Environmental Management Plan

47
KSS-VALECHA CONSORTIUM ENVIRONMENTAL MANAGEMENT PLAN Date: 23.02. 2011 Page: 1 of 27 Environment Management Plan (Health, Safety and Environment) PROJECT: SECTION OF NH-203 FROM KM. 0.000 TO KM. 59.000 IN THE STATE OF ODISHA TO BE EXCUTED AS BOT (TOLL) ON DBFOT PATTERN UNDER NHDP PHASE - III KSS – Valecha Consortium 1 st Floor, Vatika Towers, A-Wing Sector 54, Gurgaon – 122002, India Tel: +91 124 4566800 Fax: +91 1244566866 Web: www.kazstroyservice.com 1

description

Plan for environmental control in Highway Construction

Transcript of Environmental Management Plan

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Environment Management Plan

(Health, Safety and Environment) PROJECT: SECTION OF NH-203 FROM KM. 0.000 TO KM. 59.000 IN THE STATE OF ODISHA TO BE EXCUTED AS BOT

(TOLL) ON DBFOT PATTERN UNDER NHDP PHASE - III

KSS – Valecha Consortium1st Floor, Vatika Towers, A-Wing

Sector 54, Gurgaon – 122002, IndiaTel: +91 124 4566800Fax: +91 1244566866

Web: www.kazstroyservice.com

0 24.02.2011Issue for Review / Approval

C.S. Singh

1

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

REV DATE Description of revision

Prepared By Reviewed By Approved By

CONTENTS

01. Introduction.

02. Environmental Management Plan of Construction Camp.

03. Borrow Area Management.

04. Construction Plants and Diesel Generator Sets.

05. Quarry Management Plan.

06. Environmental Management at Work Sites.

07. Solid Waste Management.

08. Environmental Monitoring.

09. Permission and Consents.

10. Legal and other requirements

11. Environmental Inspection Report

2

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

1. INTRODUCTION:

The Environmental Management plan formed to protect the environment and to

implement, mitigate, monitor and provide remedial measures during the activities of road

construction work of Bhubaneswar to Puri on NH-203.

Proper procedures and records shall be maintained for the requirements related to

protection of the environment. Environment related trainings and awareness programs to

all employees on a regular basis shall be provided during the project work.

Objectives

The main objectives are to:

Ensure compliance with regulatory requirements that are applicable to the

activities.

Provide timely indication if any environmental control measures fails to achieve

acceptable standard.

Assess the environmental condition of the area where the road construction is

carried out.

Monitor effectiveness of environmental mitigation measures.

The schedule for submission of six monthly environmental monitoring reports to

the Ministry of Environment and Forest will be in the month of August and

February.

Purpose and scope

3

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

To be aware of the environmental concerns of the road construction work and the

application of environmental control during the construction phase of the project.

To facilitate road construction programme while ensuring fulfillment of our

commitment to protect the environment by minimizing any damage to the

environment and monitoring environment aspects, which may be arise from

construction activities.

To supervise compliance with environmental criteria reviewing the collected data.

Prepare Contingency plan.

Method for promoting environmental awareness

We will provide environmental awareness training to our employees.

All personnel being absorbed at site would be made to attend an environmental

awareness programme. Environmental Awareness Programme includes environmental

policy, on site emergencies, Environmental aspects, Environmental impacts, rules and

regulation.

2. ENVIRONMENTAL MANAGEMENT OF CONSTRUCTION CAMP

Construction camp is the location where the contractor will have camp office, residential

colony, workshop, Laboratory, casting yard, steel yard, Plants and Machineries for the

proposed Road work Bhubaneswar to Puri.

The site for the construction will be almost center of the proposed highway work

stretch thus reducing the transportation time and easy accessibility to the work site.

The site will be free from cultivation and in non-agricultural land.

The construction set up will have:

1. Offices and Residences

2. Plants and Machineries

4

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

3. Workshop

4. Laboratory

5. Vehicle parking area.

The layout of the construction camp is designed in such a way that there will be a

reasonable distance between the offices, residences and Plant area.

The site clearance will be the first step and the trees if any existing in the site will be

taken care and will be left as it is and in case any removal is to be done will be

compensated by planting the additional trees at the boundary or at the selected

location in the camp site. Gardening will be done at residential and at site office.

Topsoil if any will be removed only in the construction area and will be utilized in the

lawn development in the campsite.

Fencing all around the campsite will be done with check post provision in the

entrance there by restricting the camp area as restricted area for the local public.

Source of water supply:

Water required in the construction campsite will be of the following

Domestic use in office and residential colony

In Crushers, Wet Mix Plant, Hot Mix Plant and Batching Plant.

Green belt developing and gardening in and around office area and Residential area.

Domestic Use:

For the domestic usage of water in the office and residential colony the bore well (pH

value) will be driven and the water will be tested for its quality. If existing water resource

is available, this can be utilized. Upon receiving the good quality of bore water the same

will be utilized for the above proposed purpose by providing over head tanks for water

storage and necessary pipe lines for delivery.

5

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Drinking water will be tested seasonally by assuring that there are no physical, chemical

and biological contaminants.

If required suitable treatment will be done for bore water if the raw water is not potable

upon receiving the water test report.

Plant Area:

Water is required for the dust suppression system in Crushers, processing Wet Mix Plant

and Batching Plant.

Water in the existing open well (pH value) if any, will be utilized for this purpose.

Permission from the concerned authorities, if required will be obtained.

Green Belt Development and Gardening:

Open well water will be utilized for developing and for gardening.

Sanitation and Waste Water Treatment:

Offices and residential colony will be constructed with sufficient ventilation and required

numbers of toilets, bathrooms and washbasins. Non Hazardous waste collection bins will

be provided at various locations depending upon the requirements and will be safely

disposed. The residential and office blocks will be situated at reasonable distance from

Plants and Machineries.

Septic tank of adequate capacity will be provided separately for office and residential

colony. The sewage from this septic tank will flow into soak pits there by underground

strata disposal practice. The soak pits and septic tanks will be carefully located so that no

contamination will cause to sources of water.

6

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Wastewater from canteen will be routed through the drainage system.

Since Laboratory proposed in campsite is for material testing the wastewater will be of

only container washings, which will have only little bit of non-hazardous solids. This will

be settled in the grit chamber provided and the clear water will be absorbed to the

wastewater sump. There will no Chemical effluent generation from Laboratory.

Medicare and Sickbay:

A Medical center and sickbay will be established within the base camp with necessary

first aid facilities to treat minor injuries and to provide first aid. Urgent and serious cases

will be referred to the nearest hospital for treatment. Responsible persons will be trained

in the first aid treatment. The first aid boxes will be located in work areas. A separate

vehicle will be made available at any time for Emergency cases. The contact phone no. of

the nearest ambulance service will be displayed within the camp area for easy

accessibility.

Workman safety at site:

Every Workman at site will be provided with necessary PPE’s at site followed by safety

training. The list of PPE is as under:

SR.NO. DESCRIPTION REMARKS

1 Hard Hat / Safety Helmet. As per the colour code.

2 Safety Shoes. As per the activity required.

3 Safety Goggles (Plain & Black). As per the activity required.

4 Ear Plugs / Ear Muffs. As per the activity required.

5 Dust Mask. As per the activity required.

7

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

6 Cotton Knitted Hand gloves. As per the activity required.

7 Leather / Rubber Hand gloves. For welders & concrete labours.

8 Safety Belts / Safety Ropes (Life Line). For working at Heights.

Indent will be raised as per the requirement of the safety gadgets & will be procured as

early as possible. Necessary inventory of safety gadgets will be maintained on regular

basis as well as maintenance will be done.

3. BORROW AREA MANAGEMENT:

Land Identification and methodology of operation:

The location where the soil for embankment and constituents for GSB can be obtained is

called borrows land. The widening of the existing road involves both cutting and filling

of earth. Hence the amount of material generated as a result of excavation is enough for

use in filling areas provided the cut material is found suitable.

A layout showing the area with respect to the project area will be prepared.

The area will be identified and will be taken on lease. It may be any government land or

of landowner. The following points will be taken in to consideration while selecting the

land.

Whether the land is high or flat

Distance from the main road

Existing stream or water source.

High lands are highly suitable for the borrow land. On cutting the land will be brought to

the adjacent ground level. The slopes will be trimmed and no vertical cuts will be left in

the borrow lands in order to avoid landslides and soil erosion. In all cases the limits of

8

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

borrow areas will be clearly demarcated. The dry lands alone will be used as borrow

lands. The material from the trial pit of the borrow area will be tested and its suitability

with necessary approvals will be obtained.

The Excavators, JCB, Wheel loaders and tippers are the main machineries used in the

borrow areas. All this machineries will be maintained adequately fitted with silencers to

reduce noise levels. The machineries will checked for emission and will be kept within

the limits. Periodical checkups and maintenance will be done.

Location of Borrow Area:

A layout showing borrow areas with respect to the project area will be prepared. Also a

detailed borrows area management and rehabilitation (if required) plan will be prepared.

SR.NO. LOCATION OF BORROW AREA CHAINAGE NO. DISTANCE

1

2

3

4

5

6

7

8

Haul Road Management:

The approach road to the borrow area will be maintained through out the period of its

use. Periodic sprinkling of water will be carried out to suppress dust generated during

vehicular movement. Speed limit will be strictly adhered to while hauling of material is

9

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

carried out. Necessary signboards will be displayed wherever required and the traffic

assistants will be posted to regulate the traffic flow.

A friendly atmosphere will be created with the local community and all assistance will

be provided.

Top Soil Management:

Before the commencement of the excavation the topsoil will be stripped and stockpiled

for the future use. This soil will be spread after the completion period incase of high level

borrow areas. The topsoil from the other borrow areas will be utilized in the turfing of

side slopes.

Closure Plan:

The activities carried out in this regard will be as per the direction of the landowner. If it

is desired by the owner that high land be flattened for construction purpose then the land

will be leveled once the extraction of material is complete.

A record of trees cut will be maintained and it will be ensured that suitable compensatory

measures are taken.

A sketch of borrow area, distance from the project road, the area involved and expected

yield and all other relevant details will be attached with every borrow area that is

exploited.

Photographic Records:

Photographs of the area depicting the state of land before and after extraction of material

will be maintained.

10

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

BORROW AREA IDENTIFICATION:

Construction stage Report Date:

Contract Package: Concessionaire: Contractor:

Location of Borrow Area (Chainage and Offset Distance):

SR.NO. Items / Requirement Details as per Actual

1 Name / Identity of Location.

2 Name of the Owner, if private land.

3 Current land use.

4 Area (m x m), maximum depth (m) of Borrow Area.

5 Quantity available (cu.m).

6 Quantity of top – soil to be removed (cu.m).

7 Management of top – soil (preservation & reuse).

8 Distance from the nearest settlement (within 500m).

9 Distance from the nearest water bodies.

10 Details of ecologically sensitive area i.e. RF, PF,

Sanctuary, archaeological monuments within 1000m.

11 No. of trees with girth more than 0.3m within

borrow area.

12 Frequencies of sprinkling of water on haul roads for

dust suppression.

11

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

13 Plan of the Borrow area showing environmental

features within 1km radius.

14 Photograph depicting the present condition of the

proposed area.

15 Closure / Completion Plan.

4. CONSTRUCTION PLANTS AND DIESEL GENERATOR SETS:

Pollution Control in Stone Crusher:

There is no process waste from the stone-crushing unit. Hence there will be no water

pollution. The dust generated while crushing operation, conveying and at dropping point

will be suppressed by water sprinkling system provided on plant, and will be done at

point starting from the jaw crusher to the dropping point. Due to water sprinkling, weight

of dust particles get increased and will not fly in air. Water required for sprinkling

purpose will be drawn from the available sources nearby, to the overhead water tank for

continuous operation.

Pollution Control in Wet Mix Macadam Plant:

The total operation in the Wet Mix Macadam Plant is wet operation so there will not be

any air pollution. This operation will not generate any process wastewater also.

Pollution Control in Hot Mix Macadam Plant:

This operation has no process wastewater. Due to application of high flame at high speed

the dust particles in aggregates may come out in air vent. This is controlled by providing

dust collector and bag filter. The dust collector reduces the velocity and makes the

heavier particles to get settled down and this outlet air is passed through bag filter. For

12

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

periodic replacement of the bag filters maintenance schedule will be drafted in

consultation with the Engineer in-charge and schedule will be displayed.

Pollution Control in Batching Plant:

In Batching plants the cement will be stored in silos and will be conveyed in pipes using

screw pumps. Hence there is no possibility of spreading in air. Water sprinkling

arrangement will be provided at the conveyance and the drop point there by suppressing

the dust spreading. The wastewater generated while mixing drum cleaning and the

concrete transit containers will be allowed to pass in the settling tank and filtered in the

sand bed. Water sprinkling will be done for dust suppression

Waste from Construction Plants:

The process waste generated in the construction plant is stone dust. This dust is utilized in

Wet Mix Macadam Plant and if in excess it may be utilized for landfill. This will be

mechanically handled for collection and conveyance.

Pollution Control in DG Sets.

The DG sets used on site/work will comply with all legal requirements. Operating

permits will be obtained from the concerned authorities prior to use. The DG sets will be

maintained in accordance with manufacturer’s recommendation/instructions to ensure full

serviceability and with a view to cause least emission to the atmosphere.

The following DG sets will be provided in the camp site (the list will be completed by the

Plant & Maintenance Department in coordination with project management).

Capacity

Location

Pollution control equipments

13

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

List of Diesel Generator sets with the pollution control system for noise control,

exhaust dispersion & oil-spill control system is as in the table given below:

SR.

NO.

LOCATION CAPACITY OF

THE D.G. SET

POLLUTION CONTROL

EQUIPMENT

REMARKS

1

2

3

4

5

6

7

8

9

Ambient Air Monitoring

We shall undertake environmental monitoring in term of Ambient Air Monitoring for the

determination of suspended particulate matter. The air quality monitoring procedure shall

be establish to monitor the impact on air quality and measures to control air pollution

including dust suppression of activities that will cause degradation in air quality,

environmental procedures to manage pollutants, monitoring programme, record keeping

and reporting.

The main pollutants, which will come out from different road construction activities,

would be Suspended Particulate Matter (SPM), Noise pollution from different earth

moving equipments and generator sets.

14

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

The ambient air quality will be monitored twice in a week at require locations and the

level of pollutants in the air will check. The emission from the generator sets and the Hot

Mix Plant will also be monitored at two locations 8 hrs sample / Day every season and

level will be checked and improvements if any required will be done. All the vehicles

used in the project will be tested for emission and the Administration and CPE

departments will maintain the certificate of fitness.

Third party will do all the emission testing and the copies of the results will be

maintained in the site Safety Dept. The schedule of maintenance of plants, equipments

and machineries will be drafted in consultation with the technical person in charge and

the schedule will be adhered. The CPE Dept. will do periodical review of the

maintenance works completed, once in three month. If any deviation observed, root cause

will be identified and the required remedial measures will be taken.

Mitigation Measures

Transport of material from one place to another creates air pollution, which degrades the

atmosphere of the area. To minimize pollution precaution are taken to minimize visible

particulate matter from being deposited upon roadways. It includes removal of particulate

matter from equipment and cleaning of dust / mud and deposit of material on public place

by routine sweeping work.

Control requirement at road construction site:

The dumping material shall be placed in a manner that will minimize dust production.

Material shall be stabilized by watering or other accepted dust suppression techniques.

The height from which material dropped shall be the minimum practical height to limit

the fugitive dust emission. Stock piled, sand and aggregates use in concrete

manufacturing and construction work should be piled with suitable slopes and if required

it will be enclosed on three sides with suitable barricading. Cement will be stored

separately in cement godown. Water sprinklers shall be provided as required to control

15

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

and suppress dust during handling of excavation, debris and or during demolition. During

dry weather, dust control methods shall be used daily especially on windy, dry days to

prevent any dust from blowing.

Monitoring of SPM:

The impacts of fugitive dust as ambient air pollution depends on quantity generated as

well as drift potential of dust particles injected into atmosphere. Larger particles will

settle down but smaller particles will drift away. SPM levels will be monitored to check

dust impact during construction phase.

Methodology:

The samples will be collected with the help of High Volume Dust Sampler using standard

methods on pre weighted GFA filter paper at a rate of 1:1 m3/minute for 24 hours and

SPM will be monitored by suitable placement of High Volume Sampler at various

locations at the site. Air monitoring shall be carried out forth nightly at each location.

Presentation and Interpretation of results:

The results will be reported on the basis of 24 hours and will be presented as g/m3.

These results will be compared with National Ambient Air Quality standards. The results

will be recorded and mitigation measures will be taken for control of air pollution.

National Ambient Air Quality Standards

POLLUTANTS

TIME

WEIGHTED

AVERAGE

CONCENTRATION IN MICRO GRAM / CUBIC METER

SENSITIVE

AREA

INDUSTRIAL

AREA

RESIDENTIAL/

COMMERCIAL

AREAS

Sulphur

Dioxide (SO2)

Annual average

24 hours

15 g/m3

30 g/ m3

80 g/m3

120 g/m3

60 g/m3

80 g/m3

Oxides of Annual average 15 g/m3 80 g/m3 60 g/m3

16

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Nitrogen as

(NO2)24 hours 30g/m3 120 g/m3 80 g/m3

Carbon

monoxide (CO)

Average 8 hrs.

Average 1 hr.

1.0 mg/m3

2.0 mg/m3

5.0 mg/m3

10.0 mg/m3

2.0 mg/m3

4.0 mg/m3

Suspended

particulate

matter (SPM)

Annual average

24 hours

70 g/m3

100 g/m3

360 g/m3

500 g/m3

140 g/m3

200 g/m3

Respirable

particulate

matter (RPM)

Annual average

24 hours

50g/m3

75 g/m3

120 g/m3

150 g/m3

60 g/m3

100 g/m3

Noise Monitoring And Control Plan

The noise monitoring and control plan shall contain the sources of noise pollution at the

construction site. It also contains the mitigation measures to be taken.

Noise Control

Required measures will be taken so as to minimize noise impact on the community.

Provision of necessary silencers and mufflers on construction equipments, which will

properly fitted and maintained. Canopy type generator sets will be provided at required

locations and open type generators will be in housed in sheds.

Sources of Noise Pollution:

Noise generated during operating of the different Earth Moving Equipments.

Noise generated during any other construction activity.

Noise generated during truck, tipper loading, unloading and handling activities.

Noise generated from Batching Plant, Crusher unit, Hot Mix Plant and Wet mix

Macadam plant.

17

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Noise generated from Drilling and blasting activities.

Allowable Noise Emission Levels:

The permissible level at construction site is 90dB.

CATEGORIES OF

ZONES

MAXIMUM NOISE LEVEL – Limit Leq in dB (A)

DAY (Time from 6.0 AM

to 9.0PM)NIGHT

Industrial Zone 75 70

Commercial Zone 65 55

Residential Zone 55 45

Silence Zone 50 40

Mitigation Measures

To the extent required meeting the noise limits adequate efforts will be taken to reduce

the construction noise emissions level.

Scheduling the Tipper, Truck and Earth Moving Equipments for loading,

unloading and hauling operations so as to minimize noise impact on surrounding.

Locating stationery equipments as to minimize noise impact on the community.

Put off Plants and Equipments when not in use or idle.

Use only well maintained plants and Equipments, which should be serviced

regularly. Maintain equipments such that parts of vehicles and load are secure

against vibration and rattling.

Silencers and mufflers on construction equipment shall be properly fitted and

maintained.

Maximize physical isolation between noise generators and noise receptors.

18

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Grading of surfaced irregularities on construction sites to prevent the generation

of impact noise and ground vibration by passing vehicles.

Schedule work to avoid simultaneous activities that both generate high noise

level.

Construction of temporary physical barriers.

Monitoring

Noise level will be measured at various site locations as and when require with

calibrated Noise meter at different times during the operation of equipments used for

construction of the project. Noise monitoring and control plan, results submitted will

include duration of measurement distance of monitoring from activity and construction

equipment working during monitoring period.

Presentation and Interpretation

Noise level during the construction activities will be measured and presented as Leq,

L10, L90 and Lmax in decibel (dB) units. The measured value will be compared with the

standards values.

Contingency Plan

If the noise level exceeds of limiting value (either accidentally or through inadequate

implementation of mitigation measures) does occur, the cause will be quickly identified

and remedial measures will be taken with professional expertise.

Water Pollution Control:

We will provide a drainage system to drain off all surface water from the work site into

suitable drain outlet. We will collect all cement slurry, Bentonite slurry or other grouts

used in road construction shall be disposed off safely at the nearest approved disposal

area.

19

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Site Hygiene:

Site hygiene will be maintained at highest standards to keep the good healthy working

environment at our work site. Proper longitudinal and C/S profile should be maintained

so as to drain off storm water as well as waste discharge during the course of construction

activities. A septic tank for our sewage system is already constructed.

WASTE

HANDLING, STORAGE AND DISPOSAL

The waste mud generated from the pile foundation will be handled mechanically by JCB

and tippers to transport the same to approved designated place for proper disposal. Any

other waste generated from our activities will be collected properly in waste is placed in the

designated places and to the possible extent they are disposed by auction to the waste

buyers. Till that time it will be carefully stored in an area specifically marked for the

purpose.

HAZARDOUS CHEMICALS & WASTES

All hazards material must be stored in approved containers/cabinets and storage area.

Containers cabinets and storage area will have proper Labelling. Material must not be

transferred to unapproved unlabeled containers. Safe procedures will be used for

transferring material from bulk.

1. All the hazardous chemicals must be labeled properly.

2. All storage facility must be equipped with eyewash and splash goggles.

3. Temporary and permanent storage of all hazardous material must be neat and

orderly. Stored must not obstruct fire extinguishers where electrical panels exists.

4. All storage must ensure that incompatible chemicals do not come in contact with

one another.

HANDLING

Hazardous material handled with proper care under responsible person.

20

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Use proper PPE in manual handling of hazardous chemical.

An approved device carrying hazardous material will be used whenever chemicals

are taken from stock area.

Hands get contaminated while handling hazardous chemicals and should be

washed and cleaned.

In handling flammable substances all type of ignition sources are avoided.

Supervisor will ensure that the staff who works with such hazard product will be trained

in the use, storage and handling of controlled product. The training programme must

include instruction of the following:

1. Type of labels

2. MSDS Sheet

3. Procedure for safe use, storage and handling.

4. Emergency procedures.

DISPOSAL

Empty containers of hazardous chemicals may itself be a hazardous waste. Empty

containers and hazardous waste will be given to authorized dealer.

If encountered or generated as a result of our activities, then waste classified as hazardous

under “Hazardous wastes (Management and Handling) rules 1989’ and chemicals

classified as hazardous chemicals under “manufacturer, storage and import of Hazardous

Chemicals 1989 of EP A (1986) shall be disposed off in a manner in compliance with

procedure given in the rules under the aforesaid acts.

All personnel being absorbed at site would be made to attend environmental awareness

programme.

21

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

5.QUARRY MANAGEMENT PLAN: All our Quarrying does not need

blasting – (As per client requirement)

Quarry Operation:

Type of blasting:

Mining / Blasting operation as required will be carried out in a safe and secured manner.

Controlled blasting will be done. It will be ensured that least disturbance is caused while

carrying out such operations. All the applicable laws, rules and regulations pertaining to

the use of explosives will be strictly adhered. The supply of explosives required for

blasting will be done by licensed agencies on day-to-day basis. Safe blasting procedure

will be prepared as required prior to blasting/mining.

6.ENVIRONMENTAL MANAGEMENT AT WORK SITES:

In case of any diversion work for watercourse has to be done, the structure will be of RR

masonry backed sand filled available within the watercourse. After completion (for the

purpose of diversion) the RR masonry wall will be demolished and the stones will be

reused in construction works. The mortar will be disposed for land fill or basement filling

in building construction sites. The sand will be again spread in the river flow.

In case of small watercourse the Hume pipes will be laid first with sand cushion so that

the water passes through the pipes enabling no disturbance to the culvert construction.

These Hume pipes if not necessary will be removed and auctioned after completion.

Topsoil:

The topsoil generated from clearing and grubbing operation will be stocked and will be

used in slope protection measures such as turfing etc; If in excess these soil will be spread

over the dry unfertile land available at adjacent site with the permission of the land

owners or with the concern authority in case of government land.

22

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Schedule of Environmental Enhancements:

A Time bounded action plan will be prepared in the required format for the environmental improvements with the details of the improvement work planned, time of completion and person responsible.

Slope protection measures:

To protect the slopes from sliding and erosion the protection work such as stone pitching

with suitable stones will be done. Also the slopes will be turfed with the topsoil available

in the stock. Fast growing Vegetation will be developed al along the slope to avoid

erosion as per the requirement. Constructing the drainage channel along the slope will

drain the rainwater collected in the roads. Wherever necessary the pipes for drainage will

also be laid.

7. SOLID WASTE MANAGEMENT:

Waste generated during construction activities:

The different types of waste generated during construction are as follows:

Rubbish and garbage Sewage from camp Bituminous waste from Hot Mix Plant Used oil, fuel, lubricants etc; Damage precast units.

Rubbish / Garbage Disposal:

In camp garbage bins will be provided at different locations and primarily the waste will

be collected in this bins and disposed of safely on daily basis. The waste collected from

bins will be carted in a vehicle to the nearest municipal garbage collection or dumping

ground to disposed off. Signs will be provided where these bins are placed in the camp

and awareness will be created within the camp so as the waste will be disposed in the

dust collection bins. This process will ensure a healthy environment in the camp and

work site. The number of dustbins may be increased or decreased as per the requirement.

23

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Sewage / solid waste:

Septic tanks have been constructed in the camp at designated places of required numbers

and the toilets have been connected to these by PVC pipes Inspection chambers are also

provided and closed with cover. Soak pits followed by septic tank of suitable capacity

have been constructed.

Using municipal septic tank vehicles, solid waste will be cleared off from the septic tank.

A record of the same will be maintained and kept available for inspection as and when

required in camp.

Oil spills prevention control plan, storage and handling of Inflammable materials:

Various types of oils at construction site, like Diesel, Petrol, Engine oil, Grease,

Hydraulic oil, Transmission oil, etc; is used as fuel and for Hydraulic operations and for

Transformers. Oil, Grease and similar material will be stored on a paved surface. Diesel

as a fuel for all Earth Moving Equipments and other vehicles will be transported in a

separate vehicle with tank of suitable capacity. All other oily material will be transported

in a suitable container. To avoid oil spill drips pans will be provided during handling of

oil / diesel, etc. Even minor leaks from mobile equipments and generator will be

effectively arrested. Fixed generator sets will be provided with trays below them.

Flammable material like LPG cylinders and DA cylinders are used at site for gas cutting

jobs. These are to be storing at our store yard in a specially designated area. We are

keeping a bare numbers of cylinders as per our work requirement. We will strictly adhere

to statutory Gas Cylinders Rules while storing and handling these cylinders at our site.

All the hazardous waste will be collected by using necessary PPE’s and stored in the

designated area. For disposing it will be handed over to authorized agencies after

verifying their license and proper manifest copies will be maintained. All collection,

24

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

storage and disposal records related to hazardous waste will be maintained and kept ready

for inspection by the authorities and third party inspection.

Event Contingency Plan:

We shall provide adequate number of fire extinguishers and fire buckets at site to

control the fire due to inflammable materials.

We shall contact to nearest fire station and police station immediately to handle

such situation.

We shall call to nearest hospital if any emergency occurs.

Bituminous waste filter:

The Hot Mix Plant has inbuilt air bag filter system to prevent dust generation during

heating of the aggregates, mixing of aggregates with bitumen. The bag filter will have

auto arrangements for cleaning dust stocked in bags. The dust will be recycled as fines in

the process. Waste generated from the Hot Mix Plant will be used in developing the roads

inside of the construction camp or the approach road to the construction camp. The waste

will also be used for filling potholes in adjacent rural roads.

Damage Pre cast:

The damage pre cast material will be collected in the designated area and disposed of in

the disposal areas. The excess concrete will be utilized for the activities such as safety

pillars construction etc;

During site clearing the soil of approximate depth of 150mm or as per the instruction of

the technical person in charge will be removed. The stripped topsoil will be transported

using tippers to designated areas and stocked. This material will be used for turfing of

side slopes or used to cover the waste dumping area.

25

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

The material below the topsoil will be excavated for the construction activity. This

excavated material will be stocked and used in the construction if find suitable. This

material can be used for basement filling in case of building construction and can be

reapplied as fill material in road in case of roadwork. The used material will be disposed

for landfill in adjacent low lying areas.

Maintenance of Waste Records:

Register will be maintained for recording the details of the waste generated and their

disposal. These records will be kept ready for inspection for the authorized agencies.

Suggestion and complaints of these agencies during their visits will be recorded in

register. Record of septic tank cleaning will be maintained on site for reference. The

details of these agencies will be reflected in the monthly report as and when they have

been finalized.

Disposal of Waste:

All the non hazardous waste will be disposed as per the method given in the EMP. The

hazardous wastes will be disposed to the authorized agencies after verifying their permits.

8. ENVIRONMENTAL MONITORING:

Ambient Air Quality:

The pollutants level in the ambient air quality will be monitored at the four corners of the

campsite. Also air monitoring will be carried out as per the DPR at stated location.

Water Quality:

Water will be tested to ensure potability and quality.

Soil Quality:

Trail pits at four corners of the campsite will be digged and the soil is tested.

26

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

Noise Levels:

The ambient noise level at the boundary of the campsite, inside the plant and machineries

will be measured. Noise level will be measured at the stated location of site as per DPR.

Time schedule of monitoring:

Ambient Air Quality:

The ambient air quality monitoring will be done as per the requirement laid in DPR.

Water Quality:

Since there is no process wastewater generation the water quality in the bore well and

open well in and around campsite will be tested seasonally as mentioned in DPR.

Soil Quality:

The soil quality will be once in three month.

Noise Levels:

The workplace noise level will be tested periodically and the ambient noise level at stated

location will be tested as per the requirement laid in DPR.

9. PERMISSION AND CONSENTS:

All Plants will be established and operated as per the terms and condition applied by

Concern legal authority. All documentation will be maintained and records will be kept

ready for inspection as and when required by the authorities.

10. Legal and other requirements

27

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

The Chief HSE Manager is responsible for reviewing and updating (as and when required) the register of applicable legal and client requirements and for communicating the changes to the relevant personnel, verifying compliance to these requirements. The organization will keep this information up to date.

The legal and other requirements applicable to the Project are listed below:

1. The Water (Prevention and control of pollution) Act, 1974and Rules, 1975.

2. The Air (Prevention and control of pollution) Acts, 1981 and Rules, 1982.

3. The Environmental (protection)Act 1986 and rules 1986

4. The Hazardous Waste (Management, Handling & Trans-boundary

Movement) Rules, 2008.

5. The Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989

amended 2000.

6. The Bio- Medical wastes (management and handling) Rules, 1998.

7. The Noise pollution (regulation and control) rules, 2000.

8. The Ozone Depleting Substances (regulation and control) Rules, 2000.

9. The Batteries (Management and Handling) Rules, 2001.

10. The Gas Cylinder Rules, 2004.

11. The Indian Electricity Act, 2003 and Rules, 1956.

12. The central Motor Vehicle Acts, 1988 and Rules ,1989

13. The Petroleum Act, 1934 and Petroleum Rules, 2002.

14. Building and Other Construction workers (Regulation of Employment and

Conditions of Service) Act, !996, Central Rules,1998. Including requirements

of:

- Contract Labour (Regulation and Abolition) Act, 1970.

- Employees State Insurance Act and Rules.

- Workmen Compensation Act.

15. Code of Indian Road congress.

16. Client requirements

28

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

11. En v iron me n ta l Insp ecti on Report.

Report No.: Inspection Date: Inspected by :Inspection Area:Participants:

SL.NO.

ITEM OBSERVATION REMARKS

ACTION

1.0 AIR POLLUTION By Date By whom1.1 Dust

(approach roads, adjacent roads, working area, cement handling etc.)

Site Satisfactory Site Dusty Sprinkling carried

out as required Excavate removal within 2 days 1.2 Generators Satisfactory Maintenance regime followed Black smoke Leaking oil Drip Pans not available1.3 Vehicles Satisfactory PUC certificate available Black smoke Wheel Washed /Cleaned Leaking oil Side of vehicle clear of mud Material transported in

closed manner

29

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

1.4 Air Monitoring Carried out as per contract Results reported as

per contract Remedial measures in

place where required 2.0 WATER

POLLUTION2.1 Site Drains Drainage system functional

No Contamination Not blocked by

debris/garbage

No indications of Oil spilled in drains

Storage of chemical waste not nearby

Storage of refuse/ excavate muck not near

2.2 Adjacent Drains Not damaged No signs of pouring Bentonite No signs of pouring

Chemicals Signs of discharging Silt/

2.3 Separator Tanks Tank not full of silt Tank regularly emptied

3.0 NOISEPOLLUTION

3.1 Noise control measures

All powered mechanical equipments are sound reduced

Acoustic / enclosures constructed in areas of excessive noise

Equipment located 3.2 GeneratorsProvided

with acoustic enclosures

Effective Not effective Not provided

3.3 Noise Monitoring Carried out as per contract Not exceeded

baseline values Remedial

measures in place Results evaluated

statistically for inclusion in Monthly repot

4.0 WASTEMANAGEMENT

30

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

4.1 Waste Identified Chemical Flammable Corrosive Construction related/ oil/ Filters/ Batteries

Hazardous4.2 Storage

Containers & Bins

Adequate number and properly place

Proper quality Emptied regularly Labeling proper No spillage on

container surface noticed4.2 Storage

Containers & Bins

Pollutants (e.g. waste chemical), not dumped in bins

Recyclable (e.g. metal) not dumped in garbage bins4.3 Oil Waste Drip pans available

No oil stains on ground Spill absorption

material available Waste oil poured in

to designated waste drums

Used oil filters not dumped in garbage

4.4 Excavate/Muck Storage satisfactory/ properly secured

Dumping in authorized areas No interference with

nearby drainage5.0 STORAGE5.1 Diesel Storage Extensive diesel

spillage on ground not visible

Drip pans used when pumping diesel

Pipes / connectors/ pumps not leaking

Not located close to storm water drains

transfer 6. AESTHETICS &CLEANLINES

31

KSS-VALECHA CONSORTIUM

ENVIRONMENTAL MANAGEMENT PLAN

Date: 23.02. 2011

Page: 1 of 27

6.1 Housekeeping

&Hygiene

Designated storage area for materials

Scraps/brickbats/rubbish scattered at site

Proper space for handling waste

Area Clean and dry Stagnant water

treated weekly Proper stacking of drums Barricades are

clean, in line, firmly secured and proper earthling

Water not allowed to accumulate in work area for any reason

7.0 ROADS7.1 Access Roads Satisfactory Maintenance

In urgent need ofMaintena

7.2 Public Roads used

by Contractor

Satisfactory maintenance Repair not carried out

32