Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part...

77
Eskom Holdings SOC Limited Standard Presentation July 2014

Transcript of Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part...

Page 1: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Eskom Holdings SOC Limited

Standard Presentation

July 2014

Page 2: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Disclaimer

2

This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or

invitation of any offer to buy or subscribe for or underwrite or otherwise acquire, securities of Eskom Holdings SOC Limited

(“Eskom”), any holding company or any of its subsidiaries in any jurisdiction or any other person, nor an inducement to enter

into any investment activity. No part of this presentation, nor the fact of its distribution, should form the basis of, or be relied

on in connection with, any contract or commitment or investment decision whatsoever. This presentation does not constitute

a recommendation regarding any securities of Eskom or any other person.

Certain statements in this presentation regarding Eskom’s business operations may constitute “forward looking statements”.

All statements other than statements of historical fact included in this presentation, including, without limitation, those

regarding the financial position, business strategy, management plans and objectives for future operations of Eskom are

forward looking statements.

Forward-looking statements are not intended to be a guarantee of future results, but instead constitute Eskom’s current

expectations based on reasonable assumptions. Forecasted financial information is based on certain material assumptions.

These assumptions include, but are not limited to continued normal levels of operating performance and electricity demand

in the Customer Services, Distribution and Transmission divisions and operational performance in the Generation and

Primary Energy divisions consistent with historical levels, and incremental capacity additions through the Group Capital

division at investment levels and rates of return consistent with prior experience, as well as achievements of planned

productivity improvements throughout the business activities.

Actual results could differ materially from those projected in any forward-looking statements due to risks, uncertainties and

other factors. Eskom neither intends to nor assumes any obligation to update or revise any forward-looking statements,

whether as a result of new information, future events or otherwise.

In preparation of this document certain publicly available data was used. While the sources used are generally regarded as

reliable the content has not been verified. Eskom does not accept any responsibility for using any such information.

Page 3: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

3

Context of this presentation

• This presentation consists of a set of slides which provide an overview of Eskom and

are based on information contained in the 2014 Integrated Report. Users are

encouraged to add, delete or adapt slides to suit the requirements of their particular

presentation.

• Figures are quoted in rands (SA), unless otherwise indicated. The exchange rate

applied was that which applied at the end of the financial year (31 March 2014).

• The presentation is updated annually to coincide with the release of Eskom’s annual

and interim financial results.

• The presentation is in a Power Point format and the design and colours have been

specifically selected to complement our corporate identity, and for legibility.

• Comments, suggestions or requests may be directed to the Corporate Affairs Division.

Page 4: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

4

Content of the presentation

About Eskom

Business performance

Business update

Financial performance

Awards and recognition

Page 5: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

About Eskom

• Strategic 100% state-owned electricity utility, strongly supported by the government

• Supplies approximately 95% of South Africa’s electricity

• Performed 201 788 household electrification connections during the year, the highest in a single year since 2002

• As at 31 March 2014:

– 5.2 million customers (2013: 5.0 million)

– Net maximum generating capacity of 42.0GW (2013: 41.9GW)

– 17.4GW of new generation capacity being built, of which 6.1GW already commissioned

– Approximately 359 337km of cables and power lines

– 46 919 employees, inclusive of fixed-term contractors, in the group (2013: 47 295)

• Moody’s and S&P stand-alone credit ratings: b1 and b- respectively with a negative outlook

Nuclear

Gas

Coal

Hydro

Pumped Storage

Generation capacity – 30 September 2013

Number of electrification connections

5

154 250 139 881

201 788

Mar-12 Mar-13 Mar-14

Number

85.1%

5.7%

4.4%

3.4% 1.4%

42.0GW

of nominal

capacity

Page 6: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Eskom’s purpose, values and strategic objectives

Page 7: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Eskom’s seven sustainability dimensions

The changing environment requires a response that will ensure sustainability

Safety will continue to be the foundation for all our operations and is key to Eskom’s

performance and sustainability

Eskom’s mandate is

comprehensive, focused on many

dimensions of sustainability

• Core areas revolve around the

tension of asset creation,

operational sustainability, and

financial sustainability

• Beyond that, Eskom also needs

to ensure a positive wider

impact on the environment,

contribution to strategic

transformation and social

sustainability objectives as well as

the contribution to a sustainable

skills base

7

Page 8: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

8

Power station map

Page 9: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Electricity value chain

9

Page 10: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

10

Board of Directors

Mr Zola Tsotsi (Chairman) Mr Zola Tsotsi is a chemical engineer who was a corporate

consultant at Eskom from 2000 to 2004 and a corporate strategy

manager at the utility between 1997 and 2000. He has also

headed the boards of the Lesotho Highlands Development

Authority and the Lesotho Electricity Corporation and is the head

of the Lesotho Electricity Authority

Mr Collin Matjila (Acting Chief Executive)

Mr CoillinMatjila has a track record of overseeing both large

organisations and the electricity industry. The chief executive of

Cosatu's investment arm, Kopano Ke Matla, Matjila is the former

chairman of the National Energy Regulator of South Africa.

Ms Tsholofelo Molefe (Finance Director)

Appointed April 2011

BCompt Hons Certificate in Theory of Accounting ' University of

South Africa, BA Hons Accounting and Finance ' University of

East London (UK) CA(SA)

Ms Boni Mehlomakhulu Dr. Mehlomakulu is currently the chief executive officer of the

South African Bureau of Standards. She has a PhD in Chemical

Engineering from the University of Cape Town. She was

appointed to the Board in April 2010.

Page 11: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Board of Directors

Mr Bernard Lewis Fanaroff

Dr Fanaroff is currently the managing director of Fanaroff

Associates CC and project director at SKA SA. He has a PhD in

Radio Astronomy and Astrophysics. He was appointed to the

Board in May 2010.

Ms Neo Lesela

Ms Neo Lesela, who has an industrial engineering degree from

the University of Salford in the United Kingdom and formerly

worked for South African Breweries and Tiger Brands. She then

moved to Portnet (now the National Ports Authority) as a senior

engineer, joined Cell C in 2002 as the head of project

management and, in 2008, joined low-cost telecoms operator

Smile Communications as general manager.

Mr Mafika Mkhwanazi

Transnet chairman Mafika Mkwanazi was formerly chief executive

of the state-owned transport giant. He is currently also a chairman

of Letseng Diamond and a director at Nedbank. He previously sat

in the boards of SAA, Metrorail and Saatchi & Saatchi SA.

Mr Phenyane Sedibe

Mr Phenyane Sedibe, who is the owner of consultancy firm SPQ

Consulting, has a master's degree in social policy. His specialty is

small enterprise development, black empowerment and economic

transformation.

11

Page 12: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Board of Directors

Ms Lily Zondo

Ms Zondo is currently General Manager: Business Risk

Management at MTN SA. She has served on many audit

committees, focusing on risk management frameworks and

internal controls.

Ms Chwayita Mabude

Ms Chwayita Mabude an accountant with a background in

financial management.

Ms Yasmin Masithela

Ms Yasmin Masithela, a corporate lawyer and consultant at

Phukubje Pierce Masithela Attorneys, has worked for

multinational Siemens, heading its project and export finance

division. She has done extensive work in corporate law,

financial services and local government and procurement law.

Ms Bajabulile Luthuli

Ms Luthuli is a chartered accountant and Director

(Management Consulting) with South City Capital. She has

extensive experience in audit and risk management

12

Page 13: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Board of Directors

Ms Queendy Gungubele

Ms Gungubele specialises in labour relations with her current

position being a CCMA-accredited part-time commissioner and

arbitrator.

13

Page 14: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Corporate structure

14

Page 15: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

15

Executive Management Committee

Collin Matjila

Acting Chief Executive

Erica Johnson

Enterprise Development

and Acting Customer

Services

Tsholofelo Molefe

Finance Director

Ayanda Noah

Distribution

Thava Govender

Generation

Page 16: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Executive Management Committee

Dr Steve Lennon

Sustainability

Matshela Koko

(Acting) Technology and

Commercial

Mongezi Ntsokolo

Transmission and Acting Human

Resources

Dan Marokane (Acting)

Group Capital

16

Page 17: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

17

Plant mix

TOTAL

27 stations

41 995MW

Type Number Nominal capacity

Wind energy 1 station 3MW

Coal-fired

Gas/liquid fuel

turbine

Hydroelectric

Pumped storage

Nuclear

13 stations

4 stations

6 stations

2 stations

1 station

35 726MW

2 409MW

600MW

1 400MW

1 860MW

Page 18: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

18

Power stations

Station Location Nominal capacity MW

Coal-fired stations (13) 35 726

Arnot Middelburg, Mpumalanga 2 232

Camden Ermelo 1 481

Duvha Witbank 3 450 Grootvlei Balfour 1 120

Hendrina Mpumalanga 1 798

Kendal Witbank 3 840

Komati Middelburg, Mpumalanga 791

Kriel Bethal 2 850

Lethabo Viljoensdrift 3 558

Majuba Volksrust 3 843

Matimba Lephalale 3 690

Matla Bethal 3 450

Tutuka Standerton 3 510

Page 19: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

19

Power stations

Station Location Nominal capacity MW

Gas/liquid fuel turbine stations (4)

2 409

Acacia Cape Town 171

Ankerlig Atlantis 1 327

Gourikwa Mossel Bay 740

Port Rex East London 171

Hydroelectric stations (6) 600

Colley Wobbles Mbashe River 42

First Falls Umtata River 6

Gariep Norvalspont 360

Ncora Ncora River 2

Second Falls Umtata River 11

Vanderkloof Petrusville 240

Page 20: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

20

Power stations

Station Location Nominal capacity MW

Pumped-storage (2) 1 400

Drakensberg Bergville 1 000

Palmiet Grabouw 400

Wind energy (1)

Klipheuwel Klipheuwel 3

Nuclear (1)

Koeberg Melkbosstrand 1 860

Page 21: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

21

Key facts (as at 31 March 2014)

Electricity sales

2014 2013 2012

Sales within

South Africa,

GWh

205 525 202 770 211 590

International

sales, GWh 12 378 13 791 13 195

Total sales,

GWh 217 903 216 561 224 785

Growth in GWh

sales, % 0.6 (3.7) 0.2

Total revenue,

Rm 136 869 126 663 112 999

Growth in

revenue, % 7.4 16.4 24.8

Customers,

number 5 232 915 5 013 446 4 852 722

Peak demand,

MW 34 977 35 525 36 543

Electricity sales (GWh)

Electricity revenue (c/kWh)

224 785

216 561 217 903

Mar-12 Mar-13 Mar-14

GWh

50.3

58.5 62.8

Mar-12 Mar-13 Mar-14

Cents/kWh 7.4%

16.4%

(3.7)% 0.6%

Page 22: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Electricity sales

Electricity sales by customer type

6.8%, [6.8%]

14.1%, [14.6%]

5.1%, [4.8%]

5.7%, [6.4%]

25.0%, [23.8%] 41.9%, [42.2%]

Rail 1.4%,[1.4%] Residential

Industry

International

Mining

Commercial & agricultural

Municipalities

22

Page 23: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Key facts (as at 31 March 2014)

Electricity production by own stations

2014 2013 2012

Coal-fired, GWh 209 483 214 807 218 212

Hydroelectric, GWh 1 036 1 077 1 904

Pumped storage, GWh 2 881 3 006 2 962

Gas turbine, GWh 3 621 1 904 709

Nuclear, GWh 14 106 11 954 13 502

Wind energy, GWh 2 1 2

Total production, GWh 231 129 232 749 237 291

Electricity purchased by Eskom

• Foreign imports, GWh1 12 378 13 791 13 195

• Purchased from IPPs GWh 3 671 3 516 4 107

Demand-side management savings, MW 410 595 365

1. Foreign imports include wheeling of electricity

23

Page 24: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Key facts (as at 31 March 2014)

Transmission and distribution equipment 2014 2013 2012

Transmission lines, km 29 924 29 297 28 995

Distribution lines, km 46 093 44 396 43 856

Reticulation lines, km 276 027 269 535 267 011

Underground cables, km 7 293 6 960 6 657

Transformer capacity, MVA

• Transmission 138 350 135 840 132 955

• Distribution 93 829 89 959 72 910

Capacity expansion 2014 2013 2012

Generation capacity installed and commissioned, MW 120 261 535

Transmission lines installed, km 810.9 787 631

Transmission transformer capacity installed, MVA 3 790 3 580 2 525

24

Page 25: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Key facts (as at 31 March 2014)

Environmental information 2014 2013 2012

Coal burnt in power stations, Mt 122.4 123.0 125.2

Specific water consumption by power stations, L/kWh sent out 1.35 1.42 1.34

Net raw water consumption, ML 317 052 334 275 319 772

Relative particulate emissions, kg/MWh sent out 0.35 0.35 0.31

Carbon dioxide emissions (CO2), Mt 233.3 227.9 231.9

Radiation release, mSv 0.0012 0.0019 0.0024

Employees 2014

Sept

2013 2012

Employees, number 46 919 46 624 43 473

25

Page 26: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Key facts (as at 31 March 2014)

Developmental initiatives

2014 2013 2012

B-BBEE attributable spend, R billion 125.4 103.4 72.1

B-BBEE attributable spend, % 93.9 86.3 73.2

Electrification, homes connected 201 788 144 558 155 213

Corporate social investment, Rm 132.9 194.3 87.9

Jobs created through capital expansion

projects cumulative 25 181 35 759 28 616

Eskom trainees / bursars (pipeline) 2 476 6 987 6 794

26

Page 27: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Staff profile (as at 31 March 2014)

27

Employee profiles Actual

2013/14

Actual

2012/13

Actual

2011/12

Racial equity in senior management,

% of black employees

59.3 58.32 53.90

Racial equity in professionals and

middle management, % of black

employees

70.6 69.57 65.69

Gender equity in senior management,

% of female employees

28.8 28.21 24.31

Gender equity in professionals and

middle management, % of female

employees

34.9 34.60 32.43

Page 28: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Business performance

28

Page 29: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Income statement for the year ended 31 March 2014 Ensuring Eskom’s financial sustainability

• Group revenue of R139.5 billion (2013: R128.8 billion), an increase of 8.3%

• Revenue growth has been offset by escalating primary energy and operating costs

• Effective tax rate of 23.3% (2013: 26.5%)

• Embedded derivative gain is mainly due to changes in the USD:ZAR exchange rate and changes in interest rates

• Finance costs of R13.3 billion were capitalised during the year to 31 March 2014 (2013: R3.7 billion)

• Assets are accounted for at historic cost. If assets were valued at depreciated replacement cost, the loss after tax would be R12.5 billion

• No dividend was recommended

Rm

Audited year to

31 March 2014

Reviewed half-year

to 30 Sep 2013

Audited year to

31 March 20131

Audited year to

31 March 2012

Revenue 139 506 77 815 128 775 114 847

Other income 962 197 1 126 712

Primary energy (69 812) (31 266) (60 748) (46 314)

Operating expenses (including depreciation & amortisation)

(58 293) (28 702) (57 602) (44 872)

Net fair value loss on financial instruments

(620) (998) (1 655) (2 388)

Operating profit before embedded derivatives

11 743 17 046 9 896 21 985

Embedded derivative gain / (loss)

2 149 1 868 (5 942) 334

Operating profit 13 892 18 914 3 954 22 319

Net finance (cost) / income2

(4 772) (1 853) 3 003 (3 956)

Share of profit of equity - accounted investees

43 26 35 41

Profit before tax 9 163 17 087 6 992 18 404

Income tax (2 137) (4 846) (1 856) (5 156)

Discontinued operations 63 - 47 -

Net profit for the period 7 089 12 241 5 183 13 248

1. Restated due to reclassification of Eskom Energie Manantali s.a as a discontinued operation

2. There was no remeasurement of the government loan during the year to 31 March 2014, as there was no change in the electricity tariff price path.

In 2012/13 the effect of the remeasurement of the government loan was a R17.3 billion finance income for the year 31 March 2013

Page 30: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Maximise socio-economic contribution Transformation

1. Number of project beneficiaries impacted by Eskom’s corporate social initiatives at year end

A total of 201 788 homes were electrified during the

year to 31 March 2014 (2013: 139 881)

Since inception of the electrification programme in

1991, more than 4.5 million homes have been

electrified

Electrification

Corporate

social

investment

Committed R132.9 million to corporate social

initiatives during the year to March 2014 (2013:

R194.3 million)

Number of project beneficiaries1

Number

531 762

652 347

357 443

Mar-12 Mar-13 Mar-14

Page 31: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Procurement equity and localisation Transformation

1. Reflects the Eskom company’s broad-based black economic empowerment (B-BBEE) expenditure

2. Measurement of the procurement from BYO entities only started in 2013

Procurement1

from B-BBEE

compliant

entities

Total measured

procurement spend for

the year was

R133.5 billion of which

R125.4 billion or

93.9% was attributable

to B-BBEE, exceeding

the target of 75%

73.2

86.3 93.9

10

20

30

40

50

60

70

80

90

100

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

% o

f B

-BB

EE

spend

Procurement

from black-

owned (BO),

black women-

owned (BWO)

and black

youth-owned

(BYO)2 entities

%

n/a2

14.6

22.1

32.7

3.3 4.7

7.2

1.0 1.0

Mar-12 Mar-13 Mar-14

Procurement from BO entities %

Procurement from BWO entities %

Procurement from BYO entities %

Target

75

Page 32: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Procurement equity and localisation (continued) Transformation

28 616

35 759

25 181

Mar-12 Mar-13 Mar-14

Number

As at 31 March 2014, the

capacity expansion

programme employs 25 181

people on new build project

sites, down from 35 759 at

the previous year end, due

to the demobilisation of staff

as work packages are

completed

54.6% local content in the new build contracts placed for the financial

year (2013: 80.2%)

Local

sourcing

Job creation

Local skills

development

Since the inception of the capital expansion programme in 2005, a total

of 8 930 (2013: 6 851) contractor employees have been trained in various

trades

Job creation

32

Page 33: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

The Eskom group currently employs 1 305 (2013: 1 137) employees with

recognised disabilities. Although the disability percentage of 2.77% is

below the 3% target, it is above the government target of 2%

Employment equity Transformation

Racial

equity1

Gender

equity1

Disability

1. Reflects Eskom company numbers

53.9 58.3 59.5

65.7 69.6 71.2

0

10

20

30

40

50

60

70

80

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

%

■ Racial equity in senior management (% of black employees)

■ Racial equity in professionals and middle management (% of black employees)

■ Gender equity in senior management (% of female employees)

■ Gender equity in professionals and middle management (% of female employees)

24.3 28.2 28.9

32.4 34.6 35.8

0

5

10

15

20

25

30

35

40

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

%

Page 34: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Fatalities

Year to 31 March

2014

Year to 31 March

2013

Year to 31 March

2012

Employees 5 3 13

Contractors 18 16 11

Causes of fatalities Vehicle Electrical

contact Other

Employees and contractors 7 2 14

Safety Becoming a high-performance organisation

Employee

and

contractor

fatalities

Causes of

fatalities

Employee

LTIR

1. Number revised from 0.39 to 0.40 due to the late reporting of incidents

Ingula

incident

On 31 October 2013, an accident at Ingula power station construction site

resulted in the tragic loss of six lives, while a further seven sustained

injuries. Although work on the inclined high-pressure shaft was stopped in

terms of the Mines Health and Safety Act (1996) pending review by the

Mine Health and Safety Inspectorate, work on other parts of the site

continues. The statutory processes regarding this accident are in progress

Employee lost-time incidence rate

Index (Target: 0.36)

0.31 0.401

0.41

Page 35: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Business update

35

Page 36: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

85.2 84.6 82.0

77.7 75.1

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

80.0

Improve operations – Generation Becoming a high-performance organisation

Energy availability factor (EAF2) %

1. UCLF measures the lost energy due to unplanned production interruptions

resulting from equipment failures and other plant conditions

2. EAF measures plant availability, plus energy losses not under the control of plant

management

5.1

6.1

8.0 8.7

11.0

3.4

1.6

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

ConstrainedUCLF 10.0

Highlights • Koeberg unit 2 ended a record run of

484 days when it was shut down for scheduled refuelling on 24 March 2014, marking a continuous run from one refuelling to another

Challenges • The increasing UCLF percentage is an

indication of the deteriorating plant health and the high plant utilisation

• Balancing the need for adequate maintenance with the constrained system, asset creation, environmental requirements and available financial resources – not performing sufficient maintenance reduces plant reliability and increases the risk of load shedding over the longer term

• Duvha Unit 3 was taken out of service on 30 March 2014 due to an over-pressurisation incident. The incident is still under investigation

12.6 12.1

Unplanned capability loss factor (UCLF1) %

Actual Annual year-end target

Page 37: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Improve operations – Transmission Becoming a high-performance organisation

1

0

1

3

0

2

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

Number of major incidents2

Highlights

• Good system technical performance

achieved with zero major incidents,

system minutes <1 performance at

3.05 compared to a target of 3.40, and

a line fault performance of 1.73

compared to a target of 2.45 faults per

100km

Challenges

• Performance vulnerabilities remain with

ageing assets and unfirm networks

• Performance of Hydro Cahora Bassa3

scheme energy imports remains a risk

due to challenges regarding the

reliability of high-voltage direct-current

transmission lines

System minutes1 lost < 1 system minute

4.1

2.6

4.7

3.5

3.1

3.4

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

1. System minutes is a measure of the extent of interruptions to customers.

One system minute is equivalent to the loss of the entire system for one

minute at annual peak

2. Major Incident is an interruption with a severity ≥ 1 system minute

3. Hidroelectrica de Cahora Bassa S.A. Actual Annual year-end target

Page 38: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

54.4 52.6

45.8 41.9

37.0

45.0

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

SAIDI (hours/annum)2

Highlights

• Significant improvement in the SAIFI

and SAIDI interruption performance

due to:

− Additional customer network centres

− Maximisation of live-line work for

planned maintenance

− Increased network visibility

Challenges

• Managing the risk of increased

exposure of employees and contractors

to crime-related assault incidents

• Addressing the backlog in

maintenance, refurbishment and

reliability with particular focus on

preventative maintenance for

reticulation (low-voltage) networks

• Reducing the backlog in customer

connections, by addressing material

and contractor resource shortages

Improve operations – Distribution Becoming a high-performance organisation

SAIFI (number/annum)1

24.7 25.3 23.7

22.2 20.2

20.0

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

1. SAIFI: System average interruption frequency index

2. SAIDI: System average interruption duration index Actual Annual year-end target

Page 39: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Being customer-centric Becoming a high-performance organisation

Highlights

• Customers responded admirably when

Eskom declared four power system

emergencies and reduced demand by

600MW in November 2013, 340MW in

February 2014 and 1 160MW in

March 2014

Challenges

• Debt collection, especially from

municipalities, is a challenge with arrear

debt increasing significantly. Eskom is

working closely with the shareholder, the

Cooperative Governance and Traditional

Affairs (CoGTA) department and National

Treasury at provincial and national level

to address the systemic causes of

municipal arrear debt

• Energy losses due to theft of equipment,

illegal connections, meter tampering and

illegal vending of pre-paid electricity

remains a concern

85.1

84.4

85.6

86.8 86.6

88.7

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

Weighted customer service index1

Energy losses2

Year to 31 March

2014

Year to 31 March

2013

Year to 31 March

2012

Distribution 7.13 7.12 6.32

Transmission3

2.34 2.80 3.08

Total Eskom 8.88 9.08 8.65

1. Eskom uses a composite index to measure the service delivered to its

residential, small and medium customers

2. Non-technical losses are estimated to be between 1.78% and

2.85% for the year to 31 March 2014

3. Transmission losses are all technical losses

Actual Annual year-end target

Page 40: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

2 273 2 144 1 962

844 835 815

2 598 2 847 2 383

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

Engineering learners Technician learners Artisan learners

Build strong skills Becoming a high-performance organisation

Skills

Training

Eskom’s

engineering,

technician

and artisan

learners

Eskom aims to grow human capital by retaining

core, critical and scarce resources, and by

effectively developing skills and talent

There are 4 325 learners in the youth

programme as at 31 March 2014 Youth

programme

7.87% of gross employee benefit costs spent

on training in the year to 31 March 2014

Page 41: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Keeping the lights on Leading and partnering to keep the lights on

Highlights • More planned maintenance was done

during the past winter than the same period in the three preceding years, in line with the Generation sustainability strategy

Challenges • Adequate reserves available throughout

the day to meet demand, but minimal reserves available at peak periods

• In order to keep the lights on, Eskom has had to run its generating plant at significantly higher load factors

• Four power system emergencies were declared during the year

• Increased costs due to the significant reliance placed on the open-cycle gas turbine (OCGT) fleet in the current year: − R10.6 billion spent to produce

3 621GWh (2013: R5.0 billion; 1 905GWh)

− OCGT load factor of 17.16% (2013: 9.31%) against a budgeted load factor of 6.08%, based on the MYPD response budget

Average monthly % operating reserves

Summer and winter load profiles

20 000

22 000

24 000

26 000

28 000

30 000

32 000

34 000

36 000

00:0

0

03:0

0

06:0

0

09:0

0

12:0

0

15:0

0

18:0

0

21:0

0

Typical Summer Day Typical Winter DayMW

0%

10%

20%

30%

40%

50%

60%

Jan…

Apr…

Jul…

Oct…

Jan…

Apr…

Jul…

Oct…

Jan…

Apr…

Jul…

Oct…

Jan…

Apr…

Jul…

Oct…

Jan…

Apr…

Jul…

Oct…

Jan…

Monthly Avg at 06:00 Monthly Avg at 15:00

Monthly Avg at Peak Monthly Avg at 22:00

Page 42: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

• Achieved total evening peak demand

savings of 410MW (2013: 595MW)

• The average weekday evening peak

impact of the power alert and power

bulletin for all colours (green, orange

and red) is 224MW, while the average

impact for the red flightings in the

evening peak on the worst constrained

day is 294MW

• Eskom continues to improve the

internal energy-efficiency of its facilities.

Annualised energy savings of 19GWh

were achieved from new IDM projects

for the year ended 31 March 2014,

exceeding the target of 15GWh

• Going forward, it will be a challenge to

utilise IDM as a key lever in managing

demand, due to the reduction in funding

allocated in the MYPD 3 determination

0

500

1 000

1 500

2 000

2 500

3 000

3 500

4 000

4 500

Year to31 Mar2005

Year to31 Mar2006

Year to31 Mar2007

Year to31 Mar2008

Year to31 Mar2009

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

Verified MW Eskom Target

Integrated Demand Management Leading and partnering to keep the lights on

Cumulative verified demand savings

MW

Page 43: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Deliver capacity expansion Leading and partnering to keep the lights on

Highlights • Return-to-service programme of 23 units

(3 741MW) has been completed at a cost of R26 billion

• Despite outage constraints, refurbishment projects have progressed well

• Established the Medupi leadership initiative to address the demobilisation of workers

Challenges • Contract placed with a second contractor for

the engineering and manufacturing of boiler-protection systems, to mitigate against the continued failure of control and instrumentation factory acceptance tests at Medupi

• Acquisition of servitudes over state-owned and tribal land, causing delays to transmission projects

Synchronisation dates of first units • Medupi in the second half of 2014 (794MW) • Ingula in the second half of 20151 (333MW)

• Kusile in the second half of 2015 (800MW)

Progress on capacity expansion programme

66.9 77.0

54.3 66.6

15.1 19.4

38.1 28.0 64.2 52.0

10.8 6.6

2013 2014 2013 2014 2013 2014

Remaining

Completed

73.3% 56.2%

74.7%

63.7%

45.8%

58.3%

−−Medupi−−

R105.0 billion2

−−Kusile−−

R118.5 billion2

−−Ingula−−

R25.9 billion2

1. Synchronisation date delayed after the accident at Ingula on 31 October 2013 2. Approved budget (excluding capitalised borrowing costs)

R billion % completed

Page 44: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Deliver capacity expansion – progress on Medupi Leading and partnering to keep the lights on

Key milestones achieved at Medupi in the first

quarter of 2014/15

• Welding challenges which resulted in extensive

delays to Unit 6 have been effectively resolved

• Hydrostatic pressure tests on the reheater and

superheater circuits of the Unit 6 boiler were

successfully conducted in April and May 2014

• The boiler is now mechanically complete and ready

to continue with acid cleaning

• Factory acceptance tests have been successfully

completed on both the control and instrumentation

of the balance of plant and the boiler-protection

system in April and May 2014

• This released a significant part of the plant to

progress with critical commissioning activities

• Achieving these critical milestones ensures that

Eskom remains on track for the targeted first

synchronisation of Unit 6 by the second half of

2014 as previously reported

44

Page 45: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

0 290 1 351.0 1 043

1 770 453 315 535 261 120

6 137

17 384

659 237 430 480 418 600 443

631.3 787 811

5 497

9 756

5 280 1 090 1 000 1 355 1 375 1 630

5 940 2 525 3 580

3 790

27 565 42 470

2004/5 2005/6 2006/7 2007/8 2008/9 2009/10 2010/11 2011/12 2012/13 2013/14 Total Target

Deliver capacity expansion (continued) Leading and partnering to keep the lights on

Km line Transmission

MVAs Substations

MW of capacity Megawatts

To date, the construction work that has been completed has added

~ 6 137MW of capacity, ~ 5 497km of transmission network and ~ 27 565 of MVAs

1. Refers to the target of the total capacity expansion programme

1

Page 46: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Environmental

performance

Renewable

energy:

Sere wind

farm

Environmental performance Reducing Eskom’s environmental footprint and pursuing low-carbon growth

Key performance indicator Year to

31 March 2014

Year to 31 March

2013

Year to 31 March

2012

Relative particulate emissions, kg/MWh

sent out 0.35 0.35 0.31

Specific water consumption, L/kWh sent

out 1.35 1.42 1.34

Environmental legal contraventions per

the operational health dashboard,

number

2 21 5

The installation of 10 of a total of 46 wind

turbines was completed at 31 March 20142,

and a further 22 tower foundations laid. This

100MW renewable project is expected to be

completed and commissioned in the 2014/15

financial year. This will assist in reducing

Eskom’s carbon footprint

1. Increased from previously reported figure (1) due to an additional legal contravention that was identified during the year for activities associated with

the underground coal gasification (UCG) project, in October 2012

2. To date, the installation of a total of 27 of the 46 wind turbines has been completed. The transmission substation has been completed and the power

evacuation line is being commissioned

Page 47: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Generation – operational performance

47

Highlights

• At the end of September 2013 both

Koeberg units were online for 160 days

simultaneously, surpassing the previous

record which was set in 2004

• The Generation Sustainability Strategy

and the associated increased opportunity

for maintenance has enabled several

stations to significantly improve their

emissions performance

Challenges

• The higher UCLF percentage is an

indication of the deteriorating plant health

of an ageing power station fleet

• Executing the generation sustainability

strategy while keeping the lights on

85.2 84.6 82.0

77.7 78.4

35

45

55

65

75

85

95

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Half year to30 Sep2013

80.0

Energy availability factor (EAF3) %

Actual Annual year-end target

5.1

6.1

8.0 8.7 8.1

0123456789

10111213

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Half year to30 Sep2013

ConstrainedUCLF

10.0

11.52 12.1

Unplanned capability loss factor (UCLF1) %

1. UCLF measures the lost energy due to unplanned production interruptions

resulting from equipment failures and other plant conditions

2. The 11.53% normal UCLF consists of constrained UCLF of 3.45% and underlying

UCLF OF 8.08% (UCLF under Eskom’s control). Constrained UCLF refers to

emissions and short-term related UCLF due to system constraints to meet the

“Keep the lights on” objective

3. EAF measures plant availability, plus energy losses not under the control of plant

management

Page 48: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

• Eskom believes in a balanced approach to ensure environmental sustainability whilst

supporting economic growth and access to affordable electricity

• New atmospheric standards come into effect in 2015. Eskom has received new

atmospheric emission licenses for most of its power stations, except Kriel, where Eskom’s

request to increase the emissions limit and allow a grace period for when emissions

exceed the limit of the new license, has been denied

• Eskom has embarked on an extensive retrofit programme to reduce emissions at the

highest emitting power stations, but the execution of this programme will require long

outages and a significant amount of capital (currently R72 billion in nominal terms)

• Despite the retrofit programme and Eskom’s best efforts, there remains a risk that Eskom

may not be able to fully comply with the new national emission standards, which come into

effect in 2015 and 2020, for several reasons:

− Certain of the required technologies requires additional water which is not yet available

− Implementation of the required technologies requires plant outages of 120 to 150 days

per unit; there is insufficient spare capacity to enable the required outages to be taken

without impacting on the ability to meet national electricity demand

• Given the above, Eskom expects to achieve 57% compliance with the national emission

standards by 2026

• Eskom submitted an application in February 2014 for a five-year postponement from

compliance to the standards for cases where compliance within the legislated timeframe

is not possible. A response from the authorities is expected within six to nine months

National emission standards Reducing Eskom’s environmental footprint and pursuing low-carbon growth

Page 49: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Coal and water resources Securing future resource requirements

18

13

44 46

53

44

0

10

20

30

40

50

60

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

2007/8

2012/13

2013/14

Highlights • Coal stock days at 31 March 2014 remains

above target of 42 days, but has decreased to 44 days from the previous year (2013: 46 days)

• Komati water scheme augmentation project was declared operational on 5 June 2013

• Mokolo Crocodile water augmentation project delivered water to Medupi for construction activities and commissioning of the first units

Challenges • Despite the overall coal quality being on target,

coal-related load losses were experienced at Arnot, Matla and Tutuka power stations

• Production performance of some cost-plus mines continues to be a challenge

• Eskom mixes coarse coal with finer coal to prevent wet coal from coagulating on conveyors

• Although four medium-term contracts were signed for coal supply to Kusile power station during the commissioning phase, the conclusion of long-term coal and limestone supply agreements remains a focus area

Coal stock days

Page 50: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Coal road-to-rail migration Implementing coal haulage and the road-to-rail migration plan

5.1

7.1

8.5

10.1

11.6 11.5

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

Coal road-to-rail migration Eskom has been progressively migrating coal

transport from road to rail over the past four

years. Rail transport is safer, more

environmentally friendly, less damaging to

roads and more cost-effective than road

transport by truck

Highlights

• Increase of 15% against previous year of

coal transported by rail

Challenges

• Both Eskom and Transnet experienced

operational challenges regarding the rail

transport of coal

• In June 2013, rail deliveries were affected by

a series of derailments on the Transnet

Freight Rail Natcor rail line

Mt

Actual Annual year-end target 1

1. No target prior to 2012

Page 51: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Independent power producers (IPPs) Pursuing private-sector participation

Highlights

• Total energy procured from short-term

IPPs for the year is 3 671GWh at a cost of

R3 266 million (average cost of 88c/kWh)

• The first project under the renewable

energy independent power producers

(RE-IPP) programme was commissioned

on 15 November 2013, adding 7MW

• Eskom has successfully facilitated the

connection of 21 RE-IPP projects

(1 076MW) to the grid, of which 467.3MW

is currently available to the system

• DoE approved an additional 1 457MW

pursuant to the third bid submission, but

no contracts have yet been signed

• Contracts were signed for 1 005MW under

the DoE Peaker programme

Energy purchased from IPPs

4 107

3 516 3 671

Mar-12 Mar-13 Mar-14

GWh

Page 52: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Maximise socio-economic contribution Transformation

1. Number of project beneficiaries impacted by Eskom’s corporate social initiatives at year end

A total of 201 788 homes were electrified during the

year to 31 March 2014 (2013: 139 881)

Since inception of the electrification programme in

1991, more than 4.5 million homes have been

electrified

Electrification

Corporate

social

investment

Committed R132.9 million to corporate social

initiatives during the year to March 2014 (2013:

R194.3 million)

Number of project beneficiaries1

Number

531 762

652 347

357 443

Mar-12 Mar-13 Mar-14

Page 53: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Procurement equity and localisation Transformation

1. Reflects the Eskom company’s broad-based black economic empowerment (B-BBEE) expenditure

2. Measurement of the procurement from BYO entities only started in 2013

Procurement1

from B-BBEE

compliant

entities

Total measured

procurement spend for

the year was

R133.5 billion of which

R125.4 billion or

93.9% was attributable

to B-BBEE, exceeding

the target of 75%

73.2

86.3 93.9

10

20

30

40

50

60

70

80

90

100

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

% o

f B

-BB

EE

spend

Procurement

from black-

owned (BO),

black women-

owned (BWO)

and black

youth-owned

(BYO)2 entities

%

n/a2

14.6

22.1

32.7

3.3 4.7

7.2

1.0 1.0

Mar-12 Mar-13 Mar-14

Procurement from BO entities %

Procurement from BWO entities %

Procurement from BYO entities %

Target

75

Page 54: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Procurement equity and localisation (continued) Transformation

28 616

35 759

25 181

Mar-12 Mar-13 Mar-14

Number

As at 31 March 2014, the

capacity expansion

programme employs 25 181

people on new build project

sites, down from 35 759 at

the previous year end, due

to the demobilisation of staff

as work packages are

completed

54.6% local content in the new build contracts placed for the financial

year (2013: 80.2%)

Local

sourcing

Job creation

Local skills

development

Since the inception of the capital expansion programme in 2005, a total

of 8 930 (2013: 6 851) contractor employees have been trained in various

trades

Job creation

54

Page 55: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

The Eskom group currently employs 1 305 (2013: 1 137) employees with

recognised disabilities. Although the disability percentage of 2.77% is

below the 3% target, it is above the government target of 2%

Employment equity Transformation

Racial

equity1

Gender

equity1

Disability

1. Reflects Eskom company numbers

53.9 58.3 59.5

65.7 69.6 71.2

0

10

20

30

40

50

60

70

80

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

%

■ Racial equity in senior management (% of black employees)

■ Racial equity in professionals and middle management (% of black employees)

■ Gender equity in senior management (% of female employees)

■ Gender equity in professionals and middle management (% of female employees)

24.3 28.2 28.9

32.4 34.6 35.8

0

5

10

15

20

25

30

35

40

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

%

Page 56: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Financial performance

56

Page 57: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Revaluation of assets – proforma if aligned to regulatory asset base

Rm

Historical cost: For the year to 31 March 2014

After revaluation:

For the year to 31 March 2014

Historical cost: For the year to 31 March 2013

After revaluation:

For the year to 31 March 2013

Income statement (current year impact)

Historical profit/(loss) for the year 7 089 7 089 5 183 5 183

Adjustments: Depreciation and amortisation expense - (13 887) - (15 534)

Net impairment loss and other operating expenses - (40) - (105)

Net finance cost - (13 290) - (3 678)

Income tax - 7 621 - 5 409

Profit/(loss) for the year 7 089 (12 507) 5 183 (8 725)

Equity (cumulative impact)

Historical closing equity balance 119 784 119 784 109 139 109 139

Adjustments: Additional cumulative comprehensive loss - (82 746) - (63 150)

Revaluation of property, plant and equipment - 279 761 - 252 781

Deferred tax on revaluation - (78 333) - (70 779)

Adjusted closing equity balance 119 784 238 466 109 139 227 991

Statement of financial position (cumulative impact)

Property, plant and equipment 401 373 566 209 341 429 506 502

Ratios

Electricity operating costs, cents per kWh (company) 59.67 66.06 54.15 61.37

Interest cover, ratio (group) 0.77 0.00 0.22 0.65

Debt:equity, ratio (group) 2.06 1.03 1.84 0.88

Page 58: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

50.3

58.5 62.8

Mar-12 Mar-13 Mar-14

Cents/kWh

Sales and revenue Ensuring Eskom’s financial sustainability

224 785

216 561 217 903

Mar-12 Mar-13 Mar-14

GWh

Electricity sales

Electricity revenue

• Sales were 9 490 GWh lower than

forecast in the NERSA tariff application

• Local sales of 205 525GWh

(2013: 202 770GWh)

• International sales of 12 378GWh

(2013: 13 791GWh)

Electricity sales by customer type1

6.8%, [6.8%]

14.1%, [14.6%]

5.1%, [4.8%]

5.7%, [6.4%]

25.0%, [23.8%]

41.9%, [42.2%]

Rail 1.4%,[1.4%] Residential

Industry

International

Mining Commercial & agricultural

Municipalities

1. Percentages reflected for the sales achieved in the year to 31 March 2014

Numbers in brackets are those for the year to 31 March 2013

(3.7)% 0.6%

7.4%

16.4%

Page 59: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Electricity operating expenses1

Ensuring Eskom’s financial sustainability

• The electricity operating cost per kWh

sold is 59.67c/kWh2 compared to the

target of 52.67c/kWh

• The 13.2% variance on the cost per kWh

is mainly attributed to the OCGT spend in

the current year of R10.6 billion (originally

budgeted at R3.6 billion), along with the

increase in maintenance costs in line with

the generation sustainability strategy

• The employee benefit cost includes direct

and indirect expenditure for the 42 923

Eskom employees (group: 46 919)

• Included in other operating expenses is

the impairment on arrear debt of 1.10%

of revenue (2012/13: 0.82%)

1. Reflects only company expenses

2. Cents/kWh figures are calculated based on total electricity sales numbers for year

17 722 20 776 22 384

8 681 9 787 11 934 9 098 10 602

12 917 10 979 15 341

12 972

46 314

60 748 69 812

41.28

54.14

59.67

Mar-12 Mar-13 Mar-14

Primary energy costs

Other operating expenses, including impairments

Repairs and maintenance

Depreciation and amortisation expense

Employee benefit expense

Electricity operating expenses

Cents/kWh R million

Page 60: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Analysis of primary energy costs Ensuring Eskom’s financial sustainability

Rm

Year to

31 March

2014

Year to

31 March

2013

Year to

31 March

2012

Own generation costs,

excluding OCGT costs1 43 625 39 371 30 997

Open-cycle gas turbine

(OCGT) costs 10 561 5 009 1 490

Environmental levy 8 530 7 971 6 208

International electricity

purchases 3 311 2 070 1 858

Independent power

producers 3 266 2 956 3 250

Other2

519 3 371 2 510

Total cost of electricity

generation 69 812 60 748 46 314

1. Includes the cost of coal, uranium, water and liquid fuels that are used in the generation of electricity

2. Includes demand market participation, co-generation and power buybacks

• Primary energy costs have increased significantly

• Given the tight reserve margin, more expensive

OCGT stations were operated far above previous

load factors to ensure continuity of supply

1 151

136 49 197

708

1 905

3 619

0

500

1 000

1 500

2 000

2 500

3 000

3 500

4 000

Year to31 Mar2008

Year to31 Mar2009

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

OCGT annual production

GWh

2 004

233 82 434 1 490

5 009

10 561

0

2 000

4 000

6 000

8 000

10 000

12 000

Year to31 Mar2008

Year to31 Mar2009

Year to31 Mar2010

Year to31 Mar2011

Year to31 Mar2012

Year to31 Mar2013

Year to31 Mar2014

OCGT annual costs

R million

Page 61: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

20 22 24 26 28 30 32 34

0.74

2.54

(1.27)

28.05

Analysis of primary energy costs (continued) Ensuring Eskom’s financial sustainability

Primary energy costs (c/kWh)1

Cents / kWh

19% of the

increase

64% of the

increase

(32%) of the

increase

49% of the

increase

Cost of coal burnt

increased by 5%

OCGT2 costs increased

by R5.6bn (111%)

Power buyback costs

Other items in aggregate

Primary energy costs

as at 31 March 2013

Primary energy costs as at

31 March 2014

1. Primary energy costs in c/kWh based on electricity sales

2. Open-cycle gas turbine (OCGT)

1.98

32.04

20.60

• Primary energy costs increased by 14.2%

from 28.05 c/kWh as at 31 March 2013 to

32.04 c/kWh for the year to 31 March 2014

2.7%

14.2%

6.9%

(4.5%)

9.1%

Page 62: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

10.25 11.82

14.57

7.68 9.21

10.57

Mar-12 Mar-13 Mar-14

Rand:Euro Rand:USD

• Embedded derivatives

– Loss in 2012/13 was mainly due to the

decision at 31 March 2013 to account for

the full term of the underlying negotiated

pricing agreement contracts

– Profit in the current year is mainly as a

result of the changes in the USD/ZAR

exchange rate and interest rates

– Eskom submitted an application to

NERSA to review the last remaining

negotiated pricing agreement

• Foreign currency and commodity hedging

– Foreign currency and commodity

exposures are hedged

– Use forward exchange contracts with

short maturities and roll-over at maturity

as well as cross-currency swaps

– 78% of total debt at 31 March 2014 has

a fixed interest rate component

– R110.2 billion exposure to foreign

currency

Hedging policy Ensuring Eskom’s financial sustainability

334

(5 942)

2 149

Mar-12 Mar-13 Mar-14

Gain/(loss) on embedded derivatives

R million

(2 388) (1 655)

( 620)

Mar-12 Mar-13 Mar-14

R million

Net fair value loss on financial instruments

Rand versus Euro and USD exchange rates

Exchange rates

Page 63: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Group audited financial position – property, plant and equipment growth through debt raised Ensuring Eskom’s financial sustainability

Debt securities and borrowings,

R182 567m

Debt securities and borrowings,

R202 956m

Debt securities and borrowings,

R254 820m

Working capital, R33 942m Working capital, R42 946m

Working capital, R45 607m Other liabilities, R62 753m

Other liabilities, R76 983m

Other liabilities, R84 782m Equity, R103 103m

Equity, R109 139m

Equity, R119 784m

0

100 000

200 000

300 000

400 000

500 000

600 000

Mar-2012 Mar-2013 Mar-2014

Property, plant and equipment, and

intangible assets, R292 209m

Property, plant and equipment, and

intangible assets, R344 271m

Property, plant and equipment, and

intangible assets, R404 389m

Liquid assets, R40 480m

Liquid assets, R27 970m

Liquid assets, R30 583m

Working capital, R25 911m

Working capital, R29 204m

Working capital, R32 158m

Other assets, R23 765m

Other assets, R30 579m

Other assets, R37 863m

0

100 000

200 000

300 000

400 000

500 000

600 000

Mar-2012 Mar-2013 Mar-2014

Net debt to equity ratio:

1.84

Net debt to equity ratio:

2.06

Net debt to equity ratio:

1.57

R million

R million

Assets

Equity and liabilities

Page 64: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

58 815 60 133 59 803

Mar-12 Mar-13 Mar-14

Balance sheet Ensuring Eskom’s financial sustainability

Capital expenditure1

1. Excluding capitalised borrowing costs

2. Represents the repayment of nominal capital and interest in the strategic and trading portfolio. Data as at 31 March 2014

3. Reflects the 10 financial years starting 1 April 2014 and ending on 31 March 2024

Debt and borrowings maturity profile2

Within one year 5.8%

One to 10 years 40.2%

More than 10 years 54.0%

Debt securities and borrowings

19 450 10 620

19 676

21 030

17 350

10 907

Mar-12 Mar-13 Mar-14

Cash and cash equivalents Investment in securities

R million

Liquid assets at period end

40 480

27 970 30 583

R million

182 567 202 956

254 820

Mar-12 Mar-13 Mar-14

3

R million

2

Page 65: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Funding plan from 1 April 2010 to 31 March 2017 Ensuring Eskom’s financial sustainability

Source of funds

Funding

sourced

R billion

Currently

secured

R billion

Draw-downs

to date

R billion

Supported by

government

R billion

Bonds 90.0 65.4 65.4 42.6

Commercial paper1

70.0 70.0 40.0 0.0

Export Credit Agencies 32.9 32.9 21.7 0.0

World Bank 27.8 27.8 12.0 27.8

African Development Bank 20.9 20.9 16.2 20.9

Development Bank of Southern Africa 15.0 15.0 9.0 0.0

Shareholder loan 20.0 20.0 20.0 20.0

Other / new sources 23.4 19.6 4.5 5.0

Totals 300.0 271.6 188.7 116.2

Percentages 90.5%2

69.5%3

42.8%3

1. Commercial paper is issued for up to one year and then redeemed and re-issued for the same net amount. The commercial paper is thus by definition

not fully secured for the full period, however, Eskom’s long-term observations and past trends support a high level of confidence that Eskom will be

able to roll over the redemptions each year. For this reason, the gross value of the commercial paper is shown under the “secured” column in the

borrowing programme table above

2. As a percentage of the R300 billion funding sourced

3. As a percentage of the currently secured total

This plan was based on the assumption of a 16% MYPD 3 increase and will need to be

extended

Page 66: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Debt maturity profile Ensuring Eskom’s financial sustainability

Strategic and trading portfolio nominal and interest cashflows as at 31 March 2014

-

50

100

150

200

250

300

350

-

5

10

15

20

25

30

35

40

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

20

34

20

35

20

36

20

37

20

38

20

39

20

40

20

41

20

42

20

43

20

44

20

45

20

46

20

47

20

48

20

49

20

50

20

51

20

52

20

53

Bill

ion

s

Capital Interest Cumulative Nominal Capital Total

R billion

1. Annual cash flows from 2044 to 2052 are below R50 million

• Eskom has to be responsible in managing its debt profile

• The R255 billion of borrowings at 31 March 2014 will be repaid by 2052

1

Page 67: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

6.46

16.20

10.96

3.00

Mar-12 Mar-13 Mar-14 Investmentgradetarget

Debt maturity and leverage Ensuring Eskom’s financial sustainability

Gross debt / EBITDA1 ratio Debt service cover ratio

3.27

0.22

0.77

Mar-12 Mar-13 Mar-14

Interest cover ratio2 FFO as a % of gross debt

15.15

8.04 9.73

20.00

Mar-12 Mar-13 Mar-14 Investmentgradetarget

1. Earnings before interest, taxation, depreciation and amoritisation

2. In 2012/13 the effect of the remeasurement of the government loan (income of R17.3 billion) impacted the interest cover ratio

3.50

2.01

1.21

2.50

Mar-12 Mar-13 Mar-14 Target

Page 68: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Eskom credit ratings as at 31 March 2014 Ensuring Eskom’s financial sustainability

Rating Standard & Poor’s Moody’s Fitch

RSA government

Foreign currency BBB1 Baa1 BBB

Local currency A-1 Baa1 BBB+

Outlook Negative Negative Stable2

Eskom Holdings SOC Limited

Foreign currency BBB4 Baa3 -

Local currency BBB4 Baa3 BBB+

Standalone b- b1 B

Outlook Negative4 Negative Stable3

Action date 14 Oct 2013 19 Jul 2013 11 Jan 2013

Affirmation date 14 Oct 2013 19 Jul 2013 12 Dec 2013

1. On 13 June 2014, Standard & Poor’s downgraded the sovereign foreign currency and local currency ratings (from BBB to BBB- and from A- to

BBB+ respectively). This is expected to result in an adjustment to the Eskom headline and standalone credit ratings

2. On 12 June 2014, Fitch revised the sovereign outlook to “negative”, which is expected to result in an adjustment to the Eskom headline and

standalone credit ratings

3. On 18 June 2014, Fitch affirmed Eskom’s BBB+ rating, but revised the outlook to “negative”

4. On 20 June 2014, Standard & Poor’s downgraded the foreign and local currency ratings from BBB to BBB-, and also put Eskom on CreditWatch

As a significant portion of Eskom’s debt is guaranteed by government, its headline

credit rating has been uplifted, but remains closely linked to that of the sovereign

Page 69: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Financing

33 616

44 142

5 748

(55 835)

(1 372)

(8 014)

(9 070) (159)

10 620

19 676

31 Mar 2013cash and cash

equivalents

Cash generatedby operations

Capexexpenditure (incl

future fuel)

Other investing Debt raised Debt repaid Net interestrepayments

Investment insecurities

Otherfinancingactivities

31 Mar 2014cash and cash

equivalents

Summary of cash flows Ensuring Eskom’s financial sustainability

Operations Investing

R million

Page 70: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Appropriate return on assets Ensuring Eskom’s financial sustainability

• Eskom requires a rate of return on

assets that will enable it to maintain

and replace the current asset base

• An appropriate rate of return on assets

is a key building block towards cost-

reflective tariffs

• Ideally, the rate of return on assets

should at least equal the cost of capital

• The pre-tax real rate of return on

assets was negative 0.53% compared

to the pre-tax real cost of capital of

7.65%

• Continuing with inadequate returns will

result in a further erosion of Eskom’s

financial position

• It is therefore imperative that the price

of electricity migrates to cost-reflectivity

1. Rate of return on assets calculated on closing balance of assets

(revalued using the depreciated replacement cost method) and

liabilities, excluding financial assets and liabilities

(0.47%) (0.53%)

7.65% 7.65%

Mar-2013 Mar-2014

Rate of return on assets Cost of capital

Rate of return on assets1 vs cost of capital

(pre-tax real rates)

%

Page 71: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

• Critical for Eskom is ensuring a balance between security of supply, asset creation, financial sustainability and environmental compliance and to responsibly manage the trade-offs that are required

• Revenue shortfall of R225 billion created by the MYPD 3 determination has serious consequences for Eskom’s business and future sustainability

• Key to success is to ensure an appropriate return on assets in the long term and to obtain adequate funding to address liquidity in the short term

• Eskom’s response to the liquidity challenges and long-term financial sustainability includes: − Investigating alternative sources of funding, including possible equity or quasi-equity

instruments − Exploring additional borrowing options, although the ability to borrow sufficient funds at

affordable levels is constrained by credit ratings. Given the recent sovereign ratings downgrade, Eskom is at risk of a further downgrade

− Reprioritisation of capital expenditure within the R251 billion budget. However, this could negatively affect operational sustainability and impact security of supply

− Applied to NERSA for a regulatory clearing account (RCA) adjustment, to claw back prudently incurred expenditure and lost revenue due to lower demand than forecast in the MYPD 2 application

− Business productivity programme launched to reduce cost, increase productivity and enhance efficiencies

• Financial sustainability cannot be achieved through efficiencies and savings alone – cost-reflective tariffs remain a key imperative

Financial sustainability Ensuring Eskom’s financial sustainability

Page 72: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Awards and recognition

72

Page 73: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

73

Awards and recognition

Eskom brand

Sunday Times Eskom was voted as the “Most desired company to work for” by the

Sunday Times newspaper. Awards were also received in the

categories “Community Upliftment” (second place), and “Top

company that does the most to look after the environment and natural

resources” (second place)

Operation Khanyisa The campaign received an Orchid from Independent Newspapers for

its innovative approach to public sector advertising, as well as a

Loerie advertising award in the Ubuntu category

The Star Award from Crime Line was received for the second year

13th Annual Oliver

Empowerment

awards

Eskom was the recipient of two accolades at the event held on 25

April 2014, namely the Socio-economic Development award for the

Eskom Development Foundation contractor academy, and the

Enterprise and Supplier Development award for Group Commercial –

supplier development and localisation

Mail & Guardian

newspaper

Eskom was voted as the Top Engineering Company by engineering

students, and the second best by MBA and Professionals

Finweek Eskom was named the fourth most popular brand in South Africa

Page 74: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

74

Awards and recognition

Our Guardians

Institute of Personnel

Management

Eskom’s human resources function was announced as the winner in the Human

Resources Team of the Year category. The Acting chief Advisor for Strategy at

the EAL won the HR Practitioner of the year award for her outstanding

contribution to the field

SA Human Rights

Commission

Eskom was awarded the Golden Key Award for best practice by a public

institution

Stars of Africa Eskom received the Stars of Africa 2013 Gold award in the Eskom Contractor

Academy: Incubation category

African Utility Week Dr Steve Lennon received a lifetime achievement award for his outstanding

contribution to the utilities industry at the African Utility Week’s Industry awards

Visionary CIO of the

Year

Eskom chief information officer (CIO), Sal Laher, was the winner of the

prestigious Visionary CIO of the Year award. The award recognises an

executive in all industries across South Africa who has demonstrated vision and

leadership in using technology to support and grow business

Boss of the Year Ayanda Nakedi, Senior General Manager of the Renewables business unit was

awarded the 2013 Boss of the Year award

General Counsel of the

Year

At the African Legal awards, Willie du Plessis, General Manager (Legal

Specialist), was awarded the General Counsel of the Year award

Page 75: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

75

Awards and recognition

Integrated reporting

Nkonki SOC Integrated Reporting In June 2013, Eskom emerged as the overall

winner of the Nkonki SOC Integrated Report

Awards 2013. Eskom also scooped several

other awards in categories related to

governance and the application of King III

Investment Analysts Society of Southern

Africa

At the 28th annual Investment Analyst’s

Society awards, Eskom emerged as the

winner for the best presentation in the

market cap above R30 billion category

Association of Chartered Certified

Accountants

Eskom’s integrated report was the winner in

the resources category

Ernst & Young Excellence in Integrated

Reporting

Eskom was adjudged an “Excellent

Integrated Reporter” at the Ernst & Young

2013 inaugural Excellence in Integrated

Reporting Awards event

Chartered Secretaries Southern Africa and

JSE Limited Annual Report award

In November 2013, Eskom emerged as the

joint winner, alongside Transnet, in the state

entities category

Page 76: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

76

Awards and recognition

Processes

Institute of Management Consultants South

Africa

Eskom’s Group IT division received the

award for the SAP project implementation

SAP AG Eskom achieved its independent SAP

Centre of Excellence accreditation from

SAP globally, with a score of 192 out of 200,

making it one of only four companies to

achieve this level of accreditation

Enterprise Mobility Forum Eskom won two Mobility awards – one for

best enterprise solution for Distribution’s

handheld solution for field workers and the

second for best return on investment for a

mobility solution

Sustainability

Department of Water Affairs Eskom was named as the runner-up in the

2013 Water Conservation and Water

Demand Management Sector awards

(mining, industry, power)

Page 77: Eskom Holdings SOC Limited · 2014. 7. 18. · This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or ... Dr

Thank you Please note: this slide may also be used as a chapter divider slide.

To duplicate this slide, you need to first select this slide, go to the “Insert” drop down menu and select “Duplicate slide”. The duplicated slide can then be dragged to the appropriate position within your presentation.