F Control and Monitoring MottMacDonald
Transcript of F Control and Monitoring MottMacDonald
Grange BackUp Power Industrial Emissions Licence Review Application
77
F.1 Treatment, Abatement and Control Systems
F.1.1 Atmospheric Emissions Treatment, Abatement and Control
A comprehensive air emission impact assessment was prepared for this power plant as part of the
Environment Impact Statement submitted with the planning application to South Dublin County Council. This
Environmental Report is included in Attachment B.6 of this licence application.
Natural gas is a clean fuel resulting in negligible emissions of particulate matter and Sulphur Dioxide (SO2).
The main atmospheric pollutant of concern for the power plant firing on natural gas is Nitrogen Oxide (NOx).
The plant will comprise proven pollution prevention and control technology which will limit the emission of
NOx i.e. the Selective Catalytic Reduction (SCR) technique. In the SCR system the NOX is reduced with the
help of a reducing agent such as urea which will be stored on-site in 2 no. dedicated tanks, each with a
volume of 177m³. It is not proposed to use SCR when operating on its secondary fuel, distillate oil. EirGrid’s
Grid Code states that power plants must have a primary and secondary fuel (as a back-up). However
operation on the secondary fuel would only be required in very extreme circumstances such as in the event
of an interruption to gas supplies. For a plant such as Grange Power, the Operator might test a couple of
times a year on the secondary fuel. Each test might run for an hour or less. As such, it would be expected
that for testing purposes the power plant would not operate more than 18 hours per annum, and probably
less. To allow for SCR to be used when operating on its secondary fuel would mean larger and more
expensive SCR units would need to be employed on the two exhaust stacks proposed at Grange. In financial
terms the use of SCR is the most expensive control abatement technology for NOx control. Given the
expected operating hours on the secondary fuel the provision of SCR abatement is not considered BAT.
The engine stacks (A2-1, A2-2) will incorporate an in-situ proprietary Continuous Emission Monitoring
System (CEMS). The selection, installation, calibration, ongoing quality assurance and annual surveillance
testing of the CEMS will be undertaken in accordance with EN 14181 – Quality Assurance of Automated
Measuring Systems and all relevant standards referred to therein. The requirements of EN 14181 will be
incorporated into the planned preventive maintenance programme (PPMP).
The number of potential sources of leaks from the plant will be minimised through plant design, for example
the gas pipe will be welded thereby avoiding the use of flanges and valves wherever possible. Where
appropriate, valves and flanges will be fitted with leak detection alarms connected to the main control room
ensuring a rapid response in the event of an abnormal occurrence.
The plant will only operate on low sulphur distillate oil in emergency situations and for short duration testing
as required by the Commission for Energy Regulation (CER) and EirGrid. In accordance with the CER
Decision Paper Secondary Fuel Obligations on Licensed Generation Capacity in the Republic of Ireland
(2009) it is anticipated that approximately 2895m³ of low sulphur distillate oil will be stored on site in a bunded
vertical cylindrical steel tank. Tank loading and unloading will be undertaken in accordance with standard
operating procedures, manufacturer’s specifications and best practice guidelines, including IPC Guidance
Note on Storage and Transfer of Materials for Scheduled Activities, EPA (2004). Losses will be minimised
through effective site management techniques and training.
F Control and Monitoring
Grange BackUp Power Industrial Emissions Licence Review Application
77
F.1 Treatment, Abatement and Control Systems
F.1.1 Atmospheric Emissions Treatment, Abatement and Control
A comprehensive air emission impact assessment was prepared for this power plant as part of the
Environment Impact Statement submitted with the planning application to South Dublin County Council. This
Environmental Report is included in Attachment B.6 of this licence application.
Natural gas is a clean fuel resulting in negligible emissions of particulate matter and Sulphur Dioxide (SO2).
The main atmospheric pollutant of concern for the power plant firing on natural gas is Nitrogen Oxide (NOx).
The plant will comprise proven pollution prevention and control technology which will limit the emission of
NOx i.e. the Selective Catalytic Reduction (SCR) technique. In the SCR system the NOX is reduced with the
help of a reducing agent such as urea which will be stored on-site in 2 no. dedicated tanks, each with a
volume of 177m³. It is not proposed to use SCR when operating on its secondary fuel, distillate oil. EirGrid’s
Grid Code states that power plants must have a primary and secondary fuel (as a back-up). However
operation on the secondary fuel would only be required in very extreme circumstances such as in the event
of an interruption to gas supplies. For a plant such as Grange Power, the Operator might test a couple of
times a year on the secondary fuel. Each test might run for an hour or less. As such, it would be expected
that for testing purposes the power plant would not operate more than 18 hours per annum, and probably
less. To allow for SCR to be used when operating on its secondary fuel would mean larger and more
expensive SCR units would need to be employed on the two exhaust stacks proposed at Grange. In financial
terms the use of SCR is the most expensive control abatement technology for NOx control. Given the
expected operating hours on the secondary fuel the provision of SCR abatement is not considered BAT.
The engine stacks (A2-1, A2-2) will incorporate an in-situ proprietary Continuous Emission Monitoring
System (CEMS). The selection, installation, calibration, ongoing quality assurance and annual surveillance
testing of the CEMS will be undertaken in accordance with EN 14181 – Quality Assurance of Automated
Measuring Systems and all relevant standards referred to therein. The requirements of EN 14181 will be
incorporated into the planned preventive maintenance programme (PPMP).
The number of potential sources of leaks from the plant will be minimised through plant design, for example
the gas pipe will be welded thereby avoiding the use of flanges and valves wherever possible. Where
appropriate, valves and flanges will be fitted with leak detection alarms connected to the main control room
ensuring a rapid response in the event of an abnormal occurrence.
The plant will only operate on low sulphur distillate oil in emergency situations and for short duration testing
as required by the Commission for Energy Regulation (CER) and EirGrid. In accordance with the CER
Decision Paper Secondary Fuel Obligations on Licensed Generation Capacity in the Republic of Ireland
(2009) it is anticipated that approximately 2895m³ of low sulphur distillate oil will be stored on site in a bunded
vertical cylindrical steel tank. Tank loading and unloading will be undertaken in accordance with standard
operating procedures, manufacturer’s specifications and best practice guidelines, including IPC Guidance
Note on Storage and Transfer of Materials for Scheduled Activities, EPA (2004). Losses will be minimised
through effective site management techniques and training.
F Control and Monitoring
Grange BackUp PowerMott MacDonald
F.1 Treatment, Abatement and Control Systems
F.1.1 Atmospheric Emissions Treatment, Abatement and Control
A comprehensive air emission impact assessment was prepared for this power plant as part of theEnvironment Impact Statement submitted with the planning application to South Dublin County Council. ThisEnvironmental Report is included in Attachment 8.6 of this licence application.
Natural gas is a clean fuel resulting in negligible emissions of particulate matter and Sulphur Dioxide (802).The main atmospheric pollutant of concern for the power plant firing on natural gas is Nitrogen Oxide (NOX).The plant will comprise proven pollution prevention and control technology which will limit the emission ofNOx i.e. the Selective Catalytic Reduction (SCR) technique. In the SCR system the NOx is reduced with thehelp of a reducing agent such as urea which will be stored on-site in 2 no. dedicated tanks, each with avolume of 177m3. It is not proposed to use SCR when operating on its secondary fuel, distillate oil. EirGrid’sGrid Code states that power plants must have a primary and secondary fuel (as a back-up). Howeveroperation on the secondary fuel would only be required in very extreme circumstances such as in the eventof an interruption to gas supplies. For a plant such as Grange Power, the Operator might test a couple oftimes a year on the secondary fuel. Each test might run for an hour or less. As such, it would be expectedthat for testing purposes the power plant would not operate more than 18 hours per annum, and probablyless. To allow for SCR to be used when operating on its secondary fuel would mean larger and moreexpensive SCR units would need to be employed on the two exhaust stacks proposed at Grange. In financialterms the use of SCR is the most expensive control abatement technology for NOx control. Given theexpected operating hours on the secondary fuel the provision of SCR abatement is not considered BAT.
The engine stacks (A2—1, A2—2) will incorporate an in-situ proprietary Continuous Emission MonitoringSystem (CEMS). The selection, installation, calibration, ongoing quality assurance and annual surveillancetesting of the CEMS will be undertaken in accordance with EN 14181 — Quality Assurance of AutomatedMeasuring Systems and all relevant standards referred to therein. The requirements of EN 14181 will beincorporated into the planned preventive maintenance programme (PPMP).
The number of potential sources of leaks from the plant will be minimised through plant design, for examplethe gas pipe will be welded thereby avoiding the use of flanges and valves wherever possible. Whereappropriate, valves and flanges will be fitted with leak detection alarms connected to the main control roomensuring a rapid response in the event of an abnormal occurrence.
The plant will only operate on low sulphur distillate oil in emergency situations and for short duration testingas required by the Commission for Energy Regulation (CER) and EirGrid. In accordance with the CERDecision Paper Secondary Fuel Obligations on Licensed Generation Capacity in the Republic of Ireland(2009) it is anticipated that approximately 2895m3 of low sulphur distillate oil will be stored on site in a bundedvertical cylindrical steel tank. Tank loading and unloading will be undertaken in accordance with standardoperating procedures, manufacturer’s specifications and best practice guidelines, including IPC GuidanceNote on Storage and Transfer of Materials for Scheduled Activities, EPA (2004). Losses will be minimisedthrough effective site management techniques and training.
77
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
Grange BackUp Power Industrial Emissions Licence Review Application
78
Grange BackUp Power Limited will enter into a Long Term Services Agreement (LTSA) with the supplier to
service the gas engine and main auxiliaries at pre-determined intervals. The PPMP will also be developed,
in accordance with manufacturer’s specifications, incorporating all abatement and control systems as well
as plant, pipes, valves and flanges with a potential atmospheric emission source as deemed appropriate.
All defects will be prioritised. Defects associated with health and safety and environmental equipment will
be given highest priority and action will be taken immediately.
The total electricity output will be 96 MW during optimum conditions reaching thermal efficiencies in excess
of approximately 47%, which is higher than any other gas engine available on the market. The high rate of
thermal efficiency, and subsequent reduction in greenhouse gases, is in accordance with the requirements
of BAT. Operation of the power plant will incorporate the following measures in order to ensure thermal
efficiency:
� The plant will operate on an advanced computerised control system which will ensure optimum
combustion conditions that support the reduction of emissions;
� Natural gas and feedwater will be filtered before use;
� The plant design will minimise the amount of heat lost due to unburned gases and excess air;
� The plant will operate under optimum pressure and temperature conditions whenever possible. The
plant design will employ the use of advanced materials capable of reaching the levels required;
� Inlet air will be fitted with a self-cleaning fabric filter in order to prevent the ingress of particulate matter.
� Operation of the plant will include maintenance measures such as raw water pre-treatment and chemical
treatment of the cooling water thereby optimising efficiency and minimising energy consumption.
During a start-up or shut down of the power plant, the engine will ramp up or decrease its stable operational
load. This period is expected to be approximately 10 minutes in total for both scenarios. During these periods
the volume of exhaust gas exiting the exhaust stack will be reduced and its temperature will be lower
compared to standard operating levels. In addition, as an engine starts up, higher emission concentrations
of NOx and CO can be emitted.
When exhaust gas volumes and temperatures are reduced during start up and shut down the exit velocity of
the exhaust gas and its thermal buoyancy from the tip of the stack are reduced compared to normal operation
which can reduce the effectiveness of dispersion from the stack. However, as the primary fuel for the project
is natural gas the main pollutant of concern is NOx which has air quality standards for 1 hour and annual
mean averaging periods. Given the short period of time when start up and shut down occurs the changes in
dispersion characteristics and emission concentrations would have negligible effects on the predicted level
of impacts presented averaged over a 1 hour an annual mean periods and are therefore start-ups and shut
downs are not considered to have a significant effect on air quality.
The power plant will operate in accordance with the requirements of Directive 2010/75/EU on industrial
emissions (the Industrial Emissions Directive) and the BAT Guidance Note on Best Available Techniques for
the Energy Sector (Large Combustion Plant Sector), EPA, 2008. In addition, the plant will operate in
accordance with the relevant air quality standards and relevant emission limit values as specified in Section
50 and Section 51 respectively of the Air Pollution Act 1987. Furthermore the plant will operate in accordance
Grange BackUp Power Industrial Emissions Licence Review Application
78
Grange BackUp Power Limited will enter into a Long Term Services Agreement (LTSA) with the supplier to
service the gas engine and main auxiliaries at pre-determined intervals. The PPMP will also be developed,
in accordance with manufacturer’s specifications, incorporating all abatement and control systems as well
as plant, pipes, valves and flanges with a potential atmospheric emission source as deemed appropriate.
All defects will be prioritised. Defects associated with health and safety and environmental equipment will
be given highest priority and action will be taken immediately.
The total electricity output will be 96 MW during optimum conditions reaching thermal efficiencies in excess
of approximately 47%, which is higher than any other gas engine available on the market. The high rate of
thermal efficiency, and subsequent reduction in greenhouse gases, is in accordance with the requirements
of BAT. Operation of the power plant will incorporate the following measures in order to ensure thermal
efficiency:
� The plant will operate on an advanced computerised control system which will ensure optimum
combustion conditions that support the reduction of emissions;
� Natural gas and feedwater will be filtered before use;
� The plant design will minimise the amount of heat lost due to unburned gases and excess air;
� The plant will operate under optimum pressure and temperature conditions whenever possible. The
plant design will employ the use of advanced materials capable of reaching the levels required;
� Inlet air will be fitted with a self-cleaning fabric filter in order to prevent the ingress of particulate matter.
� Operation of the plant will include maintenance measures such as raw water pre-treatment and chemical
treatment of the cooling water thereby optimising efficiency and minimising energy consumption.
During a start-up or shut down of the power plant, the engine will ramp up or decrease its stable operational
load. This period is expected to be approximately 10 minutes in total for both scenarios. During these periods
the volume of exhaust gas exiting the exhaust stack will be reduced and its temperature will be lower
compared to standard operating levels. In addition, as an engine starts up, higher emission concentrations
of NOx and CO can be emitted.
When exhaust gas volumes and temperatures are reduced during start up and shut down the exit velocity of
the exhaust gas and its thermal buoyancy from the tip of the stack are reduced compared to normal operation
which can reduce the effectiveness of dispersion from the stack. However, as the primary fuel for the project
is natural gas the main pollutant of concern is NOx which has air quality standards for 1 hour and annual
mean averaging periods. Given the short period of time when start up and shut down occurs the changes in
dispersion characteristics and emission concentrations would have negligible effects on the predicted level
of impacts presented averaged over a 1 hour an annual mean periods and are therefore start-ups and shut
downs are not considered to have a significant effect on air quality.
The power plant will operate in accordance with the requirements of Directive 2010/75/EU on industrial
emissions (the Industrial Emissions Directive) and the BAT Guidance Note on Best Available Techniques for
the Energy Sector (Large Combustion Plant Sector), EPA, 2008. In addition, the plant will operate in
accordance with the relevant air quality standards and relevant emission limit values as specified in Section
50 and Section 51 respectively of the Air Pollution Act 1987. Furthermore the plant will operate in accordance
Grange BackUp PowerMott MacDonald
Grange BackUp Power Limited will enter into a Long Term Services Agreement (LTSA) with the supplier toservice the gas engine and main auxiliaries at pre-determined intervals. The PPMP will also be developed,in accordance with manufacturer’s specifications, incorporating all abatement and control systems as wellas plant, pipes, valves and flanges with a potential atmospheric emission source as deemed appropriate.All defects will be prioritised. Defects associated with health and safety and environmental equipment willbe given highest priority and action will be taken immediately.
The total electricity output will be 96 MW during optimum conditions reaching thermal efficiencies in excessof approximately 47%, which is higher than any other gas engine available on the market. The high rate ofthermal efficiency, and subsequent reduction in greenhouse gases, is in accordance with the requirementsof BAT. Operation of the power plant will incorporate the following measures in order to ensure thermalefficiency:
The plant will operate on an advanced computerised control system which will ensure optimumcombustion conditions that support the reduction of emissions;Natural gas and feedwater will be filtered before use;The plant design will minimise the amount of heat lost due to unburned gases and excess air;The plant will operate under optimum pressure and temperature conditions whenever possible. Theplant design will employ the use of advanced materials capable of reaching the levels required;Inlet air will be fitted with a self-cleaning fabric filter in order to prevent the ingress of particulate matter.Operation of the plant will include maintenance measures such as raw water pre-treatment and chemicaltreatment of the cooling water thereby optimising efficiency and minimising energy consumption.
During a start-up or shut down of the power plant, the engine will ramp up or decrease its stable operationalload. This period is expected to be approximately 10 minutes in total for both scenarios. During these periodsthe volume of exhaust gas exiting the exhaust stack will be reduced and its temperature will be lowercompared to standard operating levels. In addition, as an engine starts up, higher emission concentrationsof NOx and CO can be emitted.
When exhaust gas volumes and temperatures are reduced during start up and shut down the exit velocity ofthe exhaust gas and its thermal buoyancy from the tip of the stack are reduced compared to normal operationwhich can reduce the effectiveness of dispersion from the stack. However, as the primary fuel for the projectis natural gas the main pollutant of concern is NOx which has air quality standards for 1 hour and annualmean averaging periods. Given the short period of time when start up and shut down occurs the changes indispersion characteristics and emission concentrations would have negligible effects on the predicted levelof impacts presented averaged over a 1 hour an annual mean periods and are therefore start-ups and shutdowns are not considered to have a significant effect on air quality.
The power plant will operate in accordance with the requirements of Directive 2010/75/EU on industrialemissions (the Industrial Emissions Directive) and the BAT Guidance Note on Best Available Techniques forthe Energy Sector (Large Combustion Plant Sector), EPA, 2008. In addition, the plant will operate inaccordance with the relevant air quality standards and relevant emission limit values as specified in Section50 and Section 51 respectively of the Air Pollution Act 1987. Furthermore the plant will operate in accordance
78
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
Grange BackUp Power Industrial Emissions Licence Review Application
79
with the Air Quality Standards Regulations 2011 (S.I. No. 180 of 2011) came into force and transposed EU
Directive 2008/50/EC on ambient air quality and cleaner air for Europe into Irish law. A summary of the
emissions is provided in Tables E.1(ii) and E.1(iii).
Table F.1(i) shows the treatment, abatement and control systems implemented for the main emission points
identified in Attachment E.1, which are:
� Engine Stack 1 (A2-1);
� Engine Stack 2 (A2-2);
�
Grange BackUp Power Industrial Emissions Licence Review Application
79
with the Air Quality Standards Regulations 2011 (S.I. No. 180 of 2011) came into force and transposed EU
Directive 2008/50/EC on ambient air quality and cleaner air for Europe into Irish law. A summary of the
emissions is provided in Tables E.1(ii) and E.1(iii).
Table F.1(i) shows the treatment, abatement and control systems implemented for the main emission points
identified in Attachment E.1, which are:
� Engine Stack 1 (A2-1);
� Engine Stack 2 (A2-2);
�
Grange BackUp PowerMott MacDonald
with the Air Quality Standards Regulations 2011 (SJ. No. 180 of 2011) came into force and transposed EUDirective 2008/50/EC on ambient air quality and cleaner air for Europe into Irish law. A summary of theemissions is provided in Tables E.1 (ii) and E1 (iii).
Table F.1 (i) shows the treatment, abatement and control systems implemented for the main emission pointsidentified in Attachment E.1, which are:
Engine Stack 1 (A2—1);Engine Stack 2 (AZ-2);
79
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
80
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Selective Catalytic
Reduction (SCR)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
80
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Selective Catalytic
Reduction (SCR)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried Equipment 3 Equipment back-upout2
NOX Continuous (via in situ Selective Catalytic Maintenance suppliesproprietary Continuous Reduction (SCR) Stock of demineralisedEmissions monitoring Demineralised Water water stored on siteSystem {CEMS}) CEMS
C0 As above Controlled combustion / Maintenance suppliesCEMS
Temperature As above As above / CEMS Maintenance supplies
502 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
8O
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
81
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Use of low sulphur distillate
fuel (0.1%)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
81
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Use of low sulphur distillate
fuel (0.1%)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-1 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carriedout2
Equipment 3 Equipment back-up
NOx
CO
Temperature
502
Particulate Matter
Continuous (via in situproprietary ContinuousEmissions MonitoringSystem {CEMS})
As above
As above
As above
As above
Use of low sulphur distillatefuel (0.1%)
Demineralised Water
CEMS
Controlled combustion /CEMS
As above / CEMS
CEMS
CEMS
Maintenance supplies
Stock of demineralisedwater stored on site
Maintenance supplies
Maintenance supplies
Maintenance supplies
Maintenance supplies
81
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
82
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Selective Catalytic
Reduction (SCR)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
82
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Selective Catalytic
Reduction (SCR)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Natural Gas)
Control1 parameter Monitoring to be carried Equipment 3 Equipment back-upout2
NOX Continuous (via in situ Selective Catalytic Maintenance suppliesproprietary Continuous Reduction (SCR) Stock of demineralisedEmissions monitoring Demineralised Water water stored on siteSystem {CEMS}) CEMS
C0 As above Controlled combustion / Maintenance suppliesCEMS
Temperature As above As above / CEMS Maintenance supplies
502 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
82
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
83
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Use of low sulphur distillate
fuel (0.1%)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
83
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
NOx Continuous (via in situ
proprietary Continuous
Emissions Monitoring
System {CEMS})
Use of low sulphur distillate
fuel (0.1%)
Demineralised Water
CEMS
Maintenance supplies
Stock of demineralised
water stored on site
CO As above Controlled combustion /
CEMS
Maintenance supplies
Temperature As above As above / CEMS Maintenance supplies
SO2 As above CEMS Maintenance supplies
Particulate Matter As above CEMS Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: A2-2 (Engine Operating on Low Sulphur Distillate Oil)
Control1 parameter Monitoring to be carriedout2
Equipment 3 Equipment back-up
NOx
CO
Temperature
502
Particulate Matter
Continuous (via in situproprietary ContinuousEmissions MonitoringSystem {CEMS})
As above
As above
As above
As above
Use of low sulphur distillatefuel (0.1%)
Demineralised Water
CEMS
Controlled combustion/CEMS
As above / CEMS
CEMS
CEMS
Maintenance supplies
Stock of demineralisedwater stored on site
Maintenance supplies
Maintenance supplies
Maintenance supplies
Maintenance supplies
83
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
Grange BackUp Power Industrial Emissions Licence Review Application
84
F.1.2 Surface Water Emissions Treatment, Abatement and Control
As described in Attachment E.4 surface water will be collected from two catchment areas within the site –
the western catchment and the eastern catchment.
Surface water from the western catchment will be passed through a Class 1 full retention Enviroceptor. This
catchment includes the fuel oil unloading bay and the fuel storage tank which is located within a bunded
area. The rainwater which falls here is likely to be clean in the absence of an oil spill or leak. As a result, a
sump and pumping arrangement located within the bund will allow clean rainwater to be pumped into the
collection system when required. Pumping will be manually activated and will pass through to avoid pumping
potentially contaminated water. Surface water from the eastern catchment, which will include run-off from
the engine house and paved areas will be passed through a Bypass Separator.
The Class 1 Enviroceptor and the Bypass Separators will be fitted with visual and audible alarms to ensure
containment facilities are adequately maintained. In addition, this alarm will be linked to auto dial facilities
such that relevant staff can be alerted.
Gullies and drains entry points will incorporate silt traps to remove any grit or silt which may be washed into
the surface water drainage system.
The western and eastern catchment areas will have their own surface water attenuation tanks. The western
catchment attenuation tank will have a storage volume of 128m³ and the eastern catchment attenuation tank
will have a storage capacity of 233m³.These tanks have been designed to accommodate a 1:100 year storm
event and will discharge via hydro-brakes to the existing surface water drainage system within the Grange
Castle Business Park.
It should be noted also that the grants of planning permission issued by South Dublin County Council
(Planning Register: SD16A/0398 and SD15A/0061) reinforces many of the above treatment, abatement and
control measures through the following conditions which Grange Back Up Power will ensure are fully
complied with:
� Drainage infrastructure will comply with the requirements of the Planning Authority or Irish Water;
� All drainage works will comply with the Greater Dublin Regional Code of Practise for Drainage Works
and the South Dublin County Council Specification for the Laying of Watermains and Drinking Water
Supply Guidance Document (2012);
� No development is authorised to take place until such time that Grange BackUp Power has provided
details to the Planning Authority of pollution monitoring and control mechanisms required to contain fire
water run-off within the site and to prevent pollution of the Griffeen River (which the Business Park
attenuation pond ultimately discharges to).
� There will be complete separation of the surface water and foul wastewater drainage systems; and prior
to the occupation of the development, details of tests and surveys demonstrating full separation will be
Grange BackUp Power Industrial Emissions Licence Review Application
84
F.1.2 Surface Water Emissions Treatment, Abatement and Control
As described in Attachment E.4 surface water will be collected from two catchment areas within the site –
the western catchment and the eastern catchment.
Surface water from the western catchment will be passed through a Class 1 full retention Enviroceptor. This
catchment includes the fuel oil unloading bay and the fuel storage tank which is located within a bunded
area. The rainwater which falls here is likely to be clean in the absence of an oil spill or leak. As a result, a
sump and pumping arrangement located within the bund will allow clean rainwater to be pumped into the
collection system when required. Pumping will be manually activated and will pass through to avoid pumping
potentially contaminated water. Surface water from the eastern catchment, which will include run-off from
the engine house and paved areas will be passed through a Bypass Separator.
The Class 1 Enviroceptor and the Bypass Separators will be fitted with visual and audible alarms to ensure
containment facilities are adequately maintained. In addition, this alarm will be linked to auto dial facilities
such that relevant staff can be alerted.
Gullies and drains entry points will incorporate silt traps to remove any grit or silt which may be washed into
the surface water drainage system.
The western and eastern catchment areas will have their own surface water attenuation tanks. The western
catchment attenuation tank will have a storage volume of 128m³ and the eastern catchment attenuation tank
will have a storage capacity of 233m³.These tanks have been designed to accommodate a 1:100 year storm
event and will discharge via hydro-brakes to the existing surface water drainage system within the Grange
Castle Business Park.
It should be noted also that the grants of planning permission issued by South Dublin County Council
(Planning Register: SD16A/0398 and SD15A/0061) reinforces many of the above treatment, abatement and
control measures through the following conditions which Grange Back Up Power will ensure are fully
complied with:
� Drainage infrastructure will comply with the requirements of the Planning Authority or Irish Water;
� All drainage works will comply with the Greater Dublin Regional Code of Practise for Drainage Works
and the South Dublin County Council Specification for the Laying of Watermains and Drinking Water
Supply Guidance Document (2012);
� No development is authorised to take place until such time that Grange BackUp Power has provided
details to the Planning Authority of pollution monitoring and control mechanisms required to contain fire
water run-off within the site and to prevent pollution of the Griffeen River (which the Business Park
attenuation pond ultimately discharges to).
� There will be complete separation of the surface water and foul wastewater drainage systems; and prior
to the occupation of the development, details of tests and surveys demonstrating full separation will be
Grange BackUp PowerMott MacDonald
F.1.2 Surface Water Emissions Treatment, Abatement and Control
As described in Attachment E.4 surface water will be collected from two catchment areas within the site —the western catchment and the eastern catchment.
Surface water from the western catchment will be passed through a Class 1 full retention Enviroceptor. Thiscatchment includes the fuel oil unloading bay and the fuel storage tank which is located within a bundedarea. The rainwater which falls here is likely to be clean in the absence of an oil spill or leak. As a result, asump and pumping arrangement located within the bund will allow clean rainwater to be pumped into thecollection system when required. Pumping will be manually activated and will pass through to avoid pumpingpotentially contaminated water. Surface water from the eastern catchment, which will include run-off fromthe engine house and paved areas will be passed through a Bypass Separator.
The Class 1 Enviroceptor and the Bypass Separators will be fitted with visual and audible alarms to ensurecontainment facilities are adequately maintained. In addition, this alarm will be linked to auto dial facilitiessuch that relevant staff can be alerted.
Gullies and drains entry points will incorporate silt traps to remove any grit or silt which may be washed intothe surface water drainage system.
The western and eastern catchment areas will have their own surface water attenuation tanks. The westerncatchment attenuation tank will have a storage volume of 128m3 and the eastern catchment attenuation tankwill have a storage capacity of 233m3.These tanks have been designed to accommodate a 1:100 year stormevent and will discharge via hydro-brakes to the existing surface water drainage system within the GrangeCastle Business Park.
It should be noted also that the grants of planning permission issued by South Dublin County Council(Planning Register: SD16A/0398 and SD15A/0061) reinforces many of the above treatment, abatement andcontrol measures through the following conditions which Grange Back Up Power will ensure are fullycomplied with:
Drainage infrastructure will comply with the requirements of the Planning Authority or Irish Water;All drainage works will comply with the Greater Dublin Regional Code of Practise for Drainage Worksand the South Dublin County Council Specification for the Laying of Watermains and Drinking WaterSupply Guidance Document (2012);No development is authorised to take place until such time that Grange BackUp Power has provideddetails to the Planning Authority of pollution monitoring and control mechanisms required to contain firewater run-off within the site and to prevent pollution of the Griffeen River (which the Business Parkattenuation pond ultimately discharges to).There will be complete separation of the surface water and foul wastewater drainage systems; and priorto the occupation of the development, details of tests and surveys demonstrating full separation will be
84
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
Grange BackUp Power Industrial Emissions Licence Review Application
85
required to be submitted to the Planning Authority along with confirmation from the Councils Waster
Services Department that these tests and surveys fully meet with their requirements;
� Silt traps will be incorporated prior to the intakes to the surface water attenuation tanks;
� The hydrobrake proposed to restrict flow to the east of the site shall be relocated closer to the outfall in
order to restrict flow to all of the eastern section of the site (it should be noted that the relocation of the
hydrobrake has been updated as per this condition and the location of same is illustrated in Figure F.2.1);
and
� Only clean, uncontaminated water shall be discharged into the Griffeen River network. The specific
details of any discharges to watercourses will be agreed with Inland Fisheries Ireland. Class 1 petrol/oil
interceptors and hydrobrake controls should be provided on primary surface water discharges to protect
receiving freshwater in terms of water quality.
Table F.1(i) indicates the treatment, abatement and control systems implemented for the main emission
points identified in Attachment E.3, which are:
� Location Downstream of Surface Water Attenuation Tank 1 (SW1);
� Location Downstream of Surface Water Attenuation Tank 2 (SW2).
Grange BackUp Power Industrial Emissions Licence Review Application
85
required to be submitted to the Planning Authority along with confirmation from the Councils Waster
Services Department that these tests and surveys fully meet with their requirements;
� Silt traps will be incorporated prior to the intakes to the surface water attenuation tanks;
� The hydrobrake proposed to restrict flow to the east of the site shall be relocated closer to the outfall in
order to restrict flow to all of the eastern section of the site (it should be noted that the relocation of the
hydrobrake has been updated as per this condition and the location of same is illustrated in Figure F.2.1);
and
� Only clean, uncontaminated water shall be discharged into the Griffeen River network. The specific
details of any discharges to watercourses will be agreed with Inland Fisheries Ireland. Class 1 petrol/oil
interceptors and hydrobrake controls should be provided on primary surface water discharges to protect
receiving freshwater in terms of water quality.
Table F.1(i) indicates the treatment, abatement and control systems implemented for the main emission
points identified in Attachment E.3, which are:
� Location Downstream of Surface Water Attenuation Tank 1 (SW1);
� Location Downstream of Surface Water Attenuation Tank 2 (SW2).
Grange BackUp PowerMott MacDonald
required to be submitted to the Planning Authority along with confirmation from the Councils WasterServices Department that these tests and surveys fully meet with their requirements;Silt traps will be incorporated prior to the intakes to the surface water attenuation tanks;The hydrobrake proposed to restrict flow to the east of the site shall be relocated closer to the outfall inorder to restrict flow to all of the eastern section of the site (it should be noted that the relocation of thehydrobrake has been updated as per this condition and the location of same is illustrated in Figure F.2.1);andOnly clean, uncontaminated water shall be discharged into the Griffeen River network. The specificdetails of any discharges to watercourses will be agreed with Inland Fisheries Ireland. Class 1 petrol/oilinterceptors and hydrobrake controls should be provided on primary surface water discharges to protectreceiving freshwater in terms of water quality.
Table F.1(i) indicates the treatment, abatement and control systems implemented for the main emissionpoints identified in Attachment E.3, which are:
85
Location Downstream of Surface Water Attenuation Tank 1 (SW1);Location Downstream of Surface Water Attenuation Tank 2 (SW2).
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
P1 29/09/15 SHY For PlanningMMcC PK
Key to symbols
App’dCh’k’dDescriptionDrawnDateRev
RevStatus
Drawing Number
Scale at A0
Eng check
Approved
Coordination
Dwg check
Drawn
Designed
Title
Notes
Client
Reference drawings
Security
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.1_P2.dwg Mar 16, 2017 - 9:08AM ric66327
TFW
©
Figure F.2.1
Emissions Monitoring Sampling Points
Grange Back Up Power Ltd
Others
S. Healy
M.McCarthy
Others
P.Kelly
1:200 APR
MMD-349512-N-DR-00-XX-0011
P2 STD
Mott MacDonald
South Block, Rockfield,
Dundrum, Dublin 16,
Ireland
+353 (0)1 2916700
+353 (0)1 2916747
www.mottmac.com
This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
Mott MacDonald
1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH
ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS
AND SPECIFICATIONS.
2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
3. ANY DISCREPANCIES TO BE REPORTED TO THE
ARCHITECT.
4. ALL DIMENSIONS ARE IN MILLIMETERS.
5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE
SURVEY DATUM MALIN HEAD.
1
2
3
4
5
6
8
9
10
11
13
16
17
18
19
20
7
14
21
15
22
23
24
25
30
37
38
28
29
26
P2 10/03/17 ERN For Planning
MMcC PK
MONITORING & SAMPLING POINT
IED APPLICATION SITE BOUNDARY
ENGINE HALL - ROOF PLAN
ANCILLIARY TANKS, PLANT, EQUIPMENT AND BUILDINGS
39
40
³ SURFACE WATER ATTENUATION TANK
³
10m20m0
1:200
A
0008
A
0008
B
00
08
B
00
08
N
1
22
22
22
22
22
22
6
5
18
10
11
16
8
4
19
25
19
2423
21
14
3
7
20
15
2
14
26
17
37
38
9
16
28
29
30
3940
P1 29/09/15 SHY For PlanningMMcC PK
Key to symbols
App’dCh’k’dDescriptionDrawnDateRev
RevStatus
Drawing Number
Scale at A0
Eng check
Approved
Coordination
Dwg check
Drawn
Designed
Title
Notes
Client
Reference drawings
Security
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.1_P2.dwg Mar 16, 2017 - 9:08AM ric66327
TFW
©
Figure F.2.1
Emissions Monitoring Sampling Points
Grange Back Up Power Ltd
Others
S. Healy
M.McCarthy
Others
P.Kelly
1:200 APR
MMD-349512-N-DR-00-XX-0011
P2 STD
Mott MacDonald
South Block, Rockfield,
Dundrum, Dublin 16,
Ireland
+353 (0)1 2916700
+353 (0)1 2916747
www.mottmac.com
This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
Mott MacDonald
1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH
ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS
AND SPECIFICATIONS.
2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
3. ANY DISCREPANCIES TO BE REPORTED TO THE
ARCHITECT.
4. ALL DIMENSIONS ARE IN MILLIMETERS.
5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE
SURVEY DATUM MALIN HEAD.
1
2
3
4
5
6
8
9
10
11
13
16
17
18
19
20
7
14
21
15
22
23
24
25
30
37
38
28
29
26
P2 10/03/17 ERN For Planning
MMcC PK
MONITORING & SAMPLING POINT
IED APPLICATION SITE BOUNDARY
ENGINE HALL - ROOF PLAN
ANCILLIARY TANKS, PLANT, EQUIPMENT AND BUILDINGS
39
40
³ SURFACE WATER ATTENUATION TANK
³
10m20m0
1:200
A
0008
A
0008
B
00
08
B
00
08
N
1
22
22
22
22
22
22
6
5
18
10
11
16
8
4
19
25
19
2423
21
14
3
7
20
15
2
14
26
17
37
38
9
16
28
29
30
3940
EXISTING ESB MAINENTRANCE TO RETAIN.—\
\
_ _ A2—1
SITE BOUNDARY LINE—> ® @ T— — — — @\ II
III: E ”/3 , I \\/ ~~-§flflflflflflflfl ‘7’”, / I \\
/ ___________ \
I S ----------/""""" I \ "69
I \ IM | | \\
I \\\I II GE I I S"II II
I lI PUMPFISRTEATION | LO TANK I I
| (DIRTY) | I I
H II I\\\III I
I II 3 SCR I I \II—l_l I I
I _ 2' I I " EEIEJEIAIIIIII‘CGTSSJESl PAINTED IN DARK I PRIEICNASSUTLUCEISCRETEI ‘—'GREEN COLOR- I I PANELS WITH
C) I I SELECTED COLOR.
RAW/FIRE I 0 I I”I WATER TANK I OIL ENGINE HALL I I2400mm HIGH I I IESIEI‘BFIIFB’E I STORAGE I I I I I I:AHEDCIIORRK . I W I I .
TIIII IEIEII GGGGGGGGGGGGGGGGGGGGGIII
" \I WW C>Q<3C>O<3C>O<3C>O<3C>O<3C>O<DC>©<D III\\I H I_ll n _ | I
I m ©<DC>OCDO<3C>O<DC>O<DC>OCDO<3C>O<D III WWWI/I . . G G G G G G G G G G G G G G G G G G G G G— I I
.3 : l '
I I Q<3C>Q<3C>O<3C>O<3C>O<DC>Q<3C>O<3CL I I WWW: I. L' ® 9 A A CGGGGGGGGGGGGGGGGGGGG I.
\ t 2 PUMP I l
I ® IO 1 5 S” I I. I III I B C G 3 C DRE G G B I I\ E 3 f I —_ I I
I \ ' OOOOOOGGGGGGGGGGGGGGG iI'"// I I I/ I OOOOOOOOOOOOQQOQOQOOQ‘EII. | II (I ,,,,,,, I . A? I GGGGGGGGGGGGGGGGGGGGG— II .
\ \ ' |\\\ \\ \\\R\ \f////// “T‘DM”““€Rfi5 I C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) C) _ I I I\ \ '\_ II E \\ «\ I ©<3C>©(DCDO<3C>©<3CDC>©<DC>©<DC>O<Q II"
\ '\4 _ I I. \\ \L\ I C) C) <:> C) C) <:> C) C) <:> C) C) <:> C) C) <:> C) C) C) <:> C) C) T\J Ix \\ II4\.\ I II I III.\
II III KLARGESTER CLASS 1 FULL RETENTION @ W \ W \ \ \ I \ ' I II I II ENVIROCEPTOR (OR SIMILAR APPROVED) COIiIc AVEA—I—R EA/HOORfiSSI—I—I OP \ ' \ \ \ \_ I I\ \ \ \ \‘\_ I —II I'I I I S '
I :1:’____:_'___I.___’_:_’___'____'_:___'____:_'___'____:_'i:2:___’____’_:___’____’_:___’____:_’___’____:_’___’____’ ' I§ Q]? - ARCTIC
___________ VALVE
HYDROBRAKE ________________________________ \ . i
'I \I FVALVE \\ RETAINING WALL GAS SKID SW4 \\\\ \ I (OR SIMILAR APDRBIIED)—=u==-=-==u==- I========m==I I \=_:==:-——-=I==—I===-=-========= ==—-=-—==s—=—===l=-=,=l=—==n‘A-_—
\ \ .\\ \ \_SW-2 \ \.\ . \\ \
\ \ \\ \ -\\ \\ I\ .— EXISTING FOUL
C X 2400MM HIGH/ ____________________________________________________ EENCINGAROIJND.___EXISTING SURFACE WATER SEWER BOUNDARY LINE.
© Mott MacDonald
This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.1_P2.dwg Mar 16, 2017 - 9:08AM ric66327
Notes
1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITHALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGSAND SPECIFICATIONS.
2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
3. ANY DISCREPANCIES TO BE REPORTED TO THEARCHITECT.
4. ALL DIMENSIONS ARE IN MILLIMETERS.
5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCESURVEY DATUM MALIN HEAD.
Key to symbols
- I - I - I - IED APPLICATION SITE BOUNDARY
ENGINE HALL - ROOF PLAN
ANCILLIARY TANKS, PLANT, EQUIPMENT AND BUILDINGS
G MONITORING & SAMPLING POINT
Reference drawings
\\ \\I@_._I_§EIIIE.R._._\
PEAKING PLANT SITE ENTRANCE
@® SECURHY MOSKOW UNLOAmNG BAYSLUDGE TANKMSTWLATE OW STORAGE TANKBUNDMPE ROUTEWATER TREATMENT UNn SHELTERTREATED WATER TANKHRE PUMP STADONLO TANK (CLEAN)LO TANK (WRTY)GAS ENdNE EXHAUST STACKS (2 No)MPE BWDGE2 No SCR REAGENT TANKS (UREA)COMPACT WORKSHOP & WAREHOUSERAW WATER TANK / HRE WATER TANK2 NotMLY WATER COLLECHON PnSCAR PARK (5 + 1 NO OF SPACES)CONTROL MTSCREEN FENdNGSTAHON TRANSFORMERBLOCK TRANSFORMERPUMP HOUSEENONE HALLTRANSFORMERTRANSFORMERGAS SWDFOUL PUMP CHAMBERPROCESS WASTEWATER WSCHARGE CHAMBER150m3 SURFACE WATER ATTENUATION TANK
66
6®
Q6
@6
®®
®®
®®
66
©6
@9
@®
6©
6®
@®
®@
80m3 SURFACE WATER ATTENUATION TANK
0 10m 20m1:200 | | | I
P2 10/03/17 ERN ForPlanning MMcC PK
P1 29/09/15 SHY ForPlanning MMcC PK
Rev Date Drawn Description Ch’k’d App’d
Mott MacDonaldSouth Block, Rockfield,Dundrum, Dublin 16,Ireland
Matt Macponald 1 +353 (0)1 2916700F +353(O)12916747w www.mottmac.com
Client
Grange Back Up Power Ltd
\ 2\\ IR§\\ l\ I\\ I\/ I______________________\\/\__7__7_______7___. ,,___ ,__7____7__7__7__7_______7__7__7__7____7__7__7__7____7__7__7__/l\____7__
EXISTING SURFACE WATER SEWER \ /
EXISTING INDUSTRIAL IESTATE EXIT ROAD I
III
II
EXISTING INDUSTRIAL IIESTATE ENTRANCE ROAD I
Ill
firglssmn Main Emission Point Easting Northing
A2-1 Gas Engine Stack NO. 1 303681 232116
A2-2 Gas Engine Stack No. 2 303656 232117
SW-1 Downstream Of Attenuation Tank No.1 303696 232052
SW-2 Downstream of Attenuation Tank No.2 303607 232055SE-2 Downstream of Process Wastewater DIscharge 303598 232079
Chamber
Title
Figure F.2.1
Emissions Monitoring Sampling Points
Designed Others Eng check Others
Drawn S. Healy Coordination
Dwg check M.McCarthy Approved P.Kelly
Scale at A0 Status Rev Security
1:200 APR P2 STDDrawing Number
MMD-349512-N-DR-00-XX-OO1 1
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:47
86
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW1
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
Total Petroleum
Hydrocarbons (TPH)
Weekly Visual inspection N/A
Suspended Solids Weekly Visual inspection N/A
Total Petroleum
Hydrocarbons (TPH)
Monthly Standard Method N/A
Suspended Solids Monthly Visual inspection N/A
Conductivity Monthly (as flow permits)
Standard Method Maintenance supplies
TOC Monthly Standard Method Maintenance supplies
pH Monthly Standard Method Maintenance supplies
86
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW1
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
Total Petroleum
Hydrocarbons (TPH)
Weekly Visual inspection N/A
Suspended Solids Weekly Visual inspection N/A
Total Petroleum
Hydrocarbons (TPH)
Monthly Standard Method N/A
Suspended Solids Monthly Visual inspection N/A
Conductivity Monthly (as flow permits)
Standard Method Maintenance supplies
TOC Monthly Standard Method Maintenance supplies
pH Monthly Standard Method Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW1
Control1 parameter Monitoring to be carriedout2
Equipment 3 Equipment back-up
Total PetroleumHydrocarbons (TPH)
Suspended Solids
Total PetroleumHydrocarbons (TPH)
Suspended Solids
Conductivity
TOCpH
86
Weekly
Weekly
Monthly
Monthly
Monthly (as flow permits)
Monthly
Monthly
Visual inspection
Visual inspection
Standard Method
Visual inspection
Standard Method
Standard Method
Standard Method
N/A
N/AN/A
N/AMaintenance supplies
Maintenance supplies
Maintenance supplies
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
87
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW2
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
Total Petroleum
Hydrocarbons (TPH)
Weekly Visual inspection N/A
Suspended Solids Weekly Visual inspection N/A
Total Petroleum
Hydrocarbons (TPH)
Monthly Standard Method N/A
Suspended Solids Monthly Standard Method N/A
Conductivity Monthly (as flow permits)
Standard Method Maintenance supplies
TOC Monthly Standard Method Maintenance supplies
pH Monthly Standard Method Maintenance supplies
87
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW2
Control1 parameter Monitoring to be carried
out2
Equipment 3 Equipment back-up
Total Petroleum
Hydrocarbons (TPH)
Weekly Visual inspection N/A
Suspended Solids Weekly Visual inspection N/A
Total Petroleum
Hydrocarbons (TPH)
Monthly Standard Method N/A
Suspended Solids Monthly Standard Method N/A
Conductivity Monthly (as flow permits)
Standard Method Maintenance supplies
TOC Monthly Standard Method Maintenance supplies
pH Monthly Standard Method Maintenance supplies
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SW2
Control1 parameter Monitoring to be carriedout2
Equipment 3 Equipment back-up
Total PetroleumHydrocarbons (TPH)
Suspended Solids
Total PetroleumHydrocarbons (TPH)
Suspended Solids
Conductivity
TOC
pH
Weekly
Weekly
Monthly
Monthly
Monthly (as flow permits)
Monthly
Monthly
Visual inspection
Visual inspection
Standard Method
Standard Method
Standard Method
Standard Method
Standard Method
N/A
N/AN/A
N/AMaintenance supplies
Maintenance supplies
Maintenance supplies
87
Mott MacDonald
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
88
F.1.3 Domestic Wastewater Emissions Treatment, Abatement and Control
As described in Attachment E.5, foul wastewater from the power plant will consist of domestic effluent from
the toilets, sinks, etc. on-site. This wastewater will be discharged from the site via an appropriately sized
pumping station and will connect to the existing foul drainage system in Grange Castle Business Park which
in turn discharges to the South Dublin County Council foul drainage system which ultimately discharges to
the Ringsend Wastewater Treatment Plant.
It should be noted also that the grants of planning permission issued by South Dublin County Council
(Planning Registers:SD161/0398 and SD15A/0061) states that there will be complete separation of the
surface water and foul wastewater drainage systems; and prior to the occupation of the development, details
of tests and surveys demonstrating full separation will be required to be submitted to the Planning Authority
along with confirmation from the Councils Waster Services Department that these tests and surveys fully
meet with their requirements.
Due to its small volume and the small operational workforce, it is not proposed to monitor foul wastewater.
F.1.4 Process Wastewater Emissions Treatment, Abatement and Control
Process wastewater to be generated from the facility will consist of the waste stream arising from the
treatment of purified water for injection into the engine during the combustion process to control NOx
emissions. This wastewater will have a volume of approximately 0.5m3/hr which will be collected in an
underground storage tank before its treatment and release (at SE2) to the existing foul drainage system in
Grange Castle Business Park which in turn discharges to the South Dublin County Council foul drainage
system which ultimately discharges to the Ringsend Wastewater Treatment Plant.
The process wastewater will be dosed automatically, if required, to regulate the pH to pH 6-9. Any solids
collected in the water treatment plant will be removed from site by authorised contractors.
All chemical conditioning materials required for water treatment or for corrosion control will be stored in the
chemical storage room. Spills and leaks will be cleaned by appropriately experienced personnel using
absorbent materials. The arising waste will be disposed of off-site by appropriately authorised contractors.
All elements of the treatment systems will be monitored on a regular basis to ensure optimum performance
and maintenance. The water treatment plant effluent will be monitored for pH. If the pH is outside the range
of 6-9, or as permitted by the EPA, the discharge will automatically stop until the failure is corrected.
Monitoring equipment will be included in the PPMP in accordance with manufacturer’s specifications and
best practice guidelines. Records of checks, calibrations and maintenance checks will be retained on site.
Pipes, bunds and storage facilities will be regularly checked for deterioration, damage and leaks. Integrity
testing and the maintenance of all waste water abatement, control and monitoring equipment will be
Grange BackUp Power Industrial Emissions Licence Review Application
88
F.1.3 Domestic Wastewater Emissions Treatment, Abatement and Control
As described in Attachment E.5, foul wastewater from the power plant will consist of domestic effluent from
the toilets, sinks, etc. on-site. This wastewater will be discharged from the site via an appropriately sized
pumping station and will connect to the existing foul drainage system in Grange Castle Business Park which
in turn discharges to the South Dublin County Council foul drainage system which ultimately discharges to
the Ringsend Wastewater Treatment Plant.
It should be noted also that the grants of planning permission issued by South Dublin County Council
(Planning Registers:SD161/0398 and SD15A/0061) states that there will be complete separation of the
surface water and foul wastewater drainage systems; and prior to the occupation of the development, details
of tests and surveys demonstrating full separation will be required to be submitted to the Planning Authority
along with confirmation from the Councils Waster Services Department that these tests and surveys fully
meet with their requirements.
Due to its small volume and the small operational workforce, it is not proposed to monitor foul wastewater.
F.1.4 Process Wastewater Emissions Treatment, Abatement and Control
Process wastewater to be generated from the facility will consist of the waste stream arising from the
treatment of purified water for injection into the engine during the combustion process to control NOx
emissions. This wastewater will have a volume of approximately 0.5m3/hr which will be collected in an
underground storage tank before its treatment and release (at SE2) to the existing foul drainage system in
Grange Castle Business Park which in turn discharges to the South Dublin County Council foul drainage
system which ultimately discharges to the Ringsend Wastewater Treatment Plant.
The process wastewater will be dosed automatically, if required, to regulate the pH to pH 6-9. Any solids
collected in the water treatment plant will be removed from site by authorised contractors.
All chemical conditioning materials required for water treatment or for corrosion control will be stored in the
chemical storage room. Spills and leaks will be cleaned by appropriately experienced personnel using
absorbent materials. The arising waste will be disposed of off-site by appropriately authorised contractors.
All elements of the treatment systems will be monitored on a regular basis to ensure optimum performance
and maintenance. The water treatment plant effluent will be monitored for pH. If the pH is outside the range
of 6-9, or as permitted by the EPA, the discharge will automatically stop until the failure is corrected.
Monitoring equipment will be included in the PPMP in accordance with manufacturer’s specifications and
best practice guidelines. Records of checks, calibrations and maintenance checks will be retained on site.
Pipes, bunds and storage facilities will be regularly checked for deterioration, damage and leaks. Integrity
testing and the maintenance of all waste water abatement, control and monitoring equipment will be
Grange BackUp PowerMott MacDonald
F.1.3 Domestic Wastewater Emissions Treatment, Abatement and Control
As described in Attachment E.5, foul wastewater from the power plant will consist of domestic effluent fromthe toilets, sinks, etc. on-site. This wastewater will be discharged from the site via an appropriately sizedpumping station and will connect to the existing foul drainage system in Grange Castle Business Park whichin turn discharges to the South Dublin County Council foul drainage system which ultimately discharges tothe Ringsend Wastewater Treatment Plant.
It should be noted also that the grants of planning permission issued by South Dublin County Council(Planning Registers:SD161/0398 and SD15A/0061) states that there will be complete separation of thesurface water and foul wastewater drainage systems; and prior to the occupation of the development, detailsof tests and surveys demonstrating full separation will be required to be submitted to the Planning Authorityalong with confirmation from the Councils Waster Services Department that these tests and surveys fullymeet with their requirements.
Due to its small volume and the small operational workforce, it is not proposed to monitor foul wastewater.
F.1.4 Process Wastewater Emissions Treatment, Abatement and Control
Process wastewater to be generated from the facility will consist of the waste stream arising from thetreatment of purified water for injection into the engine during the combustion process to control NOXemissions. This wastewater will have a volume of approximately 0.5m3/hr which will be collected in anunderground storage tank before its treatment and release (at SE2) to the existing foul drainage system inGrange Castle Business Park which in turn discharges to the South Dublin County Council foul drainagesystem which ultimately discharges to the Ringsend Wastewater Treatment Plant.
The process wastewater will be dosed automatically, if required, to regulate the pH to pH 6-9. Any solidscollected in the water treatment plant will be removed from site by authorised contractors.
A” chemical conditioning materials required for water treatment or for corrosion control will be stored in thechemical storage room. Spills and leaks will be cleaned by appropriately experienced personnel usingabsorbent materials. The arising waste will be disposed of off-site by appropriately authorised contractors.
A|| elements of the treatment systems will be monitored on a regular basis to ensure optimum performanceand maintenance. The water treatment plant effluent will be monitored for pH. If the pH is outside the rangeof 6-9, or as permitted by the EPA, the discharge will automatically stop until the failure is corrected.
Monitoring equipment will be included in the PPMP in accordance with manufacturer’s specifications andbest practice guidelines. Records of checks, calibrations and maintenance checks will be retained on site.Pipes, bunds and storage facilities will be regularly checked for deterioration, damage and leaks. Integritytesting and the maintenance of all waste water abatement, control and monitoring equipment will be
88
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
89
incorporated into the on-site maintenance programmes. All equipment will be maintained and calibrated in
accordance with manufacturer’s specifications.
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SE2 (Process Wastewater)
Control1
parameter
Monitoring to be
carried out2
Equipment 3 Equipment back-up
Flow Continuous Discharge line
flowmeter
Maintenance supplies
pH Continuous Standard laboratory
Analysis
In accordance with
manufacturers
requirements
Temperature Continuous As above As above
BOD Quarterly As above As above
Dissolved Oxygen Quarterly As above As above
Suspended Solids Quarterly As above As above
Nitrate (as N) Quarterly As above As above
Ammonia (as N) Quarterly As above As above
Chloride Quarterly As above As above
TPH Quarterly As above As above
Total Phosphorus (as
P)
Quarterly As above As above
Conductivity Quarterly As above As above
Grange BackUp Power Industrial Emissions Licence Review Application
89
incorporated into the on-site maintenance programmes. All equipment will be maintained and calibrated in
accordance with manufacturer’s specifications.
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SE2 (Process Wastewater)
Control1
parameter
Monitoring to be
carried out2
Equipment 3 Equipment back-up
Flow Continuous Discharge line
flowmeter
Maintenance supplies
pH Continuous Standard laboratory
Analysis
In accordance with
manufacturers
requirements
Temperature Continuous As above As above
BOD Quarterly As above As above
Dissolved Oxygen Quarterly As above As above
Suspended Solids Quarterly As above As above
Nitrate (as N) Quarterly As above As above
Ammonia (as N) Quarterly As above As above
Chloride Quarterly As above As above
TPH Quarterly As above As above
Total Phosphorus (as
P)
Quarterly As above As above
Conductivity Quarterly As above As above
Grange BackUp PowerIndustrial Emissions Licence Review Application Mott MacDonald
incorporated into the on-site maintenance programmes. All equipment will be maintained and calibrated inaccordance with manufacturer’s specifications.
TABLE F.1(i): ABATEMENT / TREATMENT CONTROL
Emission point reference number: SE2 (Process Wastewater)Control1 Monitoring to be Equipment 3 Equipment back-up
parameter carried out2
Flow Continuous Discharge line Maintenance suppliesflowmeter
pH Continuous Standard laboratory In accordance withAnalysis manufacturers
requirements
Temperature Continuous As above As above
BOD Quarterly As above As above
Dissolved Oxygen Quarterly As above As above
Suspended Solids Quarterly As above As above
Nitrate (as N) Quarterly As above As above
Ammonia (as N) Quarterly As above As above
Chloride Quarterly As above As above
TPH Quarterly As above As above
Total Phosphorus (as Quarterly As above As above
P)Conductivity Quarterly As above As above
89
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
90
F.2 Emissions Monitoring and Sampling Points
F.2.1 General
A traceable and transparent monitoring, sampling and reporting programme will be developed by Grange
Back Up Power to ensure that emissions from the facility are within the relevant emission limit values and
irregularities and malfunctions are detected, and corrective actions implemented as soon as practicable.
The monitoring and sampling frequency implemented will be proportionate to the level of risk to the
environment.
Monitoring and sampling points will be limited to emissions to atmosphere, emissions to the sewer, emissions
to surface water and noise.
Grange BackUp Power Industrial Emissions Licence Review Application
90
F.2 Emissions Monitoring and Sampling Points
F.2.1 General
A traceable and transparent monitoring, sampling and reporting programme will be developed by Grange
Back Up Power to ensure that emissions from the facility are within the relevant emission limit values and
irregularities and malfunctions are detected, and corrective actions implemented as soon as practicable.
The monitoring and sampling frequency implemented will be proportionate to the level of risk to the
environment.
Monitoring and sampling points will be limited to emissions to atmosphere, emissions to the sewer, emissions
to surface water and noise.
Grange BackUp PowerMott MacDonald
F.2 Emissions Monitoring and Sampling Points
F.2.1 General
A traceable and transparent monitoring, sampling and reporting programme will be developed by GrangeBack Up Power to ensure that emissions from the facility are within the relevant emission limit values andirregularities and malfunctions are detected, and corrective actions implemented as soon as practicable.The monitoring and sampling frequency implemented will be proportionate to the level of risk to theenvironment.
Monitoring and sampling points will be limited to emissions to atmosphere, emissions to the sewer, emissionsto surface water and noise.
90
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
91
F.2.2 Atmospheric Emissions Monitoring and Sampling Points
Exhaust gases will be emitted to atmosphere through the engine stacks (A2-1 and A2-2). The stack will
incorporate an in-situ proprietary Continuous Emission Monitoring System (CEMS). The CEMS will
continuously monitor NOx, CO, Temperature and O2. Additional monitoring of SO2 and Particulate Matter
will be undertaken in accordance with the requirements of the EPA.
Minor emissions from the facility are not considered to be significant. Therefore, it is not proposed to
undertake additional atmospheric emissions monitoring for the minor emission points identified in Attachment
E.1 Emissions to Atmosphere.
Tables F.2(i) identifies the monitoring and sampling parameters associated with A2-1 and A2-2. The location
of these monitoring points is illustrated in Figure F.2.1.
Grange BackUp Power Industrial Emissions Licence Review Application
91
F.2.2 Atmospheric Emissions Monitoring and Sampling Points
Exhaust gases will be emitted to atmosphere through the engine stacks (A2-1 and A2-2). The stack will
incorporate an in-situ proprietary Continuous Emission Monitoring System (CEMS). The CEMS will
continuously monitor NOx, CO, Temperature and O2. Additional monitoring of SO2 and Particulate Matter
will be undertaken in accordance with the requirements of the EPA.
Minor emissions from the facility are not considered to be significant. Therefore, it is not proposed to
undertake additional atmospheric emissions monitoring for the minor emission points identified in Attachment
E.1 Emissions to Atmosphere.
Tables F.2(i) identifies the monitoring and sampling parameters associated with A2-1 and A2-2. The location
of these monitoring points is illustrated in Figure F.2.1.
Grange BackUp PowerMott MacDonald
F.2.2 Atmospheric Emissions Monitoring and Sampling Points
Exhaust gases will be emitted to atmosphere through the engine stacks (A2—1 and A2—2). The stack willincorporate an in-situ proprietary Continuous Emission Monitoring System (CEMS). The CEMS willcontinuously monitor NOx, CO, Temperature and 02. Additional monitoring of 802 and Particulate Matterwill be undertaken in accordance with the requirements of the EPA.
Minor emissions from the facility are not considered to be significant. Therefore, it is not proposed toundertake additional atmospheric emissions monitoring forthe minor emission points identified in AttachmentE.1 Emissions to Atmosphere.
Tables F.2(i) identifies the monitoring and sampling parameters associated with A2—1 and A2—2. The locationof these monitoring points is illustrated in Figure F.2.1.
91
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
92
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-1 (Engine Operating on Natural Gas)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/
technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
Pressure Continuous As above As above On line flue gas analyser
and recorder
Oxygen Content Continuous As above As above On line flue gas analyser
and recorder
Water Vapour Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 Bi-annually As above Standard Method Flue gas analyser
Particulate Matter Bi-annually As above As above Standard Method
92
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-1 (Engine Operating on Natural Gas)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/
technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
Pressure Continuous As above As above On line flue gas analyser
and recorder
Oxygen Content Continuous As above As above On line flue gas analyser
and recorder
Water Vapour Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 Bi-annually As above Standard Method Flue gas analyser
Particulate Matter Bi-annually As above As above Standard Method
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-1 (Engine Operating on Natural Gas)
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/Points technique
NOx Continuous Accessible Continuous On line flue gas analyserand recorder
CO Continuous As above As above On line flue gas analyserand recorder
Temperature Continuous As above As above On line flue gas analyserand recorder
Pressure Continuous As above As above On line flue gas analyserand recorder
Oxygen Content Continuous As above As above On line flue gas analyserand recorder
Water Vapour Continuous As above As above On line flue gas analyserand recorder
02 Continuous As above As above On line flue gas analyserand recorder$02 Bi-annually AS above Standard Method Flue gas analyserParticulate Matter Bi-annually As above As above Standard Method
92
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
93
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: A2-1 (Engine Operating on Distillate Oil)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 *Annually As above Standard Method Flue gas analyser
Particulate Matter *Annually As above As above Standard Method
93
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: A2-1 (Engine Operating on Distillate Oil)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 *Annually As above Standard Method Flue gas analyser
Particulate Matter *Annually As above As above Standard Method
Grange BackUp Power
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No:_A2-1 (Engine Operating on Distillate Oil)
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/ techniquePoints
NOx Continuous Accessible Continuous On line flue gas analyserand recorder
CO Continuous As above As above On line flue gas analyserand recorder
Temperature Continuous As above As above On line flue gas analyserand recorder
02 Continuous As above As above On line flue gas analyserand recorder
$02 *Annually AS above Standard Method Flue gas analyserParticulate Matter *Annua'ly AS above AS above Standard MEthOd
93
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
94
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-2 (Engine Operating on Natural Gas)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/
technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
Pressure Continuous As above As above On line flue gas analyser
and recorder
Oxygen Content Continuous As above As above On line flue gas analyser
and recorder
Water Vapour Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 Bi-annually As above Standard Method Flue gas analyser
Particulate Matter Bi-annually As above As above Standard Method
94
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-2 (Engine Operating on Natural Gas)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/
technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
Pressure Continuous As above As above On line flue gas analyser
and recorder
Oxygen Content Continuous As above As above On line flue gas analyser
and recorder
Water Vapour Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 Bi-annually As above Standard Method Flue gas analyser
Particulate Matter Bi-annually As above As above Standard Method
Grange BackUp PowerIndustrial Emissions Licence Review Application
TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS
Emission Point Reference No. : A2-2 (Engine Operating on Natural Gas)
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/Points technique
NOx Continuous Accessible Continuous On line flue gas analyserand recorder
CO Continuous As above As above On line flue gas analyserand recorder
Temperature Continuous As above As above On line flue gas analyserand recorder
Pressure Continuous As above As above On line flue gas analyserand recorder
Oxygen Content Continuous As above As above On line flue gas analyserand recorder
Water Vapour Continuous As above As above On line flue gas analyserand recorder
02 Continuous As above As above On line flue gas analyserand recorder$02 Bi-annually AS above Standard Method Flue gas analyserParticulate Matter Bi-annually As above As above Standard Method
94
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
95
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: A2-2 (Engine Operating on Distillate Oil)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 *Annually As above Standard Method Flue gas analyser
Particulate Matter *Annually As above As above Standard Method
95
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: A2-2 (Engine Operating on Distillate Oil)
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
NOx Continuous Accessible Continuous On line flue gas analyser
and recorder
CO Continuous As above As above On line flue gas analyser
and recorder
Temperature Continuous As above As above On line flue gas analyser
and recorder
O2 Continuous As above As above On line flue gas analyser
and recorder
SO2 *Annually As above Standard Method Flue gas analyser
Particulate Matter *Annually As above As above Standard Method
Grange BackUp Power
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No:_A2-2 (Engine Operating on Distillate Oil)
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/ techniquePoints
NOx Continuous Accessible Continuous On line flue gas analyserand recorder
CO Continuous As above As above On line flue gas analyserand recorder
Temperature Continuous As above As above On line flue gas analyserand recorder
02 Continuous As above As above On line flue gas analyserand recorder
$02 *Annually AS above Standard Method Flue gas analyserParticulate Matter *Annua'ly AS above AS above Standard MEthOd
95
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
96
F.2.3 Emissions to Surface Water Monitoring and Sampling Points
All hardstanding areas will drain by gravity to the surface water attenuation tanks. These will discharge via
hydro-brakes to the existing surface water drainage system within the Grange Castle Business Park. Details
of the proposed monitoring and sampling points of emissions to surface water drainage system are indicated
in Table F.2(ii).
Two monitoring and sampling locations are proposed at SW1 and SW2 as illustrated in Figure F.2.1
Emissions Monitoring Sampling Points. Sampling and analysis will be conducted in accordance with the
requirements of the EPA through the industrial emissions licence.
Tables F.2(i) identifies the monitoring and sampling parameters associated with SW1 and SW2. The location
of these monitoring points is illustrated in Figure F.2.1.
Grange BackUp Power Industrial Emissions Licence Review Application
96
F.2.3 Emissions to Surface Water Monitoring and Sampling Points
All hardstanding areas will drain by gravity to the surface water attenuation tanks. These will discharge via
hydro-brakes to the existing surface water drainage system within the Grange Castle Business Park. Details
of the proposed monitoring and sampling points of emissions to surface water drainage system are indicated
in Table F.2(ii).
Two monitoring and sampling locations are proposed at SW1 and SW2 as illustrated in Figure F.2.1
Emissions Monitoring Sampling Points. Sampling and analysis will be conducted in accordance with the
requirements of the EPA through the industrial emissions licence.
Tables F.2(i) identifies the monitoring and sampling parameters associated with SW1 and SW2. The location
of these monitoring points is illustrated in Figure F.2.1.
Grange BackUp PowerMott MacDonald
F.2.3 Emissions to Surface Water Monitoring and Sampling Points
All hardstanding areas will drain by gravity to the surface water attenuation tanks. These will discharge viahydro-brakes to the existing surface water drainage system within the Grange Castle Business Park. Detailsof the proposed monitoring and sampling points of emissions to surface water drainage system are indicatedin Table F.2(ii).
Two monitoring and sampling locations are proposed at SW1 and SW2 as illustrated in Figure F.2.1Emissions Monitoring Sampling Points. Sampling and analysis will be conducted in accordance with therequirements of the EPA through the industrial emissions licence.
Tables F.2(i) identifies the monitoring and sampling parameters associated with SW1 and SW2. The locationof these monitoring points is illustrated in Figure F.2.1.
96
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
97 349512/EDE/DDX/1/A 20 October 2015
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: SW1
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
Visual Inspection Daily Accessible Grab sample / Visual
inspection
Sample and inspect for TPH
and SS
Suspended Solids Monthly As above As above As above
Total Petroleum
Hydrocarbons (TPH)
Monthly As above
Grab sample Laboratory Analysis
Suspended Solids (SS) Monthly As above
As above As above
Conductivity Monthly (as flow permits)
As above
As above As above
TOC Monthly As above
As above As above
pH Daily As above
As above As above
97 349512/EDE/DDX/1/A 20 October 2015
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: SW1
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
Visual Inspection Daily Accessible Grab sample / Visual
inspection
Sample and inspect for TPH
and SS
Suspended Solids Monthly As above As above As above
Total Petroleum
Hydrocarbons (TPH)
Monthly As above
Grab sample Laboratory Analysis
Suspended Solids (SS) Monthly As above
As above As above
Conductivity Monthly (as flow permits)
As above
As above As above
TOC Monthly As above
As above As above
pH Daily As above
As above As above
Grange BackUp Power
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No:_SW1
Mott MacDonald
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/ techniquePoints
Visual Inspection Daily Accessible .Grab sample / Visual Sample and Inspect for TPHInspection and SS
Suspended Solids Monthly As above As above As above
Total Petroleum Monthly Grab sample Laboratory AnalysisHydrocarbons (TPH) AS above
Suspended Solids (SS) Monthly As above As aboveAs above
Conductivity Monthly (as flow permits) A5 above AS aboveAs above
TOC Monthly As above As aboveAs above
pH Daily As above As aboveAs above
349512/EDE/DDX/1/A 20 October 201597
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
98 349512/EDE/DDX/1/A 20 October 2015
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: SW2
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
Visual Inspection Daily Accessible Grab sample / Visual
inspection
Sample and inspect for TPH
and SS
Suspended Solids Monthly As above As above As above
Total Petroleum
Hydrocarbons (TPH)
Monthly As above
Grab sample Laboratory Analysis
Suspended Solids (SS) Monthly As above
As above As above
Conductivity Monthly (as flow permits)
As above
As above As above
TOC Monthly As above
As above As above
pH Daily As above
As above As above
98 349512/EDE/DDX/1/A 20 October 2015
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No: SW2
Parameter Monitoring frequency Accessibility of Sampling
Points
Sampling method Analysis method/ technique
Visual Inspection Daily Accessible Grab sample / Visual
inspection
Sample and inspect for TPH
and SS
Suspended Solids Monthly As above As above As above
Total Petroleum
Hydrocarbons (TPH)
Monthly As above
Grab sample Laboratory Analysis
Suspended Solids (SS) Monthly As above
As above As above
Conductivity Monthly (as flow permits)
As above
As above As above
TOC Monthly As above
As above As above
pH Daily As above
As above As above
Grange BackUp PowerMott MacDonald
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No:_SW2
Parameter Monitoring frequency Accessibility of Sampling Sampling method Analysis method/ techniquePoints
Visual Inspection Daily Accessible .Grab sample / Visual Sample and Inspect for TPHInspection and SS
Suspended Solids Monthly As above As above As above
Total Petroleum Monthly Grab sample .Laborator Anal sus
Hydrocarbons (TPH) AS above V Y
Suspended Solids (SS) Monthly As above As aboveAs above
Conductivity Monthly (as flow permits) A5 above AS aboveAs above
TOC Monthly As above As aboveAs above
pH Daily As above As aboveAs above
98 349512/EDE/DDX/1/A 20 October 2015
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
349512/EDE/DDX/1/A 20 October 2015
99
F.2.4 Emissions to Foul Sewer Monitoring and Sampling Points
Emissions to foul sewer will consist of process wastewater (SE2). Process wastewater emissions will be
discharged to the existing foul drainage system in Grange Castle Business Park which in turn discharges to
the South Dublin County Council foul drainage system which ultimately discharges to the Ringsend
Wastewater Treatment Plant. Details of the proposed monitoring and sampling point are indicated in Table
F.2(ii).
Tables F.2(i) identifies the monitoring and sampling parameters associated SE2. The location of this
monitoring points are illustrated in Figure F.2.1.
Grange BackUp Power Industrial Emissions Licence Review Application
349512/EDE/DDX/1/A 20 October 2015
99
F.2.4 Emissions to Foul Sewer Monitoring and Sampling Points
Emissions to foul sewer will consist of process wastewater (SE2). Process wastewater emissions will be
discharged to the existing foul drainage system in Grange Castle Business Park which in turn discharges to
the South Dublin County Council foul drainage system which ultimately discharges to the Ringsend
Wastewater Treatment Plant. Details of the proposed monitoring and sampling point are indicated in Table
F.2(ii).
Tables F.2(i) identifies the monitoring and sampling parameters associated SE2. The location of this
monitoring points are illustrated in Figure F.2.1.
Grange BackUp PowerMott MacDonald
F.2.4 Emissions to Foul Sewer Monitoring and Sampling Points
Emissions to foul sewer will consist of process wastewater (SE2). Process wastewater emissions will bedischarged to the existing foul drainage system in Grange Castle Business Park which in turn discharges tothe South Dublin County Council foul drainage system which ultimately discharges to the RingsendWastewater Treatment Plant. Details of the proposed monitoring and sampling point are indicated in TableF.2(ii).
Tables F.2(i) identifies the monitoring and sampling parameters associated SE2. The location of thismonitoring points are illustrated in Figure F.2.1.
99 349512r'EDE/DDX/1/A 20 October 2015
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
100
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Emission Point Reference No. SE-2
Parameter Monitoring frequency Accessibility of
Sampling Points
Sampling method Analysis method/
technique
Flow Continuous
Accessible n/a
Discharge line
flowmeter with
recorder
pH Continuous As above
On-line pH monitoring
and automatic sampler
On-line pH monitoring
and automatic sampler
Temperature Continuous As above Temperature probe Temperature probe
BOD Quarterly As above
n/a
Discharge line
flowmeter with
recorder
Dissolved Oxygen Quarterly As above Discharge line sampler Standard Method
Suspended Solids Quarterly As above As above As above
Nitrate (as N) Quarterly As above As above As above
Ammonia (as N) Quarterly As above As above As above
Chloride Quarterly As above As above As above
TPH Quarterly As above As above As above
100
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Emission Point Reference No. SE-2
Parameter Monitoring frequency Accessibility of
Sampling Points
Sampling method Analysis method/
technique
Flow Continuous
Accessible n/a
Discharge line
flowmeter with
recorder
pH Continuous As above
On-line pH monitoring
and automatic sampler
On-line pH monitoring
and automatic sampler
Temperature Continuous As above Temperature probe Temperature probe
BOD Quarterly As above
n/a
Discharge line
flowmeter with
recorder
Dissolved Oxygen Quarterly As above Discharge line sampler Standard Method
Suspended Solids Quarterly As above As above As above
Nitrate (as N) Quarterly As above As above As above
Ammonia (as N) Quarterly As above As above As above
Chloride Quarterly As above As above As above
TPH Quarterly As above As above As above
Grange BackUp Power
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Emission Point Reference No. _SE-2
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling method Analysis method/Sampling Points technique
Flow Continuous Discharge lineAccessible n/a flowmeter with
recorder
pH Continuous On-line pH monitoring On-line pH monitoringAs above . .and automatic sampler and automatic sampler
Temperature Continuous As above Temperature probe Temperature probe
BODQuarterly As above Discharge line
n/a flowmeter withrecorder
Dissolved OxygenQuarterly As above Discharge line sampler Standard Method
Suspended SolidsQuarterly As above As above As above
Nitrate (as N)Quarterly As above As above As above
Ammonia (as N)Quarterly As above As above As above
ChlorideQuarterly As above As above As above
TPHQuarterly As above As above As above
‘IOO
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
101
Grange BackUp Power Industrial Emissions Licence Review Application
Total Phosphorus (as
P) Quarterly As above As above As above
Conductivity Quarterly As above As above As above
101
Grange BackUp Power Industrial Emissions Licence Review Application
Total Phosphorus (as
P) Quarterly As above As above As above
Conductivity Quarterly As above As above As above
Grange BackUp PowerIndustrial Emissions Licence Review Application Mott MacDonald
Total Phosphorus (as
P) Quarterly As above As above As above
ConductivityQuarterly As above As above As above
101
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
102
F.2.5 Ambient Noise Monitoring and Sampling Points
Grange Back Up Power propose to undertake ambient noise monitoring at 9 no. locations on an annual
basis. These locations are illustrated in Figure F.2.2 Ambient Noise Monitoring Locations.
In addition to the above monitoring Grange Back Up Power will carry out secondary monitoring at a number
of fixed locations on the boundary of the power plant facility. These locations will be agreed as required with
the EPA prior to the operation of the power plant.
Details of the proposed ambient monitoring points are provided in Table F.2(ii).
Grange BackUp Power Industrial Emissions Licence Review Application
102
F.2.5 Ambient Noise Monitoring and Sampling Points
Grange Back Up Power propose to undertake ambient noise monitoring at 9 no. locations on an annual
basis. These locations are illustrated in Figure F.2.2 Ambient Noise Monitoring Locations.
In addition to the above monitoring Grange Back Up Power will carry out secondary monitoring at a number
of fixed locations on the boundary of the power plant facility. These locations will be agreed as required with
the EPA prior to the operation of the power plant.
Details of the proposed ambient monitoring points are provided in Table F.2(ii).
Grange BackUp PowerMott MacDonald
F.2.5 Ambient Noise Monitoring and Sampling Points
Grange Back Up Power propose to undertake ambient noise monitoring at 9 no. locations on an annualbasis. These locations are illustrated in Figure F.2.2 Ambient Noise Monitoring Locations.
In addition to the above monitoring Grange Back Up Power will carry out secondary monitoring at a numberof fixed locations on the boundary of the power plant facility. These locations will be agreed as required withthe EPA prior to the operation of the power plant.
Details of the proposed ambient monitoring points are provided in Table F.2(ii).
102
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
P1 29/09/15 SHY For PlanningMMcC PK
Key to symbols
App’dCh’k’dDescriptionDrawnDateRev
RevStatus
Drawing Number
Scale at A0
Eng check
Approved
Coordination
Dwg check
Drawn
Designed
Title
Notes
Client
Reference drawings
Security
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.2_P2.dwg Mar 16, 2017 - 9:09AM ric66327
TFW
©
Figure F.2.2
Noise Monitoring Locations
Grange Back Up Power Ltd
Others
S. Healy
M.McCarthy
Others
P.Kellly
1:2500 APR
MMD-349512-N-DR-00-XX-0012
P2 STD
Mott MacDonald
South Block, Rockfield,
Dundrum, Dublin 16,
Ireland
+353 (0)1 2916700
+353 (0)1 2916747
www.mottmac.com
This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
Mott MacDonald
1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH
ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS
AND SPECIFICATIONS.
2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
3. ANY DISCREPANCIES TO BE REPORTED TO THE
ARCHITECT.
4. ALL DIMENSIONS ARE IN MILLIMETERS.
5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE
SURVEY DATUM MALIN HEAD.
Ordnance Survey Map Ref No:
3261 - C , 3260 - D , 3325 - B & 3326 - A
OS MAPPING
1:50000
MONITORING & SAMPLING POINT
P2 10/03/17 ERN For Planning
MMcC PK
GRANGE BACK-UP POWER PLANT FACILITY - SITE LOCATION
Ordnance Survey Ireland Licence No. EN0034517©Ordnance Survey Ireland/Government of Ireland
125m250m0
1:2500
GRAND CANAL
FOOTBRIDGE
F
U
T
U
R
E
R
1
2
0
A
L
I
G
N
M
E
N
T
ESB
SUBSTATION
110KV
N
SITE LOCATION
GRAND CANAL
FOOTBRIDGE
F
U
T
U
R
E
R
1
2
0
A
L
I
G
N
M
E
N
T
ESB
SUBSTATION
110KV
P1 29/09/15 SHY For PlanningMMcC PK
Key to symbols
App’dCh’k’dDescriptionDrawnDateRev
RevStatus
Drawing Number
Scale at A0
Eng check
Approved
Coordination
Dwg check
Drawn
Designed
Title
Notes
Client
Reference drawings
Security
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.2_P2.dwg Mar 16, 2017 - 9:09AM ric66327
TFW
©
Figure F.2.2
Noise Monitoring Locations
Grange Back Up Power Ltd
Others
S. Healy
M.McCarthy
Others
P.Kellly
1:2500 APR
MMD-349512-N-DR-00-XX-0012
P2 STD
Mott MacDonald
South Block, Rockfield,
Dundrum, Dublin 16,
Ireland
+353 (0)1 2916700
+353 (0)1 2916747
www.mottmac.com
This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
Mott MacDonald
1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH
ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS
AND SPECIFICATIONS.
2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
3. ANY DISCREPANCIES TO BE REPORTED TO THE
ARCHITECT.
4. ALL DIMENSIONS ARE IN MILLIMETERS.
5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE
SURVEY DATUM MALIN HEAD.
Ordnance Survey Map Ref No:
3261 - C , 3260 - D , 3325 - B & 3326 - A
OS MAPPING
1:50000
MONITORING & SAMPLING POINT
P2 10/03/17 ERN For Planning
MMcC PK
GRANGE BACK-UP POWER PLANT FACILITY - SITE LOCATION
Ordnance Survey Ireland Licence No. EN0034517©Ordnance Survey Ireland/Government of Ireland
125m250m0
1:2500
GRAND CANAL
FOOTBRIDGE
F
U
T
U
R
E
R
1
2
0
A
L
I
G
N
M
E
N
T
ESB
SUBSTATION
110KV
N
SITE LOCATION
GRAND CANAL
FOOTBRIDGE
F
U
T
U
R
E
R
1
2
0
A
L
I
G
N
M
E
N
T
ESB
SUBSTATION
110KV
THIS DRAWING IS TO BE READ IN CONJUNCTION WITHALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGSAND SPECIFICATIONS.
DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.
ANY DISCREPANCIES TO BE REPORTED TO THEARCHITECT.
ALL DIMENSIONS ARE IN MILLIMETERS.
ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCESURVEY DATUM MALIN HEAD.
Key to symbols
— GRANGE BACK-UP POWER PLANT FACILITY - SITE LOCATION
G MONITORING & SAMPLING POINT
Reference drawings
' a - i — ' ' ' '
ep " Noise Monitoringf/I'
303627 232128
0
--—M
, t a Mott MacDonaldAg S::L“.f.i§i°§u§?:fif§'d’‘I
aw we;ansiei‘vfi "l. ire/2&4 =|:. l-lBail. Eur Em.
II I." AFT—ll. a bargains. I$51.19.: 5"”w' v i‘ "
h ' 'I ‘_ 0” “,"T—i: mm-hLocation: mm
W . 3* ‘ ——
(37,
_____, 4' I
32 egg M it M D Id T +353 (0)1 2916700. _ 0 ac and r +353 (0)1 2916747'; F”Gfilllerstown . ' 7 , ' - , ._,II Mhor Bridge‘kn k Ballymakally ; . ‘ _ ' 0nd ‘- 4' w www.mottmac.com
i . ‘ l, . - _ Client
/ 2‘: 7 __.-' I L '75- Grange Back Up Power Ltd
Aungierstjovtkand l0'4 .|.
E II b3,?- a y ane Klilcarbery
NewlandsCross Flds.
Figure F.2.2
,___r~. A fl , ’ ”i , Noise Monitoring Locations.' .5
' - Blundeistown J. ' 37 ~ ‘5 x: xx . I . _ 'r . H
.
es mans CW” 1 ,’ . '. _ J 'L, _ [-‘ .'1. 'E‘QAEa'%O”“e'/" "r “ 7 - ~ - -————-- .ero rome ‘ . - . _, -' ,z y6‘1! --~ 1' - -- l -— * i —— --OS MAPPING Scale at A0 Status Rev Security
© 1-5000“ 12500 APR P2 STDMott MacDonald
Ordnance Survey Map Ref No: Ordnance Ordnance Survey Ireland Licence No. EN0034517 Drawing Number©Ordnance Survey Ireland/Government of IrelandThis document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose. 3261 - C , 3260 - D , 3325 - B & 3326 - A 05 l Ut'VG)’ M M D 3495 1 2 N D R 00 XX 00 1 2
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties. Ireland
P:\Dublin\MPD\349512 - Grange Power\CAD\Drawings\Figure F.2.2_P2.dwg Mar 16, 2017 - 9:09AM ric66327
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
103
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No : ANL-1 (Northern Site Boundary)
Grid Reference: 303627E 232128N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-2(Eastern Site Boundary)
Grid Reference: 303705E 232085N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Equipment Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-3 (Southern Site Boundary)
Grid Reference: 303626 E 232050N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
103
Grange BackUp Power Industrial Emissions Licence Review Application
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No : ANL-1 (Northern Site Boundary)
Grid Reference: 303627E 232128N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-2(Eastern Site Boundary)
Grid Reference: 303705E 232085N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Equipment Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-3 (Southern Site Boundary)
Grid Reference: 303626 E 232050N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Grange BackUp Power
TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS
Monitoring Point Reference No : ANL-1 (Northern Site Boundary)Grid Reference: 303627E 232128N
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
Monitoring Point Reference No : ANL-2(Eastern Site Boundary)Grid Reference: 303705E 232085N
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Equipment Standard MonitoringTechniques
Monitoring Point Reference No : ANL-3 (Southern Site Boundary)Grid Reference: 303626 E 232050N
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
103
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
104
Grange BackUp Power Industrial Emissions Licence Review Application
Monitoring Point Reference No : ANL-4 (Western Site Boundary)
Grid Reference: 303545E 232094N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-5(Canal Footbridge)
Grid Reference: 303726E, 232285N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL6 (SDCC Attenuation Pond)_
Grid Reference: 304025E, 232210N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
104
Grange BackUp Power Industrial Emissions Licence Review Application
Monitoring Point Reference No : ANL-4 (Western Site Boundary)
Grid Reference: 303545E 232094N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL-5(Canal Footbridge)
Grid Reference: 303726E, 232285N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL6 (SDCC Attenuation Pond)_
Grid Reference: 304025E, 232210N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Grange BackUp Power
Monitoring Point Reference No : ANL-4 (Western Site Boundary)Grid Reference: 303545E 232094N
Molt MacDonald
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
Monitoring Point Reference No : ANL-5(Canal Footbridge)Grid Reference: 303726E, 232285N
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
Monitoring Point Reference No : ANL6 (SDCC Attenuation Pond)Grid Reference: 304025E, 232210N
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
104
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
105
Grange BackUp Power Industrial Emissions Licence Review Application
Monitoring Point Reference No : ANL7 (Adjacent Residential Property)_
Grid Reference: 303333E, 232222N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL8 (Grange Caste Business Park Location 1)_
Grid Reference: 303412E, 231791N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL9 (Grange Caste Business Park Location 2)_
Grid Reference: 303995E, 231815N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
105
Grange BackUp Power Industrial Emissions Licence Review Application
Monitoring Point Reference No : ANL7 (Adjacent Residential Property)_
Grid Reference: 303333E, 232222N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL8 (Grange Caste Business Park Location 1)_
Grid Reference: 303412E, 231791N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Monitoring Point Reference No : ANL9 (Grange Caste Business Park Location 2)_
Grid Reference: 303995E, 231815N
Parameter Monitoring frequency Accessibility of
Sampling point
Sampling method Analysis method / technique
Noise Annual Accessible Standard Method Standard Monitoring
Techniques
Grange BackUp Power
Monitoring Point Reference No :Grid Reference: 303333E, 232222N
ANL7 (Adjacent Residential Property)
Mott MacDonald
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
Monitoring Point Reference No :Grid Reference: 303412E, 231791N
ANL8 (Grange Caste Business Park Location 1)
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
Monitoring Point Reference No : ANL9 (Grange Caste Business Park Location 2)Grid Reference: 303995E, 231815N
Parameter Monitoring frequency Accessibility of Sampling method Analysis method / techniqueSampling point
Noise Annual Accessible Standard Method Standard MonitoringTechniques
105
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48
Grange BackUp Power Industrial Emissions Licence Review Application
106
F.3 Tabular Data on Monitoring and Sample Points
Point Code Point Type Easting Northing Verified Emission
A2-1 Atmospheric 303681 232116 No N0x, S02, CO2, CO, PM
A2-2 Atmospheric 303656 232117 No N0x, S02, CO2, CO, PM
SW-1 Surface Water 303696 232052 No Stormwater
SW-2 Surface Water 303607 232055 No Stormwater
SE-2 Sewer 303598 232079 No pH, BOD, Suspended
Solids, Nitrate (as N),
Ammonia (as N), Chloride, Mineral Oil,
Total Phosphorous
(as P).
ANL1 Noise 303627 232128 No Noise
ANL2 Noise 303705 232085 No Noise
ANL3 Noise 303626 232050 No Noise
ANL4 Noise 303545 232094 No Noise
ANL5 Noise 303726 232285 No Noise
ANL6 Noise 304025 232210 No Noise
ANL7 Noise 303333 232222 No Noise
ANL8 Noise 303412 231791 No Noise
ANL9 Noise 303995 231815 No Noise
Grange BackUp Power Industrial Emissions Licence Review Application
106
F.3 Tabular Data on Monitoring and Sample Points
Point Code Point Type Easting Northing Verified Emission
A2-1 Atmospheric 303681 232116 No N0x, S02, CO2, CO, PM
A2-2 Atmospheric 303656 232117 No N0x, S02, CO2, CO, PM
SW-1 Surface Water 303696 232052 No Stormwater
SW-2 Surface Water 303607 232055 No Stormwater
SE-2 Sewer 303598 232079 No pH, BOD, Suspended
Solids, Nitrate (as N),
Ammonia (as N), Chloride, Mineral Oil,
Total Phosphorous
(as P).
ANL1 Noise 303627 232128 No Noise
ANL2 Noise 303705 232085 No Noise
ANL3 Noise 303626 232050 No Noise
ANL4 Noise 303545 232094 No Noise
ANL5 Noise 303726 232285 No Noise
ANL6 Noise 304025 232210 No Noise
ANL7 Noise 303333 232222 No Noise
ANL8 Noise 303412 231791 No Noise
ANL9 Noise 303995 231815 No Noise
Grange BackUp PowerIndustrial Emissions Licence Review Application Mott MacDonald
F.3 Tabular Data on Monitoring and Sample Points
Point Code Point Type Easting Northing Verified Emission
A2-1 Atmospheric 303681 232116 No N0x, 802, CO2,00, PM
A2-2 Atmospheric 303656 232117 No N0x, 802, CO2,00, PM
SW-1 Surface Water 303696 232052 No Stormwater
SW-2 Surface Water 303607 232055 No Stormwater
SE-2 Sewer 303598 232079 No pH, BOD,Suspended
Solids, Nitrate(as N).
Ammonia (asN), Chloride,
Mineral Oil,Total
Phosphorous(as P).
ANL1 Noise 303627 232128 No Noise
ANL2 Noise 303705 232085 No Noise
ANL3 Noise 303626 232050 No Noise
ANL4 Noise 303545 232094 No Noise
ANL5 Noise 303726 232285 No Noise
ANL6 Noise 304025 232210 No Noise
ANL7 Noise 303333 232222 No Noise
ANL8 Noise 303412 231791 No Noise
ANL9 Noise 303995 231815 No Noise
106
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 18-05-2017:03:04:48