Public Workshop #3 PresentationJanuary 17, 2017
ERINSBROOK PARKMaster Plan
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
• Schedule / Recap
• Program Development
• Site Analysis
• Development Diagram
• Concepts
• Next Steps
AGENDA
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
Schedule / MilestonesERINSBROOK PARK MASTER PLAN
Project Schedule (rev. Dec. 13, 2016)
Meeting Task / Discussion Date Time LocationCPC #1 Introduction / Analysis / Program Development Thurs, Sept. 8, 2016 6:30 PM St. Francis / Cupertino
RoomPublic Workshop #1 Analysis / Site Walk / Initial Program Ideas Sat., Sept. 24, 2016 10:00 AM On-site / St. Francis /
Cupertino RoomDRT #1 Review analysis and input from CPC/Public Workshop Thurs, Oct. 20, 2016 10-11AM PRCR/RMB 609
CPC #2 Program Confirmation / Review Alternative Master Plan Concepts Tues., Oct. 25, 2016 6:30 PM St. Francis / Fellowship Hall
Public Workshop #2 Present Alternative Master Plan Concepts Thurs., Nov. 10, 2016 6:30 PM St. Francis / Cupertino Room
CPC #3 Review Draft Master Plan Tues., Dec. 13, 2016 6:30 PM St. Francis / Cupertino Room
Park Planning Review Draft Master Plan Wed., Dec. 14, 2016 1pm RMB 303
Development Services Review Draft Master Plan w/ staff (review city code implications) Mon., Dec. 19, 2016 11AM OEP Rm 701
DRT #2 Review Draft Master Plan and input received Thurs., Jan 5, 2017 10AM RMB 609
Public Workshop #3 Review Draft Master Plan Tues., Jan. 17, 2017 6:30 PM St. Francis / Cupertino Room
DRT #3 Review Draft Master Plan, Report, and input received from CPC #3 and public workshop #3 (email only)
Tues, Jan. 24, 2017 N/A Email to DRT
CPC #4 Present Final Draft Master Plan Tues., Feb 7, 2017 6:30 PM St. Francis / Cupertino Room
NWCAC Present Final Draft Master Plan Tues., Feb 14, 2017 7PM NW RPD Annex
PRGAB Present Final Draft Master Plan Thurs., March. 16, 2017
6PM TBD
PRGAB Action on Final Draft Master Plan Thurs., April 20, 2017 6PM TBD
City Council Present Final Master Plan Tues., May 2, 2017 1PM Council Chambers
LEGENDCPC : Citizen Planning CommitteeDRT : Design Review Team (City of Raleigh Parks, Rec, Cultural Resources staff)
Phas
e 2
Phas
e 3
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SITE WALK
ABOVE: Community members share information
RIGHT: Existing specimen trees are a focal point
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SITE WALK
LEFT: The meandering stream needs to be protected from erosion
RIGHT: Kids are naturally drawn to the stream that disects the site. Oppornity for education
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
VISION AND PROGRAM IDEAS
VISION PROGRAM• PLAYGROUND
• NATURAL PLAY
• DOG PARK
• TRAILS - PAVED
• NATURE TRAILS
• SPLASH PAD
• FITNESS STATIONS*
• EDUCATION - INTERPRETIVE (TREES,
MAPS, WETLANDS)
• SINGLE TRACK BIKE TRAILS 18”*
• COMMUNITY CENTER*
• ZIP LINE*
• PICKLEBALL COURT
• PUMP TRACK*
• TREE HOUSES
• QUIET SPACE
• ENCLOSED SPACE
• DISC GOLF*
• REST ROOM
• PICNIC
• SLEDDING HILL*
• OPEN SPACE / PLAY
• NATURE
• WALKABLE /
ACCESSIBLE
• EDUCATION
• FAMILY
• FITNESS
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SITE ANALYSIS
LEESVILLE RD
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
BRIGMORE CT
ERINSBROOK DR
ENGL
EHAR
DT D
R EX
PANS
ION
BELLARD CT
RESIDENTIAL
RESIDENTIAL
HOA PROPERTY
FIRE STATION
ERIN
SBRO
OK
DR
SITE ANALYSIS: EXISTING FEATURES
EXISTING TREES
CREEK LINE
50’ NEUSE RIVER BUFFER LINESITE BOUNDARY
PROPERTY BOUNDARIES
THOROUGHFARE DISTRICT BUFFER
FUTURE SIDEWALK EXISTING PUMP STATION
SLOPE > 8%
EXISITING FORMER HOME SITE
ERINSBROOK PARK
PINE STANDPROPOSED RIGHT OF WAY
50’
20’
• Slope >8%
• Thoroughfare District Buffer
• 50’ Stream Buffer
• Pine Stand
• Existing Specimen Trees
• Existing former home site requires
further investigation
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
DEVELOPMENT DIAGRAM
LEESVILLE RD
ERIN
SBRO
OK
DR
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
BRIGMORE CT
ERINSBROOK DR
ENGL
EHAR
DT D
R EX
PANS
ION
50’
20’
BELLARD CT
OPEN SPACE
NATURAL WOODS CONSERVATION
FUTURE GREENWAY
CONNECTION
RESIDENTIAL
RESIDENTIAL
FIRE STATION
WOODLAWNPROPERTY
OVERLOOK
OVERLOOK
PARKING
ACTIVITY SPACE
(SENSITIVE)
ACTIVITYSPACE(ACTIVE)
SITE ANALYSIS: EXISTING FEATURES
CREEK LINE
SITE BOUNDARY
PROPERTY BOUNDARIES
THOROUGHFARE DISTRICT BUFFERFUTURE SIDEWALK
EXISTING PUMP STATIONSLOPE > 8%
ERINSBROOK PARK
PROPOSED RIGHT OF WAYPOTENTIAL VEHICULAR ACCESSPOTENTIAL PEDESTRIAN ACCESS
• Parking / Active space on flat area to
North of site
• Overlook oportunities on high points
• Large conservation area for trails and
pathways
• Connection to Woodlawn
Neighborhood
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
• Consolidated entry / exit, right in / out
• Parking lot - 20+ spaces
• Combination rest room / shelter
• Elevated platforms - 4
• Splash pad
• Dog park - 34,500 sf
• Separated junior playground
• Multiple pedestrian loops
• Open space - 6,500 sf
• Educational boardwalk bridges - 2
• Paved path - 4,250 ft
• Natural trails - 1,500 ft
• Low impact stormwater treatment
CONCEPT A
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
CONCEPT B
• Separate entry / exit, right in / out
• Parking lot - 40+ spaces
• Combination rest room / shelter
• Hard court - Pickleball
• Tree houses - 4
• Overlook
• Open space - 30,000 sf
• Educational boardwalk bridge - 1
• Paved path - 3,750 ft
• Natural trails - 1,200 ft
• Stormwater treatment pond
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
CONCEPT C
• Separate entry / exit Englehardt Dr - full service, Leesville Rd - right in / out
• Parking lot - 40+ spaces
• Rest room separated from shelter
• Nature play near creek - 5 Tree houses
• Raised tree-top overlook
• No open space
• Educational boardwalk bridges - 1
• Paved path - 3,500 ft
• Natural trails - 1,200 ft
• Stormwater treatment pond
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
6
HOA PROPERTY(NOT INCLUDED IN
PROJECT)
POTENTIAL GREENWAY
CONNECTION
December 13, 2016
1. SHELTER2. REST ROOM3. WATER MISTERS4. DOG PARK5. PLATFORMS6. RAIN GARDEN7. NATURAL PLAYGROUND8. PLAYGROUND & SHADE SAIL9. OPEN SPACE10. PARKING LOT11. BOARDWALK12. OAK GROVE TRAIL13. OVERLOOK
LEGEND
A
A
C
C
B
B
11
7
3
4
5
5
5
8
9
10
12
11
13
11
2
DRAFT CONCEPT
• Right in- right out Parking lot. (48 spaces).
• Dog Park. (Approx. 1/2 acre).wo entry points. Double gate entry.
• Open Space. (Approx. 1/2 acre).
• Combination Restroom & Shelter. Close to playground on visual vantage point.
• Shelter. Overlooks open space. Located on visual axis to the arbor / overlook.
• Overlook & Arbor. (Overlook approx. 7’ high). Looks over rain garden and flowering trees.
• Traditional playground with shade sail. (Approx. 3,600 sf). Close to restroom and shelter.
• Natural Play area. (Approx. 6,300 sf).
• Water Misters. (Approx. 2,000 sf).
• Pathway loops. (Central Loop is approx. 1/3 mile). Path network is only fully accessible from parking lot to overlook. Overlook to creek follows natural topography.
• Boardwalks. (2). Opportunity to educate about stream ecology.
• Platforms. (3). Hang out spaces, raised overlooks, a place to get off the walking path and be surrounded by the existing woodland trees.
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SECTION A - Upper ParkNE - SW
SECTION B - Upper ParkNW - SE
SECTION C - Lower ParkNW - SE
RALEIGH, NORTH CAROLINA
ERINSBROOK PARK
10’ WALK
STREAM
PLATFORM
PLATFORM24” OAK24” POP32” BEECH
10’ WALK
10’ WALK
AA
B B
C
C
470
490
450
460
480
440
480
500
460
490
510
470
500
480
510
490
EXISTING WOODLAND 50’ STREAM BUFFER
20’ PERIMETER
BUFFER
RAIN GARDENEXISTING WOODLAND
FLOWERINGTREES
OVERLOOK / ARBOR NATURAL PLAY AREA OPEN SPACE
December 13, 2016
8’ WALK
10’ WALK
10’ WALK OVERLOOKWATER MISTERSPLAYGROUND WITH SHADE STRUCTUREPLANTINGTO DOG PARK NATURAL PLAY AREA
FLOWERINGTREES RESTROOM / SHELTER
BUILDING
DRAFT CONCEPT
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SECTION A - Upper ParkNE - SW
SECTION B - Upper ParkNW - SE
SECTION C - Lower ParkNW - SE
RALEIGH, NORTH CAROLINA
ERINSBROOK PARK
10’ WALK
STREAM
PLATFORM
PLATFORM24” OAK24” POP32” BEECH
10’ WALK
10’ WALK
AA
B B
C
C
470
490
450
460
480
440
480
500
460
490
510
470
500
480
510
490
EXISTING WOODLAND 50’ STREAM BUFFER
20’ PERIMETER
BUFFER
RAIN GARDENEXISTING WOODLAND
FLOWERINGTREES
OVERLOOK / ARBOR NATURAL PLAY AREA OPEN SPACE
December 13, 2016
8’ WALK
10’ WALK
10’ WALK OVERLOOKWATER MISTERSPLAYGROUND WITH SHADE STRUCTUREPLANTINGTO DOG PARK NATURAL PLAY AREA
FLOWERINGTREES RESTROOM / SHELTER
BUILDING
DRAFT CONCEPT
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
SECTION A - Upper ParkNE - SW
SECTION B - Upper ParkNW - SE
SECTION C - Lower ParkNW - SE
RALEIGH, NORTH CAROLINA
ERINSBROOK PARK
10’ WALK
STREAM
PLATFORM
PLATFORM24” OAK24” POP32” BEECH
10’ WALK
10’ WALK
AA
B B
C
C
470
490
450
460
480
440
480
500
460
490
510
470
500
480
510
490
EXISTING WOODLAND 50’ STREAM BUFFER
20’ PERIMETER
BUFFER
RAIN GARDENEXISTING WOODLAND
FLOWERINGTREES
OVERLOOK / ARBOR NATURAL PLAY AREA OPEN SPACE
December 13, 2016
8’ WALK
10’ WALK
10’ WALK OVERLOOKWATER MISTERSPLAYGROUND WITH SHADE STRUCTUREPLANTINGTO DOG PARK NATURAL PLAY AREA
FLOWERINGTREES RESTROOM / SHELTER
BUILDING
DRAFT CONCEPT
Public Workshop #3 Presentation | January 17, 2017
ERINSBROOK PARKMaster Plan
Next Steps
CPC #4
Present Final Draft Master Plan
Tues., February 7, 2017
6:30 PM, St. Francis / Cupertino Room
NW CAC
Present Final Draft Master Plan
Tues., February 14, 2017
7 PM, NW Raleigh Police Annex