ETCS on East Coast Main Line - IRSE on East Coast Main Line... · Testing – T and C Strategy •...

download ETCS on East Coast Main Line - IRSE on East Coast Main Line... · Testing – T and C Strategy • Factory and Lab Testing (off site) • Application Data Preparation, Verification

If you can't read please download the document

Transcript of ETCS on East Coast Main Line - IRSE on East Coast Main Line... · Testing – T and C Strategy •...

  • ETCS on East Coast Main Line

    1

    David MacLennan & Graeme Boyd

  • Introduction

    Why Growing Pains?

    Is ETCS mature?

    Does GSM-R meet the requirements for ETCS?

    Cambrian lessons learned, but not like for like

    we had nothing to measure against

    No rule sets, no reference design, immature

    team, modelling simulating requirements not

    understood, no NR standards, rule books did not

    define ERTMS

    Its a Development Project

    2

  • ERTMS

    3

  • 4

    ECML ETCS Project

    Complex or Complicated?

  • Why ERTMS on the ECML?

    Driven by the Conventional Interoperable Directive

    (2001/16/EC) TENS route

    Control, Command Signalling TSI provision of ATP

    Signalling life expired

    To meet 2020 timetable requirements

    ETCS is enabling the Digital Railway strategy

  • What is ERTMS?

    European Train Control System

    (ETCS).

    Euroradio (Railway-specific GSM: GSM-

    R).

    European Traffic Management Layer

    (ETML).

    European Operating Rules (EOR).

    ERTMS

    6

  • KXR Kings Cross Remodelling Conventional Signalling Commission Feb 2018 (Date to be agreed by industry)

    Area of Conventional Signalling Commissioning (Non-ETCS)

  • King Cross -1972

  • Phase 1A - King Cross to Wood Green ETCS Lv2 With Signals Commission December 2018

    Transitions onto ECML from Conventional Signalled Railway

    Transition onto ECML from Thamelink (Baseline 2)

    Area of ETCS Commissioning - ERTMS Lv2 With Signals (Baseline 3)

    Area of ETCS Commissioning ERTMS Lv2 without signals (Baseline 3)

  • Phase 1B - King Cross to the 73 Mile Post ETCS Lv2 Without Signals

    Commission Post February 2020

    (Date to be agreed by industry) Transitions onto ECML from Conventional Signalled Railway

    Transition onto ECML from Thameslink (Baseline 2)

    Area of ETCS Commissioning - ERTMS Lv2 without signals (Baseline 3)

  • Phase 2 - 73 Mile Post (Peterborough) to 154 mile post (Decoy). ETCS Lv2 Without Signals Commission December 2020

    Decoy

    Peterborough

    Transitions onto ECML from Conventional Signalled Railway

    Area of ETCS Commissioning - ERTMS Lv2 without signals (Baseline 3)

    Ely

    (Anglian

    route) GN/GE

    Grantham Newark Retford

    Doncaster

    Stamford

    Sleaford

    Nottingham

    Nottingham

    Lincoln Gainsborough

    Cottam

    Power

    Stn

    Worksop

  • What is GRIP 1-3 for an ETCS project?

    What does AIP

    look like?

    What are the

    survey

    requirements?

    Where are the

    system

    boundaries?

    Who is dealing

    with that? What standards

    do we follow?

  • National Operating Strategy

    The Centralisation of Signalling

    Deployment of Traffic Management (enable ERTMS)

    Operational savings

    Improved headways

    De-conflicts train movements in advance

    Improved train performance

    Delays reduced

    14

  • ERTMS Sub sets

    CCS TSI

    System Requirements Specification (SRS)

    Operating Principles and Rule Sets

    National Rule Set

    Reference Design

    Operational route requirements

    EFDs

    15

  • Building Blocks

    TSIs, SRS,

    etc.

    Reference

    Design

    Applications

    Sele

    ct

    an

    d

    assem

    ble

    Sele

    ct

    and

    ap

    ply

  • Baseline 3 Maintenance Release 2

    Current Baseline not forward compatible, on board

    issue

    Supports GPRS

    Corrects 2.30d bugs

    17

  • ETCS Test & Commission Strategy

    18

  • Testing T and C Strategy Factory and Lab Testing (off site)

    Application Data Preparation,

    Verification and Validation

    (Reflects the EFD and ORS

    requirements, tested via

    trackside simulation)

    Functionality Testing (lab/factory

    via a simulator rig)

    Static and Systems Integration Testing (proving that the new system can interface with external systems/equipment)

    Whole System Test Integrating

    testing with onboard equipment

    for all Train and Freight

    Operators (Test track, test facility

    or third party test house)

    GSM-R testing

    Trackside Installation testing interlockings, axle counters etc

    Static Testing Positioning and

    checking of balises and marker

    boards

    Dynamic Testing on-track

    confidence testing

    Functionality Testing RBC

    handovers, driving without a

    ETCS MA, transition testing,

    emergency brake application,

    start of mission

    Shadow running

    19

  • ETCS Facilities Diagrams (EFDs)

    End of the scheme plan

    Define requirements, such as shunting areas

    Prove 2020 timetable

    Demonstrate train movements and transitions

    Provides a benchmark

    MSRP does this change?

    20

  • ETCS Facilities Diagrams (EFD)

  • Transitions

    22

  • 23

  • E&P Strategy

    24

  • Why we need an ERTMS E&P Strategy

    No guidance or standards on what ETCS power requirements are

    Condition of the lineside distribution current 650 lineside distribution is

    non-compliant

    Opportunity to rationalise existing lineside plant infrastructure and to

    lower asset count

    Opportunity to take a systematic approach to how we distribute power to

    our signalling, ETCS and GSM-R assets

    Reduction in overall load due to the removal of signals

    Opportunity to increase reliability by taking power from more reliable

    sources

  • ETCS E&P Strategy Process Map

    Non ETCS Project

    Infrastructure Changes

    Responsibility Jacobs and

    Project

    Desktop Surveys and ACAR

    Responsibility - Jacobs

    Dedicated Trackside Surveys

    Responsibility - Jacobs

    Single Line ETCS Equipment

    Facilities Diagram

    Responsibility - Jacobs

    PSP details, Trackside

    Feeder limits, DNO Spare

    Capacity, Scheme Fringe

    Power Supplys

    Responsibility - Jacobs

    Prams Assignment

    Responsibility Signalling

    Innovations Team

    Systems Requirements

    Responsibility PRS, Project

    and Technical Services

    ETCS Suppliers Input

    Generic Family of Single Line

    Diagrams (SLDS)

    Responsibility Signalling

    Innovations Team

    Outline Technology and

    Product Strategy

    Responsibility Signalling

    Innovations Team

    Architecture Process

    Documents and Design Tools

    Responsibility Signalling

    Innovations Team

    LV Power Architecture

    Requirements and Plant

    Strategy Report

    Responsibility - Jacobs

    Selection of Phase 1 Specific

    SLDs

    Responsibility - Jacobs

    Grip 3 E&P AIP

    GRIP 4 Design

    ETCS E&P Strategy Process Map

    Grip 1-3

  • ETCS E&P Process Strategy ETCS E&P Strategy Process Map

    Grip 4-8

    GRIP AIP Design, Process

    Tools and Strategy

    SLD Development and

    Detailed Design

    ETCS Framework Supplier

    Industry Rollout and Training

    Requirements

    Responsibility Signalling

    Innovations Team/ ETCS

    Framework Supplier

    Technology and Product

    Development

    Responsibility Signalling

    Innovations Team/ ETCS

    Framework Supplier

    AFC Design

    Responsibility ETCS

    Framework Supplier

    Construction and Testing

    Responsibility ETCS

    Framework Supplier

    Lessons Learned

    Responsibility Signalling

    Innovations Team/ ETCS

    Framework Supplier

    Trail Sites

    Responsibility Signalling

    Innovations Team/ ETCS

    Framework Supplier

    GRIP 4-5

  • Learning from the Cambrian

    Understand local procedures- Operations and

    Maintenance

    Asset information line speed and gradient profiles,

    existing infrastructure

    GSM-R and FTN deployment is it sufficient?

    Migration strategies

    Metric or imperial?

  • Whole Life Costs

    Reduced maintenance requirements

    Less signallers required

    Reliability and availability improved via new

    technologies and improved monitoring

    More train paths

    Reduced testing and installation labour costs

    Reduced delay costs

    29

  • Collaborative approach BS11000

    SharePoint & ProjectWise The projects repository, accessible by all delivery partners.

    Skills Matrix Quick reference guide to available skill sets within the project team

    Integrated Risk Management Plan Collaborative Risk Management

    Integrated ETCS Programme Collaborative project planning

    Collaborative Project Communications Strategy

    Frequent collaborative Pulse Checks A tool for continuous improvement

    LNE Vertical Integration Plan Visual representation/tracker of collaborative partners along the route

    IDCs / IDRs Executed against an agreed Value Management Strategy

  • Challenges

    Managing the perception of a GSM-R network

    Timescales

    Clarity of overall requirements

    Limited Radio Resource Pool

    No absolute consensus on enhanced coverage levels

    Absence of signalling design

    Finalised GPRS specifications not yet available

    Building a case to support the need for an RSV train for programme and ongoing

    maintenance use

    Lineside communications post signal removal

    31

  • 32

    GSM-R GRIP 3 Delivery Strategy

    GSM-R Capacity

    assessment

    GSM-R Coverage

    assessment

    GSM-R options

    Coverage &

    Capacity

    Availability model

    based on new

    requirements

    Availability on

    current network

    build

    GSM-R availability

    enhancement

    report

    FTN availability

    enhancement

    report

    GPRS Required? GSM-R + FTN

    Tech Reports

    FULL

    GRIP

    3

    OUTPUT

  • GSM-R GRIP 3 Complexity

    33

    GSM-R Coverage

    Assessment

    (Telent)

    GSM-R Capacity

    Assessment

    (Graffica)

    ETCS Availability

    Assessment

    (Lucien)

    GSM-R Technical Report

    (Kapsch)

    FTN Technical Report

    (TDG)

    Telecoms GRIP 3 Report

    (NRT)

    Maximum

    number of trains

    per cell

    Rec

    omm

    end

    ed re

    med

    ial

    wor

    k incl.

    additio

    nal

    site

    s

    Targete

    d

    and pre

    dicted

    availab

    ility

    Targetedand predicted availability

    Recommended remedial

    work incl. additional sites

    GSM

    -R Technical

    Options assessm

    ent

    FTN

    Tech

    nica

    l

    Opt

    ions

    ass

    essm

    ent

    Additional Sites,

    Base Stations re-

    parenting,

    RBC connections,

    CSD VS PSD

    FTN Options for improved

    availability

    FTN options

    availability

    enhancements

    (NRT)

    FTN o

    ptio

    ns fo

    r

    impr

    oved

    ava

    ilabi

    lity

    GSM-R options

    availability

    enhancements

    (Kapsch)

    GSM-R options

    for improved

    availability

    GSM-R Options for improved

    availability

    GSM-R options

    Coverage and

    Capacity

    (Kapsch)

    GPRS

    required?

    GPRS

    required?

  • GSM-R EIRENE

    EIRENE Specification : Minimum value for coverage

    Coverage probability of 95% based on a coverage level

    of 41.5 dBmV/m (-95 dBm) on lines with ETCS levels

    2/3 for speeds lower than or equal to 220km/h.

    34

  • GSM-R So where were we?

    ECML mainly set up for voice only and CSD

    Telent reports on coverage were available

    Design initially started with these, However!

    RSV is set up for testing voice only and has old

    equipment (no stopping pattern)

    No remit from sponsor for ERTMS Telecoms

    ENIF identified coverage issues even though plots

    showed ok

    Interference from MNOs

    RSV being retired

    Other ETCS Projects e.g. Thameslink

    35

  • GSM-R - What happened next?

    National ERTMS Telecoms Steering Group

    Remit from Sponsor

    Issues identified

    Requirement for Guidance Notes required

    Design route changed NRT/Telent/Kapsch

    Feedback from other European Administrations

    sought

    No new FTN nodes!

    36

  • GSM-R Guidance Notes

    37

  • Coverage

    38

    Coverage Coverage

    Mainly due to

    B1042

    overbridge

    B1042

  • GSM-R Seasonal Variations

    39

  • GSM-R Target Levels

    40

  • GSM-R Minimum Levels

    41

  • Capacity

    Existing GSM-R Network is Circuit Switched

    Most of the BTS on route have only 1 DRX installed

    Increase required for data and voice in normal and

    perturbed operation

    Timetable require 28 trains per hour what does that

    mean?

    42

  • 43

    Capacity HERMES Capacity CSD GPRS/EDGE

  • Capacity HERMES Summary

    44

    Circuit Switch or GPRS?

  • CSD Vs PSD

    45

    Ingo Wendler / UIC Project Manager - ETCS over GPRS

  • RBC Connections

    0

    10

    20

    30

    40

    50

    60

    70

    00

    :01

    :10

    04

    :09

    :21

    05

    :55

    :12

    06

    :34

    :21

    07

    :07

    :00

    07

    :35

    :09

    08

    :03

    :40

    08

    :32

    :29

    08

    :59

    :14

    09

    :26

    :39

    09

    :54

    :09

    10

    :23

    :22

    10

    :52

    :07

    11

    :22

    :04

    11

    :49

    :59

    12

    :19

    :30

    12

    :48

    :00

    13

    :17

    :25

    13

    :46

    :10

    14

    :15

    :37

    14

    :44

    :51

    15

    :14

    :43

    15

    :43

    :30

    16

    :12

    :29

    16

    :39

    :35

    17

    :06

    :38

    17

    :33

    :57

    18

    :01

    :08

    18

    :28

    :27

    18

    :55

    :11

    19

    :24

    :53

    19

    :53

    :38

    20

    :23

    :36

    20

    :52

    :36

    21

    :23

    :05

    21

    :54

    :17

    22

    :28

    :05

    23

    :05

    :41

    ---------- Total Connections

    ---------- Total Connections

  • Availability

    47

    But what about the system as a whole???

  • Lineside Communications after ETCS Level 2?

    48

    Or what happens to

    SPTs?

  • Summation

    Where are we with respect to Growing Pains?

    What next?

    Standards and rule sets

    GSM-R or LTE?

    FTN-X

    Lineside Communications

    Maintenance issue 2

    ERTMS Level 3?

    49

  • Q & A?

    50