EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 · PDF file · 2012-03-03UltraTech...
Transcript of EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 · PDF file · 2012-03-03UltraTech...
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 1
(Unit: Vikram Cement Works)
EXECUTIVE SUMMARY
1.0 PROJECT DESCRIPTION
1.1 Introduction
M/s. UltraTech Cement Limited (Unit: Vikram Cement Works), earlier Vikram Cement
(A unit of M/s. Grasim Industries Ltd.), is nestled in Malwa region of Madhya Pradesh, at
Village: Khor, Tehsil: Jawad, in Neemuch district and bordering Rajasthan. It is one of
the modern cement plant equipped with state-of-the-art technology to attain highest
standard of productivity, safety and environmental management.
Vikram Cement Works has an existing Cement Plant Complex comprising of Cement
Plant (4.0 MTPA) & two Limestone Mines {Limestone Mine – I (442.923 ha) with
production capacity of 5.5 MTPA & Limestone Mine – II (342.612 ha) with production
capacity of 1.5 MTPA} in Village: Khor, Tehsil: Jawad, District: Neemuch (Madhya
Pradesh).
The approximate annual limestone requirement for the Cement Plant is 5.50 MTPA,
which is being presently met from existing Captive Limestone Mines {Limestone Mine - I
(442.923 ha) & Limestone Mine – II (342.612 ha)}. Considering the Cement Plant
requirement, available mineable reserves from the existing limestone mines would not
be sufficient to get optimum balance life of Cement Plant i.e. 40 to 45 years.
Now, Vikram Cement Works (VCW) has proposed Expansion of the Cement Plant
(Clinker 3.59 to 6.2 MTPA, Cement 4.0 to 10.33 MTPA) in Village: Khor, Tehsil: Jawad,
District: Neemuch (Madhya Pradesh). Application for the same was submitted to MoEF,
New Delhi on 30.11.2010. ToR letter for the proposed expansion project was obtained
from MoEF, New Delhi vide Letter No. F. No. J-11011/616/2010-IA-II (I) dated
10.03.2011.
Therefore, Vikram Cement Works has now proposed a New Limestone Mine – III
(564.106 Ha) with production capacity of 2.0 MTPA at Villages Nayagaon, Kesharpura,
Damodarpura, Khor & Kanka; Tehsil Jawad, District Neemuch (Madhya Pradesh). It will
increase the plant life by another 9 years.
The project was considered in front of EAC (M) for ToR approval on 17th Feb., 2010. The
Terms of References (ToR) have been issued by MoEF, New Delhi for preparation of the
Draft EIA / EMP Report vide letter no. J-11015/23/2010 IA, II (M) dated 4th March,
2010.
As per EIA Notification dated 14th September, 2006; as amended on 01st December,
2009; this project falls under category ‘A’, project or activity 1(a) (3).
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 2
(Unit: Vikram Cement Works)
1.2 Details of the Project
Table - 1
S. No. Particulars Details
1. Nature of project Mining Project
2. Size of project
2.1 Mining Lease area 564.106 ha {Govt. Barren Land – 84.957 ha, Private
Land – 479.149 ha}
2.2 Proposed Production Capacity 2.0 MTPA
3. Location Details
3.1
A. Village Nayagaon, Kesharpura, Damodarpura, Khor &
Kanka
B. Tehsil Jawad
C. District Neemuch
D. State Madhya Pradesh
3.2 Latitude 24O 32’ 38.79” to 24O 34’ 46.56” (N)
3.3 Longitude 74O 47’ 2.02” to 74O 49’ 33.31” (E)
3.4 Toposheet No. 45 L/14
4. Environmental Settings Details
4.1 Nearest Town Jawad (~ 6.0 km in NNE direction from the mine
site)
4.2 Nearest National Highway NH-79 (~ 1 km towards SW from mine site)
4.3 Nearest Railway Station Jawad Road Railway Station (~ 2.4 km in WSW
direction from mine site)
4.4 Nearest Airport Udaipur (Rajasthan) ~ 105 km in W direction from
mine site
4.5 State Boundary Madhya Pradesh & Rajasthan (~ 1.5 km towards
NW from mine site)
4.6
Ecological Sensitive Areas
(National Park, Wild Life
Sanctuary, Biosphere Reserve,
etc.) within 10 km radius
None within 10 km radius of mine site
4.7 Reserved / Protected Forest
within 10 km radius
There is no Reserve Forest falling within 10 km
radius of mine site.
o Protected Forest (~ 9.1 km in NE direction)
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 3
(Unit: Vikram Cement Works)
4.8 Water Bodies (within 10 km
radius)
o Daru River (~ 5.6 km in W direction) – seasonal
nallah
o Gambhiri River (~ 6.6 km in NNE direction) -
seasonal
4.9 Seismic Zone Zone – II
5. Cost Details
5.1 Total Cost of the Project Rs. 64 Crores
5.2 EMP Cost
• Capital Cost
Rs. 1.0 Crores
6. Requirements for the project
6.1 Water Requirement 143 KLD
Source: Existing Mine sump water (Mine-I) & Proposed Mine Sump water (Mine-III; after five
years) (for mining activities) and Ground Water (for drinking purpose).
6.2 Manpower Requirement 97 persons
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 4
(Unit: Vikram Cement Works)
1.3 Location Map
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 5
(Unit: Vikram Cement Works)
2.0 MINE DESCRIPTION
2.1 Mining Lease Status
Total mining lease area is 564.106 hectare. Revised LOI for the proposed Vikram
Cement Limestone Mine – III (ML Area: 564.106 ha) in the name of M/s. UltraTech
Cement Ltd. (Unit: Vikram Cement Works) has been obtained from MP State
Government vide their letter no. F3 - 32/08/12/1 dated 29th Nov., 2010 for a period of
30 years.
2.2 Mining Details
Table – 2
S. No. PARTICULARS DETAILS
1. Mining Method Opencast Mechanized
2. Proposed Production per year 0.1 MTPA (For first 5 years)
2.0 MTPA (6th Year onwards)
3. Total Mineable Reserves 48.99 Million Tonnes
4. Life of Mine ~ 29 Years
5. Bench Height 8 m (in Ore & OB)
6. Bench Width 20 m
7. Elevation Range 459 m AMSL to 487 m AMSL
8. General Ground Level 473 mRL
9. Ground Water Table Winter Season: 15-18 m bgl (457 mRL to 454
mRL)
Summer Season: 40-50 m bgl (432 mRL to
422 mRL)
10. Ultimate Working Depth
(at the end of life of mine)
52 m bgl (421 mRL) in Block D
11. Overall Pit Slope 45o
12. Stripping ratio 1:0.20
13. Number of Working Days 313 days
14. Number shifts per day 2
Source: Approved Mining Plan & Progressive Mine Closure Plan
2.3 Proposed Method of Mining
Mining will be carried out by Mechanized Opencast method to produce limestone @ 2.0
Million Tonnes per annum by deploying heavy earth moving machines and large
diameter deep hole drilling and controlled blasting techniques, with proper benching of
deposit.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 6
(Unit: Vikram Cement Works)
Drilling will be carried out by 115 mm dia DTH drill machines. Blasting will be done by
using various types of explosives such as Cast Booster (Slurry), ANFO, non-cap sensitive
slurry explosives etc.
2.4 Utility & Requirement for the Mining Project
2.4.1 Extent of Mechanization
Table - 3
S. No. Machine No.
1. Hydraulic Excavator 3
2. Dumper 30 tonner 9
3. Rock Breaker – Secondary 1
4. Dozers 1
5. Drill machine 115 mm dia 2
6. Mobile service van 1
7. Explosive van 1
8. Water tanker 1
9. Motor grader 1
Source: Approved Mining Plan & Progressive Mine Closure Plan
2.4.2 Water Requirement
Total water requirement for the proposed mining project will be 143 KLPD.
Table - 4
Water Requirement Quantity (in KLD)
Dust Suppression 120
Green Belt 18
Mine Operation 1
Workshop 2
Drinking 2
Total Water Requirement 143
Source: Approved Mining Plan & Progressive Mine Closure Plan
Note: Water will be sourced from Existing Mine sump water (Mine-I) and / or Proposed
Mine Sump water (Mine-III; after five years) for mining activities & for drinking purpose
bore wells will be used.
2.4.3 Man Power Requirement
Total Man Power requirement, including staff and worker, for the proposed project will
be 18 during first five year and it will reach up to 97 at ultimate capacity.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 7
(Unit: Vikram Cement Works)
3.0 DESCRIPTION OF ENVIRONMENT
Baseline study of the study area was conducted during Summer Season (March to May,
2011).
The concentration for all the 10 AAQM stations for PM10 ranges between 40.18 to 79.82
µg/m3, SO2 ranges between 6.1 to 10.67 µg/m3 and NO2 ranges between 9.1 to 19.57
µg/m3.
The ground water analysis for all the 08 sampling stations shows that pH varies from
7.12 to 8.01, total hardness varies from 121.20 mg/l to 456.52 mg/l & total dissolved
solids varies from 202.00 mg/l to 936.00 mg/l.
The analysis results for soil shows that soil is neutral to moderately alkaline in nature as
pH value ranges from 7.02 to 7.92 & is silty loam in texture. Pottasium ranges from
129.98 kg/ha to 176.73 kg/ha .The concentration of Nitrogen, Phosphorus has been
found to be in good amount in the soil samples.
3.1 Biological Environment
Flora in study area of 10 km radius
Lantana camara (Raimuniya), Cynodon dactylon (Hariali Ghas), Ficus religiosa (Peepal),
Phoenix sylvestris (Khajur), Acacia catechu (Khair), Acacia nilotica (Babul), Butea
monosperma (Palash), Dalbergia sisoo (Shisham), Albizia lebbeck (Siris), Azadirachta
indica (Neem), Ficus benghalensis (Vad) etc.
Fauna in study area of 10 km Radius
Acridotheres tristis (Indian Myna), Columba livia (Pigeon), Passer domesticus (House
sparrow), Rattus rattus (Indian Rat), Felis chaus (Jungle Cat), Duttaphrynus melanostictus
(Indian Toad), Lepus nigricollis (Hare), Boselaphus tragocamelus (Blue Bull), Corvus
splendens (House crow), Calotes versicolor (Garden Lizard), Ploceus philippinus (Weaver
bird), Presbytis entellus (Common Langur), Phalacrocorax niger (Little Cormorant) etc.
3.2 Socio-Economic Environment
The total population in the buffer zone (10 km radius), as per 2001 Census records, is
100501. Scheduled Caste fraction of the population of the study area (10 km) is 12.67%
and Scheduled Tribe 10.02%. Percentage of literacy is 57.80% and that of workers those
actually engaged in occupation is 49.15% including, 37.53% of Main workers & 11.62%
of marginal workers. Rest 50.85% of the total population, are considered as non-
workers.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 8
(Unit: Vikram Cement Works)
4.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
� Impact on Air Quality
The key air emissions from the mining activities (drilling, blasting, loading, haulage and
transportation) are particulate matter, oxides of nitrogen (NO2) and sulphur dioxide
(SO2). Gaseous emission will be generated from HEMM and their transportation
vehicles. Use of proper mitigation measures will be taken (like water sprinkling during
transport activities) & green area will be developed along the road sides to control
pollution.
� Impact of Mining on Ground Water Table
There will be no outside discharge of liquid effluent from the mine site; therefore no
significant impact on surface water bodies is anticipated due to mining operations.
The general ground level in the area is 473 mRL. The water level in the proposed area
varies a lot and fluctuates from from 15-18 m bgl in winter season and 40-50 m bgl in
peak summer season. Ultimate working depth will be 52 m bgl (421 mRL) {in Block-D}.
Ground water, if encountered during mining, will be pumped out & utilized for various
purposes in the plant and mine. Mineral as well as overburden is non – toxic in nature.
� Impact of Noise Levels & Ground Vibration
Major noise generating sources of the mining activity will be drilling and blasting and
trucks movement used for transportation of limestone. The instant noise level from
blasting will be high for some instance but it will be within the prescribed limits due to
application of improved technology and will be confined to working zones.
The proposed plantation will also check propagation of noise in the surrounding areas.
� Impact on Soil and Land Use Pattern
Topsoil generated from the mine will be stacked separately & will be used for plantation
purpose within the lease area. At the conceptual stage, there will be no top soil dump.
Opencast mining activities may alter the landscape of the lease area and will not have
any effect on the surface features of the surrounding areas. At the end of life of mine, out
of the total mining lease area (i.e. 564.106 Ha), 162.90 Ha will be excavated; out of
which 68.14 Ha will be backfilled & reclaimed by plantation & rest 94.76 Ha will be
developed as water reservoir.
Out of the total lease area i.e. 564.106 ha, 107.96 ha area will be covered under green
belt/plantation, including 33.82 ha un-worked area, 6.0 ha external dumps, 68.14 ha
backfilled area.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 9
(Unit: Vikram Cement Works)
5.0 ENVIRONMENTAL MONITORING PROGRAMME
Table - 5
S. No. DESCRIPTION FREQUENCY OF MONITORING
1. Meteorological Data Daily
2. Ambient Air Quality at project site Twice a week
3. Water Quality Quarterly
4. Noise Level Monitoring Quarterly
5. Soil Quality Quarterly
6. Health Check-up As per the guidelines
6.0 ADDITIONAL STUDIES
The Additional Studies conducted as per the additional Terms of References vide MoEF
letter no. J -11015/23/2010-IA.II (M) dated 4th March, 2010 are Biological Study, Hydro-
geological Study & Rain water Harvesting Plan and Disaster Management Plan.
7.0 PROJECT BENEFITS
The proposed project activity will help in combating the growing demand of cement in
the market & hence will help in the economic growth of the country. Vikram Cement
Works has already been actively involved in the CSR activities in the nearby villages of
the project site. Infrastructure development in the nearby villages, creating educational
facilities, gainful employment for rural, health awareness programmes & surgical
camps, assisting social forestry programmes in the area etc. are some of the highlights of
the CSR activities which are being done presently for existing Plant & mines & will also
be continued for the life of the proposed mine.
8.0 ENVIRONMENT MANAGEMENT PLAN
8.1 Air Quality Management
� Sharp drill bits will be used for drilling to reduce generation of dust.
� Drilling machines will be equipped with water spraying system to prevent dust to
get air borne.
� Controlled blasting will be done.
� Rock breaker will be used to avoid secondary blasting.
� Periodical water spraying on the haul roads will be done.
� De-dusting system will be provided at crushing plant with bag filter arrangements
to collect the dust generated during crushing.
� Green Belt / plantation will be developed around the quarry edge, along the roads,
crushing plant, office, workshop, etc.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 10
(Unit: Vikram Cement Works)
8.2 Water Quality Management
� Garland Drains will be provided around the pit to prevent the entry of rainwater
into the mining pit.
� Dump will be made at a sufficient distance from seasonal nalla.
� Garland drain/ filtration bund will be provided around dumps to retain the water
percolation coming from waste dumps for settling of solid particles. Clear water will
be allowed to flow in natural courses.
� Septic tanks and soak pits will be provided for the disposal of domestic effluent.
� Rainwater falling in the catchments area of mining pit will be collected in sump of
mines i.e. in lower benches.
8.3 Noise Management
� Drilling will be carried out with the help of sharp drill bits which will help in
reducing noise.
� Control Blasting will be carried out to minimize vibration.
� Rock breaker will be used to avoid secondary blasting
� Earmuffs/earplugs will be provided to all operators and employees working near
the machinery.
� Proper maintenance, oiling and greasing of machines at regular intervals will be
done to reduce generation of noise.
� Plantation will be done to minimize the propagation of noise.
� Periodical monitoring will be done.
8.4 Solid Waste Management
At the end of life of mine, total OB/waste generation will be 6.61 Million Tonnes & Inter-
burden generation (in the form of Interstitial Clay) will be 2.58 Million Tonnes, out of
these (9.19 Million Tonnes), a part will be utilized in backfilling 68.14 Ha of mined out
area & remaining will be dumped on the surface area - 6.0 Ha (at Block A & B).
Overburden dumps will be stabilized by plantation.
8.5 Management of Land Use Pattern
The activity will affect the present landscape of the ML area. The original topography of
the ML area will be affected mainly due to the actual mining operation.
At the end of life of mine, out of the total mining lease area (i.e. 564.106 Ha), 162.90 Ha
will be excavated; out of which 68.14 Ha will be backfilled & reclaimed by plantation &
rest 94.76 Ha will be developed as water reservoir.
Proposed Vikram Cement Limestone Mine-III (ML Area-564.106 ha) with 2.0 MTPA Limestone Production Capacity
At Villages Nayagaon, Kesharpura, Damodarpura, Khor and Kanka, Tehsil Jawad, District Neemuch, Madhya Pradesh
Executive Summary of EIA Report
M/s. UltraTech Cement Ltd. 11
(Unit: Vikram Cement Works)
Out of the total lease area i.e. 564.106 ha, 107.96 ha area will be covered under green
belt/plantation, including 33.82 ha un-worked area, 6.0 ha external dumps, 68.14 ha
backfilled area.
8.6 Greenbelt Development & Plantation Programme
Out of the total lease area of 564.106 ha, 107.96 ha area will be covered under green
belt / plantation, including 33.82 ha un-worked area, 6.0 ha external dumps, 68.14 ha
backfilled area.
The following species to be planted in the Green belt / plantation Cassia fistula
(Amaltas), Albizia lebbek (Siris), Dalbergia sissoo (Shisham), Ficus religiosa (Peepal),
Azadirachta indica (Neem), Acacia nilotica (Babul), Ficus benghalensis (Bargad), Ficus
glomerata (Gular), Tectona grandis (Teak), Syzygium cumini (Jamun) etc. Plantation
shall be carried out as per CPCB guidelines.
8.7 Socio-Economic Environment
Better education facilities, proper health care, road infrastructure and drinking water
facilities are basic social amenities for better living standard of any human being.
Vikram Cement Works will initiate the above amenities either by providing or by
improving the facilities in the area, which will help in uplifting the living standards of
local communities.
9.0 CONCLUSION
As discussed, it is safe to say that the project is not likely to cause any significant impact
on the ecology of the area, as adequate preventive measures will be adopted to contain
the various pollutants within permissible limits. Green belt development around the
area will also be taken up as an effective pollution mitigative technique, as well as to
control the pollutants released from the premises of Vikram Cement Works.