SAM-LINE CONSULT سـامت الهندسيةلتصميمايـن ل BRIGADIER ENGINEER: SAMEH F. ISKANDER بية بطاقة ضري: 803 - 647 - 320 سجل هندسى: 8377 / 4 SAM-LINE CONSULT - For Engineering Designs Tel. 22910760 01099921432 E mail: [email protected] Address: (1) El Rahala El Baghdady Street, Ard El Golf, Heliopolis, Cairo.

Transcript of شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult...

Page 1: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

SAM-LINE CONSULT

BRIGADIER ENGINEER: SAMEH F. ISKANDER اليـن للتصميمات الهندسية –سـام 8377/4:هندسىسجل 320 - 647 - 803: بطاقة ضريبية

SAM-LINE CONSULT - For Engineering Designs – Tel. 22910760 – 01099921432 E mail: [email protected]

Address: (1) El Rahala El Baghdady Street, Ard El Golf, Heliopolis, Cairo.

Page 2: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 2

Introduction: • SAM-LINE Consult for Engineering Designs, established on 2009, specialized in consulting

civil protection systems and reviewing the projects according to the requirements of the national

and international codes.

• Our company has a very capable engineering team who ensures that their innovative designs are

based on the standards of the National Fire Protection Association (NFPA) for “Fire Fighting

Network, Fire Fighting Sprinkler System, Fire Pump Set, FM200 System, CO2 System, ..etc”.

Vision: • Being a national leader in Egypt and the Middle East in providing comprehensive and reliable fire

protection solutions, implementing the fire protection code and civil defence requirements in the

least financial costs inquired to the client and the executing of the project since its idea stage till

turn-key delivery stage.

Purpose: • To be a leader in the fire protection plans by providing enhanced services, relationship and

profitability.

Mission: • Provide insurance system against fire hazards.

• Immediate response for our client's needs.

• Achieve complete client satisfaction.

• Build long-term relationships with our clients.

• Provide & Improve high-quality services.

Goals: • Regional expansion in the field of fire protection engineering consults and develops a strong base

of key customers.

• Increase the assets and investments of the company to support the development of services.

• To build a good reputation in the field fire protection engineering consults and become a key

player in the industry.

Quality Policy:

Page 3: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 3

• To empower customers to secure Life, Property and Business by delivering high quality and

innovative fire protection solution using world class techniques process with the finest

engineering technology.

• SAM-LINE is committed to working towards continuous improvement with the aim of meeting

with customer requirements and expectations.

• SAM-LINE Committed to comply with requirements and continually improve the effectiveness

of the quality management system

Values: • We consistently demonstrate high ethical standards in our actions. We honour our agreements and

are honest in our communications. We respect, care and have dignity towards all individuals and

value our diversity as a source of strength.

• We RESPECT, CARE and have DIGNITY towards all individuals and value our diversity as a

source of strength.

• We believe in teamwork and the limitless possibilities of collaborative energy. We achieve

excellence by setting collective goals ahead of personal interests. We support and encourage open

communication and meaningful cooperation among colleagues from varying backgrounds and

disciplines.

• We lead by example and establish an environment of continuous improvement, provide

opportunities for people to grow, both personally and professionally. Care and act with

compassion.

• We exceed customer expectations for value and service. We build and maintain customer

relationships and ensure long-term satisfaction.

• We strive for continuous improvement in our performance, measuring results carefully, and

ensuring that integrity and respect for people are never compromised.

• Quality is ingrained in the work of our colleagues and all our values. We have a relentless passion

for quality in everything we do.

• We play an active role in making our community a safe and better place to live and work.

• We constantly seek innovative ways to enhance our services and provide value to our customers.

We seek continuous learning by adapting existing knowledge, as well as through research and

experimentation.

Strengths: • Global thinking with an amateur spiritual.

Page 4: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 4

• We are absolutely customer oriented with having long-term relationships with customers.

• The management team and also the employees are experienced in their area.

Our Clients

We are proud to offer high quality to our multi-national clients.

Specialization:

• Study the engineering projects, prior to construction stage and reviewing them according to the

requirements of the Egyptian Design Codes and implementing requirements of the Egyptian Fire

Protection Code and/or other relevant code's (GCC - IBC - NFPA - Saudi Arabia code).

• Prepare the engineering design drawings, the bill of quantity, the technical specifications for the

automatic fire alarm systems and firefighting systems.

• Preview and review of existing projects, the work of building protection systems, evaluating their

validity, the efficiency of testing, receiving all the protection systems for the safety of users and

the protection of facilities from the dangers of fire according to the requirements of the fire

protection Egyptian Code.

• Preview all industrial projects, tourism, educational, offices, residential and assembly in order to

identify existing fire hazards and develop suitable practical solutions.

Experience:

➢ Engineering consulting office in the scope of fire protection:

• Technical advice in the field of fire protection.

• Design and Supervise the implementation of fire water networks.

• Design of sprinkler systems and automated fire alarm systems.

Page 5: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 5

• Selection of appropriate types of chemical treatment against fire.

• Supervision of all electro-mechanical installations.

• Training in fire-fighting and land rescue.

➢ Technical Consultancy:

• Study and analysis of the potential risks in the projects, and find technical solutions and the

process of harmonization.

• Study of the technical subjects for the field of fire protection.

• Study the problems of protection in the existing projects and find appropriate solutions.

• Reviewing and identifying of tourism projects, industrial, high towers and various

entertainment buildings with the international codes requirements such as American Code

(NFPA 13), British code, the Arab common code requirements for fire protection and also the

Egyptian Code of the foundations of design and implementation requirements to protect

buildings in case of fire.

• Setting fire hazard protection plans and ways to control it in the large projects in all fields.

• Develop security plans to maintain the facilities from the dangers of attacks, bombings and

theft cases.

• Design locations; arrange teams of firefighters and selection of technical staff.

• Participate in the classification, selection of arrangements, fire-fighting equipment, safety

equipment' sand personal equipment for workers.

➢ Design of the various fire water networks:

• External fire water networks for large locations.

• Firewater networks inside the dry or moist buildings.

• Design pumping rooms and fire water tanks.

➢ Design sprinkler systems and automated fire alarm:

• Automatic fire alarm systems with all their various types.

• Evacuation systems and internal radio.

• Various sprinkler systems.

• Sprinkler systems by other fire tools such as Co2, Fm 200, Inergen and foam.

• Modern sprinkler systems…water mist.

➢ Selection of appropriate types of fire chemical treatment:

• Treatment of the doors by using inflammable delayed materials.

Page 6: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 6

• Treatment of the furniture, curtains and flooring.

➢ Supervision of all electro-mechanical installations:

• Supervision of the implementation, testing and receipt of all the electromechanical

installations, to ensure their compatibility with the rest of the fire protection systems in the

site.

➢ Fire-fighting training:

• Training lectures in the field of fire-fighting.

• Training lectures in the field of fire protection.

• Training lectures specialized in the application of fire code.

• Training lectures in the protection of different factories.

• Training lectures in the protection of petroleum locations.

• Training lectures in the protection of the tourist locations.

• Training lectures in the operation and maintenance of various systems of protection.

• Training lectures in the development and implementation of evacuation plans.

Sam-Line works The Office Establishment date 1/8/2009:

Study and review of engineering drawings of Various Projects according to the Egyptian fire code,

and submitted as a document within the licensing requirements in accordance with the Construction

Law number (119) year 2008 as a specialized office without referring to the civil defence authorities

such as :

1. El Lessan hotel – Raas Al-Bar – K.A.F. Consultant – We worked on Reviewing of the

architectural design, issuing of drawings, studying and submitting a life safety report according to

the Egyptian Fire Protection Code.

2. Secon Nile Towers (Hilton El Maadi) & the Residential Hotel Tower – El Maadi – Ehaf

Consulting Engineers – We worked on Reviewing of the architectural design, issuing of

drawings, studying and submitting a life safety report according to the Egyptian Fire Protection

Code.

Page 7: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 7

3. Steigenberger Hotel – Tahrir Square – Ehaf Consulting Engineers – We worked on Reviewing

of the architectural design, issuing of drawings, studying and submitting a life safety report

according to the Egyptian Fire Protection Code.

4. Al Alamain Residential Complex – Pavillion Architects – We worked on Reviewing the

architectural design according to the Egyptian Fire Protection Code.

5. El Alamein Hotel – Sidi Abdel Rahman – Marassi El Alamein – Emaar Company – We worked

on Reviewing of the architectural design, issuing of drawings, studying and submitting a life

safety report according to the Egyptian Fire Protection Code.

6. Royal Maxim Palace Kempinski Hotel – New Cairo – (Maxim Real Estate Development) –

Prof. Dr Akram Farouk Office – We worked on Reviewing of the architectural design, issuing of

drawings, studying and submitting a life safety report according to the Egyptian Fire Protection

Code.

7. Accor Hotel – Tahrir Square – Ehaf Consulting Engineers – We worked on Reviewing of the

architectural design, issuing of drawings, studying and submitting a life safety report according to

the Egyptian Fire Protection Code.

8. Hilton El Jubail Hotel – Saudi Arabia – Ehaf Consulting Engineers – We worked on Reviewing

of the architectural design, issuing of drawings, studying and submitting a life safety report

according to the Egyptian Fire Protection Code.

9. Al Azizia Hotel – Riyadh – Al Amar Consulting Group – We worked on Reviewing the

architectural design, issuing of drawings, studying and submitting a life safety report according to

the Egyptian Fire Protection Code.

10. Boutique Hotel & Spa – Sahl Hasheesh – We worked on Reviewing the architectural design,

issuing of drawings, studying and submitting a life safety report according to the Egyptian Fire

Protection Code.

11. Marassi Hotel – HuB 1 – North Coast – Ehaf Consulting Engineers – We worked on Reviewing

of the architectural design, issuing of drawings, studying and submitting a life safety report

according to the Egyptian Fire Protection Code.

12. Majestic Hotel – Sharm El Sheikh – Raafat Miller Consulting (RMC) – We worked on

Reviewing of the architectural design, issuing of Drawings, studying and submitting a life safety

report according to the Egyptian Fire Protection Code.

13. Holiday Inn Hotel – Nasr City – Al Amar Consulting Group – We worked on Reviewing of the

architectural design, issuing of Drawings, studying and submitting a life safety report according

to the Egyptian Fire Protection Code.

Page 8: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 8

14. Tahrir Hotel – Tahrir Square – Ehaf Consulting Engineers – We worked on Reviewing of the

architectural design, issuing of drawings, studying and submitting a life safety report according to

the Egyptian Fire Protection Code.

15. The United Company For Glass Bottles – 10th of Ramadan City (Ugc) – We worked on the

automatic sprinkler firefighting designs.

16. Ain Al Aziziyah Tower – Jeddah – Saudi Arabia – Al Amar Consulting Group – The project

consists of (5) stars’ hotel, mercantile mall, administrative towers, parking cars' garages and

mosque.

17. Arab Prince – Morocco – We worked on the residential hotel building.

18. Cairo Festival City Project (CFC) – New Cairo – Al Amar Consulting Group – We worked on

the administrative buildings.

19. KidZania Cairo Festival City (CFC) – New Cairo – Al Amar Consulting Group.

20. Madinaty Project – Al Amar Consulting Group – We worked on the residential buildings.

21. Children Amusement Park – Khartoum – Al Amar Consulting Group.

22. Syrian Textile Factory – Shabatex – We worked on reviewing the project designs.

23. Retirement And Social Insurance Building – Sultanate Of Oman– Al Amar Consulting Group.

24. Arma Oil Industries – 10th of Ramadan City – We worked on the firefighting systems designs

of some stores and buildings.

25. Touristic And Financial Cairo Center Project – The project consists of (5) star hotel, (4) star

hotel, mercantile mall, cinemas complex, (7) administrative towers, restaurants and cafeterias and

parking cars' garages.

26. Army Conference Center Project – New Cairo – International Conference Center – The

project consists of conference rooms, theatre and press center.

27. Schlumberger Company For Oil Services – 6th Of October City – We worked on the

administrative headquarters project and maintenance workshops – The project consists of

administrative buildings, maintenance workshops, stores, employees' buildings and garages.

28. Al Azhar Al–Sharif Library Project – The project consists of reading rooms, meeting rooms

and books stores.

29. The Islamic Institute Project – The project consists of a residential building for students,

mosque, classrooms' building and administrative building.

30. Madinaty Project – Ehaf Consulting Engineers – We worked on the residential buildings.

31. Eva Cosmetics Factory – Saudi Arabia – The project consists of the production halls,

administrative buildings stores and laboratories.

32. Hilton AL Jubail Hotel Project – Saudi Arabia.

Page 9: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 9

33. Study Of Sodic Project – The project consists of administrative buildings, mercantile and

second stage in Sheikh Zayed City.

34. New Glass Company – 10th of Ramadan City – We worked on the firefighting networks designs

for the stores of this project.

35. Morgan Factory – Al Obour City – We worked on firefighting networks.

36. The Mercantile And Administrative Project (Valley Gate) – New Cairo – Ehaf Consulting

Engineers.

37. La Vida Compound – New Heliopolis.

38. The German Cultural Center (Goethe Institute) – Dokki – Cairo Approved Fire Stop

Supervision From The German Side.

39. Police Hospital Project – Minya – Abassya.

40. Hilton Hotel Project – Masaken Sheraton.

41. Regency Hotel Project – Haram.

42. 24 Floors Project – Zamalek – We worked in the residential building.

43. The Mercantile Mall Roaya – New Cairo.

44. Misr Café Factory For Food Industries – 10th of Ramadan City.

45. Mivida – New Cairo – We worked on the residential compound.

46. New Giza University – We worked on the first and second stages of this project.

47. Jack Company For Electrical Appliances Project – 10th of Ramadan City – We worked on

firefighting networks designs for the stores of this project.

48. Ayman Effendi Project – Belbais Fire Fighting – We worked on networks designs for the stores

of this project.

49. Lycée Français School – We worked on preparing an evacuation plan for this project.

50. Match Factory – 10th of Ramadan City.

51. Pasta Factory – 10th of Ramadan City.

52. Al–Salam International Hospital – Cairo.

53. Rofayda Project – WSP Hospital – 6th of October City.

54. Police Hospital Project – Luxor.

55. Police Academy Hospital.

56. Maxim Hotel (Kempinski) (5) Stars – New Cairo.

57. Maxim Mall – New Cairo.

58. Maxim Company – Masaken Sheraton – We worked on the administrative building.

59. Maxim Company – Maxim Resort Club – We worked in the administrative building.

60. TE Data Stores – Abu Rawash – We worked on the study and review of the safety procedures.

Page 10: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 10

61. Stone Towers Project – New Cairo – International British Experience House – The project is

considered as one of the largest current projects in the Middle East – The project is reviewed by

us as a Local Specialist Consultant Office – The project consists of (18) office towers, a hotel

tower and retail outlets in addition to the (3) basements used as a garage for cars their total land

area around (50) acre.

62. Jabal Omar Development Project – Kaabain Meccaand A (PODIUM) – We worked on the

architectural study, preparing a technical report of civil defence, reviewing the automatic fire

alarm systems and the different sprinkler systems and firefighting water networks of building no.

(S6) – The project consists of (8) floors including (3) basements and the upper tower that consists

of (24) floors.

63. Jabal Omar Development Project – Kaabain Meccaand A (PODIUM) – We worked on the

architectural study, preparing a technical report of civil defence, reviewing the automatic fire

alarm systems and the different sprinkler systems and firefighting water networks of building no.

(S7, S8, S9, S10 and S11) – The project consists of (8) floors including 3 basements and (3) upper

towers that consist of (24) floors.

64. Emaar Square Project – Uptown Cairo – Mokattam – We worked on the architectural study,

preparing a technical report of civil defence, the automatic fire alarm systems and the different

sprinkler systems and firefighting water networks – The project consists of (3) basements, ground

floor and (4) upper floors.

65. Towers Project – Uptown Cairo – Mokattam – We worked on the architectural study, preparing

a technical report of civil defense, reviewing the designs of the automatic fire alarm systems and

the different sprinkler systems and firefighting water networks of offices – The project consists of

(4) basements, ground floor and (12) upper floors.

66. Residential Towers Project – Uptown Cairo – Mokattam – We worked on the architectural

study, preparing a technical report of civil defence, reviewing the designs of the automatic fire

alarm systems, the different sprinkler systems and firefighting water networks – The project

consists of (2) basements, ground floor and (4) upper floors.

67. Cairo Financial & Touristic Center (Cairo Festival) Project – Uptown Cairo – Mokattam –

We worked on the architectural study, preparing a technical report of civil defence, reviewing the

designs of the automatic fire alarm systems and the different sprinkler systems and firefighting

water networks. The project consists of (4) basements and (5) floors covering – The project area

followed by (9) towers and each tower include (9) upper floors.

68. Zamalek Tower (The View Residence) Project – We worked on the architectural study,

preparing a technical report of civil defence, reviewing the designs of the automatic fire alarm

Page 11: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 11

systems and the different sprinkler systems and firefighting water networks – The project consists

of a basement, ground floor and (24) upper floors.

69. Boutique Hotel Project – Zamalek – We worked on the architectural study, preparing a

technical report of civil defence, reviewing the designs of the automatic fire alarm systems, the

different sprinkler systems and firefighting water networks – The project consists of a basement,

ground floor and (4) upper floors.

70. ABB Company – 10th Of Ramadan City – We worked on the architectural study, preparing a

technical report of civil defense, adding the requirements of the design of automatic fire alarm

systems and the different sprinkler systems and firefighting water networks of the administrative

building – The project consists of (1) ground floor and (3) upper floors.

71. Adera Compound Phase 02 Project – New Cairo – We worked on the architectural study,

preparing a technical report of civil defense, adding the requirements of the design of automatic

fire alarm systems and the different sprinkler systems and firefighting water networks in the

residential, administrative and commercial compounds – The project consists of (4) basements,

ground floor and (6) upper floors.

72. Sunny Days Hotels And Resorts Project – Heliopolis – Cairo – We worked on the

architectural study, preparing a technical report of civil defense, adding the requirements of the

design of automatic fire alarm systems and the different sprinkler systems and firefighting water

networks – The project consists of (2) basements, ground floor and (3) upper floors.

73. Central Workshop Of Metro Project – Fourth Line – Haram – We worked on the architectural

study, preparing a technical report of civil defence, adding the requirements of the design of

automatic fire alarm systems and the different sprinkler systems and firefighting water networks –

The project consists of (18) buildings with different assemblies and activities.

74. Horeya Tower In Horeya Street – Heliopolis – We worked on the architectural study,

preparing a technical report of civil defense, adding the requirements of the design of automatic

fire alarm systems and the different sprinkler systems and firefighting water networks of

residential and commercial buildings – The project consists of (2) basements, ground floor and

(12) upper floors.

75. Police Academy Hospital New Project – Abbasiya – We worked on the architectural study,

preparing a technical report of civil defence, adding the requirements of the design of automatic

fire alarm systems and the different sprinkler systems and firefighting water networks – The

project consists of a basement, ground floor and (12) upper floors.

76. Police Academy Hospital New Project – Minya – We worked on the architectural study,

preparing a technical report of civil defence, adding the requirements of the design of automatic

Page 12: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 12

fire alarm systems and the different sprinkler systems and firefighting water networks – The

project consists of a basement, ground floor and (7) upper floors.

77. Al Salam International Hospital – Maadi – We worked on the architectural study, preparing a

technical report of civil defence, adding the requirements of the design of automatic fire alarm

systems and the different sprinkler systems and firefighting water networks – The project consists

of a basement, ground floor and (12) upper floors.

78. San Paul Charity Center Hospital (AvaBavly Charity Center) – Hadayek El Kobba – We

worked on the architectural study, preparing a technical report of civil defense, adding the

requirements of the design of automatic fire alarm systems and the different sprinkler systems and

firefighting water networks – The project consists of a basement, ground floor and (2) upper

floors.

79. Maxim Commercial Mall Project – New Cairo – We worked on the architectural study,

preparing a technical report of civil defence, adding the requirements of the design of automatic

fire alarm systems and the different sprinkler systems and firefighting water networks – The

project consists of (2) basements, ground floor and (2) upper floors.

80. City Center Commercial Mall – Alexandria – We worked on the architectural study, preparing

a technical report of civil defense, adding the requirements of the design of automatic fire alarm

systems and the different sprinkler systems and firefighting water networks of food court

developing project – The project consists of a basement, ground floor and (4) upper floors.

81. Al Jubail Industrial Area – Kingdom of Saudi Arabia – We worked on the study review of

facilities company buildings according to the American national fire protection association NFPA

101.

82. BG Egypt Petroleum Company – 5th Settlement – New Cairo – We worked on the study

review of the administrative building according to the Egyptian fire protection code.

83. American School In Cairo – We worked on the study of the architectural drawings for the

buildings of the 2nd preparatory stage and library and applied the Egyptian fire protection code

requirements according to NFPA requirements.

84. French School Lycée Français Du Caire – Merag – New Cairo – We worked on preparing an

evacuation plan.

85. Partner Royal Alexandria Hotel Project – El Manshia – Alexandria – We worked on the study

of the engineering drawings, hazards analysis and prepare designs & drawings implantation of

automatic firefighting water sprinkler.

86. GPX Data Center – Cairo II – We worked on the study of the engineering drawings and prepare

designs & drawings implantation of automatic firefighting water sprinkler, FM 200, CO2 of the

administrative building.

Page 13: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 13

87. Arcan Buildings Project – Sheikh Zayed City – We worked on the study review of

entertainment, commercial and administrative buildings according to the Egyptian fire protection

code.

88. SODIC Buildings Project – Sheikh Zayed City – We worked on the study review of the

administrative and commercial building according to the Egyptian fire protection code and issue

the drawings of fire protection according to the code requirements.

89. Boutique Hotel Project – Zamalek – We worked on the study review of the buildings according

to the Egyptian fire protection code, adding the requirements of the design of automatic fire alarm

systems and the different sprinkler systems and fire hydrants.

90. Al Mansour (GM) For Trading And Distribution Company – Cairo – We worked on

preparing an emergency & evacuation plan, analyzing hazards, reviewing the current protection

systems and designing new systems for the new administrative buildings, storages and

refrigerators.

91. Al Mansour (GM) For Trading And Distribution Company – Alexandria – We worked on

preparing an emergency & evacuation plan, analyzing hazards, reviewing the current protection

systems and designing new systems for the new administrative buildings, storages and

refrigerators.

92. Egyptian Anode Blocks Company – The First Industrial Area – North Gulf Of Suez – Ain

Sokhna – We worked on providing the technical study for establishing the factory.

93. Disability Children – New Cairo – We worked on the study review for the developing skills

according to the Egyptian fire protection code requirements.

94. Administrative Area – Investment Institute – Nasr City – Cairo – We worked on the study

review for developing the buildings according to the Egyptian fire protection code requirements.

95. Royal Chemicals Factory – The Industrial Area – South Of Port Said – We worked on the

study review for the buildings according to the Egyptian fire protection code requirements and

reviewing, testing and approving the applied protection systems.

96. Royal Cosmetics Factory – The Industrial Area – South of Port Said – We worked on the study

review, testing and approving the applied protection systems for the buildings according to the

Egyptian fire protection code requirements.

97. Palm Oil Tanks Area – The Industrial Area – South of Port Said – We worked on the study

reviewing, testing and approving the applied protection systems in the project according to the

Egyptian fire protection code requirements.

98. Delta Express Cargo Company – Katameya – We worked on the study of the storages,

reviewing, testing and approving the applied protection systems in the project according to the

Egyptian fire protection code requirements.

Page 14: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 14

99. Residential Villa Plot No. (39), Group (13) Villas – Heliopolis – We worked on preparing a

technical revised report for the construction of this project according to the civil defence

requirements.

100. Specialty Hospital Project – Dr Abdel Qader Fahmy For Birth– New Heliopolis City– We

worked on preparing a technical revised report for the construction of this project according to the

civil defence requirements.

101. AL–Nour Cultural And Entertainment Center – Plot No. (2A) Of The Compound Services

(A) – New Heliopolis City – We worked on preparing a technical revised report for the

construction of the building according to the fire protection requirements.

102. Commercial Mall – Plot No. (2B) Compound Services (A) North Of Third District – New

Heliopolis City – We worked on preparing a technical revised report for the construction of this

project.

103. Electric Cables Chinese Egyptian Company – Industrial Zone – North Of Suez Gulf – Ain

Sokhna – We worked on the study review for the factory according to the fire protection

requirements.

104. Nada And Yara Ismail Mohamed Project – Plot No. (25) Group (22 P) Second District –

New Heliopolis City – We worked on the study review for the apartment building.

105. Entertainment Cultural Building Project – The Services Area (A) North Of Third District –

Plot No. (L.A) – New Heliopolis City – We worked on preparing a technical revised report for the

construction of this project according to the fire protection requirements.

106. Egyptian – Austrian Company For Import And Export – The Services Area (B) North of

Second District Plot No. (3A) – New Heliopolis City – We worked on preparing a technical

revised report for the construction of the commercial building project according to the fire

protection requirements.

107. OFAN Apartment Building Project – Faisal Street – Darbnegm – Sharkia Governorate –

We worked on preparing a technical revised report for the construction of this project according

to fire protection requirements.

108. Association For Judges (2) – Zagazig – Sharkia Governorate – We worked on preparing a

technical revised report for the construction of this building according to the fire protection

requirements.

109. Eldwer Restaurant For Pastry – EL Manial – We worked on preparing a technical revised

report and submit the report including solutions for the current technical problems.

110. The National River Port Management Company – Port of Imbaba River – We worked on

providing designs, engineering drawings and requested documents of fire hydrant network and

automatic firefighting for the storages of this project.

Page 15: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 15

111. PAKIN Ink Factory – El Obour City – We worked on providing designs, engineering

drawings and requested documents of firefighting and the foam system for storages of finished

products.

112. PAKIN Ink Factory – El Obour City – We worked on providing designs, architectural

drawings and requested documents of CO2 firefighting system and fire alarm system for (7) main

electric rooms.

113. El Gawda Laboratory – PAKIN Ink Factory – El Obour City – We worked on providing

designs, engineering drawings and requested documents of Inergen firefighting system and its fire

alarm system, laboratory of examination and electric distribution room.

114. El SEWEDY Company – 6th of October City – We worked on providing designs, engineering

drawings and technical specifications of the fire alarm system, water sprinkler firefighting of the

commercial mall and the administrative office.

115. Carmen Company For Paper Products – Plot No. (192) – The First Industrial Zone – 6th of

October City – We worked on preparing a technical revised report of the fire protection

requirements of ramping the floor of the storages.

116. Carmen Company For Paper Products – 6th of October City – We worked on a study of the

fire protection and the fire protection code requirements.

117. Carmen Company For Paper Products – 6th of October City – We worked on providing

designs and implanted drawings.

118. El Sawy Culture Wheel – Zamalek – Cairo – We worked on providing a design of the water

sprinkler automatic fire fighting system.

119. Moon Valley Residential Compound – New Cairo – We worked on providing a design of the

water sprinkler automatic fire fighting system and a fire hydrant for the commercial center

project.

120. ARABELLA Court Project – New Cairo – We worked on providing designs, engineering

drawings for the automatic fire fighting system.

121. The Turkey Company – EVYAP MISIR – Borg El–Arab City – We worked on the study of

the engineering drawings, hazards analysis, preparing designs of water sprinkler automatic fire

fighting system, firefighting – foam system and automatic fire alarm systems for soup and

cosmetic factory

122. National Archive For Film of National Cinema Center – We worked on providing designs,

engineering drawings and technical specifications of (5) CO2 automatic firefighting systems to

the storages.

Page 16: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 16

123. The Armed Forces – Cairo – We worked on providing designs, engineering drawings and

technical specifications of fm200 automatic firefighting system of the control room and computer

room.

124. Girls Expatriates House – 9th District – Nasr City – Cairo – We worked on a study of the

engineering drawings, review of the protection requirements and the fire protection code

requirements of the residential apartment building.

125. R D C For Real Estate Investing – New Cairo – We worked on a study of the engineering

drawings, review of the protection requirements and the fire protection code requirements of a

commercial and administrative center project.

126. Our Lady Of Perpetual Succour School – Heliopolis – Cairo – Egypt – We worked on a

study of the engineering drawings, review of the protection requirements and the fire protection

code requirements.

127. Shaker Mohamed Hamouda Factory For Textile – El Obour City – We worked on a study of

the engineering drawings, review of the protection requirements and the fire protection code

requirements.

128. Ibn Sina Pharma – Ard Shalaby – El Minya – Egypt – We worked on a study of the

engineering drawings, review of the protection requirements and the fire protection code

requirements of the administrative office.

129. Mercedes Cars Maintenance Center Exhibition – New Cairo – We worked on a study of the

engineering drawings, review of the protection requirements and the fire protection code

requirements.

130. Nouval Factory For Houseware – We worked on a study of the butane gas store station that is

liquefied in the factory, the application of protection requirements and the organized decisions of

issuing the license.

Certifications

1. Scientific Research Academy And Technology – Thanks Letter

2. OSHA - Construction Safety & Health

3. OSHA - General Industry Safety & Health

4. Basic Fire Fighting - Institute of Civil Defense (Jun 1987)

5. Basic Defense and Rescue - Institute of Civil Defense (Dec 1987)

6. Advanced Training In Ammunitions, Explosives And Bombs Demolition - Institute of Civil

Defense (Jan. 1992)

Page 17: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 17

7. Army Terrorism, Search And Fighting - Royal School Of Military Engineering – U.K (Feb.

1995)

8. Operator & Maintenance Training On Andros Mark V-A ROBOT - Remoted Oak Ridge,

Tennessee (Mar. 1996)

9. Heavy Hydraulic Fire Fighting Equipment - Institute of Civil Defense (May 1997)

10. The Use & maintenance of light F.F. vehicles FALCON, Gazelle & turntable ladders -

IVECO (Sep. 1997)

11. Customer Service Technical Training - IVECO (Oct. 1997)

12. The Use And Maintenance On The Aerial Ladder Platform Model Vt420f - SIMON (June

1998)

13. Protection Of Buildings From Fire - Egyptian Society Of Engineers (Nov. 1998)

14. Technical Training Course Concerning the Ladder DLK 52 VARIO - IVECO (Dec. 1998)

15. Disaster Management Course: CRANFILED University – U.K. (Mar. 1999)

16. The Use & Maintenance Of Turntable Ladder DLK 23-12 VARIO CC - IVECO (Nov. 1999)

17. Information Systems Training Course - Ministry of Interior (Jul. 2001)

18. Preventing And Fighting Hazardous Materials Fire Course - Institute of Civil Defense (Jan.

2001)

19. The Computer Science Basics - Ministry of Interior (Jul. 2001)

20. Design And Strengthen The Tunnels Course - Ministry of Industry (Feb. 2001)

21. International Humanitarian Law - International Committee of the Red Cross (Feb. 2002)

22. The Use & Maintenance Of Turntable Ladder DLK 37 VARIO Cc - IVECO (Jan. 2004)

23. ENSOSP – French Rescue Team (Dec. 2004)

24. Innovative Engineering Design For Fire Trucks Contest - Ministry of Interior (Jun 2004)

25. US OSHA - General Industry & Construction For Supervisors - American University (Mar.

2007)

26. OSHA - Standards For Laboratory Safety & Handling Hazardous Material - American

University (Mar. 2007)

27. USA – OSHA General Course #511, USA – OSHA Construction Course #510 - American

University (Jul. 2007)

28. OSHA General Industry #511 – AREX For Training with Consultations with Rocky

Mountain Education Center (Dec. 2010)

29. OSHA Construction Industry # 510 – AREX For Training With Consultations With Rocky

Mountain Education Center (Dec. 2010)

30. HASWOPER – AREX For Training With Consultations With Rocky Mountain Education

Center (Dec. 2010)

Page 18: شــبكـات ميــاه الإطــفاء · CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs 2 SAM-LINE CONSULT - For Engineering Designs Introduction:

CONTINUE – Company Profile - SAM-LINE Consult For Engineering Designs

SAM-LINE CONSULT - For Engineering Designs 18

31. Disaster Site Worker – AREX For Training With Consultations With Rocky Mountain

Education Center (Dec. 2010)

32. Accident Investigation – AREX For Training With Consultations With Rocky Mountain

Education Center (Dec. 2010)

33. First Aid & CPR – AREX For Training With Consultations With Rocky Mountain Education

Center (Dec. 2010)

34. CETU – OSHA - Professional Diploma In Occupational Health – Safety & Environmental

Control (Dec. 2010)

35. OSHA – #7600 – Disaster Site Worker (Dec. 2010)

36. Fire Pumps Systems & Elite Software Program – ECDT (Sep. 2012)

37. Fire Safety Engineer Programme - University of Cambridge (Jan. 2013)

38. NFPA 101 (2018) Life Safety Code – NFPA (Mar. 2019)

39. Consultant Accident Investigation - Arab Foundation (Apr. 2019)

40. Consultant Emergency Plan - Arab Foundation (Apr. 2019)

41. Internal Audit - Arab Foundation (Apr. 2019)

42. Preparing files & reports on safety & health professional program - Arab Foundation (Apr.

2019)

43. Safety Consultant - Arab Foundation (Apr. 2019)

44. Safety Management System - Arab Foundation (Apr. 2019)

45. Consultant Safety & Healthy - Arab Foundation (Apr. 2019)

Contact us:

Address: ( 1 ) El Rahala El Baghdady Street, Ard El Golf, Heliopolis, Cairo.

Tel.: (+202) 22910760

Mob.: (+2) 01099921432 – (+2) 01000643552

E-mail: [email protected]

* * *

SAM-LINE Consult

Brigadier Engineer: Sameh F. Iskander