Environmental Monitoring Report
# Semiannual Report January - June 2020 November 2020
Indonesia: Metropolitan Sanitation Management
Investment Project - Part 2
Prepared by Directorate General of Human Settlements, Ministry of Public Works and Housing
for the Republic of Indonesia and the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 30 June 2020)
Currency unit – rupiah (Rp)
Rp1.00 = $0.0000697253 $1.00 = Rp14,342
NOTE{S}
(i) In this report, "$" refers to United States dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
DOKUMENTASI
‘
SENIN, 16 MARET 2020 (KANTOR CAMAT MARISO)
SOSIALISASI IPAL LOSARI - PEMBANGUNAN PERPIPAAN AIR LIMBAH
KOTA MAKASSAR ZONA BARAT LAUT (PAKET C-1 DAN PAKET C-2)
APPENDIX 3: Minutes of Meeting of Socialization Activity
48
1
FIELD VISIT REPORT
Monitoring of Environmental and Social Safeguard on Packages B2,C1&C2
Makassar at January 20 – 23, 2020
1. Objectives
The objectives of the Duty trip are:
(i) to supervise the safeguard aspects
(ii) Presentation of CEMP to contractors
(iii) to coordination with related agencies (LPMU and DLHK) for environmental permit issues
(iv) to collecting data on communal WWTP/ community-based sanitation in Makassar
(v) to review the implementation progress from previous recommendation.
(vi) to observe the implementation of the Environmental Management Plan (EMP).
The team consists of Leti Hermawati and Tyas Utami (PISC).
2. Itinerary
Day/Date Location Activity
Mon, 20 Jan 2020 Makassar ▪ Departure Jakarta - Makassar
▪ Meeting with PPK to explain the site visit agenda for monitoring
safeguard implementation in the field for package B2, C2 & C1
progress of environmental permit for AMDAL Makassar.
▪ Briefing contractor B2, C1 and C2 to prepare CEMP document
and explain the format of Temporary social impact assessment
& management and strip map
▪ Site Visit to package B2 (construction site and base camp) to find
environmental and social issues and monitoring project progress
and implementation of environmental & social safeguard in field
▪ Closed of meeting with contractor B2 to explain environmental &
social issued was found and action to be taken by contractor
Tue, 21 Jan 2020 Makassar ▪ Working coordination with City Leader Makassar and Ibu Nur
(Public Relation & Sanitation Marketing Specialist PISC
Makassar) concerning safeguard implementation for MSMIP.
▪ Site Visit to packages C1, C2 (construction site and base camp)
and WWTP B1 to find environmental and social issues and
monitoring project progress and Implementation of
environmental and social safeguard in field
▪ Closed of meeting with contractor C1 and C2 to explain
environmental & social issued was found and action to be taken
by contractor
Wed, 22 Jan 2020 Makassar ▪ Meeting with Public Works Agency of Makassar City for update
on UPTD, land certificate & public campaign for household
connections and involved in socialization
Thu, 23 Jan 2020 Makassar ▪ Collecting data on communal WWTP/ community-based
sanitation in Makassar
▪ Return Makassar - Jakarta
2
3. Supervision Notes for Packages
The implementation progress from previous Pending issues in ADB Mission, 12 Nov 2019&EIA:
No Pending Issues Response Progress
1 Monitor the completion of the
review AMDAL addendum of
Makassar
The Amdal Makassar addendum Doc has
been discussed at Technical &
Commission AMDAL Meeting (Rapat Tim
Teknis dan Komisi AMDAL). Based on the
Kabid Amdal of DLHK information, the
SKLH will be issued end of January 2020
Process in DLHK
2 Monitor the completion of ijin
lingkungan of Makassar
The environmental permit AMDAL
addendum Makassar is being processed
at DLHK. expected will be issued end of
Jan 20 2020.
Process in KPTSP
3 We also noticed, refer to TOR
MSMIP, Technical Specification
& Regulation that contractors
should prepare CEMP
PISC has conducted presentation of the
CEMP material to contractors B2, C1 &
C2, including prepared of environmental
and social strip map
Process
4 Collecting data on communal
WWTP/ community-based
sanitation in Makassar
PISC has been meeting with settlement
& housing Agency (Perkim) to asking
data communal WWTP at Makassar.
Process
5 The contractor will provide
temporary stored (TPS) at base
camp/stockyard for the
hazardous waste and include it
in the CEMP reports
Refer to Regulation No 101/2014
concerning Management of hazardous
and toxic waste and available on table of
environment management & monitoring
of RKPPL so the contractor should
implement the programs.
Process
Source: PISC January 2020
4. The superv i sion noted several good observations of safeguard implementation that
should be sustained during the life of the project:
(i) Safety briefing for visitors was conducted at the workshop prior to facility site visit and
PPE was available for visitor use.
(ii) Safety briefing for workers was conducted daily covering safety aspects such as PPE
compliance.
(iii) Package B2, Clean restroom, the toilet has considered gender (male and female are
separated) and office, prayer rooms, worker Mess, kitchen are available.
(iv) The base camp office and others facilities under finalize construction (B2)
(v) Rain drainages available at base camp.
(vi) Base camp location for packages C1 and C2 being negotiated with the land owner
3
5. The supervision also noted several observations as the room for improvement:
No Observations Remarks 1
Briefing K3 by HSE, package B2
need to be maintained
2
project board at the base camp gate
available (pack B2)
need to be maintained
3
there is a guard post, clean enough
conditions (B2)
need to be maintained
4
Temporary K3 sign at base camp available
(B2)
need to be maintained
5
Prayer rooms, ablution places and toilets (have
considered gender) are available (B2)
need to be maintained
4
No Observations Remarks
6
Mess workers are under construction, should
be resolved immediately because construction
activity had started
need to be improvement
7
Pit activity at Jl.Mapanyuki completed with
project fences
need to be maintained
8
Jacking activities in this location will cause
impact on accessibility to the notary's office
and stadium intersection with the traffic
conditions quite crowded, before jacking
work started the contractor should prepare
traffic management plan and schedule for
transporting excavated soil also conducting
socialization to affected persons
9
Office, commercial and residential areas on
the Jl. Hati Suci (B2), open trench activity
should concern to accessibility to resident
and commercial areas, also storage of soil
excavation and material and equipment at
construction site.
10
Open trench activity will cause traffic
congestions and air pollution, the contractor
should arrange traffic management, schedule
for transportation of soil excavation also
provided access to commercial area.
5
No Observations Remarks
11
Pump houses locations at Jalan Slamet
Riyadi (park)
12
Open trench activities in Jl. Sombu Opu will
cause impact on accessibility to the
shops/commercial areas, the contractor
should prepare traffic management plan
and schedule for transporting excavated
soil also conducting socialization to affected
persons.
13
WWTP B1 location
14
Meeting with Bappeda Kota Makassar
15
Socialization for package C1
6
6. Conclusion
The findings generally as follows:
1. The Safeguard Team PISC has conducted presentation of Environmental Management
Plan to the Contractor B2, C1 and C2.
2. Package B2 ongoing construction (Pit activity), the worker Mess, parker areas under built.
then for packages C2 and C1, mobilization process and the base camp & stock yard
location under negotiation.
3. Safety briefing for visitors was conducted at the base camp B2 prior to facility site visit
and complete PPE was available for visitor use
4. Pack B2: no trash bin available for plastic, organic, inorganic and wastes
5. None of the contractors have temporary toxic and hazardous (B3) waste storage (TPS) at
base camp/stock yard.
6. Contractors have to follow the requirements in their respective environmental
documents (RKL-RPL/AMDAL).
9. Suggestions and Next Steps
▪ Organize housekeeping campaign for all working areas involving all workers to improve
site environmental performance and behaviour change is the key.
▪ Include environmental topic in regular safety morning/safety talk which should cover:
1. SOP/working instruction socialization
2. Pollution prevention
3. Spill reporting
4. Waste segregation - organic, inorganic, toxic and hazardous wastes
5. Housekeeping improvement 6. Traffic and access management
▪ The disposal should be conducted in the designated area (agreed in PCM-to be further checked).
▪ Follow the requirements in environmental documents (RKL-RPL/AMDAL) for toxic and
hazardous waste management (temporary storage and disposal).
▪ Increase field supervision by PISC and share the observations to all stakeholders as lessons learned/continual improvement. Desirable sanctions to Contractors may be considered as necessary.
APPENDIX 4: Protocol COVID -19 at Construction Activity
49
Proyek Perpipaan Air Limbah
Kota Pekanbaru Area Selatan
Paket SC-01
www.wika.co.id
PENDAHULUAN
Pola Interaksi
Proyek
Pola Interaksi
Pemasok, mitra
kerja, dan
stakeholder
Behavior Change
Assesment
DAFTAR ISI
#CovidSafeBUMN
#BUMNUntukIndonesia
INTERAKSI
PROYEK
PROTOKOL INTERAKSI DI PROYEK
• Instruksi Menteri Pekerjaan Umum dan Perumahan Rakyat No. 02/IN/2020 tentang Protokol Pencegahan Corona Virus Disease 2019 (COVID-19) dalam Penyelenggaraan Jasa Konstruksi
• OSHA ALERT : COVID-19 Guidance for the Manufacturing Industry Workforce
3Memastikan sarana
dan prasarana
proyek dalam
keadaan bersih dan sesuai dengan
protokol kesehatan
2Mengadakan rapid
test;
Mengukur suhu
semua orang di proyek/pabrik
sebelum dan setelah
bekerja
6Protokol
pembatasan
jumlah orang.
Dan pengaturan
physical
distancing
saat bekerja
(meja kerja) tempat
ibadah.
7 Menyediakan
handsanitizer
& tempat
cuci tangandi lokasi
strategis
8 Memastikan
pekerja
menggunakan
masker
(Dukungan Manajemen)
*) Rapid Test dilaksanakan sebelum pegawai mulai hari pertama kerja.
5Tim Pemantau
Kepatuhan
dilengkapi dengan
thermal gun, masker, sarung
tangan
#BUMNUntukIndonesia
#GoHomeSafely
PembentukanSatgas
Pencegahan
COVID-19 di proyek
1 Membuat
sistem absen
online. Dan
monitoring kesehatan.
Tidak boleh
menggunakan
fingerprint
4