Environmental Impact Assessment (EIA) of Metro Bhawan

133
Final Report Environmental Impact Assessment (EIA) of Metro Bhawan Barakhamba Lane, Connaught Place New Del hi Transportation Plannlng and Environment Division February, 2007

Transcript of Environmental Impact Assessment (EIA) of Metro Bhawan

Page 1: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report

Environmental Impact Assessment (EIA) of

Metro Bhawan Barakhamba Lane, Connaught Place

New Del hi

Transportation Plannlng and Environment Division

February, 2007

Page 2: Environmental Impact Assessment (EIA) of Metro Bhawan

The Environmental impact Assessment (EIA) study flndlngs/results and other

related information furnlshed in this report are based on the primary data

collected for the baseline environmental studies carried out by the Central

Road Research Institute (CRRI) New Delhl, as well as from the secondary

data available from various other agencies (Government and Non - Government). The responsibility of the CRRI Is limited to the output produced

for the Environmental Impact Assessment study for the proposed Metro

Bhawan, located in the Fire Brigade Lane, Connaught Place, as per the

objectives of the EIA study and Terms of Reference (TOR) of the work order.

Any use of the flndlngs of the report without consulting CRRI by any other

agency or person other than the client is solely at thelrfown risk and

responsibility.

Page 3: Environmental Impact Assessment (EIA) of Metro Bhawan

?he construction and operation of any commercial or offlce bulldlng/ complex In any urban area, particularly in the metropolitan cltles like Delhl have significant impacts on the surrounding envlronment because of the likely increase in demand of potable water supply and sewage dlsposal requirement of an already over-stressed system of the area, Further, air quallty degradation and nolse pollution may further worsen due to increased vehlcular tramc on the adjacent road network along with the traffic congestion and posslble Increased incldenb on road. Thus, In view of possible associated adverse environmental Impacts, Mlnistry of Environment and Forests (MoEFI Govt. of Indla, has made it mandatory to carry out Environmental Impact Assessment (EIA) study for various building and construction projects wlth built-up area between 20,000 mZ -1,50,000m2 . With a vlew to assesslng potential environmental Impacts arlslng out of the construction and operation of the Metro Bhawan building (built-up area 26,000 m2), the DMRC had retalned Central Road Research Insmute (CRRI), New Delhi to undertake EIA study for varlous environmental components and to prepare a detailed Environmental Management Plan (EMP) for the same.

The Metro Bhawan located at the Connaught Place (Central Buslness DlstrlQ) in the New Delhl District wlll be the main Operational Control Centre (OCC) for the entire Metro network of Delhl controlling its operation and maintenance.

J Thls EIA report contalns baseline data on alr quallty, noise levels, vehlcular

I traffic 81 parking, water quality, soil characteristics and green cover

,J components at the project slte wlth a vlew to identifylng and assesslng the potential Impacts during different phases of project actlvlties. An

I Environmental Management Plan has also been delineated for the mltlgation of the adverse impacts.

1 Thls report wlll prove to be valuable In that regard and meet requirements of

1 DMRC.

A4 'Ye

Dr P K Nanda Director

Page 4: Environmental Impact Assessment (EIA) of Metro Bhawan

The study team Is thankful to Shrl S D Sharrna, Chlef Engineer (Planning),

Shri S A Verma, Dy. Chief Environmental Officer, Deihi Metro Rail

Corporation (DMRC) Umited, for providing the valuable suggestions and

necessary inputs as and when required by the team. The team also

acknowledges help of Shri M K Chaturvedl, Dy. Chief Engineer (MB) for

providing valuable inputs which had greatly helped bringing the report in the

present form. The study team also sincerely acknowledges the assistance

and help that has been rendered by the CRRI staff in terms of providing all

facilities in the successful completion of the project.

Page 5: Environmental Impact Assessment (EIA) of Metro Bhawan

Director Dr.P.K.Nanda

Head (Tr'anSpartatlon Planning & Envlronment Dlvlslon) Dr.S.Gangopadhyay

Project Leader Dr. Nlraj Sharma

Study Team

Dr. Nlraj Shrama Mr.Chander Bhan

Ms. Pratlbha Nalr ( Research Intern) Mr. Naseern Akhtar (Nolse Pollution Study) Mr. Subhash Chand (Trafflc Study) Mr. S.K. Blswas (Trafflc Survey) Mr. Daya Ram Mr. Jagdlsh Janpangl (Trafflc Survey)

Sscretarlal Assistance Ms. Sarlta Sethi

Page 6: Environmental Impact Assessment (EIA) of Metro Bhawan

find neport e*l M bwu B h w n , 81fWNnb. tsm, Wefh?-w

List of Contents

Page NO. 1

1. ntroduc

I

I

Page 7: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 8: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 9: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 10: Environmental Impact Assessment (EIA) of Metro Bhawan

Dwcrlptlon NO.

7.1

7 . 2

7.3

7.4

Bhawan Monitoring Progmm during the Construction and Operation Phase Year-wise Cost Estimates for Environmental Monltoring program (During Construction phase) Year-wise Cost Estimates for Environmental Monitoring Program (During Operation phase) Estimated Financial Implications for environmental monltorlng program(Construction and Operation Phase)

NO.

7.4

7.6

7.8

7.10

Page 11: Environmental Impact Assessment (EIA) of Metro Bhawan

List of Figures

Description -

Page 12: Environmental Impact Assessment (EIA) of Metro Bhawan

Chapter I Introduction

All wnstructlon - based projects must co-exlst satisfactorily wlth its surroundlng

envlronment, so as to reduce the envlronmental Impact caused due to varlous

actlvltles related to its constructlon and subsequent operation. Hence, a sound and

safe envlmnment management plan Is requlred to be Incorporated by the project

proponent to achieve sustalnable development. In order to assess the llkely impacts

arlslng out of the constructlon of Metro Bhawan on the surroundlng environment

and evaluating means of allevlatlng the llkely negatlve Impacts (If any), emanating

from thls project, the Delhl Metro Rall Corporatlon (DMRC) LM. has retalned Central

Road Research Institute (CRRI), New Delhl as thelr envimnmental consultant. The

CRW had carried out an Environmental Impact Assessment (EIA) of Metro Bhawan

bullt at Flre Brigade Lane, Barakharnba Road, New Delhl, for varlous environmental

components, whlch am llkely to be affected due to the proposed actlvlty.

The Metro Bhawan shall be the maln Operational Control Centre for the smooth

funalonlng of DMRC related work. Thls bullding has been bullt in en area of 10,870

mZ. comprising of two basements and eight floors. The total cost Incurred in thls

project is approximately 4189 lakhs. A brlef summary of the project Is provided In

the Chapter 2 - Project Ssttlnu. Any bulldlng of thls magnitude Is bound to put \ >

pressure on publlc utilities, water avallabillty and at tlmes contrlbutlng to trafflc G . segment, besldes sometlmes involving resettlement and rehabllltatlon issues hence

I ? assessment of impacts arislng out of such actlvlty Is mandatory. , ,

The DMRC Culture specifies that the Metro and its related constructlon actlvkles

should not lead to any ewloglcal or cnvlronmental degradation. Thereby,

Envlronrnental Impact Assessments are done for every sectlon of the Metro to

ensure that the ecological balance Is not disturbed by Metro constructlon actlvltles.

This Is further established by the fact that the Delhl Metro Rail Corporatlon (DMRC)

has already acquired the I S 0 14001 certlfieate for establishing an environmental

management system maklng It the First Metro in the World to recelve thls

certlflcatlon at the constructlon stage of the Metro. In addltlon, the Delhi Metro has

Page 13: Environmental Impact Assessment (EIA) of Metro Bhawan

Z'I

lea03 au3 40 %Gz paa3xa aou saop a~nalpuedxa ay3 JO pa3uaruuro3 pu sey ~JOM UolpnJasuos ay3 WaqM pue uolamy~mu sly3 Japun pw1nba.I aue~eap aya

Bululefqo 3noytM uaywapun EU~M WI~M sa3ws3 IeIJasnpuI Mau JQ 8583 ay3 u~ (11

'~OOZ ' ,%L Alnc WOJJ w 431~ UOI~B~IJI~OU sly3 Japun aDueAsap arlnba lleys '(aha( yaulld ay3 oa dn aum

pu say ~AOM UOI~~J~SUO~ wey~ pue 'uoIaq13ou sly3 Japun parlnbw a3ue~eep

aya Bu~u~gqo anoyalM uayetlapun EU~M y~jy~ wafad UownJasum MaN (I

"$3~ SI 1e13uaaod uoRnllod Jleua JI me p ahlpadswJl saawsa pwinpul aya Bu1pnl3xa

anq Molaq JO saAspey os 40 we uo ul sawn lelqsnpul Ou~epouruoss~ sa3elsa

le~3snpu1 Bulpnpu~ ~-e~npaqas JO CE Afua mpun ~UIIIPJ wwsa IeIJwnpul Auw (11

.Molaq

JO (satas &IJ saadnll) -/000'00'00'0~'~~1 JO auawaseAul ue y31~ JO ~oleq JO

Aep Jad SWJII (puesnoq~ Slu) 000'0~ JO ae6eMas Bu1EUey3s1p JO Molaq JO suosled

(puasnoy3 auo) 000'~ JQJ sexaldwm aswo pue s~ealdsoq 'saxeldurn (wq

'saxaldwos le[ateurwo3 'squolcn lueuraluas 'sd~ysu~o~ IelJjsnpul 'sdlqsuMo3

Mau Bulpnpu~ 1-elnpay3s 40 TE haua Japun bllloj pafad uolunJ3sum Aue (I

-:Alaueu

'PW@Plsua W IlPlls Bul~ollo~ all3 UOR~lJlWu VI3 P66T 40 3UaWPUaUo PO02

'AlnC .L PW Jad sw '(tt667 AeW Paw uo1le31~13ou plo) 9002 Jaqrua3des ,,PT Pam

uo1amUlwu w13 paslnar A13uam heh aqa lllun suolaPsulpou ET anoqe auawapun

UoRBsUlaOu sly1 '~661 henue~ ul PJPIKIOJ and seM auaueJ(nba~ en(ae~~s~u~urpa

ueqa Jayam auauwlntm Aanaw e se QI~ Bpeu y31ym uoneagwu asl~ ayl

'auR do ueds woys e ysns UI 33esl~ll~a3 slqa ahlam 03 ar3aru lauo~~e~edo Aluo eyl aq Aew

3u~a 'enoua~3 '(VNM) 'pal -IN PIPUI aleAeN OU~IIWI o~~s18etl Aq (~008~ auenbas

auarussessw 14a~es PUP y3leaI-I leuotadnno) 1008~ SVSHO PepJsMe uaaq osle

Page 14: Environmental Impact Assessment (EIA) of Metro Bhawan

sanctioned cost, shall requlre clearance under this notificatlon with effect from

the 7th day of July, 2004.

111) Any project proponent lntendlng to Implement the proposed project under sub-

paras (9) and (h) in a phased manner or in modules, shall be required to submit

the details of the entire project coverlng ail phases or modules for appralsai

under this notlflcstlon"

In the rwlsed notlflcation, under the head 8 (a) ail the Bulldlng and

Construction projacb greater than 20,000 oq. rn. but 188s than 1,50,000

ma. of built-up area will be categorized as B projects which may or may not

require Environmental Clearance depending upon if located in whola or in part wlthin 10 km from the boundary of: (I) Protected Areas notlfied under the Wild

Life (Protection) Act, 1972, (11) Crlti~ally Polluted areas as notlfled by the Central

Poll~tlon Control Board from tlme to tlme, (Ill) Notifled Eco-sensitive areas, (Iv)

inter-State boundartas and International boundaries, will be treated as Category A

prdeas.

1.3 Justlfleatlon of the Project

The proposed Metm Bhawan wlll be the main operational control centre for the

Delhl Metro's Mass Rapld Transport Sysbrn. As per the revlsed notification the

proposed study might not come under its dlract: purview. But as per the terms &

conditions iald down In draft notlflcation dated 15" September 2005 all metro

projects necessarily required to undertake environmental clearance from Mlnlstry of

Environment and Forest (MoEF) and this project took off around the same tlme

hence EIA study was imparted to CRRI, New Deihi. Though as per the revlsed EIA notifleation dated 14' September 2006, all metro project were waived off carrying

out EIA of their projects.

1.3.1 Aim

Environmental Impact Assessment (EIA) of Metro Bhawan, Barakhamba Lane,

Connaught Place, New Delhi

Page 15: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM or Mam 6hawan. h k h a m b a Lam, Connaught Place

1.3.2 Objectives

The key objectives of the present study are as follows:

(I) TO study policy, legal and admlnlstratlve framework, the description of Project setting

(11) To collect of Envlronmental basellne data for varlous parameters of ecology (forestry, flshery and wildllfe], envlronrnental pollution (air, water, nolse and

solid waste) and soclo - economics (public health, education and economics)

(lli) Appraisal of Project activities and assessment of envlronmental impacts for

varlous phases of project cycle namely (a) Impacts due to project locatlon (b) Impacts due to project design & structure (c) Impacts due to project

constructlon, and (d) Impaas due to project operatlon

(Iv) To prepare Envlronmental Management Plan (EMP) to rnltlgate the adverse

impacts of the most critieal areas likely to contribute to the most slgnlflcant

envlronmental burdens, and

(v) To work out the cost of environmental mltlgatlon and monltorlng requirements.

1.3.3 Scope

the scope of the work is llmlted to Metro Bhawan, Barakhamba Lane, Connaught

Place, New Delhi.

1.3.4 Methodology

Any developmental adlvity In general is expected to cause impacts on surrounding

envlronment at the project site durlng Its Implementation and operation phases,

whlch can be elther positive or negative. The nature and lntenslty of Impacts on

different wmponents of envlronment depend on the type of project activities and

geographical mndltlons of the study area. The Impacts of the project actlvltles on

environmental wmponents can be quantlfled through Rapid Envlronmental Impact

Assessment (REIA) Studles wlthln the Impact zone of the project actlvltles. The

results of REIA Studles form the basls for the preparation of a vlable EMP for

mltlgatlon of the adverse Impacts. The REIA Studies for the proposed con!3truction

project deals with detalled studles for varlous envlronrnental components vlt. alr,

Page 16: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EIA ot~am Bhiruyar, Ba&amba Lane, Connaught Place

noise, water, land, blologlcal and soclo-economic environment. The broad

methodology to achleve above objedlves Is given below:

(I) Descrlptlon of Project Setting: The Metro Bhawan wlll be the maln

Operational Control Centre eontrolllng the operatlon and maintenance

department for the entlre MRTS network of Delhi. Along with this Management

and Project Offlces are also planned to be established here. It Is surrounded on

ends by high rlse structures. The total area of the site Is 10,870.20 sq.m. The

two wings of the complex face northwest and northeast and are connected

wlth the clrcular arc facing southwest. the height of the Metro Bhawan Is

approximately 37 metres.

(11) Collection of Envlmnmental Basellne data:-Collection and assessment of basellne data for various parameters of ecology (forestry, flshery and wlldllfe),

envlronrnental pollution (alr, water, nolse and solid waste) and soclo-

emnomlcs (publlc health, education and economics).

(III) Appraisal of Project Actlvltles :

(Iv) Assessment of Envlmmmtal ImpacW I n relatlon to location, deslgn and

structure, construction and operatlon of the project under various phases of pmject cycle namely

(a) Impacts due to project location

(b) Impacts due to project design 81 structure

(c) Impacts due to project eonstructlan; and

(d) Impacts due to project operatlon

v) Environmental Manapemant Plan (EWP): The EMP wlll be prepared to mltlgate the adverse Impacts lncludlng evaluatlon of alternative methods to reduce the adverse impacts of most crltlcal areas llkely to wntribute to most

signlflcant envlronmental burdens.

Page 17: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EIA or Metro Bhawan, Barakhamba Lane, C4nrMught Rscc

Chapter 2 Project Description

2 General Descrlptlon

The Metro Bhawan will be the main Operatlonal Control Centre (OCC) for the entire

Metro network of Delhi controlling Its operation and malntenance. Along wlth thls,

Management and Project offlce has also been planned to be established at Metro

Bhawan for efficient working and operation of Delhi Metro system. The bulldingl

land use is as per the approved Mastar Plan of Delhl. The construction adlvlty Is

restricted to project slte. The building has been bulk at Connaught Place located In

the center of Delhi in the New Daihi Dlstrlct. Being located at the Central Business

District (CBD), thls area already harbours several commercial and offlce complexes.

The buildlng Is surrounded on ends by high rise structures. The total area of the slte

Is 10,870.20 m2. The height of the Metro Bhawan Is approximately 37m (Fig. 2.1).

The constructlon of the Metro Bhawan has been carrled out by M/s Nagarjuna

Construction Co. Ltd. The approval from the Delhl Urban Art Commlsslon (DUAC)

and Delhi Fire Service (DFS) was also obtained. Thls was important, as the

proposed project Is located in the Lutyen's Delhl under the jurlsdictlon of New Delhi

Munlclpal Corporation (NDMC), Following recommendation were made by DUAC to

DMRC whlle providing neceSSary appmval/no objection csrtlficate for the

constructlon of Metro Bhawan at Barakhamba Lane, Connaught Place, New Delhl.

(I) No. reflection glass was frr be used in the buildlng (11) The traffic circulatlon and pedestrlan movement needed to be

streamlined whlch was observed to be mlxed up.

2.2 Project Location

The Natlonal Capital Territory occupies an area of 1483 m2 and lles between

28*24'15# and 28°53'~0*~ latitudes and 76'50'24" and 77'20'30~ E longitudes. For

admlnistratlve purposes, NCT Delhl Is divided Into 9 dlstrlcts and 27 tehslls/ sub-

dlvlsions. The total populatlon of NCT Delhi as per the 2001 census Is 137.83 lakhs

wlth a populatlon density of 9,344 persons per sq. km area. The population of Delhl

has increased with the rate of 4.63% per annum during the decade 1991 - 2001.

Conslderlng the same growth rate for the present decade, it Is estimated that the

Page 18: Environmental Impact Assessment (EIA) of Metro Bhawan

.ails a3aFad ay7 punme padolanap suolllpum hlelluesun ou a3uay '5~1s pafad 943

je PaPlno~d waM 33% gal103 awl S~I~IPQJ Jayao oslw .slslaq ~eauw uo araM M~J pue

Uue3 lylaa PUP aje5 araurysen 7e aueld Bulysleq ayq le paplnmd aram sluaur3nq

Anoqel aql 'aals vafwd aqa $e fuaumlnbar ~1943 uodn bulpuadap paAoldap

aJaM 18uuowad JnoqPI OOL - 009 lnoqw .aJls paFo~d aya ~oau aals pazlJoqaneun Aue

JO aals -1~0~ le pemolle sem dwm Jnoqel ON .quawarlnba Jew pue BulJaalays

JOJ ~uawa6ue~~ IClessaau apew jlasurlq ~oper~um ayj 'oslw 'panlonul wamoqol

eqa JOJ uo~epour~ossa ~UIAII 6ulysllqeJsa JOJ pasn aq mu sem afls pasodo~d aqI

aueworlnbe~ Jnoqsi E~E~Z .(auauraseq pepuw) lanai puno~6 qdn 06

(IWI~S 'ou T pue IQLUJOU &) 'ou UI p - saswlaas ~JIJ a47 IIW 'leno~dde ~laI.13 JOJ 3wa~

oa pwlwqns waM uol~uuos a6wanes aq7 icg sllgap 1~sluq3w pua 6ulpllnq do

weld UI uay6 sl ueMaqg maaw aqj JO ueld WIS) (t-z e~qe~) (.xnrdde) , w 000'9~

SI Bulpllnq ay7 p ewe JOOU leqol 'sapoqs 8+(49) ~oold punoJg pue quauraseq

pals JO LW 5'6 pue q31-rq 000'0~'~ 'xo~dde awl1 surwt Ma4 pue Iwaa 'P~OZI

IauJon 'I '9 ae af~s 6uldurna auawurahog aya ~e padurnp uaaq seq q~ly~ aweM

Page 19: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report 'EM oTMetm Bhawan, Sarakhamba lane, Eonnaught &ce

bbie 2.1: Projab Overview (Civil WOI

Ground+ 8 Storey including Bore Wells,

Page 20: Environmental Impact Assessment (EIA) of Metro Bhawan

P'Z

Page 21: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of Metro Bhawan, Barekhamba lane, Connaught Ham

2.3.4 Civll Works

The salient features of the clvll work undertaken at the Metro Bhawan are glven

below:

Two level basement for DG Room, LT Panel, HT Panel Room, AC Plant

Room, water tank and parking.

A blg atrium of steel dome with double glazed coverlng.

An Auditorium of 303 Nos. slttlng capacity at Ground Floor level.

Canteen area of approximately 305 sq.m area on ground floor.

Operational Control Centre Equipment rooms on ground & flrst floor.

Theatre on 2", 4th and 6th floors.

Fapde is wlth granlte cladding, structural glazing and steel lattice.

Vlrendeel glrder at 1" floor (partly), 3d, 5", 6" and 8" floor.

Structure supported on shear walls.

2.4 Pnrkln~ Requirements The parking space has been provlded for all the vehicles enterlng into the Metro

Bhawan. In addltion the bullding has four entry polnt and exlt points. Bitumlnous

roads have been laid inslde the project slte wlth 6-7m wide drlveway. The parking

requirement of the building has been estlmated by assumlng 1.67 cars per 100 mZ of FAR whlch can be calculated as 1.67xi63.05 = 272 cars (Table 2.2).

Tabla 2.2: Provision of Car Parklnp at Metro Bhawan

2.5 Water Supply and Sewermge Syatems The water requirement durlng its operational phase at the Metro Bhawan has been

estimated to be approximately 80 m3/day, The criterion for estlmatlon of the water

requirement has been given below in Table 2.3. It Is proposed to get the whole of

the water supply for drlnklng purpose from the NDMC through the water pipe lines.

Page 22: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM Or Metro #tawan, Beraktmmba Lent, CmaugM 'ha

Necessary permission regarding ths quantlty of water to be used for drlnklng

purpose has already been obtalned from NDMC. It is proposed that the municipal

water supply wlll be stored in the over - head water tank and this water wlll be

suppiled In the building from the overhead tank through gravlty.

Table 2.3: Caleulatlon for Dally Water Requlremant at Metro Bhawan

Description Occupanc

Works ace Visitors T-L Add 10% fi contlnqencle! Grand total ~aT(m~/day l

* UtOm per ceplta par day ~ ~

Assuming that the 80% of the water requirement at the Metro Bhawan wlll be

converted Into sewage, the quantlty of sewage generated in the Metro Bhawan,

when It is completely operational has been estimated and given in Table 2.4. The

drainage system of the building is running along the perimeter of the basement.

There are 3 nos. of recharglng wells (RW) located at periphery of the building,

which will be used to recharglng the ground water, collected from roof -top as a

part of raln - water harvesting system of the building as per the Public Notlce

Issued by Ministry of Urban Development & Poverty Alleviation on 20.06.2001

(Annexure I), As per the deslgn speclflcatlon of the project, the maximum size of

the proposed sewerage RCC pipe is 250 mm dia. wlth a veloclty of 0.87 m/s. The

total run-off generated at the Metro Bhawan was disposed through the storm water

dralnage line constructed along the periphery of Metra Bhawan before belng

discharged flnally into the existing storm water drainage line of NDMC.

2.6 Electrical & Maintenance Works at Metro Bhawan The deslred electrlclty needed for the building will be provlded by DMRC from its

own dedicated power supply system as being used in the Phase - I corridor of

65 km Delhi Metro system. No outside electric connection will be taken. The other

salient features of the electrical system for the proposed Metro Bhawan Is described

In the followlng sectlon

Page 23: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report E l l Iif &ti0 Bhawan, Bankhambe LaM, Connaught %&

Table 2.4: Details of the Proposed Sewerage System of the Metro Bhawan at Pmjaet Site

I System Calculation

(I) . rota! domestic sewage produ1.-- 64 rn3/ day (11) Average Flow 0.75 lltres/sec (111) Peak Flow 2.2 lltres/sec (iv) Averase Slope 1 In 250 (v) Maxlmum dla. of sewer line 250 rnm (vi) Approx. I.L. of Last Manhole Approx. - 1490 (w.r.t. 0.0)

Eaulvalent to 98.5 (w.r.t. outslde -1 I

2. Type of dlatrlbutlon All bv ~ravl ty upto flnal disposal 3. Plnal disposal of sewage Ta the Municlpal external ~ w e r

adjacent the site (Munlclpal wwer llne is appmx. - 3500 mm from the adlacent road level)

4. Dralnag~ system (I) (ii) (Ill)

(iv) (v)

(vl) (vll)

lines, adjacent the site, as per slte condltlons, shown on the site plan. (Munlclpal drainage llne Is approx. - 2000 mrn from the adjacent road level adjacent one boundaw of the

(vill)

(Ix) (x) (xi)

I OBI area site capprox. J Annual Averaae Rainfall wnsldered Average Runoff coefflclent for entire

Constant coefflclent No. of lnflltratlon wells provided for rainwater harvestlnq Size of wells Rainwater flow for deslgn of dralnsf

iu,twu rn- 700 rnm 0.75

0.8 3 Nos. 4 m diameter and 4.5 m effectlve depth 56.57 m3 1 cusecs /acre or 28.3 litres /acre

pipes Max. flow to be designed for (10,870/4047)28.3 Max. diameter of draln pipes provided Maxlrnum depth of Dralnaoe Llne Final dlsposal of sewage

76 litreslsec

300 mm -900 mm w.r.t. Internal slte levels To the municipal external dralnage

Page 24: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report W;4 07Eilcti-o Bhawan. BaraMamba Lane, Connaught #a&

2.6.1 Proposed Electrical, LV 8 Fire fight in^ Works 2.6.1.1 Normal Power Supply

(I) Estimated Load - 4350 kVA

(11) Maxlmum Load - 3500 kVA

(ill) One feeder of 33 kV from New Delhi RSS/ AMS

(iv) One feeder of 33 kV from I P RSS/ AMS

(v) One feeder of 33 kV from Barakhamba Road Statlon RSSI AMS

(vl) Cast Resln Dry Type Transformers - 2 worklng + 1 standby (2.5 MVA each)

2.6.1.2 Emergency Power Supply through Online UPS

(I) Online UPS - 4 x 160 kVA

(li) Emergency Power Supply for

a Lighting (OCC 30%, other areas 20%)

(b) Fire Detection System

(c) Buildlng Management System

(d) Emergency PA System

(e) Access Control System

(9 Work Statlon & LAN Servers in Office Areas

2.6.1.3 Essmntlal Power Supply through DO Sds (I) Energy Efnclent DG Sets - 4 nos. (2x1500 kVA, 2x1000 kVA)

(11) PLC based auto synchronization, Auto Mains Fallure & Auto Load Control

(lil) Provision of cooling towers & Air Washerles for supply of cooled fresh air to

DG sets

The dlesel oil shall be stored in an underqround bulk oil tank of capaclty having

faclllties for 011 tanker delivering oil and pumping of oil for transferring it to the DG

room. Fuel transfer pumps wlth flame proof motors shall pump the dlesel oil Into

buffer tank provided at the wlling level of DG room. The buffer tank shall be

provided wlth low and high level electmnlc sensors to actuate the automatic

operation of the fuel transfer pump. The oil from buffer tank shall be transferred to

the day fuel tanks of indlvldual DG sets by gravity flow.

Page 25: Environmental Impact Assessment (EIA) of Metro Bhawan

'Urns UOIWWJd

Bu1uaay61-1 pasaq UOISSIU~ muearqs pallcuauo3 pa3uenpv s,my3

~mwd nva 6u1sn qselleg 6u1urula 'WOsuaS huodnsso 6u1sn uaqsAS auawa6euew 6u1aq611

6uiay61i aua1~~3 Ahau3

uraasAs 6u1wea a3e~oqela

uo1wo3 ~wej JaMod s~aowoanv

SAelw 1mlJewnN pweq ~ossa3o~d - OJ~IW U~IM Jea6~1371Ms we JO ams

sleued auwodur~ JOJ seyal~s JWSURJ~ - mnij do wn SWIM D sa1qe3 SIW P asn

wna sng Y~IMPUPS 9 SUIBW BUISI'~~ '~APJL e1qe3 19 p asn anlsuyxa

IP~(JOM I-lrwala

.~JOM aura4 19 ay3 03 pamans me uedo

%o+ 6u1neq a6neB gz pawwad y#~ pep aq 11e4s gels uolaelnsul Paul1 ayl ways 19 a6neB pa7~31~qej slauuays H WWSL x wwotr p Bulsl~durcn WOM aww PIJB

e aplsul aq lloys gels uonelnsul loom iluaulur elll '(u I;? x &J W~L'O x U.JZL'T

do WJOJ aya UI eq lleys uoiaelnsul IOOM IEJ~UIW au .worn 9a ur0.1~ UJ T 3a WBP SL

.xeu p [anal punos vgp sz unw(u(u do $sol uo(vasu( pue aAelyse 02 Qsuap ,w/By

trg p IOOM luaulw vsp SL W~WIUIW 40 sumw Aq pama Allmlasn0se aq lleus wocxl

ga JO 6ullla3 pue S((BM ayL *sawlq 3y6lu ae alqemja~d 'lenal aslou aualqwe pnpe

03 pmnp eslou J~J pey3a1.p aq llays aueuaaaa wsnme aya JO a3uewopad eqa

'~eq614 sl auelqura aya 'Jay61q sl ~a~aylu~ spropugs aslou aualqwe aya 6u1wau

-10 sso~ vap sz wnurlulw aneluse llays auaurqwa 31~snme ey~. 'u T JO wugs~p e a@ QP SL eq lleys ws 3a ayq J~J IaAa\al a~nssa~d punos alqlsslw~ad unurlxeur au1 '83d3

Aq peauawaldwl sw zooz Aew ,,,LT mlap uo~aesulw~ JualuuJeno3 1araua3 aya ad

SQ zooz selnM auawpuauv puosas (uoluaacud) IeauawuoJlnu3 do quaua~lnbw ya1~

Aldwoo lleys asneyxa UI slumnllod do slenal uo(sslua osle se slas wcuj eslou ayl

Page 26: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report E N oPMafro Bhawan, BamIdMrnbs lam, tonnaught Race

LV Works (I) Intelllgent addressablm Fire Detection & Alarm Swtsm

(a) State of the Art Flre Alarm Control Panels

(b) Use of Mlneral Insulated Copper Cable (MICC) type Fire Survival

Cable

(c) Intelllgent Multl-criteria Photo Electric Detectors

(d) Use of Extra Sensitive Laser Detectors In OCC

(11) Emaylency Public Address system

(a) Use of 2,4 & 6 watts speakers

(b) Use of Fire Survival Cable (Ill) Aceess Control System

(a) Independent Access Control System for OCC & Main Bulldlnp

(b) 810 - Metrlc Palm Print Verification Unlts for OCC Theaters (c) Automatic Boom - Barriers

(Iv) Micro - Processor based Bulldlng Management System

(BMS) (a) BMS Using BACNET PrOtOCol

(b) Control & Monltorlng of

33 kv & 415 kv system

HVAC System

DG Set Fuel System

Hydmullcs (Water Supply, Distrlbutlon, Sump & Sewerage

Pumps)

(c) Monitoring of

Fire & Sprinkler Pumps, Hydrant Pressure

Lift Monitoring & Status

UPS

DG Sets

(d) Integration with

Fire Detection & Alarm System

~ccess Control System

Chiller Plant Management System

Page 27: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Rcport EtA or Metm Bhdwan, Bamkhamba Lane, Connaught Plan

Inergen based Gas Flooding System • C02 based Gas Floodlng system

(v) Fire Fighting System

Inergen based gas flooding system in OCC theaters,

server rooms & equipment rooms • COz based gas flooding system in Important HT/ LT panels

Internal & external flre hydrant system

Sprinkler System

Pre-action Sprinkler valves for S&T equipment rooms in

OCC

Separate jockey pump for sprlnkler & hydrant systems

2.6.1.6 HVAC Works

(1) Total capacity of alr-conditioning plant - 1050 TR (3x350 TR Chillers)

f -! (11) 4 Nos, of Chilled water pumps

' I (ill) 6 Nos, of variable speed secondary pumping system

, < (iv) 4 NOS. of Condenser water pumps

(v) 3 Nos. of 375 TR cooling towers

(vi) 2x300 kW eiectrlc Hot water Boiler for heating

(vil) 43 nos, of Air Handling Units of Double Skln Type

(vli) 15 Nos. of Variable Frequency Drive for Air Handling Unik (vlli) 8 nos. of Precision Type Alr Handllng Units for Server & critical

Equipment Rooms

(lx) 2 Nos. of Heat recovery Units for 18 Nos. of Air Handling Unlts (Thls

would m u l t in saving of 50 TR Plant Capacity)

(x) Double Skin Type Fan Coll Units

(XI) Mechanleal Ventilation System

(xli) Smoke Extraction System for OCC Theaters & Equipment Rooms by Using Flre Rated Smoke Extraction fans & Fire Rated Ducb

(xili) 275 GSM Gt Duetlng System

(xiv) Use of Class '0' type closed cell Elastomeric fnsulatlon

(xv) Use of Motorised Valves & Motorlsed Fire Dampers

Page 28: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EL4 oFMatm Bhawan, Bemamba Lane, Connaught Race

Elevator Works 4 Nw. of 884 KG Panoramlc Elevators with Machlne Room on the Top.

2 Nos. of 10 Passenger (680 Kg) Elevators with Machlne Room on the

top.

1 No. of 1500 Kg Freight cum Passenger Elevator.

Cable Laying Work One no, of 33 KV, 3 core 300 sq mm cable (Normal Feeder) from New

Delhl RSSI AM5 to Metro Bhawan ASS via Barakhamba Road Statlon is

belng lald by CEE/ planning. However, 33 KV Panel is belng provided

by IT & PD wlng

One no. of 33 KV, 3 a r e 300 sq mm cable (Emergency Feeder) Is to

be lald from Barakhamba Road station ASS to Metro Bhawan ASS is to

be laid by CEEI planning

One no, of 33 KV, 3 core 300 sq mm. cable (Normal Feeder) Is to be

lald from I P RSSIAMS vla Barakhamba Road statlon to Metro Bhawan

ASS Is to laid by CEE/ TR-1. One 33 KV Panel is also to be provided by

CEE/TR-1 at tP RSS/AMS

Page 29: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM or ~ e t m Bhawan, Baraldrarnba bnC, t i o n n i i i W .

Chapter 3 Environmental Setting of the Project

3.1 Qanerml Environment 3.1.1 Cllmakr

The climate of the Delhi region Is sernl-arid type, with three well-defined seasons.

The cold season beglns at the end of November, and extends to early July and

contlnues up to September. The hot summer extends from the end of March to the

end of June. Further, the cllmate of NCT Delhl is influenced by its Inland posltlon

and prevalence of alr of the continental type durlng the major part of the year.

Extreme dryness with the Intensely hot summer and cold winter am the

characteristla of the cllmate. Thus, year can be divided into four seasons as given

below:

Table 3.1: !%!moons of NCT Delhl

The two post monsoon months October and November constitute a transltlon perlod

from the monsoon ta winter condition.

3.1.2 Temperature

The temperature is usually between 21.1°C to 40.5OC during summer months;

many times reaching above 45OC .Winters are usually cold and nlght temperatures

often fall to 6.5OC durlng the perlod between December and February. The

mlnlmum temperature many a times fall below 4OC durlng December-January

months, The average annual temperature recorded in Delhl Is 31.5O C based on the

records over the perlod of 70 years maintained by the Meteorological Department - IMD (Annexure If). Alr humldlty varies throughout durlng the year but seldom

drops below 20%.

Cold/ Winter End of November

3.1.3 Ralnfall

The normal ralnfall In NCT Delhl is 611.8mm. The rainfall in NCT Delhl Increases

from the southwest to the northwest. About 87% of the annual ralnfall Is recelved

Summer

Ralny season

Mlddle.1 End of March

Early July

End of June

September .'

Page 30: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of Mstm Bhawsn, Bsmkhamba LBm, Connaught Ham

during months of June to September, whereas, about 81% of the annual rainfall is

received during the monsoon months of July, August and September. The rest of annual rainfall is received as winter rains and as thunderstorm rain in the pre- and

post monsoon months. On an average, raln of 2.5 mm or more falls on 27 days in a year. Out of these, 21.4 days are during monsoon months. For design

considerations, rainfall Intensity of 20 to 30 mm, which generally occurs In one-

hour duration, is taken into account.

Table 3.2: Rainfall Statlstlu of Delhl(2001-03) (Moan ValmS)

Ralnfall In Delhi is hlghly variable with deviations from 25.5% to +90% Prom normal

rainfall which in turn affects the natural recharge to ground water fmm year to

year.

3ammratura a Rainfall at mihl

25

February I 24 ( 10 1 22 T 1 March I ;; 1 ;; 1

Aprll

May 41 27 08

- -

July I 35 1 27 1 211

August I 34 1 26 1 173 . 1 September I 34 1 25 1 150 I October

November December 23 08 05

Page 31: Environmental Impact Assessment (EIA) of Metro Bhawan

E'E

pue 'eaJw ule~a eueMeg (IN

'sulseq af3euIoJp uahas o3u1 paplyp Alpetuq sl 'lulea 40 eare 1~1ude~Boet3 aul

ulseq pasopua ~nd~euey~ 40 qlsodap wnlhnllw (A!)

uleld poolj eunweA Buole IIV - un!An(w ~a6uno~ (1111

a6~1'tl 141aa P apls 4~9 uo urnlhnllw JePlO (11)

a6~1k1 (slalwnb) 141aa (11 :SMOIIOS se are asayl

-smuow uoosuou aqa UI uouum a~ou

aJe spul~ Al~wsoayanos pue Apaaseq *uoouJaye 943 UI Al~ayuou wou aq oa puaa

uoosuou aqa Bul~np jdmxq .syauow uoosuou pue Jeuruns aya 6UlJnp uay16uarp

haul '('E'E - 'E~E-BY) syauou J~~UIM pua uoosuow >sod eqa Bul~np ~4611 Alle~aua6 ~JQ spul~ '~eaA ay3 p asaA ayj JO) spnop do eaJ$ All~Jaua6 pue IsnBnv - Alnr Ou~~np

suolnala allqM 'sas /w T** 01 6'0 W[UJ hen pue aaelapou oa 3~611 are spul~ ayl

@PulM Pmt'E

Page 32: Environmental Impact Assessment (EIA) of Metro Bhawan

P'E

my OEOZ ae suauow reqwo3e(l pue JD~W~AON bul~np u~enad pul~ parum0 :T% 'OM

Page 33: Environmental Impact Assessment (EIA) of Metro Bhawan

sqauoru raaulm 6u1rnp Aloa!padse~ (aqnlu) SJ~ OEOZ pue (Aop) sry OETT qe meeA st as~lrod pehleoqo ureaed PUIM olbererrv : zU€

Page 34: Environmental Impact Assessment (EIA) of Metro Bhawan

ame of s

Final Raport Bfmtm ~hawm* ~ r a k h m b a &net ~onneught Ham

Table 3.25: Other Information

Numbers of districts

Major Gaologlcal Formation

Delhi

Soft rock - Younger/ Older

Alluvium Hard rock - Quartzites I 'laor Dnrlnage System ~amuna

,opula'tlon (as on 2001) 138.57 lakhs

NO. of Tehdls 27

eplenlsheble groundwater resources 128156.32 Ham or 0.28 BCM -

H

Total groundwater draft 147945 Ham or 0.47 BCM - tag8 of groundwater devslopment 170.28%

Merage annual mlnfall Safdarjung - 712 mm

Palam - 794 mm

ange of Mean Dally Tamperaturn 18 - 32OC

Iistrlcts showing Intehslve gmundwaWr All 7 districts except North &

Central Districts

3.3 Geological Settlnp of Delhl

Delhi, the capital of India is bounded by the Indo-Gangetic alluvial plains in the

North and East, by Thar Desert in the West and by Aravalli Hill ranges in the South.

The terrain of Delhi is flat in general except for NNE-SSW trendlng ridge, which is

considered an extension of the Aravalll hills of Rajasthan. The ridge may be said to

enter Delhi from the SW. The eastern part of the ridge extends up to Okhla in the

South and disappears below Yamuna alluvium in the NE on the right bank of the

river. River Yamuna enters Delhl from the North and flows Southward with an

Eastern bends near Okhla. The exposed rocks of Delhl are mainly quartzites with

moderate folding. What is of interest in seismic hazard estimation is the depth of

sediments over the rock layers. However, varlous recent earthquake events felt in

and around Delhi recorded by various observations located in varlous parts Delhi

are listed below. Since 1994, there has been a marked cessation of seismic activity.

Page 35: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report ad gf Metro Bhawan, mrakhamba Lane, Canneupht uacn

It is shown that the stresses, which earller were being released periodlcally, are

now stored h rocks llke a spring. I f the trend continues then one day these stresses

will be released resulting in an earthquake.

3.4 Ground Water Situation in the Study Area

Groundwater is one of the major sources for water supply in many parts of the

country. In Delhi too, ground water contributes to substantial quantity of supply.

The groundwater is largely being utlilsed as a drinklng water resource, especially in

new development areas mainly because of the Insufficiency of the Yamuna water

share for Delhl. Faster withdrawal rates have lead to fall in water table and flnally

depletion of ground water. The groundwater recharge areas need to be Identified so

that maximum recharge can be achieved. The recharge areas needs to conserved

and preserved for the sustainable management of groundwater and to maintaln the

potentlal of the groundwater In Delhi. According to the Central Ground Water Board

(Annaxure X I ) the recharge areas identlfled is the northern most part of the city.

Areas where the ponds already exist in the villages, the Najafgarh jheel and its

surroundings and the region between the Northern Ridge can also be used as water

recharge area. A cornparlson of water levels from 1962 to 1977, 1977 to 1983 and

1983 to 1995 brlngs out a clear picture of water level declines in major parts of the

territory. The water levels and fluctuations during these perlods are given in

drawing. During 1977, the water table was by and large within 6m below ground

level (bgi) in major parts of the territory deepest being 23m bgl at near Qutub

Minar In Mehrauli Block. In 1983, the depth to water level declined to 10 m bgl in

major parts with the deepest level being 26m bgi at Mehrauli In Mehrauii Block. I n

1995 the extent of area with water levels in the range of 10 to 20m bgl has

substantially increased and the deepest water level is about 35 m bgl at Gadaipur in

Chattarpur basin of Mehrauil block.

Page 36: Environmental Impact Assessment (EIA) of Metro Bhawan

t

w mwm mum- -=' I

Page 37: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EL4 o f Metm Bhawan, 88rakhambs Lane, Connaupht Place

I

Fig. 3.4 : Ground Water Situation In Delhi In Year 2002

The reasons for decline in groundwater levels are:

(1) Rapid pace of urbanization, leading to redualon in recharge of aquifers.

(11) Increaslng demand In agriculture and Industrial sectors as well as domestlc

needs for the ever growing population.

(ill) A change In cropplng patterns in order to raise cash crops in certain areas.

(Iv) Stress laid on ground water extraction durlng drought periods when all other

sources shrink.

(v) Unplanned wlthdrawai from subsoil aqua

Page 38: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EEA of Mehr Bhawan, Barakhamba Lane, Connaupht Place

Fig. 3.5: OrO~nd Wmm Quality In Dslhl (2002) 3.5 Geography of the Projact Slta The proposed study area comas under the jurlsdlction of New Delhl Munlclpal

Corporation (NDMC). The area Is plaln and devoid of rocky outcrops and Is not

covered by any notlfled forests. The project site is well connected by road and rall.

The nearest rallway station Is situated at New Delhl Railway Statlon wlthln a radlus

of 3 km. The nearest metro statlon is situated at Bardkhamba road itself (Une 3).

The project slte Is located In the New Delhl Dlstrlct, which is located centrally in

the state wlth varled surface altitude due to Delhl Rldge. Nearly 10 sq. km area falls

wlthln rldge area whlch possesses 225 to 255 m helght above mean sea level

(amsl). The surface is sloplng gradually towards east upto Yamuna rlver course

where the altitude Is 210 amsl (above mean sea level). The total area of New Delhl

Distrlct Is 35 sq. km. The top sol1 zone is predominantly consisted by sllty-clay

material followed by thin partlngs of clay-sllt, sandy-silt and clay layers

alternatively. Sandy-sllt strata behave as favourable aqulfer zone In order to get a

substantlal dlscharge. In the western part of this district covering an area of

Page 39: Environmental Impact Assessment (EIA) of Metro Bhawan

Rashtrapati Bhawan, Chankyapuri, Shantlpath, South & North Avenue and

Connaught Place, tubewells are tapplng both prevalllng formation i.e, alluvium as

well as hard rock. Whereas, in the eastern part only aquifers of alluvium are tapped

whlch are glving yleld of ZOO - 500 i/mln. The extreme eastern part of thls dlstrict

is bounded by Rlver Yamuna where a domain of Yamuna flood plaln exlsts in a

llnear fashion along river Yamuna. The potentiality of groundwater in thls formation

is relatlveiy high ranging from 500 - 1600 l/min. Groundwater in thls area occurs

both under water table as well as under sernl - conflned condltlons in the alluvium.

The depth to water level in the dlstrlct ranges from 5 - 25 m below ground level,

the wlde varlatlon occurs due to wlde range of topographic relief. Right from the

Yamuna Flood Plain where DWTL ranges from 5 - 8 m to Delhl ridge where DTWL

ranges from 10 - 25 m are the wlde-ranging level occurs in the district. The tube

wells usually tap Kankar zone admixed wlth clayey sllt and sandy-sllt aquifer zone.

These aquifer zones are generally encountered altematlvely MOW the depth of 20

mbgl (meters below ground level) and onward up to the basement rock.

b e 3 . Area UnWr Various bp th to Water Lave1 In NCT Delhl

20-40

40-45 >45

247

68 7.15

~waika, Daulatpur etc. Mahavlr Banasthali, Nehrupark, Jamali Kamall, Sanjayban, Satbarl

S-W, South, New Delhi

etc. Bhattl Gadalpur, Asola Pushp Vihar, Ladosaral, Tughlakabad, Chattarpur, Bhatti, Jaunapur, Ayanagar etc.

South South Distrlct

Page 40: Environmental Impact Assessment (EIA) of Metro Bhawan

"TTAR PRADESH

HARYANA .

1L

INDEX v

WATER TABLE FLUCTUATION IN M RIRF

C 0 . 2 - I 2 . 4 -

4.8 0 7

Fig. 3.6: Water Table Depth Fluctuatlonr In Delhl

In alluvial formations, the quality of groundwater deterlorates with depth, which Is

variable in different areas. The groundwater Is fresh at all depths in the areas

around the ridge falling in Central, New Delhi, South and Eastern part of South-

west (ridge) districts and also Chattarpur basins. The concept of hydro-chemlcal

facles can be used to denote the diagnostic chemical characteristics of water in

hydrological systems. The chemical quality of ground water in NCT Delhl varies with

depth and space.

Page 41: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EU O T M E L ~ ~hswm, aerPkhBm8d m a , Cbnneuuht Uscs

3.6 SQiemlcity Delhi reglon falls In zone I V of seismlc zoning map of lndla, which Is located on the

margin of Himalayan fore deep. The zone has falrly high Selsmlclty wlth general

occurrence of earthquakes of 5-6, a few of magnltude 6-7 and occaslonai Incidence

of 7.5-8.0 rnagnltude shocks. The flrst recorded major earthquake In this region

occurred on 15th July 1720 of Intensity 9.0. Subsequently other hlstorlal events

occurred In 1803, 1819, 1905, 1934, 1937, 1945, 1949, 1958, 1960, 1966, 1975,

1980, 1994 durlng which intensities between 7.0 and 9.0 are belleved to have been

experienced as indicated by damage pattern. Durlng recent times the area has

been shocked by a number of earthquakes, out of these earthquakes of 27th

August 1960 wlth magnitude 6.0 and having eplcentral tract between Delhi and

Gurgaon was most slgnlflcant. Reeent Himalayan earthquake namely Uttahshl and

Charnoii were experienced In Delhl, and uitlmate probablllty of major earthquakes

In the region should make the authorltles awake to the problem. The earthquake

history of Delhi reglon lndlcates falrly high Selsmlclty for the city of Delhi. The most

actlve area of the region is conslded to be the trl-junction of the Delhl-Hardwar

rldge, Lahore-Delhl ridge and axis of Delhl folding. Most d shocks are Interpreted to

be shallow focus and have concentrated around Sonepat, Rohtak and Gurgaon

region In and around Delhl may be considered as selsmlcally very actlve and the

tectonic elements of the area are consldered capable of generating an earthquake

of magnltude 7.0 on Richter Scale. Some areas of Delhl, due to thelr unique

subsurface settlngs, are relatively more prone to damage In ease of such

eventualities. In such cases, apart from the denslty of population and type and

quallty of construction of bulldlngs, thickness of sedimentary deposits play very

critical role.

Page 42: Environmental Impact Assessment (EIA) of Metro Bhawan

PI'E

Page 43: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report ELA or mtro mawan, Bamkhamba ~anc, tannaught Ham

Chapter 4 Baseline Data

4.1 Qaneral Experlence over the years from all over the world Including Indla, has shown that

the Environmental Impact Assessment (EIA) studles are always conducted under

severe llmltatlons of tlme, manpower, flnanclal resources and data. These

requirements for EIA could be greatly reduced by focusing the EIA study on a

llmlted number of relevant issues rather than an elaborate llsting of values of all

envlronmental parameters. This could be achleved through lnwrporatlon of a

method for identlflcatlon of slgnlflcant issues as a component of EIA. Scoplng is a

process of identifying slgnlflcant issues to be considered for an EIA. Essentially, it Is

a procedure design to establish the Terms of Reference (TOR). For Identlwlng the

Important parameters to be Included In the EIA of the proposed Metm Bhawan

project, an Informal meetlng of the Sclentlsts of the Central Road Research Instltute

(CRRI) wlth the Delhl Metro Rail Corporatlon (DMRC) was done. Based upon the

dlscusslon wlth DMRC offlclals, TOR lncludlng Objectives and Scope of the EIA study

was agreed upon (as described In Chapter 1).

4.2 Impact checkllst There are several methodologies for ldentifiwtlon of Impacts vlz., Ad-hoc

procedure, and Overlay technique, Checklist, Leopold Matrix and Networks. In the

present study, the chackllst methods has been preferred over the other methods

because of their slmpliclty in understandlng as they do not provide or requlm

guldellnes regarding the methodology for data eolledlon and lnterpretatlon. Thus,

Checklists present a speclflc list of envlronrnental parameters to be lnvestlgated for

possible Impam and do not require establishing direct cause - effect llnks to various project actlvltles. The checklists can be augmented by instructions on how

to present and make use of data and by the lncluslon of explicit crlterla for Impacts

of certaln magnltude and Importance. The checkllst, In general, Is used to ldentlfy

and subsequently to evaluate the magnitude and Importance of the potentlal

Impacts. It is important to recognize that at thls stage of Impact assessment, the

concern Is potentlal Impact, as opposed to the residual lmpact whlch could be

expected if mltlgation measures were to be adopted and were effective in

Page 44: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of Mktm Bhawm, Bsrakhem&a lane, Connaught Ham

mlnimlslng the Impact. In effect, this can be thought of as presentatlon of worst

case seenarlo as far as envlronmental matters are concerned. In the checklist, the

Impacts are assoclated with three phases of the project (Design and Pre-

construction., Construction and Operation phase) are subdlvlded In relation to the

principle actlvitles taking place In each phase. Thls form of presentatlon is slmpler

than the alternative of subdivlslon In relation to the envlronmental component or

value whlch is effected, slnce a slngle actlvlty may affect the several components

and values. Thls approach focuses attention on the effects of an adlon and is less

likely to result In impacts belng overlooked.

A check llst applleable for various construalon projects, whlch may not be dlrectlv

applicable for building projects have been taken as a flrst approxlmatlon (Table

4.1). Based on the check list and through literature search, site vlslts and

dlscusslon with the DMRC officials regarding their past experience of EIA projects of

slmllar nature, a detailed methodology for varlous fleld studles for collecClon of the

base llne data were planned and is descrlbed in the following section. In the present

case, the baseline data at the project slte, relevant to the proposed metro Bhawan

Project were identlfled and prlmary surveys carrled out for the detalled basellne

data collection through fleld studies;

Alr Envlronment

r Nolse Envlronrnent

Water Envlronment

Soll Envlronment

Trafflc component

Green Cover (Tree) Survey

Alang with the prlmary data, secondary data (i.e., selsmlclty, groundwater, soil

characterlsties, geological setrlng, cllmate etc.) has also been collected from

different sources (Annexurn - 11).

4.3 Mathdolopy for Base llna data collection The methodology requlred for establishing basellne envlronmental status and to generate basellne data for dlfbrent envlronmental componentsfparameters have

been descrlbed in Table 4.2.

Page 45: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report of Metm -wan, Bbrakhsmba &me, Connilught Pie

Table4.1: Impactm/paramatmrs likely to b associated with

Construction projects

Site Clearance

Construction Camp Establishment and

Establishment and

Page 46: Environmental Impact Assessment (EIA) of Metro Bhawan

P'P

WJOM yue3 p uoipn~lsuo3

asn U~WJ~H

asn u~urn~ asn ueU.lnH/JmeM

asn ue~fl~/~aqe~/puel

PU~

adll P hllenb /asn uelunH

asn uelunH

ajll p hllenb uaRnllod

JIWDJII fl Alllenb

wnpnJlseJju1 /mlhlas Y~IM BDU~J~~~BIUI

uraasAs a6aule~p (emleu 431~ asuaJa#alul:

sladlnbe 431~ a3ue~aua~u1 nlsodap

8411 40 hllenb adll 40

Al11enb /asn uewn~

luau~pas/uo~saa pasear3u1 ~1111qe~s PUPI pasea~su~

splezeq pe~/uolasaBum sld$e~~

spew oq abeuap /sa~npnqs pea 40 6u1peol~ano

SplBZDY &EJ4ES peotl /spea do 6u111os pasea~3ul

uolanllod Ale PUP qsnp p uolle~aua9

uolaeJq1A

a411 do hllenb uol3nllOd

-IIV/BJII do hrlenb puel

~aae~lpual

sle~~a~ew 40 a6e1ne~

pug aslou p uo1qe~aua9 sprezeq

4a~es peo'll/uo1asaBuo3 DW~JI screw 02 aBewPp

eune~ pue e~oy asn u~luny/puq

a411 do hllenb I pue aslou p uolqe~aua9 I JBAO~

sal~aulq3ew pue slueid heaH

adesspuel UI uolaeJaqle IP~SIA

pnp 40 uoIqeraua9 ~1111qqsu1 adols 40 Juawa3ueuu3

uo~usodap auaw~pes/uolsaa do auaruasuequq

Janm uollerbanhqlqeq . .

an~wsuas p ssg puel ah~Dnpcud 40 sw

uolsoJa imIaeJsul

ad11 40 411enb uolanllod

-~lv/~~ll 40 hllenb

smv lesodsla IIO~S P uo~e~ado pue juawysllqelsg

admspuel UI uolqeJ8lle lonsl~

qsnp p uo1ae~eua9 UolaeJqln

euna~ pue e~oy uo1qqa8anllwlqeu

anla~suas p ssol pue auaWsllqaS3

hl~enb

Page 47: Environmental Impact Assessment (EIA) of Metro Bhawan

Final ~cpor t H A of Ma& Bhgwm, SamIdramba Lane, Con~wught Race

Page 48: Environmental Impact Assessment (EIA) of Metro Bhawan

+ m

z 1 N . . a 0

% C 5 O m $

I I I *x I

?Zyr 0.

r gw

a "

t a

yg

i R

. oIGgr W

-Rz,=! Oh. gl~ac 713a

CJ; u

n -. 3 ON* 5-iyls u i e2 00

z m 02

P . 8rg ?air W3e_ IW m a II R

3 2 9 i?

W

2

D

. F5E5! m-mj F~'"'cTcl uo-

111 E. ul 'Uogc <-<mi

b*~, =zp

sou r 16 ;; .

Page 49: Environmental Impact Assessment (EIA) of Metro Bhawan

~l~m_a.Q= Pa# aqL9- a

Iya~ag$ ga-oa .3

qg..=o#$ 3.E-IVI Sz leg, s 3~ #a [Y- 3- 3 u

I QI a .

Page 50: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 51: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report H A of Metro Bhewan, Bankitamba Lene, ~ o n ~ u g h t place

4.3.2 Air Quality Monitoring

The alr quality at Connaught Place (Rajlv Chowk) was monitored for 24 hours in the

month of October 2006 through Alr Pallutlon Moblle Van fitted wlth pollutant

speclflc amblent alr quallty analyzers. The hourly varlatlon of various pollutants vit.

SO2, CO, 03, NO, THC and PMIO has been glven In Table 4.3.

Tablm 4.3: Alr pollution mwmummente at Connaught Plmm (Rajlv Chowk)

These observed average values of varlous pollutants are to be compared with the

Natlonal Ambient Air Quallty Standards (NAAQMS) speclfled by Central Pollution

Control Board (CPCB) (Annaxum 1x1).

Page 52: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 53: Environmental Impact Assessment (EIA) of Metro Bhawan

ZI'P

Page 54: Environmental Impact Assessment (EIA) of Metro Bhawan

EI'P

iC '

L1

C.'

L

Page 55: Environmental Impact Assessment (EIA) of Metro Bhawan

4.3.2 Noise Pollution Monitoring:

The noise pollution monitoring was carrled out using Sound Level Metre for a period

of 24 hours near the oPRce complex of Delhi Flre Station, Connaught Place, New Delhi

durlng October 2006. The observed values durlng daytime (06:W - 22:OO hrs)

and night time (22:OO - 06:OO hrs) Is glven in Table 4.4. and Table 4.8 and their

respective flour- is provided in FlpA.7. and Flg.4.8.

Table 4.4: Obwrvmd Lpp VnIumm at Connaught Plncm during dnytime (O6:OO - 22:OO hn)

" 1 I

- t Y * -.-....I I Flg 4.7: Obnmrved LEQ Valuu at Connaught Plow durlnp dsytlmm ( W O O - 22:OO hn)

Page 56: Environmental Impact Assessment (EIA) of Metro Bhawan

SIP

-(AX wnxouuv) (9343) PJWB IOJWO~ uotqnllod leJaua3 Aq peut~ads

sp~epue~s oslo~ 3ualqww leuo1aef-l aqa y31~ pe~8durm uaaq aney (wu 00:90

- 00:zz) ay61u pua (wq OO:ZZ - 00:go) Aep Bul~np aslou p sanleh pahlasqo asayl

Page 57: Environmental Impact Assessment (EIA) of Metro Bhawan

a461~ pue Aeg Oulrna 6u!1o51uow eslo~ p heurutns :wrn8ld

VMP SUIR-UI~U hvnp WWI oo~w MW)ulw

.WIO

.WBo

OIW .wen

-wu

.m'u

-WVL

, m'w

Page 58: Environmental Impact Assessment (EIA) of Metro Bhawan

Rnal Report EIA d Mtrb Bhawan, &&immEa Lsnc, -hf m e

4.3.3 Groundwater Quality Monitoring

The groundwater table was encountered at depths varying from 9.40 m to

11.50 m below the existing ground level at the locations of bore holes BH-1

to BH-4 and BH-6 to BH-8, It may rise up during heavy rains/ rainy season

or go down during dry season. The result of the groundwater analysis

undertaken is given below (Table 4.6). The results shows that the

graoundwater quality meets the drinking water quality standards specified

under IS 10500-1983 (Annexure V and Annexure VI)

Table 4.6: Groundwater Quallty MonltOring

Page 59: Environmental Impact Assessment (EIA) of Metro Bhawan

. nna

t Rep

ort

m

dM

etm

~h

aw

an

,Ba

ak

twm

ba

~,t

OR

Ra

op

ht~

4.3

.4

So

il C

har

acte

riza

tio

n

Abo

ut 7

be

hole

s w

ere

dug

at v

ario

us e

leva

tions

(Fig. 4

.10.

) at

th

e pr

ojec

t si

te o

f M

etro

Bha

wan

to b

e an

alyz

ed

for v

arie

d pa

ram

eter

s as

det

aile

d in

Tab

le 4

7.

and

TaM

e 4.8

.

TaM

e 4.7

: C

hem

ical

Ana

lysi

s of

Soi

l Sam

ples

at P

mje

ct S

ie

Tab

le 4

8 : G

ririn

Size

Ana

lysi

s of

a ty

pica

l soi

l sam

ple at t

he P

roje

ct Site'

*(C

=O.N

and

0 =

11° a

t son

dep

th =

3 m

)

Page 60: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 61: Environmental Impact Assessment (EIA) of Metro Bhawan

Rnal Report PIA of Mstm Bhswan, Bamkhamlnr Lana. Conneught Wace

No significant land disturbance ilke eroslon, subsidence & instability Is anticipated

at this site. The Metro Bhawan is situated In Delhl region whlch comes under

Seismic Zone IV, hence all the precautionary measures has been taken in

accordance with Natlonal Building Code (2005) to safeguard the same against

earthquake.

4.3.9 Trafflc Study

As part of study, traffic surveys were carried out to assess the impact generated by

trafflc of Metro Bhawan on the surrounding road network. A classlfled Trafflc

Volume Survey was carried out on a normal working day for 16 hours duration, The

survey was carried out on all three approach reads vlz. Bengall Market road

connecting Metro Bhawan wlth Maharaja Ranjit Slngh Marg road, Mayur Bhawan

approach road connecting Metro Bhawan with Connaught circle and Shlvaji Bridge

Railway Station and topai Dass Tower approach road connecting Metro Bhawan

with Barakhamba road. Trafflc volume counts were also carrled out on the other

smaller links such as Barakhamba lane and approach road from Bengali market

approach road to FCI building on the other side of Metro Bhawan. Classlfled trafflc

turning movement survey was carried out at Y-intersection of Bengali market - Gopal Dass Tower and Mayur Bhawan approach roads in front of Metro Bhawan

along wlth padestrlan surveys as there is appreciable pedestrian movement

between Shivafi Bridge Railway Station and Gopal Das Tower / Barakhamba

approach road. Counts of each turning movement of each class of vehlde vlz. ears, two wheelers, auto rickshaw, cycles, cycle-rickhaw bus, mini bus, trucks, LCVs and

other vehicles along with pedestrian count were taken for every 15 minute intervals

during the period of survey on pre-designed proforma through trained enumerators.

The 15-minute traffic and pedestrian data for each turning movement and each

class of vehicle were fed into Computers In Excel spread sheets for analysis (Tablo

4.9). Hourly-classified trafflc turning movements at all the approach roads were

calculated and added to get daily trafnc along various direction on the surrounding

road network. Hourly variation of total trafflc and its composition at the Intersection

in front of Metro Bhawan is shown in Flg. 4.liand Fig. 4.12 Trafflc flow diagram

Page 62: Environmental Impact Assessment (EIA) of Metro Bhawan

OJPW Bu~punouns spw~ snolleh uo Aap BUI~JOM lauou e uo 3ld;le~l A11ep Bu13eslpu1

Page 63: Environmental Impact Assessment (EIA) of Metro Bhawan

ZZ'P

I I3d I

Iq..II-aU

ws ma !WW DL- - & -WffWP!A

Page 64: Environmental Impact Assessment (EIA) of Metro Bhawan

Tab

le 4

.9:

Ho

url

y vari

ati

on

of to

tal t

raff

ic a

t th

e in

ters

ecti

on

in

fro

nt o

f M

etr

o B

haw

an

Page 65: Environmental Impact Assessment (EIA) of Metro Bhawan

From the analysts of trafnc and characteristics of surrounding road network,

followlng concluslons can be made:

(I) Metro Bhawan is connected with main road network of Delhl through three

approach road vlz Babar road in the east, connectlng Maharaja Ranjlt Slngh

Marg and Bengali Market. Mayur Bhawan approach road in the north-west

connecting Connaught Circle and Gopal Dass Tower Road In the South

connectinp Barakhamba Road

(ii) All the approach roads are relatively narrow conslstlng of three lane undivided dual carriageway excepting smaller stretches of divlded carrlageways near

Gopal Dass Tower and Metro Bhawan.

(ill) All the approach roads am carrying appreciable traffic volume because of

surrounding built up area.

(iv) The intersection In front Is catering to daily (16 hrs) trafflc volume of about

15,500 vehlcles wlth two district morning (9.00 to 10.00 am) and evenlng

(5.00 pm - 6.00 pm) peak hours.

(v) Cars constitute major share of trafflc (48%) followed by two wheelers (26%)

and auto rickshaw (21%) of the total trafflc.

(vi) There lo high pedestrian trafflc movement to the tune of 15,000 pedestrians

per day (16 hrs) along Gopal Das Tower - Shivaji Brldge approach mads at the

lntersectlon In front of Metro Bhawan.

(vll) Babar/ Bengali Market approach road Is catering to dally trafflc volume of

about 13,000 vehlcle, while Mayur Bhawan approach road is caterlng to 11,500

and Gopal Das Tower approach road about 7,500 vehicles.

(vi1l)There wlll be nomlnal effect of trafflc generated by Metro Bhawan on the

surrounding road network.

(ix) There is enough reserve capacity on all the approach roads to Metro Bhawan

to cater to future growth of tfafflc and trafflc generated by Metro Bhawan.

(x) The Intersection in front of Metro Bhawan is catering to hlgh traffic volume and

hence needs to be re-deslgned and signallzed in order to cater to the future

trafFlc.

Page 66: Environmental Impact Assessment (EIA) of Metro Bhawan

(xi) The entry and exlt gates of Metro Bhawan should be located on dlfferent

approach roads 75m away from Y-intersaction in order to avold congestion at

the intersection.

4.3.6 f reo Survey

The approval of cuttlng of 58 trees of various sizes and species were obtained from

the designated Tree Offlcer (Offlce of Conservator of Forest, Delhi) under the Delhi

Trees Act (1994) however only 38 were flnally cut as others were not requlred to be

cut during site clearlng operatlons durlng the construction phase of Metro Bhawan.

Table 4.10: Census of Trees at Project Slte

Species - Oak, Jangal laiebi (Inga Delelous), Aauna, Guiar, Pokar (Rcus In*eforfe) Patranjiva, Chandani, Neem, ,Pipal, Mango, Jamun, Palm, Muibery (Shahtut), Ashoka, Mausaml,

(Amrood), Bakyan,

"Trees" means any woody plant whose branches; spring from and are supported

upon a trunk or body whose trunk or body is not less than 5cm in dlameter at a

height of 30 cm from the ground level and is not less than l m in helght from

the ground level.

Glrth size measured at 1.85 m above the ground level as specifled under the

"The Delhl Preservation of Trees Act (1994)"

"Tree Offlcer" means a forest officer appointed as such by the Government for

the purpose of The Delhi Preservation of Trees Act (1994)

Page 67: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of M c h o $hewan, BBcakhmba lane, Connaught FIBm

Chapter 5 Environmental Impacts 5.1 Intraductlon The identification and prediction of Impacts depends on the nature and magnitude

of the activity being undertaken and also on the type of pollution control measures

that are envisaged as part of the project proposal (Table 5.1). As Metro Bhawan is

spread over an area of 10870 ma appraximately, comprlslng of offlce complex with

basic amenities and environmental infrastructure. The potential impacts from the

proposed Project area are Identified and assessed based upon the nature and

magnitude of the various activities assoclated with the project (Table 5.2).

5.2 Potential ImpactD

The various potential environmental impacts envisaged from the various project

activities are enlisted below:

(1) Alr Environment Impact on ambient air quality

Impact on ambient noise

(ii) Water Envlronment Impacts on ground water quality

Impacts on surface water quality

(Ill) Land Envlronment

Impacts on land use

Impacts on soil fertility

Impacts on agrlcultum

(iv) Ecological Impacts Impact on trees / vegetation

Impacts on forests and wildlife

(w) Socio-Economic Xmpacta Impacts on other Infrastructure

Impacts on employment

Impacts on public health and safety

Impacts on cultural resources

Impacts on aesthetics

Page 68: Environmental Impact Assessment (EIA) of Metro Bhawan

!=tria

l Rep

ort

~IA

of-

Bha

ww

l, fi

mk

bn

ba

Lane

, C

onna

upht

Race

Tab

le 5

.1:

Pol

lutt

on S

ou

rces

an

d C

har

acte

rist

ics

S.

Ac

tiv

ib , ...=-

pol

luta

nt

Pol

luta

nt C

har

acte

rist

ics

Mo

m

1. C

on

stru

ctio

n P

has

e A

ir E

mis

sion

s-SI

,-,,

Dus

t fro

m c

onst

ruct

ion

and

exca

vat.-

.. . -..

.p o

rary

du

ring

PMxo

, C

O,

NO

x, S

O2

activ

ities

co

nstru

ctio

n ph

ase

. Partic

ulat

es,

NO

x an

d C

O fr

om o

pera

tion

(Bul

k of

the e

mis

sion

s of c

onst

ruct

ion

equi

pmen

ts

are

expe

cted

fr

om

(i)

Site

dea

ring

eart

h w

ork

activ

ities

) op

erat

ion/

leve

ling

Noi

se P

ollu

tion

Noi

se g

ener

ated

from

con

stru

ctio

n D

urin

g w

hole

eq

uipm

en&

and

mac

hine

ries

cons

trucb

ion

per

id

Ear

th/S

olid

Was

tes

Spo

ils g

ener

ated

dur

ing

Dur

ing

whde

(Spo

il ge

nera

ted

€xca

vatio

n/co

nstru

ctio

n aC

tivity

co

nstru

ctio

n pe

riod

durin

g co

nshu

ctio

n . .

actM

ty1

Sto

nn watw fr

om

Silt

, oi

l, gr

ease

etc

.(ch

cckn

g of

storm

Dur

ing

rain

y se

ason

pr

ojec

t ac

tivity

w

ater

dra

ins)

on

ly

2.

Op

erat

ion

Ph

ase

Air

his

sio

ns

and

Veh

ide

exha

ust e

mis

s~on

s, no

ise

rrom

me

Con

tinuo

us/k

riodi

c (i)

V

ehic

ular

mov

emen

t m

ise

runn

ing

vehi

des

Di

l po

wer

A

ir B

mis

sion

s an

d A

ir a

nd n

oise

pol

lutio

n fr

om th

e g

ene-

in

term

itte

nt/

pe

rio

dic

(ii

l ge

nera

tors

no

ise

pottu

tion

oper

atio

n

sew

age

Was

tew

ater

from

W/C

, ur

inal

s an

d dik

e

(iii)

O

fiW

? are

a ki

tche

ns

Bio

-deg

rada

ble

arid

non

Bio

-deg

rada

ble

Con

tinuo

us

Mun

icip

al s

olid

was

te

(w&

e per an

d co

mpu

ter s

tatio

nery

) A

ccid

enta

l (iv

) D

iese

l Sto

rage

O

il A

ccid

enta

l spi

llage

from

die

sel s

tora

ge a

rea

kage

/milla

ge

Mai

nten

ance

/Hc#

rse

wat

er

(v)

Kee

ping

flo

or w

ashi

ng a

nd g

arde

n w

aste

s C

ontin

uous

Air

pol

lutio

n fr

om r

unni

ng v

ehic

les

imid

e

Con

tinuo

us,

durin

g

1 V

ehic

le p

arki

ng a

rea

Air

emis

sion

s en

dose

d pa

rkin

q ar

ea a

t bas

emen

t w

hole

offi

ce h

ours

Page 69: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 70: Environmental Impact Assessment (EIA) of Metro Bhawan

- -Fwd PB~OA~ mu3 o0 onp smudru~ ~w~~ueaod 40 ~mo~rumo :x's ~I~PI

.lsefad pesodad ay3 p uola~ledo pue uo~pruasuos 'u01lmo1 paCard 03 anp WPCJUII (BRUB~~ aya p MalmaAo ula sa~lB 2's elqq

ww aydnowo5) *uw WLLIRW~PB 'upmew WWJQ m WQ IPUU

Page 71: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA or Mstm Bhawan, Bamkhamba m, Connaught Place

5.3 Impaets due to Project Loeatlon/Deslgn

5.3.1 Dlsplacarnsnt of People

Slnce the project and its associated actlvltias are limited to acquired and approved

area of 10870 m2 and is free from encroachment, hence no dlspiacernent of any

person was antleipated. Prlor to the construction of Metro Bhawan, four old CPWD

bulldings along with thelr servants existed in the same slte and were completely

demolished before construction.

The proposed project Is being constructed In the Lutyen's Delhl under the

jurlsdictlon of NDMC. Thereby, the approval of Delhl Urban Art Cornmlsslon (DUAC)

was also mandatory and hence duly taken by DMRC for the present bullding. The

development in the entlre project area was as per the approved master plan

(Master Plan 2001) of Delhl Development Authority (DDA), hence no landuse

change has been anticipated. The pmject Site also forms part of the said master

plan and deslgnated for commercial purpose.

The proposed site Is an open land earmarked for construction of commerclai Iofflce

complex and possessed 124 trees of different ages (Table 4.10.). Thereby, the

approval for flnaliy cutting of 58 trees was taken from the designated "Tree

OfFlcer". Slnca, the entlre activltles related to project shall be confined to the

deslgnated slte, hence no cutting of trees beyond the project site was undertaken/

carried out.

5.3.4 ShlRlnp of Utilities

A few offlce bulldings previously bullt had to be removed to facllltate the

construction of metro building. Necessary permission/ Information were obtalned

from concerned agencies (electrldty, water supply, munlclpallFy atc.) befor@ the

actual dernolltion of buildings. Hence, except these dernolltlons, the project adlvlty

dld not involve any further shlftlng of existlng utiiitles such as water supply

plpellnes, sewers, OFCs, electrical lines, etc. due to the proposed project.

Page 72: Environmental Impact Assessment (EIA) of Metro Bhawan

'pazllululru

Ja4Un.d aq urn wedwl 'a3ueualuleu elnpay3s pue haulyseru JuaIDlua 40 asn 'BUIJIS

~adwd eul Y~IM pue u~ea UOYS aq IIIM wedm1 as81.t~ '(aaq~eur aya UI alqellehe

lasalp ~nqdlns %SEO'O 'A13uasa~d) lasalp aualum ~nqdlns MOI #J asn p asneaaq

MOI aq 01 pam3dxa sl haulu3Ru pull sueurdlnba do uolawado anp ells pafad

ae suolsslrua 20s 'Jayun4 'aues~luI31s eq IOU IIIM (saxnos heuo~leas B allqoru

JOJ) polJad uo~pn~lsuos Bul~np -lard Y~IM pue -Fwd anoyalm slenal uo~anllod

Ale UI a3ueJau1p 'JI~ lualqure UI 03 pue XON "0s 'wdm 'W~S P suo1ae~~ua3um

~B~A~AP unoq *Z puno~6~3eq 40 oveuess aG qx~ 'guewd~nba pue ~ueld 'se131uan

uolPnqsuo3 40 uolaeJado ruw alnsa UOIP~J~SUO~ Bu~~np suo!sslua snoesef5 Jay30

PUP !afs uolvnJwum aya 01 'saa

'quawa:, 'pues se y3ns sleyaaew uolpn~1suo3 40 uodsue~a pug auawa~nmd (11) !aa~s UO~P~J~SUO~

ae *sw ~ueurdlnba /Aauly3eur pua saplqan heey 40 asn pue a3ueJeap aals (I)

:SBRIYPB uo(unJwuco

BUIMOIIO~ aya udll A~ulew pa~e~aua6 'uo~~nllod Ale 40 auauoduos ~ofeur e si pnq

:a6ws uo~umlsum aw bpnp uo~lnllod JIB ~cy -nos pue ad& ay1 ae BUIMOIIOA

'alp pafad aya 40 A~IUI~IA elelpawurl ulyalM eaAe sly1 UI bulyonn uo~aelndod

IP~IUIW JanqeyM PUP uollelndod ~UI~JOM eya uo pedwl auos esnm cy Alayll sl

'sap~yan 40 auewanoru JO quawd~nba uolvn.rlsucn do uo(~e~ado aql urwj suolsslwa

pue SUOIJU~~O UolpnJasum snoueh way lsnp 'a6w uollsnJlsum ayl Buyna

'san~n~w 1ea1601oaw~e pauo~auaw anoqe ay1 uo salalrrlpe

valwd aqa uw4 Buls~e uo~Inllod Aue 01 anp paatzd131aue SRM ~edul aues~luClls

ou 'a3uaH *aJls pa~eu61sap aya oa peuwuo3 aq lleqs a6ws leuolaeredo JO uo!unJlsuoa

Bul~np ~efo~d oa pweta sanlnlue ayl IIV 'palm01 SI (ass pafad aw a3uaxw.I

431M S~IP~J wy 5) quo1 unAewnH 'voj pi0 'uod pau 'ptFsew auec 'Jeauew Jeluer

awl SaInpnJls lej1601oe~1s.1~ auwodwl heh auos 'ewe a3uanBul paFo~d aq1 UIYJIM

Page 73: Environmental Impact Assessment (EIA) of Metro Bhawan

!uotun~asuos 40 pollad

aya B~lJnp waqa UI Aa3eM anay aeya alts uo(pn~asu6s ala sew8 6ul~l MW . : uolpnJJ$um But~np JaaeM 40 uotaeulure3uos ~oj suolamol alqladwsns asow aya we 6u(~ollo~

'E'S e[qRl u~ uey6 st qualudlnba uo~vneuas snotJen uraj slanq punos is31dh 40 saldWRX3 *~luo awtl-Asp Bul~np

P~WIJ~S~A sl S~ntUe uotpnJfsuo3 aqa se unoq ay6tu But~np Jno paw= st A~IAIPB 6utaaaua6 astou ou leqa But~nsua Aq paez~urtu~w JayvnJ aq IIIM # 'p#~dptaue

st uotlnllod aslou oa anp nedurt lewlutur ~ana~sy~ 'paanltp ap IIIM aodwt

843 'sapts at lie lsowl~ UI s6utpltnq Jayp Aq papunoq st aats pafold aya WUIS

~auawanour aplyan AhP84 pup weld UOlpllJ3SUO3 (111)

!(pesn 41) JalltJP qat~ SuolaepunoJ JOJ UOIJ~A~X~ (11)

6ulxlw puP 6ullBJ3Uo3 'SWS E)a 40 uotae~edo (I) :apnput setatme uownJlsuo3 eyl

'eats paFdld aya jo A~IUI~IA aaatpawwt aya ut smadurl aslou ur~a~-yoys aq IIIM way3

'satalAtPe uotpnJasum snoveh aya OJ ana 'deals ut asuwnaslp pue uo~~~tunurwo~

le~o ul a3uaAeuaaul me stanel astou pasearwt p suedurl pauodar A~uowuros

wour aya 'an(paFqns st astou Aq pwnes uojurwstp p lanai aqa rl6noyl 'Aa~nlne

uotPn4suo3 40 sa3uanbasuo~ alqeJtsapun asow aua 40 auo se panlas~ad st astoN

Page 74: Environmental Impact Assessment (EIA) of Metro Bhawan

Rnal Report EIA Or flctn, BhaWiW, Lsm, m u p M USCC

Surface and ground water resources close to construction material storage

yad; Storm water drains may get choked due to silt loading flowing from the

collected/ stored spalls/so11 at eonstructlon slte. Concrete mixer plants and maintenance sltes of construction vehicles; and

Wlthln the viclnlty of project slte no major / deslgnated water body Is present

and moreover all the eonstrudlon related actlvltles are conflned to the

enclosed area, hence no major Impact on the water bodies In pmje!2 influenced area are antlcipated.

The accidental spills or bad construction pmblces may affect the near by dralns as

well as ground water quality of the area. The magnitude of such lmpact/s depends

upon the type and magnitude of the constructlon actlvlty. Chapt.r 6 on

Envlronment Management Plan (EMP) of thls report descrlbes the mitlgatlon

measures that a n needed to be taken to mlnlmlze such lmpab(s).

5.4.4 Contamination of Soil

The accldenb3l spillage, stacking or handlinp of oil and grease, cement, palnts, etc.

on open ground is llkely to affect the sol1 quality. However the magnitude of the

impact depends upon the severlty of quantum of material spills, etc.

5.4.5 Flora and Fauns

During the slte prepatatton actlvlty, 124 trees of dlfFerent sizes were recorded but

flnal permisslon of 58 trees to be cur with prior permisslon from Department of

Forests, GNCT Delhl was taken. As required, 10 tlmes of the trees actually cut and

5 tlmes of the trees transplanted wlll be planted as a part of compensatory

afforsstatlon, whlch has been described In more details in Chapter 6 (EMP). Hence,

In total 620 (10 x 58 + 5 x 8) were planted as a part of compensatory plantation

(Tabla 5.4. and Table 5.5.). Further, landsmplng lnvolvlng plantatlon of shrubs,

shady trees with large canopy, lawns, etc. wlll be developed as per the landscape

plan envisaged by DMRC for the proposed Metro Bhawan bulldlng ~0mplex. The

florlstlc component of the study area does not include any rare or endangered

specles. Thus, Impact on rare and endangered species of flora Is ruled out. The

Page 75: Environmental Impact Assessment (EIA) of Metro Bhawan

I \ Final Report EM of Metro Bhawan, BaraIdMmba Lane, Cannaught Ham

project operations will be carried out In a manner as not to dlsturb the ecology of

tna a m .

Table 5;4: Summary of Trees Approved/Pe_nnltted tobe transpmted o. mf TMU of Qllth Size (em) ROmlrh

'I@ (1) ~ o t e ~ no. of trees a p ~ . - - M/ 20 a NII

pennlttad to ba Tranmplanwd - 8 (li) T r n Spael= - Plpal, Gular 1

Table 5.5.: Summary of Trees Annrnv~dIbrml~ed to be cut itt project Site

s 5.4.6 Trafflc Congestion

approvad/~ermltted to ba cut at the project slta = 58 (1i)Tree Spdeo - Oak, Jangal Jaiebi (Inga DeIEloos), Aduna, Gular, Pokar (Ficus Infecetoria) Patranjlva,Sapon, Chandanl, Neem, Mango, Jamun, Palm, Mulbery (Shahtut), Ashoka, Mausaml, Kathal, (Ammod), Bakyan, Bamboo, Papri 1 (Pangamid Glabara), Kurauja, Guiar, Ukalyptus, Naem, Llme (Nlmbu),

1 Jamun,Kathal

As the project site is bounded by hlgh tmfflc denslty areas, hence dlsruptlon of

tramc due to movement of the constructlon vehlcles/machlnery may occur. The

disruption of trafflc was mlnlmlzed, by allowing these vehicles/ machlnerles move

only during non-peak hours that too durlng nlght hours. After reachlng the site,

these machlnerles / construction vehlcles were parked inside the project complex

so no trafflc dlsruptlon due to their operation/ movement took place at site.

5.47 Staking of Construction MaWrial

The constructlon materlal used In Metro Bhawan comprised of Steel (3700 Mf),

bricks (15,000,00), concrete (22,500 m cement (1,92,000 bags), sand

(14,500m3), Coarse Aggregate (20,000 m3), fllllng sand (7,000 m') and ad mixture

(73,000 lltres) besides plywood (11,100 m2) and planks (50,500 re). The staklng of

construction material was mnflned to the project slte only. It was carried out In a manner so as to cause mlnlmal dlsturbanee (aesthetically and environmentally) to

Page 76: Environmental Impact Assessment (EIA) of Metro Bhawan

the surrounding natural environment. Further, it should be disposed off periodically

at the dumping sites earmarked by DMRC for this purpose.

5.4.8 Construction Was-

About 62,000 m3 earthwork/ spoil generated were disposed at KSHI dumping Yard,

opposite Shastri Park Metro Station, Delhi. The construction waste consisted of

earth, debris concrete, lumber and manufactured wood produck, drywall, masonry

and cardboards. Apart from this, it also contained mix of roofing materials, metals,

plaster, plastics, foam, insulation, textile, glass and packaglng. The construction

debris along with the overburden generated during construction phase (1260 m3

approx.) has been disposed off at MCD disposal site situated at GT Karnal Road,

Delhi. In addition few items like approx. 1,30,000 bricks and 9.5 MT of steel were

sold as a scrap for reuse and recycling. A$ per the work contract document,

contractor was required to dlspose of spoils and other construction wastes to be

dumped at this site. Dust (fugitive emissions) was the main pollutant released

during construction phase. This was controlled through sprinklers etc.

5.4.8 Public hwlth and safety

Since all the construction related activities was confined to the project slte, no

health related impacts was envisaged in the project influenced a m during the

construction stage. A t the project slte about 600-700 persons were engaged in the

constructlon activities, faced direct exposure to dust, generated from construction

activity. This Is likely to cause health related problems like asthma, bronchltls, etc.

To mlnimire these anticipated impacts sprinkling of water at construction slte to

suppress the wind-blown dust suitable along with protective equipments such as

mouth mask was provided to the workers. The construction debris and waste

generated during construction malnly cause fugitive emission of dust hence are

pmvlded with helmets, gloves, safety shoes, eye shlelds, dust masks. Awareness

programme regarding the same was provided weekly extending upto 2-3 months

depending upon the need.

Page 77: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report: EM &Me& BMwan, Banmamba Lane, Connaught Mace

8.4.10 Social Impacts

Slnce the labourers were hlred by the construction agency as per the terms and

conditions already specifled, hence no adverse soclal Impacts are envisaged due to

the proposed project.

5.5 Impacts due to Project Operation

Durlng the operation of proj@ct, there would be impact on air, water, land

envlronment and sodo-econamlc aspects. The following sectlons present the

impacts envisaged during the operation phase.

5.5,1 Alr Environment

The operation of proposed project does not envlsage any major air pollutant

generatlng sources except DG sets and vehicular movement. The DG sets proposed

will provide 100% backup In casa of power break down. Thus thclr use wlll be

Infrequent. For proper dlsperslon of the air pollutants from the proposed DG sets to

minirnlse the air pollution, a stack of appmx. 8m above the m f has been proposed.

5.5.1.1 Measure to Control Emission from the DG Set

Appropriate stack height for the exhaust of flue gases shall be provlded to rninlmlze

emlssion from the DG sets for the proper dispersion of gases wlthout increasing the

ground level concentration of the pollutant. The mlnimum helght of the stack shall

be as per CPCB/ MoEF guidelines using the formulae (Annexura VII):

H = h+o.z*v~ where,

H = Total helght of stack In metre

h Height of the buildlng in metres where the generator set is

installed

kVA = Total generator capacity of the set in kVA

In this case, four D.G. Sets (2x1500 kVA, 2x1000 kVA) will be Installed for 100

percent power back up, hence for the proper emission of gases from all the four DG

set, comblned stack of at least (44.75 - 37.0 m) 7.75111 (- 8 m) may be pmvlded.

Page 78: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report. EM of Metro Bhewan, Barekhambs Lam, Connaught Pace

5.5.2 Noise Environment

The sound pressure level generated by noise source decrease wlth Increase in

dlstance, from the source due to wave divergence. An additional decrease in sound

pressure level with distance from the source is expected, due to atmospheric effect

or its lnteractlon wlth objects in the transmisslon path. The noise levels emanating

from varlous equipment, which shall be used during the operation stage are Qiven

In fable 5.6,

fable 5.6:7ypical Noise Levels from varlouo Equipmants

Nolw V P S of

m e i No. Equipment

dB(A1 1 DC _.ts 80-83

2 Pumps 70-75

3 Cooling Towers 65-70

The DG sets shall be used during power failure for controlling emergency

operations. The predictions have been made taking into account all operations and

utilities thus rdectlng the worst-case scenario. Noise level at a distance of 100

meters radius of the proposed sources Is expected to be around 40-45 dB-A, which

is well wlthin the boundary of recommendations given by World Health Organisation

(WHO) with respect to nolse level (Table 5.7) and should meet noise standard for

continuous exposure specified by CPCB (Annexure VII I ) . Table - ' "'Ha Recommendations

Levels Criterl-

During construction water will be drawn from the borewell. As the project area does

2

3

not come under the water stress zone, hence no impact Is anticipated on the

c45 d 8 ~ ~ i g h t Time - 3 Leq (24 hrs) = 52.2 dBA Sleeping criteria

quantity and quality of groundwater drawn is anticipated. Further provision has

5.5.3 Water Supply Requirement

Page 79: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Repoe RA of Mcho Bhaww, Bamkhamba bm, Connaught Place

been made to recharge rainwater through roof-top rain water harvesting when the

Metro Bhawan becomes operational.

Durlng the operatlon, 64m3/day wastewater wlll be generated that wlll be treated In

the sewage treatment plant operated by the munlclpal corpomtlon through exlstlng

sewer llnes. Any burstlng or choklng of Internal sewer llnes In the bulldlng is likely

to cause adverse Impacts such as foul smell, unhyglenic mdltlons and health

related Impact on the occupants of the bulldlng. Perlodlc cleaning of these Internal

sewer llnes Is recommended. Further, the entire project lnfluenced area has been

developed as per the Master Plan 2001, thus the exlstlng sewerage system can very

well take the wastewater demand of the project.

5.5.4 Solid Waste

Solld waste generated durlng operatlon stage wlll be both blodegradable and non - biodegradable (paper, offlce statlonerles, computer statlonerles/flopples/CD) In

nature. It Is advisable that biodegradable and non - blodegradable waste must be

segregatedl collected and dlsposed off separately. For collecting the solld waste,

provision for appropriate bins has been made. Arrangement shall be made wlth

munlclpal authority to dispose the generated solld waste In sultable manner. Hence

no major Impacts are envlsaged.

5.5.5 Induced Davelopment

As per the Master Plan 2001, the project Influenced area has been developal to

meet the comrnerclal requirement in and around Connaught Place area. Hence no

lndueed development Is foreseen due to the construction of Metro Bhawan.

5.6 Posltlve Impacts

The operation of the project, provlde valua addltlon to the exlstlng Infrastructure

faclllty such as publlc transport, water supply, telecommunlcatlons, etc.

The operation of project and Other allled facllltles, wlll Improve the employment

opportunltles (direct or Indirect) at the proposed project site. The employment thus

generated wlll have posltlve Impact on the quality of llfe.

Page 80: Environmental Impact Assessment (EIA) of Metro Bhawan

5.6.3 Enhancement of Publlc Health and Safety

All fire and safety measures as suggested by NBC (2005) have been Installed and

regular mock drills have been conducted at the project slte. Regular health check

up shall be carried for security guards and persons working near DG sets.

Page 81: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EL4 of Metm Bhawan, BBmIdramba Lane, Connaught Place

Chapter 6 Environmental Management Plan

6.1 Gsnaral The maln purpose of the Environmental Management Plan (EMP) is to

delineate all the measures to be undertaken durlng varlous phases of the

project to offset or mltlgate the adverse environmental Impacts (if any) to

acceptable level to protect the environment especially the communlty likely

to be affected by the proposed project. The EMP should necessarily cover all

phases of project cycles 1.e. piannlng and deslgnhg, construction and

operation. The potential Impacts on the environment due to the proposed

project were Identified based on the nature of aQivlties undertaken durlng its

construction and those envisaged to occur durlng Its operation in the llght of present status of the environment and legal compliance requimd. The

mitigation measures requlred to be takenlalready taken during various

stages of the project have been described below.

6.2. Mitigation Measures during Pm- Construc&ian/Demign

stags

The pre-construction stage measures already taken care in the project design

are as under:

Selection of Construction Material

Water Conservation

Energy conservation

Pathway for access

Landscape and Green Area Development

Workers Health Management

Earthquake Safety Measures

6.2.1. Selection of Construction Material

Use of burnt clay bricks in masonry is a common pmctlce In the country. The

Metro Bhawan does not Involve use of bulldlng with hlgh-embodled energy.

All the materials used In its construction (vlz., cement, brlcks, steel etc.), are

Page 82: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM OT- Bhswan, 8smEdNlmbd Lana, Cormaught &a

those which are commerclaliy available. For other purposes, glasses of low

emlsslvity power have been used In the Metro Bhawan.

6.2.2. Water Conservation

The bullding construction projects requlre a large quantity of water durlng

construction and operation phase. Suitable arrangement needs to be made

prior to the start of project regarding the availablllty of water durlng these

phases. However, If these new bulldingS are to be constructed and put

operational In the major metros, speclal efforts to be made to mlnlmize and

conserve the water requirements. Based on the estimated water

requirement, a rellable source of water wlth the specified water quality

standards is essentlal. Further adequate armngements for storage facility

should be made t~ meet any contingencies. Also, now a days water

harvestlng from the offlce buildings/ has been made essential to recharge

groundwater table and as a measure towards water conservation. A

necessary provlslon needs to be made at the design stage to facilitate the

rainwater harvesting from the roof top. For guidance purpose, raw water

harvesting manual entitled "Rain water Harvemtlna and Conservation"

publlshed by Central Public Worb mpartment (CPWD) has also been

referred for detalled deslgn purposes.

6.2.3. Enemy Conservation The amount of energy used for lighting varles from Industry to Industry, but

typically, lighting accounts for approximately 50% of the electrical load m any office building. By using the lamps, ballasts, lumlnaries and control

options available today as well as the techniques used to develop efflclent

lighting; lighting can be produced that is both energy efficient and cost

effective. Improvements In lighting efflclency can be provlded In the bullding

by adoptlng following measures:

(I) Lamps - replacing Inemclent lamps with the most efficient lamp for the

purpose, taking Into account slze, shape, colour and output of the

lamp.

Page 83: Environmental Impact Assessment (EIA) of Metro Bhawan

(ii) Ballasts - replacing standard choke ballasts wlth hlgh frequency

electronic ballasts.

(111) Lumlnarles - retroflttlng standard lumlnarles with high-effldency

spectacular reflectors or replacing standard lumlnarles with hlgh-

efficiency luminaries.

(Iv) Automatic Control systems - installation of (a) timer clrcuits that switch

lamps off during room vacancy times, (b) photoelectric sensors that

sense the amount of daylight in the room and elther switch lamps on

or off or adjust the lamp brightness accordingly and (c) occupancy

sensors that switch lamps off when work stations are unoccupied.

(v) Locallzed swltchlng - installing localized swltches near work stations to

control local llghtlng.

(vi) Llghtlng deslgn - (a) designing llghtlng systems that maxlrnlze the use

of dayllght, such as the PSAU system (permanent supplementary

artificial lighting in interlor$) and (b) Introducing local task llghts (e.g.

desks llghts), allowing a reduction in general overhead ilghtlng.

(vii) Maintenance schedule - setting up a maintenance schedule to clean

and replace lamps on a regular basls.

6.2.4. Pathway for Ac~eso

(I) The wldth of Maln Street on which the bullding abuts Is not be less

than 12m and one end of thls Street whlch joins another street Is not

less than 12m in width;

(ii) The approach to building and open spaces on all Its sides' upto 6 m

width and the layout for the same was done in consultatlon with the

Chlef FIre Offlcer of the clty and same was hard surface capable of

taking mass of the flre engine, welghlng upto 45 tonnes. The said open

space was kept free from the obstruction and was motorable.

(ill) The main entrance of the plot has adequate wldth to allow easy access

to the flre englne and In no case it measures less than 6m. The

entrance gate folds back against the compound wall of the premlses

thus leavlng the access way withln the plot free for movement of fire

vehlcie,

Page 84: Environmental Impact Assessment (EIA) of Metro Bhawan

final &port &&I of Meho Bhavvan, BaraIdrah Lem, Connaught Place

(iv) As per the Bulldlng By-Laws, 2005, for the bullding of helght greater

than 35m (In thls case 37m), l l m was left for slde and rear open

spaces around the bulldlng.

6.2.5. Landscape and Grwn Ama Development

The greenbelt development/plantation In the Metro Bhawan area wlll not only

fundlon as landscape features resulting In harmonislng and amalgamating

the physical structures of proposed buildings wlth surroundlng envlronment

but will also acts as pollution slnk/nolse bawler. It will check soil erosion,

make the ecosystem more dlverslfled and functionally more stable, make the

cllmate more conducive and restore balance. All the land sites subject to use

of constructlon related actlvltles were restored to the origlnai settlng by

restoratlon and landscaping of the sites. Sites subject to excavation and

tampering of ground profile was rectlfled and done by the Contractor before

flnal closure of the construction activities. Landscaping of the areas wlthln

the premises of Metm Bhawan was also taken up durlng construction perlod.

Overall the project area was restored to the natural settlng In an

environmentally sound manner.

The project constructlon would Involve deployment of about 700 workers

durlng the peak period. Hutments for workers are not permitted at slte and

they will commute daily to the site. The labour hutments were provlded at

the batchlng plant at Kashmere Gate and Delhl Cantt. and few were on rental

basls. Also other facilities like tollets etc were provided at the project sltes,

hence no unsanitary conditions developed around the project slte. The

provision for safe drinking water would be arranged through the contractor.

Separate arrangement of WCs for gents and ladles was made wlth water

bound sanitation. A quallfled medical attendant with adequate medicines and

other facllitles was stationed at site throughout the constructlon period to

provide any flrst ald to the workers. The construction debrls and waste

generated durlng eonstruetion malnly cause fugitlve emisslon of dust hence

the labourers are provided with helmets, gloves, safety shoes, eye shields,

Page 85: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM ofMctm Bhswn, BamMurnbu Lana, Cann8ught Race

dust masks. The awareness programme regarding the same was provided

weekly extending upto 2-3 months dependlng upon the need.

62.7. Earthquake Safety Messureo

The Delhl region come under Selsmic Zone IV, hence all measures to protect

the buildlngs built in thls region are In accordance to good practlee as

specifled under NBC (2005).

6.3. MitigatIan Measures during constructlon and Operatlan Phase

6.3.1. Air Quality

6.3.11. Durlng Construction Phase

The Alr Quallty around the project slte was affected durlng constructlon

stage. Various construction actlvitles especlally related to loose materlal are

likely to generate dust that Impacted the air quallty of the surrounding area

of the project site, In order to mlnlmlza impacts especlally from these

fugitive emlssions, following measures were taken:

(I) All the loose materlals were transported with sultable coverlng etc.

(li) Water sprinkling was carried at the locatlon where dust generation

occurred.

(iii) Care was given to personnel Involved in the dust generatlon activity in

terms of provision of safety masks etc. to avoid any health hazard #r

them.

(Iv) Transportation of constructlon materlals was carrled out durlng non-

peak hours.

(v) t o minlmlse dust emission due to handling of aggregate and cement at

slte, ready mlx concrete were carried in translt mlxers.

(vi) As the vehicular movement may lead to fugitive dust In the area,

hence provlslon was made for sprinkllng of water on the roads at least

once a day durlng the entlre construction period.

(vll) Every day the haul road at the construction site was inspected and the

debrls left by the tractor - trolleys was removed as early as possible.

(vlli) Vehlcle speed was restricted to 15 kmph applied at slte.

Page 86: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of Metm Ehawan, Barakhamba lane, mfmaupht Ram

(Ix) Downwash of trucks (especlaiiy tyres) prior to departure from Site.

(x) Proper care was given for the storage of furnace oil, LDO, etc.

(xi) The work schedule and the operation tlme of each construction

machlnery was suitably modlfled to optimist2 the use of construction

machlnery.

(xll) All statlonary machines/ DG sets emltting the pollutants was Inspected

weekly for malntenance and were fitted wlth exhaust pollution control

devices.

6.3.1.2. During Oparatlon Phase

The air quallty control measures around the project site during aperational

stage envisaged is given In the Tabla 6.1.

table - - .: Air Pollution Control Measures

Control rneasul~-

helr vehicles to strictly follow emissio

6.3.1.3. Parking Scenario inside the building Complex

There will be about 272 cars expected to vlslt the complex everyday. The

following measures may be adopted to control emissions from the movement

of vehicular trafflc:

(I) Proper maintenance of internal roads;

(11) Adequate greenbelt will be developed and malntained;

Page 87: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report M of Metro Bhawan, Eamldrsmba bne, Connaught Uace

(iii) Informatlon sign shall be provided to encourage vehicle owners to

malntaln thelr vehicle and follow the emlssion

6.31. Reduction of Incremantal Air-pollution through Traffle Manau~mant

Reduction in incremental air pollution from vehlcuiar emissions In the Metro

Bhawan project has been aimed through state of the art trafflc management.

Salient features of the trafflc management have been glven below.

(I) Adequate and clear warning signs were displayed at appropriate

distances before the commencement of the slte workings. In addltlon

prior warnlng will be glven concerning the iocatlon of the approaching

slte entry and exlt points.

(it) Slte vehicles exltlng the site obsenred caution at all times. I f the

vehlcles were exltlng dlrectly onto the llve carriageway then they were

directed by an identifiable Traffle Controller.

(ill) Regular inspection of the trafflc management schemes was conducted

by contractors in both the day-time and night-tlme hours which wem

recorded.

8.3.2. Nolw Control 6.3.2.1. DurlnQ Conetruction Phaae During the construction phase, there would be a temporaw Increase In

ambient noise levels due to operation and movement of constructlon

vehlcles. In this project, belng a buiidlng constructlon work, the magnitude

and use of machinery is llmlted exclusively to the project slte. Though the

Industrial countries have speclfled limits for occupatlonal noise exposure, the

permlsslble nolse exposure limit for lndustrial workers is primarliy concerned

wlth harmful effects of noise and its objective is to protect the hearlng of working people. The exposure to cantlnuous and Intermittent noise levels

louder than 115 dB (A) should not be permitted. Foiiowlng mltigation / management measures were adopted during construction period:

(I) Special acoustic enclosures shall be provided for individual nolse

generatlng constructlon equlpment llke DG sets. The Speclal acoustic

enclosure was provlded by way of nolse shlelds.

Page 88: Environmental Impact Assessment (EIA) of Metro Bhawan

'd3OW

Aq payxds sau1laplnB Jasn aya 01 w~ojuos plnoys ~ge~aua6 au (IA) 'saplyah JO Bulyuoy PUP 6ullp1 Aessesauun

plane oq pea IeuJaJul ayq uo pwnsua SRM ~IJJ~J~ p MOM qqoours (A) .urea 9q aplsul panlohul lauuovad Aq s6nld~w )o esn (AI)

.pamasqo SBM 'aopuah Aq

pa~13ads se 's~oq~~aua6 40 alnpeuss asuPualulRw ol wuweqpe PIJ~S (111) 'aunos

Page 89: Environmental Impact Assessment (EIA) of Metro Bhawan

(iv) Footsteps, noises, slammlng of doors in clrculatlon spaces, lift doors

and gates

(v) Sound produced in conference room, presentation moms etc.

(vi) HVAC & lift machinery.

The followlng llst may be utllized for broad classlflcatlon Into nolse produclng

and quiet rooms, It should be noted that where roams In apposlte mtegories

are planned adjacent to each other, a sound reduction of at least 45 dB

should be provlded to them as glven in Tabla 6.3. below:

Table 6.3. Classifleation of nolse producing /qulet rooms

6.3.2.2.2. Outside Bulldlng at project slta (Outdoar Environment)

Durlng Operation Phase, the major source of alr and noise pollution are

vehicular trafflc and DG sets. For DG sets followlng control measures will be

adopted:

m I) Entrance halls, staircases and (I) Exemtive's rooms, conferenm and

(I) Scrubber to be Installed at the outlet oP the DG sets.

(il) Good quallty fuel with low sulphur content should be used.

(iii) Perlodic maintenance of DG sets as per deflned schedule of

manufacturer.

(Iv) Malntainlng proper stack helght.

corridors used by vlsltors

(11) Ufb (Ill) Motor and plant moms

(Iv) Lavoratorles (v) Canteen and kltchens

(vl) Omcs machine rooms

board rooms

(11) Intewlew rooms

(Ill) Omces for one or two persons

(Iv) Sick moms

(v) Rest moms

(vl) Ubrarles

Page 90: Environmental Impact Assessment (EIA) of Metro Bhawan

.(v) Japun paqy3sard sprepugs ad se aas sa pmuallsun eqa do slaAel Jemod aslou yslu~nj plnoys Janpejnueu au

.saAnsoau lol~uo:, pug BUIUIS ada ad ~q

saueue~~nbar aslou 1ualquP aya ulyalnn 'sas~we~d slq aplslno 'aas 9a ay3 01 anp slanal aslou aqa u~op Buyq oa wo#e ayeur plnoqs Aasn ayL

'(Q~QP sz P sso~ uo!vasu~ 411~ '~ewnu

WIeqxa alqnlns e osle pue ssol uolvesul (w) gp GZ 40 ansopua

sl3snmo prepuels e lesn eqa oa Jauo plnoys Janpejnuew au

-(lasala 411~ unu %as 90 JOJ alwn asioN - v6 uolves) 986~ 'sam

(UOIPWOJCI) auauumlAu3 Japun WA~ OOOT emqe lesalp ygm unJ slas 99 JOJ

salull aslou oa Bu~ulwad (anoqe pue WAYS) slas Da $0 slesn /Janpejnuew

eu~ lo4 sau11epln6 aqa '~euunj '(w) up sz wnululur 40 ssol uolwasul

U~IM Jalddnu qsneqxa Aado~d ~UM PaplAOJd aq osle IIIM las ga ayL .pafie~a~e

uaqa pua 'uoo~ ansopue 31~snw~ a143 war4 w 5.0 3e aulod auweglp JB auop

aq Aeu SSOI UOlvaSuI AO auauarnseew ayl .(aurlJ 1461~ ayl ul 'Alq~~ajwd

'la~al eslou aualque lanpe oxln uolpnpw eslou JOJ peq3ays aq Aeu e3ueuodJad ay1 sa3ueaswns~p q3ns Jepun 'auauaesul slqsnme /e~nsopua

31lsn03e ay3 p wueuJ0pad ayl q~ay:, oa alqlssod eq pu Aeu 31 'apls

Jaqllly a41 uo sl aslou aualque p'we aqa 61) apls ~~14614 aya uo st JanaqIyM

'SPI~PU~W eslou auelqlua aya 6u1wew JOJ JO ssol uo~wasul (Q)BP st wnululu

JOJ pau6lsap aq plnoys uroo~ aqa do JuawleaJq 3IJsncne /aJnsopua :,!Jsnme

eyl 'Allm~asnme urn ayl 6ulaaaa Aq JO ansopua 3jJsnme ue 6ulpl~cud

Aq PalloJ1uo3 eq Plnoys ass 9a aq3 umd ~SION '(a~oqe pue WAY G) aas 9a rCIeuOllmS JOJ uoo~ p luauaeara 31lsnwe /;un!sOpue 317sn(11e holapueN (a)

~LOOZ UI uaua PUP zooz UI

'e-I 'LOOZ IIR 'sreeA anu &Clem Cv) SIP s Aq 11o4 plnoys laha1 SIU 'ass 9a e do 6ulae~ JaMod ~eulluou ayq sl VAN 'aay~ 'efms 6u1~npe~nueu ayq Je '(Q) gp

'(w~n) OT+P~ 'uew ssal aq plnoqs aas ga R p (MI) IaAel ~a~od punos

IWI WL :(XI wnmuuv) (WAN 00s-ST) ws 9a ~od spJepuws asloN (\I)

Page 91: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA ofbfetro Bhawan, Bamkhamba Lane, tonnaupht PYaa

The total sound power level of a DG set, at the user's end, shall be

within 2 dB (A) of the total sound power level of the DG set, at the

manufacturing stage as prescribed under (A).

Installation of a DG set must be strldly in compliance wlth the

recommendations of the DG set manufacture.

A proper routlne and preventive maintenance procedure for the DG set

should be set and followed in con5ultatlon with the DG set

manufacturer which would help prevent noise levels of the DG set from

deteriorating wlth use.

6.3.2.2.4 Poilutlon Control throuah Plantlltlon The air and noise pollution control can also be enhanced by planting certaln

species of plantsftrees. Some of floral specles which can be glvan preference

while developing the green areas of the project are: Ficus rellglosa (Pipal),

Aibiuia lebbek (Slrls), Cassia flstuia (Amaltas), Zirphus jujuba (Ber),

Azadirachta indica (Neem), Tamarindus Zndus (Imli), Daibergia sissoo

(Shlsham), Butea monospema (Dhak), Ficus giomemta (Gular), Ficus

infectorla (Pilkhan), Alsronia schoiarls (ChltvanIChattaun), Acacia nilotim

(Desi klkar), Aegie marmeios (Bel), Ailanthus excelsa (Ulloo neem), Alstonia

scholaris (Sataun), Lagerstmemia flosreginae, Mimusops eiengi (Maulsirl),

Nerlom lndicum (Kankar).

6.3.3. Water Requirement 6.3.3.1. During Construction Phase: About 8,820 KLD of water was

drawn from the existing tube wells in the metro site, of which 50% was used

In the concrete and remaining 50% was used far the labourers, curing etc.

6.3.3.2 Durlng Operation Phase: The water requirement at the

proposed Metro Bhawan has been estimated to be approx. 80 m3/day. The

details have been given below In Table 2.3. It is proposed to get the whole

of the water supply for drlnklng purpose from the NDMC through the exlsting

water pipe lines. Necessary permission regarding the quantlty of water to be

used for drlnking purpose has already been obtained from NDMC. It is

proposed that the municipal water supply wlll be stored in the over - head

water tank and thls water will be supplled in the bullding through gravity.

Page 92: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA Or McND Bhawan, Bevatdramba Lane, Connaught Place

Four water tanks of varlous capacltles have been Installed In the basements

(Table 6.4.) and two tanks (one each for drlnklng water and flre purposes)

of 20 m3 (20,000 lltres) have been provldad at the terrace.

Tabla 6.4.: Capaelty of water Tanks In the basement of Metro Bhawan

During operation perlod about 64 m3/ day of sewage wlll be generated from

the project, whlch wlll be dlsposed to the external munlclpal sewer adjacent

the site. A no. of measures to reduce the mnsumptlon of water that will be

followed are as under:

Reduction of tollet clstern volume in single flush models,

Promotion of awareness on water conservatlon and reduclng water

usage, Promptly attending the water leakages,

Provldlng urlnals and wash basins wlth autornatlc sensors and WCs

with flushing valves,

Sprinkler irrlgatlon system for watering of green spaces, Plants wlth slmllar water requirement

6.3.3.3. Raln Water Harvesting

In addition three ralny wells have been constructed to carry out rainwater

harvesting, purely for recharging purposes, In the Metro Bhawan rainwater

wlll be harvested from rooftop and paved and unpaved areas l.e.,

landscapes, storm water dralns, roads and pavements.

Rainwater harvesting can serve as a solution to the water problem in the

water crlses areas by capturing the runoff. Rainwater harvestlng helps In

utlllzlng the prlmary source of water and prevents runoff from going Into

Page 93: Environmental Impact Assessment (EIA) of Metro Bhawan

~euo~eu~aau~ pue UBIPUI asaael aya PUP (866~) ~Pnuew uoimawd aru '~WL

s,aw1~wo3 AJOSIAPV #IJ~I '(TOOZ) emu1 p (3e~) apo3 BulPl~ng I@UolaeN 40 I dno~5 'AI~JB~ uo paseq pau61sap Alle~auaB se~ waasAs uolpaacud aJU aul

suraasAs jumpAq g ~alqul~ds JOJ dwnd AaymC aaeJPdas ((A)

330 ul sworn auawdlnba 1~s JO~ sanleA ~alqul~d~ uolpa-e~d (A)

waasAs Jalqu~dS (A!)

waasAs aue~pAy IeuJaaxa 18 1eu~a3u1 (111)

s~eued 1-1 /AH auwodw~ UI ~easAs 6ulpoou sef5 peseq 203 (11)

SUOOJ aueurdlnba

w s~oa Jehlas 'slweay3 330 u( uraasAs 6ulpoo~ sef5 paseq uahau~ (1)

:6u1~ollo;l ey3 apnlsul IIIM 330 aya ae weasAS Bulay6~ a4 ayL erwyd uopormdo Oulrna mzmiv~gg

*ad& IIB 40 uolpnJasqo

wW;l eaJ4 'aoae(o3sa JO syll ~ou anq Ae~aBessed 'ABWOOP aq Aew

~lxa uw '3aa ar~ WOJ~ ~a6uap anpun ploAe se os paawado pue pepnJyuo3

aq oa SI 6u1pl1nq eqa P wle au CL(soo~) 38~ aya ~IM a3uepmoe UI waasAs wele a~ slaswoane pue uraasAs wJale ar~ pl-lpela paauado Allenueur

~IIM pddlnba aq oa peJlnbar sl 6ulpllnq y3ns .alqlasnqum-uou waM

sapme4 PUP UOPIUO~ PUB ~Aewleas 'queurala Bul~saq peal ul SlelJaaeur IIW

aueruo8wusw / 6~layO(d cry 'Vt'9

'3wa~ JO aull a8euleJp

JaaeM ur~oas ulew a43 oaul Alleu~ pasodslp aq oa uaMeyq aaaw ;lo Aaqdl~ad

ayj Buole pe~ea~3 aull a6eule~p JweM uuoas ulew p 6ulyoqs auaAaJd

oa Yeplnoq 'sl~qap 404 6uluatu3s SQe pasodslp aq 111~ paae~aua6 Noun4 ayL

aueruaBwww ~o-unll wwns mtv&m~~

'IlaM arneym ul pags JaaeM pamey3a~ p asn aqow lloys peeJsul asod~nd

sty3 JOJ JaaeM ysarj esn oa pemolle aq pu AEU SBSod~nd 6u11om JOJ JaaeM

alnbaJ queld 0u(uo1alpuos-~(e leJaua3 6ulhey ueMeq8 oJaaw 'sau(1 w(Nas

Jayp uo se llaM sla ~uold JuawaParj uo peol aya 6upnpar pue asn aman) 404

elqellene Jaaem 6u(qew 'asod~nd (enp Bu(~as Aqa~ayq 'sulrap w~gs JO JaMes

Page 94: Environmental Impact Assessment (EIA) of Metro Bhawan

-. Final ~ a p r t . . , .. EiA oikh aliic, Bamkhambr &"ri6ug.Ei,.Ei,Ra

standards/codes. The fire protection system will cover external as well as

internal premises of the building. FollowlnQ systems are planned to be

provided for the bulidlng as detailed in Table 6.5. below.

Tabla 6.5. Details of Fim DdactIon Systwn

&rat& qf F$H &tcu:liaJExflrrguishin~ mUP-3' SYs-

a)~nllObcumputer Aummntkfi~=DLenn.yEtern i n ~ l a t i o n ~ {s-d prectice (4 and

[4(19)]. and Table 23) m y suiFlldt halon slmntivc fi oxdnprishing sylrtan <ssc 5 3 ) or any other auirsbk rult axtln~l&inp won {sw a h C q Z 9 ) I I.

b)Sp*oeundcrP*lsc Automdc h a l e r m r y - W i g C-1 {m K418)I urd

14U911. and Tabb 23 1 c) Spec 9)*1va false Automatic fire d m aysPDm

dllng and wow { g a d i 4 l B ) l and f b now lY19)1, a d Tabh 231

d) Elecuical s w l W Automulc Fbr aLerm oys~mn board {gcd i*JWl

14(19)1. ucd Tabb 23) 8nd C 0 . z fins ullngriahbw inst*a*oion

Brief descrlption of Fire Flghtlng system Is given below;

A. Wet Riser Cum Down Comer System with yard Hydranu: The

number of hydrants to be provided at various locations shall be as

under:

(1) Four Internal hydrants each will be provided at all floor levels

(ii) One Internal hydrant (landing valve) w~th first aid hose reel near

every fire escape staircase/wet rise duct at every floor

(111) Six Internal hydrant (landing valve) with flrst aid hose reel in the

basement car parking

( 1 ~ ) One hydrant at each riser on the terrace of the building

(v) External flre hydrant at every 45m spaclng on the external

periphery of firewater underground network.

8. Fire Brigade connections:

(1) There shall be one 150mm fire brigade Inlet with 4 Nos. 63 mm

dla (breechlng Inlets) instantaneous coupling at the ground level

Page 95: Environmental Impact Assessment (EIA) of Metro Bhawan

nnai Report EfA or Metro Bhawm, Bankhamba Lane, Cunnaupht Mace

near the flre water pump house to connect to inside fire water

rlng mains.

There shall be one 150mm flre brigade Inlet with 4 Nos. 63 mm

dla (breechlng inlets) instantaneous coupllng at the external flre

hydrant lines near Central Block to connect from flre servlce

vehicles durlng emergency.

(111) There shall be eight numbers 150mm dia brigade inlet with 4 Nos.

63mm dl& (breechlng Inlets) Instantaneous coupling each for riser

and sprlnkler risers of Main Block of Phase - 2 to connect fram fire

servlce vehicles during emergency.

C. Automatic Sprinkler System: The system has been deslgned to

caver the basement, Podium level, all the elght floors excluding the

electric hazard areas. Sallent features of the sprinkling system wlll be

as follows;

(1) Pendant /upright, quarhoid bulb, conventional spray pattern type

of sprinklers will be used dependlng on requIrernenWarchltectura1

aspect.

(ii) The maximum area of coverage per sprinkler will be 12m2 as per

TAC regulations.

(111) The spacing of sprinklers will be 3.4m (max.).

(iv) The temperature ration will be 68'~.

(v) Orlflce size of the sprlnkler wlll be 15mm

(vl) One number Alarm valve will be provided for each sprinkler system riser in the ground floor. Each bmnch line of respective

floors of the sprinkler rlser are provlded with a flow switch, whlch

In turn is connected to the respective buildings fire alarm panel to

annunciate which zone is under flre, in turn connect to the BMS

panel also

(vfi) Each alarm valve will have water motor gong, stop valve, test

valve etc.

As per NBC (2005) flre doors with 2hrs resistance was provided at

appropriate places especially aionp the escape route. In addition, all the 4

Page 96: Environmental Impact Assessment (EIA) of Metro Bhawan

-6u1pllnq aul JOJ paflope uaaq aAeq (wapunos paJaM0d do01 alqessaJppe) slaaooH

auiod lies lenuew alqessappe pue slosues aqows awy (6olaue)

~ue6111aau1 'alqessarppe yg~ aaalduro~ UWSAS ur~elw pue uolwaaa

arlj (601aue) 1ua6111au1 pue alqtmwppv paseq ~osswa~dm~~w

'uolue aae~a~ul 03 eAu do a3uase~d aua waap 03 pau61sap $1 11 'waasAs

uolpalard wu a41 p auowela Aaq a SI ureasAs uuqe pue uolwsp WIJ

ayl :ruelsAs LUJ~IV w uo(wma wid oda olqesswppy onOo(suv 'a 'plezey ayl aplswo pea-1

(~a) an(eA a6nlaa aya 01 panauum eq llays ~JOMRU aqa 'q~owau adld

uolmap aya uo SoPalap qlnq plomanb pue yonnlau adld uolljalad

aya uo SIRN~UI ~e1n6a~ ae paxu aq lleys elzzou Ae~ds MAH ayl 'pevaamd luawdlnba a43 Punma PIPI eq IIIM wowu uolnaap pue

uolpaao~d eyl 'plepuqs 3ueAalw ayl lad se UIJ pa~lnba ya1~ ayen

abnlap pue slovwp (a01 qlnq Plowen0 U~IM q~onnlau adld uolwaep

'alzzou A~ds MI\H 411M qJOruq9u edld uolpqo~d 40 ~slsuO3 wasAs

AUdS MAH au CLSJ9UIJOJ~UPJ3 odh 110 404 WWSAS Amds WH 'a *S3~0dJnd Bu~qBu-a~u JOJ suolawado auawesuaurwoz!

ayl arwq pepl~tud aq lleqs A11113ej a6ums JaleM auapuadapul uw (A)

*sapelsqo urmj aw4 ldaq aq plnoys Bully614 aru ~oj pm~ y~eo~ddv (All

'quarpAy pue sanleA SJalqUlJds '~eqsln6u1wa 'asoq aJu Bulpnpul 'luaurdlnba 6ulay61~

~JIJ II~ 03 seuria IIR ae peulmuleur pue pepinad aq lleys ssaoow (1111 aals uo!pnmutx, aya ae papl~0Jd sraysln6u1axa aJU

JO UOIIBJ~~O pue esn aul 6u1p~eOe~ ueuryJonn asOuowa ssauaJeMv (11)

'[(z)L 1 sslpa~d poo6 ad se alperd oau~ and sau11epln6 hassmu lie pua [(P)L] es~~lzld

poo6 ad se saur~a ile ae waqs1n6ulwa ~AU 40 a~ueuaau~eu ~ado~d (11 : uo~larsplsu03

oaul uaqw aq plnoys uoianesa~d 6ul~o1104 uolalppe u~ '(auaweseq

papu-1 lanai punO~f3 oJdn (SOOZ) ~GN Aq paupads sa z asuleee UPMB~B

~JWW ul paplno~d uaaq sey (le~lds 'ou T pue ieur~ou E) sesaulms a14

Page 97: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EL4 of- Bhswan, hmEcharnsmba Lane, Connaught A"an

F. Portllble Extinguisher: Portable extinguisher will be used to fight at inclpient stages. The various types of extinguishers that wlll be

dlstrlbuted according to the nature of hazard In thls building are:

(I) Water expelling type (Gas cattrldge) type extlngulsher (11) Dry chemical powder type

(Ill) Carbon dloxlde type

Dry chemical powder type wlll be placed throughout the

servlce/electrlcal hazardous area and C02 extlngulsher will be placed in

the central corrldor area and near the lift machine room. DlWerent

capacities of foam type extlngulshers wlll be placed at DG room,

Transformer areas, car parklng areas etc. and where liquid fuels

hazardous areas are expected.

a. Photo Luminescent Sahty Signage: Photo luminescent flre safety

slgnage1s wlll be provlded at emergency exlt, staircase, lifb areas, flre

extinguisher, fire doors, sprinkler control valves, maln fire alarm panel,

graphic use Interface based repeater statlon and flre hydrant and hose

reels etc.

H. Rooflnp: Preventlon of accidental falllng of the labourers especially

roof Constructlon was ensured by provldlng platforms, catch ropes etc,

6.3.5. Solid Wamtm Managemmnt

6.3.5.1. Durlnp Constructson Phase

The recycling of construction waste was done as follows:

(1) Left over concrete and mortars, cement concrete blocks, aggregate,

sand and other lnorganlc material was recycled and used as

Granular Sub-base (GSB) layer of pavement.

Reuse of this wlll also save an equivalent quantlty of aggregate.

About 62,000 cu.m. of earth rendered surplus from the excavatlon

will be utillsed In the embankment of DMRC works. As a result

there would not be any Inorganic solld waste rendered surplus from

the project and requir~ng d~sposal.

Page 98: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Repott EDI oPPletn, Bhawan, Barakhatnba Lsnc, Connaught Plsce

Recycling and reuse of solld waste arising out of various constructlon

activities, which was lnotganic in nature, has been discussed above.

Domestic solid waste during construction was limited because no labour

amps were permitted at site. However, even when there was no labour

camps at site and most of the inorganic construction waste was recycled and

reused In construction, there still remalned some solld waste requiring

collection and disposal. This Included food waste of workers at site, empty

containers of pain& and ather chemicals, packagln~ of tiles and glass,

sweepings from omce etc. Following measures were adopted during

constructlon for management of solid waste.

(1) Covered garbage bins were provided all around the construction site including office for collection of food and other waste. These blns

were emptied daily Into a bigger container and the waste finally put

to municipal (NDMC) collection bin, nearby. The waste bins were

washed regularly every week.

(11) Inorganic waste was segregated and kept in different heaps as far as possible so that their further gradatlon and reuse was facilitated.

(ill) Material, which could be recycled and reused for the purpose of

construction, was kept in separate heaps from those which were to

be sold or disposed off.

(Iv) Empty containers, which may contain some toxlc substances such as

paints, solvents, adhesives and sealants was returned to the

manufacturers or disposed appropriately as the case may be. Tlll

such time they were stored safely.

6.3.5.2. During Operation Phesa

The project is estimated to generate about 320 Kg of solid waste every day.

Majority of the solid waste will comprise of waste papers, food waste and

green area sweepings, all of them are biodegradable. The non-biod@gradable

waste will comprise of the floor and road sweepings and the IT waste, which

include used computers and floppy disks. The blodegradable and non-

biodegradable waste shall be segregated during collection by uslng different

colour bins for different type oP waste. Every workstation shall be provided

Page 99: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM afrcrsirer Bhswan, Bsmkhmba Lana, tonnawnt Mace

with such bins. In addition collection blns shall be provlded at sultable

locations In common place and open area for waste collection from floatlng

population. The biodegradable as well as the non-biodegradable waste shall

be transferred everyday to the larger blns kept outside the bulldlng at sultable place. To avoid odour and accumulation of fly-supporting materials,

waste collection blns shall be washed at frequent intervals. The waste shall

however be stored in a separate facility and shall be disposed off through an

authorlsed person/agency of NDMC for that purpose.

Qreenbelb and Landscaplng

Greenbelts and Landscaplng besldes enhanclng the aesthetic beauty of the

bullding complex also helps In improving environmental quality. The cholce of

sultable trees is known to curb the impacts of alr pollution as it act as a fllter.

Thls should be given utmost Importance taklng advantage of both shades and

sunshlne without obstructing the wlnd flow and traffic. Further, a total no. of

620 trees was planted through the necessary afforestation programme, in

lieu of the 58 trees to be cut (Tabla 5.4.) (10 trees for every tree permitted

to be cut) and 40 trees In lieu of the 8 trees (5 trees for every tree to be

transplanted). These were planted as a part of compensatory plantation at

the Gaon Sabha land, Isapur (a site Identified as a part of NOC).

6.3.7. Spaclal Requirement for Physically Challengd

(I) Parking lot has been made keeplng in mlnd requlrement of a physically

challenged person.

(11) Entrance has been designed keeplng in mind the need of physically

challenged person (as shown in Fig. 5.1).

(lii) Stalrs are not be the only means of moving between floors. They are

supplemented by lib and ramps.

(Iv) Sanltary facllltles shall have space to allow trafflc of wheelchair bound

persons. In case of Metro Bhawan such facllltles has been provided at

the second and flRh floors.

(v) Drlnking water fountains or coolers are hand operated O r hand & foot

operated.

Page 100: Environmental Impact Assessment (EIA) of Metro Bhawan

wumrquo oqa am wn ~q ufils :vwO1;1

punoq rlelp~mmqm ova rq m1qmlnm uoop am uuld :'rg 'OM

Page 101: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM Or- B h o m , BamMmmh Lane, Gornnawght Place

An abstract of the EMP for the project has been prepared and presented In

Table 6.6. whlch deflnes actlons to be undertaken during the pre-

constructlon/design (Includlng those already undertaken), wnstructlon, and

opemtlon stages of the project. The mltlgatlon measures given in the table

have been described In the subsequent paragraphs. In addltlon a revlew of

the legal compliance has alsa been carded out (Table 6.7.). The Important

actlons during the pre-constructlon/desl~n stage was energy mnsewatlon/

natural ventllatlon, water consewatlon, reduction In Incremental alr pollution

through tmfflc management, envlronmental enhancement, flre management,

and non - lncluslon of environmental management related clauses in work

contract. The constructlon stage mltlgatlon measures Include control of alr

emlsslans, nolse pollutlon, sol1 eroslon, surface runoff, disposal/ recycle of

constructlon waste, solid waste management, non - routine events and

accidental release, workers safer// health hazard, and envlronmental

management cell/ unlt. The operation perlod rnitlgation would Involve control

of air emlsslons, nolse pollutlon, wastewater dlscharge, solld waste

management, Indoor air pollutlon, energy uses, emergency preparedness

lncludlng flre management, envlronmental management cell/ unlt.

Page 102: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 103: Environmental Impact Assessment (EIA) of Metro Bhawan

DP

R/

Des

ign

Con

sulta

nt o

r D

esig

n unit of D

MR

C in

cm

ulta

tio

n w

ith

DP

R/ W

ork

Incl

usio

n of

envi

ronm

enta

l

educ

ate

the o

ccup

ants

In

dusi

on of

vario

us e

nviro

nmen

tal

rela

ted

aspe

ct

(viz.

, di

spos

al /

man

agem

ent

of

spoi

ls d

urin

g c

onst

ruct

ion

phas

e, m

onito

ring

of e

nviro

nmen

tal

para

met

ers

durin

g pre

-

man

agem

ent r

elat

ed

clau

ses

in w

ork

cont

ract

Co

nst

ruct

ion

Ph

ase

Air

Em

issi

ons

Noi

se P

ollu

tion

com

tnrc

tion /

mns

truc

bion

/

Ope

ratio

n E

nviro

nmen

tal

Pha

se)

of b

uild

ing

com

plex

, ap

poin

tmen

t of

M

anag

emen

t Cel

l/ U

nit o

! en

viro

nmen

tal

cons

ulta

nts

to

advi

se

on

DM

RC

envi

ronm

enta

l matte

rs

All

equi

pmen

ts a

re o

pera

ted

with

in s

peci

fied

desi

gn p

aram

eter

s

Veh

icle

trips

to b

e m

inim

ized

to the e

xtent

pw

sible

Any

dr

y,

dust

y m

ater

ials

sto

red

in S

eale

d co

ntai

ners

or

prev

ente

d fr

om b

low

ing

Com

pact

ion

of

soil

durin

g

vario

us

cons

truc

tion

activ

ities

Am

bien

t A

ir Q

ualit

y M

onito

ring

with

in

cons

truc

tion

zone

to b

e m

onito

red

List

of

all n

oise

gen

erat

ing

mac

hine

ry o

nsite

ab

ng

with

age

to b

e pr

epar

ed, E

quip

men

t to

be

mai

ntai

ned

in q

ocd

wor

king

ord

er

Ran

dom

che

cks

Of

quip

mew

lo

gs/

man

uals

Logs

Abs

ence

of

stoc

kpile

s or

ope

n co

ntai

ners

of

dust

y co

ntai

ners

of

dust

y m

ater

ials

Const

mct

ion logs

The

Am

bien

t Air

Qua

lity

will

con

form

W

e st

anda

rds

For

SPM

, S

O2,

and

N4

, C

O a

nd P

b

Equ

ipm

ent

logs

, nois

e re

adin

g

Con

trac

tor/C

ivil

Eng

g un

lr:

at t

he P

roje

ct s

ite

Co

nb

acb

f/C

'iit

Eng

g un

it a

t the P

roje

ct s

ite

Con

ttact

w/C

ivil

~n

gg

unit

the p

ro

m site

/ E

nvim

nmen

tal

Man

agem

ent C

ell/

Uni

t of

DM

RC

C

on

trac

tor/

Ciii

l E

ngg

unit

at the P

roje

ct s

ite

Con

tract

or/

Env

ironm

enta

l M

anag

emen

t Cel

l/ U

nit o

f DM

RC

Con

tra-/

Env

ironm

enta

l M

anag

emen

t Cel

l of

DM

RC

Page 104: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 105: Environmental Impact Assessment (EIA) of Metro Bhawan

Fin

d C

lepo

rt

ED

of-

Bha

wan

, Bar

akba

mba

Lan

e, C

bmau

ght P

lace

Con

tract

orlC

ivil

Eng

g un

it of

DM

RC a

t the P

roje

ct s

ite

Con

trac

tor/C

ivil

Eng

q un

it of

DM

RC a

t the P

roje

ct s

ite

Con

trac

tw/C

ivil

Eng

g unit

at th

e m

je

site

Con

trac

tw/C

ivil

Enq

g unit

of D

MRC a

t the

Pro

ject

site

Env

ironm

enta

l M

anag

emen

t Cel

l/ U

nit

of

DM

RC

Phy

sica

l impe

mon

,s

uper

vision

Log

book

s of d

ispo

sal

truks

, P

hysi

cal

insp

ectio

n /s

uper

visi

on

DP

WW

ork

Con

tract

DPR

/Wor

k C

ontra

ct

DP

R/W

ork

Con

tract

Sur

face

Run

off

Dis

posa

l/ R

ecyc

le o

f C

onst

ruct

ion

Was

te

- E

vent

s an

d A

ccid

enta

l Rel

ease

Wor

kers

Saf

ety/

Hea

lth

Haz

ard

Env

ironm

enta

l M

anag

emen

t Cel

l/ U

nit

exte

nt p

ossi

ble

Cov

erin

g th

e s

poils

to

Pre

vent

the w

ash

out

durin

g rai

ny s

easo

ns,

prov

isio

n of

gree

n belt

to m

inim

ize

surfa

ce r

un o

fF P

rovi

ding

suf

ficie

nt n

o. o

f gar

bage

bin

s,

segr

egat

e bi

odeg

rada

ble

and

non-

bi

odeg

rada

ble

was

tes

and

disp

ose off

them

ac

cord

ingl

y in

clud

ing

disp

osal

of

s@

s/w

arte

ge

nera

ted

durin

g co

nstruc

tion

phas

e a

t th

e p

re -

des

igna

ted

site

by

the

cont

ract

or,

reus

e of

co

nstruc

tion

was

te

at

the

cons

truc

tion

site

itse

lf.

Pre

para

tion/

indu

sion

of e

mer

genc

y pr

epar

ed-

plan

in

the

wo

k co

ntra

ct ta

avoi

d m

aria

F

irst a

id fa

cilit

ies

at t

he w

ork/

cons

truc

tion

site

, pr

ovis

ion

of s

afe

drin

king

wat

er a

nd

sani

tatio

n fa

cilit

ies

for

cons

truc

tion

wor

kers

, sa

fety

lhea

ttft r

e- is

sues

for

cons

truc

tion

wor

kers

to b

e in

clud

ed in

the

civi

l/ele

chic

al

wor

k c

mti

ac

t aw

ards

Set

ting

up of

E

nviro

nmen

tal

Man

agem

ent

Cel

l1

Unit

to

be

set

up

to

ensu

re

impl

emen

tatjo

n an

d m

on

Mn

g

of

envi

ronm

enta

l saf

egua

rds

Dp

era

tio

n P

has

e

Air

Em

issi

ons

Sta

ck e

mis

sion

s fm

m D

G s

ets

to b

e A

ir p

ollu

tion

Env

ironm

enta

l op

timiz

ed a

nd m

onito

red,

per

iodi

c am

bien

t m

onito

ring

Man

aqem

ent C

ell/

Uni

t of

Page 106: Environmental Impact Assessment (EIA) of Metro Bhawan

--

--

--

-

--

--

-

Fina

l Rep

ort

aa o

f ~e

tm

~

ha

wm

, ~ara

kfra

mb

a Lane, C

bnm

upM

Pla

ce

DM

RC

Env

ironm

enta

l M

anag

emen

t Cel

l/ U

nit o

f DM

RC

Con

hact

or/C

ivil

Eng

g an

d E

nviro

nmen

tal

Man

agem

ent C

ell/

Uni

t of

D

MR

C

Mai

nten

ance

unit of

DM

RC

Env

ironm

enta

l M

anag

emen

t Cel

l/ U

nit of

DM

RC

Noi

se P

ollu

tion

monito

ring

Phy

sica

l insp

ectio

n as

a

pa

rt o

f per

iodi

c m

aint

enan

ce

Phy

sica

l ins

pect

ion

as

a part

of

perio

dic

mai

nten

ance

Indoor A

ir P

ollu

tion

Mon

itorin

g

Noi

se P

ollu

tion

(DG

sets

and

Veh

icle

s)

Was

tew

ater

Dis

char

ge

Sol

id W

aste

M

anag

emen

t

Indoor A

ir P

ollu

tion

( In

side O

ffice

build

ing

and

Par

king

lots

)

air

qual

ity m

onito

ring

at t

he p

roje

ct s

ite a

s pe

r th

e Pwt P

roje

ct M

onito

ring(

PP

F1)

deta

ils,

Ince

ntiv

es/e

ncou

rage

men

t to

the

build

ing

occu

pant

s to

use

pub

lic tr

ansp

ort

inst

ead

of

priv

ate

vet

tiide

s N

oise

gen

erat

ed fr

om o

peta

tion

of D

G s

ets

to b

e op

timiz

ed a

nd m

onito

red,

Dg sets to

ge

nera

te le

ss th

an 7

5dB

(A)

Leq

at 0

.5m

fr

om t

he

sou

rce,

DG s

ets

to b

e pr

ovid

ed a

t ba

sem

ent w

ith p

rope

r aco

ustic

end

osur

es

/muf

flers

, C

him

ney

heig

ht o

f 8rn

abo

ve th

e ro

of to

p , no

-hor

n zo

ne in

side

the

bui

ldln

g m

ple

x

All

the

was

tew

ater

gen

erat

ed in

the

bui

ldin

g co

mpl

ex to

be

colle

cted

thro

ugh th

e in

tern

al

sew

er li

ne a

nd u

ltim

ate

ly d

isch

argi

ng it

to

m

unic

ipal

; se

wag

e lin

e to

be

take

n to

se

wag

e tr

eatm

ent p

lan,

Sep

arat

e lin

es fo

r su

rface

run off a

nd it

s di

spos

al In

to d

rain

age

syst

em

Pro

visi

on o

f ade

quat

e no

. of

bin

s in

the

bu

ildin

g, s

egre

gatio

n an

d co

llect

ion

of b

io-

degr

adab

le(

kitc

hen

was

tes)

and

non

- b

ideg

rad

able

was

te(p

aper

and

com

pute

r st

atio

nery

), D

ispo

sal o

f sol

id w

aste

s as a

part

of m

aint

enan

ce a

nd in

clud

ed in

the

wor

k co

ntra

ct

Indoor a

ir p

dlu

tan

ts ( v

iz.,

CO

, VO

C,

RSP

M

to b

e re

duce

d by

pro

vidi

ng p

roper

ventil

atio

n a

nd to

be

mon

itore

d pe

riodi

cally

as

per

the

stip

ulat

ed P

PM,

Dec

larin

g w

hole

II

I

Page 107: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 108: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA or mtro attawen, ~samumba L ~ M , connaught urn

Table 6.7. : Environmental Leglslatlon/ Acts Appllcabie for the Metro Bhawan

Leglmlatlon Demcrlptlon

1. Alr (Prevention and Control of - Pmtedlr~fl of Air Quality Pollution) Act, 1981 with - Consent to Establish (NOC) for Rules. establlshlng and Consent to

Operate ( C T E ) for activities causing air pollution from DG sets from SPCB

- Compllanee to National Ambient Air Qualitv Standard

2. Water (Prevention and Control - Protection of Water Quality of - Discharge of sewage from Pollution) ~ c t , 1974 with Project Rules. - Obtaining Consent to Establish

(NOC) for establishing and Consent to Operate (CTE) for activities causing water pollution from SPCB

3. Water (Prevention and Control - Stipulates provision For levy and Of collection of Cess on water Pollution) Cess Act, 1977 consumed by the local (including Amendments In authorities and by persons 1978 and 1991). carrying on certain industrial

activities with a view to generate resources for prevention and control of water pollution.

3. Environment (Protection) Act, - Overall Environment PmtecFlon 1986 (Umbrella Act) with Rules including - Compliance to envlronmentai Environment Protectlon Rules (Air, WaFer, Noise)Standads (1986) issued under EPR

4.1. EIA NotiEation, 1994 - Prepare EIA/ EMP report (revised on September i4th - Obtain Environmental Clearance 2006) from MoEF

- Take part in Environmental Public Hearing (EPH)

4.2 Noise Pollution (Regulation - Compliance with Ambient Noise and Standards in accordance to land Control) Rules, 2000 use of the area

4.3 Hazardous Waste - Obtaining Authorization from (Management SPCB for handling and and Handling Rules, 2002 (as - storing of hazardous waste like amended) waste oil and lubricants - Following guidance for handling

and storing of such hazardous waste

Page 109: Environmental Impact Assessment (EIA) of Metro Bhawan

u3N Ul SWl JO uo~lehlasard e4a JOJ aplnad oa uw uv -

saSIur&Jd paFwd UILIJIM sa3umsqns

urnalaaad p uolaqodsuwa pue 'a6e~ols JOJ saJnseau hajes

pue esuapln8 JIM Aidwo3 -

uo1aw111qeu~j pue auauraluasau - *ulaauJ PaPlAWd l~l~uaure 311qnd AU~JO s6ulpunw~ns JO

41ienb 3lwysee aya JQ 8u11Ads aya page AI~~I s! JO waw

4311.1~ lasodwd 1uaurdolanap Aue JO suone~ado 6ul~aaul6ua

JO suo~ae~ado 6ulpllnq JO parad hue JO pedsa

UI Apoq lesol Aue 01 BSU~pln8 pue winpe ep~nard oa pug 1u1aa

ulyq~ u61sap ~rquawumlnua pue ueqJn do rtllenb

~1~4lsae aya 6u1ul~u1eur put2 6uldolenap '8ul~asmd

JO Jagow a47 ul auauruano9 leJJUa3 943 aSlApD Ol -

sueid JaaseM pue asn puq 431~ muep~me

ul pafo~d a41 dolanaa - PUB1

OOOZ swna UJIM uw Unalwaad

(alqmllddP 41) uonw1i1qeua pue

auauraluasw uo hllod IeUolleN

. . JOJ uo~nues pue n~uued UI~O -

aueld JaMod IewJau paseq I a~lufin JO iw~ UOJJ uq OOT - os JO snipe.! UILI~~M Buipllnq

OulpngUl SalaIAlUQ UOlpnJpUO3 666T 'lueld JaMOd Jeuao pue n(31~q JO anpeJnuaur IPUJ~UL paseq q1u61i JO ayl ulqsw urowoq AM JQ esn - 1eo3 WOJJ uolaeslllan ysv AM

Ijooz

Page 110: Environmental Impact Assessment (EIA) of Metro Bhawan

Final m r t EIA OrMemBhswan, B a n r m b a lane, cQmaMQrJtflw

S. NO. --

- 10.

Legislation

Delhi Metro Rallway (Operation & Maintenance Act, 2002)

Deccrlptlon

existing tress, nurseries, supply of seeds to persons required to plant new trees - An Act to provide for the operation and maintenance and to regulate the working of metro railway in the metropolitan city of Delhi

Page 111: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report: EM or mtm B ~ P I W ~ , mmhsmt~ bne, c4nnswht f laa

Chapter 7 Post Project Monitoring (PPM)

7.1 General

Implementation and follow up are used to identlfy the impacts that occur; check

that these a n withln the levels predicted and stipulated standards; determine that

mitigation measures are properly implemented; ensure the environmental beneflts

expected are being achieved; and provide feedback to improve future applications

of the EIA process. Wlthout appropriate impiementatlon and follow up to declslon-

maklng, EIA b a m e s a paper exercise to secure an environmental clearance,

rather than a practical exercise to achieve environmental beneflts. The purpose of

EIA implementation and follow up Is to ensure that the conditions stipulated in

environmental clearance are implemented and function effectively, and to galn

Information that mn be used to improve EIA practlce in the future. The major

components and tools of EIA implementatlon and follow up which are proposed to

be followed as a part of EIA exercise Include the following:

(I) Surveillance and supervision - to oversee adherence to and implementatlon of

the terms and condltlons of project approval

(ii) Effects or impact monitoring - to measure the environmental changes that can

be attributed to project construction and / or operation and check the

effeeblveness of mltigation measures

(ill) Compliance monitoring - to ensure the applicable regulatory standards and

requlrements are belng met, e,g. for waste discharge and pollutant emissions

(iv) Environmental audlting - to verlfy the Implementation of terms and conditions,

the accuracy of the EIA predictions, the effectiveness of mitigation measures,

and the compliance with regulatory requlrements and standards ;

(v) Ex-post evaluation - to review the effectiveness and perFormance of the EIA

process as applled to a specific project ; and

(vi) Post-project analysis - to evaluate the overall results of prole& development

and to draw lessons for the future

Page 112: Environmental Impact Assessment (EIA) of Metro Bhawan

W'QnJ ayl Ul B3lpEUd PUF3 ssa;lOJd VI3 a~0Jdlul 03 q3wpWJ aplAWd

pue ! SaJnseaur uo1ae61llw aqa do SseuaAlpaUa ay3 eaanlehg

! suolplpa~d v13 aua do A3ednme a43 aaenlena

!Aessa3au 41 sappey3s

palela pue suo13esMpads mafad pue sarnseau uo11~361a1w eua aped6dn

!wsdwl ewanpe paed13nueun Aue 4lm JO esnpar a uolpe eya~

! eI-laa1m

JO splepulals alqeslldde put? swaurwlnbzu hoaelnBBJ 431~ 83u~lldwm ~IJ~A

! Aq1unwurm

aya puo aueuruwnue aw uo sa~a~l~e vaFard JO wage Ilanpe aqa ~oaluow

!&ldoylne Loanatas peu~a3um aya wdo~ul

PUP parlnbw are aeya saf3uey3 Aua p suolleslldu~ ~quauuwlrrua aya Malna

!a~uedaap

lwuewualnue do suolgpum p uolaguaualdwl aya q3aw pue J3adsu1

:pXldoPe Alledeua6 aJQ dn Mollo~ Put? uolaeauaualdul VI3 do q3~0~dde ~UIMOIJOJ aul

uleuasun st auro3lno Jlaya JO awla papa are swnseaw uone6131(*1

'au~31~1u61s aq 01 Alayll we =edw( IBIJUB~O~

uayM ueywapun Alloleue6 we uo~aanlend

pus 6u1a1pnw '~UIJ~IUOW eql 'plwa lwauo=r uotanllod aaeas oa pauluqns

woda #pne ~eauewunr~~ue llanuue oa uolalppe UI wedad pue 6u1doa1uour

Aallenb (wuawuculnua apnpul plnoys wodar slq~ '~euolawado awmaq

sew rCI~npu~/ICl(hl~e/Ue~aId ue laye ueeA anu hana ssqJlJoqane hlo7n.a~~

pauJa3um 847 a peuluqns aq plnoys svodad dn MOIIOJ pue uo1ae1uawa1dwI (1111 pue ! wedwl le~u~od aqa 40 ajum~lu6ls

aya 411~ avansuaurwos aq plnoys salgnlpe dn MOIIOJ dau~o do edox ayl (11)

!&nd sty1 404 lueuala augnar o eq plnoys uoluadsu~ pue a3ualllaNnS (I)

! d~3NOdad v13 ayq ul apeu qualugwwo3 ayl pue leno~dde 40 suo1a1puo3 yalm esulawome ul PO palurn eq plnoys UaF0Jd eu :dn MO~IOJ pue uol1eauaualdurl w13 40 wed e se papuawwo3a~ ade BU~MOIIOJ ayl

Page 113: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA of Metm Bhawan, Bsdhamba Lane, Connaught Place

7.2 Cost Irnplleations of the Envlronmsntal Monitoring System The different aspect of the envlronmenhl management of the proposed Metro

Bhawan project can be effectlveiy monltored and documented through the

Envlronmentai Monltorlng System (EMS) durlng the construdlon and operation

phase, as a part of the Environmental Management Plan(EMP) and Post Project

Monltorlng(PPM). The proposed Monltorlng Progmm durlng the Construction and

Operation Phase has been shown in Table 7.1 and year-wise cost estimates for

envlronmental monltoring pmgram during the Construction and Opemtion Phase Is given in Table 7.2 and Tabla 7.3 respectively. On the basls of these tables'

estimated flnanclal lmpllcations for envlronrnental monltoring progmmlyear durlng

Construction and Operation Phase and are shown in Table 7.4.

Page 114: Environmental Impact Assessment (EIA) of Metro Bhawan

Fina

l Rep

ort

EL4 of M

etro

Bha

waur

, Bar

aldr

amba

Lan

e, C

omau

gIlt

Pla

ce

Tab

le 7

.1.:

Mo

nito

rin

g P

rog

ram

du

rin

g th

e C

on

stru

ctio

n a

nd

Op

erat

ion

Phas

e

Para

mete

r

(Op

erat

ion

ph

ase)

(Op

ed

on

ph

ase)

Op

erat

ion

Ph

ase

stan

dard

met

hods

for

Page 115: Environmental Impact Assessment (EIA) of Metro Bhawan

Fina

l Report

-a ~

~r

ma

ww

r,

B

ara

ma

mb

am

, t3

MM

up

ht p

lace

rn

En

vifo

nm

enta

t pro

posed

Par

amet

er

Mo

nito

rin

g

~&

od

Rec

om

men

ded

.o

catio

n(s

I

publ

ishe

d by

Am

eric

an

Pub

lic H

ealth

A

ssoc

iatio

n(A

PH

A)

BO

D,'C

OD

, ph

enol

, H

eavy

met

als

and

Baaerldogkal (

Tot

al

colif

orm

s, f

aeca

l co

lifw

ms

Gro

und w

ate

r:

one

Ph

ysic

al (

pH

, Te

mp,

Q

uarter

ly

Gra

b sa

mpl

es , S

~n

ple

~

sam

ple

from

th

e

Tur

bidi

ty,

(Co

nst

ruct

ion

&

colle

cted

and

ana

lyze

d as

gr

ound

wat

er

h-e

Col

our)

,Cha

mic

al

Op

era

tio

n p

erio

d)

per IS :

2488

(P

art

1-5)

w

ell

mag

nesi

um

hard

ness

, an

d as

per

the

Consh

wet

ion

&

tota

l al

kalin

ity,

stan

dard

met

hods

for

Op

er

ati

d P

has

e ch

lorid

e,

sulp

hate

, ex

amin

atio

n of

wat

er a

nd

nttra

te,

fluor

ide,

w

aste

wat

er a

naly

sis

sodi

um,

pota

ssiu

m,

publ

ishe

d by

Am

eric

an

salin

ity, T

otal

nitr

ogen

, P

ublic

Hea

lth

tota

l ph

osph

orus

, D

O,

Ass

ocia

tion(

AP

HA

) I B

OD

, CO

D,

Phe

nol,

1 B

iolo

gic

al

En

viro

nm

ent

Alo

ng

the

cons

truc

tion

/ P

roje

ct

site-

- &

O

pera

bion

sl P

has

e

Hea

vy m

etal

s G

reen

C

over

asp

ects

( fo

r m

onito

ring

tree

ou

tting

, tr

imm

ing a

nd

com

pensa

bw

pl

anta

tion)

Dur

ing

the

who

le

cMts

truct

ion

perio

d M

onito

ring

and

supe

rvis

ion

as

per

the

Env

ironm

enta

l M

anag

emen

t Pla

n(E

MP

)

Page 116: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 117: Environmental Impact Assessment (EIA) of Metro Bhawan

r - .. . - -

I:, 1

I- I

Page 118: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 119: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 120: Environmental Impact Assessment (EIA) of Metro Bhawan

OI'L

(mseyd uolamrodg pus uopnrwug) roeA/rumrOard Oulroaluoru lquewuarlrruo roj wolas311dru1 lmpueu y ~PUIIW~ Y'L elqml

Page 121: Environmental Impact Assessment (EIA) of Metro Bhawan

1 MINISTRY OF URBAN I DEVELOPMENT AND POVEH fY

Page 122: Environmental Impact Assessment (EIA) of Metro Bhawan

( ,,

I " ,

f-s * .

Final Repm EIA ormm mawan, B B r a M b s h e , i%miwght PI=

The following organlrations may be consulted directly or through their web sites for

secondary data collection

Mlnlstry of Environment and Forests (MoEF)

Central Pollutlon Control Board (CPCB)

State Pollutlon Control Boards (SPCBs)

India Meteorological Department (IMD)

Central Ground Water Board/Authorlty (CGWBICGWA), Mlnistry of

Water Resourees

State Ground Water Board

Central Water Commlsslon (CWC)

Botanical Survey of Indla

Zoological Survey of Indla

State Forest Department

Department of Census

Agriculture Depattment/Unlverslties

Survey of Indla

Geological Survey of Indla

Dlstrlct Administration

Panchayat

Page 123: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report Eld dkii~~ro &wan, BBtabhsmba Lam, Connaught PI-

Alr 0-

measurement

Suspendsd Particulate Matter (SPM)

Respirable Particulate Matter WPM) (size <lop)

Lead (Pb)

hours**

Annual Average*

24 hours**

Annual Average*

24 hours**

Annual Average*

24 hours**

pg/m3

360 pg/m3

500 )rg/m3

120 pg/m3

150 pg/m3

1.0 pg/m3

1.5 pg/m3

140 pg/rn3

200 pg/m3

60 pg/m3

100 pg/m3

0.75 KJ/m3

1.00 w/m3

70 pg/m3

100 1~4Irn'

50 pg/m3

75 )rg/m3

0.50 m/m3

0.75 W m 3

Method - Gas Phase

Chemlluminescen CB

- Hlgh volume Sampling,

(average flow rate not

less than 1.1 m3/mlnute)

Resplrable part'lculate matter

sampler

- ASS Method after

sampllng uslng EPM 2000 or

equivalent Fllter paper

Page 124: Environmental Impact Assessment (EIA) of Metro Bhawan

F l ~ l Report EIA d e b Bhawan, eraktramba la&; &tiiuofit ~ d t c

Pollutants

Ammonla W H a )

Carbon Monoxide (CO) -

*Annual Arlthmetlc Mean of mlnlmum 104 measurements in a year taken twlce a week 24 hourly at uniform Interval. **24-hourly/8-hourly values should be met 98% of the tlme in a year. However, 2% of the tlme, it may exceed but not on the two consecutive days.

Time- weigh-

d average

Annual Average*

24 hours**

8 hours**

Method of measurement

Colorlmetr[c method

- Non Dispersive lnfra Red (NDIR)

s p e c t r o s ~ ~ ~

Concentration in ambient air

Industr 181

Arms

0.1 mg/m3

0.4 mg/m3

5.0 mg/m3

Resident1 a1 Aimas

0,i mg/m'

0.4 mg/m3

2.0 mg/m3

Sensitlv e Areias

0.1 mg/m3

0.4 mg/m3

1.0 mg/m3

Page 125: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnel Report m ofmm mawan, BrrmIdrarnba Lsna, Cdnn@~&fktt H c e

Llmlt in dB(A) Leq Category of Area Day time Night time

Industrial Area 75 70 Commercial Area 65 55 Residential Area 55 45 Silence Zone 50 40

Day time b reckoned between 6 am to 10 pm Night time is reckoned between 10 pm to 6 am Silence zone is defined as areas upto 100 m around such premises as hospitals, educational institutions and courts. The silence zones are to be declared by the competent authority

Page 126: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 127: Environmental Impact Assessment (EIA) of Metro Bhawan

v i i

flnal Report EL4 of Mew Bhawwr, isrrmkhamba lane, ConnsugM Place

No&

fluorosis and lower value shall carries May Impair treatability and cause foamlng

Parameters

Range / Limiting Value use with Use after

only conventional disinfection treatment

16 .

e 0.2 SurCactanW, ma/i

c 0.2

Page 128: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EM of Metm Bhawan, BarsWMmba Lak, Connaught Race

Xndlan Standard#/ Speclflc~tlon~ for Drlnkln~ Water (IS 10500 - 1983)

Fluorides (as F), mgli Max

Phenolics (as C6H50H), mgll Max

Mercury (as Hg), mgll Max

Cadmium (as Cd), mgll Max

Selenium (as Se), mgll Max

Arsenic (as As), mgll Max

0.6 - 1.2 0.001

0.001

0.01

0.01

0.05

Page 129: Environmental Impact Assessment (EIA) of Metro Bhawan

Final Report EIA of Metro Bhswan, Balgkhamba Lane, Connaught M a n

Page 130: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM of Me& Bhawan, Banrwlamba Urna, C4muphf Place

Eml88lon Standard9 for Dle-1 En~lnem (Englne Ratlnp More Than 0.8 MW (800) KW for Power Plant, Qenerator Set Applications and Other

lbqulmments)

Parameter

- - - -

NOx (as NO21 (At 15% 02# dry basis, in P P ~ V )

- - -

Generator set commimslonln~ data

O/o

02)

Area Catego

A B

- ~.

- I

CO(at 15% 02)# mg/Nrn3

Sulphur content in fuel

Fuel speciflcgtion

Total englns rating of the

Plant (includes

existing as well as new Generator sets)

Upto 75 MW Upto 150 MW - - -. --

On or a~ter 1.7.20 05

710 360

Before 1m7'20 O3

1100 1100

Furnace oils -

Stack height (for Generator sets commissioned a'er 1.7.2003)

Barwe en

1.7.20 03 3 1.7.20

05 970 710

b ore Than 75 MW More Than 150 MW

Both A & B

00th A & 6 A

A only

meter: (1) 14 Q ~ * ~ ~ Q = Total SOz emlsslon from the plant in kg/ hr (ii) Minimum 6 rn above the build where generator set is installed

150

75

Stack helght shall be maximum of the foilowlng, in

Upto 5 MW

100

75

150

150

100

< 29'0 ~ 4 %

Only Dlesel Fuels (HSD, LDO) shall be used

Page 131: Environmental Impact Assessment (EIA) of Metro Bhawan

Flnal Report EM or Metro Ehawm, Blrmkhamba Lam, Camuphr nace

Category A: Areas wlthin the municipal llmlts of town1 cltles having papulatlon more than 10 lakhs and also upto 5 km beyond the municipal limits of such towns1 cltles

Category 8: Areas not covered by Catepory A.

Other Cases: The minlmum helght of stack to be provided set an be worked out using the following formula: H .r h+O.ZxqKVA H = Total height of stack In metre h r height of the building in metres where the generator set is Installed KVA = Total generator mpaclty of the set in KVA.

Based on the above formula the minimum stack heiaht to be ~rovlded wlth different

formula.

range of generator sets may be cateqorized as follows: Far ene era tor sets

50 KVA 50 - 100 KVA 100 - 150 KVA 150 - 200 KVA 200 - 250 KVA

Total height of stack in metre Ht. of the bulldlnq + 1.5 m Ht. of the building + 2.0 m Ht. of the building + 2.5 m Ht. of the buildlna + 3.0 m Ht. of the bulidlnq + 3.5 m

Similarly for higher KVA mtings a stack height can be worked out uslng the above

Page 132: Environmental Impact Assessment (EIA) of Metro Bhawan
Page 133: Environmental Impact Assessment (EIA) of Metro Bhawan

Pinel Report un urmtm ~ h e w w l , mnmmba me, connaught PI=

B. Noise Limit for Generatar Seb run with Diemi (upto 1000 KVA) manufacturad on or attar the id January 2005

A. Noise Limlt for Generator Sats run wlth Petrol or Kerosene.

The maximum permlsslble sound pressure level for new dlesel generator shall be 75 dB (A) at 1 metre from the enclosed surface. The dlesel generator sets should be provided wlth Integral acoustic enclosure at the manufacturing stage Itself.

Sound Power Level

8.1. Nolse llmlt for DG sets not covered by paragraph 1.

1. Nolse from DG set shall be controlled by providing an acoustlc enclosure or by treating the room acoustically, at the users end.

2. The acoustlc enclosure or acoustlc treatment of the room

Noise Limit from

Noise Caiculutions

[September 1, 20021

90 Dba

To determine the comblned sound pressure level (L,) resulting from the sound pressure levels of two or more nolse sources (4, 4, etc.) It lis necessary to calculate and add the mean square values of their lndlvldual sound pressures and then convert this back to a sound pressure level uslng the formula given below:

[September I, 20031

86 dBA