EUMETSAT development and plans since CGMS-46

10
CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984) Coordination Group for Meteorological Satellites - CGMS EUMETSAT development and plans since CGMS-46 Presented to CGMS-47 Plenary session, agenda item 4

Transcript of EUMETSAT development and plans since CGMS-46

Page 1: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMSCoordination Group for Meteorological Satellites - CGMS

EUMETSAT development and

plans since CGMS-46

Presented to CGMS-47 Plenary session, agenda item 4

Page 2: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

EUMETSAT currently exploits 11 satellites

METOP-A, -B & -C (98.7° incl.)

LOW EARTH, SUN-SYNCHRONOUS ORBIT

EUMETSAT POLAR SYSTEM (EPS) / INITIAL JOINT POLAR SYSTEM

JASON-2 & -3 (63° incl.)

LOW EARTH, NON-SYNCHRONOUS ORBIT

OCEAN SURFACE TOPOGRAPHY MISSION, SHARED WITH CNES/NOAA/EU

METEOSAT-8 (41.5° E)

GEOSTATIONARY ORBIT

METEOSAT 2ND GENERATION PROVIDING IODC FROM FEBRUARY 2017 – MID-2022

METEOSAT-9, -10, -11

GEOSTATIONARY ORBIT

METEOSAT 2ND GENERATION

TWO-SATELLITE SYSTEM

FULL DISC IMAGERY MISSION (15 MINS) (METEOSAT-11 (0°))RAPID SCAN SERVICE OVER EUROPE (5 MINS) (METEOSAT-10 (9.5° E))BACKUP SATELLITE AND GAP FILLER FOR RSS (METEOSAT-9 (3.5°E))

SENTINEL-3A & -3B (98.65° incl.)

LOW EARTH, SUN-SYNCHRONOUS ORBIT

COPERNICUS SATELLITES DELIVERING MARINE AND LAND OBSERVATIONS

JASON-3 IS A COPERNICUS MISSION

Page 3: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

• Flawless launch on 7 November at 01:47 CET

• Satellite-in Orbit Verification (SIOV) with ESA, CNES and NOAA concluded on 30-31 January

• 21 March: Satellite Acceptance, Commissioning and Handover to operations Review

• 15 May: 3-Metop Operations Readiness

• Planned early July:

– Operational qualification of remaining Metop-C Level 1 products

– Start of 3-Metop routine operations

Metop-C launch and commissioning

Page 4: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

Routine operations of dual Sentinel-3 marine mission started

Page 5: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

SSVT-1/-2 tests with satellite successful, SSVT-3 campaign started

12-15 November 2018 7-8 March 2019

Launch of Jason-CSA manifested for 15 November 2020

Preparations for Jason-CS/Sentinel-6

Page 6: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

Meteosat Third Generation: MTG satellites

• ESA MTG-I satellite CDR concluded on 9 May

• STM test campaign nearing completion

• MTG-I1 launch planned in Q4 2021

• MTG-I system CDR in Q4 2019

• MTG-S1 launch planned mid-2023

MTG-I Satellite STM Picture TAS

Page 7: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

(Photos courtesy ESA)

• Metop-SGA: launch planned end of 2022– ESA CDR successful (Nov. 2018), EFM and STM programmes nearing completion

Satellite STM

Eumetsat Polar System - Second Generation – EPS-SG

Satellite EFM

• Metop-SGB: Launch planned end of 2023

• Ground segment: CDR completed for two main functional chains

Page 8: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

Sentinel-5 STMIASI-NG STM METimage STM

All STM Models delivered for integration

Eumetsat Polar System - Second Generation – EPS-SG

Page 9: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

• Stations and site infrastructure services

– Ka- & X-Band stations (PDAP) factory-tested, with NOAA support

– Factory tests of S-Band station (MCO) concluded in May

– All stations will be shipped to Svalbard & Azores for on-site testing in July-September

Svalbard Site InfrastructureKa-Band and X-Band Antennas

Eumetsat Polar System - Second Generation – EPS-SG

Page 10: EUMETSAT development and plans since CGMS-46

CGMS-47 EUMETSAT-WP-01, v0, 20 May 2019 (DMT #1082984)

Coordination Group for Meteorological Satellites - CGMS

Metop-SG A1

MTG-S1

Metop-SG B1

MTG-I2

MTG-I1

2020 2021 2022 2023 2024 2025

SYS IV&V LC CAL/VALSIOV

MTG-I1 Launch

SYS IV&V LC CAL/VALSIOV

Metop-SG A1 Launch

SYS IV&V LC CAL/VALSIOV

MTG-S1 Launch

SYS IV&V LC CAL/VALSIOV

Metop-SG B1 Launch

SYS IV&V LC SIOV

MTG-I2 Launch