Re-sequenced Wastewater & Well Permitting Options Wake County Environmental Services May 20, 2020

Transcript of Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental...

Page 1: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

Re-sequenced Wastewater&

Well Permitting Options

Wake County Environmental Services

May 20, 2020

Page 2: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

2

❖ Overview of Permitting Timeline

❖ Resequencing the Wastewater Permit

❖ Permitting Menu

❖ Choosing the Right Permit

❖ Strategies to support streamlined permit approval

❖ Communication

Presentation Outline

Page 3: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

3

Wastewater and Building Permit applications submitted together

Application includes final building footprint

Issuance of the Building Permit dependent upon Wastewater permit timeline:

o Site survey

o Soil evaluation

o System layout and design

Current Permit Process

Page 4: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

4

Current Permitting Timeline

WW Site Evaluation and CA Permit

Issuance

27 days

Building

Permit

Issuance

Building Permit Review

10 days maximum

WW Application

&

Building Permit

Final Application

CA issued Building

Permit

issued

Page 5: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

5

Wastewater Application submitted in advance of Final Building Application

Building Envelope encompasses any potential building footprint

Building Footprint will be compared to approved Building Envelope

Re-sequenced Permit Process

Building Envelope

Property Boundary

Page 6: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

6

Re-sequenced Permit Process

WW Site Evaluation Process

(initiated with Building Envelope)

60+ daysWW Permit Issuance

10 days maximum

Building Permit

Final Application

WW Application &

Building Permit

Preliminary Check

CA Issued

Building Permit

Issued

IP Issued

Building Permit Issuance

10 days maximum

Page 7: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

Permitting OptionsChoosing the Right Permit

7

Page 8: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

8

Choosing the Right Wastewater/Well Permit

Engineered Option Permit

Licensed Soil Scientist

Evaluation

Subdivision Blitz

Well PermitApprove Use

of Existing Well

SL 2020-3

Option Permit

for COVID-19

Engineered Flow

Reduction

Page 9: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

9

Engineered Option Permit

Owner can plan wastewater permitting and construction schedule independently.

County acts within 15 business days to issue construction approval.

Benefits

Owner must hire engineer for inspections, future modifications, upgrades or repairs

No County QA/QC processDrawbacks

Engineered Option- New

Engineered Option- Expansion

Engineered Option- Addition

Engineered Option- Existing

Applicable Permits

Page 10: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

10

SL 2020-3 Option Permit for COVID-19*

Owner can plan wastewater permitting and construction schedule independently.

County acts within 15 business days to issue construction approval.

Benefits

Owner must hire certified LSS for inspections, future modifications, upgrades or repairs

No County QA/QC processDrawbacks

LSS SL 2020-3 Option – Expansion

LSS SL 2020-3 Option – Addition

LSS SL 2020-3 Option – Existing

LSS SL 2020-3 Option – New

Applicable Permits

*This permit option is available until August 1, 2020

Page 11: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

11

Engineered Flow Reduction Permit

Flow reduction achieved through engineering design utilizing low-flow fixtures/technologies.

Allows up to 25% less reduction in flow and drainfield space.

Benefits

Plumbing fixtures required to be maintained

Deviation from permitted fixtures may cause premature malfunction.

Drawbacks

Residential Permit-New

Residential Permit-Expansion

Residential Permit- Addition

Applicable Permits

Page 12: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

12

Licensed Soil Scientist (LSS) Evaluation

LSS delineates soil areas for initial and repair systems

Environmental Services review limited to setbacksBenefits

NoneDrawbacks

Residential Permit-New

Residential Permit-Expansion

Residential Permit- Addition

Residential Permit- Existing

Applicable Permits

Page 13: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

13

Subdivision Blitz

Multiple lots reviewed by small team of permitting staff

LSS on site to assist with challenging soil conditionsBenefits

NoneDrawbacks

Residential Permit-NewApplicable

Permits

Page 14: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

14

Permit for New Well

Lower-cost water supply option for development outside of municipal limitsBenefits

Time associated with water quality testing

1 in 5 wells in eastern half of county will require radiological treatment

Well owner responsible for future testing and maintenance

Drawbacks

Permit for New WellApplicable

Permits

Page 15: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

15

Approve Use of Existing Well

Avoid cost of drilling new well

Lower-cost water supply option for development outside of municipal limits

Benefits

Time associated with water quality testing

1 in 5 wells in eastern half of county will require radiological treatment

Older wells may require repairs.

Drawbacks

Approve Existing Well for New ConstructionApplicable Permits

Page 16: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

16

✓Apply as early as possible

✓Prepare site for inspection

✓Ensure fees are paid

✓Private wells:

o Install well as early as possible

o Request wellhead inspection when

well is fully operational

Streamlining the Permit Process

Page 17: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

17

❖ Re-sequenced Permitting

Process is now available

❖ Many permit options

❖ Apply as early as

possible

Take Aways

Page 18: Environmental Services Permit Resequencing & Other Permitting …€¦ · Wake County Environmental Services May 20, 2020. 2 Overview of Permitting Timeline Resequencing the Wastewater

18

Questions

Environmental Service Support

919-856-7400

Permit Portal

Scheduling Inspections

Fees

Wastewater Information Specialist

919-856-7434

[email protected]

Design Questions

Setbacks

Operation & Maintenance

Contact Us!