Multi-Family Fourplex Apartment ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Transcript of ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Page 1: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Multi-Family Fourplex Apartment

ET-493 Senior DesignBy: Brian Toomer

Advisor: Mr. Rode’

Page 2: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Purpose The purpose of this project is to show that I can

complete a construction project using all aspects of the construction process.

This project will exercise the skills and abilities learned from the Construction Engineering Technology program.

Page 3: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Pre-Design and Design Phase(First Semester)

Preliminary Drawings Rough Estimate Economic Feasibility Report Site Assessment and Selection Decision on Building Layout Building Codes

Page 4: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

The Building Wood Framed Concrete Foundation

Estimated 3,826 sq. ft. for each building

Estimated 957 sq. ft. for each unit.

Page 5: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Preliminary Drawings Drawings will be used for a rough estimate and

budget.

One story layout. Two story layout.

Each building will have 4 units. Three bedrooms Two Bathrooms Kitchen Utility Living and Dining Room

Page 6: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Two Story FourplexFirst Floor

Page 7: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Second Floor

Page 8: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

One Story Fourplex

Page 9: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Economic Feasibility Assessment

Cost/Benefits Analysis• Do the Benefits outweigh the Costs for the

owner? • Will it be a profitable business ?• How long will it take for the business to pay

itself off?

Page 10: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Site Assessment and Selection Location will be in the Hammond area. The owner would like a site big enough for future

expansion, if desired.

Once the land is chosen it will be surveyed. Building codes will be acquired.

The location, size, and cost of property will determine:• The building layout that will be used. • The number of buildings that can be built on

the property.

Page 11: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Conclusion The completion of the activities this

semester will allow the full completion of the pre-construction documents for next semester.

Page 12: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Pre-Construction Documents(Second Semester)

The construction documents will include:

Final Drawings (using AutoCad): Floor plan Electrical Plumbing Elevations Schedules and Details of Construction Overall Site Drawing (parking included)

Page 13: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Pre-Construction Documents Cont.

Building specifications Building Permits Project budget and financing A complete estimation of labor, costs, and

materials Detailed materials and equipment list Planning and scheduling of the project using

Primavera Project Planner.

Page 14: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Timeline (First Semester)

  Aug-20-Aug 22 Meet with advisor to discuss topic

Aug 25 - Aug 29 Cont.

Sept1 - Sept 5 Cont.

Sept 8 - Sept 12 Select a Project

Sept 15 – Sept 19 Begin Research

Sept 22 – Sept 26 Prepare Proposal and Presention

Sept 29 – Oct 3 Preliminary Drawings

Oct 6 – Oct 10 Cont.

Page 15: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Timeline cont.(First Semester)

Oct 13 – Oct 17 Economic feasibility assessment of Costs and Benefits

Oct 20 – Oct 24 Cont.

Oct 27 – Oct 31 Rough Estimate and Budget

Nov 3 – Nov 7 Site Assessment and Selection

Nov 10 – Nov 14 Cont.

Nov 17 – Nov 21 Decide on Building Layout

Nov 24 – Nov 28 Building Codes

Dec 2 – Dec 5 Begin Final Drawings/ End of Classes

Page 16: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Timeline (Second Semester)

Jan 20 – Jan 23 Construction Documents: Floor plan/ Electrical/ Plumbing/ Elevations/ Overall site plans/

Jan 26 – Jan 30 Cont.

Feb 2 – Feb 6 Cont.

Feb 9 - Feb 13 Cont.

Feb 16 - Feb 20 Project Budget and Financing

Feb 23 - Feb 27 Cont.

Mar 2 – Mar 6 Building Specifications

Mar 9 – Mar 13 Cont.

Page 17: ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’

Timeline cont. (Second Semester)

Mar 16- Mar 20 Estimation of materials, costs, and labor

Mar 23 – Mar 27 Cont.

Mar 30 - Apr 3 Building Permits

Apr 6 – Apr 10 Planning and scheduling using Primavera

Apr 13 - Apr 17 Cont.

Apr 20 – Apr 24 Cont.

Apr 27- May 1 Prepare for final presentations

May 4 – May 8 Present Project