FacilityMAX Project Certification Close-Out

8
FacilityMAX Project Certification Close-Out General Services Department Building Services Division Property Control Division October 28, 2009 Presented to: Project Certification Committee

description

October 28, 2009 Presented to: Project Certification Committee. FacilityMAX Project Certification Close-Out. General Services Department Building Services Division Property Control Division. FacilityMAX Costs. Current Status: Project Close Out All deliverables have been satisfied - PowerPoint PPT Presentation

Transcript of FacilityMAX Project Certification Close-Out

Page 1: FacilityMAX Project Certification Close-Out

FacilityMAXProject Certification Close-Out

General Services Department

Building Services Division

Property Control Division

October 28, 2009

Presented to:

Project Certification Committee

Page 2: FacilityMAX Project Certification Close-Out

FacilityMAX Costs

• Current Status: Project Close Out– All deliverables have been satisfied– IV&V has been completed– System is in production and is being utilized by both

Divisions• Expenditures to Date: $729,521.13 • Funding Sources:

– BSD General Fund– PCD Project Admin

• Recurring Costs:– Annual Maintenance: $52,000

Page 3: FacilityMAX Project Certification Close-Out

Justification, Objectives and Impacts

Source: Asset Lifecycle Model for Total Cost of Ownership Management

Core Working Group: APPA, Federal Facilities Council, Holder Construction, IFMA, NASFA.

Page 4: FacilityMAX Project Certification Close-Out

Project Goals/Objectives• Enhance GSD’s ability to better manage operation, performance and life

cycle of equipment and facilities • Improve and automate the work flow processes• Eliminate separate automated and manual systems and processes to

improve operating efficiencies• Leverage FMax’s features to track key operational performance measures• Improve work management processes - building maintenance, custodial

services, project management, and leasing• Move agencies from leased space to State owned Campus Settings, with

leased and owned facilities and land in one integrated system.• Reduce energy costs by facilitating improved data flow and management on

energy consumption in state buildings.• Implement an Integrated Facilities Management System, retiring an old end

of life system – reduce system support costs– provide system failover– provide higher levels of security– provide a central data repository

Page 5: FacilityMAX Project Certification Close-Out

Project Accomplishments

• Successfully implemented all modules in original scope • Little to no customization required • System is in production and is being utilized• Successfully completed all project requirements• Project was under budget• Project was within project schedule• Benefit to Agency/Stakeholders.

– Reduction in manual processing– Capability of interfacing to SHARE for the purpose of performing a cross check

against the SHARE accounting system, for financial information.  – Provides ability to now track dates on the different phases and timeline of an

architect contract. i.e., how long did it takes for the architect to do the programming phase, schematic phase, design development phase, etc.

– Central data repository for building inventory, property, deeds and leasing information. Eliminates stand alone data bases for this information.

– Scanned project and property documents, such as contacts, deeds, etc., are now being placed into the FM central repository.

Page 6: FacilityMAX Project Certification Close-Out

Business Performance Measures

Phase Complete Objective/Goal CostInitiation June 2006 Purchase FacilityMAX

software/hardware. Install hardware

$333.6

Planning April 2007 Define schedule, budget, resource requirements, staffing to support system, develop as-is and to-be work process flows, define data elements and fields, install software

$129.2

Implementation May 2008 Complete software installation, set up database and input data, train end users and sys admin, test, user acceptance conduct IV&V

$266.7

Close Out June 2009 IV & V Final Report, Transition to Operations, Maintenance,

Implement Redundant DB server

$-0-

Total Costs $729.5

Page 7: FacilityMAX Project Certification Close-Out

Lessons Learned• The IV & V reports documented several recommendations. These

recommendations will serve as the basis to insure that FacilityMAX remains useful for years to come.

• The Building Services Division will likely require another “Workflow Specialist” in order to keep up with Time Card Entry, Work Order Creation and Equipment Inventory. Currently Building Services Division has two FTE dedicated to this issue with one vacant position.

• Additional expertise will be required to develop BIRT reports in order to fully utilize data in FacilityMAX.

• Upfront training and identifying and documenting custom report requirements for quicker implementation is required

• Higher levels of attention must be paid to developing training documentation and requirements

• User Satisfaction Survey activities should become a separate section in project schedules

• Train System Administration and end users on Security Policy and Procedures

Page 8: FacilityMAX Project Certification Close-Out

Approval of Close Out

• Requesting approval to close the FacilityMax Project out

• Questions?