FAD-1 AcceptanceA Quick Overview of Optical Fiber and FAD(Fixed Asset Development)Prepared By : Mohammed Shoeb
FAD-1 Acceptance ……
TRANSMIT LIGHTS IN THE CORE LIGHTS TRAPPED IN THE CORE BY THE OPTICAL CLADDING BUFFER OR PRIMARY COATING PROTECTS FIBER FROM MOISTURE
OR DAMAGE MOST FIBERS ARE ALL GLASS, BUT SOME FIBERS HAVE A GLASS CORE
WITH PLASTIC CLADDING (PCS/HCS) OR ARE ALL PLASTIC (POF) CABLE PROTECT FIBERS IN THE APPLICATION ENVIRONMENT CONNECTORS: JOIN FIBERS OR CONNECT TO ACTIVE DEVICES SO
THEY CAN BE DISCONNECTED FOR REROUTING, TESTING, ETC. SPLICE: JOIN TWO FIBERS PERMANENTLY HARDWARE: PROVIDES THE MOUNTING, PROTECTION, ETC. FOR
CONNECTORS OR SPLICES TEST EQUIPMENT: CHECKS PERFORMANCE
AN OVERVIEW OF FIBER OPTICS
FAD-1 Acceptance ……
SPLICING: METHOD OF JOINING A FIBER CABLE IS KNOWN AS SPLICING.
TWO METHOD OF SPLICINGWE ARE USING (FUSION,MECHANICAL)
OTDR(OPTICAL TIME DOMAIN REFLECTOMETER):OTDR WORK FROM ONE END CREAT”SNAPSHOT” OF CABLE SEND OUT HIGH POWER SIGNAL GATHER BACKSCATTER LIGHT AVERAGES SIGNAL DISPLAY BACKSCATTER SIGNAL OVER TIME
POWER METER AND LASER: TRANSMITTER OUTPUR, RECIVER INPUT, REFRENCES FOR LOSS MEASURMENT
PARAMETER’S OF FIBER OPTICS
FAD-1 Acceptance ……
FAD ARCHITECTURE
FTTC FTTE FTTM ROAD
FTTX Topology GPON(Gigabit Passive Optical Network) Data rates up to 2.5 Gb/s Wavelength: 1- Upstream 1310 nm(Voice and Data) 2- Downstream 1490 nm(Voice and Data) 3- 1550 nm (TV)
FAD-1 Acceptance ……
THERE ARE TWO TYPES OF WORK CIVIL
• JOINT BOXES(JOINT REINFORCE CONCRETE)
1. JRC 4/ JRC 10 WITH 1-COVER (1.2M*0.78M*1.02M)
2. JRC12 WITH 4-COVER (1.73M*1.24M*1.34M)
3. JRC14 WITH 6-COVER (2.58M*1.28M*1.4M)
4. MRT• MR-1,MR-2,MR-4 AND MR-86. EB(ENTRY BOX)
TYPES OF WORK
FAD-1 Acceptance ……
JRC 4/ JRC 10 with 1-COVER (1.2m*0.78m*1.02m) JRC12 with 4-COVER (1.73m*1.24m*1.34m)
JRC14 With 6-COVER (2.58m*1.28m*1.4m) MRT
FAD-1 Acceptance ……
• BTMG(Brake through and make good) • TRENCH
FAD-1 Acceptance ……
• DUCTS(D54-D56) FDH O/D(FIBER DISTRIBUTION HUB
FAD-1 Acceptance ……
• CABLE
EXPRESS CABLE: THIS TYPES OF CABLE ARE USING FOR LONG DISTANCE SUCH AS IN BETWEEN TWO EXCHANGES (200F)
DISTRIBUTION CABLE: THIS TYPES OF CABLE ARE USING FOR SHORT DISTANCE SUCH AS IN BETWEEN TWO JOINTS (24F)
FAD-1 Acceptance ……
DROP FIBER CABLE: SINGLE FIBER /THIS TYPES OF CABLE ARE USED AT CUSTOMER END OR PREMISES
JOINT ENCLOSURE: THIS TECHNIQUE ARE USING TO PROTECT TWO FIBRE JOINTS THERE ARE DIFFERENT TYPES OF JOINTS SUCH AS (100F,200F AND DROP FIBER JEC
FAD-1 Acceptance ……
FDH(FIBER DISTRIBUTION HUB):
UNDER GROUND FDH: THIS TECHNIQUE IS VERY POPULAR AND LATEST,KEEPING THE FDH INSIDE JRC
INDOOR OR WALL MOUNT FDH: I/D FDH CAN INSTALL INSIDE BUILDING OR CUSTOMER END TO PROVIDE CONNECTIVITY
FAD-1 Acceptance ……
NECESSITY DOCUMENT RELATED TO ACCEPTANCE
1. UJ/UC As-Built diagram2. Scheme Plan As-Built for Civil Work Projects3. DSR As-Built (ONLY FOR CABLE)4. Circulation mail to R&R 5. CPN by R&R in case of Splitter6. PM/LS Test result7. OTDR Test Result in excel8. OTDR Test Results in .sor format9. Store Check List10. SIV/MRN OR Material Transaction Report if applicable.11. LOI/Work Order from PCC12. RFS
13. CCC (Cable Completion Certificate)14. PCC ( Project Completion Certificate) 15. FAC (Final Acceptance Certificate)16. Signed Diary Sheet17. Summary of Diary Sheet18. Invoice19. Partner's Letter for Invoice20. Certificate of Contract Completion 21. Covering letter for Certificate of Contract
Completion to Director/Payable(Projects)22. Certificate of Invoice for Payment/GIS
UPLAODED
FAD-1 Acceptance ……
• FOLLOWING ACCEPTACE DOCUMENTS:
FOR CABLE: UC/UJ DIAGRAM OTDR TEST INSERTION LOSS TEST FOR CIVIL : LAB TEST AND MUNCIPALITY CERTIFICATE AS BUILD DIAGRAM