Harlan High School Facilities Construction N N O O R R T T H H S S I I D D E E I I N N D D E E P P E E N N D D E E N N T T S S C C H H O O O O L L D D I I S S T T R R I I C C T T Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION January 2016

Transcript of Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities...

Page 1: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

Harlan High School

Facilities Construction

NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT

Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS

Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION

January 2016

Page 2: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field
Page 3: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2010 BOND SAVINGS

PROJECTS

Page 4: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)

Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Chris Parker Contractor – Bartlett Cocke General Contractor Construction Amount - $25,371,707.00 (2010 Bond Savings) Construction Period – April 2015 – June 30, 2016 (53% Complete) Project Scope – New 800 Student Elementary School

Concrete superstructure, MEP rough-in, permanent power installation, masonry, structural steel, decking and drywall framing in progress.

Page 5: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 7, 2015)

Page 6: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)

Page 7: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 11, 2016)

Page 8: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)(Dec. 29, 2015)

Page 9: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BENNIE L. COLE ELEMENTARY SCHOOL (Future Library) (Dec. 29, 2015)

Page 10: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke General Contractor Contract Amount – $26,326,724.00 (2010 Bond Savings) Construction Period – May 2015 – October 2016 (23% Complete) Project Scope – Provide a District-Wide Sports Gymansium at the Farris

Complex. Site work, electrical and plumbing rough-ins in progress. Concrete foundation and columns being placed. Precast concrete seating being installed.

Page 11: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM Aerial View (December 17, 2015)

Page 12: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM – Entry Perspective View

Page 13: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM – Plaza Perspective View

Page 14: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM (January 11, 2016)

Page 15: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM – Seating Perspective View

Page 16: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE SPORTS GYM (January 11, 2016)

Page 17: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2014 BOND PROJECTS

Page 18: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 (54% Complete) Project Scope – New 2800 Student High School

Notice to Proceed issued October 8, 2014. Site Construction began October 14, 2014. Site grading, 1st,2nd and 3rd Floor framing and columns in progress. Underground utilities and Interior CMU walls, drywall framing, electrical, plumbing, and HVAC rough-in in progress. Roof steel erection, roof deck roofing and window installation in progress. Interior painting in progress. Exterior brick veneer in progress.

Page 19: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Dec. 22, 2015)

Page 20: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

Page 21: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (Jan. 11, 2016)

Page 22: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARLAN HIGH SCHOOL (CONNECTION BETWEEN MAIN BUILDING and GYMS) (Jan. 11, 2016)

Page 23: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field
Page 24: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3)

Architect – O’Neill Conrad Oppelt Project Architect – Mark Oppelt NISD Project Manager – Marilyn Sevedge Contractor – Joeris General Contractor Contract Amount - $24,615,127.00 Construction Period – April 2015 – June 30, 2016 (49% Complete) Project Scope – New 800 Student Elementary School

Steel superstructure and masonry in progress. Plumbing, electrical and mechanical rough-ins in progress, site drainage. Window install in progress. Exterior damp roofing, insulation in progress. Brick starting.

Page 25: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Aerial (Dec. 22, 2015)

Page 26: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Front Entry

Page 27: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) (Jan. 11, 2016)

Page 28: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ADDITIONS AND RENOVATIONS

PROJECTS IN PROGRESS

Page 29: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)

Consultant – Combs Consulting Group NISD Project Manager – Charles Pereira Contractor – Convergint Technologies Construction Contract Award – $13,422,826.29 Total Change Orders to Date - $661,683.79 Adjusted Construction Contract Amount - $14,084,510.08 Total Construction Contract Completed - $13,787,503.30 Balance to Finish Construction Contract - $297,006.78 Notice to Proceed – January 23, 2013 Original Construction Completion – May 31, 2014 Revised Construction Completion – November 11, 2015 Contract Percentage Completion – 98%

Page 30: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ELEMENTARY SCHOOL ISMS – (Integrated Security Mgmt System)

Project Scope – Furnish and install all new interior and exterior security

surveillance cameras, with access control electrified hardware and security alarm disarm keypads. Connect and integrate the existing intrusion alarm devices, motion sensors and glass break sensors at all existing campuses.

75 Elementary School Campuses have Substantial Completion Certificates. 2 Additional Middle School Campuses have Substantial Completion

Certificates. 75 Elementary School Campuses have ISMS software training completed. 2 Additional Middle School Campuses have ISMS software training

completed. 75 Elementary campuses have Post Warranty Documents completed. 2 Additional Middle school campuses have Post Warranty Documents

completed.

Page 31: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field
Page 32: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – D.L. Bandy Contract Amount - $4,782,000.00 Construction Period – May 15, 2015 – August 1, 2016 (46% Complete) Project Scope – New Science Classroom Addition and Renovation.

Site work and underground site utilities in progress. Exterior and interior CMU walls completed. Plumbing, electrical and HVAC rough-in in progress. Window install in progress. Brick veneer in progress. Interior painting in progress.

Page 33: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Perspective)

Page 34: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Front Entry – Final Scheme)

Page 35: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (1st Floor Plan)

Page 36: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (2nd Floor Plan)

Page 37: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (January 8, 2016)

Page 38: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – Guido Brothers Construction Contract Amount - $3,198,000.00 Construction Period – June 2015 – June 2016 (32% Complete) Project Scope – New Classroom Addition

Pilot holes drilled for addition foundation. Piers are completed. Plumbing rough-in underway. Foundation columns completed.

Page 39: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Site Plan)

Page 40: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION (1st Floor Plan)

Page 41: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION (2nd Floor Plan)

Page 42: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Elevation)

Page 43: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LUNA MIDDLE SCHOOL CLASSROOM ADDITION (January 11, 2016)

Page 44: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2014 BOND PROJECTS

IN

BID/DESIGN PHASES

Page 45: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field
Page 46: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

KALLISON RANCH #2 ES (ELLISON ES PROTOTYPE)

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction Construction Budget - $22,500,000.00 Tentative Construction Period – May 7, 2016 – May 26, 2017 Project Scope – Construction of an 800 Student Elementary School

Page 47: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

KALLISON RANCH #2 ES - (Ellison ES Prototype) Front Entrance

Page 48: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

CHILD NUTRITION WAREHOUSE - Warehouse Renovation

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,000,000.00 Tentative Construction Period – April 4, 2016 – October, 2016 Project Scope – Warehouse Renovation

Page 49: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)

Page 50: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $6,230,000.00 Tentative Construction Period – March 7, 2016 – November 7, 2016 Project Scope – Classroom Addition/ADA/Window Upgrades

Proposals in progress.

Page 51: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ALLEN ES CLASSROOM - (Rendering of Site and Floor Plans)

Page 52: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ALLEN ES CLASSROOM - (Rendering of Floor Plan, Elevation and Perspectives)

Page 53: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HOLMES HS FINE ARTS - UPGRADE

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – James Berg Contractor – TBD Construction Budget - $14,000,000.00 Tentative Construction Period – TBD Project Scope – Fine Arts Building Replacement

Page 54: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

THORNTON ES - MUSIC ROOM ADDITION

Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – James Berg Contractor – TBD Construction Budget - $300,000.00 Tentative Construction Period – June 6, 2016 – August 5, 2016 Project Scope – Music Room Addition

Page 55: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

THORNTON ES - MUSIC ROOM ADDITION (Rendering of Site Plan)

Page 56: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

THORNTON ES - MUSIC ROOM ADDITION (Rendering of Music Room Addition)

Page 57: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ZACHRY MS BUS CANOPY MODIFICATIONS

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – February 8, 2016 – July 1, 2016 Project Scope – Proposal Evaluations in Progress

Board approval recommendation scheduled for January.

Page 58: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ALE Upgrades at CLARK HS, JAY HS & PEASE MS & ESPARZA ES – Library Addition

Architect – O’Connell Robertson Project Architect – Chris Narendorf NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,125,000.00 and $880,000.00 Tentative Construction Period – March 4, 2016 – August 5, 2016 Project Scope – Upgrades of Existing ALE Classrooms and

Library Addition for Esparza ES Bid Drawings To Be Issued in January.

Page 59: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

GLENOAKS ELEMENTARY - Administration Upgrades

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,750,000.00 Tentative Construction Period – March 14, 2016 – March 3, 2017 Project Scope – Administration Upgrades

Page 60: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

GLENOAKS ELEMENTARY - (Rendering of Front Elevation)

Page 61: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

CODY ES & LEON VALLEY ELEMENTARY - (CAFE & KITCHEN RENOVATIONS)

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget - $3,500,000.00 Tentative Construction Period – February 15, 2016 – August 8, 2016 Project Scope – Renovations to Cafeteria and Kitchen

Proposals in Progress.

Page 62: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2016 SECURITY LOBBIES - LOCKE HILL ES, THORNTON ES, CARLOS COON ES, LEON VALLEY ES, POWELL ES, MICHAEL ES, MARY HULL ES AND CABLE ES

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $480,000.00 Tentative Construction Period – February 1, 2016 – August 1, 2016 Project Scope – New Security Lobby for (10) Elementary Schools

Page 63: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

NORTHSIDE ACTIVITY CENTER RENOVATIONS

Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - TBD Tentative Construction Period – April 4, 2016 – March 1, 2017 Project Scope – Addition

Program Phase

Page 64: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

PAUL TAYLOR FIELD HOUSE RENOVATIONS

Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - TBD Tentative Construction Period – April 2016 – November 2016 Project Scope – ADA Interior/Exterior Renovations

Schematic Design Phase

Page 65: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field
Page 66: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2016 GROWTH & IMPROVEMENT

Page 67: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HARDIN SOCCER COMPLEX - UPGRADES

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - TBD Tentative Construction Period – February 1, 2016 – July 5, 2016 Project Scope – Replacement of existing ticket collection, concessions

and officials trailer with a building. Contractor evaluation complete. Board approval recommendation scheduled for January.

Page 68: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2016 ATHLETIC AREA UPGRADES (JAY HS, CLARK HS, JONES MS & ROSS MS)

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - TBD Tentative Construction Period – May 30, 2016 – August 8, 2016 Project Scope – Installation of Athletic Storage Units and Interior

Renovations. Site Verifications in progress. CDs in progress.

Page 69: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

2016 CTE RENOVATIONS - (CLARK HS HOLMES HS, & TAFT HS)

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Jim Berg Contractor – TBD Construction Period – TBD Tentative Construction Period – May 2, 2016 – August 12, 2016 Project Scope – Renovations to Cosmetology at Holmes and Taft, Health

Science Technology at Clark, Residential Kitchen at Clark and Engineering Lab at Taft HS.

Page 70: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ROOFING PROJECTS

Page 71: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

BOONE ELEMENTARY SCHOOL – ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – TBD Budget – $365,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing

Page 72: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

CABLE ELEMENTARY SCHOOL – ROOFING PROJECT

Roofing Consultant – Austech Engineering Contractor – TBD Budget – $160,000.00 Construction Period – June – August 2016 Project Scope – Roof Repairs & Waterproofing

Page 73: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

HOWSMAN ELEMENTARY SCHOOL – ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – TBD Budget – $740,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing

Page 74: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

ANSON JONES MIDDLE SCHOOL – ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $165,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing

65% Review

Page 75: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LEWIS ELEMENTARY SCHOOL - ROOFING PROJECT

Roofing Consultant – Austech Contractor – TBD Budget – $200,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing

Page 76: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

LINTON ELEMENTARY SCHOOL - ROOFING PROJECT

Roofing Consultant – Raba Kistner Contractor – TBD Budget – $180,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing

Page 77: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

MARY HULL ELEMENTARY SCHOOL – ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $70,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing

65% Review

Page 78: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

MAY ELEMENTARY SCHOOL - ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $2,175,000.00 Construction Period – June – October 2016 Project Scope – Roof Replacement & Waterproofing

Board Approval Scheduled for January 19, 2016

Page 79: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

TAFT HIGH SCHOOL – ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $1,885,000.00 Construction Period – June – December 2016 Project Scope – Roof Replacement & Waterproofing

Board Approval Scheduled for January 19, 2016

Page 80: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

PAUL TAYLOR FIELD HOUSE – ROOFING PROJECT

Roofing Consultant – Hollon + Cannon Contractor – TBD Budget – $525,000.00 Construction Period – June – August 2016 Project Scope – Roof Replacement & Waterproofing

Board Approval Scheduled for January 19, 2016

Page 81: Facilities Construction - Home | Northside Independent ... · PDF filedirector of facilities construction january 2016. 2010 bond savings ... kallison ranch #2 es ... paul taylor field

VILLARREAL ELEMENTARY SCHOOL – ROOFING PROJECT

Roofing Consultant – Austech Contractor – TBD Budget – $110,000.00 Construction Period – June – August 2016 Project Scope – Roof Repair & Waterproofing