Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the...

59
Environmental Monitoring Report Project No: 42378-016 Semi-annual Report January – June 2017 3087-BAN: Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Part C: Increased North Dhaka Distribution Capacity: Augmentation and Rehabilitation of Distribution System in DESCO Area. Prepared by : Dhaka Electric Supply Company Ltd (DESCO) for the Asian Development Bank for People’s Republic of Bangladesh. This monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

Transcript of Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the...

Page 1: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Environmental Monitoring Report

Project No: 42378-016 Semi-annual Report January – June 2017

3087-BAN: Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Part C: Increased North Dhaka Distribution Capacity: Augmentation and Rehabilitation of Distribution System in DESCO Area. Prepared by : Dhaka Electric Supply Company Ltd (DESCO) for the Asian Development Bank for People’s Republic of Bangladesh. This monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

Page 2: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power
Page 4: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

DHAKA ELECTRIC SUPPLY COMPANY LIMITED (DESCO)

MINISTRY OF POWER, ENERGY & MINERAL RESOURCES

GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH

1st Environmental Monitoring Report

on

Augmentation and Rehabilitation of Distribution System in DESCO Area

Dhaka

22 June, 2017

Page 5: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Table of Contents

Acknowledgements ........................................................................................................ i Table of Contents ........................................................................................................... ii List of Tables .................................................................................................................. iv List of Figures ................................................................................................................ iv Unit of Measurement .................................................................................................... v Abbreviations and Acronyms .................................................................................... vi Summary Statement ................................................................................................... vii 1. Introduction ............................................................................................................... 1

1.1 Background ............................................................................................................. 1

1.2 Objectives ............................................................................................................... 1

1.2.1 Main Objective .............................................................................................. 1

1.2.2 Specific Objectives ....................................................................................... 1

1.3 Project locations ..................................................................................................... 2

1.4 Scope of Studies .................................................................................................... 5

1.5 Monitoring Law and Policy Standard .................................................................. 6

1.5.1 Compliance with National Environmental Laws ...................................... 6

1.5.2 Bangladesh Government Regulation and compliance monitoring ....... 7

1.5.3 Compliance with DoE’s Guidelines ............................................................ 9

1.5.4 ADB loan covenants with the DESCO ..................................................... 10 2. Approach and Methodology ................................................................................ 13

2.1 Introduction .......................................................................................................... 13

2.2 Overall Approach.................................................................................................. 13

2.3 Study mobilization ............................................................................................... 13

2.4 Study Team Mobilization .................................................................................... 13

2.5 Methodology ......................................................................................................... 14

2.5.1 Physical environment ................................................................................ 14

2.5.2 Biological environment .............................................................................. 15

2.5.3 Socio-economic environment ................................................................... 15 3. Monitoring Results ................................................................................................ 17

3.1 Introduction .......................................................................................................... 17

3.2 Physical Environment .......................................................................................... 18

3.2.1 Air quality .................................................................................................... 18

3.2.2 Ambient noise quality ................................................................................ 18

ii

Page 6: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

3.3 Biological Resources ............................................................................................ 18

3.3.1 Bio ecological zone ..................................................................................... 18

3.3.2 Terrestrial ecosystem ................................................................................ 18

3.3.3 Terrestrial Fauna ........................................................................................ 19

3.3.4 Aquatic Ecosystem ..................................................................................... 19

3.4 Socio–economic Resources ................................................................................ 19 4. Institutional Arrangement and Grivence Redress Mechanism .............. 20

4.1 Institutional Arrangement .................................................................................. 20

4.2 Grivence Redress mechanism ............................................................................ 20 5. Specific Environmental Management Plan .................................................... 21 6. Conclusions and Recommendations ................................................................ 28

6.1 Conclusions ........................................................................................................... 28

6.2 Recomendations ................................................................................................... 28 Reference ....................................................................................................................... 29 Appendix A: Field Photos .......................................................................................... 30 Appendix B: Monitoring Checklist .......................................................................... 32 Appendix C: Contract Agreement Between DESCO and Simens India ...... 42 Appendix D: A3 Size Map .......................................................................................... 46 Appendix E: Environmental Clearence Certificate ........................................... 47

iii

Page 7: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

List of Tables

Table 1.1 : Proposed Twenty Four 33/11kv Substations in DESCO Area ............ 4 Table 1.2 : Selected IESCs and Parameters ................................................... 9 Table 2.1: The composition of the main team .............................................. 14 Table 2.2: The composition of the multidisciplinary field team ....................... 14 Table 3.1: Visited proposed sites at 1st Environmnetal Monitoring ................. 17

List of Figures

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kv Substations in DESCO Area ....................................................................................................... 3 Figure 4.1 : Institutional arrangement of DESCO for compliance and monitoring .. ..................................................................................................... 20

iv

Page 8: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Unit of Measurement

1 Bigha = 33 Decimals

1 Katha = 1.65 Decimals

1 acre = 0.404686 Hectare

v

Page 9: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Abbreviations and Acronyms

ADB Asian Development Bank

BOD

CEGIS

Biological Oxygen Demand

Center for Environmental and Geographic Information Services

DESCO Dhaka Electric Supply Company Limited

DO

DoE

Dissolved Oxygen

Department of Environment

DBH Diameter at breast height

BECA Bangladesh Environement Conservation Act

BECR Bangladesh Environmental Conservation Rule

ECR Environmental Conservation Rule

ERF Extracting area Rehabilitation Fund

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EPC Engineering, Procurement and Construction

GoB Government of Bangladesh

IESCs

IUCN

Important Environmental and Social Components

International Union for Conservation of Nature

SDG Sustainable Development Goal

SPM Suspended Particulate Maters

SPS Safeguard Policy Statement

ToR Terms of Reference

vi

Page 10: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Summary Statement

The environmental monitoring was carried out on monthly basis (6 nos field visit) to understand the EMP compliance status of 6 substation areas out of 24 substation under the project - Augmentation and Rehabilitation of Distribution System in DESCO Area. As there was no construction activity, here, base information collected and it was found that initial visit was completed by the officials of Siemens and Topographyical Survey is being started to understand the shape, form, level and geographical position of the proposed 24 sites. At this stage, it was identified that existing physical, biological and social conditions observed to get an insight about the base situation. During the construction, the monitoring team will visit physical, biological and social environmental status of the construction site based on prepared questionnaires which have been specified both in qualitative and quantitative approaches. The labors, site manager, HSE manager, and relevant stakeholders will be consulted and explored environmental and social issues like occupational health and safety and working condition status (i.e. labor shed, toilet facilities, source of drinking water, wash room, kitchen etc) and gender status and equal opportunity for those labors. The compliance result will be specified based on the set indicators and presented as in a matrix in Appendix B for both compliance and non compliance status.

vii

Page 11: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

1. Introduction

1.1 Background

1. The People’s Republic of Bangladesh has scaled up its priority to strengthen the electricity production, transmission, and distribution for overall growth and development of the country. In this respect, Bangladesh Govt. has set their goal in providing access to affordable and reliable electricity for all by 2021. With the ever growing demand for energy to cope with the impact of climate change on the natural environment and to ensure adequate supply of energy and its efficient use has become the key factor for sustainable development goal (SDG).

2. To meet up this increasing demand, Dhaka Electric Supply Company Limited (DESCO) has taken initiatives to expand its infrastructure in the distribution system with the construction of the new line, substations, and renovation of existing substations. This project has already obtained the site and environmental clearance certificate from DoE to start the construction work.

3. The project should be implemented in compliance with all the applicable Environmental and Social Rules and Regulations under the Environmental conservation Rule (ECR) 1997 of Bangladesh, Environmental and Social Management Plan and Monitoring plan described in the EIA report as well as the requirement of Project financer- Asian Development Bank (ADB).

4. In this context, Center for Environmental and Geographic Information Services (CEGIS), a public trust under the Ministry of Water Resources requested by DESCO for conducting Environmental Compliance Monitoring of Construction of Twenty Four 33/11kv Substations in DESCO Area. This compliance monitoring would be very helpful to establish EMP to make this proposed project environmentally friendly and sustainable. Presently, there is no construction activity, therefore, the progress of work and base condition on the proposed sites identified base on primary and secondary data. Besides, A checklist has been prepared to monitor all indicators regarding national laws and policies as well as the ADB loan covanents. The assessment of the physical environement like air,noise,soil and water will be substantiated in the next monitoring report.

1.2 Objectives

1.2.1 Main Objective

5. The main objective of the environmental monitoring is to observe how EMP is compiled in relation with national and international standard in pre-construction, construction and operation phase of the project.

1.2.2 Specific Objectives

6. The specific objectives of the environmental monitoring are to:

i. Analyze the water and air quality in pre and construction phase of the project ii. Analyze noise in three stages of the project iii. Explore land characteristics in the project sites iv. Analyze the waste management system of concerned authority or EPC

Contractor

1

Page 12: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

v. Monitor working condition and occupational health safety during project lifetime

vi. The environmental compliance monitoring would include: vii. Analysis of Environmental and Social Safeguarding Laws and Policies of

Bangladesh

7. Description of Environmental and Social Management, and Monitoring Plan described in the EIA in line with ADB’s requirements.

1.3 Project locations

8. Following figure 1.1 and table 1.1 shows the locations of proposed 24 (twenty four) 33/11kV Substations in DESCO area. An A3 size map is shown in the Appendix D.

2

Page 13: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kv Substations in DESCO Area

9. In the EIA report the sub-stations area and locations were mentioned clearly. But in the meantime the DESCO authority has changed /shifted some of the sub-station area due to land availability. The final list of the proposed sub-stations area mentioned in the Table 1.1.

3

Page 14: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

Table 1.1 : Proposed Twenty Four 33/11kv Substations in DESCO Area

Sl. No.

Name of the substations

Address Remarks

1 Kazipara Switching Station

740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station)

-

2 Mazar Road Plot: J-82, J-10 Eastern Housing Mirpur,Dhaka

Relocated: Mazar Road shifted to Eastern Housing. It is fallow land and suitable for housing and any kind of infrastructure.

3 Kalshi (Shenpara)

Bijoy Rakeen City Plot: 1/2, Block: D, Section: 15, Mirpur, Dhaka.

From Mirpur Road Beside Police Staff College and Behind Institute of Science Trade & Technology. (At the end of Piling work.)

4 Mirpur DOHS-2 Road#33, Plot#837, Mirpur 14, Dhaka.

On the Right after entering in DOHS

5 Lake City Concord

Mouza: Joarsahara, Ward No: 17, Khikhet, Dhaka

Area of Land: 11.8 Katha1.

6 Satarkul-2

Sun Valley Abason, Swadesh Properties Ltd. Plot#11, Block#E Road#7, Sector#2 Mauza: Satarkul Thana: Badda

Area of Land: 16.0 Katha Before United City

7 Satarkul-1

Road# 317,Plot#4, Sect#03, Dag:1100,1105,1106 United City Mauza: Satarkul Thana: Badda

Area of Land: 1.0 bigha2

8 Barua

Plot# 13,Road# 11, Block#A,Sector#1, Swarnali Properties Mauza: Borua, Thana: Dakshinkhan.

Area of Land: 20 Katha.

9 Gulshan-03 BRAC university, Merul Badda, Dhaka

Relocated: Gulshan-03 shifted to Merul Badda

10 Basundhara Block G

AIUB New campus Relocated: Basundhara shifted to AIUB

11 Sholahati Uttara Third Phase (Sector-15, Block-G, Commercial Plot) Besides Rajuk Apartment Project

Enter through sector-12, Cross khalpar and Grid. Turn Left from Diabari Golchokkor (first Golchokkor)

12 Mohakhali DoHS

Mohakhali DoHs, Dhaka Cantonment, Dhaka

The proposed location is located at Mohakhali DoHS, beside the British American Tobacco industry.

1 1 katha = 1.6 decimals 2 1 bigha = 33 decimals

4

Page 15: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

Sl. No.

Name of the substations

Address Remarks

13 Uttarkhan (Promy)

Promy Agro Foods Ltd., Moinertek Mauza: Gobindapur, C.S.-305,306. R.S.-538

Area of Land : 22-23 Katha

14 Tilargati, Tongi Sataish

S.A.R.S-01, S.A-129, R.S-251, Mauza-Kakil 27, Tilargati, Tongi.

West from S&D, Near Uttara Proborton City & Sangbadik Bari, Tilargati, Sataish,Tongi.

15 Agargaon

New Colony, Behind BCS Computer City,With Probin Hitoishi Hospital, Opposite to the Agargaon S&D.

Existing 33/11 KV substation

16 Mirpur DOHS At the end of R#10 , DOHS, Mirpur-12.

Existing 33/11 KV substation

17 Mirpur-06 Near Al-Markajul Mosque & Market of Section-06, Original Mirpur-10.

Existing 33/11 KV substation

18 Tongi-01 BSCIC I/A, Tongi, Gazipur Existing 33/11 KV substation

19 Tongi-02 Cherag Ali, Beside Tongi S&D Division.

Existing 33/11 KV substation

20 Civil Aviation (CAAB)

Left from Jashimuddin, Beside Airport Boundary & Sector#1) Kurmitola, Uttara, Dhaka

Existing 33/11 KV substation

21 ADA Beside Civil Aviation Quarters’, Kaola.

Existing 33/11 KV substation

22 Sector – 14,Uttara

Existing DESCO’s Sub-store

23 Tongi (BSCIC) Near BPDB’s 80 MW Power Station, Tongi.

Existing 33/11 KV substation

24 Baunia Mouza: Faridabad, Airport, Uttara, Dhaka

Existing 33/11 KV substation

Source: PD office, DESCO, May, 2017.

1.4 Scope of Studies

10. In line with the aforementioned objectives the scope of the services should cover the following:

i. Monitoring ambient air quality of the project site and its adjoining area before construction stage;

ii. Review of environmental management and environmental monitoring plan suggested in the EIA report in line with the action plan proposed by ADB;

iii. Upgrade (if required) the environmental monitoring framework and work plan specifying the indicators, method, location, time, frequency of monitoring provided in the EIA that shall be followed by the EPC contractor;

iv. Monthly monitoring of construction activities to see their compliance with national environmental and social regulations, and ADB’s performance standards on social and environmental sustainability;

5

Page 16: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

v. Physical observation (monthly) to assess that all mitigation measures are carried

out or in place in conformity with the EMP and action plan;

vi. Monthly monitoring of implementation of environmental monitoring activities as specified in the environmental monitoring plan;

vii. Monthly monitoring of different activities of EPC contractor regarding analysis of air quality, water quality, soil texture and quality, soil and land erosion, noise measurement, waste management, etc in connection with the environmental monitoring plan;

viii. Monthly monitoring of socio-economic issues like community safeguard due to pollution, hazards and employment opportunity;

ix. Suggestion of pollution prevention and mitigation measures to ensure environmental safeguard, to ensure compliance with national environmental and social regulations;

x. Keep close liaison with the project implementation office (Project Director), and EPC contractor;

xi. Provide an interim monitoring report at the end of every three (3) months in line with the reporting requirement of DESCO/ ADB satisfying equator principles;

xii. Provide a monitoring report at the end of every six (6) months in line with the reporting requirement of ADB satisfying equator principles.

1.5 Monitoring Law and Policy Standard

11. The Environment Conservation Rules place construction of power plant into the Red category. The site clearances based on IEE and for environmental clearance certificate have been obtained from Department of Environment (DoE). As per the Bangladesh Govt. policy standard, environmental compliance monitoring is one of the important part that would be initiated following the Environmental compliance monitoring guidelines by DoE and the agreement between ADB and Bangladesh Govt based on the ADB loan covenants. DESCO has taken initiative to expand its infrastructure of the distribution system through construction of new lines, installation of new substations and rehabilitation of existing substation in order to provide new connections to the incoming consumers. In this regard, during carrying out the EIA study for the proposed twenty four 33/11kV Substations, the DESCO has developed EMP that needs to be complied following the national guidelines of Bangladesh and policies of Asian Development Bank. Now, the purpose of the environmental monitoring is to monitor whether the construction activities are performing based on the EMP or is creating any environmental impacts or any adjustment is required in safeguard measures.

1.5.1 Compliance with National Environmental Laws

12. The environmental legislation of GOB gives importance to reduce the negative impacts of infrastructure development projects, and give priority for the enhancement of positive impacts due to the project implementation. It conforms the National Environmental Policy

6

Page 17: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

1992 based on the Agenda 21 of Rio Conference and subsequent enactments of the Bangladesh Environmental Conservation Act (BECA) 1995 and Bangladesh Environmental Conservation Rules (BECR) 1997.

National Environmental Laws Compliance Requirement Performance of DESCO

Bangladesh Environmental Conservation Act (BECA) 1995 and Bangladesh Environmental Conservation Rules (BECR) 1997

The Construction of Twenty Four 33/11kv Substations in DESCO Area requires environmental clearance certificate (EC)

The environmental clearance (valid for 1 year) for the project was obtained from the DoE on 25.06.15. The processing for renewal is ongoing as per the Government rules.

3 sites under this project

have been relocated that require Environmental clearance certificate. The completion of EIA for these relocated sites is in under process.

1.5.2 Bangladesh Government Regulation and compliance monitoring

13. The Bangladesh Environment Conservation Act of 1995 (ECA, 1995) is the key legislation in relation to environment protection in Bangladesh. This Act is promulgated for environment conservation, standards, development, pollution control, and abatement. It has repealed the Environment Pollution Control Ordinance of 1977. The Act has been amended in 2000, 2002, 2007 and 2010.

The main objectives of the Act are:

• Conservation and improvement of the environment; and

• Control and mitigation of pollution of the environment.

The main strategies of the Act can be summarized as:

• Declaration of ecologically critical areas and restriction on the operations and processes, which can or cannot be carried/initiated in the ecologically critical areas;

• Regulations in respect of vehicles emitting smoke harmful for the environment;

• Environmental clearance;

• Regulation of the industries and other development activities’ discharge permits;

• Promulgation of standards for quality of air, water, noise and soil for different areas for different purposes;

• Promulgation of a standard limit for discharging and emitting waste; and

• Formulation and declaration of environmental guidelines.

14. The ECA, 1995 specified that no industrial unit or project shall be established or undertaken without obtaining Environmental Clearance from Director General in a manner prescribed by the Rules. The project promoter must obtain Environmental Clearance from the Director General of Department of Environment (DoE). An appeal procedure does exist for those promoters who fail to obtain clearance. Failure to comply with any part of this Act may result in punishment of imprisonment or fine or both. The DoE executes the Act under the leadership of the Director General.

7

Page 18: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

15. The Bangladesh Environment Conservation Act (Amendment), 2000 focuses on: (1) ascertaining responsibility for Compensation in cases of damage to ecosystems, (2) increased provision of punitive measures both for fines and imprisonment and (3) fixing authority on cognizance of offences.

16. The Bangladesh Environment Conservation Act (Amendment), 2002 elaborates on: (1) restriction on polluting automobiles, (2) restriction on the sale and production of environmentally harmful items like polythene bags, (3) assistance from law enforcement agencies for environmental actions, (4) break up of punitive measures and (5) authority to try environmental cases.

17. The Bangladesh Environment Conservation Act (Amendment), 2010 introduces new rules & restriction on: a) Ensure proper management of hazardous wastes to prevent environmental pollution and Health Risk, b) No remarked water body cannot be filled up/changed; in case of national interest; it can be done after getting clearance from the respective department; and c) Emitter of any activities/incident will be bound to control emission of environmental pollutants that exceeds the existing emission standards (d) Government may declare any ecosystem as “Ecologically critical area” if it appears to be degraded or expected to be degraded and take all precaution measures to protect that ecosystem. In addition, government shall stop any ongoing activities and will not allow any new developments in the ecosystem after declaration of “Ecologically Critical Area”.

18. The Bangladesh Environment Conservation Rules, 1997 is the first set of rules, promulgated under the ECA 95 (so far there have been three amendments to this set of rules – February and August 2002 and April 2003). The Environment Conservation Rules of 1997 has provided categorization of industries and projects and identified types of environmental assessments needed against respective categories of industries or projects.

19. Among other things, these rules set (i) the National Environmental Quality Standards for ambient air, various types of water, industrial effluent, emission, noise, vehicular exhaust etc., (ii) the requirement for and procedures to obtain environmental clearance, and (iii) the requirement for IEE and EIA’s according to categories of industrial and other development interventions.

20. The proposed project, according to the DoE, is considered under the “Red” category of the Environmental Conservation Rules, 1997.

21. Noise Pollution (Control) Rules, 2006 gives the authority to all the Union Councils, Paurasabhas, City Corporations, City Development Authority (i.e. RAJUK, CDA, KDA, RDA etc.) to mark off the areas under their jurisdiction as silent, residential, mixed, commercial or industrial. They should also put signs to mark those areas. The act also describes the approved standard limit of sound in the added schedule 1 and 2. In the schedule 1, silent area means area up-to a radius of 100 meters around hospitals or educational institutions or special institutions/ establishments identified/to be identified by the government. In the silent area, it is prohibited to use any kind of horns of vehicles, audio signals and loudspeakers. According to this act, daytime is counted from 6am to 9pm whereas nighttime is counted from 9pm to 6am.

22. The Motor Vehicle Ordinance, 1983 stated to impose a penalty of maximum two hundred taka for those vehicles that are emitting smokes that poses health hazard in the public places. It also restricts the passenger from smoking in public service vehicles and in any other vehicles with notice of not smoking. This ordinance is enforced occasionally but a regular enforcement would be helpful to reduce air pollution in big cities including Dhaka.

8

Page 19: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

However, it is to be noted that amount of the penalty is very low which may be revised as well.

23. The Environment Court Act, 2000 provides for the establishment of environment courts and matters incidental thereto. This act also provides the jurisdictions of environment court, penalty for violating court’s order, trial procedure in special magistrate’s court, power of entry and search, procedure for investigation, procedure and power of environment court, authority of environment court to inspect, appeal procedure and formation of environment appeal court.

1.5.3 Compliance with DoE’s Guidelines

24. As mentioned above, the project activities fall under the ‘red’ category according to the Environment Conservation Rules, 1997. For projects under this category, it is mandatory to carry out IEE and subsequently EIA including Environmental Management Plan (EMP) and where necessary develop a Resettlement Plan for getting environmental clearance from the DoE. The DoE has issued EIA Guidelines for Industries and addresses the IEE and EIA for several industrial sectors and activities. Each Project Proponent shall conduct an IEE or EIA and is expected to consult and follow the DoE guidelines. The provisions of the environment legislations and the EIA guidelines of the DoE have been reviewed under this study. The DoE has issued application procedure for obtaining site/environmental clearance.

25. Environmental quality standards for air quality, noise, odor, sewage discharge, industrial effluents, and industrial project emissions for Bangladesh

26. The Environment Conservation Act, 1995 and the Environment Conservation Rules, 1997 are the main legislative base in Bangladesh for protection and conservation of natural environment. The Environment Conservation Rules (1997) place activities of power plant into the Red category. However, the Safeguard Policy Statement (SPS) of Asian Development Bank has also been reviewed since ADB is financing the project in partnership with the GoB. As per the ADB categorization, the sub-station construction activities are under the category B considering the significance of the project’s potential environmental impacts. Therefore, the EMP is prepared based on the combination of both the national and the ADB.

27. The environmental standards are determined in the Environmental Conservation Rules. The standards for air, water, sound, odor and other components of the environment is started to monitor in accordance with the standards specified in Schedules - 2, 3, 4, 5, 6, 7 and 8. The Bangladesh standards, in general, are less stringent compared to the developed countries. This is in view to promote and encourage industrialization in the country. The Bangladesh standards are not for any specific period of time. There is no provision for partial compliance too. For this reason, monitoring is based on the national standards unless there is absence of clear standards; only then ADB’s standard is being considered.

28. Following IESCs and parameters are selected for monitoring in DESCO’s 24 sub-station areas which have presented in Table 1.2.

Table 1.2 : Selected IESCs and Parameters

IESCs Parameters

Air Suspended Particulate Maters (SPM), Sulphur dioxide, Carbon Monoxide, Oxides Nitrogen

9

Page 20: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

IESCs Parameters

Waste Waste generation and proper waste disposal

Noise dBa unit at both day and night time

Water (if any) DO, PH, BOD, Arsenic whether water is usable for irrigation or by fisheries

Biodiversity Habitat conversion and fragmentation

Health & Safety Risk of electrocution, safety measures within the construction site, emergency plan.

Resettlement livelihood challenges, restoration process, compensation process, whether any complaints from affected people

29. The results of the monitoring are needed to compare the established benchmarks/ baseline and compliance status and help to identify the areas where adverse environmental and social adverse impacts are still occurring. It would be helpful to formulate the corrective actions accordingly and in a timely manner.

1.5.4 ADB loan covenants with the DESCO

30. According to the Loan Covenant Article (II), section 2.01, DESCO should carry out the project, with the due diligence and efficiency and in conformity with sound administrative, financial, engineering, environmental and power sector practices. For the execution of project following criteria should be followed.

Implementation arrangement

31. DESCO should ensure the project implementation in accordance with the detailed arrangements set forth in the PAM. Besides, it is the responsibility of DESCO to ensure their project management staff who have the qualification to undertake necessary tasks of procurement, construction, supervision, inspection, and testing of equipment, payments to contractors, monitoring, environmental and social safeguards due diligence and reporting of progress relevant to the components under their responsibility.

Environment

32. DESCO should ensure that the preparation, design, construction, implementation, operation, and decommissioning of the project and all project facilities comply with;

• All applicable laws and regulations of the relating to environment, health and safety

• The environmental safeguard

• The EARF

• All measures and requirements set forth in the respective IEE and EMP and any corrective or preventive actions set forth in a safeguard monitoring report

• Land Acquisition and Involuntary Resettlement3

• All land acquisition and resettlement activities are implemented in compliance with

3 There is no land acquisition and RP related activities that have been found in EIA study report under this project.

10

Page 21: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

• Compensation and other entitlements have been provided to affected people in accordance with the RP

• A comprehensive income and livelihood restoration program has been established in accordance with the RP.

Human and financial Resources to implement safeguards requirements

33. The DESCO should make available, or cause the project executing agency to make available, necessary budgetary and human resources to fully implement the EMP, the RP and any small ethnic community peoples planning framework.

Safeguards-related provisions in bidding documents and works and work contracts

34. The DESCO should ensure the following compliance in relation to contract p or bidding during the project implementation.

• Comply with the measures and requirements relevant to the contractor set forth in the IEE, EMP and RP (if required) any small ethnic community peoples plan and any corrective or preventive actions set out in a safeguard monitoring report.

• Make available a budget for all such environmental and social measures

• Provide the borrower with a written notice of any unanticipated environmental, resettlement or small ethnic community peoples plan.

• Adequately record the condition of roads, agricultural land, and other infrastructure prior to starting to transport materials and construction

• Fully reinstate pathways other local infrastructure and agricultural land to at least their pre-project condition upon the completion of construction

Safeguard Monitoring and Reporting

The DESCO should comply the following section:

• Submit semiannual safeguards monitoring reports to ADB and disclose relevant information from such reports to the affected person

• Any anticipated environmental and social as well as impacts arise during the construction, implementation, or operation of the project that were not considered in the IEE , the EMP or the RP promptly inform ADB of the occurrence of such risks and impacts with detailed description of the events and proposed corrective action plans.

• The Monitoring process should be verified by the external experts

• Reporting would be completed based on the any potential beach of compliance with the measures and requirements set forth in the EMP

Labor standards

Following labor standards should be followed as per AND loan covenants:

• Comply with all applicable labor law and related international treaty obligations of the borrower and do not employ child labor as defined under the Bangladesh law

• Provide Safe working condition for male and female workers

• Carry out HIV/Aids and human trafficking prevention and awareness campaigns in the campsites and corridor of influence

11

Page 22: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Introduction

• Engage women workers as wage laborers depending on their skill and

• Provide equal wage for equal work between men and women.

Project Reviews

• The project progress would be reviewed by the ADB with necessary midcourse corrections

• The Assistance should be provided by the Executing Agency (i.e. DESCO).

35. The environmental monitoring will assess the compliance that has been suggested under the Bangladesh Govt. laws, policies and national standards (i.e. air, noise and water quality) and ADB loan covenants. As there is no involuntary resettlement and ethnic minority issues, therefore, this monitoring assess the environmental and social safeguard issues in accordance with the Govt. laws and ADB loan covenants like the above mentioned ways.

12

Page 23: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

2. Approach and Methodology

2.1 Introduction

36. At the time of Monitoring of the project area and compiling this report (June 2017) there is no construction, rehabilitation or remediation activities had commenced on site and none is envisaged to commence until August 2017 at the earliest. However, a monitoring team from CEGIS visited 6 sites of proposed 24 substations to monitor existing physical, ecological and socio-economic conditions of the proposed project sites. In the following sections, these components along with indicators, tools and techniques are discussed.

2.2 Overall Approach

37. The objective of the Environmental Compliance Monitoring is to identify environmental issues and to work proactively with the project team to resolve these issues before they affect the construction schedule. The proactive approach become very helpful to identify where violations have occurred, but rather to take an active role in the design, planning and sequencing of the project, to identify problem areas ahead of time and to suggest solutions. In this environmental monitoring, a proactive approach has been followed and mobilizes a multidisciplinary team to monitor whether the construction activities are performing based on the EMP or is creating any environmental impacts or any adjustment is required in safeguard measures. At this stage of the project, no construction activities have been found but existing physical, biological and social scenario have been identified following the proactive approach regarding the issues related to the environmental monitoring.

2.3 Study mobilization

38. In the Inception Phase, a roadmap for environmental monitoring prepared with detailed approach and methodology. Following the roadmap, the monitoring team visited the project site and collected relevant data. Before the visit, the team also prepared necessary tools for data collection.

39. Thus, a comprehensive checklist on environmental and social compliance was prepared. A preliminary checklist (Appendix B) was first prepared considering the recommendations suggested in the Environmental Management Plan (EMP) of the EIA report of the Augmentation and Rehabilitation of Distribution System in DESCO area

40. In the EMP included in the EIA report, a number of guidelines for construction activities was recommended to be followed, which was prioritized during the preparation of the checklist, as compliance of those suggested measures would ensure the overall environmental protection and social security. Along with this, Equator Principles were also followed in the preparation of checklist.

2.4 Study Team Mobilization

41. A contract agreement between DESCO and CEGIS (the Monitoring Consultant) was signed on 9 May, 2017. From this time, a multidisciplinary team mobilized to prepare work plan, monitoring check list and other tasks related to the Terms of Reference (ToR).

42. After signing the Contract Agreement, CEGIS mobilized a core group of highly skilled professionals as proposed in the technical proposal. Initiatives had been taken for

13

Page 24: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Approach and Methodology

accomplishing the study within the expected time-frame through formulating an action plan, setting up of the office in Dhaka, forming the multidisciplinary field team and providing all necessary logistics and technical supports to perform required investigations.

43. The consultant (CEGIS) started work under the overall supervision of the Project Director, DESCO and maintain close liaison with DESCO offices (both field and central offices). The Team Leader is responsible for direct supervision of the study. He guided the multidisciplinary team to achieve the goal of the study. The progress of the study was reviewed in weekly progress review meeting. Each report and deliverable was reviewed carefully by the team members and Team Leader and finally, checked by technical and linguistic editors.

44. As per the guidance of the ToR directives, a multidisciplinary expert team (Photo Appendix A) was formed with suitable allocation of time for each professional. Table 2.1 and 2.2 present the composition of the study team with their designation.

Table 2.1: The composition of the main team

Sl. No. Name of Professional Position Assigned

1 Engr. Jalal Ahmed Chawdhury

Environmental Expert/ Transmission Line/ Power Plant Expert

2 Dr. Dilruba Ahmed Sociologist

3 Subrata Kumar Mondal Economist

45. As per commitment the following multidisciplinary team was mobilized for collecting data from the field.

Table 2.2: The composition of the multidisciplinary field team

Sl. No. Name of Professional Position Assigned

1 Amith Dutta Anthropologist

2 Md. Nurul Hoque Upal Water Resource Engineer

3 Bilkish Sultana Electrical Engineer

4 Ujjal Kumar Saha Ecologist

2.5 Methodology

2.5.1 Physical environment

a) Ambient air quality

46. Air quality is an indicator of purity of air for respiration process of human being plants, and animals. Poor air quality can affect human health and deteriorate surrounding environment. Air quality was monitored through visual inspection as potential pollution sources were from external air contamination.

b) Noise level

47. Noise level is an important parameter as excessive noise may create disturbance to local communities, ecosystem and workers at worksite due to project activities. Short-term noise exposure can be overcome with rest, but if exposure is sustained, it may result in irreversible long-term damage. Hearing loss in the workplace can lead to safety risks if

14

Page 25: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Approach and Methodology

workers are unable to hear alarms or critical communications from other workers. Noise level was perceived from individual acoustics of monitoring team.

c) Waste management

48. An inefficient waste management system may create serious negative impacts like infectious diseases, land and water pollution and obstruction of drains. As there was no waste generated from project activities, there was no inevitability for monitoring of waste management.

d) Water quality

49. Water quality is an important issue here since construction activities might pollute nearby water sources. In addition, drinking water quality is also an important consideration in terms of health concern of project employees. In this context, water quality was monitored on site through visual assessment likewise air quality.

e) Soil quality

50. Soil is an important, but often overlooked component of water management. Soil quality refers to the ability of soil to perform its functions. Soil is especially important in regulating runoff of storm water and in supporting trees, shrubs, and herbs. Management practices are often needed to restore soil quality after development. The soil composition of the project sites were investigated visually to observe soil quality and present soil condition will be understood in the next stage of monitoring as the construction activities has not yet been started.

2.5.2 Biological environment

a) Ecological resources

51. This component entails the terrestrial lives and habitats of the ecosystem, and their natural processes. Many construction activities might directly or indirectly lead to the overall disruption of surrounding ecosystem and biodiversity. Such disruptive events might affect birds and wildlife during construction phase of the project. A number of measures have already been suggested in the EIA report to avoid these ecosystem disruptions. In the monitoring, presently, the overall project area condition observed and identify vegetation (i.e. Terrestrial and Aquatic) habitat (i.e. Native Birds, small Mammals, Reptiles and Amphibians). With the starting of construction work, EMP (provided in EIA report) will be checked whether they are compiled or not. Most of the data is started to collect through visual observation, True plus (tree height and DBH measurement) and consultation with local people.

2.5.3 Socio-economic environment

a) Compensation

52. The project proponent is obliged to provide compensation to the land owners if it acquires private lands. Those affected stakeholders is started to monitor as they got proper compensation or not. Besides, the collected information will be updated at the monthly on site field visits. In this regard, a checklist is prepared and data will be collected through community meeting, informal group discussion and key informant interview.

15

Page 26: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Approach and Methodology

b) Livelihood and living condition

53. Livelihood and living condition of those primary stakeholders have started to monitor through in depth observation, group discussion and key informant interview. The present livelihood and living condition of surrounded people of project area have been identified and will also be updated at the next stage of monthly environmental compliance monitoring.

c) Community health, safety and security

54. Occupational health safety and security will be monitored through field visit and public consultation (i.e. Informal discussion, Community meeting etc.) during construction phase of the project. At this stage no construction activity is found so, community health, safety and security condition will be monitored at the further stage of this environmental monitoring.

d) Labor and working condition

55. During construction, labor and working condition will be monitoring based on observation and consultation with primary and secondary stakeholders. The present labor and working condition of surrounded project areas have been identified through informal meeting, observation and key informant interview.

16

Page 27: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

3. Monitoring Results

3.1 Introduction

56. Dhaka Electric Supply Company limited has made a Contract Agreement (Appendix C) with Simens Ltd India in consortium with Siemens Bangladesh to Design, Supply, Install & Commission 24 (twenty four) 33/11kV Substations in Turnkey Basis in DESCO area under the Dhaka and Gazipur districts against Bid No. IFB 01/2016, Package-C1 of Lot-3 under ADB Loan No.: 3087- BAN: under “Power System Expansion and Efficiency Improvement Investment Program” (Trench 2). A team from Siemens has already visited and started Topographical Survey to understand geographical position , shape, form for the proposed 24 sites.

57. With the consultation with the DESCO officials, the monitoring team understood that any construction activity in any of the locations of 24 sites had not yet been started. In this first monitoring, a multidisciplinary team visited 6 sites with a checklist (Appendix B) and again found no construction activity within the project vicinity. The findings of those sites are stated in Table 3.1.

Table 3.1: Visited proposed sites at 1st Environmnetal Monitoring

Sl. no. Name of the Substations

Address Amount of

Land Remarks

01 astern Housing Eastern Housing, Block J, Pallabi, Mirpur, Dhaka

9.5 Katha (15.68 decimals)

Mazar road Shifted to Eastern housing. It is an fallow land and arranged for eastern housing project.

02 AIUB Campus AIUB Campus, Word no : 17, Badda, Dhaka

8 Katha (13.2 Decimals)

Bashundhara shifted to AIUB. It is an under developed residential and commercial area. The proposed area is closely associated with newly shifted main campus of American International University of Bangladesh (AIUB)

03. BRAC University (Merul Badda)

Newly Proposed Brac university Campus, Word no :21

12 Katha (19.8 Decimals)

Gulshan 3 shifted to Merul Badda. Primarily, this proposed land was acquired by BRAC and selected for the construction of BRAC’s permanent campus. DESCO got this land from BRAC and planned to set up a sub-station

04. Uttarkhan (Promy Agro Food)

Promy Agro Food Ltd. Plot :17, 19,21,23,24,25,26 Road: 12, Block A, C.S Dag: 2320,2321,2325

16 Katha (26.4 Decimals)

It is plain fallow land. No sensitive receptors found adjacent to the proposed substation area.

17

Page 28: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Monitoring Results

Sl. no. Name of the Substations

Address Amount of

Land Remarks

Mauza: Dakhin Khan , Asian City.

05. Lake City Concord

Mauza: Gobindapur, C.S-305,306,R.S -538 Khilkhet, Dhaka

12 Katha (19.8 Decimals)

It is Fallow land, close to the Lake city Concord residential area.

06. Uttara sector 14 Plot: 67/69/71, Road no: 14, Sector -14, Uttara, Dhaka

10 Katha (16.5 Decimals)

It is a store room of DESCO used to dump electric materials of DESCO office.

Source: Monitoring Study. CEGIS, June, 2017

58. Based on field visit the existing site condition has been narrated in the following sub-section:

3.2 Physical Environment

3.2.1 Air quality

59. The monitoring team did not notice any construction or operation activity in the project area or in its vicinity. So the present air quality of the project area is solely dependent on the vehicle movement (emission from vehicle exhaust, dust due to vehicle movement etc.) around the area.

3.2.2 Ambient noise quality

60. The noise levels around all the project sites were within acceptable limits. As there was no construction or operation activity in or around the project site, the project sites in most cases were calm and quite. However, there was some insignificant noise generated due to traffic movements around the vicinity of some project sites, which were within the permissible limits.

3.3 Biological Resources

3.3.1 Bio ecological zone

61. According the International Union for Conservation of Nature (IUCN), Bangladesh has divided the country into 25 Bio-ecological Zones in context of Biological diversity. The project area has fallen under Bio-ecological Zones of a) Brahmaputra - Jamuna floodplain, and b) Madhupur Sal Tract.

3.3.2 Terrestrial ecosystem

62. The proposed substations (24 numbers) fall mostly in the urban area. The urban area is denuded due to the practice of urbanization and support urban lifestyles especially housing and infrastructure development. A few number of the project area is vegetated by local tree species such as Banana (Kola), Mango (Aam), Barry (Jaam), etc. In some locations herbs found scattered with a limited number of individuals i.e. Bhat (Clerodendrum viscosum), Biskantali (Polygonum Sp), Teet Begun (Solanum nigram), etc. The vegetation provide habitat for some small wildlife species

18

Page 29: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Monitoring Results

3.3.3 Terrestrial Fauna

63. Amphibian species favor wetland and the marginal dried areas. The available species are Asian Brown Tree frog (Polypedates leocomystax), Cricket frog (Fejervarya Sp.) and Common Toad (Duttaphrynus melanostictus).

64. Reptiles are rare in these urban locations. Some species have found such as Bengal Lizard (Varanus bengalensis), Common Garden Lizard (Calotes versicolor), Buff-striped Snake (Amphiesma stolata), etc.

65. Common bird species of the project area are: Common Myna (Acridotheres tristis), Asian Pied Starling (Sturnus contra), Red-vented Bulbul (Pycnonotus cafer), Oriental Magpie Robin (Copsychus saularis), Spotted Dove (Streptopelia chinensis), Blue Rock Pigeon ( Columba livia), Coppersmith Barbet (Megalaima haemacephala), Jungle Babbler (Turdoides striata), Black Drongo (Dicrurus macrocercus), Brahminy Kite (Heliastur indus), Common Kingfisher (Alcedo atthis), White breasted Kingfisher (Halcyon smyrnensis).

3.3.4 Aquatic Ecosystem

The wetlands in these areas remain completely dry and local people are cultivating seasonal vegetables in this area during dry period. The Cricket Frog (Fejervarya Sp.) and Skipper Frog (Euphlyctis cyanophlyctis) commonly found amphibians in most wetland habitats. Common Smooth Water Snake and water birds are severely affected by the alteration of the natural habitat. Wetland degradation has left very little or no shelter to waterfowl. The Indian Pond Heron (Ardeola grayii), Little Egret (Egretta garzetta), Common Kingfisher (Alcedo atthis), Little Cormorant (Microcarbo niger), Common Moorhen (Gallinula chloropus), etc.

3.4 Socio–economic Resources

66. The proposed project fall under the Badda, Kafrul, Gulshan, Mirpur, Khilkhet, Pallabi, Turag, Uttara, Biman Bandar Thana, Uttarkhan and Gazipur Sadar thana.

67. People showed greater interest and opined that there is urgency to install Substations to meet the growing demands of electricity. The availability of non-farm laborer is medium for both genders in the area. The study area includes some industries e.g. Garments Industry, ice-factory; Sweater factory, Conversion Natural Gas Company Limited, ice-cream factory, saw mill, sweetmeat factory, furniture factory, Cottage industries Blacksmith, handicrafts, bamboo works, cane works etc. The rate of industry labor varies due to types of work and industry. Male labor gets more wages than female labor.

68. The wage rate of the male laborers ranges between Tk. 400 /-per day for farm and Tk. 500 /-per day for non-farm activities. Besides, females are getting highest Tk.300/-per day and Tk. 200/- per day respectively for the non-farm activities. It is assumable that rapid industrialization and urbanization will take place if the uninterrupted supply of electricity is ensured. The officials of DESCO are aware to ensure occupational and health safety, and people’s participation with all stages of project implementation.

19

Page 30: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

4. Institutional Arrangement and Grivence Redress Mechanism

4.1 Institutional Arrangement

69. The organogram (provided by the DESCO) is responsible to monitor environmental compliance and monitoring during the project construction. The assistant engineer (electrical), assistant manager, and sub assistant engineer are working under supervision of the deputy project director for monitoring of augmentation, rehabilitation of distribution system in DESCO area. The project director is responsible to supervise and guide the whole work regarding monitoring and compliance. The following figure 4.1 shows the institutional arrangement those who are responsible to ensure monitoring and compliance in accordance with Govt. laws, rules regulations and ADB’s loan covenants

Project Director

Deputy project Director

Assistant EngineerAssistant Engineer

Sub assistant Engineer

Manager

Sub assistant Engineer

Figure 4.1 : Institutional arrangement of DESCO for compliance and monitoring

4.2 Grivence Redress mechanism

70. At this stage, There is no Grievence redress comitee to address the grivence redress but the EA will assist the grivence redress mechanism through their institutional arrangement. As there is no construction activities, no sign provided at the project office to accept peoples complain as well as redress the grivences. The subdivisional engineer will work as the field officer and would be responsible to arrange consultation for peoples awareness at the respective project sites.

20

Page 31: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

5. Specific Environmental Management Plan

71. There are fifty-four (54) Mitigation Measures extracted from the EIA report conducted and 37) Mitigation Measures are suggested as the SEMP plan for the proposed 24 substation under the augmentation rehabilitation and distribution system project in DESCO area.

72. The thirty-seven (37) common measures (presented in part I) are categorized into ten (10) environmental issues/topics, they are:

• Top soil (contains 2 measures) • Fauna/Wildlife (contains 1 measure) • Solid Waste (contains 4 measures) • Drainage congestion and flooding (contains 2 measures) • Noise level (contains 5 measures) • Air quality & dust (contains 3 measures) • Setting of construction camp (contains 12 measures) • Traffic congestion/road accident (contains 2 measures) • Community health and safety (contains 3 measures) • Occupational health and safety (contains 3 measures)

73. The fourteen (14) special measures (presented in Part II) are categorized into three environmental (3) issues/topics, they are:

• Water Pollution (contains 6 measures applicable to 4 substations), • Tree Cutting (contains 5 measures applicable to 6 substations), • Natural Habitat (contains 3 measures applicable to 9 substations).

PART 1

74. Mitigation Measures for the General/Common Impacts of Substation Subprojects, during construction

Sl. Environmental

Issue Proposed Mitigation Measures

Implementation Plan by Siemens

1.

Top soil

Ensure the topsoil excavated from the proposed construction site not be dumped or stockpiled anywhere.

We will label all uneven land and excavated topsoil will immediately spread in between site working area.

Confirm the sediment-laden runoff must be prevented from entering into nearby water courses, if erosion occurs from stockpiles due to their location in drainage paths.

Stockpiles will be planed and located such way (away from water courses) so that sediment-laden cannot runoff into nearby water courses.

2. Fauna (Wildlife)

Make sure that project workers and employees should not disturb, catch, fish, hunt, kill, trade and consumption of birds and wild animals available in natural environment around the project site.

We will provide official instruction (written, verbal and signboard) to all workers and employees to do not disturb wildlife. Also from management sites we will keep monitoring it throughout projects.

21

Page 32: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

Sl. Environmental

Issue Proposed Mitigation Measures

Implementation Plan by Siemens

Establish and enforce daily site clean-up procedures, including maintenance of adequate disposal facilities for construction debris.

One clear system under waste management will be established for daily clean of construction area.

3.

Solid Waste

Establish daily cleaning through adequate collection and storage of solid waste produces at project site because of various activities throughout the work site, construction yard and labour camp.

Sufficient number of workers will be trained on cleaning to maintain cleaning activities of site areas. Besides this separate waste bin with color code and labeling would be provided to collect and segregate different types of waste.

Ensure adequately safe handling and transportation, with no dropping from waste carrier, of the solid wastes to the disposal sites.

Under waste management training all site personnel and assigned cleaner would be instructed and trained on handling and transporting of waste. Standard tools will also provide to carry and transport waste.

Establish an order that under no circumstances dispose any materials in environmentally sensitive area (example: designated forest area, area of endanger/rear flora, natural drainage course).

Buckets, places and area will be placed or allocated far away from any environmentally sensitive’s area. Proper barricade will be provided along with billboard or signage to restricted waste and create awareness.

4. Drainage

Congestion

Confirm an effective system for smooth draining of storm and rain water, and resulting no water logging (for rain and flood water in the monsoon).

Proper drainage system includes rain water drain, water pits sloping in the surface will be constructed/provided for smooth draining of storm and rain water and ensuring no water logging during monsoon.

Ensure no congestion in the

drain(s) resulting blockage of water passing.

To avoid blockage drain would be clean periodically.

5.

Noise level

Control sound pollution from construction equipment and machineries installed in the construction site.

Sound level for several heavy equipment and machineries and generator will be measured individual during their operation and record will be maintained properly.

Maintain noise levels associated with all machineries and equipment at or below 90 decibel (db), in particular for nearby community facilities.

Air plug will provide all site personnel who are working near the noisy area.

Fully avoid use of hydraulic

horns to project vehicles.

Hydraulic horn (if any exist) of each and every project vehicle will be replaced by non-hydraulic horn.

Control sound pollution from

generation.

We will ensure Installation of soundless generator. If not, generators will be placed in the

22

Page 33: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

Sl. Environmental

Issue Proposed Mitigation Measures

Implementation Plan by Siemens

closed room having barricaded from all sides, which will restrict sound level.

Regulate use of horns of

project vehicles as much as minimum, especially in night.

Strict instruction will be given to the flagman and drivers of project vehicles (motor cycle, car, truck, etc.) for use of horns as much as minimum.

6.

Air quality & Dust

Ensure use of dust-masks by all personnel in areas prone to dust emissions throughout the period of construction.

Proper dust mask will be provided and monitored by site management and EHS officer in the construction area.

Ensure minimum dust

emission in places where earth and cement works is done.

We will prepare and maintain proper HIRA (Hazard Identification & Risk Assessments) and implement SWMS (Standard work method system) to ensure minimum dust emission during earth and cement work. Also regular water will be sprayed all over those area to restrict dust emission.

7. Setting of

Ensure health facilities for the workers and employees at camp site.

Standard camp along with proper sanitation and fresh drinking water and safe area will be provided to ensure proper health facilities for workers.

construction camp

Ensure safe disposal of wastewater from the labor camp and causing no pollution of nearby ponds and watercourses.

Proper drainage system including a temporary septic tank will be setup to avoid any pollution of nearby ponds and watercourses.

Confirm maintenance of all camp facilities in a safe clean and/or appropriate condition throughout the constructed period.

A routine cleaning would be ensured to maintain safe, clean and appropriate labor camp.

Ensure hygienic toilet facility (with constant water supply system) at residence of the workers in the camp area.

At least one water closet toilet will be constructed and provided to each 25 workers.

Ensure hygienic urinal facility (with constant water supply system) at residence of the workers in the camp area and its usage.

At least one urinal facility will be constructed and provided to each 25 workers.

Confirm appropriate usage of

the toilet and urinal facilities for all workers and personnel.

Signage and billboard will be provided to create awareness and also site management will strictly monitor of using it.

Ensure safe water supply system for bath, cook and other essential use in camp and their usage by workers.

Tube well, submergible pump (if necessary) will be provided to ensure safe water supply.

23

Page 34: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

Sl. Environmental

Issue Proposed Mitigation Measures

Implementation Plan by Siemens

Ensure no accident from fire at

camp, residence/quarter. Fire extinguisher will be setup in camp and other important areas.

Ensure immediate

troubleshooting and maintenance of facilities.

Maintenance of all facilities will be done in time as scheduled for keeping the things in a safe, clean and appropriate condition throughout the constructed period.

8. Traffic congestion

Regulate traffic congestion, especially at the entry of the substation site and camp areas.

Traffic signs/signals and signboard will be installed in places where important. Flagman at entrance will be engaged for traffic control.

/Road accident

Regulate all on-site vehicle speeds of all project vehicles at project site to avoid road accident.

Vehicle movement will be restricted or partially restricted inside of construction area. Allowable speed of driving all vehicles movement would be 10Km/Hour. Proper signage will also provide to aware drivers and flagman.

9.

Community health

and safety (H&S)

Ensure safety inside substation, worker camp and construction yard areas.

At least 1.5m height wal l including barbed wire on the top of wall wi l l be constructed around the project area of substation, worker camp and construction yard areas.

Confirm public awareness

building/information.

Warning signs will put where applicable at surrounding the construction site.

Ensure physical safety to the

surrounding natives and strangers.

Notification (signboard, billboard, etc.) and/or announce to the community will be done at reasonable time, if any construction event/plan would result inconvenience to the natives.

10 Occupational health

Ensure occupational safety measures4 for the workers.

Only permitting trained/certified and experienced workers will be recruited to work specially with any electrical equipment. Safe/quality equipment will be provided to the workers to work with. Personal Protective Equipment (PPE) for all workers will be provided and use of it will be mandatory through official order.

4 The PPE materials are: hard hat, safety shoe, goggle, ear plug, waist belt, mask, hand glove, body protective apron, ear muff and insulating cum s tee l - toed boot. Wear helmet for PPE are: Head Protection, Ear plugs/muffs for Hearing Protection, Spectacles/Goggles/Face Shield/Arc-welding Mask with Hand Masks for Eye and Face Protection, gas masks/dust filters/insulating appliances with air supply for Respiratory Protection to work at septic tanks, dump sites, sewers etc., Over sleeves/gloves for Hand and Arm Protection and safety shoes/boots for Foot Protection.

24

Page 35: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

Sl. Environmental

Issue Proposed Mitigation Measures

Implementation Plan by Siemens

and safety Ensure accidental safety

measures for the employees.

A sickbay-room/place will be made available at a suitable location for combating emergency situation. First Aid Box (with supply of medicine and other aid materials) will be made available over there.

11 (H&S) 5

Ensure traffic safety measures for the employees6.

Provide official order/instruction (written, verbal, signboard) to drivers and flagman for keeping speed limit of vehicles within 10 Km/Hour in the camp and construction areas. If necessary pedestrian-safe access routes will be provided inside the construction and camp areas.

Ensure personal safety measures of workers and employees at workplace.

Strict order/instruction (written, verbal, signboard) and engage supervisor for prohibited smoking in the workplace and also drinking alcohol in camp area by workers and employees will be provided. Site personnel will only allow smoking in designated smoking areas. Carry of any illegal substances, weapons and firearms in camp or construction area will be strictly prohibited. Site supervisors, team leader will continuously monitoring and counseling to ensure personal safety measures of workers and employees over there.

PART 2

75. Mitigation Measures for Specific Impacts of Specific Substation Subprojects, during construction

76. The EIA/EMP report stated especial measures only for specific nine affected substations. In particular, the affected objects are:

• Water (water pollution occur due to disposal of waste from construction site into the nearby pond).

• Tree (cutting and felling trees is required because of site clearance for workspace,

5 Educate all construction workers on the following issues but not limited to them: firearm possession, traffic regulations, illegal logging and collection of non-timber forestry products, non-disturbance of resettlement communities, hunting and fishing restrictions, waste management, erosion control, health and safety issues, all prohibited activities, the Code of Conduct requirements and disciplinary procedures, and general information on the environment in which they will be working and living. In addition, educate workers on the identification of occupational expose to Electro Magnetic Field (EMF) levels and hazards is required.

6 Safety signs, safety collar, health signs, prohibition sign, warning sign, mandatory sign, emergency escape sign, first-aid sign, information sign, signboard, supplementary signboard, symbol, pictogram, illuminated sign, acoustic signal, verbal communication and hand signal.

25

Page 36: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

RoW, etc.), • Natural habitat (construction activities cause disturbance to nearby natural habitat),

and • Aquatic life (land filling causes migration and killing of aquatic fauna).

(Note: No mitigation measure is suggested in the EIA/EMP report for aquatic life)

77. Impacts on vegetation because of “Cutting tree and clearance of substation site and RoW from gridline to substation”

[Applicable to two (2) substations are: (1) Lake city Concord (2) Tongi-3].

(Note: Site clearance will be required; accordingly 3 trees will need to be felled for the substation at LAKE City Concord, and 6 trees will need to be felled for the substation at Tongi-3).

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

12 Cutting Trees7

Avoid tree cutting as many as possible.

SIEMENS will not involve in any kinds of cutting trees and activities which will cause of it.

Confirm replantation of double number of trees against tree cutting.

N/A

Ensure additionally replantation of 107 8 numbers of trees along the access road slopes.

N/A

Strictly prohibit collection of any kind of construction material from within the natural habitat.

No materials for construction, cook, fire, etc. will be collected from within the natural habitat.

When removing vegetation from right of ways, workspaces etc. featheredge the cut to ensure that line of site and cover (both security and thermal protection) issues are addressed.

N/A

7 1) The species shall be identified in consultation with officials of forest department and/or local community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation.

3) Plantation must follow availability of water during dry season.

4) Plants must be protected at initial stage of growth. 8 The EIA/EMP report suggested for planting 107 trees along the access road slops commonly for each of six specific substations.

26

Page 37: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Specific Environmental Management Plan

78. Impacts on “natural habitat” because of water pollution and cutting vegetation.

[Applicable to all of four (4) substations are: (1) Uttarkhan (2) Lake city concord , (3) Satarkul-1, (4) Satarkul-2, (5) Solahati ]

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

13. Natural Habitat9

Prohibit disposal of construction waste within the natural habitat.

It will be strictly monitored and controlled by supervising and raising awareness through training and meeting.

Restrict any disturbance to water resource within the natural habitats.

All site personnel will be clearly instructed to avoid any disturbance to water resources within the natural habitats.

Prevent human disturbance and ecosystem impacts on sensitive areas adjacent to projects by using temporary fencing or flag off area to restrict travel to construction zones, RoW and workplace.

Temporary fencing or flag will be provided to avoid any disturbance of human by traveling or moving inside construction zones, RoW and workplace. Also at least one security guard will be placed to ensure unauthorized personnel movement on sites and maintain site security during project execution.

9 1) The species shall be identified in consultation with officials of forest department and/or local community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation. 3) Plantation must follow availability of water during dry season.

3) Plants must be protected at initial stage of growth.

27

Page 38: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

6. Conclusions and Recommendations

6.1 Conclusions

79. With the respect to the environmental compliance monitoring, it has been found that initial tasks related to the construction had already been started, and a contract agreement was signed between Dhaka Electric Supply Company limited (DESCO) and Siemens Ltd. India in consortium with Siemens Bangladesh. Primarily, a tender was called by DESCO, and Simens ltd. India in consortium with Siemens Bangladesh got the offer to design, manufacture, test, deliver, install, complete and commission, certain facilities viz. design, supply, installation & commissioning of 24 nos. 33/11KV Substations in Turnkey Basis against Bid No. IFB 01/2016, Package-C1 of Lot-3 under ADB Loan No.: 3087- BAN: Power System Expansion and Efficiency Improvement Investment Program. Afterthat, Initial visit has been completed by the officials of Siemens and Topographyical Survey is being started to understand the shape, form, level and geographical position of the proposed 24 sites. At this stage of the monitoring, twenty four proposed locations have been identified and existing physical, biological and social conditions observed to get an insight about the base situation.

80.

6.2 Recomendations

81. Following recommendation needs to be followed to continue next monitoring smoothly

• An overall idea should be given to the EPC contractor for complying EMP

provided by EIA report.

• A layout plan for all substation needs to be provided

• It is recommended to identify the best ways for carrying out construction

activities in which the environmental pollution can be lessened

• EPC Contractor should arrange all safety logistics estimating their required labor

before construction.

• Training programs should be initiated on occupational health safety issue after

the labor recruitment.

28

Page 39: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Reference

ADB (2009). Safeguard Policy Statement, Policy Paper

29

Page 40: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix A: Field Photos

Existing and Proposed Substation in the study area (Mirpur-6 )

Existing Substation At CAAB Location of the 33/11 KV Substations at ADA

Meeting with DESCO official at Block-C, Mirpur-6, Dhaka

Public Consultation with local people at Sholhati, Uttata, Dhaka

30

Page 41: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix A

Proposed Substation At Uttarkhan (Promy)

Proposed Substation At Uttara Sector 14 Proposed Substation at AIUB Campus

Proposed substation at Eastern Housing Proposed substation at Merul Badda ( BRAC

University)

31

Page 42: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B: Monitoring Checklist

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Monitoring Component: Physical Environment

Noise Level

Disturbance to local communities, ecosystem and workers at worksite due to construction activities of the proposed plant site.

Use modern low noise producing machineries.

Switching off machines which are not in use.

Develop temporary corrugated/Tarja fencing around the project boundary

Provide hearing protection for the workers

Follow mandatory regulations in case of night shift operations.

Maintaing noise level 45 dBA at the residential area and 55 dBA at day light hour

.

Maximize the offset distance between noisy plant items and nearby sensitive receivers

Employ effective silencing measures for equipment and other abatement techniques to minimize construction site noise.

Ensure that all equipment is in good repair and operated in the correct manner.

Consult with local people /residents and building owners to address community concerns

32

Page 43: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Air Quality

Emission of particulate matter, SOx and NOx due to construction activity and from construction machineries.

Water spraying system to control fugitive dusts

Restricting excavation activities such as top soil removal during period of high winds

Locating stockpiles away from the sensitive receptors

Carrying out progressive rehabilitation of cleared land

Locating contractor’s compounds away from residential areas

restricting the burning of waste

minimize exhaust emissions from construction equipment through the regular maintenance of all construction machinery and vehicles

Construction materials (sand/soil) to be kept covered with polythene

Provide broad fence/ barrier to restrict wind current

Introduce vehicle speed limit

Use good engine quality machines/vehicles

Ensure that emissions from on-road and off-road

vehicles should comply with Schedule 6 (Standards for emissions from motor vehicles) of ECR 1997

Soil The soils of the project areas Topsoil that is to be removed should be stockpiled for

33

Page 44: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Characteristics have clay loam/ silty loam to loamy texture. The area under the project would be filled up with external soils having sandy materials. Then the existing soil might turn into sandy soil in the proposed Sub-station sites.

site rehabilitation and landscaping works.

Soil-erosion and sedimentation-control measures should be undertaken in stages to minimize the area of unstable or unprotected soil surfaces

Wherever possible, vegetation is to be left undisturbed and retained as soil cover. If vegetation cover is not available, spread mulches over the surface to reduce dust and rainfall impact.

Undertake the progressive revegetation of excavated areas as quickly as possible. Revegetation may include grassing or planting the area with trees or shrubs. The selection of species should be compatible with the local conditions and use requirements.

All fuel storage areas and refueling vehicles are to be provided with spill –containment kits

An emergency Spill Contingency plan shall be prepared by the contractor as part of the SEMP

Proper deposition of loose soil and construction materials to avoid water logging

Waste Management

An efficient municipal solid waste management system may create serious negative impacts like infectious diseases, land and water, pollution, obstruction of drains

Specific sites for waste disposal

Quantification of solid wastes

Sanitation system

Location of backfilling stockpile in safe area

Measures to control odor problems

34

Page 45: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

and loss of bio diversity. Excavated material unsuitable for fill should be disposed in an environmentally safe manner.

Ensure that the waste management measures (collection, sorting, and disposal) are correctly implemented on the project site

Ensure that correctly signed waste containers are available at convenient locations for the disposal of wastes

Dispose of all used oil and fuel filters in a secure landfill, unless they can be recycled

Ensure that an adequately sized area is made available for the safe storage of wastes prior to collection

Ensure that all on-site wastes are suitably contained and prevented from escaping into

Neighboring fields, properties, and waterways, and that the waste contained does not contaminate soil, surface, or groundwater, or create unpleasant odors for neighbors or workers

Ensure the site is regularly cleaned and waste material appropriately removed, i.e., to a landfill in accordance with regulations

35

Page 46: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Biological Environment

Ecosystem and Biodiversity

Conservation

Bird’s habitat loss, damages of herbs, shrubs and degradation of ecosystem and biodiversities due to construction works.

No disturbance on wildlife movement

Limiting the use of night light

No plantation of non-native species

The removal of vegetation shall be restricted to the development footprint, which should encompass areas that are already relatively disturbed in preference to clearing vegetation

Any additional clearing for construction will compound the impacts, so ancillary facilities outside the footprint shall be avoided

The construction footprint shall be clearly demarcated. The clearing boundaries are to be shown to machinery operators with the instruction that machinery is not allowed to operate outside the boundaries. The area is then cleared to minimize disturbance to adjacent areas

The boundary will be fenced and the area cleared in such a way that the footprint shall not be extended during clearing works.

If the area is to be revegetated, preference should be given to naturally occurring species that are recognized as non-invasive species.

Socio-Economic Environment

36

Page 47: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Land Acquisition Land owners livelihood status would be affected due to land acquisition

Conduct a rapid assessment through consultation with land losers (15 acres) to assess whether they are facing any significant livelihood restoration challenges and whether they have replaced their assets

Cash payment and monitoring

Land owners may be deprived of proper compensation due to lack of monitoring or improper land ownership.

Disburse Cash for compensation of land (CCL)

Develop a plan which includes compensation, restoration, livelihood, living standards etc.

Provision of monitoring the compensation process

Livelihood and living condition

Livelihood and living system may be disturbed due to the development activities

Causing no threat to the livelihood of local people

Prioritize local labors in employment

Develop a separate road network during construction

Separate water facilities for workers

Community Health, Safety and Security

Health, safety and security would be affected during pre, construction, operation and decommissioning phases of the project.

Construction of Fence around project area

Evaluation for risks and impacts on health and safety during preconstruction, construction, operation and decommissioning of the project

Involve Community in Risk Assessment Process

Consider Community Health and Safety in Designing infrastructure and equipment

Practicing safe management for hazardous materials which may pose threat to the community

Availability of plan for natural hazards

Develop and Implement an Emergency Response Plan

37

Page 48: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Training and instruction to the security personnel about their behavior and communication with the local people

Practice of Tool box meeting and reporting

Establishing a grievance mechanism for the community dwellers

Provision of health service facilities to community

Safety trainings for workers (i.e. fire control, working at height, working in heat, first aid etc.)

Increase awareness amongst the workers and employees and conduct health awareness drivers and medical camps in the neighboring areas (HSBC)

Causing no disturbance on locally or culturally important sites

Ensure no use of Polychlorinated Biphenyls (PCB) in transformers

The workers’ camps should be located away from residents and sensitive receptors schools, health centers etc.

All vehicles exit points from the construction site shall have a washdown or shakedown area where mud and earth can be removed from the vehicles before it enters the public road system. All washdown areas are to drain to a sedimentation basin.

38

Page 49: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Information dissemination

Disputes may arise in the nearby community if public consultation meeting is not held.

Disclosure of EIA Report and sharing project information

Arranging public consultation meeting

Quality of consultation and disclosure

Working Condition

Community dwellers may feel that they are not giving substantial share in project related job opportunity

Adequate fire precautions in place (for example, fire extinguishers, escape routes)

Documentation and reporting of occupational accidents, diseases, and incidents

Ensuring fair treatment, non-discrimination and equal opportunity

Compliance of project’s labor policy with the national labor law

No Child Labor

No incident of forced labor

Conduct regular third party audits during construction phase of the project to assess the contractors compliance levels in meeting the statutory and ADB requirements

Develop a site specific safety plan including standard operating procedures (SOPs) and work permits required to protect employees (both full-time employees and contractors) from injuries

Provide adequate provision of drainage and access to

39

Page 50: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

toilets

Cleanup litters and other wastes regularly

Provide secure containers for disposal at designated area

Properties safety on site, and illuminate well if work at night

Provision of PPE for workers and maintenance of work safety procedure

Regular safety checks and maintenance

Emergency response plan for events such as accidents, spillage of hazardous materials etc.

Employment Without the involvement of local labor, Social unrest will be held among the local people

Local Labor (technical and non-technical) should be recruited.

Site Closure

Environmental and social safety can be hampered without completion of site works and restoration properly

At the completion of work at a particular site, or when the construction program as a whole is completed, the contractor will be responsible for removing all equipment and structures, cleaning up and disposing all waste materials, and rehabilitating all construction sites and work areas so that these can be returned as much as possible to their previous use.

There must be a stabilization of all project construction sites, roads, and tracks (where batters and embankment fill must be stabilized, and road drainage stabilized as well). All borrow pits and quarries are to be rehabilitated; all fuel and oil depots closed; any

40

Page 51: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix B

Category Description of potential

impact Measures/Indicators

Due Diligence

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

Co

mp

lied

No

t C

om

plie

d

Rem

arks

contaminated soil removed; and the areas restored. All spoil heaps must be reshaped and revegetated.

All work sites must be rehabilitated as per needs. Areas where topsoil has been removed will require a reapplication of topsoil, and revegetation as required.

Care must be taken to ensure that the sites are adequately restored. This will require adequate time to ensure that the sites are effectively reestablished.

Monitoring Indicator:

1 = Same as Baseline

2 = Not Applicable at this stage

3 = EPC contractors hired a water spraying car, but it does not spray water into the area regularly

4 = In progress

5 = About 5~6 people did not receive compensation due to lack of ownership transparency

6 = Directly paid by DC office to the incumbent

7 = Some impacts are caused which are intangible

8 = EPC contractors displayed presentation only, but no document is yet available

9 = No water car was required as it was raining during this season

Legend:

Complied = ✓ Partially complied= (--)✓ Not complied= ✓

41

Page 52: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix C: Contract Agreement Between DESCO and Simens India

Page 53: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix C

43

Page 54: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix C

44

Page 55: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix C

45

Page 56: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix D: A3 Size Map

46

Page 57: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Appendix E: Environmental Clearence Certificate

47

Page 58: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

Government of the Feople's Republic of BangladeshDepantmaemt of Emvix"oaamaemt

Head Office, Faribesh BhabanE- 1 5 Agargaon, Dhaka- 1 207

wnvw.doe.goy,hd

N4emo No : DoE/Clearuncel 526412014 I 3 2C Date: '?\il0e tzots

Suh3eat: Appnoval ofl Emvironlmaemtal nmapact ,{ssessmaemt (trxA) x'(eport for-Auganaemtatiom amcl R.enaahilitatiom of Distrihutnon Systerm Froieat rm DlltrSC0Area.

Ref: 1) Your application dated 2110512A15.

With reference to the above, the Department of Environment (DOE) is pleased to approveEnvironm.ental lmpact Assessment (EIA) R.eport for Augmentation and Rehabilitation ofDistribution System Froject in DESCO Area. This approval authorizes and regulates thefollowing activities:

Project Froponent may undertake activities for land developrnent and infrastructuralcleveloi:ment of' the said Sub-Component;Froject Froponent may cpen LiC (Letter of Credit) for irnporting machineries for the Sub-Component which shall also include machinef ies relating to pollution control devices;Ae,tivities must be car"ried out in a competent manner. This inciudes:(a) the prccessing, handling, movement and storage of materials and substances used to

t.

2.

3.

carry out the activity; and(b) the treatment, storage, processing,

generated by the activity.Construction works sha11 be restricted to day time hours so as to avoid/mitigate thedisturbance of local lives as well as implementation schedules of the works shall benotified in advance to nearby residents.Storage area for soils and other construction materials shall be earefully selected to avoiddisturbance of the natural drainage.

6. Proper construction practices shall be followed that minimize loss of habitats and nurserysites.

7. In order to control noise pollution, vehicles & equipment shall be maintained regularly;working during sensitive hours and locating machinery close to sensitive receptor shall beavoided.Proper and adequate on-site precautionary measures anti safety illeasures shall be ensureclso that no habitat of any flora and fauna would be demolished or destructed.All the required mitigation measures suggested in the EIA report are to be strictlyimplemented and kept operative/functioning on a continuous basis.Any heritage sight, ecological critical area, and other environrnentally and/or religioussensitive places shall be avoided during construction phase.

reprocessing, transport and disposal of waste

A

5.

ao.

9.

10.

*ry

Page 59: Environmental Monitoring Report ·  · 2017-11-10Station 740/B, West Kazipara,Mirpur (Beside the mosque of west Kazipara Bus station) - ... 23 Tongi (BSCIC) Near BPDB’s 80 MW Power

12.1J.

I 1. F.esettlement plan should be properly implemented and people should be adequatelycompensated, where necessary.Construction material should be properly disposed off after the construction work is over.

The Environmental Ntlanagement and Mitigalion Plan included in the EIA report shallstrictly be implemented and kept functioning on a continuous basis.Comprehensive Environmental Ferformance repofi, upon completion of, the project shallhave to be submitted to the Head Offlce of DOE in Dhaka with a copy to DhakaMetropolitan oftice and Dhaka Regional office of DOE oescribing actual intervention and

rehabilitation at the project site,Violation of any of the above conditions shail render this approval void.The project authority shall apply for Environmental Clearance along with NOCs frorn otherrelevant agencies for operational activity to the Head Office of DOE in Dhaka with a copyto the Dhaka Metropolitan office and Dhaka Regional office of DOE in Dhaka.This'EIA Approvai has been issued with the approval of the appropriate authority.

'\j [5

(Syed Nazmtnnn Ahsam)Ilirectcr (Environnrental Ciearance, c.c)

Phone # 8181778

Systern Froject in DESCO AreaDhaka Electric Supply Company Limited (DESCO)House # 221F., Faruk Sarani, Nikunja-2Dhaka-7229.

Copy Forwardedtp_i

1) PS to-Secretary, Minisffy of Environment and Forests, Bangladesh Secretal"iat, Dhaka.2) PS to Secretary, Power Division, Ministry of Energy and Mineral Resources, Bangladesh

Secretariat, Dhaka.3) Managing Director, Dhaka Electric Supply Company Limited (EESCO), Dhaka.4,\ Director, Department of Environment, Dhaka RegionalArietropolitan Cffice, Dhaka.5) Assistant Director, Office of the Director General, Department of Environment, Head Office,

Dhaka.

14.

15.

t6.

17.

1

/1 6-:X;.J*J:

/ n^ F. I? \ --L1 L'