Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register....
Transcript of Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register....
![Page 1: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/1.jpg)
YOUR COMPANYPROJECT NAME: XXXXCUSTOMER NAME: XXXX
Date: 27-04-2011
![Page 2: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/2.jpg)
Project Name: Customer Name:Document Number / Version Number:
Exception Report
1. Purpose
An Exception Report is produced when a Stage Plan or Project Plan is forecast to exceed tolerance levels set. It is prepared by the Project Manager in order to inform the Project Board of the situation, and to offer options and recommendations for the way to proceed.
.
2. Derivation
The Exception Report may be derived from the following:-
Current plan and actual Issue Register, Risk Register and Quality Register Highlight Reports (for stage/project-level deviations) or Checkpoint Reports
(for team level deviations) Project Board advice of an external event that affects the project.
3. Quality criteriaWhat makes a excellent Exception Report
The current plan must accurately show the status of time and cost performance
The reason(s) for the deviation must be stated, the exception clearly analysed, and any impacts assessed and fully described
Implications for the Business Case have been considered and the impact on the overall Project Plan has been calculated
Options are analysed (including any risks associated with them) and recommendations are made for the most appropriate way to proceed
The Exception Report is given in a timely and appropriate manner.
Your Company Limited, 2023 Issue Date:
Author Name: Document Status:
![Page 3: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/3.jpg)
Project Name: Customer Name:Document Number / Version Number:
From To Date Stage
4. Introduction
5. Exception TitleAn overview of the exception being reported
6. Cause of ExceptionA description of the cause of a deviation from the current plan
7. Consequence of the deviationWhat the implications are if the deviation is not addressed for:
The Stage
The project
Corporate or programme management
8. OptionsWhat are the options that are available to address the deviation and what would the effect of each option be on the Business Case, risks and tolerances.
Options Impact on the Business Case
Impact on the Risks
Impact on the Tolerances
1.
2.
3.
4.
5.
Your Company Limited, 2023 Issue Date:
Author Name: Document Status:
![Page 4: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/4.jpg)
Project Name: Customer Name:Document Number / Version Number:
9. Project Managers RecommendationOf the available options, what is the recommendation, and why? You may wish to recommend more than option to deal with the exception situation.
10. LessonsWhat can be learned from the exception, on this project or future projects.
Lesson Type Lesson Detail Logged By
1.
2.
3.
4.
5.
Your Company Limited, 2023 Issue Date:
Author Name: Document Status:
![Page 5: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/5.jpg)
Project Name: Customer Name:Document Number / Version Number:
11. Supporting Information[Add here any supporting information, such as comments, charts, tables, documents or diagrams that will assist].
Your Company Limited, 2023 Issue Date:
Author Name: Document Status:
![Page 6: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/6.jpg)
Project Name: Customer Name:Document Number / Version Number:
12. Exception Report Sections Omitted [Omitted section]
[Omitted section]
13. Document Distribution
Name Organization Role
14. ApprovalsPrepared By __________________________________
([Job Title])
This document requires the following approvals
Approved By __________________________________
([Job Title])
__________________________________
([Job Title])
_________________________________
([Job Title])
Approval Date __________________________________
15. Document LocationThis document is only valid on the day it was printed. The document will be found/stored in the following location [xxxxx].
16. GuidanceGuidance Text (delete all the guidance text when completing the report)
Your Company Limited, 2023 Issue Date:
Author Name: Document Status:
![Page 7: Exception Report - Excel TMP€¦ · Web viewIssue Register, Risk Register and Quality Register. Highlight Reports (for stage/project-level deviations) or Checkpoint Reports (for](https://reader035.fdocuments.us/reader035/viewer/2022071419/611888a7096069504979b454/html5/thumbnails/7.jpg)
Project Name: Customer Name:Document Number / Version Number:
Use the Microsoft Word document “properties” to view and edit document properties such as “Title, Author, Subject and any Keywords. To access the “Properties” fields follow the instructions below:-
1. Click on the “Office Button”2. Select “Prepare”3. Select “Properties”
Your Company Limited, 2023 Issue Date:
Author Name: Document Status: