ESPLOST Update

6
ESPLOST Update Savannah-Chatham County Public Schools August 1, 2007

description

ESPLOST Update. Savannah-Chatham County Public Schools August 1, 2007. ESPLOST. Fourth payment received $5,292,731.43 (May Collections) Total of $24,107,940.79 G.O. Bond Debt Payment of approximately $12 Million due August 1, 2007. ESPLOST. Project Management - PowerPoint PPT Presentation

Transcript of ESPLOST Update

Page 1: ESPLOST Update

ESPLOST Update

Savannah-Chatham County Public SchoolsAugust 1, 2007

Page 2: ESPLOST Update

ESPLOST

Fourth payment received $5,292,731.43 (May Collections) Total of $24,107,940.79 G.O. Bond Debt Payment of

approximately $12 Million due August 1, 2007

Page 3: ESPLOST Update

ESPLOST

Project Management URS in association with Pat Mathis was

selected on July 11. Contract Review URS has prepared draft schedule of

construction Goal to open at least 3 schools in Fall

2009

Page 4: ESPLOST Update

ESPLOST

ESPLOST Project Updates Woodville-Tompkins

Phase I on schedule W/T Phase II

Architect Selection – August 1 Safety Fencing

Extending Bid Timeline due to low response on initial bid

Godley Station Land Study Site Selection Criteria for DOE

Page 5: ESPLOST Update

ESPLOST

ESPLOST Financial Reporting Updated Monthly Synchronization with Program

Management Data

Page 6: ESPLOST Update

ESPLOST Update

Board Discussion / Questions