Eval de Proyectos Valor Ganado Evpm

download Eval de Proyectos Valor Ganado Evpm

of 17

Transcript of Eval de Proyectos Valor Ganado Evpm

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    1/17

    1

    Earned Value ProjectManagement

    Colonel John KeeseeColonel John Keesee

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    2/17

    2

    Objective

    To introduce and discuss the fundamentalsTo introduce and discuss the fundamentalsof earned value project managementof earned value project management

    Work Breakdown StructuresWork Breakdown Structures

    Program plans and schedulesProgram plans and schedules

    Earned value management systemsEarned value management systems

    Cost and schedule variancesCost and schedule variances

    Estimates at completionEstimates at completion

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    3/17

    3

    Scenario

    You have been tasked to be the projectYou have been tasked to be the projectmanager for an important projectmanager for an important project

    You have been directed to use an earnedYou have been directed to use an earned

    value management systemvalue management system

    Time to market is critical for thisTime to market is critical for this

    developmentdevelopment

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    4/17

    4

    Work Breakdown Structure

    Identifies 100 % of the work to beIdentifies 100 % of the work to beaccomplishedaccomplished

    WBS dictionary breaks the scope intoWBS dictionary breaks the scope into

    measurable tasksmeasurable tasks

    Each with an estimated valueEach with an estimated value

    Responsibility for each task assigned toResponsibility for each task assigned to

    individuals or work teamsindividuals or work teams

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    5/17

    5

    Work Breakdown Structure

    Launch Vehicle

    Payload Spacecraft Reentry vehicle Integration, Assembly,Test and Checkout

    Space Vehicle Ground Command,

    Control, Communications

    and Mission Equipment

    Space System

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    6/17

    6

    Project Master Schedule

    Detailed plan and scheduleDetailed plan and schedule Identified dependencies between tasksIdentified dependencies between tasks

    18 months18 months Estimated resources for each taskEstimated resources for each task

    10 units at $150K each10 units at $150K each

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    7/17

    7

    Project Master ScheduleTask/Event Jan - Jun Jul - Dec Jan - Jun

    Award ^Design ^

    Buy specifications ^

    Vendor quotes ^

    Purchase orders ^Receive materials ^

    Factory plans ^

    Tool design ^

    Tool fabrication ^

    Parts fabrication ^

    Assembly: sub and final ^

    Test & checkout ^

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    8/17

    8

    Project Performance Display

    0

    200000

    400000

    600000

    800000

    10000001200000

    1400000

    1600000

    Jan April July

    October

    January April July

    BCWS

    BCWP

    ACWP

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    9/17

    9

    Plan Review Before Go-Ahead

    CEO:CEO: Time to market is critical. You have 12Time to market is critical. You have 12

    months.months.

    This looks goldThis looks gold--plated at $1.5M. Youplated at $1.5M. You

    have $1.0M.have $1.0M.

    Go ahead, but come back to me withGo ahead, but come back to me with

    your progress in three months.your progress in three months.

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    10/17

    10

    The Three Month Review

    Three units scheduled for completionThree units scheduled for completion Two units actually completedTwo units actually completed

    $300,000 budgeted at this point$300,000 budgeted at this point $300,000 actually spent$300,000 actually spent

    Optimist PM: A little behind schedule butOptimist PM: A little behind schedule but

    right on the cost plan.right on the cost plan.

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    11/17

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    12/17

    12

    Earned Value Measurements

    1.1. Work scheduledWork scheduled

    2.2. Budgeted cost of work scheduled (BCWS)Budgeted cost of work scheduled (BCWS)

    3.3. Work performedWork performed

    4.4. Budgeted cost of work performed (BCWP)Budgeted cost of work performed (BCWP)

    5.5. Actual cost of work performed (ACWP)Actual cost of work performed (ACWP)

    6.6. Schedule variance (SV) = BCWPSchedule variance (SV) = BCWP -- BCWSBCWS7.7. Cost Variance (CV) = BCWPCost Variance (CV) = BCWP -- ACWPACWP

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    13/17

    13

    New Project Performance

    Display

    0

    200000

    400000

    600000

    800000

    1000000

    1200000

    January

    April

    July

    Octob

    er

    Dece

    mbe

    r

    BCWS

    BCWPACWP

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    14/17

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    15/17

    15

    Management Reserve

    Budgeted to provide the ability to adjust forBudgeted to provide the ability to adjust foruncertaintyuncertainty

    Always accounted at the total project levelAlways accounted at the total project level

    Normally retained and controlled at the totalNormally retained and controlled at the total

    project levelproject level

    Must not be eliminated by negotiationsMust not be eliminated by negotiations

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    16/17

    16

    Summary

    Earned value management system providesEarned value management system providesa key link between the cost, schedule, anda key link between the cost, schedule, and

    technical aspects of a projecttechnical aspects of a project

    Provides an early and reliable prediction ofProvides an early and reliable prediction of

    future performancefuture performance

  • 8/14/2019 Eval de Proyectos Valor Ganado Evpm

    17/17

    17

    References

    Fleming, Quentin W. and Joel M.Fleming, Quentin W. and Joel M.KoppelmanKoppelman,, Earned Value ProjectEarned Value Project

    Management,Management, PMI, Newtown Square, PAPMI, Newtown Square, PA

    20002000

    Lewis, James P.,Lewis, James P., Fundamentals of ProjectFundamentals of Project

    ManagementManagement, AMACOM, NY 2002, AMACOM, NY 2002