EVALUATION REPORT - National Highway...
Transcript of EVALUATION REPORT - National Highway...
![Page 1: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/1.jpg)
EVALUATION REPORT(As per Rule 35 of PP Rules,2004)
Lowest Evaluated Bidder: M/s ACEG-MATRACON (JV)(M/s Anhui Construction Engineering Group Co., Ltd. in JointVenture with M/s Matracon Pakistan (Pvt.) Ltd.)
1 1. Any other additional / supporting information, the procuring agency may like to share:*Award will be subject to final approval by the NHA Executive Board.
Generr,' -o' "qger (P&'CA)
offrciar Stamp: .,.....Natt$,. i;fif:#.ltuthoritv
**Standard Bidding Documents (SBD)
I Name of Procuring Agency: National Hiehway Authority2. Method of Procurement: Sinele Stase Two Envelope Procedure3. Title of Procuredrent: Dualization of Indus Highway (N-55), Package-Il: Karak
to Kohat (Km 60+846 - Km 127+349)4. Tender Inouirv No.: 2@90 -0D IGM(P&CA)A{HA/20 1 7/5 . PPR.A. Ref. No. 0SE): TS315691E6. Date-& Time of Bid Closins: l7'n Julv 2017 at I 100 hours local time7. Date & Time of Bid Opening: 17'n Julv 2017 at 1130 hours local time8 . No. of Bids Received: Six (06)9. Criteria for Bid Evaluation: Criteria of Bid Evaluation is attached at Annex-I.10. Details of Bid(s) Evaluation: As below
Sr.No.
Name of firmTechnical
(ifnpplicable
Financial(if
rpplicable)
Evaluated Cost(Rs.)
Rule / Regulation/ SBD** / Policy /
Basis forRejection /
Acceptance as perRule 35 of PPRules.2004.
(i)M/s ACEG-MATRACON(JV) Qualified
Price Bidopened
1r,945,666,748 * Itt Lowest
(iD IWs ESER-SMC (JV) QualifiedPrice Bidopened
13,152,628,355 2nd
(iiD M/s Frontier WorksOrganization r
QualifiedPrice Bidopened
13,250,980,101 r r dJ
(iv) M/s LIMAK-ZKB (JV) QualifiedPrice Bidopened El3'792,301,725
4th
(v)M/s SMADB _ SACHAL- usMANr - sEC (JV)
Dis-Qualified
Price Bidnot opened
PPRA Rule36 (b) (v)
(vi)M/s National LogisticsCell (NLC)
Dis-Qualified
Price Bidnot opened
-do-
![Page 2: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/2.jpg)
oAnnex-l
GOVERNMENT OF PAKISTANMINISTRY OF COMMUNICATIONS
NATIONAL HIGHWAY AUTHORITYProcurement & Gontract Administration Section
28-Mouve Area, G-9/1, lslamabad.Tel: 051 -9032727, Fax: 051 -9260419
teifxo,-r ri$r.a.Ars
![Page 3: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/3.jpg)
![Page 4: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/4.jpg)
![Page 5: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/5.jpg)
![Page 6: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/6.jpg)
![Page 7: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/7.jpg)
![Page 8: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/8.jpg)
![Page 9: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/9.jpg)
![Page 10: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/10.jpg)
![Page 11: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/11.jpg)
![Page 12: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/12.jpg)
![Page 13: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/13.jpg)
![Page 14: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/14.jpg)
![Page 15: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/15.jpg)
![Page 16: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/16.jpg)
![Page 17: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/17.jpg)
![Page 18: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/18.jpg)
![Page 19: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/19.jpg)
![Page 20: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/20.jpg)
![Page 21: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/21.jpg)
![Page 22: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/22.jpg)
![Page 23: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/23.jpg)
![Page 24: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/24.jpg)
![Page 25: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/25.jpg)
![Page 26: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/26.jpg)
![Page 27: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/27.jpg)
![Page 28: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/28.jpg)
![Page 29: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/29.jpg)
![Page 30: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/30.jpg)
![Page 31: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s](https://reader036.fdocuments.us/reader036/viewer/2022063012/5fc9c72434294d7640473af6/html5/thumbnails/31.jpg)