ETV Verification Report - European Commission · RINA, commissioned by Pozzoli Depurazione, has...

17
ETV VERIFICATION REPORT Verification Report N° “2014-DG-MP-50” for “VRT – Vacuum Rain Tank” ETV_07_VReport (08/2015) page 1/17 Final “VRT – Vacuum Rain Tank” Report N° 2014-DG-MP-50 Revision N° 01 Prepared by: Felice Alfieri Approved by (ETV Technical Manager): Laura Severino 23/09/2015

Transcript of ETV Verification Report - European Commission · RINA, commissioned by Pozzoli Depurazione, has...

ETV

VERIFICATION REPORT

Verification Report N° “2014-DG-MP-50” for “VRT – Vacuum Rain Tank”

ETV_07_VReport (08/2015) page 1/17

Final

“VRT – Vacuum Rain Tank”

Report N° 2014-DG-MP-50

Revision N° 01 Prepared by: Felice Alfieri

Approved by (ETV Technical Manager): Laura Severino

23/09/2015

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 2/17

Contents 1. INTRODUCTION ........................................................................................................................ 3 1.1. NAME OF TECHNOLOGY ....................................................................................................... 3 1.2. NAME AND CONTACT OF PROPOSER .................................................................................. 3 1.3. NAME OF VERIFICATION BODY/VERIFICATION RESPONSIBLE ......................................... 3 1.4. VERIFICATION ORGANISATION AND EXPERTS ................................................................... 3 1.5. VERIFICATION PROCESS ...................................................................................................... 3 1.6. DEVIATIONS TO VERIFICATION PROTOCOL ........................................................................ 5 2. DESCRIPTION OF THE TECHNOLOGY .................................................................................... 5 2.1 SUMMARY DESCRIPTION OF THE TECHNOLOGY ............................................................... 5 2.2. INTENDED APPLICATION (MATRIX, PURPOSE, TECHNOLOGIES, TECHNICAL CONDITIONS) ................................................................................................................................ 7 2.3 VERIFICATION PARAMETERS DEFINITION ........................................................................... 8 3. EXISTING DATA ....................................................................................................................... 10 3.1. ACCEPTED EXISTING DATA ................................................................................................ 10 4. EVALUATION ............................................................................................................................ 10 4.1. CALCULATION OF PERFORMANCE PARAMETERS ........................................................... 10 4.2. EVALUATION OF TEST QUALITY ......................................................................................... 12 4.2.1 CONTROL DATA .................................................................................................................. 12 4.2.2 AUDITS ................................................................................................................................ 12 4.2.3 DEVIATION .......................................................................................................................... 13 4.3. VERIFICATION RESULTS (VERIFIED PERFORMANCE CLAIM) ......................................... 13 4.3.1. PERFORMANCE PARAMETERS ....................................................................................... 13 4.3.2 OPERATIONAL PARAMETERS ........................................................................................... 14 4.3.3 ENVIRONMENTAL PARAMETERS ...................................................................................... 15 4.4. RECOMMENDATIONS FOR STATEMENT OF VERIFICATION ............................................. 15 5. QUALITY ASSURANCE ............................................................................................................ 15 6. REFERENCES ......................................................................................................................... 16 APPENDIX 1 TERMS, DEFINITIONS AND ABBREVIATIONS ...................................................... 17 APPENDIX 2 QUICK SCAN .......................................................................................................... 17 APPENDIX 3 PROPOSAL ............................................................................................................ 17 APPENDIX 4 SPECIFIC VERIFICATION PROTOCOL ................................................................. 17 APPENDIX 5 AMENDMENT AND DEVIATION REPORT FOR VERIFICATION ............................ 17 APPENDIX 6 TEST PLAN (WHERE RELEVANT) ......................................................................... 17 APPENDIX 7 TEST REPORT (WHERE RELEVANT) ................................................................... 17

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 3/17

1. INTRODUCTION RINA, commissioned by Pozzoli Depurazione, has verified the performance claim of the technology “VRT – Vacuum Rain Tank” according to the relevant procedures for EU ETV as for GVP Version 01 - July 7th, 2014 and the requirements set in the Specific Verification Protocol N° 2014-DG-MP-50, Revision N° 02.

1.1. NAME OF TECHNOLOGY “VRT – Vacuum Rain Tank”

1.2. NAME AND CONTACT OF PROPOSER Name: Pozzoli Depurazione S.r.l. Contact: GIORGIO POZZOLI Address: VIA M.QUADRIO 11,23022 CHIAVENNA (SO) Telephone: +39 034337475 Telefax: +39 034332798 Email: [email protected] 1.3. NAME OF VERIFICATION BODY/VERIFICATION RESPONS IBLE RINA, accredited EU ETV Verification Body, conform to the requirements of ISO/IEC 17020 for inspection bodies type A and of the GVP version 1.

1.4. VERIFICATION ORGANISATION AND EXPERTS

ROLE LAST NAME FIRST NAME

ETV TECHNICAL MANAGER

SEVERINO LAURA

ETV SERVICE COORDINATOR/ETV INSPECTOR

ALFIERI FELICE

ETV TECHNICAL EXPERT

MONETTI MASSIMILIANO

ATEX DIRECTIVE EXPERT OLIVIERI FABIO

INTERNAL REVIEWER FAZZI MATTIA

EXTERNAL REVIEWER CATTANEO CLAUDIA

1.5. VERIFICATION PROCESS The verification carried out by RINA included the following activities:

• Eligibility Assessment: The VRT System is technology eligible for EU ETV. This technology falls within the scope of the EU ETV pilot programme and in particular in the Technological Area 1 “Water Treatment and Monitoring Technologies” according to the GVP; it is ready for the market being several plants already installed and its purpose is to contribute to the environmental protection and to the efficient use of natural resources.

• Verification Proposal Assessment: The initial performance claim has been revised. RINA has provided a detailed cost estimate for the verification procedure. Based upon the cost estimate, the verification contract has been drafted and signed by the Pozzoli Depurazione and RINA.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 4/17

• Specific Verification Protocol review: Upon successful completion of the contact phase and proposal phase RINA developed the specific verification protocol following the provisions of the GVP. The drafted SVP was reviewed by an internal and by an external technical expert. The SVP includes:

o Summary description of the technology, its intended application and associated environmental impacts

o Definition of verification parameters (revised performance claim) o Requirements on test design and data quality o Requirements on test and measurement methods, definition of calculation methods for

performance parameters o Description of the way in which operational, environmental and additional parameters are to

be dealt with in the verification process o Assessment of existing data and conclusions on the need or not for additional tests or

measures • Test plan review: the test plan, drafted by Pozzoli Depurazione was subject to review and approval

from RINA. • Test system / test performance audit: a physical audit was conducted by RINA during the actual

testing of the technology in order to perform a qualitative and quantitative evaluation of the measurement system as used in the specific test. The testing activities were performed on 23rd of April 2015 by Pozzoli Depurazione at the following fuel service stations: - PV Eni 4817 Viale Montegrappa 250, 59100 Prato (VRT-219 l/h model); - PV Eni 55857 Viale Montegrappa 300, 59100 Prato (VRT-650 l/h model). The two models have been in operation at the fuels stations for more than one year. According to the Specific Verification Protocol the test was conducted in normal operating conditions and no dedicated maintenance operations have been conducted before the test.

• Test report review: the test report, drafted by Pozzoli Depurazione, was subject to review and approval from RINA.

• Verification reporting. Based on the outcome of the assessment of data and verification RINA drafted the Verification report and the Statement of Verification

• Verification Report / Statement of Verification review: the drafted Verification Report and Statement of Verification were reviewed by an internal and by an external technical expert. The verification report has been finally approved by the RINA’s ETV Technical Manager Laura Severino. A detailed time schedule of the activities carried out by RINA is available in the table 1 below.

Table 1: ETV Time Schedule TASK DATE

Eligibility Assessment August 2014

Verification Proposal Assessment September 2014

Specific Verification Protocol – Review February 2015

Specific Verification Protocol – External Independe nt Review February 2015

Test Plan Review April 2015

Test System / Test Performance Audit April 2015

Test Report Review May 2015

Verification Reporting August 2015

Verification Report / Statement of Verification – R eview September 2015

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 5/17

1.6. DEVIATIONS TO VERIFICATION PROTOCOL Four deviations from the specific verification protocol are reported from the implementation of the test activities. The deviations and their impact on the verification process are described in section 4.2.3. 2. DESCRIPTION OF THE TECHNOLOGY 2.1 SUMMARY DESCRIPTION OF THE TECHNOLOGY The rainwater leaked in the manholes of the tanks used for the storage of fuels can create noticeable problems of environmental management and compliance with the laws. The meteoric water infiltrated may contain traces of hydrocarbons.

Manholes are expected to be dry and hermetic both for safety reasons and to prevent the leakage of water into the tanks, polluting the fuel.

Actually, despite the correct construction and positioning of the manholes, the normal activity daily involves their opening for the duration of tanks loading and their inspection. If the activity, whose average duration is about 1-2 hours/day, occurs in the presence of rainfall, rainwater can fall into the manholes.

VRT system provides the suction and the following depuration of rainwater in the manholes of fuel storage tanks and in other closed areas characterized by the presence of water polluted by hydrocarbons.

The purpose of the verification is to verify that depurated waters respect the EU legislation for direct discharge in superficial water bodies (Italian D.LGS. 152/06) for total hydrocarbons and total suspended solids.

Most of the components of VRT system are classified as ATEX II and can be installed in explosive environments.

Installation of VRT system, consisting of ATEX II components, properly communicated to competent bodies, does not alter the administrative and control requirements provided by DPR 151 of 01/08/2011, regarding the regulation scheme for the discipline of procedures relative to fire prevention.

CONCEPTUAL DESIGN AND TECHNICAL COMPONENTS The principle used by VRT System is Vacuum suction and physical water treatment with oil separators.The scheme below represents the components of VRT plant that are in summary:

• suction pipes installed in the manholes – PEHD DN 20-25 SDR 11; • collector provided with nr.10 sphere valves installed inside control cabinet; • peristaltic pump ATEX2IIG installed inside control cabinet – suitable for 219 l/h, 650 l/h and 3600 l/h; • ON-OFF pushbutton system ATEXII, installed at the side of control cabinet; • pump discharge pipe – PEHD SDR 11; • electrical panel, installed outside of ATEX zone, 380 V, connected with pushbuttonsystem and pump

in the control cabinet through a 24V (or 230V Atex) cable; • siphon shaft installed underground between control cabinet and oil separator, as fire safety system; • sludge/oil separator, installed underground, provided with coalescent insert, that allows the treatment

of wastewater ensuring a maximal hydrocarbons concentration of 5 mg/l (class 1 according to UNI EN 858);

• sampling shaft, installed underground, to control discharge concentrations according to law-limits.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 6/17

FUNCTIONING OF THE SYSTEM:

Once it is confirmed the presence of water within a manhole the corresponding valve is opened. Thanks to the on-off pushbutton system the peristaltic pump is activated. The water aspirated from the manhole reach the siphon shaft and then goes into the sludge/oil separator which begins to discharge. When the manhole is completely empty the peristaltic pump is stopped through the pushbutton and the corresponding valve is closed.

The following scheme represents VRT System conceptual design.

The following figure shows a manhole with water leaked in and a VRT system installed.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 7/17

2.2. INTENDED APPLICATION (MATRIX, PURPOSE, TECHNOL OGIES, TECHNICAL CONDITIONS) VRT system provides the suction and the following depuration of rainwater in the manholes of fuel storage tanks installed by fuel stations, transport areas, private commercial activities and so on.

This system avoids the contamination of terrains and groundwater by collecting contaminated rainwater, treating in oil separator and subsequent conveyance of treated waste water to the existing sewerage system.

Although VRT system is conceived for suction and depuration of the water within the manholes, it can be also used in other closed areas interested by infiltration of water potentially polluted by hydrocarbons. A detailed description of the intended application is described in table 2.

The full range of models of the VRT system includes:

VRT - 219 l/h VRT - 650 l/h

VRT - 3600 l/h

The different names indicate the different peristaltic pump ATEX2IIG installed inside the control cabinet (219 l/h, 650 l/h or 3600 l/h). Normally, the quantity of rainwater that can be found within a manhole does not exceed 100 liters.

Hence, for a fuel service station, the most suitable model of VRT system is VRT - 219 l/h or VRT - 650 l/h. VRT – 3600 l/h is a model to be used only for particular applications. For this reason the EU ETV verification of the VRT systems focused on the verification of the following models:

VRT - 219 l/h (the principle components of this model are the sludge/oil separator NEUTRAcom 3/300 and the peristaltic pump Verderflex VF 15)

VRT - 650 l/h (the principle components of this model are the sludge/oil separator NEUTRAcom 3/300 and

the peristaltic pump Verderflex VF 25)

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 8/17

Table 2: Intended application of the technology

Matrix Purpose Technologies and technical condition s

Soil, ground water, superficial waters.

Simple, efficient and instantaneous suction of rainwater infiltrated within the manholes;

Prevention of the risk of soil and groundwater contamination;

Reducing wear of the metallic components within the manholes;

Lower economic impact in the long term.

The initial conditions under which VRT System is applicable is the presence of rainwater in manholes of fuel storage tanks or in other closed areas.

The separator ordinary maintenance must be carried out twice a year and consists in: - verification of sludge and oil quantities and eventual removal; - verification of correct working and cleaning of the emergency float; - wash of the coalescent filter; - verification of the ATEX II alarm system (if present). Waterflow range that can be treated in VRT system is from 219 l/h up to 3600 l/h.

NOTE: VRT System is not applicable if the percentage of hydrocarbons within the mixture exceeds 5 %, (e.g. in case of incidental fuel spreading). In this case fuel removal must occur through clean truck services in according with applicable laws.

2.3 VERIFICATION PARAMETERS DEFINITION The list of parameters considered in the specific verification protocol is described in Table 3.

Pump discharge parameter shows the water flow rate that can be treated in VRT system by the VRT models VRT - 219 l/h and VRT - 650 l/h. “Total hydrocarbons” and “total suspended solids” parameters have been defined according to the emission values in surface water bodies as for Legislative Decree 152/06 Italian law as transposition of EU norms 96/61/CE, 2000/60/CE, 91/156/CE and followings).

Table 3 includes also the operative conditions:

• Hydrocarbons in volume within the manholes (%) • Environmental Conditions

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 9/17

Table 3: parameters considered in the specific veri fication protocol Parameter Value

at the 95% confidence level

Existing legal Requirements and/or BAT values

Test or measurement method(s)

Test /available data (+ performer of tests)

PERISTALTIC PUMP:

Pump discharge

OIL SEPARATOR:

Total hydrocarbons concentration downstream of the plant

Total suspended solids downstream of the plant

Hydrocarbons in volume within the manholes (%)

Environmental Conditions

219 l/h ± 15%, 650 l/h ± 15%

≤ 5 mg/l

≤ 80 mg/l

1st manhole: 0,5 % diesel – 99,5 % water;

2nd manhole: 2,5 % gasoline – 97,5 % water;

3rd manhole: 5 % diesel – 95 %

T > 0 °C

No rainfalls

≤ 5 mg/l for direct discharge in superficial water bodies by D.LGS. 152/06 (italian law as transposition of EU norms 96/61/CE, 2000/60/CE, 91/156/CE and followings)

≤ 80 mg/l for direct discharge in superficial water bodies by D.LGS. 152/06 (italian law as transposition of EU norms 96/61/CE, 2000/60/CE, 91/156/CE and followings)

APAT CNR IRSA 5160 B2 Man 29 2003

APAT CNR IRSA 2090 B Man 29 2003

According to the Specific Verification Protocol.

No test /available data at beginning

of the ETV Process

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 10/17

3. EXISTING DATA 3.1. ACCEPTED EXISTING DATA No existing data was submitted by Pozzoli Depurazione.

4. EVALUATION 4.1. CALCULATION OF PERFORMANCE PARAMETERS Pump discharge flow rate The pump discharge flow rate at the siphon shaft was measured. Six measurements of flow rate have been conducted for the model “VRT - 219 l/h” and six measures of flow rate for the model “VRT - 650 l/h”. Table 4 shows the results. Some of the planned measurements were not performed; it was justified in the test registry and in the test report. The average and the confidence interval at 95 % of the confidence level have been calculated. According to the collected values of flow rate it can be confirmed that both the peristaltic pumps respect the claimed nominal values (219 l/h and 650 l/h). All the collected data fall within the claimed range (± 15 %).

Table 4: Results of the measured flow rates

VRT - MODEL 219 L/H VRT - MODEL 650 L/H

Measurement Measured flow rate [l/h] Measurement Measured flow rate [l/h]

Manhole 1 – 1° Measurement 234,25 Manhole 1 –

1° Measurement 657,17

Manhole 1 – 2° Measurement 233,25 Manhole 1 –

2° Measurement 644,01

Manhole 1 – 3° Measurement ----- Manhole 1 –

3° Measurement 641,71

Manhole 2 – 1° Measurement 230,18 Manhole 2 –

1° Measurement 659,1

Manhole 2 – 2° Measurement 228,51 Manhole 2 –

2° Measurement 632,02

Manhole 2 – 3° Measurement ---- Manhole 2 –

3° Measurement 634,47

Manhole 3 – 1° Measurement 228,17 Manhole 3 –

1° Measurement ----

Manhole 3 – 2° Measurement 220,64 Manhole 3 –

2° Measurement ----

Manhole 3 – 3° Measurement ---- Manhole 3 –

3° Measurement ----

Average [l/h]

229,17 644,75

Confidence Interval (95%) [l/h]

± 3,88 ± 9,04

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 11/17

Total Hydrocarbons and total suspended solids The analytical laboratory “Tecnologie d’Impresa Srl” was designated by Pozzoli Depurazione for the measurement of the total hydrocarbons and total suspended solids. The laboratory is accredited according to the ISO 17025 for methods in the area of analysis relevant for the verification process (Accreditation n° 0175). Six samples of total hydrocarbons and six samples of the concentrations of total suspended solids were collected at the sampling shaft. No samples have been discarded and the samples numbering was due to progressive identifications of all the samples included the test including samples collected at the siphon shaft and flow rate measurements. The measurements of total hydrocarbons and total suspended solids was performed following respectively APAT CNR IRSA 5160 B2 Man 29 2003 and APAT CNR IRSA 2090 B Man 29 2003 methods. For these data it has been calculated the average and the confidence interval at 95 % of the confidence level. Table 5 shows the results.

Table 5: Results of the measured concentrations

TOTAL HYDROCARBONS TOTAL SUSPENDED SOLIDS

Sample ID

Measured concentration at the sampling shaft [mg/l]

Aspiration from

manhole

Sample ID

Measured concentration at the sampling shaft [mg/l]

Aspiration from

manhole

3.1 1,0 1

Model 219 L/H

4.1 13 1

Model 219 L/H

7.1 1,5 2

Model 219 L/H

8.1 15 2

Model 219 L/H

11.1 1.0 3

Model 219 L/H

12.1 23 3

Model 219 L/H

3.2 2,5 1

Model 650 L/H

4.2 10 1

Model 650 L/H

7.2 2,0 2

Model 650 L/H

8.2 18 2

Model 650 L/H

11.2 0,7 3

Model 650 L/H

12.2 19 3

Model 650 L/H

Average [mg/l]

1,45 16,33

Confidence Interval (95%)

± 0,55 ± 3,71

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 12/17

4.2. EVALUATION OF TEST QUALITY 4.2.1 CONTROL DATA An In-house method was developed and used. The method developed was included in full in the specific verification protocol and in the test plan. The analytical methods applied were referenced (“APAT CNR IRSA 5160 B2 Man 29 2003 method” and “APAT CNR IRSA 2090 B Man 29 2003”

The test report included the list and summary of any amendments to the test plan and deviations recorded during tests, all analytical and calculated data as well as a reference to the staff that performed the test, the description of test measurements and performance parameters from raw data, the details on equipment used. Regarding the analytical results test reports were drafted by the ISO 17025 test body “Tecnologie d’Impresa Srl”.

A validation of the method has been conducted by Pozzoli Depurazione in order to assess whether the method is fit for the intended use. For this purpose several samples have been collected at the siphon shaft on the 23rd of April 2015 and analyzed by the laboratory – “Tecnologie d’Impresa Srl”.

A test system control was performed by Andrea Invernizzi (Pozzoli Depurazione) at the test site on the 23rd of April 2015 before the starting of the testing activities. The test system control included an evaluation of the following equipment:

• adequate tool to open the manholes; • a graduated rod and a reagent paste to measure the thickness of oil within the separator; • adequate graduated containers to realize the correct water-fuels mixture within manholes and

separator; • a test register and a digital camera in order to document all test procedures; • a graduated beaker of 5000 ml and a chronometer to measure the flow rate within the siphon shaft; • a kit of sampling for total hydrocarbons, supplied by the ACCREDIA certified EN ISO/IEC 17025

laboratory – “Tecnologie d’Impresa Srl” according to APAT CNR IRSA 5160 B2 Man 29 2003 method, that includes 12 clean glass bottles of 1000 ml and what necessary for the stabilization of samples (hydrochloric acid, pipette, dosers, ecc).

It was concluded, that the equipment was suitable for the test activities. An internal audit was conducted by the Internal Auditor (Bruno Soracco) in order to verify the compliance of the testing activities carried out to the test plan and to the specific verification protocol. The internal auditor confirmed the correct modality of execution of the test. Verification registers and spreadsheet used for the collection of data and for the calculations of the results were subject to control and on a sample basis (spot validation of at least 5 % of the data) from RINA.

4.2.2 AUDITS A test system audit was conducted on site on 23/04/15 by Felice Alfieri (ETV Inspector) and Fabio Olivieri (Technical Expert). It was evaluated whether the testing was done according to the requirements specified in the test plan and in the specific verification protocol. In particular the auditing activities carried out included the check of the test equipment, the assessment of the preparation, sampling and handling of samples, the check of the test methods applied, of the measurement traceability, the control of data, the quality assurance activities and the result reporting. It was concluded from the audits, that there was consistency with the test plan and set up and that handling of measurements were carried out as described; testing premise and environmental conditions were in line with the SVP requirements; the sampling was performed according to APAT CNR IRSA 5160 B2 Man 29 2003 method, the samples for total hydrocarbons (collected within clean glass bottles not completely filled)

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 13/17

were taken to pH=2 with 1:1 diluted hydrochloric acid in order to inhibit the bacterial activities. These samples have been put in a refrigerator and conserved at 4°C until the delivery at the laboratory “Tec nologie d’Impresa Srl” located in Via Don Minzoni, 15 Cabiate (CO). The samples have been provided to the laboratory on 23rd of April 2015 according to the laboratory instructions for preparation and delivery according to the test reports provided by the laboratory. The analytical results for the samples have been communicated from the laboratory to Pozzoli Depurazione on 11/05/2015.

Also the quality management system was object of audit. Pozzoli Depurazione is an ISO 9001 Certified Organization. Organizational documents were checked including the quality manual, the organizational charts, training registrations and planning. In conclusion the quality management system complies with the requirements set out in C.III. of the GVP. 4.2.3 DEVIATION Two deviations from the Specific verification protocol are reported. An overview with a description of the deviation and the impact/consequence is given in Table 6.

Table 6: Deviation from the specific verification p rotocol No. Description of deviation Impact / consequence 1 At the test site PV Eni 4817 Viale

Montegrappa 250, 59100 Prato was possible to carry out only two measures of flow rate per manhole because at the same time the operators had to collect samples at the siphon shaft (DEVIATION NR.1)

This deviation has no impact on the demonstration of the respect of the performance claim. The test results are in line with the performance interval claimed.

2 By PV Eni 55857 Viale Montegrappa 300, 59100 Prato, during the aspiration from manhole 3, after the three minutes provided, it was not possible to measure the flow rate because of the general conformation of the manhole (DEVIATION NR.2)

This deviation has no impact on the demonstration of the respect of the performance claim. The test results are in line with the performance interval claimed.

4.3. VERIFICATION RESULTS (VERIFIED PERFORMANCE CLA IM) 4.3.1. PERFORMANCE PARAMETERS According to the verified performance (Table 7) VRT system (models VRT - 219 l/h and model VRT - 650 l/h) provides the suction and the following depuration of rainwater in the manholes of fuel storage tanks installed by fuel stations, transport areas, private commercial activities and so on ensuring a maximal total hydrocarbons concentration at discharge of 5 mg/l and maximal total suspended solids concentration at discharge of 80 mg/l for both the models and a pump discharge flow rate of 219 ± 15%, 650 ± 15% respectively. This performance has been verified with the operational conditions specified in 4.3.2.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 14/17

Table 7: Verified performance for the selected perf ormance parameters (95 % confidence intervals are shown in brackets). Parameter Claimed Performance Verified Performance TOTAL HYDROCARBONS (Total hydrocarbons concentration downstream of the VRT System)

≤ 5 mg/l

1,45 mg/l [0,9 – 2 ]

TOTAL SUSPENDED SOLIDS (Total hydrocarbons concentration downstream of the plant)

≤ 80 mg/

16,33 mg/l

[20,04 – 12,62 ]

PUMP DISCHARGE FLOW RATE (model 219 l/h)

219 l/h ± 15%,

229,17 l/h

[225,29 – 233,35]

PUMP DISCHARGE FLOW RATE (model 650 l/h)

650 l/h ± 15%

644,75 l/h

[635,71 – 653,79]

4.3.2 OPERATIONAL PARAMETERS The testing and verification activities were performed with different fuel-water emulsions simulating real events of pollutions in the manholes of fuel storage tanks (up to 5% of fuel). Mixture preparation will be carried out by Pozzoli Depurazione operators according to the instructions of the ACCREDIA certified EN ISO/IEC 17025 laboratory – “Tecnologie d’Impresa Srl” as described in Table 8.

A hydrocarbons concentration in volume within the oil separator >0,5% was ensured in order to simulate real conditions (oil separators stores the oil separated in previous treatments). Using a graduated rod and a reagent paste it was measured the thickness of separated oils within the sludge and oil separator. Through this thickness it was calculated the volume of separated oils contained in the separator.

Sludge and oil separator NEUTRAcom 3/300 has a cylindrical shape. To a thickness of 4 mm corresponds a percentage of oils that represents the 0,5% of the whole volume1. The measured thickness ensured hydrocarbons concentration in volume within the oil separator >0,5%.

Appropriate environmental conditions were ensured (T > 0 °C and no rainfalls) for the test performance . See the details in table 8

1 The internal diameter is 1200 mm. The distance between the bottom and the outlet of the separtator is 760 mm, so the maximum content of the separator is: 600 mm x 600 mm x π x 760 mm = 859514400 mm3 = 0,86 m3 The 0,5 % of the total content is 859514400 mm3 x 0,005 = 4297572 mm3. The correspondent thickness is: 4297572 mm3 / (600 mm x 600 mm x π) = 3,8 mm From this calculation we have chosen the value of 4 mm as thickness of separated oil that exceeds 0,5 % of total volume.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 15/17

Table 8: Operational Parameters Operational Parameter Value

Hydrocarbons in volume within the oil separator (%)

>0,5%

Hydrocarbons in volume within the manholes (%)

1st manhole: 0,5 % diesel – 99,5 % water; 2nd manhole: 2,5 % gasoline – 97,5 % water; 3rd manhole: 5 % diesel – 95 % water

Environmental Conditions T > 0 °C No rainfalls

The test results confirm that VRT is suitable for the treatment of water with a percentage of hydrocarbons within the mixture up to 5 %. In case of higher percentage (e.g. in case of incidental fuel spreading) the removal must occur through cleaning truck services according with the local legislation.

4.3.3 ENVIRONMENTAL PARAMETERS The relevant environmental parameters are included as performance parameters as described in section 4.3.1

4.4. RECOMMENDATIONS FOR STATEMENT OF VERIFICATION Based on the verified performance described in section 4.3 above it is recommended to issue a Statement of Verification including results on the following parameters:

• pump discharge flow rate • Total hydrocarbons concentration downstream of the VRT System) • Total hydrocarbons concentration downstream of the plant • Operational Parameters: Hydrocarbons in volume within the manholes (%)

5. QUALITY ASSURANCE The personnel and experts responsible for quality assurance as well as the different quality assurance activities are described in the table 9.

• Review of the SVP: an internal technical review and an external technical review from an external technical expert. The internal review was performed by Mattia Fazzi (qualified as ETV Inspector). External review was performed by Claudia Cattaneo (qualified as Technical Expert):

• test plan and test report review: the test plan and the test report was subject to a review by Massimiliano Monetti, a qualified technical expert from RINA. The ETV inspector Felice Alfieri (Coordinator for this specific inspection activity) approved the test plan and the test report;

• test system control: it was performed by Andrea Invernizzi (Pozzoli Depurazione); • the internal audit of the testing process was performed by Bruno Soracco; • test system audit / test performance audit: a physical audit was conducted by the ETV Inspector

Felice Alfieri and by the Technical Expert Fabio Olivieri during the actual testing of the technology; • The verification report and the statement of verification were reviewed according to EU ETV pilot

programme. External review was performed by Claudia Cattaneo. An internal review was performed by Mattia Fazzi. The verification report has been finally approved by the RINA’s ETV Technical Manager Laura Severino.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 16/17

Table 9: Verification and Quality Assurance plan ETV

Inspector ETV

Technical Expert

Technical Expert (ATEX

Directive)

ITR E-ITR Proposer Proposer (Internal Auditor)

Personnel Responsible

Felice Alfieri

Massimiliano Monetti

Fabio Olivieri

Mattia Fazzi

Claudia Cattaneo

Bruno Soracco

Task

Specific Verification Protocol

Draft Review Review Review and approve

Test Plan Approve Review Review

Test System at test site

Audit Audit Audit

Test Performance

Audit Test System Control

Audit

Test Report

Approve

Review

Review

Verification Report

Draft Review Review

Statement of Verification

Review Review Acceptance

6. REFERENCES EU Environmental Technology Verification Pilot Programme. General Verification Protocol, version 1.1 of 07-July-2014 APAT CNR IRSA 2090 B Man 2003– Metodi Analitici per le acque. Decree152/06. Italian law as transposition of EU norms 96/61/CE, 2000/60/CE, 91/156/CE and followings.

Verification Report N° “2014-DG-MP-50” for “VRT – Vacu um Rain Tank” ETV_07_VReport (08/2015) page 17/17

APPENDIX 1 TERMS, DEFINITIONS AND ABBREVIATIONS “EU ETV – European Environmental Technology Verific ation” is the EU programme providing for third-party verification, on a voluntary basis, of the performance claims made by technology manufacturers in business-to-business relations. “GVP – General verification protocol” means the description of the principles and general procedure to be followed by the ETV pilot programme when verifying an environmental technology. “SVP – Specific verification protocol” means the protocol describing the specific verification of a technology and applying the principles and procedures of the General verification protocol. “Performance claim” means a set of quantified and measurable technical specifications representative of the technical performance and environmental added value of a technology in a specified application and under specified conditions of testing or use. “Verification” means the provision of objective evidence that the technical design of a given environmental technology ensures the fulfilment of a given performance claim in a specified application, taking any measurement uncertainty and relevant assumptions into consideration. “Deviation” is a change to a specific verification protocol or a test plan done during the verification or test step performance. “Pozzoli Depurazione” is Pozzoli Depurazione S.r.l. “RINA” is RINA Services S.p.A. “Test performance audit” means the quantitative evaluation of a measurement system as used in a specific test, e.g. evaluation of laboratory control data for relevant period, evaluation of data from laboratory participation in proficiency test and control of calibration of online measurement devices. “Test system audit” is the qualitative on-site evaluation of test, sampling and/or measurement systems associated with a specific test. “Test system control” is the control of a test system as used in a specific test. E.g. test of stock solutions, evaluation of stability of operational and/or on-line analytical equipment, test of blanks and reference technology tests. “Accreditation” has the meaning assigned to it by Regulation (EC) No 765/2008. APPENDIX 2 QUICK SCAN The report from the quick scan is attached to the verification report as a separate file. APPENDIX 3 PROPOSAL The verification proposal is attached to the verification report as a separate file. APPENDIX 4 SPECIFIC VERIFICATION PROTOCOL The specific verification protocol is attached to the verification report as a separate file. APPENDIX 5 AMENDMENT AND DEVIATION REPORT FOR VERIF ICATION No amendment report has been made for the verification of the VRT System. The deviations are described in the test report in a separate file. APPENDIX 6 TEST PLAN (WHERE RELEVANT) The test plan is attached to the verification report as a separate file. APPENDIX 7 TEST REPORT (WHERE RELEVANT) The test report is attached to the verification report as a separate file.