Experience of NTPC · NTPC Kudgi: Project site for Wind-Solar Hybrid Site Characteristics Site...

18
Experience of NTPC Setting up Large scale Solar-Wind Hybrid Project 22/11/2017 Presented by : Mr. N.S.P. Singh AGM, PE-Wind NTPC

Transcript of Experience of NTPC · NTPC Kudgi: Project site for Wind-Solar Hybrid Site Characteristics Site...

  • Experience of NTPC

    Setting up Large scale Solar-Wind

    Hybrid Project

    22/11/2017 Presented by : Mr. N.S.P. Singh

    AGM, PE-Wind

    NTPC

  • NTPC at a glance

    The total installed capacity of the company is 51,708 MW { 29 coal based (including JV), 7 gas based stations

    1 Hydro based station

    1 Wind based station

    11 Solar PV projects. }

    Projects under implementation including JV and subsidiaries in

    total are about 19,654 MW, and the long term corporate plan is

    to be a 130 GW company by 2032.

    We envision a diversified fuel mix and are committed to attain

    nearly 30% generation capacity from non-fossil fuel resources by

    year 2032 in turn lowering carbon footprint by reducing GHG

    emissions.

  • Moving Towards Renewable Energy

    Adapting innovative technologies for blending thermal power with wind & solar energy generation

    Supporting factors:

    • Remotely located – Higher Land availability

    • Existing power evacuation facility

    • Capability to invest in larger CAPEX projects

    Case Study: USAID PACE-D Program provided Technical Assistance in drafting Detailed Feasibility Report and Bid document

    “NTPC’s Wind-Solar hybrid project (252 MW )”

  • Advantages of Wind-Solar Hybrid

    Increased output

    (MWh)/km2

    Savings on Evacuation

    System Costs

    More balanced

    power mix for sale

    Reduced ‘OPEX’ due to shared services

  • Wind-Solar Hybrid: Basic Design Approach

    1 • Maximize Wind Generation in the Given Area

    2 • Leave space around WTG before placing solar (Shadow Analysis)

    3 • Optimize Solar Capacity for high Generation, low

    Cost (DC:AC ratio, pitch angle)

    4 • Optimize AC system to Pooling Station

    5 • Design Common Services and Facilities

  • Wind-Solar Hybrid: A Typical Hybrid Block

  • PVsyst Analysis: Solar Module Placement Approach Approach

    140 Meters square area was kept empty

    Near shading loss = 1.6%, which is just

    0.2% greater than 171 meters

    Solar capacity = 178 MW AC

    Energy generation = 378,868 MWh per

    annum.

    171 meters Radius area was kept empty

    Near shading loss = 1.4%

    Capacity= 89 MW AC

    Energy generation = 190,050 MWh per

    annum.

    It clearly shows a potential to pack solar capacity by choosing to leave just

    the operating space, depending on the land availability and the goals for

    balancing generation.

    Comparative study

  • NTPC Kudgi: Project site for Wind-Solar Hybrid

    Site Characteristics

    Site Location NTPC Kudgi, Bijapur, Karnataka

    Site Co-ordinates 16.15 degrees North and 75.84

    degrees East

    Terrain Type Simple/Plain Terrain having

    power plant structures

    Contiguous/ Non-contiguous

    land Non-Contiguous

    Water Bodies -Nil- (Within the periphery)

    Obstacles Power plant chimney & other

    associated structures

    Elevation (m.a.s.l) 488-587m

    Wind Direction Predominantly West

    Distance of built-up structures Within the periphery

    Nearby WTGs of OEMs No other wind farm exists in the

    vicinity

  • NTPC Kudgi: Wind Micrositing

    Wind farm

    Capacity (MW) 60

    No. of WTGs 30

    Proposed WTG

    Rating (MW) 2.0

    Proposed WTG

    locations

  • NTPC Kudgi: Solar PV Layout

  • NTPC Kudgi: Solar PV selected Case Analysis

    Total Generation

    AC:DC ratio 1:1.35

    Tilt Angle (Degree) 10

    Pitch (m) 7.5

    Installed Capacity MWp

    DC 259.2

    Installed Capacity MW

    AC 192

    Total Gen (GWh/Yr) 358.7

    Parameters Values

    AC to DC ratio 1:1.35

    PV module 320 Wp

    Installed capacity (kWp) DC 8102

    Installed capacity AC (kW) 6000

    Module efficiency at STC (%) 16.67%

    Capacity Utilization Factor (CUF) at P75 18.20%

    Solar Resource For fixed tilt

    angle 10o

    Effective global irradiance incident on

    collector plane (kWh/m2) 1933.7

    First Year Energy Output at Inverter

    Output (MWh/annum) 13570

    Specific energy production

    (kWh/kWp/year) 1640

    Performance Ratio 79.57%

  • PVsyst output AC:DC ratio of 1:1.35

  • Final hybrid capacity mix

    The total capacity of solar-wind hybrid project is 252 MW

    leading to AEP of 603.32 GWh per year.

  • Estimated tariff for Hybrid project

    Tariff (INR / kWh)

    Without Land

    Cost

    With Land

    Cost

    Solar 3.44 4.56

    Wind 3.06 3.57

    Overall LCOE 3.32 4.25

    Cost Saving due to shared Infrastructure

    •There will be no extra cost to develop high voltage power evacuation

    infrastructure for the wind power project.

    •Capital cost savings on other infrastructure such as roads, security,

    plant control, spares warehousing, energy storage; forecasting and

    scheduling.

  • International Competitive

    Bidding to be conducted

    Tender will be issued for LSTK

    (Lump sum Turnkey) EPC

    contractor, for the entire plant

    up to Pooling SS

    Bidders to quote for EPC + 10

    Years OMS contract.

    Consortium Allowed

    NTPC Kudgi: Wind-Solar Hybrid Bidding Approach

    Evaluation Criteria V = (EPC Contract Value with taxes + PV of 10

    yrs of O&M Expenses)/(KWh generated over 10

    years)

    The lowest V would be the winner

    The forecast generation figures would become the basis

    for Performance Guarantees (peak capacity, performance

    ratio, power curve tests, plant availability, degradation

    etc.)

  • 1. Power Sale- Recognition of Large Consumer to purchase

    power.

    2. Metering – Metering to be done independently for wind

    and solar/ combined Metering. Discom discussions to

    take place

    3. Regulation – The Policies which setup directives are in

    draft stage and expected to be finalized before the project

    gets implemented.

    Resolution of issues such as RPO fulfillment, Long Term Transmission capacity allocation, Metering, Scheduling and

    Forecasting etc. would likely be clarified.

    Issues requiring further work

  • Some Pictures from Site Visit

  • THANK YOU