Environmental Monitoring Report - adb.org Development Bank does not intend to make any judgments as...

46
Environmental Monitoring Report Semi-annual Report JanuaryJune 2017 Philippines: Angat Water Transmission Improvement Project Prepared by Metropolitan Waterworks and Sewerage System for the Asian Development Bank.

Transcript of Environmental Monitoring Report - adb.org Development Bank does not intend to make any judgments as...

Environmental Monitoring Report

Semi-annual Report January–June 2017

Philippines: Angat Water Transmission Improvement

Project

Prepared by Metropolitan Waterworks and Sewerage System for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Contents

Executive Summary 1

General 1

Assessment of compliance 1

1 Introduction 2

1.1 Background 2

1.2 Project Implementation Progress 4

2 Compliance with ADB loan covenants and applicable

government laws, regulations and requirements 21

2.1 Status of compliance with government environmental requirements: 21

3 Changes in project scope 25

4 Summary of Environmental Mitigations and

Compensation Measures Implemented 26

4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if

relevant or required in the EMP) 31

4.2 Ambient Monitoring Program, i.e., air quality, noise, water quality, etc.

(if relevant or required in the EMP) 31

5 Key Environmental Issues 32

5.1 Key Issues Identified 32

6 Complaints 34

6.1 Details of Complaint/s 34

7 Conclusion and Recommendation 35

7.1 Overall Progress of Implementation of Environmental Management

Measures 35

8 Appendices 1

8.1 AWTIP Monitoring Matrix 1

8.2 Tree Cutting Permits 2

8.3 Permits and Licenses 3

8.4 Grievance Case - Invalid 4

List of Tables

Table 1. Contract Price for design and construction service ....................................................................................... 3

Table 2. Key information about the project .............................................................................................................. 3

Table 3. Key project progress .................................................................................................................................... 4

Table 4. Overall Progress of the project as of June 2016 ........................................................................................... 4

Table 5. Workforce as of June 30, 2017 ................................................................................................................ 17

Table 6.. Filipino Workforce as of June 30, 2017 – by geographic location ............................................................. 17

Table 7. Workforce as of June 30, 2017 – by Gender ............................................................................................ 17

Table 8.. Workforce as of June 30, 2017 – Dumagats ........................................................................................... 18

Table 9. Workforce as of June 30, 2017 – by Age Groups .................................................................................... 18

Table 10. Staff requirement in the next 3 months ................................................................................................... 18

Table 11. Sub-contractor: First Balfour .................................................................................................................. 19

Table 12. Sub-contractor: Trevi Foundations Philippines ........................................................................................ 19

Table 13. Sub-contractor: Trevi Foundations Philippines ........................................................................................ 19

Table 14. Sub-contractor: Don Vic Construction .................................................................................................... 20

Table 15. Permits ............................................................................................................................................... 21

Table 16. Other Permits ...................................................................................................................................... 22

Table 17. Safety Report as of June 2017 .............................................................................................................. 23

Table 18. Summary of Environmental Mitigations and Compensation Measures Implemented .............................. 30

Table 19. List of grievances as of June 2017 ........................................................................................................ 34

List of Figures

Figure 1. Project Site .............................................................................................................................................. 3

Figure 2. Construction of MWSS’ Living Quarters ................................................................................................ 6

Figure 3. Construction of Temporary Facilities at Industrial Area .......................................................................... 6

Figure 4. Concreting of Pavement for Sta.0+474 – Sta.0+609 (Left Lane).......................................................... 7

Figure 5. Formworks for Slope Protection on Crane Platform Area ........................................................................ 7

Figure 6. Rebar works for Wall and Top Slab and Concreted Bottom Slab of RCBC ............................................ 8

Figure 7. Formworks stripping of Revetment wall at Crane Platform Area ............................................................. 8

Figure 8. Drilling at Sta. 0+500 for Soil Nails .................................................................................................... 9

Figure 9. Rock Breaking for Conveyance Channel .................................................................................................. 9

Figure 10. Rock Breaking for Conveyance Channel .............................................................................................. 10

Figure 11. Wire mesh installation at Outlet Portal area ....................................................................................... 10

Figure 12. Bridge Overpass Aqueduct 1 ............................................................................................................... 11

Figure 13. Large RCBC ...................................................................................................................................... 11

Figure 14. Gripper Shield and Back-up Cars manufacturing in China ................................................................. 12

Figure 15. Manufacturing of Back-up Cars in China ........................................................................................... 12

Figure 16. Manufacturing of Segments Erector in China ...................................................................................... 12

Acronyms1

AWTIP Angat Water Transmission Improvement Project

ADB Asian Development Bank

CCO Chemical Control Orders

CEMMP Contractor’s Environmental Management And Monitoring Plan

CENRO City Environment and Natural Resources Office

CMC Cooperativa Muratori Cementisti di Ravenna

DENR Department of Environment and Natural Resources

ECC Environmental Compliance Certificate

EIA Environmental Impact Assessment

EMP Environmental Management Plan

IEC Information, Education and Communication

IEE Initial Environmental Examination

IP Indigenous People

km Kilometer

L Length

MENRO Municipal Environment and Natural Resources Office

MMT Multi-partite monitoring team

MWSS Metropolitan Waterworks and Sewerage System

NA Not applicable

NCIP National Commission on Indigenous Peoples

NPC National Power Corporation

PD Presidential Decree

PO Permit to Operate

RCBC Reinforced Concrete Box Culvert

RCPC Reinforced Concrete Pipe Culvert.

ROW Right of way

SEMP Self-Environmental Management Plan

TBM Tunnel Boring Machine

1 This is a standard acronym list for all monitoring reports. The acronym may not appear in all reports

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

1

Executive Summary

General

The Contractor, CMC di Ravenna, monitors its performance against the CEMMP obligations. Because

of this, it will record non-compliance where performance does not meet the original obligations. In

many cases this should not be taken to mean that the outcomes are bad and where alternative courses of

action have been adopted CMC and MWSS has recorded this.

This report highlights prevailing issues about the project. Only obligations which are assessed as in

progress, non-compliant (in specification and time schedule), and not applicable are presented in the

body of the report. A full review of the CEMMP obligations is presented in the CA matrix in excel

format.

The layout of this report followed recommended ADB monitoring report structure.

Assessment of compliance The following are the definition of remarks used to assess the CEMMP, EMP of IEE and EIA and other environment related project documents.

(a) COMPLIANT – completed according to schedule and specifications in the

CEMMP and other relevant ADB policies;

(b) NON-COMPLIANT – not completed according to schedule and

specification and/or not according to specification;

(c) NC time – completed beyond the date of completion stated in the CEMMP

(d) IN PROGRESS – partly compliant and pending for completion

(e) NOT APPLICABLE – obligations not applicable to AWTIP project

(f) CANNOT DOCUMENT COMPLIANCE – insufficient document or no

document provided to support assessment of compliance

A full review of the CEMMP and other relevant project documents on environment is presented in

Appendix Section 8.1.

No grievance case reported in the period January to June 2017.

Monitoring and survey services/ consultancy procurement are in progress.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

2

1 Introduction

1.1 Background

The Angat Water Transmission Improvement Project (AWTIP) is part of a bigger scheme of

modernization and improvement of the Metro Manila Water Distribution Network. The

water of the Angat basin, which is fed through the Umiray tunnel, provides around 35% of

the water for domestic use to the city of Manila. Currently the transportation of water from

Ipo dam basin to the Bigte sedimentation plant happens through 4 tunnels, 2 of which are

very obsolete. The progressive deterioration of the existing tunnels (2 of which were built

more than 75 years ago), or the occurrence of an earthquake (which is very likely since the

area is close to two active faults), may seriously compromise the provision of water to millions

of people.

The project is located in the province of Bulacan, at around 50 km north of Manila, close to

Norzagaray, city of 150,000 inhabitants which hosts several important cement industries and

which is easily accessible via highway or normal roads.

More than 95% of the water supply for Metro Manila comes from a single source: the Umiray–

Angat– Ipo, or Angat system. Water from the Angat reservoir is conveyed through three

parallel tunnels followed by six parallel aqueducts, to water treatment plants in Metro Manila.

The treated water is then distributed to households, businesses, and industries in Metro

Manila, and parts of Cavite and Rizal provinces. The transmission’s tunnel system which is

about 75 years old, has not been assessed ever since. The earlier tunnels, tunnels 1 and 2 are

not in compliance with current structural and seismic requirements. These factors could lead

to serious interruptions of Metro Manila’s water supply. The proposed project will construct

the urgently required fourth parallel tunnel. This new tunnel will not increase system capacity,

but it will enable the rehabilitation or decommissioning of the upstream tunnels and

downstream aqueducts.

The proposed project aims to (i) help restore the full design capacity of the Angat systems

and thus ensure the sustainable provision of the water supply distribution system, and (ii)

mitigate the risk of a total loss of water supply to Metro Manila and portions of Cavite and

Rizal provinces. Both objectives are essential for the stable economic growth of Metro Manila

and the Philippines. The government has asked the Asian Development Bank (ADB) to

finance this investment. The figure below shows the general location of the project.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

3

Figure 1. Project Site

The Angat Water Transmission Project (AWTIP) is a design and build project consists of

Design and Construction activities:

Table 1. Contract Price for design and construction service

ITEM GRAND SUMMARY CONTRACT PRICE

1 Designs Services 93,516,701.06

2 Construction Devices 3,198,038,168.46

Grand Total for Design Services and Construction Service

(1) + (2)

Php

3,291,554,869.52

1.1.1 Project Data

Table 2. Key information about the project

Project Name Angat Water Transmission Improvement Project

(AWTIP)

Components 6.4 km Tunnel Construction, Intake/Outlet

Structure, and Interconnection to Basin of

Aqueduct No. 5

Location Norzagaray, Ipo Dam to Bigte Basin

Duration 52 months (4 years and 4 months) Design Period

= 6 months Construction Period = 46 months

Source of Fund Asian Development Bank (Loan 3377 PHI-AWTIP)

Contractor Cooperativa Muratori Cementisti di Ravenna (Italy)

Contractor’s Project Manager Mr. Salvatore La Valle

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

4

Project Manager/ CO for MWSS Engr. Nestor G. Lualhati

Consultant’s Project Manager MWSS’s Consultant is not yet in place. MWSS,

the principal will do direct supervision

Notice to Proceed (NTP) May 31, 2016

Actual Date of Start June 01, 2016

Target Completion September 07, 2020

1.2 Project Implementation Progress

1.2.1 Overall Progress as of 30 June 2017

Table 3. Key project progress

PERIOD ENDING 30 JUNE 2017

Project Phase Construction Phase

Target Accomplishment to Date (30 June

2017)

7.119%

Actual Accomplishment to Date 14.37%

Scheduled Accomplishment for the Month 2.435%

Actual Accomplishment for the Month 0.46%

% Variance to Date

7.250 % (+)

(Ahead/Slippage)+/-

% Variance last Month

(Ahead/Slippage)+/-

9.224 % (+)

Contract Time Elapsed 395 c.d. or 25.32%

1.2.2 Physical Progress

Table 4. Overall Progress of the project as of June 2016

Contract Amount Relative Weight

(%)

Accomplishment (Php Millions)

Weighted (%) % Target

Previous

This Period

To date Previous This Period

To date

1. Designs Services

P93,516,701.06 2.84% 93.517 93.517 2.84% 2.84% 2.84%

2. Construction Services

P 3,198,038,168.46 97.16% 364.267 15.181 379.448 11.07% 0.46% 11.53% 4.28

TOTAL

P 3,291,554,869.52 100% 457.784 15.181 472.965 13.91% 0.46% 14.37% 7.12%

Note: This report shows the physical accomplishments of the Contractor’s work for items 1 and 2

Progress Status (Ahead/Slippage; +/-)

14.37 % (+)

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

5

1.2.3 On-going Site Works (as of June 2017)

(a) Facilities for the client’s office

(i) Living Quarters

(b) Outlet Portal Area General Site Facilities

(i) Industrial Area/Precast Segments Storage Platform Formation

(ii) Workshop and Warehouse

(iii) Fuel Station and Tank

(c) Permanent Access Road (5m – width and 865m – length)

(i) Earthworks

(ii) Basecourse Preparation

(iii) Concreting of Pavement

(d) Slope upon Portal

(i) Installation of Geocomposite Steel Mesh with Anchor Bolts

(ii) Installation of 28mmØ threaded rock bolts, 5 meters

(iii) Rock breaking for conveyance channel

(e) Railway for TBM preparatory Works

(i) Large RCBC, (Sta 0+010, 4.00x1.80, L=9.50m)

(ii) Large RCBC (Sta 0+010, 2x 4.00x1.80 L=6.00m)

(iii) Bridge overpass Aqueduct 1 (Span 3.65m, Length 33.35m)

(f) Tunnel Boring Machine (TBM) and Back-up Manufacturing

(g) Inland Drilling by TREVI FOUNDATIONS at IPO (For Seismic Test)

(i) Drilling at Core Holes

(ii) Installation of PVC Pipes at Core Holes

(iii) Grouting of Core Holes

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

6

1.2.4 Progress Photos (as of June 2017)

(a) Facilities for the Clients Office

Figure 2. Construction of MWSS’ Living Quarters

(b) Outlet Portal General Site Facilities

Figure 3. Construction of Temporary Facilities at Industrial Area

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

7

(c) Permanent Access Road to IPO Dam

Figure 4. Concreting of Pavement for Sta.0+474 – Sta.0+609 (Left Lane)

Figure 5. Formworks for Slope Protection on Crane Platform Area

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

8

Figure 6. Rebar works for Wall and Top Slab and Concreted Bottom Slab of RCBC

Figure 7. Formworks stripping of Revetment wall at Crane Platform Area

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

9

Figure 8. Drilling at Sta. 0+500 for Soil Nails

(d) Outlet Portal Area

Figure 9. Rock Breaking for Conveyance Channel

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

10

Figure 10. Rock Breaking for Conveyance Channel

Figure 11. Wire mesh installation at Outlet Portal area

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

11

(e) TBM Excavation – Preparatory works

Figure 12. Bridge Overpass Aqueduct 1

Figure 13. Large RCBC

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

12

Figure 14. Gripper Shield and Back-up Cars manufacturing in China

Figure 15. Manufacturing of Back-up Cars in China

Figure 16. Manufacturing of Segments Erector in China

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

13

1.2.5 Previous Site Works (January to May 2017)

(a) January 2017

(i) Facilities for the Client’s Office

• Refurbished of Existing MWSS Office at Bigte Compound

• Security, electricity, water, telephone, and internal services

• Parking Areas & Concreted Walkways

• Living Quarters/Collapsible Office

(ii) Contractor’s Temporary Facilities

• Toilet Blocks & Locker Rooms.

• Parking Area First Aid Block & Medical Equipment.

• First Aid Block & Medical Equipment.

• Canteen Block, Furniture & Equipment

• Septic Tank

• Provide necessary security, electricity, water, telephone, and internet

services

• Access Road to Office building

(iii) Outlet Portal Area General Site Facilities

• Industrial Area/Precast Segments Storage Platform Formation

• Workshop and warehouse

• Fuel station and tank

(iv) Other Works not included in the Baseline Programme

• Boreholes at Inlet Area

(b) February 2017

(i) Facilities for the Client’s Office

• Provide necessary security, electricity, water, telephone, and internet

services

• Provide Office Furniture for the Office and Living Quarter

(ii) Contractor’s Temporary Facilities

Installation of exterior wall panels and roof frame started on 6 February

2017. Installation of inner partitions, doors and windows. Construction of

restrooms in the three buildings and sewage connections to the external

septic tanks. Construction of the external drainage system for storm water.

Installation of electrical wiring system and main switch. Construction of the

water treatment house with 2 tanks and pumps.

• Toilet Blocks & Locker Rooms

• Parking Area First Aid Block & Medical Equipment

• First Aid Block & Medical Equipment.

• Canteen Block, Furniture & Equipment

• Septic Tank

• Provide necessary security, electricity, water, telephone, and internet

services

• Access Road to Office building

• Industrial Area/Precast Segments Storage Platform Formation

(iii) Permanent Access Road

• Subbase preparation

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

14

• Disposal and compaction of subbase

(iv) Outlet Portal Area

• Temporary Access Road

(v) Portal Area

• Excavation of surveying pit

• Condition Survey of IPO Dam Slope

(vi) Railway for TBM Preparatory Works

• Clearing and Grubbing

(c) March 2017

(i) Facilities for the Client’s Office

• Provide necessary security, electricity, water, telephone, and internet

services

• Living Quarters/Collapsible Office

(ii) Contractor’s Temporary Facilities

• Toilet Blocks & Locker Rooms

• Parking Area First Aid Block & Medical Equipment.

• First Aid Block & Medical Equipment.

• Canteen Block, Furniture & Equipment.

• Septic Tank.

• Provide necessary security, electricity, water, telephone, and internet

services.

• Access Road to Office building

• Industrial Area/Precast Segments Storage Platform Formation

(iii) Permanent Access Road

• Survey Works

• Clearing and Grubbing

• Road preparation at Sta. 0+160 to Sta. 0+200

(iv) Inlet Portal

• Pit Test Excavation

(v) Outlet Portal Area

• Temporary Access Road

• Excavation of basalt/limestone portal slope

• Clearing and Grubbing

• Rock breaking at Abutment area

• Resumption of Rock breaking at Portal

• Backfilling from Sta. 0+150 to Sta. 0+200

(vi) Drainage Works

• RCPC laying near Aqueduct No. 1

(vii) Conveyance Channel and Transition Basin

• Excavation at the area where the Conveyance Channel and Transition

Basin will be built

(viii) Railway for TBM Preparatory Works

• Installation of drainage pipe culvert

• Backfilling and compaction of railway

(d) April 2017

(i) Facilities for the Client’s Office

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

15

• Provide necessary security, electricity, water, telephone, and internet

services. - Completed on 8-Apr-2017

• Living Quarters/Collapsible Office

(ii) Contractor’s Temporary Facilities

• Office Building, Toilet Blocks & Locker Rooms. - Completed on 8-Apr-

2017

• Parking Area First Aid Block & Medical Equipment. - Completed on 8-

Apr-2017

• First Aid Block & Medical Equipment. - Completed on 8-Apr-2017

• Canteen Block, Furniture & Equipment. - Completed on 8-Apr-2017

• Septic Tank. - Completed on 8-Apr-2017

• Provide necessary security, electricity, water, telephone, and internet

services. - Completed on 8-Apr-2017

• Construction of workshop basement at Industrial area

• Construction of drainage at Industrial area

(iii) Permanent Access Road (Inlet)

• Survey Works

• Clearing and Grubbing

• Road preparation at Sta. 0+160 to Sta. 0+200

(iv) Slope Stabilization (Inlet)

• Removal of soil from the intake slope

(v) Outlet Portal Area

• Temporary Access Road

• Clearing and Grubbing

• Rock breaking at Abutment area

• Presumption of Rock breaking at Portal

• Backfilling from Sta. 0+150 to Sta. 0+200

(vi) Railway for TBM Preparatory Works

• Construction of box culvert

• Backfilling and compaction

• Construction of structure passing over Aqueduct No.1

• Construction of pipe culvert

• Construction of steel bridge abutment

(vii) Batching Plant at Calumpit, Bulacan

• Construction of Batching Plant to FreyFil Factory for production of

tunnel lining precast segments

(e) May 2017

(i) Facilities for the Client’s Office

• Living Quarters/Collapsible Office

• Industrial Area/Precast Segments Storage Platform Formation

• Workshop and warehouse

• Fuel station and tank

(ii) Permanent Access Road

• Earthworks

• Basecourse preparation

• Concreting of pavement –

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

16

(iii) Pipe Culverts and Drainage System

• Construction of grouted riprap, Class A

• Construction of Grouted Riprap, Line Ditch

• Pipe Culvert, 1220mm Ø

• Pipe Culvert, 910mm Ø –

(iv) Slope upon the Portal

• Installation of Geocomposite Steel Mesh With Anchor Bolts

• Installation of 28mmØ threaded rock bolts, 5 meters

(v) Drainage and slope protection

• Stream Regularization and Apron Upstream Culvert (4.00x1.80m)

• Stream Regularization and Apron Downstream Bridge @ STA 0+290

(vi) Railway for TBM preparatory Works

• Large RCBC, (Sta 0+010, 4.00x1.80, L=9.50m)

• Large RCBC (Sta 0+010, 2x 4.00x1.80 L=6.00m)

• Bridge overpass Aqueduct 1 (Span 3.65m, Length 33.35m)

• Gravity Retaining Wall - Left side of outlet platform L=30m

• Gravity Retaining Wall - Right side of outlet platform L=5+7m

• Gabions Retaining Wall - Left Side of Abutment A L=10m Hmax 3m

(vii) 1 Inland Drilling by TREVI FOUNDATIONS at IPO (For Seismic Test)

• Drilling at Core Hole 9 - Completed on 27-May-2017

• Drilling at Core Hole 33

• Drilling at Core Hole 26

• Drilling at Core Hole 29 - Completed on 28-May-2017

• Drilling at Core Hole 13 - Completed on 28-May-2017

• Drilling at Core Hole 10

• Drilling at Core Hole 30

• Drilling at Core Hole 14

• Drilling at Core Hole 11

• Drilling at Core Hole 31

• Drilling at Core Hole 15

• Drilling at Core Hole 12

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

17

1.2.6 Contractors Resources

(a) List of Production Construction Staff

Table 5. Workforce as of June 30, 2017

Entity Filipino Foreigner

TOTAL # % # %

CMC permanent staff

7 10% 10 14% 17

CMC contract workers / utilities

52 71% 0 0% 52

CMC consultants 3 4% 1 1% 4

First Balfour 111 100% 0 0% 111

Trevi Foundations Philippines

60 100% 0 0% 60

Don Vic Construction

60 100% 0 0% 60

TOTAL 293 96% 11 4% 304

Table 6.. Filipino Workforce as of June 30, 2017 – by geographic location

Entity

Personnel employed from Brgy San Mateo

Personnel employed from Bgry Bigte

Personnel employed from other Bgrys in Norzagaray

Personnel employed from other municipalities/ cities in Bulacan

Personnel employed from other provinces TOTAL

# % # % # % # % # %

CMC permanent staff

0 0 0 0 0 0 1 2% 6 10% 7

CMC contract workers / utilities

5 8% 9 15% 3 3% 0 0 35 57% 52

CMC consultants 0 0 0 0 1 2% 0 0 2 3% 3

First Balfour 13 12% 22 20% 1 1% 11 10% 64 58% 111

Trevi Foundations Philippines

12 20% 8 13% 0 0% 0 0% 40 67% 60

Don Vic Construction

21 35% 37 62% 0 0% 0 0% 2 3% 60

TOTAL 51 17% 76 26% 5 2% 12 4% 149 51% 293

Table 7. Workforce as of June 30, 2017 – by Gender

Entity Male Female

TOTAL # % # %

CMC permanent staff 12 17% 5 7% 17

CMC contract workers / utilities

42 58% 10 14% 52

CMC consultants 3 4% 1 1% 4

First Balfour 102 92% 9 8% 111

Trevi Foundations Philippines

58 97% 2 3% 60

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

18

Don Vic Construction 57 95% 3 5% 60

TOTAL 274 90% 29 10% 304

Table 8.. Workforce as of June 30, 2017 – Dumagats

Entity Male Female

TOTAL # % # %

CMC permanent staff 0 0 0 0 0

CMC contract workers / utilities

0 0 0 0 0

CMC consultants 0 0 0 0 0

First Balfour 6 100% 0 0% 6

Trevi Foundations Philippines

12 100% 0 0% 12

Don Vic Construction 18 86% 3 14% 21

TOTAL 36 92% 3 8% 39

Table 9. Workforce as of June 30, 2017 – by Age Groups

Entity 18-25 26-35 36-45 46-60 Over 60

TOTAL # % # % # % # % # %

CMC permanent staff 2 3% 2 3% 7 10% 6 8% 0 0 17

CMC contract workers / utilities

5 7% 22 30% 9 13% 16 22% 0 0 52

CMC consultants 0 0 0 0 1 1% 0 0 3 4% 4

First Balfour 26 23% 40 36% 27 24% 18 16% 0 0% 111

Trevi Foundations Philippines

15 25% 17 28% 17 28% 11 18% 0 0% 60

Don Vic Construction 30 50% 30 50% 0 0% 0 0% 0 0% 60

TOTAL 78 26% 111 37% 61 20% 51 16% 3 1% 304

(b) Recruitment Table 10. Staff requirement in the next 3 months

Position No. of Required

1. Health, Safety & Environmental Manager 1

2. TMB Hydraulic Mechanic 1

3. Cutter Head Mechanic 1

4. Welder 1

5. Tunnel Line Extension 2,3,4 3

6. Fork Lift Operator 3

7. Shift Boss 2

8. TMB Operator 1

9. TMB Mechanic 1

10. Laborer 2

11. Chief Mechanic 1

12. Driver Lorry Crane 1

13. Chief Electrician 1

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

19

14. Electronics Technician 1

15. Technician 1 & 2 2

16. Helper 2 1

17. Driver Lorry 1

TOTAL 24

(c) 1.2.7.3. List of Equipment Table 11. Sub-contractor: First Balfour

Item Quantity

1. Backhoe (20Tons Capacity ) 3

2. Vibratory Compactor ( 10Tons Capacity ) 1

3. Motor Grader ( 4 mtr width ) 1

4. Dump Truck ( 15 cubic capacity ) 1

5. BHI Hydraulic Breaker 1

6. Service Vehicles 3

7. Mini Dump Truck 1

8. DRG 1500 Drill rig 1

9. Shotcrete plant 1

10. Compressor 2

11. DRG200 Crawle Mount rig 1

12. Grout pump 1

13. Grout mixer 1

14. Bagger Mixer 1

Table 12. Sub-contractor: Trevi Foundations Philippines

Item Quantity

1. CK 50 Rig no.1 1

2. CK 50 Rig no. 2 1

3. CK 50 Rig no. 3 1

4. TOHO 1

5. YBM-1WA Crawler drill rig no.1 1

6. MGJ-50L Crawler drill rig no. 1 1

7. Tone NAS 4 Grout Pump 1

8. Bean Royal 520 2

9. NAS 3 1

10. Garner Denver 1

11. NW 190 1

12. Genset 2

13. Tower Light 1

14. Welding Machine 1

15. Air Compressor 1

16. TRPLEX Nenzi Pump 200 Motor Pump 1

Table 13. Sub-contractor: Trevi Foundations Philippines

Item Quantity

17. SM 103 1

18. Manitowoc Crane 1

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

20

19. Compressed Air Tank 1

20. Cylinderal Water Tank 1

21. Water Tank 4

22. FMC 420 Drilling Pump 1

Table 14. Sub-contractor: Don Vic Construction

Item Quantity

1. Mini dumptruck 1

2. Double Cab truck 1

3. Concrete Mixer 3

1.2.7 Specific dates (day/month/year) site visits/inspections conducted by the supervision consultant to monitor

compliance of the contractors (and subcontractors) with the mitigation measures specified in the EMP.

The construction supervision consultants have not yet been commissioned by MWSS. MWSS

staff were the ones monitoring the compliance of CMC with the mitigating measures specified

in the Contractor’s Environmental Management and Monitoring Plan (CEMMP) Issues and

concerns were discussed in their weekly project management meeting with CMC.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

21

2 Compliance with ADB loan covenants and applicable government laws, regulations and requirements

2.1 Status of compliance with government environmental requirements:

The following table presents the permits acquired for the project. Copies

of the permits are in Appendix Section 8.2 and 8.3 of this report.

Table 15. Permits

Environmental Laws

Permits Date of Issue/ remarks Expiry Date

PD 1586 (Establishing EIS System)

ECC1 (Environmental Compliance Certificate)

ECC-CO-1508-0022

7 April 2017.

The certificate shall cover the following:

1. construction of water tunnel #4 with 6.4 kilometer length and 4 m diameter from Ipo Dam, Barangay San Mateo to Barangay Bigte, with associated facilities such as Contractor’s Work areas, Spoil Disposal Sites as enumerated in the EIS

2. Repair and rehabilitation works of Tunnel Nos 1,2,3

3. Water transmission operations of Tunnels No 1,2,3 and 4 for an aggregate water flow of up to 43 m3/sec

4. Fencing of the Right-of- way

-

RA 6969 (Toxic Substances and Hazardous and Nuclear Waste)

DENR Registry ID

N/A. no major construction activity as of this time. Only used oil from

vehicle is generated and all maintenance services of vehicles

are done offsite. Permit application will be processed

when temporary Hazmat disposal area is 50% filled.

CCO Registry (Chemical Control Order Registry)

N/A. no major construction activity as of this time. Only used oil from

vehicle is generated and all maintenance services of vehicles

are done offsite. Permit application will be processed

when temporary Hazmat disposal area is 50% filled.

Importer Clearance No

N/A. no major construction activity as of this time. Only used oil from

vehicle is generated and all maintenance services of vehicles

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

22

are done offsite. Permit application will be processed

when temporary Hazmat disposal area is 50% filled.

Permit to Transport

N/A. no major construction activity as of this time. Only used oil from

vehicle is generated and all maintenance services of vehicles

are done offsite. Permit application will be processed

when temporary Hazmat disposal area is 50% filled.

RA 8749 (Phil Clean Air Act)

PO No.1 (permit to Operate)

Permit to Operate (gen set) –

application in progress

PD 705 (The Forestry Reform Code Of The Philippines)

Tree Cutting Permit

- Tree cutting permit dated September 23, 2016 (10 assorted tree species in Bigte) issued by CENRO Tabang

September 30, 2016

- Tree cutting permit dated October 5, 2016 (38 mixed trees in Brgy San Mateo and Bigte) issued by MENRO Norzagaray

October 20, 2016

- Tree cutting permit dated November 10, 2016 (10 assorted fruit tree species in Bigte) issued by CENRO Tabang

November 25, 2016

- Tree cutting permit dated March 16, 2017 (10 assorted fruit tree species in the Ipo Dam Access Road) issued by CENRO Tabang

March 31, 2017

- Tree cutting permit dated April 3, 2017 (10 assorted fruit tree species in the Ipo Dam Access Road) issued by CENRO Tabang

April 18, 2017

- Tree cutting permit dated April 21, 2017 (10 assorted fruit tree species in the Ipo Dam Access Road) issued by CENRO Tabang

May 6, 2017

- Tree cutting permit dated March 20, 2017 (50 trees in Brgy San Mateo and Bigte) issued by MENRO Norzagaray

April 4, 2017

Table 16. Other Permits

Permits Date of Issue/ remarks Expiry Date

Mayor’s Permit

Permit number: 2017-0722 Date of Issue: June 5, 2017

December 31, 2017

Excavation Permit

In progress. - All document requirement already submitted to the Office of the Municipal

Engineer. Letter of response from the Municipal Engineers Office dated 19 June 2017 – asking for the formation of the MMT, general project description and spoil management.

- Request for meeting by CMC in letter dated 21 June 2017 - Meeting with Engr Zeus Borja on 27 June 2017 - Presentation of the project required and is schedule on week 3 of July

2017

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

23

Land use Permit issued by NPC

In progress. Land use permit has been applied to NPC Follow-up made by MWSS and CMC. Waiting for comments from NPC

Application was done on May 2017. Joint inspection of CMC and NPC was conducted on May 29, 2017.

Table 17. Safety Report as of June 2017

Previous This Period To Date

Average Manpower 263 45 308

CMC di Ravenna 64 8 72

Sub-contractor 199 37 236

Safe Man-hours 131,408.5 268,016.7 361,198.2

CMC di Ravenna 60,400 57,217.6 174,835.2

Sub-contractor 71,008.5 22,173 93,181.5

Major Accidents2 3 - 3

Minor Accidents3 1 - 1

Activity Previous This Period To Date

Accidents / Cases

Vehicle Accidents4 3 - 3

Near Misses5 6 - 6

First-Aid Cases6 1 1 2

Medical Treatment Cases7 11 1 12

Restricted Work Cases8 - - 0

Lost-Time Cases9 - - 0

Meeting

Safety Meeting 4 1 5

Toolbox Meeting 170 106 276

Orientations 233 19 252

2 Major Accidents – defined as an acute incident such as major discharge/emission or a fire/explosion, which

immediately or subsequently causes several serious injuries and/or fatalities, serious harm to environment and/or loss of substantial material assets.

3 Minor Accidents – an accident that causes minor damage. 4 Vehicle Incidents – when a motor vehicle strikes or collides another vehicle, a stationary object, a pedestrian, or an

animal 5 Near Misses – unplanned event that has the potential to cause, but does not actually result in human injury,

environmental or equipment damage, or an interruption of normal operation. 6 First Aid Cases – workers injury cases administered immediately after the injury occurs at the location where it

occurred. 7 Medical Treatment Cases – recordable incident involving injury or illness that has required management and care of

the patient above and beyond first aid, but not severe enough to be a reportable fatality or lost work day case or restricted work day case.

8 Restricted Work Cases – when a person is so injured that they cannot perform their normal duties. Therefore they

are transferred temporarily to some other jobs (light duties). 9 Lost-Time Cases – refer to the number of lost-time injuries within a given accounting period, relative to the total

number of hours worked in that period.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

24

Previous This Period To Date

Inspection Audits 84 24 108

Training Activity

HSE 1 - 12

PPE - - 1

Fire - - 0

Radio - - 0

First Aid - - 0

Alcohol Test - - 0

Driving 1 1 2

Work Permit 1 0 1

Hazardous Material Handling - 1 1

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

25

3 Changes in project scope

No change in project scope.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

26

4 Summary of Environmental Mitigations and Compensation Measures Implemented

A full review of the CEMMP, IEE, EIA EMP and other obligations is presented in the compliance

matrix in Appendix Section 8.1 of this report. Below is a summary of prevailing issues on

mitigation and compensation issues. Details can be found in Appendix Section 8.1.

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

Water

Impact on surface water quality due to/ from: · Contaminants from materials used and construction activities and processes · Siltation from soil erosion, spoil disposal area, dewatering excavations, etc · Water quality Deterioration of water quality in Ipo Dam and Bigte river Tributary during construction

· Implement hazardous waste management that minimizes, properly segregates and promptly and properly disposes of generated hazardous wastes. · Store hazardous construction materials in appropriately contained and elevated area and at least100 m away from surface water bodies. · Implement corrective action, when trigger thresholds of water quality are reached. · During construction, the contractor shall take corrective action to reduce concentration to below the standard.

Partial

High coliform was reported in segment of surface water where there are communities along the riverbanks. The construction camp is near the riverbank and might be a potential contributor to poor surface water quality. Hazmat identified at this stage of construction is limited to oil, lubricants used by heavy equipment and vehicles. Most vehicles used are brand new. Maintenance is done off site. Temporary Hazmat disposal area will be located in the Industrial Area and is planned to be constructed when excavation of the tunnel commences.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

27

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

This is considered partial as no water quality sampling/ monitoring has been done yet. Procurement process for portable water quality meters are on-going. Request for quotation has been sent to Brownasia Tech Inc. Request for quotation for the conduct of the water quality has been sent to CRL Laboratories.

Air Quality and Noise

a) Deterioration of ambient air quality due to dust and gas emissions from: · Earthworks and other construction processes; tunnelling (TBM) • stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas; • increased transport activities in the construction areas and along Ipo Road; • Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day • burning of

In active work sites: Use of dust curtains / nets to capture dust from the construction sites

Apply dust suppression techniques, e.g., watering with bowsers, sheeting particularly at Bigte area Require trucks, particularly those hauling aggregates, to have secure covers. · Limit engine idling to 5 minutes. · Prohibit open burning of vegetation and

Partial

No dust curtains/net has been installed. This will be installed at the outlet portal area once excavation activities commence and measured air duality parameters such as total suspended particles and PM 10 are almost near the standard limits of air quality. Dust suppression such as watering has been implemented already. Open burning is not practiced onsite

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

28

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

vegetation and wastes; and • operation of mechanical equipment

other waste in the project area · Ipo Road, main access road, other roads in the Project area, limit speed of all construction vehicles to maximum of 40 kph on the access road to, and maximum of 30 kph in the site · Control noise at source, e.g. low noise plant, muffling, acoustic screening, switch off campaigns · Restrict use of noisy and highly vibrating equipment from 8AM-5PM. Necessary overtime work should: a) not go beyond 9:00PM; b) observe regulated noise and vibration levels; c) not use noisy and highly vibrating equipment; and d) should be coordinated with the barangay and affected households. · Manage the ins and outs of hauling trucks. Spread out the schedule of material, waste

Speed limit has not yet implemented No air quality has been conducted yet. Request for quotation for the conduct of the ambient air quality monitoring has been sent to CRL Laboratories.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

29

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

and spoil transport in the day (off-peak hours). · Enforce the rule of no blowing of horns. · Strictly enforce upon workers the compliance with wearing of ear mufflers, especially those who are operating equipment.

Biological Environment

Loss of vegetation due to: • vegetation clearing and potential trampling of trucks/equipment beyond project footprints • Over-clearance and damage to vegetation around the construction sites

· Provide environmental training for workforce

Non-Compliant

No environmental training for workforce has been done yet. Target date to conduct environmental training to workforce is 2018 February

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

30

Table 18. Summary of Environmental Mitigations and Compensation Measures Implemented

EMP Requirement (list all mitigation

measures specified in the

EMP/CEMP/SEMP)

Compliance Attained

Location

Comment on Reasons for Partial or Non-Compliance

Required Action and Target Dates to Achieve Compliance

1. Water Quality Monitoring

Partial Ipo and Bigte River

Visual monitoring through photograph and Video documentation. Procurement process of water quality portable meters on going. Request for quotation has been sent to Brownstone Asia-Tech Inc

Water quality monitoring will be done monthly starting August 2017. Other parameters such as turbidity, pH, temperature and conductivity will be monitored weekly once the portable water quality meters arrived.

2. Air quality monitoring

Partial Request for quotation for the conduct of the ambient air quality has been sent to CRL Laboratories.

Air quality monitoring will be done quarterly. Target date of air quality monitoring are as follows: -February 6-8,2018 -May 8-10, 2018 -August 7-9,2018 -November 6-8, 2018 -February 5-7, 2019

3. Freshwater ecology monitoring

Partial Request for quotation for the conduct of the water quality has been sent to CRL Laboratories.

Target date of freshwater ecology monitoring is on April and August 2018-2019

4. Social and Economic Survey

Partial Socio-economic survey currently being discussed with an IP Specialist/ Anthropologist (Mr Joseph Lalo)

Target date of socio economic survey is on September 2018

5. Social and environmental awareness

Partial Residences near construction area and tunnel ROW

Bulletin boards for IEC purpose were installed in the barangay halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third letter to NCIP in relation to FPIC application was sent on 15 June 2017.

IEC will be done to students and residents should there be major construction activities, deliveries of large goods, notice of employment requirement starting July 2017.

6. Public Health and safety

Partial Health and safety staff are hired More detailed grievance procedure will be formulated on July 2017.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

31

4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if

relevant or required in the EMP)

4.1.1 Summary of Monitoring No sampling has done yet.

4.1.2 Results No results are available yet.

4.1.3 Assessment10

4.2 Ambient Monitoring Program, i.e., air quality, noise, water quality,

etc. (if relevant or required in the EMP)

4.2.1 Summary of Monitoring No sampling has done yet.

4.2.2 Results No sampling has done yet.

4.2.3 Assessment11

10 Discharge levels should be compared to the relevant discharge standards and/or performance indicators noted in

the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, discharge levels could be compared to baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:

1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)

Additional explanatory comments should be provided as necessary. 11 Ambient environmental conditions should be compared to the relevant ambient standards and/or performance

indicators noted in the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, ambient environmental conditions could be compared to the baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:

1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)

Additional explanatory comments should be provided as necessary.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

32

5 Key Environmental Issues

5.1 Key Issues Identified

The following are the key issues to be addressed:

(i) The following monitoring is being established:

• Water quality monitoring o Water quality monitoring will be dome monthly but other

parameters such as turbidity, pH, temperature, and conductivity

will be done weekly. Target start date of water monitoring is on

August 2017.

• Air quality monitoring

o Air quality monitoring will be done quarterly. Target dates of the

air quality monitoring are as follows:

▪ February 6-8, 2018

▪ May 8-10, 2018

▪ August 7-9, 2018

▪ November 6-8, 2018

▪ February 5-7, 2019

• Freshwater water ecology monitoring

o Target date of the freshwater monitoring are as follows:

▪ April 2018

▪ August 2018

• Social and economic survey

o Target date of the socio-economic survey and monitoring are as

follows:

▪ September 2018

• Social and environmental awareness

o Bulletin boards for IEC purpose were installed in the barangay

halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third

letter to NCIP in relation to FPIC application was sent on 15

June 2017. Target date of the social and environmental

awareness campaign for the residents and students will be done

on during:

▪ to start on July 2017 and monthly updates thereafter or

in cases such as employment requirement of the

construction project; and major construction activities

and deliveries of largo goods that will have potential

impact to the environment as well as community health

and safety impact

• Public Health and safety

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

33

o Target date of the public health and safety campaign are as

follows:

▪ September 2017

Procurement of laboratory services, consultancy services and surveys is on-going.

(ii) MWSS has no Construction Supervision Engineer Team where an

environment specialist is included. CMC provides environmental and

social technical inputs to the project.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

34

6 Complaints

6.1 Details of Complaint/s Table 19. List of grievances as of June 2017

Valid Grievance Cases 0

Invalid Grievance Cases 1

Unresolved Grievance Case from previous months

0

Pending Valid Grievance Cases 0

Resolved Grievance Cases to date 0

No grievance cases have been reported as of June 2017. The complaint

forwarded by the LGU of Brgy Bigte on vehicular incident is considered

invalid since the vehicle was not owned by the contractor, CMC. The pick-

up car with plate number CO7-650 driven by Mr. Rolando Castro is owned

by MWSS. Please see Appendix Section 8.4 for details.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

35

7 Conclusion and Recommendation

7.1 Overall Progress of Implementation of Environmental Management

Measures12

The overall progress can be assessed as fair. The project construction

phase started in December 2016, only temporary facilities and work areas

has been established from January to June 2017. In such construction

activities, potential environmental impacts associated to tunnel

construction per se is yet to be observed until the excavation work will

commence. Only impacts such as generation of dust and slight increase

in turbidity of the surface water in Bigte Creek is observed. The turbidity

of Angat River is attributed to other activities and physical conditions

upstream of Angat River. Dust generation is mitigated through regular

watering and cleaning of roads. For turbidity, visual monitoring is done

regularly through photograph and video documentation. Procurement

process of water quality portable meters are still on going. Request for

quotation has been sent to Brownstone Asia-Tech Inc. Once the meters

arrived, monitoring of turbidity and other water parameters will be done

regularly.

12 Overall sector environmental management progress could be described in qualitative terms or be evaluated based

on a ranking system, such as the following: 1. Very Good 2. Good 3. Fair 4. Poor 5. Very Poor

Additional explanatory comments should be provided as necessary.

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

1

8 Appendices

8.1 AWTIP Monitoring Matrix

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

2

8.2 Tree Cutting Permits

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

3

8.3 Permits and Licenses

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 January – June

4

8.4 Grievance Case - Invalid