ENVIRONMENTAL ISSUES
-
Upload
constance-downs -
Category
Documents
-
view
48 -
download
0
description
Transcript of ENVIRONMENTAL ISSUES
Environmental Changes for 2010 NOFAS
Environmental Changes for 2010 NOFAS
New Requirements:• Application processing stage
– Environmental Report• New requirement• 202s, 811s as Cat A• Not curable deficiency• To help HUD with prelim environmental
review
New Requirements:• Application processing stage
– Environmental Report• New requirement• 202s, 811s as Cat A• Not curable deficiency• To help HUD with prelim environmental
review
2
Environmental ChangesEnvironmental Changes
Environmental Report
• Separate from Phase I ESA• Per NOFA: should focus on
– State environmental requirements– Relevant topics in SFNC and 4128– Per NOFA HP, FP wetlands, endangered
species, noise, fire/explosive hazards, CZM, flood zones
Environmental Report
• Separate from Phase I ESA• Per NOFA: should focus on
– State environmental requirements– Relevant topics in SFNC and 4128– Per NOFA HP, FP wetlands, endangered
species, noise, fire/explosive hazards, CZM, flood zones
3
Environmental Changes Environmental Changes
Phase I Environmental Site Assessment (ESA),
– Phase I Environmental Site Assessment no longer curable deficiency
– Vapor Encroachment analysis– Environmental Professional (EP) requirements
laid out– Applicant to fill out “User Questionnaire “and
provide to EP, to be included in Phase I ESA– Applicant to inform EP of reasons and
requirements for the Phase I ESA– Findings, Opinions, and Conclusions
requirements described in greater detail– More detailed discussion of Phase I ESA timing
requirements
Phase I Environmental Site Assessment (ESA),
– Phase I Environmental Site Assessment no longer curable deficiency
– Vapor Encroachment analysis– Environmental Professional (EP) requirements
laid out– Applicant to fill out “User Questionnaire “and
provide to EP, to be included in Phase I ESA– Applicant to inform EP of reasons and
requirements for the Phase I ESA– Findings, Opinions, and Conclusions
requirements described in greater detail– More detailed discussion of Phase I ESA timing
requirements
4
Environmental Changes, contd. Environmental Changes, contd.
Phase II ESA when required
– Must be submitted with application– Must address all Recognized
Environmental Conditions (REC) and Vapor Encroachment Conditions (VEC) identified in Phase I ESA
– To address on-site and off-site RECs and VECs
Phase II ESA when required
– Must be submitted with application– Must address all Recognized
Environmental Conditions (REC) and Vapor Encroachment Conditions (VEC) identified in Phase I ESA
– To address on-site and off-site RECs and VECs
5
Environmental changes, contd. Environmental changes, contd.
Clean-up
• Clean-up plan and associated documentation outlined below must be submitted with application
• Risk-based Corrective Action (RBCA) now allowed
• Contract for any remediation not required at application processing
• Estimate only of clean-up costs required with application
Clean-up
• Clean-up plan and associated documentation outlined below must be submitted with application
• Risk-based Corrective Action (RBCA) now allowed
• Contract for any remediation not required at application processing
• Estimate only of clean-up costs required with application
6
Environmental Changes Environmental Changes
Clean-up• Approval of remediation plan from the
federal, State or local authorities not mandatory at application Processing stage
• Final clean-up plan prior to FIRM
• Completion of work prior to final closing or initial occupancy, whichever comes first with feasibility statement to same in NOFA
• Clarifies how clean-up an allowable cost
Clean-up• Approval of remediation plan from the
federal, State or local authorities not mandatory at application Processing stage
• Final clean-up plan prior to FIRM
• Completion of work prior to final closing or initial occupancy, whichever comes first with feasibility statement to same in NOFA
• Clarifies how clean-up an allowable cost
7
Hazard Identification and Remediation
Hazard Identification and Remediation
• Groundwater exception to complete clean-up of site
– All contamination in GW at least 25 feet below surface
– No groundwater use in area or active water supply wells on site
• Groundwater exception to complete clean-up of site
– All contamination in GW at least 25 feet below surface
– No groundwater use in area or active water supply wells on site
8
Environmental ChangesAsbestos requirements
Environmental ChangesAsbestos requirements
When Comprehensive Building Asbestos Survey required– ASTM E 2356-10 “Standard Practice for
Comprehensive Building Asbestos Surveys.”• “baseline survey”
•Not required if no pre-1978 or 4 or fewer units.
When Comprehensive Building Asbestos Survey required– ASTM E 2356-10 “Standard Practice for
Comprehensive Building Asbestos Surveys.”• “baseline survey”
•Not required if no pre-1978 or 4 or fewer units.
9
Comprehensive Building Asbestos Survey
Comprehensive Building Asbestos Survey
• Not required if sponsor statement that no Pre-1978 structures or only 1-4 units residential on site
• Asbestos screen not acceptable
• Friable or affected by rehabilitation/demolition – abate
• Other asbestos: O&M plan
• Not required if sponsor statement that no Pre-1978 structures or only 1-4 units residential on site
• Asbestos screen not acceptable
• Friable or affected by rehabilitation/demolition – abate
• Other asbestos: O&M plan
10
Floodplains and WetlandsFloodplains and Wetlands
Sponsors should try to select sites out of
– 100-year floodplain– 500-year floodplain for critical
actions: special care; i.e..., not independent living projects
– Wetlands
Sponsors should try to select sites out of
– 100-year floodplain– 500-year floodplain for critical
actions: special care; i.e..., not independent living projects
– Wetlands11
Environmental Changes ENVIRONMENTAL REVIEW PROCESS Environmental Changes ENVIRONMENTAL REVIEW PROCESS
Application Processing Stage • Preliminary environmental Reviews– Except Technical reject for: floodway,
coastal high hazard, 100-year flood plain
• Not constitute HUD environmental approval of project site
Application Processing Stage • Preliminary environmental Reviews– Except Technical reject for: floodway,
coastal high hazard, 100-year flood plain
• Not constitute HUD environmental approval of project site
12
Environmental Changes ENVIRONMENTAL REVIEW PROCESS Environmental Changes ENVIRONMENTAL REVIEW PROCESS
Approved grantees
– If site deemed environmentally unacceptable:• Pursuant to NOFA, fund reservation
may be cancelled• So, in Environmental Report make
sure to address issues
Approved grantees
– If site deemed environmentally unacceptable:• Pursuant to NOFA, fund reservation
may be cancelled• So, in Environmental Report make
sure to address issues
13
Environmental Changes Environmental Changes
Environmental Rating
– HUD will deduct 2 points if HUD’s preliminary environmental review determines that there are obvious adverse environmental conditions and appropriate mitigation of such does not appear to be achievable within 6 months of the fund reservation date.
Environmental Rating
– HUD will deduct 2 points if HUD’s preliminary environmental review determines that there are obvious adverse environmental conditions and appropriate mitigation of such does not appear to be achievable within 6 months of the fund reservation date.
14
General General
• 202/811 Sponsors and HUD are partners
• HUD wants Sponsors to– Find a site with no concerns/easily
resolvable concerns, especially• Toxic Hazards• Historic Preservation• Floodplain or Wetland
• 202/811 Sponsors and HUD are partners
• HUD wants Sponsors to– Find a site with no concerns/easily
resolvable concerns, especially• Toxic Hazards• Historic Preservation• Floodplain or Wetland
15
Hazard Identification and Remediation
Hazard Identification and Remediation
• Phase I Environmental Site Ass
• essment (ESA) Must use ASTM 1527-05, as amended
• Phase I Environmental Site Ass
• essment (ESA) Must use ASTM 1527-05, as amended
16
Hazard I&R Hazard I&R
Phase I ESA
– Tech reject• If use earlier version of 1527• Failure to use Appendix X4• Failure to use Sections 12.5, 12.6, 12.8• Failure to follow new/revised requirements
discussed earlier
Phase I ESA
– Tech reject• If use earlier version of 1527• Failure to use Appendix X4• Failure to use Sections 12.5, 12.6, 12.8• Failure to follow new/revised requirements
discussed earlier
19
Choosing an Environmentally “Safe”
Site
Choosing an Environmentally “Safe”
Site• Accessed through WEB page of 202/811
SuperNOFA• Excellent discussion• Discusses Phase I ESAs, especially for
202/811 programs• Special discussions on– Toxic & hazardous substances– USTs– Asbestos– LBP
• Accessed through WEB page of 202/811 SuperNOFA
• Excellent discussion• Discusses Phase I ESAs, especially for
202/811 programs• Special discussions on– Toxic & hazardous substances– USTs– Asbestos– LBP
20
Choosing an Environmentally “Safe” Site
Supplemental Guidance
Choosing an Environmentally “Safe” Site
Supplemental Guidance
• Accessed through Funds Available Web page for the 202/811 Programs
• Discusses manmade hazards as well as items that HUD may look at during environmental review
• Accessed through Funds Available Web page for the 202/811 Programs
• Discusses manmade hazards as well as items that HUD may look at during environmental review
22
HUD Form 4128HUD Form 4128
• Used to record environmental review
• HUD appraiser performs site visit and records results on the “Sample Field Notes Checklist”
• Used to record environmental review
• HUD appraiser performs site visit and records results on the “Sample Field Notes Checklist”
23
Historic PreservationHistoric Preservation
• Sample letter to SHPO/THPO– Accessed through HUD WEB page of
202/811 SuperNOFA– Developed by HUD HPO– Includes all information necessary for
SHPO/ THPO to provide comment– Allows for dual response to sponsor &
HUD– Some Field Offices might have other
sample letters
• Sample letter to SHPO/THPO– Accessed through HUD WEB page of
202/811 SuperNOFA– Developed by HUD HPO– Includes all information necessary for
SHPO/ THPO to provide comment– Allows for dual response to sponsor &
HUD– Some Field Offices might have other
sample letters
26
Historic PreservationHistoric Preservation
• If HUD needs to contact SHPO– will be done only for approved
applications
• HUD will complete HP prior to FIRM– At application stage if HUD believes it
will take longer than 6 months – minus 2 points
• If HUD needs to contact SHPO– will be done only for approved
applications
• HUD will complete HP prior to FIRM– At application stage if HUD believes it
will take longer than 6 months – minus 2 points
27
Historic PreservationHistoric Preservation
If HUD possesses knowledge that a site might have Religious or Cultural Significance to Indian tribe or Native Hawaiian Organization
– HUD will request their comments
If HUD possesses knowledge that a site might have Religious or Cultural Significance to Indian tribe or Native Hawaiian Organization
– HUD will request their comments
28
HUD HP Archeological Survey Policy
HUD HP Archeological Survey Policy
• HUD rarely requires (even if SHPO requests such)– HUD HP fact sheet 6 REVISED
• http://www.hud.gov/offices/cpd/environment/review/hpfactsheet06.pdf
– Proposed or adjacent site already determined eligible/listed
– Preliminary site work (e.g. previous surveys or predictive models) has established eligibility
• HUD rarely requires (even if SHPO requests such)– HUD HP fact sheet 6 REVISED
• http://www.hud.gov/offices/cpd/environment/review/hpfactsheet06.pdf
– Proposed or adjacent site already determined eligible/listed
– Preliminary site work (e.g. previous surveys or predictive models) has established eligibility
29
Floodplains and WetlandsFloodplains and Wetlands
• Sponsors should try to select sites out of – 100-year floodplain– 500-year floodplain for critical
actions: special care; i.e..., not independent living projects
– Wetlands– Reminder: 6 months – minus 2
points
• Sponsors should try to select sites out of – 100-year floodplain– 500-year floodplain for critical
actions: special care; i.e..., not independent living projects
– Wetlands– Reminder: 6 months – minus 2
points30
Floodplains and WetlandsFloodplains and Wetlands
• For new construction projects deemed acceptable based on no practicable alternatives, condition on approval documents– CLOMA/CLOMR prior to firm– FLOMA/FLOMR prior to final closing– Flood insurance during construction
• For new construction projects deemed acceptable based on no practicable alternatives, condition on approval documents– CLOMA/CLOMR prior to firm– FLOMA/FLOMR prior to final closing– Flood insurance during construction
31