Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19...

21
Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 1

Transcript of Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19...

Page 1: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Essential Elements of the Complaint

Request for Review of Public Procurement Procedure

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 1

Page 2: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Contents

•EU Directives•Austrian Implementation•Practical Necessities

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 2

Page 3: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Relevant Directives

•Remedies Directive (Dir 89/665/EEC; since 21/12/1991)

•Utilities Remedies Directive (Dir 92/13/EEC;since 01/01/1993)

•Amendment Remedies Directives (Dir 2007/66/EC; since 20/12/2009)

•Art 55 – 64 Directive Defence and Security Procurement (Dir 2009/81/EC; since 21/08/2011)

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 3

Page 4: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Purpose of EU Directives

•enforcement of individual rights•of economic operators

•derived from public procurement directives

•no ex offo control of public procurement procedures

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 4

Page 5: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Contents of EU Directives

• minimum requirements for•review authorities•review procedures

• no details of review procedure•review authorities to be implemented by member states•contracting authority•administrative body•court

•review procedures to be implemented by member states: depending on review authority•integration into legal system of member states

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 5

Page 6: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Approach EU Directives I

• who?•interest in concluding the contract•damagecomplaint: proof interest and damage

• for which purposes?•interim measures; complaint: damage threatening•set aside decision; complaint: illegality of decision•award damages; complaint: illegality of procurement

procedure, damage•ineffectiveness of a contract; complaint: illegality of

conclusion of contract

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 6

Page 7: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Approach EU Directives II

• in which cases?•before the award of the contract•avoid damage until decision of review authority

•set aside decision

•after the award of the contract•award damages

•declare contract ineffective

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 7

Page 8: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Austrian System

•Bundesvergabegesetz 2006•detailed provisions for applications for•interim measure

•set aside a decision

•ascertainment

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 8

Page 9: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Aim of Interim Measures

•prevent damages until decision of review•prevent contracting authorities from creating

unchangeable facts•ensure effectiveness of review procedure

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 9

Page 10: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Application for Interim Measures• exact designation of•procurement procedure•separately voidable decision•contracting authority•applicant•including fax or electronic address

• relevant facts including the prerequisites for application for setting aside a decision

• illegality• damage threatening• interim measure• information on timeliness

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 10

Page 11: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Application to Set Aside a Decision I

•exact designation of •procurement procedure•separately voidable decision

•exact designation of contracting authority including electronic address or fax

• facts including interest in entering into the contract; in case of contesting the award decision nomination of economic operator proposed for the award of the contract

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 11

Page 12: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Application to Set Aside a Decision II

•damage•offended right•reasons for infringement•application for nullification• information about timeliness

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 12

Page 13: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Inadmissibility

•not against a separately voidable decision•not within the given time limits• fees not paid

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 13

Page 14: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Application for Ascertainment I

•exact designation of procurement procedure and of decision

•exact designation of contracting authority including electronic address or fax

• if possible nomination of economic operator awarded with the contract

• facts including interest in entering into the contract

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 14

Page 15: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Application for Ascertainment II

•damages

•offended right

•reasons for infringement

•certain demand

• information about timeliness

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 15

Page 16: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Inadmissibility

•not within the given time limits• infringement could have been claimed in

nullification proceeding• fees not paid

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 16

Page 17: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Practical Necessities

•which information does the review authority need?

•which parts of the application can be amended?•does the review authority have to help the

applicant – manuduction?

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 17

Page 18: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Necessary Information

•contracting authority + address•procurement procedure• facts• interest in entering into the contract•damage threatening• infringement•timeliness•demandKiev, 19 April 2012 Essential Elements of the Complaint

Hubert Reisner 18

Page 19: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Possible Amendments

•contracting authority + address?•procurement procedure?• facts?• interest in entering into the contract?•damage threatening?• infringement?•timeliness?•demand?Kiev, 19 April 2012 Essential Elements of the Complaint

Hubert Reisner 19

Page 20: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Manuduction

•applicant not represented by an attorney?•applicant represented by an attorney?

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 20

Page 21: Essential Elements of the Complaint Request for Review of Public Procurement Procedure Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner.

Thank you for your attention.

Mag. Hubert ReisnerFederal Public Procurement Office

Praterstraße 31, A-1020 WienTel +43 (1) 213 77 – 224

e-mail [email protected]

Kiev, 19 April 2012 Essential Elements of the Complaint Hubert Reisner 21