Environmental Management Plan -...
-
Upload
vuongkhanh -
Category
Documents
-
view
226 -
download
0
Transcript of Environmental Management Plan -...
EEnnvviirroonnmmeennttaall MMaannaaggeemmeenntt PPllaann
DHUNKAPADA STONE QUARRY
Village Dhunkapada
Tahasil-Polasara
District- Ganjam
Odisha
Lease area - 7.27 Ha
Khata No- 1382
Plot No- 5896, 5897 & 5898
For & on behalf of
SMT LAXMI BHUYAN
At- Kendubadi, Po-Mandar PS-Polasara, Dist- Ganjam
Odisha
1
Environment Management Plan of Dhunkapada Stone Quarry
1.0 Introduction
The stone quarry project, Dhunkapada Stone quarry over an area
17.968Acre or 7.27 Ha. situated in village Dhunkapada, Tahasil-Polasara of
Ganjam district Odisha. The mining plan has been approved by Sri K. Patnaik,
Dy Director Geology, south zone, Berhampur for a period from 2015-16 to
2019-20 (Five years) as per the provisions of OMMC(Ammendment ) Rule
2014. The Quarry at Dhunkapadais situated in Plot No- 5896, 5897 & 5898of
Khata No- 1382, Kissam-Pahad.
As per EIA Notification 2006 and subsequent amendment Environment
clearance is mandatory for mining of minerals. As per MoEF circular
15.01.2016 the minor mineral project below 25 Ha has been considered as B2
category and will be appraised based on Form 1, Pre-feasibility report and
Environment Management Plan. Environmental management involves functions that determine and
implement environmental policy. It involves identification of objectives,
adoption of appropriate mitigation measures, protection of ecosystem,
enhancement of quality of life for those affected and minimization of
environmental cost. Environmental Management Plan (EMP) will be
formulated with an objective to mitigate the adverse impact of any proposed
project. This includes an environmental policy on protection of environment
and public safety.
2
Environment Management Plan of Dhunkapada Stone Quarry
1.0.1 Name and address of the holder of the Mining Lease :
Name of the Project Dhunkapada Stone Quarry
Applicant Smt. Laxmi Bhuyan
Address of the Applicant At- Kendubadi, Po- Mandar
Ps- Polasara, Dist- Ganjam,
Odisha
Granted On 09/12/2015
Period of Concession 2015-16 to 2019-20
1.0.2 Details of the Area :
Name of the Project Dhunkapada Stone Quarry
Area 17.968Acres / 7.27 Hectares
Village Dhunkapada
Tahasil Polasara, Ganjam District, Odisha.
Khata Number 1382
Plot Number 5896, 5897 & 5898
Kisam Pahad
Location Latitude – N19045’24.0” to N19045’31.0”N
Longitude – 84046’28.3” to E 84046’51.9”E
Toposheet E44A13
Accessibility Dhunkapada Stone quarry over an area 17.968Acre
or 7.27 Ha. situated in village Dhunkapada, Tahasil-
Polasara of Ganjam district Odisha of Smt. Laxmi
Bhuyan can be approached from Bhubaneswar the
state capital of Odisha covering a distance 160 Km.
The district head quarter, Chhatrapur is situated at
a distance of 70km.
Mthod of mining Open cast Semi Mechanized Method
Reserve Geological Reserve: 732600 Cu.m
Mineable Reserve: 347400 Cu.m Waste Generation 500 Cu.m
Water/Power Drinking water is made available from the tube
wells. There is no passing of power line adjacent to
lease area.
Man Power 13 no.s
3
Environment Management Plan of Dhunkapada Stone Quarry
1.0.3 Location (map showing general location, specific location, project
boundary and project site layout)with co-ordinates.
Fig-1 showing general location of the project site
4
Environment Management Plan of Dhunkapada Stone Quarry
Specific location of the project site with project boundary
1.0.4 Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental considerations gone
into should be highlighted :
No alternate site is considered, as this particular site has been carrying
out stone mining previously.
1.0.5 Details of Machineries to be used in Mining Operation
The machinery details required for mining of construction stone is given
below:
5
Environment Management Plan of Dhunkapada Stone Quarry
Name of the Machine Capacity Nos. Main Purpose Remarks
Jack Hammer drill 32 mm 1 Drilling Hired
Truck/Tipper 10t 1 Waste/stone
transportation
Hired
Breaker 210T 1 Breaking of
ordinary stone
Hired
Drill rods & Hammer -- -- As required ---
Safety equipments such
as Helmets, Safety
shoes, goggles and
hand gloves.
-- As
required
Safety To be
Purchased
1.0.6 Detail of measurement of mining pit earlier excavation in the area
to be sanctioned and details of mineral concessions situated within
100m periphery of the area :
Not required as the source is declared as new source and there are no
other mines present within 500m periphery of the area.
1.0.7 Scheme of Plantation :
It has been proposed to plant 7.5 m width all along the quarry lease
boundary. Total 3.100 Acres of area proposed to be planted by 500 no of
saplings during plan period. Local species like Neem, Mahaneem, Karanja,
Banyan, Peepal, Arjun, Jackfruit & Mango etc. are proposed to be planted at
10m spacing.
6
Environment Management Plan of Dhunkapada Stone Quarry
year No. of saplings
to be planted
Species of
plants to be
planted
Place of
Plantation
1st 60 Mango, Neem,
Mahaneem,
Banyan, peepal,
Arjun and
others as
suggested by
forest
department
In the alluvial
soil present on
the southern
side of the lease
hold and free
govt. lands with
proper
permission
from concerned
authorities.
2nd 60
3rd 60
4th 60
5th 60
Total 300
1.0.8 Details and approximate distance of National Park, Sanctuary,
Biodiversity area, Interstate boundary situated within periphery
of 10 Km from the area to be sanctioned :
No above mentioned features are present within 10Km radius from the
lease area.
1.0.9 Proposed annual production of minerals :
The proposed annual production is2500 Cum of sand.
Year ANNUAL PRODUCTION
2015-16 900
2016-17 900
2017-18 900
2018-19 900
2019-20 900
Total 4500
7
Environment Management Plan of Dhunkapada Stone Quarry
1.0.10 Effect on Ground Water level due to mining operation and it’s
preventive measures :
As the proposed extraction will be done much above the ground
water table, hence no safety precautions are required for this
head.
1.0.11 Details of scheme of continuous reclamation and rehabilitation
of the land degradation due to mining operation :
Sl.No. Type Of Land Use At the end of 5 years
Area in Acre
1 Area under Excavation 3.706
2 Waste/stacking of stone 0.200
3 Road 0.150
4 Green belt Area 3.100
5 Un-utilized land 10.812
Total 5.058
1.0.12 Anticipated environmental impacts and control schemes :
a) Land use pattern and river course environment :
� Selection of mining site :
� Mining will be done in the lease hold inside the
safety zone.
b) Air quality monitoring :
� Monitoring :
� Time to time air monitoring will be done and
required steps will be taken.
8
Environment Management Plan of Dhunkapada Stone Quarry
� Loading :
� Before loading, the sand will be moisturized by
sprinkling water on it to stop air pollution.
� Transport :
� Tractors / Tippers will be covered by Tarpaulins.
� Water will be sprinkled on approach roads for dust
suppression.
� Overloading will be restricted.
� Periodic maintenance of these vehicles will be
done.
� Plantation :
� Plantation on the safety zone of quarry lease
boundary. If required, avenue plantation in nearby
free govt. lands will be done with proper
permission from the concerned authorities.
c) Water quality management :
� Surface water quality management :
� As the mining activity is restricted to dry area,
hence no waste water will be generated during
extraction of sand.
� Groundwater quality management :
� Ground water table will not get punctured by any
means as the mining activity will be performed
much above it.
� Waste water management :
9
Environment Management Plan of Dhunkapada Stone Quarry
� No waste water will be generated during
extraction of sand.
� However, if so happens, then septic tanks and soak
pits will be provided as per demand.
d) Noise management :
� Transported :
� All vehicles used for transportation should bear
PUC certificate.
� Minimum use of horns will be proposed.
� Adequate silencers will be provided in all diesel
engines of vehicles.
� Speed limit of 10Km/hr. will be regulated in village
area driving.
e) Green belt :
� Plantation :
� Plantation of suitable local species will be done in
outside of the lease hold as the lease area is river
bed.
� Avenue plantation will be done in nearby free govt.
lands with proper permission from the concerned
authorities, if required.
f) Solid waste management :
� No solid waste will be generated during mining
activity.
10
Environment Management Plan of Dhunkapada Stone Quarry
Surface water : -
a) General :
NA
The mining practice will not affect any change or diversion of any
source of water in the area or any drainage pattern because the mining
will be restricted to much above the ground water table. However, an
additional 7.5m mining restricted zone has been proposed, so that the
perennial flow of the river will not be affected by the mining activity.
The mining activity has been proposed on the upstream side of the
river.
b) Chemical :
NA
c) Ground Water :
The ground water will not be affected due to mining activity as this will
not puncture the ground water table by any means and will be
conducted much above it.
Environmental mitigation measures to be taken :
� Water sprinkling will be done before loading making it moist.
� Water sprinkling during transportation over approach roads will be
done for suppression of dust.
� Development of green belt will be carried out to reduce dust pollution.
� Periodic maintenance of vehicles will be done to reduce water and noise
pollution.
11
Environment Management Plan of Dhunkapada Stone Quarry
1.0.11 Provision for separate stacking of surface soil excavated from
mining operation and its utility:
No surface soil stack is required as no soil will be generated during extraction of sand.
So no provision for separate stacking of surface soil is required.
1.0.12 Details of social and economic up gradation of mining affected
area due to proposed project:
The impact on the social and economic condition of the local people will be positive,
as due to the mining activity, 2 personals will get direct employment and 11 personals will
get indirect employment.
1.0.13 Details of budgetary arrangement for environment management :
Total Rs 0.9 lakhs will be utilized annually for environment management and CSR activities.
Details are given as follows.
PROPOSED ACTION PLAN EXPENCES PER YEAR ( IN RS.)
Pollution control/ Dust suppression 20,000
Environment monitoring 20,000
CSR activities 25,000
Haul road repair 12,000
Miscellaneous 13,000
Total 90,000
1.0.14 Any other details to be submitted by mineral concession holder :
Change in Topography & Land Use pattern :
12
Environment Management Plan of Dhunkapada Stone Quarry
There will be no change in topography. However, the change in land use
pattern will be temporary. Depressions will be created in the lease hold area
due to mining activity, which will be converted to water recharge pits during
conceptual periods. Hence the above said changes will be reclaimed after
mining.
1.0.15.1 Effect on Flora and Fauna :
Land degradation and deforestation happen due to mining activities which
have impact on Flora and Fauna.
The mining area is in Non-forest land i.e. sandy river bed, where presence of
Fauna is not at all seen. As such, there will be no adverse impact of the manual
mining activity on Fauna around the mining lease area.
No adverse impact will be envisaged on the existing aquatic fauna, if any, on
downstream side, as the mining confined to above water level and at all
touching / disturbing water table.
As the lease hold area is devoid of any trees, hence no there will be no chance
of uprooting any tree due to mining operation. Only some scrubs and bushes
will e uprooted.
There will be no significant impact on the biological diversity around 5 Km
radius of the site as there is none of them.
1.0.15.2 Effect on Climate :
There is no impact on the climate as the proposed mining will be adopt the
mitigation measure to control the pollution. Every step will be taken to
13
Environment Management Plan of Dhunkapada Stone Quarry
control the pollution, which will cause no effect on microclimate regime. For
up gradation of the climatic condition, plantation will be done.
1.0.15.3 Noise pollution:
Noise is generated due to activity of machineries during mining. This will be
maintained by taking adequate measures for time to time maintenance of
these machines (Vehicles like Tractors and Tippers).
1.0.15.4 Accumulation of waste:
Waste (rejects) generated during plan period will be 500cu.m. No dump is
proposed as the total rejects will be utilized for the construction and
maintenance of haul road within the lease.
1.0.15.5 Visual impact:
There is no any visual impact in the vicinity.
1.0.15.6 Historical Monuments:
There is no place of tourist interest, historical or religious importance in the
vicinity.
15
Environment Management Plan of Dhunkapada Stone Quarry
ENVIRONMENT MANAGEMENT PLAN
Environmental Management Plan (EMP) consists of a set of impact
mitigation, management, monitoring, waste minimization and institutional
measures to be taken during implementation and operation of the project to
eliminate the adverse environmental impacts or to reduce them to the
acceptable level. The EMP is required to ensure sustainable development as it
tries to ensure judicious utilization of non renewable resources and keep the
pollution level within permissible assimilative capacity of the area. The
assimilative capacity of the study area is the maximum amount of the
pollution load that can be discharged in the environment without affecting the
16
Environment Management Plan of Dhunkapada Stone Quarry
designated use and is governed by dilution, dispersion and removal due to
natural physiochemical and biological process.
Mining of Construction stone has a direct impact on the land
topography, ambient air quality, drainage and water, soil and land use pattern.
The impact of mining on the surrounding environment include increase dust
emission during excavation of granite stone, squaring, sizing loading,
unloading and transportation activity. The ground water regime and surface
water quality may have some impact due to the mining process. To mitigate
such adverse impacts, appropriate remedial measures have been proposed.
An EMP is an implementation plan to mitigate and offset the adverse
environmental impacts of the project and to protect and where possible,
enhance the environment. EMP should be viewed as a legal commitment on
the part of the proponent to minimize environmental impacts. So
Environmental Management Plan (EMP), which will be an integral part of the
project for minimizing the adverse impacts and to ensure the sustainable
development of the area.
There are various sources of pollution during the mining and allied activities.
These includes drilling, block cutting, sizing and dressing, dumping, loading
and unloading, transportation etc which are having direct impact on the
environment.
17
Environment Management Plan of Dhunkapada Stone Quarry
ENVIRONMENT MONITORING PLAN
2.1 Introduction:
Regular monitoring of the environmental parameters is of immense
importance to maintain the environmental conditions as monitoring plays an
important role in management. Hence environmentalists and policy makers
can make changes in pollution control equipments and environment policy to
save the environment.
The main objectives of monitoring area as follows:
1. Very effectiveness of planning decisions
2. Measure effectiveness of operational procedures
3. Conform statutory and corporate compliance
4. Identify unexpected changes
2.2 Environmental Monitoring Cell:
A centralized Environmental Monitoring Cell will be established for
monitoring of important environmental parameters which are of immense
importance to access the status of environment during mine operation. The
routine monitoring program will be implemented under project
monitoring as per CPCB & MoEF & CC guidelines. Officer not below the
rank of Manager will be responsible of environmental management cell
and execution of environmental monitoring program.
2.3 Environmental Parameters
18
Environment Management Plan of Dhunkapada Stone Quarry
Environmental monitoring Program will be conducted once in season
except Monsoon. Various parameters which will be taken into account are
as follows.
ENVIRONMENTAL PARAMETERS AND FREQUENCY
Sl. No. Potential
Impact
Parameters for
monitoring
Frequency of monitoring
1 Air Emission PM10, PM2.5, SO2,
NOX & CO
As per CPCB / MoEF & CC
requirements i.e. 24 hourly
monitoring for one month in
each season except monsoon
season.
2 Noise Spot Noise level
recording
Leq(Day)
Leq(Night)
Leq(Dn)
Periodic / As per CPCB norms
i.e. Once in season (1 – hourly)
3 Water Quality As per drinking
water standards
Once in season except
Monsoon
4 Soil Quality Analyzed as
CPCB method
Once in season except
Monsoon
5 Health Total health
parameters
Initial Medical Examination
(IME) and periodic medical
examination – once in five
years as per Mines Rules, 1955.
19
Environment Management Plan of Dhunkapada Stone Quarry
Sl. No. Description Frequency Of Monitoring
1 Ambient Air Quality in and
around Mines
One sample after 24 hours
continuous monitoring will be done
twice a week in every year during
mining period or as per norms of
SPCB, Odisha
2 Water Quality Annually once for 2 surface water
samples during mining period or as
per norms of SPCB, Odisha & MoEF
for various parameters
3 Noise Level Monitoring Once in every year for 24 hours
during mining period or as per
norms of SPCB, Odisha & MoEF.
SUMMARY
Fugitive emission in the form of dust shall be generated during handling and
loading ofsand. The adequate preventive measures will be adopted to contain
the various pollutants within permissible limits. Plantation development will
be carried out in the mine premises, along the approach roads, around Govt.
buildings, schools. It will prove an effective pollution mitigate technique, and
help avoid soil erosion during monsoon season. Employment opportunities
will be provided to the local villagers to improve their live hood.
20
Environment Management Plan of Dhunkapada Stone Quarry
FINAL RECOMMENDATION
Post-Project Environmental Monitoring is an essential tool in
Environmental Management Program to check the environmental quality
status through monitoring of environmental parameters as per frequency and
method recommended by CPCB. It helps environmentalist and policy makers
to maintain the status of the green environment. It will help sustainable
growth through clean mining activity.
The environmental cell will co-ordinate all monitoring program,
Environmental awareness Program, Training and its importance in proposed
project at site. Half-yearly report will be submitted on June and January of
each year to the regional office of MoEF / CC, Odisha. Objective of the entire
process will be to improve environment and reduce the impact of project
activities on Our Environment.
In course of mining there will be no generation of waste. As every year during
rainy season there will replenishment of the excavated portion, there will be
no need of closure procedure. The total operation shall be carried out with
ease & minimum risk of the workers. The excavation of river sand will not
only generate royalty for the Government but also keep the river bed from
filling up and the carrying capacity of the river will be intact to mitigate the
floods.
The proposed Environmental Management Plan will keep the area in a safe
environment with negligible impact on the environment. The Plantation will
substantiate the impact due to the mining activity.
The Lessee shall pay 5 % of the royalty to the authority towards environment
management fund.