coil and fan.

2. Accumulator.

D. Preventative Maintenance: Split outdoor fan shroud for easy access to outdoor coil for cleaning and maintenance.

Page 103: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

E. Air System: Forward or backward curved, centrifugal, indoor fans with two speed TEFC permanently lubricated permanent-split-capacitor motor, permanent one or two-piece interchangeable polyurethane washable filters, return air indoor filters and outdoor vent filter with concealed operation located under the front panel to manually open and close the outdoor vent.

1. Curtain Deflector: Manufacturers standard curtain deflector to insure the curtains will not blow into the discharge air stream.

F. Electric-Resistance Heating Coil: Nickel-chromium wire, electric-resistance heating elements with contactor and high-temperature-limit switch.

G. Condensate Drain: Slinger Technology used to pick up/disperse condensate to outdoor coil for re-evaporation. In addition, provide auxiliary condensate drain kits for connection to piped condensate drain system to a code approved location..

H. Outdoor Fan: Propeller type with corrosion resistant finish.

I. Coils: Aluminum plate fins mechanically bonded to seamless copper tubes with all joints brazed.

J. Insulated Wall Sleeve:

1. Provide wall sleeve with factory installed insulation.

2.03 CONTROLS

A. Control Module:

1. Unit Mounted Controls: Unit-mounted adjustable thermostat, off-heat-cool mode switch, and fan cycle/continuous switch.

2. Wall Thermostat Controls: Wall thermostat interface with user selectable hi/low fan speed switch.

a. Refer to Section 23 09 00 (15900) – “HVAC Instrumentation and Controls”. Standard Thermostats supplies with PTAC units will not be acceptable.

B. Low Ambient Lockout Control: Prevents cooling cycle operation below 55 deg F ambient outdoor temperature.

2.04 SOURCE QUALITY CONTROL

A. Sound-Power Level Ratings: Factory test to comply with AHRI 270, "Sound Rating of Outdoor Unitary Equipment."

B. Unit Performance Ratings: Factory test to comply with AHRI 310/380, "Packaged Terminal Air-Conditioners and Heat Pumps."

PART 3 EXECUTION 3.01 INSTALLATION

A. Install units according to manufacturer's written instructions.

B. Coordinate installation of wall sleeves in finished wall assembly; seal and weatherproof.

C. Install accessory Molding trim kit to hide any imperfections in wall around wall sleeve.

3.02 CONNECTIONS

A. Electrical: Connect units to wiring systems and to ground as indicated and instructed by manufacturer.

B. Ground equipment.

Page 104: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 81 13.13 (15735) - PACKAGED TERMINAL AIR-CONDITIONING UNITS ▪ ▪ PAGE 5 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. Where manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B.

3.03 CLEANING

A. After completing system installation, including outlet fittings and devices, inspect exposed finish. Remove burrs, dirt, and construction debris, and repair damaged finishes including chips, scratches, and abrasions.

3.04 COMMISSIONING

A. After installation, check the following:

1. Unit is level on base and is flashed in exterior wall.

2. Unit casing has no visible damage.

3. Compressor, air-cooled condenser coil, and fans have no visible damage.

4. Condenser are clean and free of construction debris.

5. Controls are connected and operable, cycle unit through hi/lo fan and heat/cool operation.

6. Shipping bolts, blocks, and tie-down straps are removed.

7. Return air and outdoor vent air filters are installed and clean.

8. Drain pan and slinger ring are functioning properly.

9. Effectively disable the temperature limiter stops.

B. Check fan-wheel rotation (evaporator and condenser) for correct direction without vibration and binding.

C. Start unit according to manufacturer's written instructions.

1. Complete manufacturer's startup checks.

D. After starting and performance test, clean filters.

3.05 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel.

1. Conduct training as specified in Section 01 79 00 "Training”.

2. Train Owner's maintenance personnel on procedures for starting and stopping troubleshooting, servicing, and maintaining equipment.

END OF SECTION

Page 105: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 82 39 (15767) - UNIT HEATERS ▪ ▪ PAGE 1 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

SECTION 23 82 39 (15767) - UNIT HEATERS

PART 1 GENERAL 1.01 SUMMARY

A. Section includes:

1. Electric Propeller Unit Heaters.

2. Electric Cabinet Unit Heaters.

3. Electric Wall Heaters.

B. Related Sections:

1. Section 23 05 00 (15050) – Common Work Results for HVAC

2. Section 23 08 00 – Commissioning of HVAC

3. Division 26 (16) Sections for electrical connections.

1.02 REFERENCES

A. National Fire Protection Association (NFPA) Publications:

1. 70 "National Electric Code"

2. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”

B. Underwriter's Laboratories, Inc. (UL) Standards:

1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper Conductors”

1.03 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01 Specification Sections.

B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating specified items selected for use in project with the following supporting data.

1. Product data for each type of product specified.

2. Wiring diagrams detailing power and control wiring and differentiating clearly between manufacturer-installed wiring and field-installed wiring.

3. Samples of cabinet finish colors for approval.

4. Qualification data for firms and persons specified in the "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of Owner’s Representatives and owners, and other information specified.

5. Field test reports from a qualified independent inspecting and testing agency indicating and interpreting test results relative to compliance with performance requirements of unit heaters.

1.04 QUALITY ASSURANCE

A. Manufacturer Qualifications: Firm experienced in manufacturing unit heaters similar to those indicated for this Project and that have a record of successful in-service performance.

B. Comply with NFPA 70 for components and installation.

C. Listing and Labeling: Provide products specified in this Section that are listed and labeled.

Page 106: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 82 39 (15767) - UNIT HEATERS ▪ ▪ PAGE 2 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

1. The Terms "Listed" and "Labeled": As defined in the National Electrical Code, Article 100.

PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Approved Manufacturers:

1. Indeeco (800-243-8162)

2. Emerson Electric Co. (314-553-2000)

3. QMark, Marley Engineered Products, An SPX Company (843-479-4006)

4. Markel Products Company (800-682-3398)

2.02 ELECTRIC PROPELLER UNIT HEATERS

A. Heating Elements: Nickel-chromium heating wire element; free from expansion noise and 60-Hz hum; embedded in magnesium oxide, insulating refractory; and sealed in high-mass steel or corrosion-resistant metallic sheath with fins no closer than 0.16 inch. Element ends are enclosed in terminal box. Fin surface temperature does not exceed 550 deg F at any point during normal operation.

B. Heater Circuit Protection: One-time fuses in terminal box for overcurrent protection and limit controls for overtemperature protection of heaters.

C. Fan and Motor: Direct-drive propeller fan and manufacturer's standard motor. Motors sized 1 hp and less include motor overload protection.

D. Wiring Terminations: Match conductor materials and sizes indicated.

E. Discharge Configuration: Horizontal discharge with horizontal, adjustable louvers.

F. Optional Accessories: Include the following:

1. Wall thermostat.

2. Safety-switch disconnect on cover of terminal box.

3. Mercury contactors.

4. Fan-delay relay.

2.03 ELECTRIC CABINET UNIT HEATERS

A. Description:

1. Semi-recessed, ceiling-mounted cabinet.

B. Heating Elements: Nickel-chromium heating wire element; free from expansion noise and 60-Hz hum; embedded in magnesium oxide, insulating refractory; and sealed in high-mass steel or corrosion-resistant metallic sheath with fins no closer than 0.16 inch (4 mm). Element ends are enclosed in terminal box. Fin surface temperature does not exceed 550 deg F (288 deg C) at any point during normal operation.

C. Heater Circuit Protection: One-time fuses in terminal box for over-current protection and limit controls for over-temperature protection of heaters.

D. Fan and Motor: Centrifugal blower, direct driven by a single-phase, 2-speed electric motor with inherent overload protection and resilient motor/fan mount.

E. Wiring Terminations: Match conductor materials and sizes indicated.

Page 107: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 82 39 (15767) - UNIT HEATERS ▪ ▪ PAGE 3 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

F. Unit Controls: Thermostat with remote wall mounted temperature sensor, fan-speed switch, fan ON-AUTOMATIC switch, and interval time.

G. Optional Accessories: Include the following:

1. Disconnect switch.

2. Mercury contactor.

3. Fan-delay relay.

H. Finish cabinet with manufacturer's standard enamel, color as selected by Owner’s Representative.

2.04 ELECTRIC WALL HEATERS:

A. General: Provide electric wall heaters with architectural styling for exposed or recessed application.

B. Heater Assembly: The heater assembly which fits into the back box shall consist of a fan panel upon which is mounted all of the operational parts of the heater.

C. Heating Element: The heating elements shall be of the non-glowing design consisting of a special resistance wire enclosed in a steel sheath to which steel plate fins are copper brazed. It shall be warranted for 5 years.

D. Fan and Motor: Fan shall be five bladed aluminum. Fan motor shall be totally enclosed.

E. Fan Delay Switch: Fan control shall be of bi-metallic, snap-action type and shall activate fan after heating element reaches operating temperature. The fan shall continue to operate after the thermostat is satisfied and until the heating element is cool.

F. Thermostat: The tamper-proof thermostat shall be of the bimetallic snap-action type with enclosed contacts. It shall be completely concealed and reactive behind the front cover to become tamper proof.

G. Thermal Cutout: A thermal cutout shall be built into the system to automatically shut off the heater in the event of overheating and reactivate the heater when temperatures return to normal.

H. Disconnect Switch: A double-pole, single throw disconnect switch shall be mounted on the back box for positive disconnect of power supply. It will be completely concealed behind the front grid panel.

I. Back Box: The back box shall be designed for duty as a recessed rough-in box in either masonry or frame installations, and is also used with the surface mounting box in surface mounted installations. The back box shall be 20 gage cold-rolled steel and shall contain knockouts through which power leads are brought.

J. Front Panel: The front panel shall be of the bar grille type and shall be constructed of 16 gage cold-rolled steel, welded into a uniform grille to direct the warmed air toward the floor. The front grille shall be surrounded by a decorative satin-finish aluminum “picture” frame.

K. Three Piece Design: The heater shall be made up of a back box, a heater assembly and a front panel. Provide surface mounting kit where indicated.

PART 3 EXECUTION 3.01 EXAMINATION

A. Examine substrates and supports to receive unit heaters for compliance with requirements for installation tolerances and other conditions affecting performance of units. Do not proceed with installation until unsatisfactory conditions have been corrected.

Page 108: FAIRFIELD INN & SUITES at The Highlands Town Center ... Mech... · 12 54 13.13 (12505) Hospitality Furniture Installation ... Gages for Plumbing Piping 22 ... for HVAC Piping and

▪ SECTION 23 82 39 (15767) - UNIT HEATERS ▪ ▪ PAGE 4 ▪

Fairfield Inn and Suites by Marriott at the Highlands Town Center November 7, 2014

3.02 INSTALLATION

A. Install heaters as indicated, according to manufacturer's written instructions and NFPA 90A.

B. Connect heaters and components to wiring systems and to ground as indicated and instructed by manufacturer. Tighten connectors and terminals, including screws and bolts, according to equipment manufacturer's published torque-tightening values for equipment connectors. Where manufacturer's torque requirements are not indicated, tighten connectors and terminals according to tightening requirements specified in UL 486A.

3.03 FIELD QUALITY CONTROL

A. Testing: After installing unit heaters and after electrical circuitry has been energized, demonstrate product capability and compliance with requirements.

B. Remove and replace malfunctioning units with new units and retest.

END OF SECTION