ESPLOST Update
-
Upload
colleen-beach -
Category
Documents
-
view
15 -
download
0
description
Transcript of ESPLOST Update
ESPLOST Update
Savannah-Chatham County Public SchoolsAugust 1, 2007
ESPLOST
Fourth payment received $5,292,731.43 (May Collections) Total of $24,107,940.79 G.O. Bond Debt Payment of
approximately $12 Million due August 1, 2007
ESPLOST
Project Management URS in association with Pat Mathis was
selected on July 11. Contract Review URS has prepared draft schedule of
construction Goal to open at least 3 schools in Fall
2009
ESPLOST
ESPLOST Project Updates Woodville-Tompkins
Phase I on schedule W/T Phase II
Architect Selection – August 1 Safety Fencing
Extending Bid Timeline due to low response on initial bid
Godley Station Land Study Site Selection Criteria for DOE
ESPLOST
ESPLOST Financial Reporting Updated Monthly Synchronization with Program
Management Data
ESPLOST Update
Board Discussion / Questions