Eskom's State of the System
-
Upload
matthewlecordeur -
Category
Documents
-
view
18 -
download
0
description
Transcript of Eskom's State of the System
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 1/26
Quarterly System Status Briefing
Winter Status
Brian Molefe
Acting Chief Executive
17 June 2015
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 2/26
Content
2
Introduction
Half-year performance
Winter Outlook
Build Programme
Conclusion
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 3/26
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 4/26
Overview
4
• Eskom has continued to supply up to an average of 96% of electricity in the
country during the first half of 2015 and will continue to do so in Winter
• We endeavour to do maintenance with no or minimal load shedding this winter
• Notwithstanding, we have an aging and volatile plant :
- the cold weather increases demand, which pushes our plant to run at
100% capacity for extended periods, further exacerbating unplanned
outages- maintenance will put an already strained system under further pressure
• Up to 5 500 MW of planned maintenance will be performed, three times more than
previous winters
• Every effort is being made to reduce plant breakdowns (unplanned maintenance)to allow for planned maintenance
• Medupi unit 6 is on track towards commercialisation and supplies up to 800 MW to
the grid, while still in test (synchronisation) mode
• There is no prospect of a blackout in South Africa
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 5/26
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 6/26
Eskom is committed to supplying the country andminimising the risk of load shedding
6
• During the first-half of the year, an average of 96% of electricity was suppliedin the country when load shedding in Stage 2, despite a higher demand during this
period, compared to last year
• Generating performance was slightly better than expected
• Open cycle gas turbines were used extensively, with the highest usage in May
• Independent Power Producers continue to play an important role, contributing
about 1 827MW to the grid at a time when the power system is constrained
• Renewable energy contributed about 1 300 MW during the day, of which 800 MW
was from solar and 500 MW from wind.
• Benefits from the Build Programme contribute to the grid: 100 MW from Sere, and
up to 800 MW from Medupi during peak periods
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 7/26
Despite load shedding on average in Stage 2, Eskomsupplied 96% of electricity during the first half
electricity supplied
electricity demand
• In the recent
months, Eskom
had to implement
regular loadshedding due to
the unavailability
of some of the
generation units
• Eskom supplied
on average 96%of the demand
during the period
Key insights
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
A p r - 1 4
M a
y - 1 4
J u
n - 1 4
J
u l - 1 4
A u
g - 1 4
S e
p - 1 4
O
c t - 1 4
N o
v - 1 4
D e
c - 1 4
J a
n - 1 5
F e
b - 1 5
M a r - 1 5
A p r - 1 5
D e m a n d
NotSupplied
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 8/26
We had forecast a high probability of load sheddingon most days
8
Adequate generation capacity available to meet
demand and reserves
Jan-15
Sun Mon Tue Wed Thu Fri Sat
1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 * 26 * 27 28 29 30 31
Feb-15
Sun Mon Tue Wed Thu Fri Sat
* 5 6 7
8 9 10 * 11 12 13 14
* 15 16 17 18 19 20 21
22 23 24 25 26 27 28
1 2 3 * 4
Mar-15
Sun Mon Tue Wed Thu Fri Sat
5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
1 2 3 4
29 30 31
Apr-15
Sun Mon Tue Wed Thu Fri Sat2 3 4
5 6 7 8 9 10 11
12 13 * 14 * 15 * 16 17 18
19 20 21 22 * 23 24 25
26 27 28 29 30
1
May-15
Sun Mon Tue Wed Thu Fri Sat1 2
3 4 5 * 6 * 7 8 * 9
10 * 11 12 13 * 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
Constrained generation capacity with sufficient
supply to meet demand and reserves. Medium
probability of load shedding
Insufficient generation capacity unable to meet
demand and reserves. High probability of loadshedding
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 9/26
Actual system status: We performed better thanexpected for January - April 2015
9
No load shedding Stage 1 Stage 2 Stage 3 * stage change
Jan-15
Sun Mon Tue Wed Thu Fri Sat
1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 * 26 * 27 28 29 30 31
Feb-15
Sun Mon Tue Wed Thu Fri Sat
* 5 6 7
8 9 10 * 11 12 13 14
* 15 16 17 18 19 20 21
22 23 24 25 26 27 28
1 2 3 * 4
Mar-15
Sun Mon Tue Wed Thu Fri Sat
5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
1 2 3 4
29 30 31
Apr-15
Sun Mon Tue Wed Thu Fri Sat2 3 4
5 6 7 8 9 10 11
12 13 * 14 * 15 * 16 17 18
19 20 21 22 * 23 24 25
26 27 28 29 30
1
May-15
Sun Mon Tue Wed Thu Fri Sat1 2
3 4 5 * 6 * 7 8 * 9
10 * 11 12 13 * 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
• With the exception of May, the lights were
kept on, most days
• Even during load shedding, 96% of the
country had electricity
• During the month of May, on average, load
shedding was implemented for only 6 hoursin a 24-hour day
Key insights
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 10/26
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
Wi t tl k
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 11/26
Winter outlook:While the system will be tight, Eskom will onlyimplement load shedding as a last resort
• Winter 2015 is likely to be colder than last year, with a higher expecteddemand in electricity during the peak periods.
• We anticipate to supply 100% of electricity most days and 96% during peakperiods from 6am to 10am and 5pm to 10pm.
• Even during the cold front that hit from Wednesday, 3 June, Eskomimplemented only 5 hours of load shedding on Sunday, 7 June. This after 10consecutive days of no load shedding.
• The recent load shedding from Monday, 8 June 2015 to Friday, 12 June 2015was the result of an increase in demand and an increase in unplanned
breakdowns
• Localised power outages in urban areas and illegal connections generallyincrease during winter due to increased levels of customer demand and hencecause greater stress on the system.
11
Wi t tl k ti d
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 12/26
Winter outlook: continuedWhile the system will be tight, Eskom will onlyimplement load shedding as a last resort
• We will continue with maintenance during winter, three times more than
previous winters.
• We will continue to use all available resources: Independent Power Producers
(including renewable energy), Open Cycle Gas Turbines and Demand Market
Participation.
• To date wind energy contributes between 300 MW to 500 MW during the dayand solar energy about 800 MW.
• Industrial customers continue to contribute an average of 10% savings
• Coal stock levels are healthy at all but three stations. The average stock level
days as at 8 June is 50.4 days against an average target of 51.2 days
12
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 13/26
Summer and winter load profiles
In Winter, more electricity is used during the morningand evening peak periods
13
Insights• In Winter, the demand/load
profile increases and peaks
during the morning and
evening, as more electricity is
used during these periods
• In Summer, the risk of load
shedding is longer and for
most of the day
• In Winter, the risk of load
shedding is for shorter
periods and only during the
peaks
• The generating plant
generally performs better in
winter, as the cooler
temperatures have less
impact on the equipment
• As the greatest demand is
during the peak, 4% of South
Africans could be impacted
by load shedding from 06:00-
10:00 & 17:00-22:00 (as per
load shedding schedules)
Increase in
demand
from 5pm to 10 pm
Increase in
demandfrom 6am to 10am
H d d i t ith t l d
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 14/26
14
How do we do maintenance without loadshedding? Eskom intends to do maintenance withlimited load shedding
43.5
32.5GW
35GW
0
5
10
15
20
25
30
35
40
45
50
Capacity Summer Demand Winter Demand
G w
GW installed (includes Cahora Bassa and excludes Medupi)
+ 1 500 MW
operating
reserves
M a x i m u m d e m a n d
3 6 G W i n s t a n t a n e o u s
M a x i m u m d e m a n d
3 3 G W i n s t a n t a n e o u s
7 GW maintenance window that must
include planned, unplanned & load losses
2014 peak demand
was 35 677 MW
36.5 GW
34 GW
Capacity from independent power producers, including renewables, reflect as a reduction indemand when the capacity is available
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 15/26
Eskom’s maintenance philosophy consists ofplanned and unplanned maintenance
Maintenance
Plannedmaintenance
Unplannedmaintenance
• Philosophy maintenance
• Safety maintenance
• Statutory maintenance
• Risk maintenance
• Breakdowns (Total andpartial load losses)
Maintenance = Philosophy + safety + statutory + risk + breakdowns
In the short term, Eskom will prioritise RISK MAINTENANCE in order to reduce
the amount of unplanned maintenance• 15 of a total of 18 maintenance outages (83%) are on power plants that are classified
as Risk 1/Risk 2/Risk 3
• 13 of a total of 18 maintenance outages (80%) is also philosophy maintenance
11
On average Eskom has a maintenance budget of 7 000 MW in winter,
which is dependent on demand requirements
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 16/26
Progress at Majuba Power Station, as all sixunits can operate at full load
• An immediate and gap solution is in place, enabling the station to run all six units(3 843 MW) at full load.
- This provides coal supplies to all six units via mobile equipment and temporary coalstock piles.
• A contract was awarded on 2 March 2015 for the interim solution which replaces
the mobile equipment with conveyor belts running from the permanent stockpiles to
ensure greater efficiency in the coal handling process.
• Construction is in progress and will be completed by end September 2015.
• A new permanent coal handling plant is expected to be in place at the end of 2016.- Design consultants have been appointed and construction is expected to begin early
January 2016, once a construction contractor has been appointed.
• The investigation has been concluded and will be presented
to the Board and Shareholder
16
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 17/26
Duvha unit 3 boiler contract soon to be inplace
• The over-pressurisation incident at Unit 3 of Duvha power station in
March 2014 took 575MW unit out of service for repair.
• The incident investigation has been completed and the primary causewas noted as a build-up of unburnt fuel within the boiler, which ignitedin an uncontrolled manner
• A process is under way to address all the recommendations from thereport, and key learnings have been shared with other power stations.
• Negotiations have started with a boiler supplier and once technical,financial and commercial issues have been agreed, repair workshould begin in July 2015.
17
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 18/26
Load shedding stages have been amended tocreate less impact for electricity consumers
• In order to reduce the impact on customers and the complexity of managingStage 3 load shedding, Stage 3 has been adjusted down by 1 000MW.
Stage Old schedules New schedules
Stage 1 1 000 MW 1 000 MWStage 2 2 000 MW 2 000 MW
Stage 3 4 000 MW 3 000 MW
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 19/26
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 20/26
Build programme shows progress and contributesMWs to the grid
Medupi Power Station Project (6 x 800MW)
▪ Up to 800 MW contributing to national grid even while unit 6 is still in
test phase /synchronisation mode)
▪ 1st Unit (unit 6) on track for commercialization - August 2015
▪ Synchronization of second unit expected in 2017.
Kusile Power Station Project (6 x 800MW)
The project is making good progress
Synchronization of 1st Unit (Unit 1) expected at the end of the first half
of 2017
Ingula Pumped Storage Scheme Project (4 x 333MW)
Synchronization of 1st unit (Unit 3) has been revised to the first half of2016
Project Sere (100MW)▪ Successfully commercialized on time and within budget
▪ 100 MW feeding to the national grid, when the wind blows.
20
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 21/26
Eskom needs to ensure capital is available to ensuredelivery of one Medupi and two Ingula units for FY16
21Source: GCD, Team analysis
Feb 2015
Sere Wind Farm
Aug 2015
Medupi Unit 6
Mar 2016
Ingula Unit 4
Aug 2017
Kusile 1
Jul 2016
Ingula Unit 1
Mar 2015
Majuba
Recovery
Jan 2016
Ingula
Unit 3
May 2016
Ingula
Unit 2
2019/2020
Duvha 3
Recovery
Sep 2017
Medupi 5
xx MW added to
the network
1200
100 800
333
333
333
333
800
800
500
• Commissioned in
early Feb 2015
• Additional 100MW
added to the
network
• 600MW from unit
3 gap solution in
Feb & 600MW
from Unit 4 in Mar
2015
• First sync Mar
2015
• Full stable power
by Jun 2015
• Unit 3 to be
commissioned
Jan 2016
• Unit 4 to be
commissioned Apr
2016
• Unit 2 to be
commissioned
May 2016
• Medupi 5
commercial
operation date is
Sep 2017
• Unit 1 to be
commissioned
Aug 2016
• Kusile 1 will be
commercially
operating Aug
2017
• Duvha 3 will be
fully recovered in
2019/2020
• This project falls
out of MYPD3
window
Post MYPD3
Total MW
5 532
2015/16
1 466 MW
Medupi x1 unit
Ingula x2 units
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 22/26
Eskom keeps the country informed
• Eskom communicates via the national, regional and local media including social mediaregarding its intention to load shed and during the process.
• Load shedding information and schedules are available on Eskom’s website for Eskomcustomers
• National and regional spokespersons continue to spread the message and shareadditional information to provide information and clarity
• Stakeholders and direct customers are informed predominantly via social media and textmessages and are able to communicate via Eskom’s customer contact centres
• The Power Alert on SABC and DSTV channels continues to provide real-time informationon the power system status and encourages customers to switch off.
- An average of 350MW reduction in demand is observed during this flighting
• Eskom issues Power Alert system bulletins and holds a Quarterly system status mediabriefing to provide regular updates
• Face-to-face stakeholder engagements provide an opportunity for further dialogue on thestatus
Electricity users are encouraged to follow Eskom on twitter and Facebook and to
download the free Eskom App ‘Myeskom’ from Android and Apple stores.
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 23/26
We all can help to reduce demand and ‘Beat thePeak’ this winter
Saving electricity reduces pressure on the grid, cuts your
electricity bill and reduces South Africa’s carbon emissions
1. Use alternatives to electrical space heating
• Dress for the weather, to postpone switching on space
heaters
• Install ceiling insulation - an insulated room requires 51%
less energy to heat up
• Invest in a thermostatically controlled heater - a fan heater
is ideal for quick heat situations, while an oil heater can be
considered to keep a room warm for longer periods
• Consider gas heaters and hot water bottles to keep warm
2. Switch off all geysers and pool pumps (all day until
9pm), and invest in a timer
3. Switch off all non-essential lighting and appliances
4. Respond to Power Alert messages by switching off all
appliances that are not being used 23
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 24/26
Contents
Introduction
Half-Year Performance
Winter Outlook
Build programme
Conclusion
C
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 25/26
Conclusion: While the system is tight Eskomendeavours to keep load shedding to a minimum
• Eskom has continued to supply up to an average of 96% of electricity in the
country during the first half of 2015 and will continue to do so in Winter
• Unlike in Summer when the load shedding risk is for longer periods throughout
the day, in Winter, the load shedding risk is for shorter periods and over the
peak periods of 06:00 to 10:00 and 17:00 to 22:00, as more electricity is used
during this time.
• As the demand peaks in Winter, we anticipate that 100% electricity supply
during the day, and a minimum of 96% during the morning and evening peak
periods
• We will continue with maintenance with the intent to do no or minimal load
shedding
• We appreciate the support of all our customers and encourage that we maintain
10% electricity savings.
• We are committed to provide early warning, however at times the system status
changes rapidly. Please follow us on twitter @Eskom_SA and
@Eskom_MediaDesk for updates. 25
7/18/2019 Eskom's State of the System
http://slidepdf.com/reader/full/eskoms-state-of-the-system 26/26
Thank you