ES&H Status of Construction and Technical System Installations
description
Transcript of ES&H Status of Construction and Technical System Installations
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20081
SLAC National Accelerator Laboratory
ES&H Status of Construction and Technical System Installations
Mike Scharfenstein
Project ES&H Coordinator
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20082
SLAC National Accelerator Laboratory
Construction Safety
November 17, 2008 – Substantial Completion
146 Days without lost time incident - Major Milestone60 days w/o recordable – Major Milestone
Safety in GC managed work a disappointmentAggressive Management Steps
Weekly Senior Executive - Conference Calls & On-Site Meetings
Increased LCLS & TCCo field staff
Full-Time On-Site Nurse
Full time DOE field presence
Lessons Learned
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20083
SLAC National Accelerator Laboratory
TCCo Incident Distribution
0
2
4
6
8
10
12
1stQtr
2ndQtr
3rdQtr
4thQtr
5thQtr
6thQtr
7thQtr
8thQtr
Procedural
Injuries
Notices
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20084
SLAC National Accelerator Laboratory
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20085
SLAC National Accelerator Laboratory
Construction Development
Safety Stewardship Meeting – Weekly Analyze emerging issues
Define action items (R&R, Nurse, Mgt Walks)
LCLSModified staffing
UTR Safety Observation Training
TCCo Job Hazards Analysis Re-invigoration (WP&C)
LIFE Training
Bottom Line
Communicate to Hands-on Craft and Immediate Supervisors LCLS emphasis on safety.
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20086
SLAC National Accelerator Laboratory
Leading & Lagging Indicators
Lagging Indicators Incident/Injury
Indicator of Poor …
Opportunity to Learn Work Planning
Work Execution
Work Oversight
Field Work AssessmentsAssessed past performance
Developed Corrective Actions
ISM / WPC
Leading Indicators Lessons Learned from incidents lead to improvements
More oversight and involvement with work planning and execution
Added Field PersonnelSuperintendents
Lab UTRs
Added Occupational Safety Nurse
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20087
SLAC National Accelerator Laboratory
Lessons Learneda little more detail
APPLY ISEMS ! 7 Guiding Principles & 5 Core Functions
Good for All; staff and contractors
Work Planning & Control Contractor Selection
Needs to be thorough Meet the team / know the work
Recent jobs / EMR Work Planning & Control
Site Specific Safety Plan Detailed R2A2s
Personnel competencies, Know the work – including hazards, Perform the work w/I controls, Feedback & Improvement
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20088
SLAC National Accelerator Laboratory
Work Planning and Controla little more detail
SLAC has undertaken a lab-wide initiative to consistently assure that work is planned and controls identified before work is authorized to begin…
2006 downtime WP&C strategy
2007 LCLS begins dialog w/ NIF
2008 LCLS participating/driving process w/I Lab & w/ contractors
Lesson Learned - Active Participation in Oversight Be a part of the major work packages
Collaborate for success Firm and Fair
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 20089
SLAC National Accelerator Laboratory
Work Goals
Subcontracted Work Goals CF & Technical Systems Installation
APPLY Integrated Safety Management Direct subcontractor management Detailed work planning
The goal is to maintain exemplary safety record
GC managed Current performance acceptable
Maintain engagement of GC and subs <30 days of field work remaining area to watch = demobilization
The goal remains Zero future incidents
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 200810
SLAC National Accelerator Laboratory
Conclusion
Apply ISEM Work Planning & Control
Maintain CF & Technical System direct managed work performance
Continue close work with TCCo LCLS / Lab / SSO involvement
Past 6 months = acceptable performance
The goal remains Zero!
Mike Scharfenstein
CF Breakout - ESH [email protected]
12 November 200811
SLAC National Accelerator Laboratory
end of presentation