Evolution of Indian Power Grid Phenomenal expansion since Independence Generation : 1349 MW 101,866...
-
Upload
kristian-davidson -
Category
Documents
-
view
213 -
download
0
Transcript of Evolution of Indian Power Grid Phenomenal expansion since Independence Generation : 1349 MW 101,866...
Evolution of Indian Power GridEvolution of Indian Power Grid
• Phenomenal expansion since Independence
Generation : 1349 MW 101,866 MW (in 1947) (in 2001)
Grid :
Local grid – at the time of Independence.
State Grids – emerged in 1960s.
Regional Grids – in 1970s.
Five Regional Grids – Northern, Western, Southern,
Eastern & North-eastern
National Grid – under progress.
Power Scenario – at a GlancePower Scenario – at a Glance
Existing• Installed capacity - 101,866 MW Coal – 71%
Hydro – 25 Nuclear & others – 4%
• Peak demand Peak power - 78,000 MW
Energy (average) - 1395 MU/day
• Availability Peak power - 68,000 MW
Energy (average) - 1288 MU/day
• Shortage Peak power - 10,000 MW (12.8%)
Energy - 107 MU/day (7.7%)
Power Scenario – at a GlancePower Scenario – at a Glance All figs. are in MW
Region Peak Installed Peak Demand Capacity
Surplus/Deficit
Northern 21,000 27, 000 - 2,100Western 25,000 30,800 - 4,500Southern 20,400 24,800 - 2,600Eastern 7,800 15,700 + 2,000North-eastern 950 1,800 - 25
• Limited exchange of power between Regions --- Main reasons:
– Inadequate interconnectors, especially from Eastern Region– Lack of proper Commercial and administrative mechanisms
Need for National GridNeed for National Grid• Uneven disposition of energy resources
Major Hydro resources in NER & NRCoal reserves mostly in Bihar/Orissa/West Bengal
Cost of power transmission (1.11 cents/kwh) lower than cost of fuel transportation (3.33 cents/kwh).
• Some Regions are no longer Self-sufficient
Major resources in SR exhausted In NR, mainly hydro resources having long gestation period
• Unbalanced Growth of different Regions
Some regions are surplus and some are deficit.
• Optimisation of generation capacity additionUtilising time diversitySpinning reserve optimisation
Power Transfer Envisaged from ER and Power Transfer Envisaged from ER and NER by 2012NER by 2012
Table
Development of National Grid – Major Development of National Grid – Major Considerations Considerations
• Development in a phased manner – commensurate with
generation/ load growth
• Conservation of Right-of-Way - especially in areas with
scarcity of ROW ---- viz. area near hydro, chicken-neck area,
forest area, town etc.
In forest area with rich flora & fauna, construction of line with high
towers ---- no forest cutting required.
• Minimisation of transmission cost - immediate as well as long-term basis.
• Flexible enough to accommodate change in load-generation pattern.
Plan for National GridPlan for National Grid PHASE-I (By 2002):
Interconnection through HVDC Back-to-Back links-
North – West: 500MW Vindhyachal Back-to-Back Under
West – South: 1000MW Chandrapur Back-to-Back Opera-
East – South: 500MW Gazuwaka Back-to-Back tion East – North: 500MW Sasaram Back-to-Back – expected by
(AC line of this project in operation 2002--- transferring 350 MW in radial mode)
With the completion of Sasaram HVDC Back-to-back link, framework of National Grid would be completed.
MAP
Plan for National GridPlan for National GridPHASE-II (By 2007):
• High capacity “Transmission highways” envisaged alongwith major generation projects-
East-South 2000 MW HVDC bipole between Talcher-Kolar - 2003.Augmentation of Gazuwaka HVDC back-to-back by 500MW - 2004.
East – North
High capacity 400 kV link from Tala to Delhi - 2004.2500 MW HVDC bipole between Hirma – Jaipur- 2005
East – West 400kV AC link between Rourkela and Raipur –2003400kV AC link between Hirma and Raipur & Sipat - 2005.
.
MAP
Plan for National GridPlan for National Grid
PHASE-III (By 2012):
Establishment of a ring of 765kV lines traversing across Northern, Western and Eastern Regions
Construction of various sections of Ring progressively along with major generation projects viz. Barh, Kahalgaon, North Karanpura etc.
Strengthening of East-South interconnection through another 2500MW bipole
MAP
National Grid: Cost-benefit analysisNational Grid: Cost-benefit analysisCost
Investment required Rs. 23,000 crores
Benefits Reduction in capacity addition requirement by about 13750 MW--- hence
saving on investment of Rs. 55,000 crore. (due to peak time diversity and
saving in spinning reserve)
Transmission highway would enable setting up of large pit head stations
having lower cost of energy
Savings on account of this - Rs. 9000 crores per annum.
In addition, Nation’s investment towards fuel transportation infrastructure
could be avoided.
Better overall hydro-thermal mix
Very low for ER and WR ( ER – 15 : 85, WR - 17 : 83 ) – affecting grid
operation
With National Grid, it would become 33 : 67 on all India basis. .
Major Challenges & their RedressalMajor Challenges & their Redressal
Mobilisation of Funds
Considerable investment required for creation of National Grid
Investment requirement in : Rs. 70,000 Cr Central transmission sector (including National Grid) by the year 2011-12
Investment by POWERGRID : Rs. 39,000 Cr
Investment by Private Sector : Rs. 31,000 Cr
POWERGRID facilitating private sector participation in transmission
sector through Joint Venture and Independent Private Transmission
Companies (IPTCs) routes
Major Challenges & their RedressalMajor Challenges & their Redressal ...contd....contd.
Private Sector Participation• Joint Venture Route
– Project specific Shell company for obtaining statutory approvals to offer bankable projects to private sector
– Transmission system identified India portion for Tala Hydro Electric project (1020 MW) in Bhutan
with an Estimated cost of Rs. 1,200 Cr – Proposed equity participation to the tune of 26%– NIT issued for Selection of JV partner through ICB
• IPTC Route– Selection of the promoter through two stages (RfQ & RfP) ICB based
on Transmission Service Charges (TSC)– International consultant appointed under the technical
assistance(TA) of ADB– Transmission licensee to establish the project under BOOT– A pilot project to be taken up shortly.
Major Challenges & their RedressalMajor Challenges & their Redressal ...contd....contd.
Realisation of Investment
Total Charges of SEBs due to POWERGRID is about 1385Cr.
Including surcharge of 317cr. as on July 2001.
As National Grid is planned on long term basis, its utilisation in initial
period will be less --- hence, transmission charges would be on higher
side. SEBs may be reluctant to pay higher transmission charges.
Poor recovery can affect health of POWERGRID --- hence future development of transmission system.
Perceived Solution: Special methodology need to be adopted for recovery of tr. charges of Transmission highways.
Major Challenges & their RedressalMajor Challenges & their Redressal ...contd...contd
Proper Load Despatch & Communication Facilities POWERGRID is implementing ULDC schemes in all five regions with
state-of-art- SCADA, EMS and dedicated Communication system at an investment of US $468 million. Schemes for NR & SR under implementatin, expected by Jun’2002.
Establishment of National Load Despatch Centre (NLDC) by
interconnecting all the regions.
Integrated Grid Operation Strict adherence to grid discipline to maintenance of voltage and
frequency.
Operation of generating units in free governor mode.
Implementation of “Availability Tariff” having provision of penalties and incentives to encourage grid discipline.
Comprises of:Capacity chargeEnergy chargeUnscheduled interchange charge
Dependent on Actual Plant Availability & generation / drawal
No provision regarding deemed generation No year-end commercial adjustments Perpetual incentive for maximizing generation &
reducing drawal during deficit, but no incentive to over generate during surplus
Availability based TariffAvailability based Tariff
Defines responsibilities between Utilities, RLDCs and REBs
Defines scheduling mechanism for day ahead scheduling of Generation and Drawal
Specified frequency bands for operation of regional grids
Frequency stabilization through free governor mode of generating units
Defines charge for Reactive Energy drawal
Indian Electricity Grid CodeIndian Electricity Grid Code
Eastern Region – Power ScenarioEastern Region – Power Scenario Effective Installed Capacity : 15,958 MW
Demand
Peak : 7800 MW (persists for 3-4 hrs a day).
Off-peak : 4500 MW (persists for 20 hrs a day).
Surplus Available -
In peak hours : 2000 MW
Extent of max. surplus : 3500 MW
Additional surplus power would be available with injection of power from Ranganadi HEP (405MW – expected by March 2002).
Eastern Region – Power Eastern Region – Power Scenario ..Scenario ..contd.contd.
Surplus Available with 68% average PLF -
In peak hours : 4500 MW
Extent of max. surplus : 6000 MW
At the end of X - Plan -
Likely increase in Installed Capacity : 6500 MW
Likely increase in Load : 2500 MW
Likely increase in Surplus power : 3000 MW
Therefore, the surplus scenario is likely to continue in future also.
Reasons for Surplus PowerReasons for Surplus Power
Poor load growth - 5% as compared to national average of 9% due to -
Non-completion of state sector transmission scheme approved long back.
Inadequate sub-transmission & distribution facilities.
Overall slow economic growth of the Region.
Adequate Inter- regional transmission links were not planned – as power was to be consumed in ER only.
On-Going SchemesOn-Going Schemes
Link Capacity (MW) Expected comm.
ER to NR
Sasaram HVDC B-t-B
(AC line is being utilised for transfer of 300MW, with HVDC 500MW would be transferred on regular basis)
500 Dec, 2002
ER to WR
Rourkela – Raipur 400kV D/c(Award placed)
700 Dec, 2002
Additional Links - ProposalAdditional Links - Proposal Feasible Capacity to
evacuate Surplus Power
(MW)
Estimated Cost
(Rs. in Crs.)
I. Tala-Delhi Transmission System 2000 2000
II. Gazuwaka – II ; augmentation by 500MW block
500 790
III. Series Capacitor on Raipur – Rourkela 400kV D/c
Raipur-Chandrapur 400 kV D/c
500 260
IV. Sasaram – II ; augmentation by 500MW block
500 350
V. Ib Valley – Jaipur HVDC Bipole of Hirma Tr. system
2500 3300
VI. Meramundali – Hosur 2000MW HVDC bipole
2000 3500
Total 8000 10,200
DEVELOPMENT OF NATIONAL GRID
NER
ER
NR
WR
SR
EXISTING
500MW
MW1000
MW500
GAZUWAKA
CHANDRAPUR
VINDHYACHAL
SASARAM
UNDERCONST.
EXISTING
400 kV
220 kV
BONGAIGAONBIRPARA
MALDA
KORBA BUDHIPADAR
KOLHAPUR
BELGAUM
U.SILERU
BALIMELA
DEHRISAHUPURI
MALANPUR
AURAIYA
PHASE-I(By 2002)
Back
ROURKELA
RAIPUR HIRMA
TALCHER
JAIPUR
NER
ERWR
NR
SR
B'SHARIF
ALLAHABAD
SIPAT
GAZUWAKA
JEYPORECHANDRAPUR
SINGRAULI
VINDHYA-
1000MW
500MW
LUCKNOW
CHICKEN NECK
KRISHNA
TEESTA
MISA
KATHAL-GURI
LEGEND
765 KV LINES
400 KV LINES
HVDC B/B
HVDC BIPOLE
EXISTING/ X PLAN
ZERDA
HISSAR
BONGAIGAON
DEVELOPMENT OF NATIONAL GRID
KOLHAPUR
NARENDRA
KAIGA
MANGALORE
PONDA
IX PLAN
MARIANI
N.K.
KAHALGAON
RANGANADI
SEONI
CHEGAON
BHANDARA
DEHGAM
KARAD
LONIKAND
VAPI
GANDHAR/
TALA
BANGLA
BALLABGARH A'PUR(DELHI RING)
BANGALORE
KOZHIKODE
COCHIN
KAYAMKULAM
TRIVANDRUM
PUGALUR
KAYATHAR
KARAIKUDI
CUDDALORE
SOUTH CHENNAI
KRISHNAPATNAM
CHITTOOR
VIJAYAWADA
SINGARPET
PIPAVAV
LIMBDI
KISHENPUR
DULHASTI
WAGOORA
MOGA
URI
BHUTAN
RAMAGUNDAM
RAVI
JULLANDHAR
DESH
NAGAR
VARANASI
/UNNAO
M'BAD
PURNEA
KORBA
NAGDA
SILIGURI/BIRPARA
TEHRI
MEERUT
BHIWADI
BINA SATNA
MALANPURSHIROHI
KAWAS
PHASE - II(By 2007)
SIRSI
CHAL
JETPURAMRELI
BOISARPADGHE
DHABOL
KOYNA
/BARH
G'PUR
HOSUR
Back
ROURKELA
RAIPUR HIRMA
TALCHER
JAIPUR
NER
ERWR
NR
SR
B'SHARIF
ALLAHABAD
SIPAT
GAZUWAKA
JEYPORECHANDRAPUR
SINGRAULI
VINDHYA-
1000MW
500MW
LUCKNOW
DIHANG
CHICKEN NECK
KRISHNA
TEESTA
TIPAIMUKH
BADARPUR
MISA
DAMWE
KATHAL-GURI
LEGEND
765 KV LINES
400 KV LINES
HVDC B/B
HVDC BIPOLE
EXISTING/ X PLAN XI PLAN
ZERDA
HISSAR
BONGAIGAON
DEVELOPMENT OF NATIONAL GRID
KOLHAPUR
NARENDRA
KAIGA
MANGALORE
PONDA
IX PLAN
MARIANI
N.K.
KAHALGAON
RANGANADI
SEONI
CHEGAON
BHANDARA
DEHGAM
KARAD
LONIKAND
VAPI
GANDHAR/
TALAARUN
BANGLA
BALLABGARH A'PUR(DELHI RING)
BANGALORE
KOZHIKODE
COCHIN
KAYAMKULAM
TRIVANDRUM
PUGALUR
KAYATHAR
KARAIKUDI
CUDDALORE
SOUTH CHENNAI
KRISHNAPATNAM
CHITTOOR
VIJAYAWADA
SINGARPET
PIPAVAV
LIMBDI
KISHENPUR
DULHASTI
WAGOORA
MOGA
URI
BHUTAN
RAMAGUNDAM
SATLUJRAVI
JULLANDHAR
DESH
NAGAR
VARANASI
/UNNAO
M'BAD
PURNEA
KORBA
NAGDA
SILIGURI/BIRPARA
PHASE - III
TEHRI
MEERUT
BHIWADI
BINA SATNA
MALANPURSHIROHI
KAWAS
AMRAVATI
AKOLA
(By 2012)
AGRA
SIRSI
CHAL
JETPURAMRELI
BOISARTARAPUR
PADGHE
DHABOL
KOYNA
/BARH
G'PUR
HOSUR
Back
Demand-Availability Scenario – by 2011-12Demand-Availability Scenario – by 2011-12
Assumptions: • Demand – as per 16th Electric Power Survey Report (EPS).• Capacity addition – as per information available from MoP & CEA.• Generation availability (average) – 75%.
All figs. are in MW
Region Demand Installed Availability Deficit/ Capacity Surplus
Northern 49000 52354 39265 - 9735
Western 46000 53343 40007 - 5993
Southern 42000 50075 37556 - 4444
Eastern+North-east 19000 44275 33206 + 14206
````````````````````
Sl. NO.
Tariff Parameter
Norms as per GOI Notification (Existing Norms)
Norms Recommended by CERC
Fin. Impact (2001-02) Rs. Crs.
1. ROE 16% 16% -
2. DEP T/L-5.27%, S/s-7.84%, PLCC-12.77%, BLDG-3.02%
T/L-2.57%, S/s-3.6% (-)355.68
3. O&M 1.5% for plain and 2% for hilly terrain
On the basis of actual O&M in last 5 years
(-)4.48
4. FERV As per actual. To be billed annually To be capitalized and charged in tariff. FERV on
interest also allowed.
(-)62.17
5. Treatment of
Corporate Tax
Grossing up of income-tax permitted
Tax recovery on actual basis, to be calculated in advance and billed on monthly basis.
(-)4.02
6. Normative availability & incentive
95% for recovery of full transmission charges 1% increase
on ROE for each % point of increase in availability beyond 95%
98% for recovery of full transmission charges.
(-)59.81