Estimate Guidelines

48
COST ESTIMATE GUIDELINES AND REFERENCES How to Avoid Bidding Errors A. Read thoroughly plans, specifications, and general conditions of contract, addendums, and invitation to bid. Study carefully the following terms and conditions. 1. Bid bond – 5% to 10% Cash or manager’s check 2. Time of completion – number of working days or calendar days 3. Performance bond – all risk insurance 10% to 20% of contract. a. Work Guarantee Bond – 20% to 30% of contract 4. Construction Bond for Residential – Subdivision Requirements 5. City Tax or Contractor’s Tax 6. Contractor’s insurance – Verify approved insurance company 7. Liquidated damages for 1% of 10% of bid 8. Price Escalation/ Time Extension 9. Revisions, changes, extra works 10. Last minute addendums, bid bulletins, time and date of the bid submission 11. Owner-supplied materials 12. Terms of Payments – Check Dpayments 13. Permits Construction Permits (Architectural, Structural, Plumbing, Mechanical & Electrical Occupancy Permits Demolition & sidewalk Permits City tax new codes 14. Building Code Requirements/Boundaries 1

description

estimate

Transcript of Estimate Guidelines

Page 1: Estimate Guidelines

COST ESTIMATE GUIDELINES AND REFERENCES

How to Avoid Bidding Errors

A. Read thoroughly plans, specifications, and general conditions of

contract, addendums, and invitation to bid. Study carefully the following terms

and conditions.

1. Bid bond – 5% to 10% Cash or manager’s check

2. Time of completion – number of working days or calendar days

3. Performance bond – all risk insurance 10% to 20% of contract.

a. Work Guarantee Bond – 20% to 30% of contract

4. Construction Bond for Residential – Subdivision Requirements

5. City Tax or Contractor’s Tax

6. Contractor’s insurance – Verify approved insurance company

7. Liquidated damages for 1% of 10% of bid

8. Price Escalation/ Time Extension

9. Revisions, changes, extra works

10. Last minute addendums, bid bulletins, time and date of the bid

submission

11. Owner-supplied materials

12. Terms of Payments – Check Dpayments

13. Permits

Construction Permits (Architectural, Structural, Plumbing, Mechanical &

Electrical

Occupancy Permits

Demolition & sidewalk Permits

City tax new codes

14. Building Code Requirements/Boundaries

1

Page 2: Estimate Guidelines

B. Look for confusing requirements or any discrepancies in plans

and specifications. Refer to architect and owner in writing ( black & white)

C. Look for notations on plans – general scope of work, changes,

alterations, impossible requirements, Building code requirements

D. Evaluate & study carefully specifications

1. Make list of trades, brand, type that can fulfill the contract

2. Subdivide each trade list if needed

3. Ask quotations from subcontractors

4. Electrical, plumbing and mechanical if required.

Make sure you know the subcontractor suppose to quote on you. Set forms

to avoid gaps and mistakes

E. Set procedures for preparing bids

1. Plan the bid like a project with checklist, target date and project checklist

2. Check if bid required itemized cost breakdown/ unit cost of materials.

F. Check and double check take-off estimate. It might have been

overlooked. Spot check subcontractor proposals if complete. Take note of scope

of works. Verify items not included, unit cost of materials.

G. Site inspections – Verify thoroughly the following conditions.

1. Existing facilities to be demolished – wood, concrete steel.

2. Hauling In/ Out of matls– Disposal of debris. Location. Tools and

Equipment to be Used

3. Sources of Materials – Verify materials unit cost of nearby suppliers.

Major materials from existing supplier and minor materials from new supplier.

Verify terms of payment. Prepare materials checklist. Always check Current

Cost of materials, prepare checklist.

2

Page 3: Estimate Guidelines

4. Geographical conditions of site. Slopes, verify on plans, if backfilling is

required. Check if adobe, soil of backfill. Note depth of excavation requires.

Hauling in/out of backfilling, Dumping of debris from site.

5. Ideal location of bunkhouse, temporary warehouse or storage.

Temporary utilities. Dumping of materials to site must not have conflict with

the layout of proposed building.

6. Sources of manpower, technical expertise, tools and equipment

7. Temporary facilities- power, water, telephone

8. Future tapping of the following:

- Power

- Water

- Telephones

- Sewer and Drainage

Verify if in conformity with the plans. Check utility company

requirements. Project Study. Roads, sidewalks to be demolished.

Permits and payments.Deposits c/o Owner

H. Use the “RULE OF THUMB” method. Check the most contentious

items of bid. Recheck addition of subcontractors.

I. Analyze the bid even if it is not successful. Update cost of

materials. Check file records and other historical data. Get result of bidding and

prepare feedback for future references.

J. Major error in bid. Determine whether or not to continue work on the

project. Determine if you are willing to live with the error. Know the bid of other

contractor.

K. Take note of indirect cost, VAT and other government taxes and

requirements.

Subdivision requirements, construction bonds, insurance, city tax, performance bond.3

Page 4: Estimate Guidelines

L. You may wish to withdraw the bid.

Reminders before Estimating

A. Read first plans, specifications and general conditions of contract to familiarize

yourself with the general scope of works.

B. Spot check nebulous requirements if available in local market. Verify if imported,

suppliers, type of materials

C. Rough estimate to try. It must be 30-50% of what might be the ultimate cost.

D. Preliminary estimate. Unit cost obtained from past project. Recheck verify current

unit cost.

E. Always use the rule of thumb in the final estimate

F. RE-check your estimate. Let someone do it. Spot check multiplications and

additions of subtotal

G. Ask for quotations of suppliers or subcontractors of specialty works

H. Use different techniques in estimate

1. By volume method

2. BY area method – sq. m.

3. By direct count

Be systematic. Breakdown estimate or use the area method.

Schedule organized breakdown.

I. Begin estimate with fresh mind. Difficult items first, easy items like addition of total

cost can be done when you are tired

J. Always use your imagination, observation, take note of items lacking or errors in

plans and specifications. Do not leave items. Immediately look for unforeseen

requirements before continuing to other portion.

4

Page 5: Estimate Guidelines

Estimate Checklist

A. Site Development/General Requirements

1. Mobilization/Temporary facilities

a. Temporary Fence – Total linear meter

Sawali 4’ x 5’ or GI sheets

Coco lumber – 2x3/2x4

C.W. nails

Check if corr. GI sheet temp. fence

2. ID / Uniforms/ Biodatas

3. Workers Quarters – Verify number of workers

a. Temporary Field Office

Plywood

2 x 4 lumbers

Roofing G.I. sheets or Lona – 20’ x 40’

Emergency Kit

Drums

Tools and Equipment

b. Temporary Power, Water and Telephone – Cost of utilities

during construction. Contractor or Owner

B.1 Checklist Temporary Power (Residential Only)

Description Qty Unit Unit Cost

RSC pipe ½ x 10’ 1 PieceEntrance Cup ½ 1 PieceRSC Conduit NippleSafety Switch 60 A 2p 1dia 1 SetTHW wire # 12 (5.5 mm²) 1 RollElectric Tape (big) 1 RollOne way switch 2 PieceDuplex Convenience Outlet 2 Piece

5

Page 6: Estimate Guidelines

Fluorescent 40 w 2 PieceMeter base 1 Set4 X 4 X 8’ coco lumber or equal

1 Piece

B.2 Temporary Toilet/Waterlines/Sewer

Description Qty Unit Unit Cost

PVC pipe 3”ρ x 10’ 2 PiecesPVC wye 3 x 3 3 PiecesPVC bend 4 PiecesPVC bend 2 PiecesPVC Cement 100 cc 1 QrtG.I. pipe ½ x 20’ 2 PiecesG.I. tee ½ 4 PiecesG.I. Elbow ½ 4 PiecesTaplon Tape 3 RollsFlush Type Water Closet 1 SetDrums 3 SetWater Hose ¾” x 15 lm

B.3 Checklist of tools and equipment to be used

Concrete Mixer (1 bugger)

Bar Cutter/Circular Cutter or Hacksaw Blade

Shovel

Pick Mattock

Leveling Hose

Bareta/Pointed bar

Angle Grinder

Vibrator

Compactor

Plastic Container

B.4 Manpower Transportation/Cash Advance for Mobilization

B.5 Temporary Bunkhouse for Workers and Storage of Materials

B. Siteworks

1. Demolition of Existing Structure

2. Hauling out/in

6

Page 7: Estimate Guidelines

Verify the following:

a. Slab, beams, footing, etc.

b. Materials that can be utilized – wood/steel/doors/etc.

c. Hauling out of usable materials and debris (labor+delivery

charges) – location of disposal

d. Storage of usable materials

3. Clearing and Grubbing – 3.00 m around building

a. Uprooting of trees and shrubs

b. Soil stripping if required

4. Sheet Piling – Verify adjacent existing structures

a. Near creek, beside high-rise building, etc

b. Piles to be used – Concrete pre-cast, steel or apitong lumber – 2

x 10 x 12’ for property walls

5. Verification of monuments, lot boundaries, slopes and topographical

conditions. Prepare fixed reference above the street level, building

elevations.

- Check if soil test is required for 4 storey buildings up.

6. Excavation

a. Manually

b. By machine – Calculate number of hours required

Verify Soil Conditions

7.

Earthfill/Backfilling works

Description Qty Unit Unit Cost

Soil Cu.m. 150Adobe Cu.m. 200

7

Page 8: Estimate Guidelines

a. Backfill – Excavated portion of footing, wall footing

b. Earthfill

– Slope of existing lot

– Elevations of Proposed finished flooring from

street line or other reference point.

c. Type of filling materials

Dump truck Or Ten Wheeler Truck

d. Tamping by Manual or Machine

Formula: LOOSE VOLUME or VL =Length x Width x DepthCompact Volume in Place or VC = VL + 25%

Hauling In of Backfill Materials

*

Depending on the type of Backfill – escombro, soil, and lastillas?

8. Gravel Fill a. 0.05 m thickness below slab on fill and footingb. G.I. gravel or ¾” gravel

TOTAL AREA OF SLAB = Length x Width x .05 m = Total Volume of Gravel Fill

9. Soil Poisoning – For application before pouring of footing and slab

a. Type of Soil Poison – Lentrex/Chlordane or F3D14

Description Qty Unit Unit Cost

Escombro T/L*Banda’y Banda or Lastillas T/L*Garden Soil for landscape/ Ordinary soil

Description Capacity (soil)

Unit Unit Cost

6 wheeler truck 4-6 cu.m T/L10 wheeler or dump truck

12-16 cu.m T/L

Description Capacity (soil)

Unit Unit Cost

6 wheeler truck 4-6 cu.m Per cu.m.10 wheeler or dump

truck12-16 cu.m

8

Page 9: Estimate Guidelines

10. Polyethylene Sheet under slab on fill – for Ground floor S lab

0.006 Thickness Polyethylene sheet approximately 9 kgs/sq.m. Specially for

narra parquet and vinyl tile floor finish

Reference Checklist: Foundation

a. Soil Bearing Capacity

1,500 – 2,000 psf (pounds per sq. ft.) Most commonly used

assumptions at city engineer’s office

3,000 to 4,000 psf

- if adobe or hard soil depending on soil test done by

geotechnical Engineers

b. Soil Test – For high rise building (Boring Test)

Cost P15,000 – P20,000.00 per hole depending on the

requirement of structural engineer

c. Seismic Analysis if required

11. Other Outside Building Development Checklist

a. Fence – Verify height and total length

b. Special Fence for Slope Area – shear wall with perforated

pipes ( verify detail)

c. Concrete curb and gutter, roads, walk, sidewalk

d. Parking Area

e. Rip rapping if required

f. Water Tank/Genset Rooms/other base foundations

g. Landscaping

9

Page 10: Estimate Guidelines

Note: Provide during construction permanent benchmark for elevation references.

C. Concreting Works

Checklist – check strength required

2,500 psi slab on fill

3,500psi to 4000 psi for footing/ column/beam/slab/residential for high rise

building

1. Manual or concrete mixer – Actual Site conditions if 2 – storey

building

2. Ready Mixed Concrete – for high rise building

a. Interval of Delivery of Truck - 30 to 45 minutes

b. Capacity of One truck – 4 to 6 cu. mts.

c. Retarder or additives fast curing if required

d. Verification of scaffolding work before pouring-safety precautions

e. Dumping of excess cement if necessary

f. Emergency Scaffolding/tools and equipment

Checklist of Concrete Works for Estimate

a. Footing, wall footing, footing tie beam

b. Columns per floor schedule

c. Last Floor to roof or deck

d. Shear Walls

e. Concrete stairs

f. Floor Beams and Girder – per floor

g. Suspended slab

h. Parapet walls and canopy

i. Elevator shaft

j. Slab on fill (includes driveways and walks

k. Cistern Tank and Septic tank

10

Page 11: Estimate Guidelines

l. Kitchen and Lavatory counter

m. Lintel beam for doors and windows

n. Electrical and Plumbing lines embedded in concrete, pullboxes

and catch basins

o. Concrete Curb and gutter

p. Fence/electric post

q. Others as per plan

- Computations shall be scheduled systematically to

above items not included in the estimate. Itemized per

floor

-

Volume = Length x Width x Depth

Note : To include all portion below natural grade line (footing, column, walls, etc..

depth)

Estimate References for Concrete Works

Ratio : 1 part cement

2 part sand

3-part gravel

Compressive Strength of Concrete = Fc’ Psi- Pounds per square inch

Class Fc’@28 days Ratio Cement Sand GravelAAA 4000 psi (281 kgs/sq.cm) -

ready mixed concrete1:2:3 11 bags .40 m 3 .40 m 3

AA 3,500 psi (special) 1:2:4 ½ 10 bags .41 m 3 .82 m 3

A 3000 psi(regular –211 kgs/sq.cm.)

1:2:4 9 bags .42 m 3 .84 m 3

B 2,500 psi (176 kgs/sq.cm) 1:2 ½:5 8 bags .44 m 3 .87 m 3

11

Page 12: Estimate Guidelines

For estimate use .50 m 3 1.0 m 3

Example :

3,000 psi = Total Volume ( Concrete per computations) = 35 cu.mCement = 35.00 m3 x 9.0 m3 = 315 = 315 bags

Sand = 35.00 m3 x .42 m3 = 14.7 = 15 m3

Gravel = 35.00 m3 x .84 m3 = 29.40 = 29.40 m3

Note: Use only Local Brand Cement – Portland cement

Brand : Dragon, Northern Cement, and Island Cement

Get one (1) concrete sample for every 10.00 cu. mts. of concrete during

pouring of concrete on 12” concrete cylinder for testing of strength as required

for occupancy permit.

Capacity of Truck

1 bag of cement = 1 cubic foot

Note: pump cute interval of delivery of concrete every 30 min. capacity of truck 4 – 6.00m³

Cement

Gravel/ Sand

S-1 - for concreting worksWhite Sand - for plastering/topping

Concrete Mixed

Description Capacity (bags) Cost6 wheeler truck 100-200 bags10 wheeler or dump truck 500 bags

Description Capacity Unit Cost6 wheeler truck 2-4 m310 wheeler or dump truck 12-14 m3

12

Page 13: Estimate Guidelines

For one bag of Cement = 40 kgs (weight)

Gravel

G – 1 ¾ “ to 1 ½” gravel for foundations

Slab on fill

¾ gravel – 3/8 to 3/14” for all structural members

verify if crushed gravel or washed gravel

D. Formworks

1. Estimate form lumber using 2x3/2x4/2x6 coco lumber per total volume of

concrete to be used. Estimate first total concrete volume as per guidelines.

Coco lumber supplier – to order coconut bark, avoid lumber at center

2 x 3 / 2 x 4 - for vertical lateral ties and braces

2 x 6 - for beam support and footing

cost of coco lumber 12.5 to15.50 per bd. Ft.(jan ’06)

2. Normal coco lumber requirements

150 board feet per cubic meter of concrete

1 truckload of coco lumber – Elf, -1,800 to 2,500 bd. Ft.

Ten-wheeler -4,000 to 5,000 bd. Ft.

Cost of cocol umber 6.50 to 7.50 per board foot

3. Assorted C.W. Nails

C.W. nails 1 ½ “C.W. nails 2”C.W. nails 3”C.W. nails 4”

For scaffoldings

Commercial Sizes

1 box = 20-25 kgs (small)

1 box = 30-38 kgs ( large)

13

Page 14: Estimate Guidelines

Estimate Guide : 1 kilo per 50 board foot or lumber

QTY = Total board foot / 50 = N o s. of kilos / 25 = No. of

box

50 bd. Ft. 25 or 38 kgs/box

4. Concrete Nails – 3 “ & 4” for CHB filing guide, concrete walls ceiling joist

and cabinet frames. Quantity depends on the actual requirements

NAILS CHART

CW Nails Pieces per kilo Usage2D 1” 1,680 pcs Forms Plywood4D 1 ½” 705 pcs Forms plywood6D 2” 380 pcs T & G flooring8D 2 ½” 260 pcs Ceiling joist10 D 3” 120 pcs Trusses/Rafters20 D 4” 55 pcs Floor Joist

Finishing nailsSize Usage1” ceiling1 ½ “ T & G flooring2” Cabinet frames

5. PLYWOOD - Use 3/8” to ½” plywood. Normal market/commercialize of ¼ is too thin

Solve for Contact Surfaces. Columns/Beams/slabs as per plan. See checklist for concrete works.

Column Example: 4 sides or Perimeter(.20 + .20 + .40 + .40) x height = sq.m.

Beam Example 3 sides(.15 + .40 + .15) x height = sq.m.

Slab = Length x Width = Sq.m.

Summarize all required formworks

Total Contact Surface in Sq. Mts. = Nos. of Pieces

14

area required for formsa

area required for formsa

Page 15: Estimate Guidelines

2.88 or 1.20 x 2.42 Plywood Size of Plywood Required Note : Check if you can use it again if building is large. Small buildings assume as per estimate. Formoil – Normally to use USED oil – Quantity approximate; 1 ltr. per 15 sq. mts.

If steel scaffolding is to be used check rental per day of steel accessories. Verify to supplier.

Note : For residential, use good lumber for scaffolding, to be used later for rafters, purlins, ceiling joist, etc.

E. Steel Reinforcement/BarsSteel forms – rental per piece /day. As per plan

REBARS DESIGNATIONAmerican Society for

Testing Materials (ASTM)

Philippine Standard

Yield Point Strength

Tensile Strength

Usage

Kgs/ mm2

Psi Kgs/ mm2

Psi

Structural Grade

Grade 230

24.452 33,000 39.77 55,000 For residential only

Intermediate Grade (Grade 40)

Grade 275

28.042 40,000 48.95 70,000 Depend on structural design

Grade 60 Grade 410

41.80 60,000 63.22 90,000 For high-rise building

Standard Length of BarsFeet Meter Most commonly used available in hardware

6.00m20’ 6.00 m Special Length, per order to supplier26’ 7.50 m30’ 9.00 m35’ 10.50 m40’ 12.00 m

15

Page 16: Estimate Guidelines

20’ (6.00m) – 9mmd, 10mmd, 12mmd20’ and above – 16mmd, 20mmd, 25mmd

Commercial Sizes of Rebars

Nominal Diameters(metric)

Designation(English)

Unit weight per meter(Kilos per

meter)

Cross Sectional area

insq

Inch8 mm Substandard

Commercial Sizes9 mm (2.3 kgs)10 mm (standard) 3/8 # 3 0.616 0.1112 mm (standard) ½ # 4 0.888 0.1216 mm (standard) 5/8 # 5 1.579 0.3120 mm (standard) ¾ # 6 2.466 0.4425 mm (standard) 1” # 8 3.854 0.7928 mm (standard) 1 1/8 # 9 4.83332 mm (standard) 1 ¼ # 10 6.313

Example:

20 pcs – 16 mm dia. X 6.00 bars20 x 1.576 x 6.0 = 189.46 kgs.

To get quantity of G.I. wire # 16

a. G.I. wire # 16, through use of Concrete Volume

2 kilograms per cu. m. of concrete = NO. OF ROLLS25 – 30 kilos per roll (Check commercial weight to supplier)

b. Estimate thru Rebars

20 kilos of G.I. wire per metric tons1 metric ton = 10,000 kilos1 kilo of wire = + 53 linear meter1 roll = 35-40 kilograms

or current commercial kilos per roll = 38 kgs/roll

c. G.I. wires for CHB walls4” chb - 10” length of tie wires5” or 6 “chb - 12” length of tie wiresSpacing of rebars

16

Page 17: Estimate Guidelines

Vertical @ 0.60 m. o.c.Horizontal every third layer

GI wires Kilos per sq. mts – 0.04

Example : Total Area of CHB walls – 230 m2 x 0.04 = 9.2 kilos, or 10 kilos of G.I. wire # 16

d. Welding Rodse. Rust Proofingf. Post Tensioning – per plan special Construction, quotation per suppliers

Rebars substitution

Say 12-16 Ø To 20 mm Ø

Reinforcement/Rebars DataHow to Determine Bar Splicing LengthType Minimum Splice Length1. Tension Bars 25 x bar size +150 mm2. Compression Bars 20 x bar size + 150 mm

Example : Column 20 mm = 20 x 20 mm + 150 mm

Compression = 550 mm or .55 m

NO FOOTING SHALL REST ON FILLING MATERIALS“Y” – spacing of bars 1 @ 0.05 2 @ 0.10

3 @ 0.15 rest @ 0.20 m on center

F. Masonry Works

17

Page 18: Estimate Guidelines

Estimating CHB walls4” chb – interior chb partition6” chb – exterior chb partition for buildings5” chb – exterior chb partition for residential

Example :

A1 = L X H= SQ. M. GROSS AREA

A-1 LESS (A-2+ A-3)= SQ. M. NET AREA

A-1 = 3.0 X 4.0= 12.0 SQ.M

A-2 = 1.60 X 1.20 Take note of portion below grade line

= 1.68A-3 = 0.80 X 2.10 = 1.92

A-2 + A-3 = 3.60

A-1 LESS (A-2 + A-3) = 12.00- 3.60 = 8.40 SQ. M. = NET TOTAL AREA

FORMULAS1 cubic foot 0.0285 cu. mts1 cubic meters 35.28 cu. Feet1 bag of cement 1 cu. Foot

1. CHB FillerRatio 1: 3 or 1 part cement to 3 parts sand

Cement Sand4 “ chb 25 pcs. Per bag 0.0855 m3 per bag

cement6 ” chb 20 pieces per bag

Example:2,200 pcs. 4” chb = 88 bags cement-----------------------

25

88 bags x 0.0855 = 7.52: say 8.00 cu. mts. sand

2. CHB PlasteringRatio 1: 2 or 1 part cement to 2 part sand

Cement½ - ¾ “ thk plastering

0.50 bags per sq. m.

Sand 0.057 cu. mts per bag

Example:

18

Page 19: Estimate Guidelines

Say, 200 sq. m x 2: both face--------------------------------

0.50= 200 bags cement

200 x 0.057 = 11.4 says, 12 cu.m.

3. CHB Type/ Strength

NLB or non load bearing 400-500 psi Available in local market

LB or Load Bearing (Jackbuilt), etc. 700-1000 psi Locally available special

chb

Note : Verify delivery cost within Metro Manila or outside Metro Manila

4. Floor Topping

Mortar Per cu.m . Volume Sand UsageClass A 1:2* 16 bags/cu.m. 0.80 cu.m. For topping,

finishing works, tiles,

etc.Class B 1:3** 12 bags/ cu.m. 0.89 cu.m For topping

over slab to level flooring after pouring

*1:2 Ratio 1 part cement for every 2 part sand** 1:3 Ratio 1 part cement for every 3 part sand

5. Rebars for CHB

4” chb 10 mm diameter at every 3rd layer horizontal bars10 mm diameter at 0.80 m vertical bars

6” chb 12 mm diameter at every third layer horizontal bars12 mm diameter at 0.80 m. vertical bars

Assume : 4.25 LM per sq.m. of chbSay : 210 sq.m. x 4.25 lm

= 892.50 LM---------------------------

6.00 m: standard length of bars= 148.75 pieces,

19

Page 20: Estimate Guidelines

say 150 pieces – 10 mm dia.x 6.0 m def bars

6. G.I. wire Masonry works Ga # 16

Tie Wire 10” to 12“ length. Included in rebars wire computation (see checklist)

7. Firewalls/ Toilets. Floor Toppinga. Requirement for waterproofing

Sahara Compound – 1 pack per bag of cement for plastering of firewalls

b. Plaster Board –. Assume 5 sq. meters per gallons for floor topping

G. Steel Trusses. Verify details as per plan.1. Type of trusses

Steel trussesOpen Web Rigid Frame Built Up

2. Checklist for Estimate per Plan. Always verify if roof framing is correct/ economical. Angular Bars

Top and bottom chordsWeb MembersCross BracingTurnbucklesBaseplate (Thickness)Bolts and nutsSag rodHanger or support for ceiling with boltsWelding rodOxygen AcetyleneC Purlins 2 x 4/ 2 x 6 1.5 mm thicknessAngular bars for fascia board connection

* Preferable to get quotation from qualified subcontractor

Wooden Trusses. Checklist per plan

Top Chord/ Bottom Chord

Web Members/ Collar Plate/ Struts

Wood Plate

20

Page 21: Estimate Guidelines

Girters

Fascia Board – Tanguile KD S4S

Wood Braces

Purlins

Machine Bolts, nuts and washers

Eaves ventilation – wood slots with US Aluminum Screen

Tension Rod and Sag Rods

Special Trusses – Fabricated for Low Cost Gang nail/Others

To get board foot of lumber

Example:

1 pc 2 x 3 x 16 2 x 3 x 1612

1 pc 8 bf/pc8 bf

5 pcs 2 x 5 x 14 2 x 5 x 1412

11.66 bf x 6 pcs58.33 bf

6 pcs 1 ½ x 2 x 14 1.5 x 2 x 1412

3.50 bf / pc x 6 pcs21 bf

Conversion FactorsCu.ft x 0.02832 Cu. mts.Bf ft. x 0.0833 Cu. ft.Cu. mts x 35.314 Cu. ft.Cu. ft x 2.8317 x 10-2 Cu. mts.

H. Roofing Works

Ordinary Corrugated GI sheet Ga.# 16

Standard Market Sizes Width Standard Length

Corr. GI sheet Ga # 26 x 32” Standard 7 feet-do- 8 feet-do- 9 feet-do- 10 feet-do- 12 feet

0.30 meters – standard overlap

21

Page 22: Estimate Guidelines

1 1 . 5 0 0.70 side lapped 2 ½ “

or 2 corr.

= 16.42, say 17 pcs. X 2 side

= 34 pieces Ga# 26 x 32 x 10’ Corr GI sheet

5.40 m. = 18’ 2 pcs.- 10’ length

2. Plain GI sheet Ga. # 26 x 32” x 8’

standard. Solve for flashing and counter flashing for firewalls and parapet. Verify actual

plan.

3. G.I. gutter Ga. # 26 x 8’ -

Standard Gutter

- Special Gutter ( Spanish type)

4. Ridge Rolls x 8’

5. Valley gutter. Verify if outside gutter or

inside gutter

6. Others per plan. To include fascia board

for estimate.

7. Accessories

a. GI roof nails 3 ½ “ - kilos

b. Lead Washer - kilos

c. GI washer ( medium or thick)- kilo

d. GI rivets ¼ x 3/16

e. GI strap Ga # 26

f. Nicolite Bar

g. Muriatic Acid

22

Page 23: Estimate Guidelines

h. Roof Cement ( Vulcanized)

i. Red Oxide or red lead primer

j. Silicon Sealant

For Color roof – Verify type to be used. Ask for quotation of supplier. Standard Sizes Brochures

Type 1 – Rib type long span ; most common for residential

ChecklistGa. # 26 (Thickness)

Width Length

a. 0.40 mm X 1.040 m X ___ LM Rib Type roofb. 0.40 mm X 0.610 m X 2.44 S type gutterc. 0.40 mm X 0.610 m X 2.44 V type gutter – valleyd. 0.40 mm X 0.610 m X 2.44 Ridge rolle. 0.40 mm x 0.915 m x 2.44 Capping/Flashing

Accessories

a. Tek Screw (Metal Screw) 12 pcs per sq m

b. Blind Rivets

c. Silicon Sealant Per tube

d. Touch Up Paint

e. Vulcaseal – gallon

Take note of delivery charge – Around P 2,000.00 – 2,500 per trip, within Metro Manila or

outside Metro Manila

Order roofing one month in advance. Delivery is 2 – 3 weeks after order and payment.

Always estimate as per actual plan.

Formulas

A2 = c2 – b2

23

Page 24: Estimate Guidelines

B2 = c2 – a2

C2 = a2 + b2

Roofing by area methoda. Determine total flat area required

L x W + pitch factor solve for linear feet requiredRoof pitch Add to total flat area

(Height) meters (Percent)0.32 2%0.40 4%0.45 5%0.50 6%0.55 7%0.60 8%0.70 11%0.80 14%0.90 18%1.00 21%

b. Verify type of roofing as per plan

Tegula – 11.50/m²

Rib type

Banaue type

Others per brochures or specifications

I. Windows as per plan

1. Verify if the window jambs are required

2. Checklist on type of windows to be used

K. Jalousie windows 7/32” thk clear or smoked glass

- Verify if operator type

- Jalousies with steel grilles or aluminum

- Grilles with or without design normally grilles shall be

10mm square bar (3/8”) or 12 mm square bars (1/2”)

To compute: L x W= area in m² x 10.76

= area in ft²

24

Page 25: Estimate Guidelines

Jalousie Windows Specifications

Hoover alloy 6063-T-5 Anodized natural Anodized natural color lever

type operator with 7/32” clear glass 4” blade

StandardNo. of blades

Single controlStandard height

In meters

WidthMinimum of 0.80 m

4 0.3785 0.4666 0.5667 0.6448 0.7339 0.822

10 0.91011 1.0012 1.08013 1.17814 1.26615 1.35516 1.44417 1.53318 1.62219 1.71020 1.80021 1.88822 1.97823 1.060

Note: verify of aluminum screen for windows is included in contract

L. steel casement windows (casement or awning type)

1/8” x 7/8” or ¾” T & 2 mild steel section

1/8” thick clear or smoked glass

12mm square bar grilles with or with out design or as specified

aluminum screen if with u frame or detached

A= L x H= area in m² x 10.76= ft²

M. aluminum frame windows (sliding or fixed)

verify if anodized (white), analok (brown) or powder coated

25

Page 26: Estimate Guidelines

7/32” or ¼” thick glass bronze or clear glass green or blue

weather strip vinyl (mohair)

N. French type windows(wood or steel)

7/32”thick glass

hinges

special

locks and bolts

O. Window casing if required on plans(wood or concrete)

P. Other special type windows(local or imported)

I. Doors and Jambs

A

1. Door jambs –4” – 2” x 6” yakal or quijo

2. Door casings per plan/ mouldings 1x 5 / 1 x 6

3. Wood preservatives –solignum or black coal

4. Flush type doors 1.3/4” thick or height per plan

1. Hollow core ordinary both face

2. Hollow core 1 face marine

3. Hollow core both face narra

4. Hollow core with glass for kitchen

5. Narra panel floor solid core 1-3/4” thick per plan

1. Tang. KD panel door solid core 1-3/4 thick per plan

6. 1 ¼” louver door for toilets tang. Kd/aluminum, door.

7. metal louver door for pump room, electrical etc.

8. accordion door

1. metal with or with out plates GA # 14

2. wooden accordion

26

Page 27: Estimate Guidelines

9. aluminum doors

1. anodized – kawneer finish

2. analok finish

3. with or with out grilles

10. roll-up door

1. metal – manually operated/machine operated

11. sliding doors/windows per design

12. aluminum screen doors

13. metal clad doors

14. special doors for vaults

B. Accessories

1. 3 ½ x 3 ½” loose butt hinges us or local

2. 3” x 3” double action hinges

3. door track and hanger set

4. lockset per specification-local or imported

5. door closer

6. door bumper and stopper

7. master keys for buildings 2 sets

8. barrel bolts

9. foot bolts / head bolts

10. padlocks

11. peepholes

12. night-latch / privacy lock for toilets

J. Miscellaneous hardware

1. stair nosing- brass or non slip/ carborandum

2. Washington hinges or hettich hinges piano hinges

27

Page 28: Estimate Guidelines

3. closet/cabinets, handles and pulls roller catches an magnetic catches

4. finishing nails and concrete nails

5. railing for stairs

K. Thermal and moisture protection

1. vapor barrier – polyethylene sheet 4 width - > 7.8 m²/kgs. 107.8 kgs. Per roll

2. Sahara cement – 1 pack per bag of cement for firewall plastering

3. ceiling insulation (thickness to verify)1 roll = 5’ x 15mts

1. sisalation or aluminum foil

2. fiberglass

3. styropor boards

4. cauling and sealants

5. fireproofing materials

1. elastomeric

2. membrane

3. asphalt (hard) 30kgs. / bags

note : guarantee 5 to 10 yrs

preparation and cleaning of surface before application

L. Carpentry works

A. WALLS

a. Vertical & horizontal studs 2x3 / 2x4 S4S

b. Plywood panel - per plan ord. Or narra

c. Baseboards 1x6 with or without design

d. C.W, Nails 2" and finishing nails 1 "

e. Concrete nails 3"I rat proofing PLN GI SHT

1. Ordinary or narra or marine for ext.

2. Danarra 1 tempered lawanit

28

Page 29: Estimate Guidelines

3. 5-cut KD LBR

4. Wood lattice with design

2.Wooden Post 4"x4" per plan

Post strap - 3116 x 1 1/2x 24"

3. Special Walls - Corkboard

B. CEILING WORKS1. 2x2 Apitong RO or S4S @ 0140 x0.60 / 140 x 140

Ordinary or treated - Wolmanized tanalized

2. 2x3 / 2x4 Runner

3. Hanger 1/2 " PLN Round bar with thread and nuts

4. Concrete Nails

5. Exterior Ceiling

a. 1x1TANGKDWoodSlats

b. 1/4" x 4' Screen wire (welded)

c. 1x2 Frame

6. Ceiling niouldings size Per plan

¼ Ordinary - 1" to 1 112," to 3" special design

7. False beam per design

8. T and G or S-cut for ceiling

9. Cover lights ½ " - 1/4 “ plywood

Acrylic diffusers .30 x 1.20 / .60 x 1.20 per plan

10. Special ceiling design

a. Mirror

b. architectural Glass

c. Acoustic board - T runner

C. FLOORING 1. Wood girter and corbel plates

29

Page 30: Estimate Guidelines

2. Machine bolts with nuts and washer

3. Floor Joist Apitong Ro

4. T and G Flooring

a. Sanding of T & 0

b. Wood Filler and Paints

D. CLOSETS & HANGING CABINETS PER DESIGN

1. Plywood

2. Hardwares - drawer slides / handles / hinges

3. Weldwood glue

4. Hanger rod and bracket

5. Drawer locks / bolt

6. Secret drawer

E. HANGING CABINETS

1. Bar counter per design 2. Kitchen Hanging cabinet

F. WOODeN STAIRS

1. Handrails 3x8 narra or guijo S45 2. Riw

3. Threads

4. Balusters

5. Flat bars and screw

G. KITCHEN COUNTERS PER DESIGN

1. Wood / Concrete a. Frame 2x3

b. Plywood 3/4

c. Cabinet louver door

d. Formica top / Adhesives

f. Tiles inside counter white

30

Page 31: Estimate Guidelines

2. Marble/Granite tiles

a. Countertop 1 b. Splashboard 4" to 6"

A. Area method

1. board ft of studs / m² @ 0.60 m.o.c.b.w.

2. 2 x 3 – 5.38 bf/m²

3. 2 x 4 - 7.30 bf/m²

B. wooden partition

1. 2 x 3 – 9 bf/m²

2. 2 x 4 – 12bf/m²

C. ceiling plywood – joist

1. 2” x 2” @0.60m o.c b.w = 7bf/m²

2. 2” x 2” @ 0.40 m o.c. b.w.=9bf/m²

D. plywood ceiling by sheet method (bf/sheet)

@0.60 B.W. @0.60 & 0.40 @0.402”x2” 12bf/sheet 15bf/sheet 18 bf2”x3” 18bf/sheet 22bf/sheet 27bf2”x4” 24bf/sheet 30bf/sheet 36 bf

E. T & G flooring / V-cut

Nos. of T&G/meter run

Bf/m²

1 x 4 12.11 pcs. 13.851 x 6 7.70 pcs. 13.20

F.

G.

H. C. W. nails

Usage Unit Required kilos

Size Kind

Floor joist 1000 bf

10.354”

CWN

Flooring 1000 bf

14.342 ½

f

V/H studs 1000 10.43 2 ½ CWN

31

Page 32: Estimate Guidelines

bfRafters/Purlins 1000

bf18.38

4CWN

Trusses 1000 bf

7.934

CWN

Facia BD 1000 bf

9.572 ½

CWN

Ceiling joist 1000 bf

16.302 ½

CWN

1000 bf

12.934

f

Plywood ceiling

8 pcs. 1.001

f

Baseboard 1000 bf

6.081 ½

CWN

scaffolding 1000 bf

25.003

CWN

4 CWNI. Bolts

Wooden columns

bolt length L = w + 2(t) – 1”

Example: L = 4 + 2 (3 ) – 1”

= 4 + 5

= 9 bolts take note of commercial sizes of lumber

J. Trusses

L = thickness of lumber in layer + 1”

32

Page 33: Estimate Guidelines

FLOOR JOIST (WASTE FACTOR & BRIDGING CONSIDERED)

Per m² method

Spacing @ 0.30 O.C.2” x 6” 16.10bf/m²2” x 8” 21.33bf/m²

2” x 10” 26.73bf/m²Girter, corbel; plate by direct count

M. Specialty roofing Verify discount for Archt.

A. SHIN YEE METALGA # 0.40 /GA # 0.50mm

1. length maximum or 60 feet

2. width = 30” (760mm)

3. minimum roof 3%

B. accessories

1. gutter with design 0.50 x 0.914x_______

2. ridge roll 0.40mm x 0.577x________

3. ridge wall flushing – 0.40m x 0.577m x 3.30m

4. end flushing

5. End flushing wall

6. counter flushings

7. Counter nails

8. blinds rivets 1/8”

9. type 17 – self drilling screw no. 12x2” (50mm)

10. tek screw #10x1/8”

33

Page 34: Estimate Guidelines

11. wire basket strainer

12. silicon rubber sealant / acrylic paints

C. for walls – spandrel

1. Rib

2. Plain

3. V – spandrel

N. Downspouts, catch basins, manholes, septic tank and cistern tank

A. Downspouts

1. 3” or 4” per plan

2. 1/8” x _______PVC bend

3. ¼ x_______PVC bend

4. PVC coupling

5. epoxy and PVC cement

B. catch basins/ drainage per plan

1. .4” to 10” concrete pipe x1.00 non-reinforced or reinforced

2. perforated PVC pipe for basement walls

3. cement

4. sand

5. gravel

6. steel grating if required – angular bars

C. manholes for electrical or plumbing

*Concreting for embedded electrical and PCBG Lines

O. Finishes

A. Walls- exterior and interior

1. plain cement finish

2. tooled finish (plaster)

3. patch on joints

B. synthetic adobe / adobe rubble finish

34

Page 35: Estimate Guidelines

1. with or without shells

2. with or with out grooves

3. color scheme

C. pebble or boracay washout bohol or ordinary

1. white or ordinary cement

2. size #5, 10, 15

D. anay finish

1. with pebbles

2. fissured finish

E. bricks tiles finish / cal-tiles

F. mactan stone 2x8”

G. marble tiles 4”x8” / 6”x12” etc – Bulacan or Romblon

H. wall tiles 4x8

1. colored or white 4 ¼” x 4 ¼”

2. with or without design 6”x6” / 8” x 8”

3. white cement – 350 pcs/kilo

4. tile adhesive

I. marble ashlar finish 2”x8”

1. flooring per plan

a. plain cement finish or colored red green cement 1:2 5 m² / kilo

b. marble tiles

c. vinyl tiles 1.5mm thick x 1’x 1”

3.6mm thick x 1’x1”

Adhesive: gallons per m² x 0.042 = gallons

d. stone inlay finish 2” to 3”

e. wood parquet per design sanding

f. mosaic tile 1” x 1”

g. narra wood planks 1” x 6” to 8” nailers/insulation/c. winnails

35

Page 36: Estimate Guidelines

h. floor tiles 4” x 8” class a or class b

6” x 6” colored light or dark

i. terrazzo finish or marble chips washout

j. others per design

2. Ceiling Finishes

a. acoustic boards with or without design

aluminum T-runner/if plywood with adhesives

b. 1” x 4” t&g

c. S-cut or v-cut finish 1”x6”

d. Acrytex finish

e. Mirror

f. False beams

3. FLOOR FINISHES verify specs & Plan

4 ¼ tiles – 86 pcs. Per sq. m

white cement – 0.80 kilo/m² or 250 pcs. / kilo

cement – 0.076 bags /m²

cement tiles:

Tiles/m² Cement Bag/m²

SandM³/m²

¾ x 6’” x 6” 45 pcs, 0.3375 0.0191” x 8” x 8” 25 pcs. 0.3400 0.019

1” x 10” x 10” 16 pcs. 0.3400 0.019Vinyl adhesive x gals /m² x 0.042 =

Or 200 pcs. Per gallon =

P. Grille works

A. Fence grilles with or with out design

½” to ¾” square bars or 1 ½” x ¼” flat bars

B. gate with mailbox GA # 16 or per design

C. window grilles – ordinary or pregnant grilles

D. fire escape ladder

36

Page 37: Estimate Guidelines

E. air con frames / manhole cover

F. open court grilles – flat bars and angular bars

G. stair railings with design

H. cyclone or interlink wire

G.I pipes/ Welding rod

I. others per plan

brass nosing for stair / screws

Q. Electrical works

Note : if floor plan has no electrical layout

Assumption

Nos. of c.o Nos. of light outletResidential 0.38/m² 0.18/m²Commercial 0.42/m² 0.22/m²Industrial 0.60/m² 0.40/m²

1. Get total nos. of C.O. outlet x unit cost

2. Get total nos. of ceiling outlet x unit cost

R. Add 30% of 1 & 2 for load center and panel boards

1. Add 40% of 2 for lighting fixtures

2. Add 15% of 1 & 2 for wiring devices

3. add 12% of 1 & 2 for fire alarm

4. add 12% of 1 & 2 for telephone

5. add 10% of 1 & 2 for music and paging system

6. add 8% of 1 to 8 for miscellaneous and contingencies

note: verify MeRalCo / PLDT for tapping

1. Transformer

37

Page 38: Estimate Guidelines

2. Tel. House cable

3. Single phase or three phase

ELECTRICAL COMPUTATIONS:

SINGLE PHASE

Total load x 80% demand factor = LOAD

FOR 110 / 220V

C.O. x 0.75 A =__________total amps

Ground Wire – size =TOTAL LOAD WIRE 3

or 75% if lights & C.O.

ELECTRICAL LOAD COMPUTATION (STANDARD)

DESCRIPTION

# OF WATTS

PER UNIT

WIRE SIZEAMPERE

LOAD

English MetricConvenienceOutlets

180watts-200watts

TW # 12 3.5mm² 20A

Lights:Fluorescent Lights 20 watts

TW # 14 2.0mm² 15A

Halogen lights40 watts

TW # 14 2.0mm² 15A

Incandescent 100 watts

TW # 14 2.0mm² 15A

Track lights150 watts

TW # 14 2.0mm² 15A

Air con unit 1.0 HP

1,980 watts

TW # 10 5.50mm² 30A

1.5 HP2,200 watts

TW # 10 5.50mm² 30A

2.0 HP2,640 watts

TW # 10 5.50mm² 30A

Water heater SPO

1,000 watts

TW # 10 5.50mm² 30A

Range outlet8,000 watts

TW # 08 8.00mm²

40A / 50A

Water pump

½ HP880 watts

TW # 10 5.50mm² 30A

1HP1,780 watts

TW # 10 5.50mm² 30A

Electric stove2,000 watts

TW # 10 5.50mm² 30A

38

Page 39: Estimate Guidelines

Chandelier1,000 watts

Refrigerator 320 wattsFreezer 200 wattsWashing machine 585 watts

Dryer 3,000 watts

Jacuzzi 1 HPWater heater centralized

6,000 watts

Ampacity Of Conductorssolid stranded

AWG mm² TW THW IN. Conduit mm²

16 For stereo

wire

14 2.0 15 15 ½ 1512 3.5 20 20 ½ 2010 5.5 30 30 ¾ 208 8.0 40 45 ¾ 206 14.0 55 65 1’ 254 22 70 85 1 ½ 322 30 90 110 1 ¾ 321 38 100 125 1 ½ 400 50 120 145 2” 50

00 60 135 160 2” 503 / 0 80 160 195 2” 504 / 0 100 185 200 2 ½ 65250 125 210 255 2 ½ 65300 150 240 280 2 ½ 65400 200 280 330 3” 80500 250 315 375 3 ½ 90650 325 370 435 3 ½ 90750 400 405 485 4” 1001000 500 445 540 4” 100

ELECTRICAL LOAD COMPUTATIONS (RESIDENTIAL)

CKTNOS.

LIGHTS SWOTHERLOAD

VOLTS WATTS AMPS

1 10 11 220 1,000 4.542 9 9 220 900 4.09

39

Page 40: Estimate Guidelines

3 6 6 220 600 2.724 5 220 1,000 4.545 11 220 2,200 10.006 2 220 400 1.81

7 1-SPOStove 3

KW220 3,000 13.63

8 1-SPOBell or buzzer

220 50 0.22

Total 41.55 A

Computations:

TOTAL FLOOR AREA = 135m²

135m² @ 24 W / SW 3,240 W

Small Appliance load 3,000 W

6,240 W

First 3,000 W @ 100% DF 3,000 W

Renaming 3,240 W @ 35% DF 1,134 W 4,134 W

4,134 = 18.79 A220 V

1 Electric stove 3W 13.631 Buzzer 0.22 A

IT = 32.64 A

Use 2 # 14.0 mm² THW wire in 25 mmd RSC 4.55 A / 65 A

Watts = Volts x Ampere W=EI

Ampere = watts I= W Volts V

1 horsepower = 746 watts

volts = voltampere

CARRIER AIR CONDITION

MODEL NOS BTV/HR HORSE POWER Suggested room space

WC 90 RCY 9,000 1 hp Up to 18 m²

40

Page 41: Estimate Guidelines

WC 120 RCY 12,000 1 ½ hp 18 to 24 m²WC 120 RCY 12,000 1 ½ hp 18 to 24 m²WC 150 RCY 15,000 1 ½ hp 24 to 30 m²WC 180 RCY 18,000 2 hp 30 to 36 m²

Cabinet Dimension H (40mm) x (w) 658 mm

Split type air con /package = 20m² / tons

B. Rough- in

1. PVC pipes

a. ½” to 3” SCH. 40 Neltex, Atlanta, super

b. PVC cement

c. PVC coupling ½” to 3”

d. PVC Elbow ½” to 3”

2. RSC pipe and fitting per plan/brand –Maru– ichi ,setsuyo

a. 3/4” to 3” – entrance / up to panel verify

b. RSC elbow

c. RSC coupling

d. LB /LR

e. Entrance cup

f. Locknuts and bushing

3. secondary rack – power and telephone

4. Solderless connector

Angle connector

Straight connector

5. RSC conduit clamp

6. metal moulding

7. circular loam ¼” to ¾”

8. THW, THHN, TW wires solid or stranded 150 LM/roll

9. G.I. k#16 – guide wires

41

Page 42: Estimate Guidelines

10. P.D. jacketed telephone wires #22/3 flat cord

11. BX wire #12/2 / #123/2 / #8/2’

12. Intercom wires

13. telephone steel cabinets GA # 16 or GA #18

telephone cable wires for 3 storey building

14. pull box (steel ) per plan

15. wire gutter per plan (distribution panel)

16. utility box local or imprinted, plastic or metal GA #16 -#18

17. junction box 4” x 4”

18. 4 11/6 x 4 11/16 square box with ½” and ¼” K.O.

19. PVC Tape or rubber tapes

20. Wiring devices

a. Switches – National , Veto or Mikosha

Flush mounted

a. One gang switch with cover complete

b. Two gang switch with cover complete

c. Three gang switch with cover complete

d. Three way switch

e. Dimmer switch

b. Convenience outlets – ordinary duplex

a. Weather proof outlet

b. Water heater

c. Floor c. outlet

d. Range outlet

e. Air con outlet

f. Microwave oven outlet

c. Door bell and buzzer /chime

d. Telephone outlet cover

42

Page 43: Estimate Guidelines

e. Blank cover

f. Fire alarm bell and station

g. Intercom set band- air phone

h. Smoke detectors

i. Camera monitor

j. CATV antenna – “Winegard” w/ splitter, booster an accessories

k. Lighting panel – “Flush-type or flush mounted enclosure” circuit

breaker plug in or bolt-on

l. Safety switch

m. Double throw switch – emergency generator

n. AVR – automatic voltage regulator

o. Emergency lights.

p. Lighting fixtures

Note: most often owner supplied materials installation done

by contractor

q. Lighting arrester Verify Brand

S. Plumbing works

A. Cold water consumption

Type of building gallons/person/day

Residence – average 50Residence – average 100Apartment – low rent 75Apartment – high rent 100Hotels 100Office buidings 25

MWSS WATER METER TAPPING

43

Page 44: Estimate Guidelines

Size of Nos. of units per connection¾” ½” ¾”1” 1-2

1 ¼” 3-5 1-21 6-9 3-4 1-2 1-2½” 10-15 5-6 3 3 1-2

2 16-32 7-11 4 4 3 2 1

B. Rough –in

1. PVC pipes and fittings S-40

2. Cast iron pipes and fittings

C. Checklist PVC PIPES OR OTHER TYPES

1. Pipes x 10’ length

2. Cast iron x 5’ (length)

3. WYE

4. TEE

5. Double TEE

6. ¼ bend

7. 1/8 bend

8. P-trap with or without clean out hole

9. coupling

10. Double WYE

11. Tap Tee

12. PVC cement

13. Lead sheet

14. Epoxy A and B set

15. PLBG. Oakum

D. Waterlines: Check hot or cold lines

1. GI pipe and fittings local or japan

1. ½ - 12mm

44

Page 45: Estimate Guidelines

2. ¾ - 15mm

3. 1” – 25mm

4. 1 ¼” – 32mm

2. Fittings

1. GI elbow

2. St. Elbow

3. TEE

4. Union Patente

5. TEE – reducer

6. GI bushing

7. GI nipple

3. Water tank fittings per plan

4. septic tank and cistern tank

V= L x W x H x 264 gals.= Cu. Meter

Septic tank – design standard (minimum)

National Plumbing Code

Nos. of persons Inside depth of chamberServed Depth Width Length

10+5 1.20 1.10 1.8020 1.20 1.25 2.5025 1.20 1.40 2.8030 1.30 1.50 3.0035 1.30 1.60 3.2040 1.40 1.65 3.3045 1.40 1.75 3.5050 1.50 1.80 3.6060 1.50 1.95 3.8070 1.50 2.00 4.0080 1.60 2.20 4.4090 1.80 2.30 4.60

100 1.80 2.50 5.00Note: leaching well is aproximately ½ of volume of digestion chamber

Capacity of cylindrical tanks

Diameter 2 x 0.7854 x length = volume

If cubic feet x 7.4805 = nos. of gallons

45

Page 46: Estimate Guidelines

1. Cement

2. Sand

3. Gravel

4. Forms

5. 4 ¼” tiles (white)

5. Water heater

6. Shower values and heads

1. Single shower valve

2. Three valve diverter

7. Lavatory centerset faucet

8. Kitchen sink faucet

9. hosebibb – faucet with or without HB

10. Gate valves ½” ¾”

11. Angle valves / check velves

12. Siamese twin (fire hydrant) 3”x2 ½ x2 ½

2 ½ x 2 ½ x 2 ½

13. Fire hose cabinet with F. extinguisher

14. Water meters – main, branches

Note verify MWSS tapping of waterline to building

15. Accessories

1. floor drain/ strainer

2. roof drain

3. grease traps

4. drinking fountain and other per plan

5. special equipment

16. PLUMBING FIXTURES Verify Specs

1. waterclosets

46

Page 47: Estimate Guidelines

2. lavatories

3. bidet

4. urinals

5. kitchen sink

6. bathtub

7. soap holder

8. paperholder

9. toilet

10. dispenser

11. shampoo & tooth brush holder

12. towel bar

13. mirror

14. medicine cbinet

15. curtain rods

T. Painting works

A. Painting works

47

Page 48: Estimate Guidelines

1. Masonry Surfaces – latex

2. finishes washout and others – repellent

3. wood surfaces – cabinets/ closets/ceiling/walls

4. wood preserver

5. steel windows/ grilles – qde

6. varnish

7. automotive lacquer finish

8. natural oil finish

9. special finishes

1. acre – cast

2. spraytex

3. Alladin finish

10. roofing – Portland cement paintor Acrylic Paint

B. Overhead/ Contingencies

- note: contractor’s tax

- insurance

- permits – locational clearances

- power and water for construction

- barangay clearance

Updated Jan 12, 2006 FOR RESEARCH & IMPROVEMENTS

48