EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that...

13
EXCAVATION PROCEDURE

Transcript of EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that...

Page 1: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

Page 2: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 2 of 13

TABLE OF CONTENTS 1 PREFACE .................................................................................................................... 3

2 OBJECTIVE ................................................................................................................. 3

3 SCOPE ........................................................................................................................ 3

4 RELATED DOCUMENTS ............................................................................................. 3

5 PURPOSE ................................................................................................................... 3

6 PPA EXCAVATION PERMIT FORM ............................................................................ 4

6.1 THE EXCAVATION PERMIT FORM. ................................................................. 4

6.2 WHERE TO OBTAIN THE EXCAVATION PERMIT ........................................... 4

6.3 HOW TO SUBMIT THE FORM .......................................................................... 4

7 CONDITIONS ............................................................................................................... 4

7.1 COMPLIANCE TO LEGISLATION AND REGULATION ..................................... 4

8 ENVIRONMENTAL REQUIREMENT ........................................................................... 6

9 SAFE WORK PROCEDURE AND CODE OF PRACTICE ............................................ 6

10 COMPETENT PERSON ............................................................................................... 7

11 RISK ASSESSMENT AND SAFETY WARNINGS ........................................................ 7

12 INCIDENT REPORTING .............................................................................................. 8

13 SITE INSPECTION AND AUDIT .................................................................................. 8

14 CLEAN-UP ON COMPLETION .................................................................................... 8

15 CANCELLATION OF PERMIT ..................................................................................... 8

16 UNKNOWN SERVICES ............................................................................................... 8

17 RESPONSIBILITY ........................................................................................................ 9

18 DISTRIBUTION OF APPROVED PERMIT .................................................................... 9

19 REFERENCES ............................................................................................................. 9

20 APPENDICES .............................................................................................................. 9

20.1 APPENDIX 1A – PORT OF PORT HEDLAND – LOT 6098 …………………..11

20.2 APPENDIX 1B – PORT OF DAMPIER – LOT 471 ........................................... 12

21 PROCESS OWNER ....................................................................................................13

Page 3: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 3 of 13

1 PREFACE

The aim of this procedure is to have appropriate measures in place to minimize the risk of

harm to persons undertaking excavation work, damage to PPA underground utilities and

outages to the business, due to utility services being disturbed.

2 OBJECTIVE

Underground services have been installed, moved and removed throughout the Port since

1960. Due to various reasons PPA cannot guarantee the accuracy of utility drawings in its

possession.

The objective of this procedure is to ensure all excavation work deeper than 150mm is

notifiable to relevant PPA staff and all measures have been taken to reduce the risk of harm

or damage.

3 SCOPE

To ensure all PPA personnel and contractors understand the requirements of the Port

Authority in relation to any excavation work that has the potential to be deeper than150mm.

To provide a set of actions to approve and Permit any excavation work deeper than 150mm

regardless of method.

4 RELATED DOCUMENTS

Excavation Permit

PPA Safe Work Instruction – Excavation Work

Risk assessment/JHA

Dial before you dig application if outside Utah BHF site and PPA east site

http://www.commerce.wa.gov.au/Worksafe/PDF/Codes_of_Practice/code_excavation.pdf

5 PURPOSE

This procedure aims to:

Protect employees, contractors and other port users from harm whilst undertaking

excavation works

Eliminate interruption and/or damage to services; and

Eliminate damage to equipment.

Page 4: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 4 of 13

It outlines the requirements in carrying out the excavation and related activities within the

jurisdiction of Pilbara Ports Authority. It applies to all PPA staff, contractors and nominated

lessees within the secure area of Port of Port Hedland and southern side of Gilbert Street,

Utah Point Bulk facility and the gazetted boundaries of Port of Dampier.

6 PPA EXCAVATION PERMIT FORM

The Excavation Permit Form 6.1

It is a requirement that the Form must be completed and approved by PPA prior to any

work being undertaken.

The Form must be completed for all types of excavation including digging, trenching or

boring, which extends more than150mm below ground level.

Where to obtain THE EXCAVATION Permit 6.2

The procedure and the accompanying Form can be downloaded from the PPA website

at http://www.pilbaraports.com.au.

A copy can also be obtained from the Landside Operations Superintendent East, Utah

and Dampier and, Maintenance Superintendents at East, Utah and Dampier.

How to submit the Form 6.3

The Completed Form can be submitted in three ways:

by email at [email protected]

email to respective issuing officer above

in person directly with the respective issuing Officer above

7 CONDITIONS

Compliance to Legislation and Regulation 7.1

In carrying out the works covered by this permit, the permit holder is required to comply

with the Occupational Safety and Health Act 1984, Occupational Safety and Health

Regulations 1996, Mines Safety and Inspection Act 1994, Mines Safety Regulations

1995 and other applicable legislation and regulations. Specifically, the following

obligations apply:

Page 5: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 5 of 13

Consider use of temporary support systems, battering, benching, other forms of retaining

structures, and de-watering systems to reduce the risk of injury (Occupational Safety and

Health Regulations 1996, regulation 3.108).

a. Ensure that, when there is a risk of injury due to an excavation:

i) Suitable barriers are erected between the person at risk and the likely cause

of danger

ii) Suitable signs that warn of the risk are erected at the place where the

excavation work is to be done

iii) Means to safely move in, around, and across the top of, the area are

provided for persons and plant (Occupational Safety and Health Regulations

1996, regulation 3.109).

b. Ensure that no loads are placed near the edge of excavations which may cause

the excavation to collapse (Occupational Safety and Health Regulations 1996,

regulation 3.110)

c. Unless a competent person has assessed the sides of the excavation or

earthworks to be stable, ensure that:

i) Shoring is provided to prevent material falling or dislodging and a person

working in an excavation that is at least 1.5 meter’s deep is protected

(Occupational Safety and Health Regulation 1996, regulation 3.111)

ii) Another person is in the immediate vicinity of a person working in an

excavation that is at least 1.5 meter’s deep (Occupational Safety and Health

Regulations 1996, regulation 3.112)

d. Prepare a work method statement when the excavation exceeds 1.5 meter’s in

depth. Safe work method statement is defined as a “statement prepared under

regulations 3.143 (Occupational Safety and Health Regulations 1996, Part 3,

Division 12, 3.137). Please refer to the specific regulations to determine details

of your obligations.

e. THE RESPECTIVE LANDSIDE SUPERINTENDENT IS TO BE NOTIFIED OF

ALL APPROVED EXCAVATION PERMITS.

Page 6: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 6 of 13

8 ENVIRONMENTAL REQUIREMENT

If the Applicant is proposing to carry out the excavation works within PPA Lot 6098 (Port

Hedland – Refer to Map in Appendix 1A), or Lot 471 (Damper- Refer to Map in Appendix 1B)

and is seeking to specifically:

a) undertake excavation of material and move the material from its current location;

and/or

b) move an existing stockpile of material to another location within or outside these Lots,

then the site Environment team must be notified immediately and the following

conditions will apply. Note that material must not be moved from the excavation

location until all of the below conditions have been satisfied:

A soil sampling and laboratory analysis plan must be developed by the Applicant to

demonstrate the contamination status of the material. This plan shall be prepared in

accordance with the Western Australian Department of Environment Regulation

Landfill Waste Classification and Waste Definitions (as amended) and Environment

Protection (Control Waste) Regulations 2004 (where relevant). As a minimum, the

plan shall outline the total estimated volume of material, a site map showing the

location of the material, the number of samples required and where/how they will be

collected. The plan shall also state that sampling will be conducted by competent

personnel, and all samples will be independently tested at a NATA accredited

laboratory. The plan shall be submitted to the relevant PPA Environment and

Heritage team for review and written approval.

The Applicant shall send a written report to the PPA for review and approval that

summarises the outcomes of the material sampling and laboratory analysis, and the

proposed destination of the material. The report shall be accompanied by suitable

photos, and a copy of the NATA accredited laboratory results.

Once the material has been moved from its current location, PPA’s relevant site Environment

team shall be presented with electronic copies of all waste tracking and/or landfill receipts

(where relevant).

Note that these requirements exist as both the King Bay Industrial Estate (Lot 471) and Lot

6098 (PPA Site and/or leased areas) are listed under the Contaminated Sites Act 2003

9 SAFE WORK PROCEDURE AND CODE OF PRACTICE

The permit holder has to comply with PPA Safe Work Instruction – Excavation Work.

The Code of Practice is published by the Commission for Occupational Safety and Health,

Government of WA and is available on this website:

http://www.commerce.wa.gov.au/Worksafe/PDF/Codes_of_Practice/code_excavation.pdf

Page 7: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 7 of 13

The Code (page iii) applies to: “all workplaces in Western Australia covered by the

Occupational Safety and Health Act 1984 where excavation occurs, and to all persons with

the potential for exposure to hazards resulting from excavation in those workplaces,

including:

All areas where equipment is used to excavate; and

All areas where processes associated with excavation are undertaken”.

The Code “provides guidance to prevent occupational injury and disease in all workplaces

where excavation and associated earthworks are performed” (page iii).

PPA expects that the appropriate practices from this Code of Practice will be observed by the

permit holder.

10 COMPETENT PERSON

As the nature of excavation work varies from simple excavations to complex ones, the

approved contractor representative holder must ensure that the excavation and/or related

works are carried out or supervised by a competent person.

A competent person, as defined in section 1.3 of Occupational Safety and Health

Regulations 1996, is “one who has acquired through training, qualification, or experience, or

a combination of those things, the knowledge and skills required to do that thing

competently.”

It is expected that the knowledge and skills expected from a competent person “will increase

as the complexity of excavation increases” (page 13 of the Code of Practice).

11 RISK ASSESSMENT AND SAFETY WARNINGS

This condition reiterates the importance of Health and Safety of workers and the public in all

areas within the jurisdiction of Pilbara Ports Authority.

PPA expects that an approved Job Safety Analysis is in place prior to any excavation

works taking place.

During the duration of the approved works, the permit holder shall put in place all the

appropriate warnings to the public and signage on safe access and egress to the area to be

excavated. The signs shall be displayed to persons in or entering the area. All excavations

that are to be left open overnight must have additional warning devices such as flashing

lights in addition to existing barricading, access tape and tags and signage. The appropriate

signs shall comply with and shall be used in accordance with AS 1319-1994: Safety Signs

for the Occupational Environment.

Page 8: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 8 of 13

12 INCIDENT REPORTING

All near-misses, accidents, incidents or damage to in ground services relating to the

excavation covered by a PPA permit must be reported immediately.

In case of emergency, dial 000 or contact the Control Tower at Eastern Harbour Port

Hedland on (08) 9173 9030, or VHF CH 12 or 16 at Utah or Security Gatehouse Port

Hedland on (08) 9159 6584 or VTSC on (08) 9159 6556, or UHF CH 17 at Dampier Port.

13 SITE INSPECTION AND AUDIT

PPA has the prerogative to undertake inspection of the site with or without notice.

COMPACTION

Areas of large excavations and or excavations deeper the 500mm are to be compacted.

Compaction quantities will be determined by PPA Engineering Services on a case by case

basis.

14 CLEAN-UP ON COMPLETION

On completion, the permit holder shall return a copy of the approved permit to the PPA

Issuing Officer as acknowledgment that all works have been completed and site left in a

clean and safe condition. PPA has the option to inspect the site on completion and may

require the permit holder to clean the site if left in an unsatisfactory condition.

15 CANCELLATION OF PERMIT

PPA can cancel this permit at any time if the permit holder is found to violate the

conditions of this permit. The appropriate disciplinary actions may also be taken against the

permit holder, if required.

16 UNKNOWN SERVICES

The P i l b a r a Port Authority makes every effort to identify in-ground services to those

undertaking excavation works. However, many of the drawings of services are old and

their location may be approximates only. Additionally, older services may not be shown on

any drawings.

All excavations are to proceed with care. Where unknown services are found, work is to

cease immediately and the Pilbara Ports Authority advised to allow for further inspection.

PPA’s Electrical Supervisor or Civil Supervisor is to be notified when in ground service

locating is required on the East Harbour and the Mechanical Engineer or Electrical

Supervisor at Utah BHF and Maintenance Supervisor at Dampier.

Page 9: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 9 of 13

17 RESPONSIBILITY

The approval of excavation Permits and monitoring of compliance to this procedure

shall be the responsibility of the Issuing Officer

18 DISTRIBUTION OF APPROVED PERMIT

Original: Contractor or Permit holder

Copy: Issuing Officer

19 REFERENCES

Occupational Safety and Health Act 1984

Occupational Safety and Health Regulations 1996

Mines Safety and Inspection Act 1994

Mines Safety and Inspection Regulations 1995

Code of Practice – Excavation 2005 Government of Western Australia. Commission

for Occupational Safety and Health.

Dial before you dig for external works

Environment and Safety Law Online

Environmental Protection (Controlled Waste) Regulations 2004

Please note that copies of PPA main service drawings for East are available from PPA

Maintenance East Group and for Utah PPA Mechanical Engineer or Utah Electrical

Supervisor, and Superintendent at Dampier, if you require them.

Once permit becomes effective, in case of emergency d ial 000 or contact the

Control Tower at Eastern Harbour Port Hedland on (08) 9173 9030, or VHF CH 12 or 16

at Utah or Security Gatehouse Port Hedland on (08) 9159 6584 or VTSC on (08) 9159

6556, or UHF CH 17 at Dampier Port.

20 APPENDICES

PPA Site and/or Leased areas

Page 10: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 10 of 13

Page 11: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 11 of 13

Appendix 1A – Port of Port Hedland – Lot 6098 20.1

Page 12: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 12 of 13

Appendix 1B – Port of Dampier – Lot 471 20.2

Page 13: EXCAVATION PROCEDURE - Pilbara Ports Authority - Home · EXCAVATION PROCEDURE ... excavation that is at least 1.5 meter’s deep ... A soil sampling and laboratory analysis plan must

EXCAVATION PROCEDURE

A22895 Page 13 of 13

21 PROCESS OWNER

The Maintenance Manager has overall responsibility for this procedure.

To be reviewed January 2017.

Date approved: 18th

January, 2016 Review date: 18th

January, 2016

Version: 3 Approved by: General Manager Engineering & Infrastructure