Total Area: 1242 sft
Item Quantity Unit
Bazri 27.324 CUM
Binding Wire 24.84 Kg
Bitumen 42.228 Kg
Brick Blast 11.178 CUM
Brick Tiles 4968 NOS
Bricks 24094.8 NOS
Cement 433.576 Bags
Cement for Base Coarse 21.114 Bags
Cement Paint 186.3 SqM
CI Pipe 18.63 Meter
Coarse Sand 14.904 CUM
Commercial Hardwood 558.9 RFT
Earth 11.178 CUM
Fine Sand 17.388 CUM
Glaze Tile 183.816 SqM
Hard Wood Shutter 18.63 NOS
Hardwood and Commercial Plyboard 4.968 NOS
Hardwood Window Shutter 37.26 NOS
Iron Grills 310.5 Kg
Labour for Brick Sup. Str
Labour for Brick Tiles
Labour for Brick Work Foundation
Labour for Ceiling Plaster
Labour for Cement Concrete
Labour for Ceramic Glaze Tile
Labour for DPC
A more accurate estimate can be prepared after reviewing the structural and elevation drawings of the building and by using the exact dimensions of each wall. This high level estimate is based on the square feet of constructed area and would help you in understanding breakup of
various cost involved in a construction project.
Bill of Quantity (This is an Estimate only. Exaxt quantity can be arrived after reviewing the plans. Write to [email protected])
Get prices from multiple vendors and put in this sheet. Compare the cost of your project. Note that actual quantity may vary depending upon the design.
Labour for Earth Excavation & Earth Filling
Labour for pipe including cost of Joints
Labour for Pointing
Labour for RCC
Labour for Steel RCC
Labour for Wall Plaster
MS Steel 2484 Kg
Oil Bound Distemper with Labour 521.64 SqM
Paint Work with Labour 248.4 SqM
Sand 38.502 CUM
Shuttering 1863 SFT
Stone Blast 24.84 CUM
White Cement 1.242 Bags
Item Quantity Unit
Cement 58.374 Bags
Stone Blast 24.84 CUM
Sand 12.42 CUM
Labour for Cement Concrete
Total for Cement Concrete 1:6:12
Labour for Brick Work Foundation
Sand 3.726 CUM
Cement 17.388 Bags
Bricks 6210 NOS
Total for Brick Work in Foundation with Cement Mortar 1:6
Labour for DPC
Bitumen 21.114 Kg
Cement 3.105 Bags
Coarse Sand 2.484 CUM
Bazri 4.968 CUM
Total for Horizontal DPC with Cement Concrete 1:2:4( 40MM)
Labour for Earth Excavation & Earth Filling
Brick Work in Foundation with Cement Mortar 1:6
Horizontal DPC with Cement Concrete 1:2:4( 40MM)
Earth Work in Excavation in Foundation and Filling under Floors
Foundation
Cement Concrete 1:6:12
Total for Earth Work in Excavation in Foundation and Filling
under Floors
Labour for RCC
Shuttering 1863 SFT
Bazri 22.356 CUM
Coarse Sand 11.178 CUM
Cement 199.962 Bags
Total for RCC without Steel Cement Concrete 1:1.5:3
Labour for Steel RCC
MS Steel 2484 Kg
Binding Wire 24.84 Kg
Total for MS Steel For RCC
Labour for Brick Sup. Str
Cement 44.712 Bags
Sand 9.936 CUM
Bricks 17884.8 NOS
Total for Brick Work in Super Structure Cement Mortar 1:6
Earth 11.178 CUM
Sand 1.242 CUM
Cement 11.178 Bags
Labour for Brick Tiles
Brick Tiles 4968 NOS
Bitumen 21.114 Kg
Total for Brick Tile Tracing on Roof
CI Pipe 18.63 Meter
Labour for pipe including cost of Joints
Total for Rain Water Pipe
Glaze Tile 121.716 SqM
Cement 23.095 Bags
White Cement 1.242 Bags
Cement for Base Coarse 21.114 Bags
Brick Work in Super Structure Cement Mortar 1:6
Brick Tile Tracing on Roof
Rain Water Pipe
Flooring
Ceramic Glaze Tiles Flooring 300X300 MM First Quality with course
Super Structure
RCC without Steel Cement Concrete 1:1.5:3
MS Steel For RCC
Fine Sand 17.388 CUM
Brick Blast 11.178 CUM
Coarse Sand 1.242 CUM
Labour for Ceramic Glaze Tile
Total for Ceramic Glaze Tiles Flooring 300X300 MM First Quality
with course
Sand 2.484 CUM
Cement 13.662 Bags
Labour for Ceiling Plaster
Total for Plaster on Ceiling (Roof) Cement Mortar 1:4
Labour for Wall Plaster
Cement 49.68 Bags
Sand 7.452 CUM
Total for Plaster on Walls Cement Mortar 1:4
Sand 1.242 CUM
Labour for Pointing
Cement 12.42 Bags
Total for Cement Pointing Cement Mortar 1:2
Glaze Tile 62.1 SqM
Total for Glazed Tiles in Dado or Skirting in Bathroom snd
Kitchen Walls
Hard Wood Shutter 18.63 NOS
Total for Hardwood Door
Commercial Hardwood 558.9 RFT
Total for Hardwood Frame Including Labour
Hardwood Window Shutter 37.26 NOS
Total for Hardwood Window
Hardwood Frame Including Labour
Hardwood Window
Hard Wood Frame and Commercial Plyboard Shutter
Plaster on Ceiling (Roof) Cement Mortar 1:4
Plaster on Walls Cement Mortar 1:4
Cement Pointing Cement Mortar 1:2
Glazed Tiles in Dado or Skirting in Bathroom snd Kitchen Walls
Door,Window,Cupboard shutter,Iron Grills
Hardwood Door
Plastering/Wall tiles
Hardwood and Commercial Plyboard 4.968 NOS
Total for Hard Wood Frame and Commercial Plyboard Shutter
Iron Grills 310.5 Kg
Total for Iron Grilling with Labour
Paint Work with Labour 248.4 SqM
Total for Paint on Wooden Doors and Windows
Oil Bound Distemper with Labour 521.64 SqM
Total for Oil Bound Distemper with Filling on Walls
Cement Paint 186.3 SqM
Total for Exterior Finish Cement Paint Snowcem
Oil Bound Distemper with Filling on Walls
Exterior Finish Cement Paint Snowcem
Add 10% for Electric fitting wiring & Labor:
Add 10% for Water Supply fitting & Sanitary:
Add 5% for Sewerage:
Grand Total:
Iron Grilling with Labour
Paint
Paint on Wooden Doors and Windows
Ask question from Experts See Elevation/Interior Designs
Project Cost in Rs.: 1598446.238 Project Labor Cost in Rs.: 190957.5
Project Cost Rs. Per SFT: 1287 Project Labor Rs. Cost Per SFT: 154
Rate Total Amount Knowledgebase Links Vendor 1
1400 38253.6 Guidelines for Bazri
70 1738.8 Guidelines for Binding Wire
60 2533.68 Guidelines for Bitumen
600 6706.8 Guidelines for Brick Blast
7 34776 Guidelines for Brick Tiles
6 144568.8 Guidelines for Bricks
320 138743.82 Guidelines for Cement
320 6756.48 Guidelines for Cement for Base Coarse
35 6520.5 Guidelines for Cement Paint
500 9315 Guidelines for CI Pipe
1300 19375.2 Guidelines for Coarse Sand
201 112338.9 Guidelines for Commercial Hardwood
220 2459.16 Guidelines for Earth
975 16953.3 Guidelines for Fine Sand
800 147052.8 Guidelines for Glaze Tile
4380 81599.4 Guidelines for Hard Wood Shutter
4590 22803.12
Guidelines for Hardwood and Commercial
Plyboard
1030 38377.8 Guidelines for Hardwood Window Shutter
70 21735 Guidelines for Iron Grills
18630 Guidelines for Labour for Brick Sup. Str
13662 Guidelines for Labour for Brick Tiles
6210
Guidelines for Labour for Brick Work
Foundation
4968 Guidelines for Labour for Ceiling Plaster
8694 Guidelines for Labour for Cement Concrete
16146 Guidelines for Labour for Ceramic Glaze Tile
621 Guidelines for Labour for DPC
Construction Cost Estimate. A high level rough estimate.
A more accurate estimate can be prepared after reviewing the structural and elevation drawings of the building and by using the exact dimensions of each wall. This high level estimate is based on the square feet of constructed area and would help you in understanding breakup of
Bill of Quantity (This is an Estimate only. Exaxt quantity can be arrived after reviewing the plans. Write to [email protected])
Get prices from multiple vendors and put in this sheet. Compare the cost of your project. Note that actual quantity may vary depending upon the design.
24840
Guidelines for Labour for Earth Excavation &
Earth Filling
3105
Guidelines for Labour for pipe including cost
of Joints
14904 Guidelines for Labour for Pointing
13662 Guidelines for Labour for RCC
7452 Guidelines for Labour for Steel RCC
19872 Guidelines for Labour for Wall Plaster
50 124200 Guidelines for MS Steel
62 32341.68
Guidelines for Oil Bound Distemper with
Labour
60 14904 Guidelines for Paint Work with Labour
975 37539.45 Guidelines for Sand
20 37260 Guidelines for Shuttering
1050 26082 Guidelines for Stone Blast
850 1055.7 Guidelines for White Cement
Sub Total: 1278756.99
Rate Total Amount
Guidelines for Foundation
Guidelines for Cement Concrete 1:6:12
320 18679.68
1050 26082
975 12109.5
8694
65565.18
Guidelines for Brick Work in Foundation with
Cement Mortar 1:6
6210
975 3632.85
320 5564.16
6 37260
52667.01
Guidelines for Horizontal DPC with Cement
Concrete 1:2:4( 40MM)
621
60 1266.84
320 993.6
1300 3229.2
1400 6955.2
13065.84
Guidelines for Earth Work in Excavation in
Foundation and Filling under Floors
24840
24840
Guidelines for Super Structure
Guidelines for RCC without Steel Cement
Concrete 1:1.5:3
13662
20 37260
1400 31298.4
1300 14531.4
320 63987.84
160739.64
Guidelines for MS Steel For RCC
7452
50 124200
70 1738.8
133390.8
Guidelines for Brick Work in Super Structure
Cement Mortar 1:6
18630
320 14307.84
975 9687.6
6 107308.8
149934.24
Guidelines for Brick Tile Tracing on Roof
220 2459.16
975 1210.95
320 3576.96
13662
7 34776
60 1266.84
56951.91
Guidelines for Rain Water Pipe
500 9315
3105
12420
Guidelines for Flooring
Guidelines for Ceramic Glaze Tiles Flooring
300X300 MM First Quality with course
800 97372.8
320 7389.9
850 1055.7
320 6756.48
975 16953.3
600 6706.8
1300 1614.6
16146
153995.58
Guidelines for Plastering/Wall tiles
Guidelines for Plaster on Ceiling (Roof)
Cement Mortar 1:4
975 2421.9
320 4371.84
4968
11761.74
Guidelines for Plaster on Walls Cement
Mortar 1:4
19872
320 15897.6
975 7265.7
43035.3
Guidelines for Cement Pointing Cement
Mortar 1:2
975 1210.95
14904
320 3974.4
20089.35
Guidelines for Glazed Tiles in Dado or
Skirting in Bathroom snd Kitchen Walls
800 49680
49680
Guidelines for Door,Window,Cupboard
shutter,Iron Grills
Guidelines for Hardwood Door
4380 81599.4
81599.4
Guidelines for Hardwood Frame Including
Labour
201 112338.9
112338.9
Guidelines for Hardwood Window
1030 38377.8
38377.8
Guidelines for Hard Wood Frame and
Commercial Plyboard Shutter
Door,Window,Cupboard shutter,Iron Grills
4590 22803.12
22803.12
Guidelines for Iron Grilling with Labour
70 21735
21735
Guidelines for Paint
Guidelines for Paint on Wooden Doors and
Windows
60 14904
14904
Guidelines for Oil Bound Distemper with
Filling on Walls
62 32341.68
32341.68
Guidelines for Exterior Finish Cement Paint
Snowcem
35 6520.5
6520.5
Sub Total: 1278756.99
127875.699
127875.699
63937.8495
1598446.238
Price Quoted by Vendor 1 Vendor 2 Price Quoted by Vendor 2
A more accurate estimate can be prepared after reviewing the structural and elevation drawings of the building and by using the exact dimensions of each wall. This high level estimate is based on the square feet of constructed area and would help you in understanding breakup of