Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal...

34
Building Plumbing Civils Concreting Metal fabrication Gas fitting Asbestos removal Evidence of Capabilities

Transcript of Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal...

Page 1: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

COMPANY PROFILE

Building

Plumbing

Civils

Concreting

Metal fabrication

Gas fitting

Asbestos removal

Evidence of CapabilitiesCOMPANY PROFILE

Building

Plumbing

Civils

Concreting

Metal fabrication

Gas fitting

Asbestos removal

Page 2: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant scope

Client Location Photo of task Description Task Details

3.1-a Boyne Smelters

Carbon Area

Site office Aestec have set up a site office at Boyne Smelters at our own cost, we are also working with Chris Harp to set up access to a desk at Yarwun, advantages to client are:

1. Allow prompt service to the client. 2. Ease of management of Aestec site crew

Aestec are willing to set up site office at QAL if awarded the contract

3.1-a Boyne Smelters

Contractor laydown area

Site container Aestec site containers are set up to run our daily toolbox meeting, we have adopted the Lean methodology and have embedded 5S in our containers/workshops and storage yards. All members of our team are involved in using, auditing and improving the 5S of these areas. Each day each team member checks his or her accountable area and makes any changes or improvements as required.

3.1-a Boyne Smelters

South East corner line 3

Site laydown yard Our site laydown area is set up to store items regularly required for site use e.g. Expansion joint material, form work etc. Aestec purchase a lot of material in bulk and store it in the site specific lay down areas. This allows Aestec to pass on the reduced cost associated with bulk purchasing and reducing the overall freight costs.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 3: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-b Gladstone Area water board

South Gladstone Reservoir

Exposed steel ready for treatment and repair of concrete

Spall areas where identified and chipped back to rebar removing all poor quality concrete. It was found that the ‘drummy’ area of concrete extended well beyond the obvious spall. Chipping along the rebar showed that the corroded rebar extended deeper into the concrete in all cases and non-corroded reinforcement was not found. The chipping back was stopped and client contacted to make decision of repair or removal of parapet wall. (Parapet wall was removed)

3.1-b Boyne Smelters

Cell 160 wall

Concrete repair (completed with no impact to operations)

1. Divert all effected services (water, air, HV and LV cables) 2. Remove wall cladding and HV cable tray protection 3. Saw cut concrete to allow for safe removal of wall 4. Use excavator to demolish concrete wall 5. Prepare bonding surface and install 16mm rio 6. Install formwork and brace it ready for pour 7. Place and finish concrete including curing 8. Remove form and install all original cladding and services 9. Hand work area back to operations

3.1-b Boyne Smelters

Reduction line 1

Expansion Joint repairs

Aestec have set up a trailer specifically for expansion joints, this allow us to repair the joints in the required time frame to ensure we do not compromise the reduction line operations. Aestec work with the operations planner each week to plan the joint repairs around the operations miss areas. Aestec team members have a very good understanding of the Reduction Line and ensure safe work practices are followed. Aestec has worked with the repair product supplier to establish the best repair method for this specific application, this was done to extend the life of the repair

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 4: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-b Boyne Smelters

Metal products

Repair concrete and replace steel plate

Replace damaged concrete and 40mm steel plate. 1. Cut around the extremities of the failed area into good sound

concrete (40mm deep but do not cut rebar) 2. Oxy cut current plate tie down bars and remove 40mm plate 3. Profile cut new 40mm steel plate and weld in place 4. Mix, place and finish refectory concrete mix to finish flush

with new plate and existing concrete removing all trip hazards

All of the mechanical work was completed by Aestec Boilermakers and welded to approved weld procedures

3.1-b Boyne Smelters

Line 3 car park

Road maintenance and new installation

Aestec removed all current contaminated road base to a depth of 300mm, then replaced it with new compliant 2.1 grade mix compacted to 100% SDDR. The compacted road base was allowed the correct bake time and then capped with 40mm, 14DG asphalt installed and compacted by Aestec.

3.1-b Boyne Smelters

Line 3 car park

Road maintenance and new installation

Aestec removed all current contaminated road base to a depth of 300mm, then replaced it with new compliant 2.1 grade mix compacted to 100% SDDR. The compacted road base was allowed the correct bake time and then capped with 40mm, 14DG asphalt installed and compacted by Aestec.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 5: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-c Boyne Smelters

Reduction line 1 and 2 D-line shed

Bollards and Armco rail

The attached photo is of some installed Armco rail and ground bollards. Aestec fabricated, painted the bollards in there off site fabrication workshop and then installed the bollards on site in the correct location. Aestec have installed and painted Armco rail here and all over site, we paint the Armco rail with a spay gun as it presents a better finish then a brush. Aestec have trade qualified painters employed that perform the painting ensuring a great job every time.

3.1-c Boyne Smelters

Z Store

Fencing Aestec have installed chain mesh in various location at BSL and Yarwun. We have also installed colour bond fences at Yarwun around the CCF and Hydrate areas.

3.1-c Boyne Smelters

Line 3

Signage supply and installation

Aestec have supplied and installed numerous signs at BSL and Yarwun. The photo attached required the following job steps 1. Excavate foundations with excavator and Auger attachment 2. Form up pedestal foundations 3. Install concrete and support posts plumb and correct 4. Fixed sign to posts using galvanised bolts

All plant and equipment used is owned by Aestec

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 6: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-d Boyne Smelters

North metal pad

Installing Rio (16mm deformed bar)

Aestec has placed 15000m3 of concrete in the Gladstone area over the past years, all of which has been placed to the highest quality standard ensuring all quality assurance documents are completed to meet the required site standards. Aestec’s leaders are very familiar with the site standards and the requirements with printed copies made available to staff when required.

3.1-d Cement Australia

Fisherman’s landing

Spraying concrete batter

Aestec place all types of concrete (spray, stencil, stamped, exposed, coloured) this allows Aestec to complete all require concrete works in house without the use of subcontractors. Some of the concrete placed includes Structural walls, laydown pavement, metal pad, pathways, culverts, batters foundations and many more.

3.1-d RioTinto Yarwun

CPB

Place and finish concrete for CPB extension

Aestec poured and placed 350m3 into the CPB extension, while completing this work Aestec completed a risk assessment with the RioTinto Yarwun safety Rep and was given permission base on risk control to wear safety glasses while concreting inside the building. (Not Mono Goggles)

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 7: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-d Boyne Smelters

304 bag house foundations

Structural pile cap foundation

Aestec completed the bag house foundation on budget and on time safely. This gave BSL the confidence to engage Aestec to complete the next 3 bag house civil packages on schedule of rates purchase orders. Work included all civil excavation, compaction and detail trim prior to concrete works. Aestec also managed wag staff pilling company for the installation of the piles.

3.1-d Boyne Smelters

Sludge bunker

Detailed form work

The sludge bunker required the installation of sumps and catchment area, all concreted to direct the flow of water through the settlement areas. This project also required the installation of plumbing and fabricated painted handrails all of which was completed by Aestec requiring no subcontractors.

3.1-d Boyne Smelters

Cell 163

Pouring concrete nib wall

Aestec has poured a lot of special mix concrete including concrete grating insulation, wall repairs to the reduction line, piles and more. While performing some of these pours you can see in the attached photo it is not just the mix design that needs to be executed well there is also detailed planning of the work required as it effects numerous output teams on site.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 8: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-e Gladstone Area water board

South Gladstone Reservoir

Core drilling hole for structural through bolts

Value in use Aestec designed a jig to support the core drilling machine in the exact location to drill the holes required so there was no measuring required, this saved an average of 15mins per hole for 160 holes Saving of $6,400.00. The core drill jig is clamped onto the existing concrete beams at the location of a new steel rafter support bracket. The drill is held in position using a customized ergonomic jig.

3.1-e Gladstone Area water board

South Gladstone Reservoir

Saw cutting concrete parapet wall

Aestec’s skilled staff cut concrete of all shapes, size and locations Photo attached: Concrete wall was cut through into 6 meter sections via Scissor lift, then removed via crane Other similar tasks completed were all the holes in the side of the substations at BSL for the installation of air-conditioning ducts and vents

3.1-e Boyne Smelters

Reduction line 2

Saw cutting concrete wall

Cutting of Reduction Line concrete wall into pieces to be loaded onto Aestec truck via forklift and disposed of at the Benaraby land fill. Aestec have trained competent staff to complete any saw cutting or drilling required.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 9: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-f Boyne Smelters

Reduction line 1 and 2

Replaced preventative maintenance

Aestec complete all of the preventative maintenance to all of the Reduction Line 1 and 2 roller doors. Aestec created the PM check sheet and procedure to ensure that all of the PM checks are complete to the current best practice at all times. The Reduction Line roller doors must be operational at all times so they can be closed in storming condition protecting the reduction line from increase of wind and water.

3.1-f Boyne Smelters

Carbon

Replace tracks and electric motors

The maintenance of roller doors site wide is a task that Aestec complete very well and we pride ourselves on being one of the leaders in this field. An example of this is: Aestec repaired a roller door on site that have been condemned by others, saving BSL up $40,000 in one occasion, Aestec received a performance report for this work.

3.1-f Boyne Smelters

Line 1 and 2 bag good shed

Line 3 paste and Comcast storage

The containers you see in the photo were purchase as full second hand containers. Aestec then designed and modified the containers for the use of paste storage out of the weather. The reason for the vinyl roller system in this occasion is to absorb any impact that it may be exposed to as a lot of forklift activity is in this area.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 10: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-g Boyne smelters

North Metal pad

Compacting subgrade for metal pad concrete pavement

Aestec have installed tonnes of concrete however one of the most important layers to the pavement is the sub base and sub grade. Aestec ensure compliance to all specification through quality testing by NATA accredited third part testing company as per Australian and RioTinto Standards.

3.1-g RioTinto Yarwun

330 Area

Install basalt stone and garden mulch

Aestec install all types of ground cover utilising all owned equipment materials include Soil, rock, garden mix, garden mulch, road base, cracker dust and many more

3.1-g NRG power station

Gladstone

Tree clearing grass maintenance

Aestec currently has the contract for Vegetation management at NRG, this work includes brush cutting, slashing, tree clearing and the application of herbicides.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 11: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-h Boyne Smelters

Crane assembly work area

Installed foundations and demountable offices

Aestec were chosen to complete the installation of the foundation for Thomas and Coffey while they were working on the CAW. A number of Aestec’s employees have been working on site for more than 12 years in this time we have gained a great knowledge of the Reduction Line and it hazards.

Aestec’s Reduction Line knowledge allows all work in the area to be complete with little hassle and the assurance that safety procedures will be adhered to at all times.

3.1-h Boyne Smelters

Crane assembly work area

Installed foundations, crib room and plumbing

Aestec will work whatever hours are required by the client to complete the task. The crib rooms attached had to be installed on the weekend as there was a lot of activity through the week making very hard for all of the required contractors to work in the area. Aestec completed all work in the required time frame including plumbing of the water and sewer requirements

3.1-h Boyne Smelters

AADS project office

Installed foundations, crib room and plumbing

Aestec installed numerous foundations and offices in the AADS project area. Included in this scope of work was grey water management and water supply to taps and water bubblers including water filters

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 12: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-i Boyne Smelters

Cell 136 Cutting of tap out material

Aestec have all the equipment required to handle all spent cell and tap out materials. We have built and maintain at our cost a trailer which holds all of the equipment required to cut out Cell material. We are sometimes asked to perform this work at very short notice and it is important that our equipment is ready to go always. Aestec also have skilled staff that can cut and dispose of aluminium tap out metal, in some cases we cut the metal into manageable sizes to allow BSL to run material through furnace to help achieve required output. Aestec have developed its own training and assessment package to ensure staff are competent to complete this work as it is a high risk activity.

3.1-j Boyne Smelters

Reduction Line 1 and 2 D-line shed

Excavation of a Reduction Line Cell

Aestec have trained staff that are competent to operate the required excavator and attachment to dig out reduction line cells in the D-line shed and on the Reduction Line. However if Aestec is awarded the contract we have negotiated rates with S&S Kiely to continue to perform this work as a subcontractor to Aestec. If S&S Kiely cannot perform the task or meet the requirements of the client Aestec will then perform the work.

3.1-k Boyne Smelters

Metal products crucible cleaning building

Cleaning of metal crucibles

Aestec have trained staff that is competent to operate the required excavator and attachment to clean out metal crucibles. However if Aestec is awarded the contract we have negotiated rates with S&S Kiely to continue to perform this work as a subcontractor to Aestec. If S&S Kiely cannot perform the task or meet the requirements of the client Aestec will then perform the work.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 13: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-l Boyne Smelters

Laydown area

Jack hammering concrete/ anode material

The handling of anode materials is completed using excavator with jackhammer attachment; this photo visually demonstrates the use of Aestec equipment that can manage the requirements of the carbon quantity. However if Aestec is awarded the contract we have negotiated rates with S&S Kiely to continue to perform this work as a subcontractor to Aestec. If S&S Kiely cannot perform the task or meet the requirements of the client Aestec will then perform the work.

3.1-m Boyne Smelters

Line 3 car park

Delivering a load of Hot Mix asphalt

Aestec have a fleet of tip and flatbed trucks ranging from light to heavy rigid. Aestec also have a licence to transport Contaminated Waste Including asbestos Aestec delivers all types of materials to site including soil, garden mix, blue metal, Asphalt, and many others.

3.1-n RioTinto General

RioTinto General

Aestec own and maintain earthmoving, excavating and plumbing equipment, Aestec also dry hire equipment that is not required a lot as it reduces Aestec’s overheads allowing us to keep our entire charge out rates aggressive in the market enabling our clients to continually receive great value for money.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 14: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-o RioTinto Yarwun

East drain CPB area

Detailed excavation

Aestec were engaged to install 2000m2 of ground cover in different areas of the plant including concreting of V drains as shown in the photo attached. Aestec can perform detailed excavation to the millimetre as well as bulk earth works including a recent task utilising a 20 tonne excavator to load filter bags into skips at Yarwun.

3.1-o Boyne Smelters

Metal pad

Compaction of sub grade

Aestec operate their own plant and equipment as well as dry hired plant and equipment. Some plant/equipment Aestec operate include Excavators, loaders, trucks, graders, rollers, elevated work platforms to say a few. Aestec also own and operate a visual drainage system to inspect drain lines for condition an blockages.

3.1-o Boyne Smelters

South entrance to BSL

Installation of new asphalt

Aestec replaced the asphalt at the south entrance to Boyne Smelters. The task was to design and construct a pavement that could handle the traffic that was required to complete the CBF 4 project. Aestec engaged Road Test to design the pavement and carrier out the relevant QA testing, while Aestec carried out the earth works ready for the asphalt to be installed.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 15: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-p Boyne Smelters

Reduction Line 1 Sub Station

Installed Air-conditioning system

Aestec have a sheet metal work shop that fabricates all types of requests, the photo attached illustrates air-conditioning ducting fabricated and installed by Aestec. Aestec also concreted the foundations, painted hazardous strips, cut the holes in the wall and install the air-conditioning unit.

3.1-p Boyne Smelters

Line 3 bag good shed

Paste heater ovens

Aestec fabricated the last 4 panels (on the right) of the heater oven and the paste transport skip you can see in the picture. These item were fabricated, insulation installed, lined with sheet metal and then painted all by Aestec employees requiring no subcontractors.

3.1-p Boyne Smelters

East end of Reduction line 1

Secure flashing the building

Contractor positive performance awarded The flashing fixings had failed and there was potential for the flashing to fall onto power supply. Aestec were asked to quote the replacement of the flashing. Aestec determined that the existing flashing was in good condition it just required adequate fixings installed so that is what we installed saving the client $20,000

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 16: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-p RioTinto Yarwun

CPB

Roof and ceiling sheeting

Aestec installed all of the roof and internal ceiling sheeting on the CPB extension. This work was completed at heights with no incidents or injuries

3.1-p RioTinto Yarwun

JPU’S

Lagging of a JPU bend

Aestec currently have the sheet metal contract at Yarwun provide prompt service at all times. The JPU segments are profiled at our workshop and the installed on site. Aestec have replaced a lot of lagging on different appliances all over the site giving us a great understanding of all area and there specific requirements.

3.1-p RioTinto Yarwun

Y2 Project

Roof and wall sheeting

Aestec was awarded the project to install roof and wall sheeting as well as ridge ventilation on a large shed on the Y2 site. Aestec installed all of the sheeting and ventilation while working at heights with no incident or injury. Aestec team members were payed under the site construction agreement ensuring there were no disputes internally or externally.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 17: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-q Boyne Smelters

Reduction line 1

Temporarily divert water

Aestec replace concrete walls in different location all over Reduction Line 1 and 2, for us to complete this work we need to divert all effected services (water, air, HV and LV cables) In the past Aestec have completed all of the diversions as this is the most cost effective way of managing the work. Now the BSL rep engages the site plumbing contractor to divert the water only, this often results in down time for Aestec as it does not allow for opportunity to continue when we are ready for the plumbers prior to them arriving. The decision was made by the Rep as there is a plumbing contract in place.

3.1-q Boyne Smelters

Crane assembly area

Installation of grey water tank and plumbing

Aestec were engaged to install a crib room for the CAW, this required water supply and sewer discharge, on the site inspection Aestec made the client aware that you could not achieve the required falls on the sewer line that are specified to meet Australian standard. Aestec performed the require calculations and designed an alternate system to manage the sewer discharge. All the excavation and plumbing was completed by Aestec employees requiring no subcontractors.

3.1-q Boyne Smelters

AADS office

Installation of water supply

Aestec installed water supply to various sinks and water fountains including the installation of the correct filter systems. Aestec also installed the sewer discharge connection. Aestec also installed some of the site offices including tie down and concrete pathways. All the excavation, concreting and plumbing were completed by Aestec employees requiring no subcontractors.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 18: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-r Boyne Smelters

Carbon Maintenance male toilets

Disconnect, divert and Installation of water and sewer

Aestec complete many office refurbishments on site, as per of these refurbishments they often have plumbing services that needs to be diverted, replaced, repositioned and then recommissioned. On one occasion Aestec tried to engage the site plumbing contractor to install some fixtures, this was not as cost effective as Aestec completing the work themselves and as a result Aestec complete all works with their own plumbers ensuring quality, safety and timeliness of the tasks is achieved.

3.1-r Boyne Smelters

Carbon Maintenance male toilets

Disconnect, divert and Installation of water and sewer

As part of the office refurbishments Aestec often removes all asbestos sheeting and replaces it with the correct wall sheeting for its purpose, this include toilet areas. Photo attached is of a toilet refurbishment completed by Aestec including plumbing All work including Asbestos removal/transporting and plumbing were completed by Aestec employees requiring no subcontractors.

3.1-r Boyne Smelters

Carbon offices crib room

Disconnect, divert and Installation of water and sewer

Photo is of a kitchen that was fabricated off site by a cabinet maker then installed on side by Aestec carpenters. Prior to the kitchen being installed Aestec plumbers run all the required services to this location ensuring all aspects of the task meet the appropriate Australian standards. All on site work including plumbing were completed by Aestec employees requiring no subcontractors.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 19: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-r RioTinto Yarwun

Boiler unit 1

Installation fire system

This photo is of a fire system that Ben Matthew an Aestec director installed on the Construction of the Y1 site, Aestec has the required competencies allowing the company to hold the relevant licensing to disconnect, maintain and also install new fire systems. All work including plumbing can be completed by Aestec employees requiring no subcontractors.

3.1-r Cement Australia

Truck maintenance shed

Installation of plumbing systems

Aestec complete all required plumbing when a new shed is installed including: fire system water supply sewer management This requires tapping into existing services, demonstrating the common practice of disconnection, maintenance and reconnection of plumbing services. All works completed by Aestec employees requiring no subcontractors.

3.1-r APA Yarwun

Testing, monitoring and maintenance to Natural gas supply station for Gladstone.

Aestec have a contract for the works on the major Gas systems throughout Gladstone. The works include installation of Natural Gas mains, regulators, valves and meters. Left, shows the Yarwun Gas Station AESTEC have the contract to maintain. As part of the contract, Aestec attend to all major and minor “000” Gas emergences. This involves containing burst mains, directing emergency services to control the public and using special equipment to enter dangerous atmospheres to contain and repair the damaged gas main.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 20: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-s-i Boyne Smelters

Carbon offices

Installation of toilets, Sink and urinals

Aestec complete many office refurbishments on site, as per of these refurbishments they often have plumbing services that needs to be diverted, replaced, repositioned and then recommissioned. Aestec are also trained and competent in the programing of urinal water system timers/sensors All plumbing completed by Aestec employees requiring no subcontractors.

3.1-s-ii RioTinto Yarwun

Installation of pipe work

Aestec Installed these High Pressure Oil and Lube Lines throughout the Area 240 worth pumps, 2000PSI fittings were tested for leaks before commission, Proud employees achieved not a single leak ,out of the 200 or more meters of pipework. All piping and welding of support brackets completed by Aestec employees requiring no subcontractors.

3.1-s-iii Cement Australia

Hot water systems and heating appliances

Aestec install and maintain gas, electric and solar powered hot water systems. All plumbing completed by Aestec employees requiring no subcontractors.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 21: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-s-iv Boyne Smelters

AADS office

Installation of drinking fountains and filters

3.1-s-v Cement Australia

SBF Servicing of Eyewash & Safety

Showers

Just over 5 years Aestec have been servicing Safety showers, we are the Maintenance agents for the manufactures Enware & Speakman, allowing Aestec to deliver huge discounts to the client.

3.1-s-vi Cement Australia

Raw Water Tanks

Water flow devices

This is one of many valves Aestec have regular PM’s to complete. This Particular valve controls the inlet supply water and maintains the correct level of water in the vessel. Aestec installed this valve and the new 150mm steel pipeline three years ago, we recommended this particular valve after the existing had regular failures leaving the Fire supply with no back up supply, We have not had a single fault with the new Valve.

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-q Boyne Smelters

Reduction line 1

Temporarily divert water

Aestec replace concrete walls in different location all over Reduction Line 1 and 2, for us to complete this work we need to divert all effected services (water, air, HV and LV cables) In the past Aestec have completed all of the diversions as this is the most cost effective way of managing the work. Now the BSL rep engages the site plumbing contractor to divert the water only, this often results in down time for Aestec as it does not allow for opportunity to continue when we are ready for the plumbers prior to them arriving. The decision was made by the Rep as there is a plumbing contract in place.

3.1-q Boyne Smelters

Crane assembly area

Installation of grey water tank and plumbing

Aestec were engaged to install a crib room for the CAW, this required water supply and sewer discharge, on the site inspection Aestec made the client aware that you could not achieve the required falls on the sewer line that are specified to meet Australian standard. Aestec performed the require calculations and designed an alternate system to manage the sewer discharge. All the excavation and plumbing was completed by Aestec employees requiring no subcontractors.

3.1-q Boyne Smelters

AADS office

Installation of water supply

Aestec installed water supply to various sinks and water fountains including the installation of the correct filter systems. Aestec also installed the sewer discharge connection. Aestec also installed some of the site offices including tie down and concrete pathways. All the excavation, concreting and plumbing were completed by Aestec employees requiring no subcontractors.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICESAESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 22: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-s-vi Cement Australia

Front Boundary

Back flow prevention device

47 RPZ valves and DCV’s are tested and serviced by Aestec throughout Cement Australia. These particular valves prevent cross contamination into the Potable water supply.

3.1-s-vii Cement Australia

Raw mill building

Hose reels Cement Australia rely on Aestec to maintain a Safe & healthy Fire system throughout the site, Tested 6 monthly, Aestec perform works regularly to ensure no failures should there be an emergency.

3.1-s-viii Cement Australia

Additives Building

Sprinklers and timers

Aestec Installed this Fire Sprinkler system, it protects the Conveyor Cross belt analyser (X-ray) should a Fire break out. Regular flow testing and Alarm activation ensures the system will perform correctly in an emergency.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 23: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-s-ix Boyne Smelters

Carbon Maintenance male toilets

Install new sewer lines for urinal orientation

Aestec complete many office refurbishments on site, as per of these refurbishments they often have plumbing services that needs to be diverted, replaced, repositioned and then recommissioned. Aestec are also trained and competent in the programming of urinal water system timers/sensors. All plumbing completed by Aestec employees requiring no subcontractors.

3.1-t APA Gladstone Industrial Laundry Gas supply Valve train.

Installing gas Valve trian

Left shows a 80mm dual Gas train being installed by Aestec. This supply’s and regulates the Natural Gas to the Industrial Laundry which launder’s Boyne Smelters Work Wear. Another Gas System completed by Aestec employees requiring no subcontractors!

3.1-t Boyne Smelters

Cruice cleaning Building

Installation of appliance

Aestec Installed and commissioned this GAS Ladle Heater in Cruice Cleaning BSL. Installation of appliances are completely installed by Aestec then signed off by a third party (Third party is at no cost to the client), Aestec will be fully licensed for Installation by the 30th November 2010

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 24: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-t Cement Australia

Raw Water Tank

Hypo Dosing system

This is a Hypochlorite Dosing system into the raw water storage tank. The Concrete Pad, pipe & electrical Supports and dosing pumps and lines installed by Aestec, GE were employed to commission the system.

3.1-t Cement Australia

New Truck Maintenance Shed.

Oil Separators. This oil separator is one of many Aestec have installed and regularly service and test. This oil separator is not fully installed, we have yet to complete the Discharge pump and solids waste collector. Oil Separators are critical for environmental safety and regulatory compliance.

3.1-t Cement Australia

Settling Ponds High level Discharge Line.

This 1mtr dia Poly line allows water to be conveyed from 1 pond to another, Aestec have a number of experienced staff trained in ploy welding.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 25: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-t APA Gladstone Industrial Laundry Gas supply Valve train.

Testing of Gas Equipment for

compliance

Nathan is testing a Gas OPSO Regulator ensuring the Safety Shut off will activate should the regulator fail.

3.1-t GAWB Awoonga Dam

Welding of 700mm Dia Pipe line.

Aestec completed weld repairs and inspection Audits on the Main Water supply line from Awoonga Dam to Gladstone. This required critical shut down periods and could not have any failures !. As part of our Quality Assurance we completed in house and third party weld testing and inspections before re-charging the water lines, our coded weld team were very proud of the zero failures throughout the 4 km’s of pipeline.

3.1-t Boyne Smelters

Reduction Line 1

Concrete Wall installation

As seen in the photo, Aestec Staff have adapted to the site requirements, performing diffifult Photo attached is of some detailed form work secured ready for structural concrete to be poured via pump. Aestec work in with production plan and requirements consistently while performing this task.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICESAESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 26: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-u Boyne Smelters

Reduction line 1 and 2

Excavator using rock breaker attachment

Photo attached demonstrates qualified Aestec personal trained and competency assessed to operate and maintain equipment owner by Aestec or supplied to Aestec. Aestec has created a culture that drives ownership of equipment while an individual is operating it. Wether short term or long term, pride of the condition they leave there machine in is commonly demonstrated at daily toolbox meetings.

3.1-u

Removing cladding via EWP

Aestec do a wide range of task at heights, this sometimes requires the use of Boom lifts and Scissor lifts. Due to the frequent need to use this equipment, Aestec has trained a large percentage of its staff providing them with national accredited licences. Aestec is often utilised to provide grounds people and operators for EWP’s for BSL when they require inspection to plant at heights.

3.1-u Aestec Service

28 Benaraby Road

Compaction of sub base to engineered specification

One of Aestec core functions is earth works, attached is a photo demonstrating compaction of earth once shaped to the required RL’s. Aestec work with NATA approved third parties to complete QA testing of materials placed by Aestec Aestec has a system in place that allows for continuous training of it staff this includes operating and maintaining machinery

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-u Boyne Smelters

Reduction line 1 and 2

Excavator using rock breaker attachment

Photo attached demonstrates qualified Aestec personal trained and competency assessed to operate and maintain equipment owner by Aestec or supplied to Aestec. Aestec has created a culture that drives ownership of equipment while an individual is operating it. Wether short term or long term, pride of the condition they leave there machine in is commonly demonstrated at daily toolbox meetings.

3.1-u

Removing cladding via EWP

Aestec do a wide range of task at heights, this sometimes requires the use of Boom lifts and Scissor lifts. Due to the frequent need to use this equipment, Aestec has trained a large percentage of its staff providing them with national accredited licences. Aestec is often utilised to provide grounds people and operators for EWP’s for BSL when they require inspection to plant at heights.

3.1-u Aestec Service

28 Benaraby Road

Compaction of sub base to engineered specification

One of Aestec core functions is earth works, attached is a photo demonstrating compaction of earth once shaped to the required RL’s. Aestec work with NATA approved third parties to complete QA testing of materials placed by Aestec Aestec has a system in place that allows for continuous training of it staff this includes operating and maintaining machinery

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICESAESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 27: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-v Boyne Smelters

Reduction line 1 and 2

Cleaning of equipment prior to removal from site

Aestec often complete maintenance to client plant and equipment, prior to the equipment leaving site Aestec ensure that any site specific substances are removed to ensure the wellbeing of the public and the environment. The cleaning of Aestec owned and operated equipment is complete at the end of each task ensuring substances are not spread across site and equipment is kept in prestige condition.

3.1-w On all sites On all sites

Demobilisation of all equipment and personal from site

Aestec often perform site specific projects requiring the following: prepare site, install foundations, install site offices including services, mobilise personal, complete required project. On completion of the project Aestec demobilise: Personal, equipment and offices this includes the removal of all installed services and foundations back to original condition or better. All on site work including excavation and plumbing completed by Aestec employees requiring no subcontractors.

3.1-x Boyne Smelters

Boyne Smelters

Equipment requirements and specifications are met

Aestec currently have the contract to supply BSL with a water truck, as part of the tender process Aestec had to provide evidence that they could meet all of the specifications. Aestec have supplied to BSL and RioTinto Yarwun fully compliant vehicles ranging from utes to 25tonne excavators. Aestec pride themselves on the condition of all equipment and staff.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 28: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-y Gladstone Area water board

South Gladstone Reservoir

Construct floating work platform

Value in use Aestec designed a floating work platform to perform the reservoir roof and structure member replace. This Innovative idea to perform all works from a floating work platform saved the client an estimated $94,500.00 in crane and scaffold hire as no scaffold was required in the reservoir.

3.1-y Gladstone Area water board

South Gladstone Reservoir

Jig design to reduce work time

Value in use Aestec designed a jig to support the core drilling machine in the exact location to drill the holes required so there was no measuring required, this saved an average of 15mins per hole for 160 holes Saving of $6,400.00. The core drill jig is clamped onto the existing concrete beams at the location of a new steel rafter support bracket. The drill is held in position using a customized ergonomic jig.

3.1-y RioTinto Yarwun

Site

Set up of site container

Value in use Aestec Currently transports all items to site, most of the time requiring more than 1 trip to collect all tools and materials. With Aestec Storing the common items on site, this would reduce travel and increase production. 2 additional trips / day: 2 men 1.5 hrs / trip. $53.00 x 2 men x 1.5hrs x 2 trips. $53 x 2 x 1.5 x 2 = $318.00 / day Currently applies at least 2 day/ week. 52 weeks / year x 2 occurrences 52 x 2 x $318.00 = $33,072.00

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 29: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-y Boyne Smelters

Reduction line 1 and 2 deline shed

Replaced door Value in use The South roller door was continually being damaged by the 20Tonne excavator so instead of continually repairing the door Aestec designed and relocated the mounting structure from inside the shed to the outside of the shed this has reduced the damage. Estimated saving of $20,000.00 per year

3.1-y Boyne Smelters

Reduction line 1 and 2

Cost saving initiative implemented

Value in use

Aestec Supervisor having clearances signed prior to toolbox meeting

There are times an Aestec team is required to wait for the affected area owner to complete their morning task prior having the clearance signed this is costly for the client and frustrating for the contractor, as a result Aestec supervisors have clearance certificates signed by affected area owners prior to start of shift, this eliminated down time for the Aestec crew allowing our team to be produc-tive earlier.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICESAESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 30: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

3.1-Z Gladstone Area water board

South Gladstone Reservoir

Installation of roof Purlins

Value in use The purlins detail to be used in this project were to be 450g/m however using that type of coating system would not receive any warranty, Aestec negotiated with Strammit to supply ZAM coated purlins for the same price as the 450g/m coating which was a saving $8000.00. Zam coated purlins give a 15 year warranty which was passed on the client at no extra cost. The Down turned lip lapped zed purlins installed on rafters via the work platform.

3.1-Z Boyne Smelters

Line 3 area

Relocate equipment container

Best interest of the relevant company Aestec have been made aware of the main car park congestion and in response have: 1. Encouraged car-pooling. 2. Drive site utes home so our employees do not use car park. 3. Talking to Jo Burns about possibly moving our site container

to the other side of the site Line 3, to help reduce the need to use the main car park, Aestec are happy to relocate our container at our own cost if required.

3.1-Z Boyne Smelters

Line 1 and 2 D-line shed

Install roller door protection

Cost reduction Idea implemented Once Aestec relocated the roller door to the outside of the shed it significantly reduces the damage but did not eliminate it. Aestec then designed, fabricated and installed protection belts to reduce the impact from spent cell debris.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 31: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

Building works

Gladstone Area water board

South Gladstone Reservoir

Rafters installed on concrete precast beams

Rafters loosely bolted in place over most of the roof area. Work is progressing on final line-up and bolting of rafters from the pontoon on the left. The second pontoon at the perimeter wall is being used to fully inspect the perimeter of the parapet wall for cracking, ‘drummy’ concrete and taking concrete samples to test for chloride penetration.

Building works

Gladstone Area water board

South Gladstone Reservoir

Rafters installed on concrete precast beams

Rafters were lifted from the ground to a storage built on top of existing precast beams. Rafters were then loaded into the work platform and installed in the required location as per marking plan. Rafters are secured with 2 m24 8.8 HDG structural bolts tensioned to the required torque

Building works

Boyne Smelters

Cell 62

Building maintenance (Replace office wall line 1)

Managers office wall was damaged by forklift, Aestec replaced internal wall and external block wall then core filled with concrete. This work was scheduled and completed in a week where the manager was away on leave to ensure there was no impact to the business.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 32: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

Building works

Gladstone Area water board

South Gladstone Reservoir

Removal of timber structure

Crew working from work platform comprising PVC pipes and plywood. Existing timber is unbolted from their fixings and set down onto the pontoon then transported to the perimeter of the tank for stacking. Timber stacks are then removed to ground by crane.

Building works

Gladstone Area water board

South Gladstone Reservoir

Removal of cut concrete via crane

Lifting off a 6 metre length of parapet wall that has been cut off the top of the tank wall.

Addition Boyne Smelters

Substation

Demarcation Aestec installed the hazardous strip demarcation to the vertical face and 200mm on the horizontal edges of the foundation to warn people of the potential trip hazard

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 33: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Relevant

scope Client Location Photo of task Description Task Details

Addition Aestec 28 Benaraby Road Gladstone

Installing concrete tilt up panels

Tilt up panels were lifted by a 130 tonne crane and located into position, hold down rods were then epoxy grouted into position. Prior to the crane removing the lifting equipment the panels were welded to locating lugs on the columns.

Addition Aestec Services

28 Benaraby road Gladstone

Erect structural steel

Aestec are in the process of constructing their own workshop on a 4000m2 block of land, the structural steel shed members were fabricated and erected by Aestec employees . The workshop construction is scheduled around our client’s needs so at times it does not progress as fast as it could, if we designated a team to complete the work.

Addition Boyne Smelters

Carbon

Install new water trap

Aestec are very strong in planning and executing scheduled work, that is why we were chosen to complete the installation of inspection openings in the carbon scrubber shut down.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES

Page 34: Evidence of COMPANY Capabilities PROFILE - Aestec Services Evidence of... · Asbestos removal Evidence of COMPANY Capabilities PROFILE Building Plumbing Civils Concreting Metal fabrication

EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES Umbrella Supply Contract Contract No. CW1974582 Civil, Plumbing and Ancillary services

Addition Gladstone Area water board

South Gladstone Reservoir

Structural steel rafters

Structural steel rafters fabricated in Aestec workshop then hot dipped galvanised by a subcontractor

Addition Gladstone Area water board

South Gladstone Reservoir

Asbestos Removal All work is carried out from plywood strips laid over the brittle asbestos sheeting; full PPE and harnesses are being used. Sheeting is stacked and wrapped in polythene ready to be craned off the roof onto the ground Via crane. Existing roof structure is shown at left and this comprises asbestos cement sheeting, timber battens on timber rafters supported by steel cleats on concrete encased steel beams.

Addition Gladstone Area water board

South Gladstone Reservoir

Truck transporting asbestos sheeting.

Aestec Services are licenced Transporters for Asbestos The asbestos sheeting has been removed from the tank roof, stacked, polythene wrapped and craned from the top of the tank. The sheeting is transported to an approved landfill dump.

AESTEC

BUILDING * PLUMBING * CIVIL

S E R V I C E S EVIDENCE OF AESTEC PERFORMING SCOPE OF SERVICES