Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water &...
Transcript of Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water &...
![Page 1: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/1.jpg)
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environmental Monitoring Report
Project Number 37381-013 Loan Numbers 2477-SRI (SF)/2977 SRI (SF) and Grant Numbers 0129-SRI(SF)/0130-SRI Semestral Report July to December 2016
SRI : Dry Zone Urban Water and Sanitation Project
(DZUW&SP) – Per Aru Reservoir and Surface Water
Intake
Prepared by DZUW&SP Project Management Unit of National Water Supply & Drainage
Board(NWS&DB), for the Ministry of City Development and Water Supply, Sri Lanka and the
Asian Development Bank.
![Page 2: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/2.jpg)
ADB ASSISTED DRY ZONE URBAN WATER AND SANITATION PROJECT
Environmental
Management and
Monitoring Report
Per Aru Reservoir and Surface Water
IntakeFor the period from July to December 2016
Prepared by
SMEC International in association with Ocyana Consultants and Ceywater Consultants (Pvt) Ltd
On behalf of
Project Co-ordination Cell of the
National Water Supply And Drainage Board
Ministry of City Planning and Water Supply
Submitted to
Sri Lanka Resident Mission,
Asian Development Bank,
Colombo.
![Page 3: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/3.jpg)
2
![Page 4: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/4.jpg)
3
Contents
LIST OF FIGURES.............................................................................................................................................3
LIST OF TABLES ...............................................................................................................................................3
LIST OF ABBREVIATIONS ..............................................................................................................................4
1. Introduction..................................................................................................................................................6
1.1. Contractors’, Supervision Consultants’ and Clients’ role in environmental safeguards
compliance ......................................................................................................................................................7
2. Monitoring of environmental parameters ................................................................................................8
3. Key construction activities during the period..........................................................................................8
4. Environmental impacts, mitigation measures taken at site and monitoring ....................................11
5. Examples of good practices, noncompliance notices and corrective plans ....................................24
6. Public complaints .....................................................................................................................................26
7. Conclusion and further actions...............................................................................................................26
LIST OF FIGURES
Figure 1.1. Location of Per Aru reservoir and surface water intake
Figure 5.1. Constructed fish ladder
Figure 5.2 Maintenance work being carried out at Cheddikulam
Figure 5.3 Taking plants from nursery for vacancy planting
LIST OF TABLES
Table 2.1. Monthly total rainfall and No. of rainy days
Table 4.1. Activities carried out during the reporting period, related environmental concerns,
mitigation measures, effectiveness and any further action needed
![Page 5: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/5.jpg)
4
LIST OF ABBREVIATIONS
ADB Asian Development Bank
DP Displaced Person
DPR Daily Progress Report
DZUWSP Dry Zone Urban Water & Sanitation Project
EA Environmental Assessment
EIA Environmental Impact Assessment
EMS Environmental Method Statement
EMP Environmental Management Plan
EMoP Environmental Monitoring Plan
EMR Environment management and Monitoring Report
ES Environmental Specialist
EPL Environmental Protection License
GoSL Government of Sri Lanka
GRC Grievance Redress Committee
IEE Initial Environmental Examination
IEER Initial Environmental Examination Report
ISO International Organization for Standardization
MSW Municipal Solid Waste
NEA National Environmental Act
NBRO National Building Research Organization
PPE Personal Protection Equipment
PPTA Project Preparatory Technical Assistance
PPV Peak Particle Velocity
SC Supervision Consultant
SLS Sri Lanka Standards
STC State Timber Corporation
VET Vehicle Emission Test
![Page 6: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/6.jpg)
Figure 1.1. Location of Per Aru reservoir and surface water intake
Flow direction
![Page 7: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/7.jpg)
Environmental Management and Monitoring Report of Per Aru Reservoir and
Surface Water Intake
July to December 2016
1. Introduction
North and north western region of Sri Lanka is classified as part of the dry zone of the country. This
zone is benefited mainly by the second inter monsoon and north east monsoon rains which spread
from October to early February. The remaining period of the year is mostly dry in climate. With ending
of a nearly three decade civil conflict the Government of Sri Lanka (GoSL) in year 2009 identified the
need of supplying safe drinking water and improving sanitation needs of people living in urban and
peri-urban towns located in north and north-western regions of the country.
Vavuniya town and its suburbs located between the north and central part of the country has now
become a hub in socio-economic development in northern region. Therefore Vavuniya is one of the
towns which required urgent development in the areas of water and sanitation.
The GoSL secured funds from the Asian Development Bank (ADB) in year 2009 to initiate a project
that would supply safe drinking water and to provide improved sanitary facilities to public living in north
and north west dry zone regions of the country. The project was named as “Dry Zone Urban Water
and Sanitation Project” or DZUWSP. The project is financed under ADB loans No. 2477 and 2977 with
a total amount of US $ 163 million and grant No G129. The project which is expected to complete in
year 2016 is executed by Ministry of City Planning and Water Supply and National Water Supply and
Drainage Board (NWS & DB) is implementing the project.
Vavuniya district was also considered under this project, where the need of constructing a new surface
water reservoir and a water treatment plant was agreed. Per Aru reservoir and surface water intake is
one of the subproject in Vavuniya district under DZUWSP.
Under this subproject an earth dam having a maximum height of 10 m with a length of about 3 km was
designed to be constructed across Per Aru River. The reservoir is to store and pump raw water to the
water treatment plant for purification, storage and distribution.
Construction of this reservoir was considered to be a prescribed project under the National
Environmental Act (NEA) requiring and Environmental Impact Assessment (EIA). The project has also
been categorized as “Category A” under ADB Safeguards Policy Statement, 2009 (SPS). An EIA
report was compiled in November 2012 which included sections “Screening of Potential Impacts” and
“Mitigation Measures”. With completion of the EIA and obtaining necessary approvals, land clearing
and civil works of dam and intake structure commenced in July 2013.
An Environmental Management Plan (EMP) was developed based on environmental good practices
discussed under the EIA report. An Environmental Monitoring Plan (EMoP) was also prepared
![Page 8: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/8.jpg)
7
including information on environmental parameters to be monitored, Location, time and frequency,
cost for sampling and stage of subproject on which the monitoring should be conducted. The EMoP
is considered to be a useful tool to monitor the implementation of mitigation measures and EMP.
Under safeguards requirements of ADB’s for the project, it is required to prepare an Environment
management and Monitoring Report (EMR) on a semi-annual basis. This report is developed to satisfy
the above requirement. Construction works of the reservoir and intake structure of Per Aru reservoir
was completed in September, 2016. However the report is prepared for the time period from July to
December 2016.
1.1. Contractors’, Supervision Consultants’ and Clients’ role in
environmental safeguards compliance
Construction of the dam and reservoir was carried out by BMG – K.D.A. Weerasinghe & Co. (Pvt) Ltd
(a joint venture). During the construction period the contractor was responsible to implement the
mitigation measures listed under EMP and conduct environment parameter monitoring based on the
EMoP.
A Project Co-ordination Cell (PCC) headed by the Project Director was setup within NWS & DB
(project implementing agency) with overall responsibility implementation of EMP and EMoP by the
contractor. The Supervision Consultant/ Engineer {(SC), SMEC International in association with
Ocyana Consultants and Ceywater Consultants (Pvt) Ltd} working under the PCC directly supervise/
monitor the contractor in implementing the EMP.
The contractor has developed an Environmental Method Statement (EMS) which has been reviewed
and approved by SC. The SC monitor any critical construction activity on a daily basis, any non-
compliance situations and rectification measures/ instructions to contractor are recorded in Daily
Progress Reports (DPRs), engineers’ log books and monitoring checklists.
Monitoring of air quality, water quality, noise and vibration levels are done on a quarterly basis by the
contractor, while compliance indicators such as availability of Vehicle Emission Test certificates are
monitored by the SC at a lesser frequency. A public complaint register is also maintained by the
contractor under the supervision of SC. Any complaint received from public is expected to attend by
the contractor in consultation with NWS & DB and SC.
An Environmental Specialist (ES) has been appointed by the SC on an intermittent basis, to look into
the environmental safeguards aspects of the overall project. Due to the intermittent nature of the
assignment the ES has developed a mechanism to communicate between Team Leader, Deputy
Team leaders and Resident Engineers of SC to assist them in resolving any environmental issue
arising in each subproject. However the ES conducts site visits at least once a month to record the
level of compliance by the contractor and instructions are given to improve on any non-compliance
situation/s.
![Page 9: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/9.jpg)
8
Status of environmental safeguards compliance with respect to Per Aru sub-project in Vavuniya for
the time period from July to December 2016 is presented through this report. The report is based on
actual field observations made during the site visits; Daily Progress Reports (DPRs), engineers’ log
books, monitoring checklists and other available records/ approvals at site.
2. Monitoring of environmental parameters
As per the contract agreement the contractor has to conduct environmental parameter monitoring on
a quarterly basis. As the construction works were completed by September 2016 no measurements
on selected environment parameters were taken during this reporting period. Monthly total rainfall and
the number of rainy days from July to December 2016 is presented in below table.
Table 2.1. Monthly total rainfall and No. of rainy days
Month Per Aru reservoir - Vavuniya
No. of rainy days Total rainfall (mm)
July 04 10.8
August 01 3.6
September 00 0.0
October 05 19.4
November 17 140.0
December 10 72.4
Source: Daily rainfall records at Per Aru site
Compared to the first six months of the year the project area received less rain during the last six
months (with a highest of 140.0 mm in November). Compared to the last six months in year 2015
which yielded a total rainfall of around 900 mm the last six of year 2016 has received less rains (a total
of only around 240 mm). Therefore the last six months of the year could be considered as relatively
dry.
3. Key construction activities during the periodBeijing Municipal Construction Group Co. Ltd & KDA Weerasinghe Joint Venture, who is the contractor
was issued the letter of acceptance on 30th May 2013. With signing of contract agreement the
contractor commenced work in August 2013. The key construction activities related to Per Aru
reservoir are clearing of jungle and vegetation along dam axis, tank bed and spillway tail canal;
establishing engineer’s site facilities and mobile office; construction of causeway; construction of
access and by roads; construction of Bentonite cut-off wall; construction of spillway structure including
the fish pass, spillway tail and approach canals, construction of the earth dam and construction of
Hindu Kovil. As per the recommendations of EIAR a reforestation and forest enrichment planting
program and a species rescue and translocation program were also carried out in parallel to the
construction works of the reservoir. The construction work of the reservoir is now completed (in
September, 2016) and the reservoir is now being filled with water. This section of the report
summarizes the key activities which were carried out during the reporting period.
![Page 10: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/10.jpg)
9
1. Jungle clearing in dam axis, tank bed and spillway tail canal
Clearing of vegetation (jungle) in dam axis and tail canal is 100% completed. All trees with timber
value was marked and removed from the site by State Timber Corporation. A total of around 1,600
such valuable trees were removed during this operation. Clearing of shrub jungle in tank bed
inundating area was completed by August 2016. Removal of tank bed area vegetation was carried out
by small scale contractors and bushes/ shrubs were also taken by villagers around the project area.
As stated in the EMR for January – June 2016 the final phase of translocation of fauna & flora in tank
bed area commenced and field works completed in month of October 2015. Final report of this bio
diversity rescue and species translocation was received by consultant in March 2016.
2. Establishing engineer’s site facilities and mobile office
Engineer’s site facilities have been established. Mobile office was operational from the location where
it was re-established during November 2015.
3. Construction of causeway
Construction of left and right bank abutments, wing walls and top slab has been completed. Back filling
works have also completed. Construction of approaching ramps with side drains on left and right banks
of stream were completed in August 2016. Improvement and protection works identified is stream
banks of upstream and downstream was identified as extra works were also completed during this
period. Trees identified in stream stretch obstructing the water flow in upstream and downstream
causeway also completed by Timber Cooperation.
4. Construction of access, by roads and inspection road
Key works in the access road and by road included laying of sub base, construction of culverts and
providing top wearing surface. Sub grade work in by road has been completed by September 2016.
Providing gravel wearing surface to some parts of access road was not completed during the reporting
period due to the issue of obtaining gravel permits. Drainage crossings, formation and gravelling of
bund inspection road was also completed by September 2016.
5. Construction of Bentonite cut-off wall
All construction works related to Bentonite cut-off wall has been completed in September 2015, hence
no activity was carried out with respect to construction of Bentonite cut-off wall during reporting period.
6. Reforestation and forest enrichment planting
A reforestation and forest enrichment planting program was developed in order to compensate the
loss of vegetation due to construction of the reservoir. Locations selected for planting and forest
enrichment included; 1. Around the reservoir (buffer zone above Full Supply Level (FSL)), Down
Stream (DS) and high land inside the reservoir; 2. Upper catchment at Chemamadu and 3. Upper
![Page 11: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/11.jpg)
10
catchment at Cheddikulam. Contractor maintained two plant nurseries for this activity (one at project
site office and other at Pampaimadhu).
All original planting works of stage 1 related to reforestation and enrichment forest planting in
Chemamadu and Cheddikulam has been completed substantially by end December 2015. Up to the
end of this reporting period, around 155,000 plants have been planted as stage 2 and another 140,000
plants have been planted as stage 1. However only maintenance and vacancy planting was carried
out during the reporting period.
7. Construction of spillway structure, spillway tail and approach structures including the
fish pass
Spillway structure construction was completed during the reporting period which included fixing of
radial gates and operation system and protection walls. The fish pass which commenced construction
during the first quarter of year 2016 was also completed.
8. Construction of the dam
Jungle clearing, stripping and removal top layer in dam axis, core trench excavation has already
completed. With completion of formation of earthen embankment the construction of bund top road
with gravel base course was completed during this reporting period. Turf sods placing along selected
bund sections were also completed during the reporting period. As stated in the previous report the
Hindu Kovil was constructed and handed over to the Kovil Committee in June 2016 by NWS&DB.
![Page 12: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/12.jpg)
11
4. Environmental impacts, mitigation measures taken at site and monitoring
Construction of the reservoir was completed during this reporting period and no any activity that could cause significant adverse impact
on physical, ecological and social environments were not carried out. Most of the activities carried out during this period such as turf
sods placing, maintenance and vacancy planting, construction of the fish pass were beneficial to the environment. However measures
that were carried out to avoid, minimize or mitigate any adverse impacts was in line with the mitigation measures listed in the EIA
report. Effectiveness of mitigation measures have been monitored and recorded by the SC. In cases where further actions were needed
the SC continued to advise the contractor. Table 4.1 below summarizes the activities carried during the reporting period, their impacts/
concerns to the environment, mitigation measures suggested in the EIA.
Table 4.1. Activities carried out during the reporting period, related environmental concerns, mitigation measures, effectiveness and
any further action needed
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Clearing of land andvegetation.
Environmental stability(i.e. loss and damage tovegetation, loss ofhabitats).
Implementing ofcompensatoryafforestation and forestenrichment programs.
Implementingrecommendations ofthe additionalecological survey.
Land clearing operationfor dam axis, reservoirinundation area andspillway canal havebeen completed.
Contractor continued tomaintain the plants atfield and carried outvacancy planting wherenecessary.
Removal oflogs anddebris/ biweekly
Removal of timer andother vegetation inareas of dam axis andreservoir bed has beencompleted.
Replanting and forestenrichment plantinghas been carried out inthree areas identified.A program needs to beformulated to maintainthese plated areas(after handing over bycontractor).
Maintenance of siteoffice, yard andlabour camps.
Accumulation anddisposal of solid andkitchen waste.
Solid waste andsewage shall bemanaged according to
Waste collection binshave been provided atsite offices, yards andworker camps.
Protectionmeasures thatdisposed wastewill not be: (1)
Housekeepingactivities and sitecleaning activitiescontinued to be in place
![Page 13: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/13.jpg)
12
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Accumulation of vehicle/equipment service andmaintenance waste anddisposal.
the national and localregulations.
Used oil and lubricantsshall be reused orremoved from the site infull compliance withnational and localregulations.
Waste oil must not beburned.
Open burning of wasteshall not be allowed.
Dip trays and a canopyhave been provided atfuel storage and pump.
Used oil and lubricantsare removed from site.
Fuel depot, laboratoryand material storeshave been provided withfire extinguishers andsand baskets.
No waste including usedoil is burned at site.
Servicing and repairs ofall construction vehiclesand equipment done
washed awayto the rivercourse, (2)nuisance to thepublic, (3) leftalone at thesite/ weeklyStoragefacilities,methods andfire protectionmeasures/monthly.
Collectingarrangement ofall discarded&usedlubricants &greases. Safedisposal orreuse/ sell/monthly.
during the reportingperiod.
Contractor hascontinued to maintainthe dip tray and canopyabove the fuel pumpingpoint.
![Page 14: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/14.jpg)
13
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
only at approved servicestations and repaircenters outside theproject site.
Proper warningsignboards and noticesare placed at site,offices.
Maintenance of yardand fuel storage
Contamination of soil,surface and groundwater by accidentalchemical spills.
Instruct and trainworkforce in the storageand handling ofmaterials andchemicals that canpotentially cause soilcontamination.
Accidentally spills onopen ground includingthe top soil 2 cm of aycontaminated soil shallbe disposed of aschemical waste to adisposal site acceptableto the local authority/community.
A dip tray has been keptat the fuel pumpingdeport.
All chemicals have beenplaced in an enclosedstructure (stores) withan impervious floor androofing.
Any running repair ofvehicles at site whereremoval of oil is requiredis done with dip trays tocollect oil.
Incidents of anyoil/ chemicalspills/ monthly.
Contractor hasmaintained the dip trayat the fuel pumpingdepot. No reports ofaccidental chemicalspills were recorded.
Maintenance oflabour camps.
To ensure that theoperation of work campsdoes not adverselyaffect the surroundingenvironment andresidents in the area.
Confirm location of workcamps in consultationwith PMU and localauthorities. Locationsubject to approval byPMU. If possible,
Use of local labourers toreduce the number oflabour camps.
No worker camp locatedwithin settlement area.
Incidences ofovercrowdedbillets/monthly.
No worker camp wasobserved withovercrowdedlabourers.
![Page 15: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/15.jpg)
14
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
camps shall not belocated nearsettlements or neardrinking water supplyintakes.
Water and sanitaryfacilities shall beprovided for workersand employees.
Portable lavatories or atleast pit latrines will beinstalled and opendefecation shall bediscouraged andprevented by keepinglavatory facilities cleanat all times.
The contractor shalldocument that all liquidand solid hazardousand non-hazardouswaste are separated,collected and disposedof according to thegiven requirements andregulations.
Water and sanitaryfacilities are provided toworker camps.
The labour camps areprovided with temporarytoilets (water seal type)and water.
Availability oftoilet facilitiesand water atworker camps/monthly.
No. of traininggiven toworkers onhealth andsafety issues/monthly.
Adequate toiletfacilities have beenprovided at workercamp sites withsufficient quantities ofwater for drinking andsanitary requirements.
Mobilization of workforce at site
Hazardous workingconditions to work force.
Submit safety plan onemonth beforecommencement ofconstruction.
All workers wereinstructed to use suitsavoiding exposure todirect sun light and use
Daily Advance precautionarymeasures taken at sitewas taken to avoid anyworker getting exposed
![Page 16: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/16.jpg)
15
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Accidents to work force. Providing adequatewarning signs.
Providing every workerwith skull guard or hardhat and safety shoes.
Establish all relevantsafety measures asrequired by law andgood engineeringpractices.
The contractor shallinstruct his workers inhealth and safetymeasures, and requirethe workers to use theprovided safetyequipment.
lot of drinking water toavoid dehydration.Adequate supply ofdrinking water wasprovided at constructionsites.
All workers have beenprovided with PersonalProtection Equipment(PPE).
All workers have beencompelled to wear PPEwhen they are at worksites.
All offices, work site,yards have beenprovided with warningsigns and notices.
Basic first aid facilitieshave been provided.
Regular tool boxmeeting are held onhealth and safetymeasures.
No. serious ofaccidentsreported/month.
No. of healthand safetytoolboxmeetings held/weekly
to the extreme sunnyand hot weatherconditions.
No serious accidentrecorded at site duringthe reporting period.
Construction of spill,spill gates, intakestructure and tailcanal
Change in surfacehydrology includingdown stream flowregime.
Drainage managementand soil conservationplan.
Construction workcommenced mainlyduring the dry flowseason.
Conveyingcapacity ofdrainagecanals
Construction ofspillway and relevantstructures completed.
![Page 17: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/17.jpg)
16
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Providing adequatedrainage facilities.
Confirm amounts ofsurplus rock basedmaterials that can beused in project or byother interested partiesfor public projects.
Confirm sufficientlocations for disposal ofsurplus materials as inthe estimate.
Specify locations fordisposal of all
A diversion canal wasconstructed initially todivert the river flow andwith construction ofspillway the river wasdiverted through the siltejector. Until radialgates of spillway areoperational underemergency, portion ofclear overflow (CO) keptopen at ground level.
All excavated material isstock pilled within theproject boundary andmost of them arereused.
Disposal of surplusmaterial only atapproved locations.
including thetemporarydiversion canaland canalmaintenanceduring rainyseason/monthly.
Availability ofwaterdownstream/monthly
Reuse ofmaterial/monthly.
The reservoir is nowbeing filled with water.
Radial gates of thespillway has beeninstalled and areoperational.
All major excavationworks have beencompleted and acumulative volume ofaround 116,000 cumhas been excavated.Out of this excavatedearth volume, about53,500 cubic metershad been reused forthe construction worksunder the Bentoniteslurry wall, temporaryaccess & byroads, the
![Page 18: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/18.jpg)
17
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
construction waste andspoil.
flank bund and landimprovement works inthe resettlement sites.The remaining volumehas been disposed atapproved sites leveledwith site restorationalso completed.
Transport of materialand spoil to and fromconstruction sites
Difficulties faced bypublic (including trafficcongestions) that usesuch roads.
Paving and maintainingroad surfaces, use ofwater trucks to wet theunpaved surfaces.
All material transportedhave been covered withTarpaulin and slightlydampened.
Speed limits have beenenforced for all haulagetrucks.
Maintenance ofcompactedsurface, gravellayer and sidedrains/monthly.
No public complainthas been received onpoor road conditionsduring the reportingperiod.
Material haulage truckshave followed thespeed restrictions.
Soil erosion andsediment transfer todownstream (soilconservation)
Providing soilconservation bunds andsedimentation ponds.
Turfing downstreamslope and providing rip-rap protection onupstream section ofearth bund.
Turfing of downstreamslope and rip-rap onupstream slopes of theearth bund.
Progress of soilconservationbunds/ traps&functionality,turf over bundslope(downstream)& rip-rapprotection(upstream)/monthly
Turfing of downstreamand rip-rap onupstream slopes of thebund has beencompleted.Maintenance of turfsods has been carriedout by the contractor.
Water resources Camps will be locatedat least 100 m awayfrom the nearest localsettlements.
Labour camps havebeen located away fromsettlements.
Complaintsfrom public onwater useconflicts/monthly
Contractor facilitated tohave continuousstream flow in todownstream withoutany interruption.
![Page 19: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/19.jpg)
18
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Project water will beobtained withoutdepleting local villagesupplies.
The contractors will berequired to maintainclose liaison with localcommunities to ensurethat any potentialconflicts related tocommon resourceutilization for projectpurposes are resolvedquickly.
Guidelines will beestablished to minimizethe wastage of waterduring constructionoperations and at campsites.
Water requirement forconstruction works isobtained withoutdisrupting water use bythe public.
All staff and workershave been made awareto avoid wastage ofwater.
No complaints wererecorded on conflicts ofwater usage.
Contractor hasadequately suppliedwater to all labourcamps and offices.
Water quality Carrying out standardwater quality tests inregular intervals andevaluation.
Training of operatorsand other workers toavoid pollution of waterbodies by operation ofconstruction machineryand equipment.
Measurements on waterquality at selected sitestaken once in threemonths.
Workers and machineoperators have beenmade aware of avoidingwastage of water.
Chemicalquality of waterin nearby waterbodies anddownstreamriver/ once in 3months.
No measurementswere carried out asconstruction workswere completed bySeptember, 2016.
![Page 20: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/20.jpg)
19
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Storage of lubricants,fuels and otherhydrocarbons in safeself-containeddedicated enclosures (>30 m away from waterbodies).
No stockpiles next lyingto water bodies.
Proper disposal of solidwaste from constructionactivities and workercamps.
Borrow sites should notbe close to sources ofdrinking water.
Storage of all chemicalson an enclosedstructure withimpervious floor androofing.
No stock pile has beenplaced near waterbodies.
Waste material isdisposed only atdesignated andapproved sites of localauthority.
No borrow site islocated close to waterbodies.
Accidents to work force Providing adequatewarning signs.
Providing every workerwith skull guard or hardhat and safety shoes.
Establish all relevantsafety measures asrequired by law and
Warning signboardsand notices have beenplaced at all work sites.
All workers have beenprovided with basicPPE, and the contractoris monitoring the use ofthese PPE by workers.
Providing workingplatforms when workingat heights.
Effectivenessof safetyprecautions,safetymeasures, ILOstandards/weekly
Warning sign boardshad been installed atmain store fuel storageas per previousinstruction.
Workers are using PPEat site.
Construction ofspillway structures
![Page 21: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/21.jpg)
20
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
good engineeringpractices.
The contractor shallinstruct his workers inhealth and safetymeasures, and requirethe workers to use theprovided safetyequipment.
Providing safetybarricade around deepcuts and tranches.
Regular safety tool boxmeetings are held atsite.
No. of training/awarenessprogramsconducted/monthly.
including the fish passis now completed.
Nuisance of noise andvibration
Install, maintain andmonitor all requisitemitigation as percontract and machineryshall be fitted withacoustic installation asmuch as possible.
Hammer type piledriving operations shallbe avoided during nighttime.
Well maintainedhaulage trucks will beused with speedcontrols.
Avoid activities thatgenerate high noiselevels between 22:00hrs and 06:00 hrs
Operation of plants &machineries as per CEAregulations.
Regular servicing &maintenance ofmachinery.
Providing ear plugs toworkers who work withhigh noise generatingmachinery.
Noise andvibrationmeasurements/once in 3months
No public complaintshave been received onnoise nuisance duringthe reporting period.
Impacts on air quality Control all dustymaterials at source.
Spraying of water at siteas means of reducingdust.
Air qualitymeasurements/once in 3months
No public complaintshave been receiveddue to dust. Contractorhas been spraying
![Page 22: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/22.jpg)
21
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Stockpiled soil andsand shall be slightlywetted before loading,particularly in windyconditions.
Fuel efficient and wellmaintained haulagetrucks shall beemployed to minimizeexhaust emissions.
Vehicles transportingsoil, sand and otherconstruction materialsshall be covered.Limitations to speed ofsuch vehiclesnecessary. Transporttrough denselypopulated area shouldbe avoided.
Spray bare groundareas, temporaryaccess roads withwater.
Covering all materialwhen transporting toand from site.
Enforcement of vehiclespeeds at site and onroads throughsettlements.
Regular servicing &maintenance ofmachinery.
Obtaining VehicleEmission Test (VET)certificate for allvehicles.
Operation of plants asper CEA regulations.
Progress ofwatersprinkling,covering ofstock piles,covering ofloaded haulagetrucks/ daily
Availability ofVET certificate/annually
Availability ofCEA licensesand approvalsfor plants/annually
water at site exceptduring rainy days.
Afforestation oflands
Environmental stability Demarcation ofafforestation lands asper EIA report.
Implementingafforestation plan.
Planting/enrichment inthe 66 hectares bufferzone around thereservoir with localspecies.
Type ofavailable &suitable plants.Healthy growth.No. of newplants grown inthe selected
Replanting and forestenrichment plantingworks are completed.During the reportingperiod the contractorcontinued to maintainthe plants in field and
![Page 23: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/23.jpg)
22
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
Implementingrecommendations ofthe additionalecological survey.
Planting/forestenrichment in the 50.0hectares in uppercatchment areaChemamadu.
Planting/forestenrichment in the 52.4hectares Cheddikulam.
area.Demarcation ofboundary withboundarypoles/ monthly
carried out vacancyplanting at requiredlocations.
Resettlement andlivelihood restoration
Social impacts Use of local labour asfar as possible formanual work.
Use of local educatedpeople for clerical andoffice work wherepossible.
Claims/ complaints ofthe people onconstruction nuisance/damages to beconsidered andresponded promptly bythe contractor andmonitored by PMU.
Resettlement of theaffected personsaccording to the NIRPand Land AcquisitionAct.
Paying ofcompensation.
Progress ofresettlementworks/ monthly
Status ofcompensationis payments/monthly
Progress ofminor tankrenovationworks/ monthly
Progress ofKovilconstructionworks/ monthly
Alternative paddy landpreparation workscompleted. Althoughthe lands have beenhanded over andfarmers cultivatedpaddy, it is affected bydry weather conditionprevailed during thereporting period.
Cash compensationhas been paid to DPsduring the reportingperiod. This included;
1. Vulnerable paymentof Rs 15,000 to 29 DP’s(100% completed).
2. Payment for loss ofcultivation for 52 DP’sfor the 2013/2014Maha season and 63DP’s for the 2014/2015Maha session.
![Page 24: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/24.jpg)
23
Specific activity Environmental Impact/ Concern
Mitigation measure/srecommended in theEIA
Mitigation measure/sadopted
Monitoringindicator/frequency
Effectiveness &further actionsneeded
3. Renovation of 3 nos.of minor tanks andconstruction of 2channels completed.
4. Compensation forwells has been paid for11 DPs.
5. Three houses withwells have beenconstructed andhanded over to twoDPs.6. Construction ofHindu Kovil wascompleted and handedover to the villagers.
![Page 25: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/25.jpg)
24
5. Examples of good practices, noncompliance notices and corrective
plans
Construction works of Per Aru reservoir was completed by September, 2016. During the near three
yearlong construction period the contractor has obliged instructions given to improve management of
environment and safety aspects. There were no major construction works during the reporting period
and no major non-compliance incidents were observed or recoded at site during the reporting period.
Overall there were few environment good practices carried out by this sub-project under DZUWSP,
which are summarized below.
Biodiversity rescue and translocation
The biodiversity rescue and translocation program was conducted in two stages as dam axis, access
roads, tail canal and reservoir bed area. Final cumulative number of individual species translocated
during the translocation and bio diversity rescue operation was 1783.
Construction of fish pass (fish ladder) at spill site
The conditional approval granted by CEA for the subproject included construction of a fish pass in the
dam (reservoir). The EIAR recommended a fish pass with two pipe tunnels across the dam. However,
both SC and contractor carried out detailed studies to obtain information on fish behavior and fish
passages. After a considerable review of literature a fish ladder was designed by end December 2015.
Construction of this fish ladder commenced from January 2016 and was completed during the
reporting period.
Figure 5.1. Constructed fish ladder
Maintenance work and vacancy planting in areas of replanting and forest enrichment planting
Maintenance and vacancy planting has been carried out by the contractor at all three sites where
replanting and forest enrichment planting was done. However, it is important to develop a system to
![Page 26: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/26.jpg)
25
further maintain these plants even after handing over of site is completed. Such system will enable
the survival of the planted trees and bushes.
Figure 5.2. Maintenance work being carried out at Cheddikulam
Figure 5.3. Taking plants from nursery for vacancy planting
Site restoration including disposal sites
Contractor has carried out clearing of debris at site, leveling of soil dumps and piling up of unwanted
rock and boulders as measures of site restoration around the reservoir area. Below figures depict this
situation. The first photograph was taken in April 2016 while the second one was taken in December
2016. Debris spread at site and after restoration are marked in circles.
![Page 27: Environmental Monitoring Report · DPR Daily Progress Report DZUWSP Dry Zone Urban Water & Sanitation Project ... was issued the letter of acceptance on 30th May 2013. With signing](https://reader036.fdocuments.us/reader036/viewer/2022071419/6117e1ad464bc303253ddca2/html5/thumbnails/27.jpg)
26
(a) (b)
Figure 5.4. Contractor attending to site restoration activities (a) before restoration (b) with restoration
activities
6. Public complaints
Grievance Redress Committees (GRCs) have been established to look into any public complaints
during the commencement of construction works and a public complaint register has been maintained
by the contractor. However, no public complaint was received during the reporting period.
7. Conclusion and further actions
Construction works of Per Aru reservoir which will supply raw water for the water treatment plant was
completed by September, 2016. As most of the finishing works were carried out during the reporting
period no major environment or social issue was reported. The reservoir is now in the process of filling.
The fish pass which was recommended as part of CEA conditional approval was constructed as a
section of the spillway structure. It is now important to monitor the migration of fish through this
structure.
Contractor continued maintenance and vacancy planting in all three locations where replanting and
forest enrichment works had been carried out. It is important to develop a program which will continue
to maintain these plants even after handing over is completed. Such measure is important as these
plants are damaged by grazing cattle.
As the construction of this reservoir completed and this is the final environment management and
monitoring report in respect to Per Aru surface water reservoir under the Dry Zone Urban Water and
Sanitation Project.